BRISBANE CITY COUNCIL'S APPROVAL PACKAGE.



APPLICATION DETAILS

This package relates to the application detailed below
Address of Site: 1800 IPSWICH RD ROCKLEA QLD 4106
1808 IPSWICH RD ROCKLEA QLD 4106
Real Property Description of Site: L2 RP.148384
L1 RP.148384
Aspects of development and type of approval: DA - PA - Building Work Development Permit - warehouse
DA - PA - Material Change of Use Development Permit - warehouse
DA - PA - Referral Agency for Building Work Referral Response - Flood hazard area
Council File Reference: A006982595
Permit Reference Number/s: DABW436202823; DAMC437848623; DAEB452899924.
Package Status: APPROVED - Version 2 (4th of June, 2026 4:20:35 PM)
Package Generated: 04/06/2026


PROJECT TEAM

The assessment of this application has been undertaken by:
Errin Xiaofang LU
Senior Urban Planner
Planning Services South
Errin.Lu@brisbane.qld.gov.au
(07) 3403 3694
Timothy BYRNE
Principal Urban Planner
Planning Services South
Timothy.Byrne@brisbane.qld.gov.au
(07) 3403 0314
Errin Xiaofang LU
Senior Urban Planner
Planning Services South
Errin.Lu@brisbane.qld.gov.au
(07) 3403 3694
Zarndra PIPER
Principal Urban Planner
Planning Services South
Zarndra.Piper@brisbane.qld.gov.au
0731780370
Michael O'REILLY
Environmental Management Officer
Environmental Management Services
Michael.O'Reilly@brisbane.qld.gov.au
3403 9517
JOANNE LOVE-SLOMAN
Landscape Architect
Landscape Architecture Team
joanne.lovesloman@brisbane.qld.gov.au
(07) 3403 8888
Chris HENNESSY

Engineering Services Traffic
Chris.Hennessy@brisbane.qld.gov.au
(07) 3403 5768
Eric OWEN
Senior Technical Officer
Engineering Services South
eric.owen@brisbane.qld.gov.au
(07) 3178 5195
Khiang POH
Senior Engineer
Engineering Scoping
khiang.poh@brisbane.qld.gov.au
(07) 3407 0889
Timothy BYRNE
Principal Urban Planner
Planning Services South
Timothy.Byrne@brisbane.qld.gov.au
(07) 3403 0314
Margaret ORR
Team Manager
Planning Services South
margaret.orr@brisbane.qld.gov.au
(07) 34070751
Eric OWEN
Senior Technical Officer
Engineering Services South
eric.owen@brisbane.qld.gov.au
(07) 3178 5195
Chris HENNESSY

Engineering Services Traffic
Chris.Hennessy@brisbane.qld.gov.au
(07) 3403 5768
Tim DWYER

WaRRS Assessment
Tim.Dwyer@brisbane.qld.gov.au
JOANNE LOVE-SLOMAN
Landscape Architect
Landscape Architecture Team
joanne.lovesloman@brisbane.qld.gov.au
(07) 3403 8888
Craig SLACK
Engineer
Engineering Scoping
craig.slack@brisbane.qld.gov.au
(07) 3403 8888


DRAWINGS AND DOCUMENTS



The term 'drawings and documents' or similar expressions mean:
Drawing or Document Number Plan Date
Proposed Site Plan DA-02.2 E 26-MAY-2026 (Received)
Demolition Ground Floor Plan DA-05.1 F 26-MAY-2026 (Received)
Demolition Roof Plan DA-05.2 E 26-MAY-2026 (Received)
Proposed Ground Floor Plan DA-05.3 E 26-MAY-2026 (Received)
Proposed First Floor Plan DA-05.4 D 26-MAY-2026 (Received)
Proposed Roof Plan DA-09.1 F 26-MAY-2026 (Received)
Elevations DA-11.1 F 26-MAY-2026 (Received)
Section A DA-12.1 F 26-MAY-2026 (Received)


Advice

Please see the attached document(s) for any advices.

