| Address of Site: | 1800 IPSWICH RD ROCKLEA QLD 4106 1808 IPSWICH RD ROCKLEA QLD 4106 |
| Real Property Description of Site: | L2 RP.148384 L1 RP.148384 |
| Aspects of development and type of approval: | DA - PA - Building Work Development Permit - warehouse DA - PA - Material Change of Use Development Permit - warehouse DA - PA - Referral Agency for Building Work Referral Response - Flood hazard area |
| Council File Reference: | A006982595 Permit Reference Number/s: DABW436202823; DAMC437848623; DAEB452899924. |
| Package Status: | APPROVED - Version 2 (4th of June, 2026 4:20:35 PM) |
| Package Generated: | 04/06/2026 |
| Errin Xiaofang LU Senior Urban Planner Planning Services South Errin.Lu@brisbane.qld.gov.au (07) 3403 3694 |
Timothy BYRNE Principal Urban Planner Planning Services South Timothy.Byrne@brisbane.qld.gov.au (07) 3403 0314 |
Errin Xiaofang LU Senior Urban Planner Planning Services South Errin.Lu@brisbane.qld.gov.au (07) 3403 3694 |
| Zarndra PIPER Principal Urban Planner Planning Services South Zarndra.Piper@brisbane.qld.gov.au 0731780370 |
Michael O'REILLY Environmental Management Officer Environmental Management Services Michael.O'Reilly@brisbane.qld.gov.au 3403 9517 |
JOANNE LOVE-SLOMAN Landscape Architect Landscape Architecture Team joanne.lovesloman@brisbane.qld.gov.au (07) 3403 8888 |
| Chris HENNESSY Engineering Services Traffic Chris.Hennessy@brisbane.qld.gov.au (07) 3403 5768 |
Eric OWEN Senior Technical Officer Engineering Services South eric.owen@brisbane.qld.gov.au (07) 3178 5195 |
Khiang POH Senior Engineer Engineering Scoping khiang.poh@brisbane.qld.gov.au (07) 3407 0889 |
| Timothy BYRNE Principal Urban Planner Planning Services South Timothy.Byrne@brisbane.qld.gov.au (07) 3403 0314 |
Margaret ORR Team Manager Planning Services South margaret.orr@brisbane.qld.gov.au (07) 34070751 |
Eric OWEN Senior Technical Officer Engineering Services South eric.owen@brisbane.qld.gov.au (07) 3178 5195 |
| Chris HENNESSY Engineering Services Traffic Chris.Hennessy@brisbane.qld.gov.au (07) 3403 5768 |
Tim DWYER WaRRS Assessment Tim.Dwyer@brisbane.qld.gov.au |
JOANNE LOVE-SLOMAN Landscape Architect Landscape Architecture Team joanne.lovesloman@brisbane.qld.gov.au (07) 3403 8888 |
| Craig SLACK Engineer Engineering Scoping craig.slack@brisbane.qld.gov.au (07) 3403 8888 |
DRAWINGS AND DOCUMENTS
| Drawing or Document | Number | Plan Date |
|---|---|---|
| Proposed Site Plan | DA-02.2 E | 26-MAY-2026 (Received) |
| Demolition Ground Floor Plan | DA-05.1 F | 26-MAY-2026 (Received) |
| Demolition Roof Plan | DA-05.2 E | 26-MAY-2026 (Received) |
| Proposed Ground Floor Plan | DA-05.3 E | 26-MAY-2026 (Received) |
| Proposed First Floor Plan | DA-05.4 D | 26-MAY-2026 (Received) |
| Proposed Roof Plan | DA-09.1 F | 26-MAY-2026 (Received) |
| Elevations | DA-11.1 F | 26-MAY-2026 (Received) |
| Section A | DA-12.1 F | 26-MAY-2026 (Received) |
APPROVAL CONDITIONS
| Permit to Which These Conditions Relate: | DA - PA - Building Work |
| Activity(ies): | warehouse |
| Stage: | Extension to Warehouse |
| 1) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers. Note: This condition is imposed to ensure compliance with the conditions of development approval. |
While site/operational/building work is occurring |
| 2) Carry Out the Approved Development Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS. Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners. |
While site/operational/building work is occurring |
| 3) Complete All Building Work Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS. Note: Building work must also be completed in accordance with any other current development approval. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 4) Protect Existing Infrastructure Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure. Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations. The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements. |
While site/operational/building work is occurring |
4(a) As Constructed Drawings - Alterations to
Existing Infrastructure Submit to Development Services As Constructed drawings showing all new and/or rectification works and an asset register, prepared by a Registered Professional Engineer Queensland. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 5) Repair Damage to Kerb, Footpath or Road Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
5(a) Interim Repairs If at any time during the construction phase of the approved development, damage to the existing kerb and channel, footpath or roadway creates unsafe, unreasonable and/or not fit for purpose conditions as assessed by Council, interim repairs must be undertaken as directed by Program Planning and Integration. Note: Any interim repairs required to be undertaken shall not be considered to satisfy the requirements of this condition for the permanent repair of the infrastructure prior to the issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. Timing: While site / operational / building works is occurring. |
As indicated |
| 6) Flood Emergency Management Plan Prepare, implement and maintain a Flood Emergency Management Plan (FEMP) in accordance with the requirements of this condition. Note: Guidance for the preparation of drawings and/or documents to comply with this condition is provided in the Flood Planning Scheme Policies. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
6(a) Prepare and Certify a Flood Emergency
Management Plan Submit to Development Services a Flood Emergency Management Plan (FEMP) for the approved development prepared and certified by a Registered Professional Engineer Queensland with experience in flood risk management. Timing: Prior to issue of Certificate of Occupancy/Final Inspection. |