APPROVAL CONDITIONS



Permit to Which These Conditions Relate: DA - PA - Building Work
Activity(ies): warehouse
Stage: Extension to Warehouse

General/Planning Requirements
 
Timing
1)   Approved Drawings and Documents

A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers.

Note: This condition is imposed to ensure compliance with the conditions of development approval.

 
While site/operational/building work is occurring
 
2)   Carry Out the Approved Development

Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS.

Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners.

 
While site/operational/building work is occurring
 
3)   Complete All Building Work

Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS.

Note: Building work must also be completed in accordance with any other current development approval.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
Engineering
 
Timing
4)   Protect Existing Infrastructure

Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure.

Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations.

The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements.

 
While site/operational/building work is occurring
4(a) As Constructed Drawings - Alterations to Existing Infrastructure

Submit to Development Services As Constructed drawings showing all new and/or rectification works and an asset register, prepared by a Registered Professional Engineer Queensland.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

PROOF OF FULFILMENT
Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
5)   Repair Damage to Kerb, Footpath or Road

Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
5(a) Interim Repairs

If at any time during the construction phase of the approved development, damage to the existing kerb and channel, footpath or roadway creates unsafe, unreasonable and/or not fit for purpose conditions as assessed by Council, interim repairs must be undertaken as directed by Program Planning and Integration.

Note: Any interim repairs required to be undertaken shall not be considered to satisfy the requirements of this condition for the permanent repair of the infrastructure prior to the issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

Timing: While site / operational / building works is occurring.

 
As indicated
 
6)   Flood Emergency Management Plan

Prepare, implement and maintain a Flood Emergency Management Plan (FEMP) in accordance with the requirements of this condition.

Note: Guidance for the preparation of drawings and/or documents to comply with this condition is provided in the Flood Planning Scheme Policies.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
6(a) Prepare and Certify a Flood Emergency Management Plan

Submit to Development Services a Flood Emergency Management Plan (FEMP) for the approved development prepared and certified by a Registered Professional Engineer Queensland with experience in flood risk management.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection.

 
As indicated
 
7)   Minimum Flood Planning Levels

Design and construct all building pad levels, floor levels and ancillary structures to the appropriate flood planning level with freeboard (where required) in accordance with the relevant Brisbane Planning Scheme Codes and the approved drawings and documents.

The minimum floor level must be 8.0 metres AHD.

The minimum level for essential electrical services must be 8.0 metres AHD.

PROOF OF FULFILMENT
As-Constructed drawings prepared by a Registered Surveyor (Qld). The Registered Surveyor (Qld) must certify that the development has been constructed in accordance with this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
Standard Advice
 
Timing
8)   Construction Noise and Dust Emissions

Pursuant to the Environmental Protection Act 1994, all development involving the emission of noise and dust from building and/or construction activities, must ensure that the emissions are in accordance with the requirements of the Act.
The Environmental Protection Act 1994 prescribes that:

1. A person must not carry out building work in a way that makes an audible noise-
-  on a business day or Saturday, before 6.30a.m. or after 6.30p.m; or
-   on any other day, at any time. 
2. The reference in subsection (1) to a person carrying out building work-
-  includes a person carrying out building work under an owner-builder permit; and
-  otherwise does not include a person carrying out building work at premises used by the person only for residential purposes.

Note: A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management delegate Development Services.

 
As indicated
 
9)   Further Development Permit Required

Further Development Permit(s) to carry out assessable building work under the Building Act may be required.

 
As indicated
 
10)   Currency Period

The currency period for this development approval is stated in the Decision Notice and is expressed as a date.

This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016.

 
As indicated
 
11)   Flood Resilience and Awareness

This advice is provided for buildings that are on sites that are subject to the flood overlay, as shown within City Plan 2014.

Council makes decisions to minimise flood risk based on the best information available at the time of the development application. Flood studies and applicable flood levels may be updated by Council overtime where new flood information is available or changes to engineering standards/methodology have occurred. Flood levels for various flood events and flooding types are outlined in Council's Floodwise Property Reports available from Councils website.

The minimum flood planning levels that apply to new development do not necessarily mean that the development will never flood. Therefore, when choosing materials for building on sites that are known to be affected by flooding, regardless of whether it is constructed to the minimum flood planning level, it is recommended that flood resilient materials are used to improve the speed of recovery and reduce the cost of repairs if required.

For more information refer to:

Council's website at https://www.brisbane.qld.gov.au/community-and-safety/community- safety/disasters-and-emergencies/be-prepared/flooding-in-brisbane/flooding- support-for-residents/flood-resilient-homes-program

Queensland Reconstruction Authority "Flood Resilient Building Guidance for Queensland Homes"https://www.qra.qld.gov.au/resilient- homes/flood-resilient-building-guidance-queensland-homes

 
As indicated
 



Permit to Which These Conditions Relate: DA - PA - Material Change of Use
Activity(ies): warehouse
Stage: Extension to Warehouse

General/Planning Requirements
 
Timing
12)   Security Lighting - On Site

Install and maintain a suitable system of security lighting to operate from dusk to dawn within all areas where the public may gain access, including car parking areas, internal pathways, building entrances and vegetated areas. Lighting of publicly accessible internal areas is in accordance with Australian Standard – AS/NZS 1158.3.1 Lighting for roads and public spaces – Pedestrian area lighting – Performance and design requirements.

All external lighting within the site is in accordance with Australian Standard - AS4282- Control of the Obtrusive Effects of Outdoor Lighting.

Lighting must be maintained in safe and good working order.

Timing: 'Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first'

 
As indicated
 
13)   Building Format Plan

Where the timing of a condition, or part thereof , states 'Prior to issue of Certificate of Occupancy/Final Inspection Certificate' or 'Prior to commencement of use' and the development involves the creation of a Building Format Plan, the timing of the condition, or part thereof, is taken to mean 'prior to Council's endorsement of any plan of subdivision'.

 
As indicated
 
14)   Car Parking

The car parking within the premises must be maintained exclusively for the ancillary use of the development. The parking must not be made available to the general public and there must not be signage erected on or in the vicinity of the site advertising the availability of car parking to the general public.

 
At all times
 
15)   Maintain the Approved Development

Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions.

 
At all times
 
16)   Original Condition Package

All conditions relating to the original approval (Council reference: 420/10- 2522/89) issued on 8 February 1990 and as modified on 3 May 1990, remain applicable, unless varied by this approval.

 
At all times
 
17)   Approved Drawings and Documents

A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers.

Note: This condition is imposed to ensure compliance with the conditions of development approval.

 
While site/operational/building work is occurring
 
18)   Carry Out the Approved Development

Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS.

Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners.

 
While site/operational/building work is occurring
 
19)   Demolish or Relocate Buildings/Structures

Demolish buildings/structures on the site in accordance with the approved DRAWINGS AND DOCUMENTS and where applicable, the approved Construction Management Plan.

The removal of buildings/structures includes the removal of all existing concrete slabs, foundations and footings.

 
Prior to Council's notation on the plan of subdivision
 
20)   Complete All Operational Work

Complete all operational work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such operational work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS or, if requiring a further approval from the Council, in accordance with the relevant further approval(s).

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
21)   Complete All Building Work

Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS.

Note: Building work must also be completed in accordance with any other current development approval.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
22)   Limitation of Use - Ancillary Administration Area - Industry

The ancillary administration space/s on the site are to be limited to the area shown on the APPROVED DRAWINGS AND DOCUMENTS. This area/s must remain ancillary to the approved Warehouse use and must not operate separately.

TIMING: At the commencement of use and then to be maintained

Should the approved Warehouse use cease, the use of the ancillary administration area must also cease.

TIMING: At the time the approved use ceases.