As indicated |
| 7) Minimum Flood Planning Levels Design and construct all building pad levels, floor levels and ancillary structures to the appropriate flood planning level with freeboard (where required) in accordance with the relevant Brisbane Planning Scheme Codes and the approved drawings and documents. The minimum floor level must be 8.0 metres AHD. The minimum level for essential electrical services must be 8.0 metres AHD. PROOF OF FULFILMENT As-Constructed drawings prepared by a Registered Surveyor (Qld). The Registered Surveyor (Qld) must certify that the development has been constructed in accordance with this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 8) Construction Noise and Dust Emissions Pursuant to the
Environmental Protection Act 1994, all development involving the emission of
noise and dust from building and/or construction activities, must ensure that
the emissions are in accordance with the requirements of the Act. |
As indicated |
| 9) Further Development Permit Required Further Development Permit(s) to carry out assessable building work under the Building Act may be required. |
As indicated |
| 10) Currency Period The currency period for this development approval is stated in the Decision Notice and is expressed as a date. This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016. |
As indicated |
| 11) Flood Resilience and Awareness This advice is provided for buildings that are on sites that are subject to the flood overlay, as shown within City Plan 2014. Council makes decisions to minimise flood risk based on the best information available at the time of the development application. Flood studies and applicable flood levels may be updated by Council overtime where new flood information is available or changes to engineering standards/methodology have occurred. Flood levels for various flood events and flooding types are outlined in Council's Floodwise Property Reports available from Councils website. The minimum flood planning levels that apply to new development do not necessarily mean that the development will never flood. Therefore, when choosing materials for building on sites that are known to be affected by flooding, regardless of whether it is constructed to the minimum flood planning level, it is recommended that flood resilient materials are used to improve the speed of recovery and reduce the cost of repairs if required. For more information refer to: Council's website at https://www.brisbane.qld.gov.au/community-and-safety/community- safety/disasters-and-emergencies/be-prepared/flooding-in-brisbane/flooding- support-for-residents/flood-resilient-homes-program Queensland Reconstruction Authority "Flood Resilient Building Guidance for Queensland Homes"https://www.qra.qld.gov.au/resilient- homes/flood-resilient-building-guidance-queensland-homes |
As indicated |
| Permit to Which These Conditions Relate: | DA - PA - Material Change of Use |
| Activity(ies): | warehouse |
| Stage: | Extension to Warehouse |
| 12) Security Lighting - On Site Install and maintain a suitable system of security lighting to operate from dusk to dawn within all areas where the public may gain access, including car parking areas, internal pathways, building entrances and vegetated areas. Lighting of publicly accessible internal areas is in accordance with Australian Standard – AS/NZS 1158.3.1 Lighting for roads and public spaces – Pedestrian area lighting – Performance and design requirements. All external lighting within the site is in accordance with Australian Standard - AS4282- Control of the Obtrusive Effects of Outdoor Lighting. Lighting must be maintained in safe and good working order. Timing: 'Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first' |
As indicated |
| 13) Building Format Plan Where the timing of a condition, or part thereof , states 'Prior to issue of Certificate of Occupancy/Final Inspection Certificate' or 'Prior to commencement of use' and the development involves the creation of a Building Format Plan, the timing of the condition, or part thereof, is taken to mean 'prior to Council's endorsement of any plan of subdivision'. |
As indicated |
| 14) Car Parking The car parking within the premises must be maintained exclusively for the ancillary use of the development. The parking must not be made available to the general public and there must not be signage erected on or in the vicinity of the site advertising the availability of car parking to the general public. |
At all times |
| 15) Maintain the Approved Development Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions. |
At all times |
| 16) Original Condition Package All conditions relating to the original approval (Council reference: 420/10- 2522/89) issued on 8 February 1990 and as modified on 3 May 1990, remain applicable, unless varied by this approval. |
At all times |
| 17) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers. Note: This condition is imposed to ensure compliance with the conditions of development approval. |
While site/operational/building work is occurring |
| 18) Carry Out the Approved Development Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS. Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners. |
While site/operational/building work is occurring |
| 19) Demolish or Relocate Buildings/Structures Demolish buildings/structures on the site in accordance with the approved DRAWINGS AND DOCUMENTS and where applicable, the approved Construction Management Plan. The removal of buildings/structures includes the removal of all existing concrete slabs, foundations and footings. |