 
As indicated
 
23)   On-site Staff Recreation Area - Industry

Provide an on-site recreation area for staff in accordance with the APPROVAL DRAWINGS AND DOCUMENTS and which:

- includes seating, tables and rubbish bins;

- is adequately protected from the weather;

- is safely accessible to all staff;

- is separate and private from public areas; and

- is located away from noisy or odorous activities

 
Prior to the commencement of the use and then to be maintained
 
Landscape Architecture and Open Space Planning
 
Timing
24)   Retain and Protect Existing Street Tree(s)

Identify, retain and protect the existing street trees including the roots unless otherwise agreed in writing with Program, Planning and Integration Arboriculture (PPI Arb).

Note: Street trees are protected under the Natural Assets Local Law. Street trees must not be removed or pruned without prior approval from PPI Arb.

Where driveway crossovers occur within the Tree Protection Zone (TPZ) of existing street trees, seek approval from the Arboricultural Team in Program Planning and integration, City Standards for the final driveway crossover design and construction methodology to ensure the successful retention of the existing street tree(s)

PROOF OF FULFILMENT
Contextual photographic evidence that the tree has been retained in equal or greater health than before development commenced. OR, evidence in writing fromPPI Arboriculture that an alternative arrangement has been made. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
At all times
24(a) Implement Protection Measures

Install tree protection measures in accordance with Australian Standard - AS4970 Protection of Trees on Development Sites.

There must be no excavation, filling or storage of materials or plant within the drip line of the tree(s).

Where works are within the canopy drip line of existing street trees, contact PPI Arb Coordinator in relation to the required provision of protection measures.

Note: If fencing is to protect street trees, a permit to temporarily occupy the footway will be required from Compliance and Regulatory Services.

Timing: Prior to site/operational/building work occurring.

PROOF OF FULFILMENT
Contextual photographic evidence to demonstrate the installation of protection measures prior to building works commencing. Timing: Prior to site / operational / building work occurring.

 
As indicated
24(b) Maintain Protection Measures

Maintain protection measures while development is occurring and remove protection measures prior to commencement of the use.

Timing: While to site/operational/building work is occurring.

 
As indicated
 
25)   Streetscape Works - Industrial Street

Carry out streetscape improvement works including concrete path, turf and street trees to the Ipswich Road and Reginald Street verges to an Industrial Street standard in accordance with the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD), the requirements of this condition and the Infrastructure Design Planning Scheme Policy including sections 3.7.4.5 and 3.7.5.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
25(a) Concrete Path

Install a 1.2m wide broom finished standard Portland grey concrete path. The edge of the path is to be setback 1.9m from the back of kerb. The path is to transition to existing paths on verges that adjoin the development.

If the above requirements cannot be achieved, contact the Landscape Architecture Team via email: specialistservices@brisbane.qld.gov.au

Transition to existing paths on verges that adjoin the development. The transition is to occur fronting the adjoining developments, not the subject site.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

PROOF OF FULFILMENT
Submit to Development Services, photographic evidence of concrete path.

 
As indicated
25(b) Submit As-Constructed Drawings

Submit to Development Services "As Constructed" plans including an asset register, checked by a Registered Professional Engineer Queensland, certifying that the concrete path works have been completed in accordance with relevant Brisbane Planning Scheme Codes/Policies.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

PROOF OF FULFILMENT
As constructed drawings and asset register signed by an RPEQ.

 
As indicated
25(c) Turf

Install turf to the full width of the verge excluding any concrete path required by this condition.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

PROOF OF FULFILMENT
Photographic evidence of installed turf.

 
As indicated
25(d) Street Tree(s)


Enter into and implement an arrangement with the Program Planning Integration Regional Coordinator Arboriculture in relation to the required provision of the street tree planting in accordance with the Infrastructure Design Planning Scheme Policy, including the number, species, location, installation and maintenance of the required street tree(s) as determined by Program Planning Integration. Provide to Development Services a copy of the agreement signed by Program Planning Integration.

Note: Street trees should not be planted until all utilities have been installed.

Timing: Prior to issue of Certificate of Occupancy / Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation on the plan of subdivision (ROL).

PROOF OF FULFILMENT
Provide to Development Services a copy of the agreement signed by Program Planning Integration.

 
As indicated
 
26)   Landscape the Site - Self Certification

Landscape the site in accordance with the requirements of this condition.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
26(a) Detailed Landscape Plan for Self- Certification

Prepare a Detailed Landscape Plan at a scale of 1:100 for all on-site landscape works including planting areas identified on the approved DRAWINGS AND DOCUMENTS. The plan must be prepared by a qualified Landscape Architect and must comply with the relevant Brisbane Planning Scheme Codes.

The plan must include the following:
- Planting media and mulch in accordance with AS4454 Composts, soil conditioners and mulches and AS 4419-2003 Soils for landscaping and garden use.
- Unless otherwise specified, trees provided as 45 litre stock or larger, staked and tied, and complying with Australian Standards.
- Plant selection and densities to achieve full surface coverage of garden beds within 2 years of planting.
- A reticulated drip irrigation system to all planting areas, with drainage connected to the stormwater system; the irrigation system must be connected to a non-mains water source.
- Trees required to be retained are documented, integrated into landscape design, and protected in accordance with the relevant sections of Australian Standard AS4970 Protection of trees on development sites.
- Details of a 12 week establishment period.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

PROOF OF FULFILMENT
A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
26(b) Industry

In addition to the requirements listed above, the plan must include the following:
- All landscape areas are to consist of a tiered landscape structure (trees, screening trees/shrubs, low shrubs and ground covers).
- Trees planted in landscaped areas along site frontages which will achieve a canopy spread over 50% of the site frontage within 5 years of planting, as shown on the approved drawings (northern boundary).
- New trees planted within the landscape areas shown on the approved drawings including the side boundary, northern and southern boundaries.
- Large screening shrubs and ground covers in landscaped areas shown on the approved drawings along the side boundaries.
- One shade tree per six car parking spaces where landscaped areas shown on the approved drawings adjoin car parking.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

PROOF OF FULFILMENT
A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
26(c) Certify Detailed Landscape Plan

On completion of the Detailed Landscape Plan, submit to Development Services:
- Brisbane City Council Form CC10616 - Landscape Design Certificate prepared by a Qualified Landscape Architect to certify that the Detailed Landscape Plan complies with the requirements of this condition
- A copy of the certified Detailed Landscape Plan.

Timing: Prior to building work commencing.

PROOF OF FULFILMENT
A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to building work commencing.

 
As indicated
26(d) Implement Certified Detailed Landscape Plan

Carry out the landscape work in accordance with the above certified detailed Landscape Plan.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
26(e) Certify Work

On completion of the landscape work, submit to Development Services:
- Brisbane City Council Form CC10613 - Landscape Works Certificate prepared by a Qualified Landscape Architect or licensed Landscape Contractor to certify the completed landscape work complies with the certified Detailed Landscape Plan
- A copy of the as-constructed certified Detailed Landscape Plan.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

PROOF OF FULFILMENT
An as constructed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
26(f) Maintain Landscape Work

Maintain the landscape work, including deep planting, in accordance with the certified Detailed Landscape Plan.

Timing: To be maintained.

 
As indicated
 
Pollution
 
Timing
27)   Air Quality

There is to be no Air Pollutants emitted from industrial activity in this warehouse development.

 
At all times
 
28)   Dangerous Goods

This approval allows the storage of hazardous materials where the product is a flammable gas, gas under pressure or flammable liquid, and stored in quantities that are less than those in column 5 of schedule 11 of the Work Health and Safety Regulation 2011. All materials listed as dangerous goods under The Australian Code for The Transport Of Dangerous Goods By Road and Rail (ADG Code) must be stored and handled on site in accordance with the relevant Australian Standard which applies to the Dangerous Goods Class of the material. This limitation is applied to the approved development, not to individual buildings, areas or tenancies.

 
To be maintained
 
29)   Warehouse

This development approval is for warehouse use only.