Prior to Council's notation on the plan of subdivision |
| 20) Complete All Operational Work Complete all operational work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such operational work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS or, if requiring a further approval from the Council, in accordance with the relevant further approval(s). |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 21) Complete All Building Work Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS. Note: Building work must also be completed in accordance with any other current development approval. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 22) Limitation of Use - Ancillary Administration Area -
Industry The ancillary administration space/s on the site are to be limited to the area shown on the APPROVED DRAWINGS AND DOCUMENTS. This area/s must remain ancillary to the approved Warehouse use and must not operate separately. TIMING: At the commencement of use and then to be maintained Should the approved Warehouse use cease, the use of the ancillary administration area must also cease. TIMING: At the time the approved use ceases. |
As indicated |
| 23) On-site Staff Recreation Area - Industry Provide an on-site recreation area for staff in accordance with the APPROVAL DRAWINGS AND DOCUMENTS and which: - includes seating, tables and rubbish bins; - is adequately protected from the weather; - is safely accessible to all staff; - is separate and private from public areas; and - is located away from noisy or odorous activities |
Prior to the commencement of the use and then to be maintained |
| 24) Retain and Protect Existing Street Tree(s) Identify, retain and protect the existing street trees including the roots unless otherwise agreed in writing with Program, Planning and Integration Arboriculture (PPI Arb). Note: Street trees are protected under the Natural Assets Local Law. Street trees must not be removed or pruned without prior approval from PPI Arb. Where driveway crossovers occur within the Tree Protection Zone (TPZ) of existing street trees, seek approval from the Arboricultural Team in Program Planning and integration, City Standards for the final driveway crossover design and construction methodology to ensure the successful retention of the existing street tree(s) PROOF OF FULFILMENT Contextual photographic evidence that the tree has been retained in equal or greater health than before development commenced. OR, evidence in writing fromPPI Arboriculture that an alternative arrangement has been made. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
At all times |
24(a) Implement Protection
Measures Install tree protection measures in accordance with Australian Standard - AS4970 Protection of Trees on Development Sites. There must be no excavation, filling or storage of materials or plant within the drip line of the tree(s). Where works are within the canopy drip line of existing street trees, contact PPI Arb Coordinator in relation to the required provision of protection measures. Note: If fencing is to protect street trees, a permit to temporarily occupy the footway will be required from Compliance and Regulatory Services. Timing: Prior to site/operational/building work occurring. PROOF OF
FULFILMENT Contextual photographic evidence to demonstrate the installation of protection measures prior to building works commencing. Timing: Prior to site / operational / building work occurring. |
As indicated |
24(b) Maintain Protection
Measures Maintain protection measures while development is occurring and remove protection measures prior to commencement of the use. Timing: While to site/operational/building work is occurring. |
As indicated |
| 25) Streetscape Works - Industrial Street Carry out streetscape improvement works including concrete path, turf and street trees to the Ipswich Road and Reginald Street verges to an Industrial Street standard in accordance with the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD), the requirements of this condition and the Infrastructure Design Planning Scheme Policy including sections 3.7.4.5 and 3.7.5. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
25(a) Concrete Path Install a 1.2m wide
broom finished standard Portland grey concrete path. The edge of the path is to
be setback 1.9m from the back of kerb. The path is to transition to existing
paths on verges that adjoin the development. Transition to existing paths on verges that adjoin the development. The transition is to occur fronting the adjoining developments, not the subject site. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL). PROOF OF FULFILMENT Submit to Development Services, photographic evidence of concrete path. |
As indicated |
25(b) Submit As-Constructed
Drawings Submit to Development Services "As Constructed" plans
including an asset register, checked by a Registered Professional Engineer
Queensland, certifying that the concrete path works have been completed in
accordance with relevant Brisbane Planning Scheme Codes/Policies. PROOF OF FULFILMENT As constructed drawings and asset register signed by an RPEQ. |
As indicated |
25(c) Turf Install turf to the
full width of the verge excluding any concrete path required by this
condition. PROOF OF
FULFILMENT Photographic evidence of installed turf. |
As indicated |
25(d) Street Tree(s)
Note: Street trees should not be planted until all utilities have been installed. Timing: Prior to issue of Certificate of Occupancy / Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation on the plan of subdivision (ROL). PROOF OF FULFILMENT Provide to Development Services a copy of the agreement signed by Program Planning Integration. |