 
As indicated
 
30)   Hours of Operation

Hours of operation, including deliveries are:

· 24hrs, 7 days a week

 
As indicated
 
31)   Tyre Noise Reduction

The driveways and carpark surfaces are to be appropriately treated/surfaced to reduce tyre noise impacts from the development.

PROOF OF FULFILMENT
Provide Certification that appropriate treatments/surfacing has been provided to the driveways and carpark areas to reduce tyre noise impact from the development. Certification must be provided by a Member or professional eligible to be a Member of the Australian Acoustic Society. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
32)   Dampening of Grilles And Metal Plates

All metal grilles, metal plates or similar subject to vehicular traffic must be acoustically damped to prevent environmental nuisance.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
33)   Plant and Equipment Certification

Following the installation of all mechanical plant and equipment (e.g. air conditioning, mechanical ventilation and refrigeration equipment and heat pump hot water systems), submit to Development Services certification that the plant and equipment is adequately noise-attenuated and is in accordance with the criteria of the relevant Brisbane Planning Scheme Codes/Policies.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
34)   Spillage - Materials & Equipment to Contain & Clean Up

Appropriate materials and equipment are to be available on site at all times to contain and clean up spills of potentially polluting materials. An inventory of all clean up and containment materials and equipment, and documented emergency response and clean up procedures must be kept on site.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
35)   Liquid Contaminants - Storage

Provide and maintain adequate storage areas for potential liquid contaminants such as paints, thinners, cleaning solvents, detergents and oils to prevent contaminated washdown waters and material from entering waterways, soil or ground water.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
36)   Acid Sulphate Soils

Submit for the approval of Development Assessment, an Acid Sulfate Soils (ASS) Investigation Report and Management Plan, where soil disturbance (e.g filling, excavation, drainage works, stripping of topsoil) is greater than 100m3 and the disturbance level is equal to or less than 5mAHD. The ASS Management Plan must detail management measures of possible impacts of soil disturbance and demonstrate the disturbance impact will be appropriately managed. Prepare the ASS Investigation Report and Management Plan in accordance with the following: 

 

- ASS Investigation Report and the ASSMP sections of City Plan - Potential and actual acid sulfate soils PSP; 

- State Planning Policy 2017 and State Planning Policy State Interest Guideline Water Quality;

- Queensland Acid Sulfate Soil Technical Manual: Soil Management Guidelines. - Guidelines for sampling and analysis of lowland acid sulfate soils (ASS) in Queensland 1998 (Ahem et al, 1998); and

- Queensland Acid Sulfate Soil Technical Manual: Soil Management Guidelines, Sampling Guidelines, and Laboratory Methods Guideline.  

 

The Management Plan must be prepared by a suitably qualified and experienced professional, with the following qualifications:  - qualifications in agricultural or environmental soils science with specialisation in soil chemistry and hydrology; - at least 2 years experience in acid sulfate soil management; and - accreditation by a professional organisation such as the Australian Society of Soil Science.

 
"Prior to building works commencing, or prior to making application under Section 401 of SPA 2009, or prior to making application under Schedule 19 of SPR 2009, or where approved under IPA 1997, prior to survey plan endorsement, whichever comes first
36(a) Certification

Submit to Development Assessment certification from a Registered Professional Engineer Queensland, that the measures recommended in the Acid Sulfate Soils (ASS) Management Plan have been implemented into the development.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first
36(b) Impliment Management Plan

Implement and maintain the provisions of the approved Acid Sulfate Soils Management Plan.

 
While site/operational works/building works is occurring and until all exposed soil areas are permanently stabilised against erosion
 
Engineering
 
Timing
37)   On-site Erosion (Medium Risk)

Manage on-site erosion and the release of sediment or sediment laden water from the site at all times by implementing best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version).

Timing: Prior to commencement of any land disturbing activities and until all exposed soil areas are permanently stabilised against erosion.

 
As indicated
37(a) Manage earth disturbance on- site

(i) Drainage control measures must be implemented and maintained to minimise water flow onto areas of exposed earth.