As indicated |
| 26) Landscape the Site - Self Certification Landscape the site in accordance with the requirements of this condition. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
26(a) Detailed Landscape Plan for Self-
Certification Prepare a Detailed Landscape Plan at a scale of 1:100 for all on-site landscape works including planting areas identified on the approved DRAWINGS AND DOCUMENTS. The plan must be prepared by a qualified Landscape Architect and must comply with the relevant Brisbane Planning Scheme Codes. The plan must include the following: Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
26(b) Industry In addition to the
requirements listed above, the plan must include the following: Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
26(c) Certify Detailed Landscape
Plan On completion of the Detailed Landscape Plan, submit to Development
Services: Timing: Prior to building work commencing. PROOF OF FULFILMENT A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to building work commencing. |
As indicated |
26(d) Implement Certified Detailed Landscape
Plan Carry out the landscape work in accordance with the above certified detailed Landscape Plan. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
26(e) Certify Work On completion of the
landscape work, submit to Development Services: Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT An as constructed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
26(f) Maintain Landscape Work Maintain the landscape work, including deep planting, in accordance with the certified Detailed Landscape Plan. Timing: To be maintained. |
As indicated |
| 27) Air Quality There is to be no Air Pollutants emitted from industrial activity in this warehouse development. |
At all times |
| 28) Dangerous Goods This approval allows the storage of hazardous materials where the product is a flammable gas, gas under pressure or flammable liquid, and stored in quantities that are less than those in column 5 of schedule 11 of the Work Health and Safety Regulation 2011. All materials listed as dangerous goods under The Australian Code for The Transport Of Dangerous Goods By Road and Rail (ADG Code) must be stored and handled on site in accordance with the relevant Australian Standard which applies to the Dangerous Goods Class of the material. This limitation is applied to the approved development, not to individual buildings, areas or tenancies. |
To be maintained |
| 29) Warehouse This development approval is for warehouse use only. |
As indicated |
| 30) Hours of Operation Hours of operation, including deliveries are: · 24hrs, 7 days a week |
As indicated |
| 31) Tyre Noise Reduction The driveways and carpark surfaces are to be appropriately treated/surfaced to reduce tyre noise impacts from the development. PROOF OF
FULFILMENT Provide Certification that appropriate treatments/surfacing has been provided to the driveways and carpark areas to reduce tyre noise impact from the development. Certification must be provided by a Member or professional eligible to be a Member of the Australian Acoustic Society. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 32) Dampening of Grilles And Metal Plates All metal grilles, metal plates or similar
subject to vehicular traffic must be acoustically damped to prevent
environmental nuisance. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 33) Plant and Equipment Certification Following the
installation of all mechanical plant and equipment (e.g. air conditioning,
mechanical ventilation and refrigeration equipment and heat pump hot water
systems), submit to Development Services certification that the plant and
equipment is adequately noise-attenuated and is in accordance with the criteria
of the relevant Brisbane Planning Scheme Codes/Policies. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 34) Spillage - Materials & Equipment to Contain & Clean
Up Appropriate materials and equipment are to be
available on site at all times to contain and clean up spills of potentially
polluting materials. An inventory of all clean up and containment materials and
equipment, and documented emergency response and clean up procedures must be
kept on site. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 35) Liquid Contaminants - Storage Provide and maintain adequate storage areas for
potential liquid contaminants such as paints, thinners, cleaning solvents,
detergents and oils to prevent contaminated washdown waters and material from
entering waterways, soil or ground water. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 36) Acid Sulphate Soils Submit for the approval of Development Assessment, an Acid Sulfate Soils (ASS) Investigation Report and Management Plan, where soil disturbance (e.g filling, excavation, drainage works, stripping of topsoil) is greater than 100m3 and the disturbance level is equal to or less than 5mAHD. The ASS Management Plan must detail management measures of possible impacts of soil disturbance and demonstrate the disturbance impact will be appropriately managed. Prepare the ASS Investigation Report and Management Plan in accordance with the following:
- ASS Investigation Report and the ASSMP sections of City Plan - Potential and actual acid sulfate soils PSP; - State Planning Policy 2017 and State Planning Policy State Interest Guideline Water Quality; - Queensland Acid Sulfate Soil Technical Manual: Soil Management Guidelines. - Guidelines for sampling and analysis of lowland acid sulfate soils (ASS) in Queensland 1998 (Ahem et al, 1998); and - Queensland Acid Sulfate Soil Technical Manual: Soil Management Guidelines, Sampling Guidelines, and Laboratory Methods Guideline.
The Management Plan must be prepared by a suitably qualified and experienced professional, with the following qualifications: - qualifications in agricultural or environmental soils science with specialisation in soil chemistry and hydrology; - at least 2 years experience in acid sulfate soil management; and - accreditation by a professional organisation such as the Australian Society of Soil Science. |
"Prior to building works commencing, or prior to making application under Section 401 of SPA 2009, or prior to making application under Schedule 19 of SPR 2009, or where approved under IPA 1997, prior to survey plan endorsement, whichever comes first |
36(a) Certification Submit to Development Assessment certification from a Registered Professional Engineer Queensland, that the measures recommended in the Acid Sulfate Soils (ASS) Management Plan have been implemented into the development. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first |
36(b) Impliment Management Plan Implement and maintain the provisions of the approved Acid Sulfate Soils Management Plan. |
While site/operational works/building works is occurring and until all exposed soil areas are permanently stabilised against erosion |
| 37) On-site Erosion (Medium Risk) Manage on-site erosion and the release of sediment or sediment laden water from the site at all times by implementing best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version). Timing: Prior to commencement of any land disturbing activities and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
37(a) Manage earth disturbance on-
site (i) Drainage control measures must be implemented and maintained to minimise water flow onto areas of exposed earth. (ii) Sediment and erosion control measures must be implemented and maintained to prevent soil loss from earth disturbance areas and prevent deposition beyond earth disturbance areas. (iii) No release of contaminants to land beyond on-site area of earth disturbance other than releases that achieve water pollutant concentration release limits of: A. 50mg/L TSS (Total Suspended Solids); B. Turbidity, Nephelometric Turbidity Units (NTU) value less than 10% above background, 75 NTU, or as agreed in writing by an Officer from Councils Erosion and Sediment Control (ESC) Team in Compliance and Regulatory Services; C. pH between 6.5 and 8.5 at all times. (iv) Maintain a written record to demonstrate that water discharges from the site, including any dewatering operations, meet the release limits as detailed in (iii) for water discharge(s) from the site that occur during or immediately after a rainfall event, and during normal business hours. The water quality of the discharge flows must be measured at each discharge point from the site, including but not limited to sediment basin outlets, other applicable sediment control devices, the site water drainage system, and recorded against the release limits at least once on each calendar day until such discharge stops. Timing: Prior to commencement of any earth disturbing activities and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
37(b) Provide Land Occupier Notification to
Council (i) Notify Council's ESC Team of proposed land occupier/s by sending an email to CARS-ESC@Brisbane.qld.gov.au (ii) If the land is to be occupied by any person other than the registered landowner then advice must be provided to Council that confirms the name, contact information and the duration of any proposed occupation of the land. Timing: Prior to commencement of any earth disturbing activities. |
As indicated |
37(c) Prepare Erosion and Sediment Control
Plan Prepare an Erosion and Sediment Control Plan (ESCP) in accordance with best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version) and, to the extent of any inconsistency, relevant Brisbane Planning Scheme Codes and Policies. Obtain a design certificate in accordance with the relevant Brisbane Planning Scheme Codes and Policies. The ESCP and design certificate must be certified by a Certified Professional in Erosion and Sediment Control (CPESC) or a Registered Professional Engineer Qld (RPEQ) with suitable qualifications and experience in erosion and sediment control. Documentary evidence demonstrating appropriate qualifications in erosion and sediment control must be provided to the Council upon request. Timing: Prior to the commencement of any earth disturbing activities. |
As indicated |
37(d) Attend a pre-start
meeting Arrange and attend a pre-start meeting for Erosion and Sediment Team, Compliance and Regulatory Services (CARS). All relevant documentation, including the certified erosion and sediment control plan and the certified design certificate must be submitted with the request. Note: To request a pre-start meeting refer to Council's website and search 'Pre-start meeting'. - A minimum 10 working days' notice is required. Timing: Prior to the commencement of any earth disturbing activities. |
As indicated |
37(e) Implement Certified Erosion and
Sediment Control Plan Implement the certified ESCP and maintain all ESC measures in accordance with best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version) and, to the extent of any inconsistency, relevant Brisbane Planning Scheme Codes and Policies. The ESCP and design certificate must be available on site at all times for inspection by Council officers. Any alteration to supplementary or Type 3 ESC measures must be reflected in the certified ESCP. Any alteration to Type 2 or Type 1 ESC measures will require a revised ESCP and design certificate that has been certified by either the CPESC or RPEQ. Timing: While earth disturbing activities are occurring and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
| 38) Information Signage Erect an information sign on the subject property in
accordance with Council's general requirements for signage and in accordance
with the requirements outlined below: Timing: Prior to site works commencing and then to be maintained until completion of the development for all stages. |
As indicated |
| 39) Construction Management Plan (Minor) Carry out development in a method consistent with a Construction Management Plan (Minor) prepared in accordance with the requirements of this condition. |
While site/operational/building work is occurring |