(ii) Sediment and erosion control measures must be implemented and maintained to prevent soil loss from earth disturbance areas and prevent deposition beyond earth disturbance areas.

(iii) No release of contaminants to land beyond on-site area of earth disturbance other than releases that achieve water pollutant concentration release limits of:

A. 50mg/L TSS (Total Suspended Solids);

B. Turbidity, Nephelometric Turbidity Units (NTU) value less than 10% above background, 75 NTU, or as agreed in writing by an Officer from Councils Erosion and Sediment Control (ESC) Team in Compliance and Regulatory Services;

C. pH between 6.5 and 8.5 at all times.

(iv) Maintain a written record to demonstrate that water discharges from the site, including any dewatering operations, meet the release limits as detailed in (iii) for water discharge(s) from the site that occur during or immediately after a rainfall event, and during normal business hours. The water quality of the discharge flows must be measured at each discharge point from the site, including but not limited to sediment basin outlets, other applicable sediment control devices, the site water drainage system, and recorded against the release limits at least once on each calendar day until such discharge stops.

Timing: Prior to commencement of any earth disturbing activities and until all exposed soil areas are permanently stabilised against erosion.

 
As indicated
37(b) Provide Land Occupier Notification to Council

(i) Notify Council's ESC Team of proposed land occupier/s by sending an email to CARS-ESC@Brisbane.qld.gov.au

(ii) If the land is to be occupied by any person other than the registered landowner then advice must be provided to Council that confirms the name, contact information and the duration of any proposed occupation of the land.

Timing: Prior to commencement of any earth disturbing activities.

 
As indicated
37(c) Prepare Erosion and Sediment Control Plan

Prepare an Erosion and Sediment Control Plan (ESCP) in accordance with best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version) and, to the extent of any inconsistency, relevant Brisbane Planning Scheme Codes and Policies.

Obtain a design certificate in accordance with the relevant Brisbane Planning Scheme Codes and Policies.

The ESCP and design certificate must be certified by a Certified Professional in Erosion and Sediment Control (CPESC) or a Registered Professional Engineer Qld (RPEQ) with suitable qualifications and experience in erosion and sediment control.

Documentary evidence demonstrating appropriate qualifications in erosion and sediment control must be provided to the Council upon request.

Timing: Prior to the commencement of any earth disturbing activities.

 
As indicated
37(d) Attend a pre-start meeting

Arrange and attend a pre-start meeting for Erosion and Sediment Team, Compliance and Regulatory Services (CARS).

All relevant documentation, including the certified erosion and sediment control plan and the certified design certificate must be submitted with the request.

Note: To request a pre-start meeting refer to Council's website and search 'Pre-start meeting'.

- A minimum 10 working days' notice is required.

Timing: Prior to the commencement of any earth disturbing activities.

 
As indicated
37(e) Implement Certified Erosion and Sediment Control Plan

Implement the certified ESCP and maintain all ESC measures in accordance with best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version) and, to the extent of any inconsistency, relevant Brisbane Planning Scheme Codes and Policies.

The ESCP and design certificate must be available on site at all times for inspection by Council officers. Any alteration to supplementary or Type 3 ESC measures must be reflected in the certified ESCP. Any alteration to Type 2 or Type 1 ESC measures will require a revised ESCP and design certificate that has been certified by either the CPESC or RPEQ.

Timing: While earth disturbing activities are occurring and until all exposed soil areas are permanently stabilised against erosion.