39(a) Construction Management Plan (Minor) -
Prepare Plan Prepare a detailed Construction Management Plan (CMP) for the
construction phase of the approved development.The Construction Management Plan
must be in accordance with the relevant Brisbane Planning Scheme Codes and
address the following: The Construction Management Plan must be supported by 'approval in principle' or written approvals from the relevant Council sections or other governing bodies responsible for any potentially impacted infrastructure. The list of relevant infrastructure and contacts is available on Council's website - Search 'Construction Management Plan'. Note: The Construction Management Plan is not required to be approved by Development Services. Timing: Prior to site/operational/building work commencing. |
As indicated |
39(b) Construction Management Plan (Minor) -
Submit Plan Submit a copy of the Construction Management Plan to Council's Development Services Branch at the following mailbox: engineeringservices@brisbane.qld.gov.au quoting the BCC planning development approval reference number. Timing: At least 10 days prior to site works commencing. |
As indicated |
39(c) Construction Management Plan (Minor) -
Documentation on Site Legible copies of the Construction Management Plan and current permits must be kept on site and be made available on request by Council at all times. The requirements of the CMP must be included in all induction of principal and subcontractors utilised in the development. An outline of the induction provided to contractors may be requested by Council to confirm compliance with this condition. Timing: While site/operational/building work is occurring. |
As indicated |
39(d) Construction Management Plan - Works to
be Performed Out of Hours Obtain an approval from Development Services for any
work that is proposed to be undertaken outside of normal business hours -
6:30am to 6:30pm, Monday to Saturday. |
As indicated |
39(e) Implement Construction Management Plan
(Minor) Carry out the development in accordance with the submitted Construction Management Plan. |
While site/operational/building work is occurring |
| 40) Protect Existing Infrastructure Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure. Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations. The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements. |
While site/operational/building work is occurring |
40(a) As Constructed Drawings - Alterations
to Existing Infrastructure Submit to Development Services As Constructed drawings showing all new and/or rectification works and an asset register, prepared by a Registered Professional Engineer Queensland. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 41) Filling and / or Excavation (Minor) Filling and/or excavation works on the site must be in accordance with the APPROVED PLANS and the relevant Brisbane Planning Scheme Codes. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
41(a) Prepare Earthworks
Drawings Earthworks drawings must be prepared and certified by a Registered Professional Engineer Queensland in accordance with the relevant Brisbane Planning Scheme Codes. The drawings must include the
following: Timing: Prior to site/operational/building work commencing. Note: The Earthworks drawings are not required to be submitted for Council approval. |
As indicated |
41(b) Implement and Maintain the
Earthworks Carry out and maintain the earthworks in accordance with the certified drawings. Note: A copy of the certified Earthworks Drawings must be available on-site for inspection by Council Officers during these works. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 42) Access, Grades, Manoeuvring, Carparks, Signs and
Line Marking Construct and maintain access, parking and manoeuvring for vehicles on site in accordance with the relevant Brisbane Planning Scheme Codes, as indicated on the approved DRAWINGS AND DOCUMENTS, including the following: i. A pavement of minimum local road standard or equivalent surface material (including associated drainage) to the area on which motor vehicles will be driven and/or parked. ii. Manoeuvring on site for an Articulated Vehicle and for the loading and unloading of vehicle(s); iii. Parking on the site for 25 cars, including 1 parking space for people with disabilities and for the loading and unloading of vehicle(s) within the site. There must a minimum number of 25 total number of spaces provided on site. iv. A minimum of 2.3 metres height clearance to all undercover parking areas, including the entry and access to these areas, and a minimum of 2.5 metres above parking spaces for people with disabilities. The minimum clear height must be measured to the lowest protrusion from the ceiling (e.g. fire sprinklers, services, lighting fixtures, signs, etc). v. A height clearance sign located at the entrance(s) to undercover car parking areas and a directional visitor parking sign clearly visible from the vehicle entrance to the site. vi. An appropriate area for the storage and collection of refuse, including recyclables, in a position which is accessible to service vehicles on the site. vii. Prepare and implement signs and line markings drawings that show the internal paved areas signed and delineated in accordance with the approved drawings and documents. The drawings must be prepared and certified by a Registered Professional Engineer Queensland in accordance with the relevant Brisbane Planning Scheme Codes and the Manual of Uniform Traffic Control Devices. PROOF OF
FULFILMENT Certification from a Registered Professional Engineer Queensland, that the above requirements have been implemented in accordance with this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 43) Repair Damage to Kerb, Footpath or Road Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
43(a) Interim Repairs If at any time during the construction phase of the approved development, damage to the existing kerb and channel, footpath or roadway creates unsafe, unreasonable and/or not fit for purpose conditions as assessed by Council, interim repairs must be undertaken as directed by Program Planning and Integration. Note: Any interim repairs required to be undertaken shall not be considered to satisfy the requirements of this condition for the permanent repair of the infrastructure prior to the issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. Timing: While site / operational / building works is occurring. |
As indicated |
| 44) Flood Emergency Management Plan Prepare, implement and maintain a Flood Emergency Management Plan (FEMP) in accordance with the requirements of this condition. Note: Guidance for the preparation of drawings and/or documents to comply with this condition is provided in the Flood Planning Scheme Policies. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
44(a) Prepare and Certify a Flood Emergency
Management Plan Submit to Development Services a Flood Emergency Management Plan (FEMP) for the approved development prepared and certified by a Registered Professional Engineer Queensland with experience in flood risk management. Timing: Prior to issue of Certificate of Occupancy/Final Inspection. |
As indicated |
| 45) Minimum Flood Planning Levels Design and construct all building pad levels, floor levels and ancillary structures to the appropriate flood planning level with freeboard (where required) in accordance with the relevant Brisbane Planning Scheme Codes and the approved drawings and documents. The minimum floor level must be 8.0 metres AHD. The minimum level for essential electrical services must be 8.0 metres AHD. PROOF OF FULFILMENT As-Constructed drawings prepared by a Registered Surveyor (Qld). The Registered Surveyor (Qld) must certify that the development has been constructed in accordance with this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 46) Non-Residential Refuse Collection - On Site Provide for the installation and collection of refuse/recycling bins. |
At all times |
46(a) Arrange Refuse Collection Arrange for the installation of refuse/recycling bins and for the subsequent collection of refuse including recycling from the site by a private waste contractor or Brisbane City Council's Waste and Resource Recovery Services. Timing: A minimum of four weeks prior to the commencement of use and then to be maintained. PROOF OF FULFILMENT Where a private waste contractor is engaged, provide written confirmation from the proposed waste collection contractor of the agreement to service the property. The written agreement must be submitted to Council's Waste and Resource Recovery Services and include full details of the proposed system, bin sizes, number of bins, frequency of collection and the refuse collection vehicle size. Prior to commencement of use |
As indicated |
46(b) Indemnify Council Where Council is engaged as the waste contractor, the owner and any subsequent owner must, by approved form to Waste and Resource Recovery Services, indemnify Council and its agents in respect of any damage to the pavement and other driving surfaces. Timing: When an arrangement for refuse/recycling collection services is made with Brisbane City Council. |
At all times |
46(c) Notify Future Owner Where Council is engaged as the waste contractor, the owner must notify any future owner/body corporate that the development has been approved on the basis that an indemnity must be provide for refuse collection vehicles to enter the property. Timing: At time of a change of ownership. |
At all times |
| 47) Refuse Storage - On Site Collection Provide a roofed and wholly screened refuse enclosure utilising materials consistent with the development or a dedicated refuse storage room, as shown on the approved plans and documents. The enclosure/refuse storage room must be of a design to accommodate the quantity of refuse and recycling including source separation to allow for low servicing collection of the development. Bins must be located in an area which allows them to be manoeuvred from the bin storage area to the designated internal collection point. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 48) Remove Redundant Drainage Outlets Remove any redundant
drainage outlets from the kerb and channel including any associated pipe work
across the footway and reinstate the kerb and channel and the footway area in
accordance with the relevant Brisbane Planning Scheme Codes. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 49) Ponding of Stormwater Carry out the approved development to ensure that adjoining properties and roads are protected from ponding or nuisance from stormwater during construction. Notes: If remedial works are necessary to comply with this condition, prior approval must be obtained from Development Services. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 50) On Site Drainage - Minor Provide a stormwater connection to all new or existing allotments and provide drainage infrastructure to ensure stormwater run-off from all roof and developed surface areas will be collected internally and piped in accordance with the relevant Brisbane Planning Scheme Codes to 'a lawful point of discharge' being the existing drainage in the Ipswich Road Service Road. Note: - Guidance for requesting a pre-start and co-ordinating the On/Off Maintenance process can be found on Council's website (https://www.brisbane.qld.gov.au/planning-and-building/applying-and-post- approval/on-and-off-maintenance-approvals). |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 51) Service Conduits and Mains Provide and install all
service conduits and meet the cost of any alterations to public utility mains,
existing mains, services, street lighting or installations that are required to
carry out the approved development. These works must be in accordance with the
relevant Brisbane Planning Scheme Codes, and include the following, where
applicable: Note: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
51(a) Submit As Constructed
Drawings Submit to Development Services As Constructed drawings, including an asset register, prepared and certified by a Registered Professional Engineer Queensland. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the requirements of this condition. Note: Civil works are to be certified by a RPEQ(Civil) and electrical works are to be certified by a RPEQ (Electrical). |
As indicated |
| 52) Telecommunications Submit to Development Services, certification from
an authorised telecommunications carrier/contractor, that the following works
and infrastructure have been undertaken and installed in accordance with
telecommunications industry standards: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 53) Agreement with Electricity Supplier Submit to Development Services, evidence of an agreement with an electricity supplier to provide necessary services to the development in accordance with the relevant Brisbane Planning Scheme Codes. Where development is within an established area of overhead electricity supply and the electricity supplier determines that a property pole is the appropriate solution to supply electricity to the development, the developer must be responsible for the installation of the property pole(s). In the above circumstances, submit to Development Services, certification from the developer's electrical consultant confirming that the above installation has been completed in accordance with the relevant AS/NZS Standards and the Queensland Electricity Connection Manual (QECM) and Queensland Electricity Metering Manual (QEMM). |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 54) Water and Wastewater Pursuant to Schedule 18 of the Planning Regulation 2017 submit to Development Services, documentary evidence, issued by the relevant distributor-retailer, to verify that the conditions of any necessary connection certificate under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009, have been complied with. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 55) Construction Noise and Dust Emissions Pursuant to the
Environmental Protection Act 1994, all development involving the emission of
noise and dust from building and/or construction activities, must ensure that
the emissions are in accordance with the requirements of the Act. |
As indicated |
| 56) Further Development Permit Required Further Development Permit(s) to carry out assessable building work under the Building Act may be required. |
As indicated |
| 57) Plumbing and Drainage Work Pursuant to the Plumbing and Drainage Act 2018, any plumbing and drainage work must be carried out in compliance with the Plumbing and Drainage Regulation 2019. Note: All new and existing plumbing services should be located within the lot that they serve. Compliance assessable plumbing and drainage work requires approval by Brisbane City Council prior to the work being carried out. |
As indicated |
| 58) Currency Period The currency period for this development approval is stated in the Decision Notice and is expressed as a date. This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016. |
As indicated |
| 59) Referral Agency Requirements State Assessment and Referral Agency (SARA) as referral agency has imposed the requirements contained in the letter dated 8 August 2024 (SARA reference: 2306-35319 SRA). |
As indicated |
| 60) Damage to Trees on Adjoining Land Please note that any damage caused to vegetation on adjoining land as a result of exercising this development approval may result in an offence under other legislation (e.g. Natural Assets Local Law) and/or civil action |
As indicated |
| 61) Fire Ant Movement Controls To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected. These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products. Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014. For further information contact the relevant Queensland State Government department on 13 QGOV. |
As indicated |
| 62) Water and Wastewater Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. For further information about any necessary Water Approvals contact Urban Utilities. |
As indicated |
| 63) Flood Resilience and Awareness This advice is provided for buildings that are on sites that are subject to the flood overlay, as shown within City Plan 2014. Council makes decisions to minimise flood risk based on the best information available at the time of the development application. Flood studies and applicable flood levels may be updated by Council overtime where new flood information is available or changes to engineering standards/methodology have occurred. Flood levels for various flood events and flooding types are outlined in Council's Floodwise Property Reports available from Councils website. The minimum flood planning levels that apply to new development do not necessarily mean that the development will never flood. Therefore, when choosing materials for building on sites that are known to be affected by flooding, regardless of whether it is constructed to the minimum flood planning level, it is recommended that flood resilient materials are used to improve the speed of recovery and reduce the cost of repairs if required. For more information refer to: Council's website at https://www.brisbane.qld.gov.au/community-and-safety/community- safety/disasters-and-emergencies/be-prepared/flooding-in-brisbane/flooding- support-for-residents/flood-resilient-homes-program Queensland Reconstruction Authority "Flood Resilient Building Guidance for Queensland Homes"https://www.qra.qld.gov.au/resilient- homes/flood-resilient-building-guidance-queensland-homes |
As indicated |
| 64) Cultural Heritage Aboriginal cultural heritage is protected under the Aboriginal Cultural Heritage Act 2003. This Act establishes a cultural heritage duty of care and in section 23(1) mandates that a person who carries out an activity must take all reasonable and practicable measures for ensuring activities are managed to avoid or minimise harm to Aboriginal cultural heritage.
The Duty of Care Guidelines gazetted pursuant to the Aboriginal Cultural Heritage Act 2003 provide guidance on identifying and protecting Aboriginal cultural heritage to fulfil the duty of care.
For further information contact the relevant Queensland State Government Department (Department of Aboriginal and Torres Strait Islander Partnerships). |
As indicated |
| Permit to Which These Conditions Relate: | DA - PA - Referral Agency for Building Work |
| Activity(ies): | Flood hazard area |
| Stage: | Early Referral Agency Response for Flood Hazard Area |
| 65) Early Referral Agency Response (Flood hazard
area) Council has chosen to issue an early referral agency response under section 57 of the Planning Act 2016 for the proposed building work located within a Flood hazard area (Planning Regulation 2017, Schedule 9, Part 3, Division 2, Table 12). The response is attached to this decision notice. |
As indicated |