 
As indicated
 
38)   Information Signage

Erect an information sign on the subject property in accordance with Council's general requirements for signage and in accordance with the requirements outlined below:
a) The sign should provide a brief description of the development proposed;
b) The sign is to list the name, postal and/or email address and a contact telephone number for the following parties (where relevant) that are undertaking work on the site:
- Developer;
- Project Coordinator;
- Architect/Building Designer;
- Builder;
- Civil Engineer;
- Civil Contractor/s; and
- Landscape Architect;
c) The lettering on the sign is to be at least 25 millimetres in height, be of regular weight and in sentence case;
d) The sign is to be a minimum size of 1,200 millimetres by 900 millimetres;
e) The maximum area of the sign is to be 2.0m2;
f) The sign is to be positioned as follows:
- located centrally along each road frontage of the site to Reginald Street;
- located on or within 1.5 metres of the road frontage;
- mounted at least 300 millimetres above ground level; and
- clearly visible from the street for a pedestrian;
g) The sign is to contain no commercial or corporate advertising other than the name, logo or slogan of the parties outlined in part (b) of this condition;
h) The sign is to be non- illuminated; and
i) Both the sign and the supporting structure are to be made of weatherproof material and to be properly maintained at all times;

Timing: Prior to site works commencing and then to be maintained until completion of the development for all stages.

 
As indicated
 
39)   Construction Management Plan (Minor)

Carry out development in a method consistent with a Construction Management Plan (Minor) prepared in accordance with the requirements of this condition.

 
While site/operational/building work is occurring
39(a) Construction Management Plan (Minor) - Prepare Plan

Prepare a detailed Construction Management Plan (CMP) for the construction phase of the approved development.The Construction Management Plan must be in accordance with the relevant Brisbane Planning Scheme Codes and address the following:
(i) Provision for pedestrian management including acceptable alternative DDA compliant pedestrian routes (adjacent to or surrounding the site);
(ii) Existing and proposed kerbside allocation signs and line marking (such as bus stops, loading zones and parking meters and/or ticket dispensers);
(iii) Location of and impacts to any Council or other public utility or local authority's assets on or within external to the site;
(iv) Location and design of temporary vehicular construction access points, including frequency of use;
(v) Management and mitigation strategies for the impact of dust, noise and vibration upon adjoining and nearby properties;
(vi) Provision for loading and unloading of materials including the location of any remote loading sites;
(vii) Location of materials, structures, plant and equipment to be stored or placed on the construction site;
(viii) Location of proposed external hoardings and/or gantries, and including clearances to the impacts of this on existing street furniture and other footpath assets located within the verge as well as impacts on any existing advertising signage located either along or adjacent to the site frontage - this includes any potential obstruction of sight lines for such advertising (e.g. bus stops with advertising);
(ix) Location of proposed employee and visitor parking areas;
(x) Anticipated staging and programming;
(xi) Impacts of any actions proposed to address any of the above items or any actions resulting from construction of the development that will impact on existing street trees;
(xii) Complaint management processes to be implemented; and
(xiii) Compliance with the Management Plans Planning Scheme Policy and other relevant Planning Scheme Policies.

The Construction Management Plan must be supported by 'approval in principle' or written approvals from the relevant Council sections or other governing bodies responsible for any potentially impacted infrastructure.

The list of relevant infrastructure and contacts is available on Council's website - Search 'Construction Management Plan'.

Note: The Construction Management Plan is not required to be approved by Development Services.

Timing: Prior to site/operational/building work commencing.

 
As indicated
39(b) Construction Management Plan (Minor) - Submit Plan

Submit a copy of the Construction Management Plan to Council's Development Services Branch at the following mailbox: engineeringservices@brisbane.qld.gov.au quoting the BCC planning development approval reference number.

Timing: At least 10 days prior to site works commencing.

 
As indicated
39(c) Construction Management Plan (Minor) - Documentation on Site

Legible copies of the Construction Management Plan and current permits must be kept on site and be made available on request by Council at all times. The requirements of the CMP must be included in all induction of principal and subcontractors utilised in the development. An outline of the induction provided to contractors may be requested by Council to confirm compliance with this condition.

Timing: While site/operational/building work is occurring.

 
As indicated
39(d) Construction Management Plan - Works to be Performed Out of Hours

Obtain an approval from Development Services for any work that is proposed to be undertaken outside of normal business hours - 6:30am to 6:30pm, Monday to Saturday.

Timing: Prior to site/operational/building work commencing.

 
As indicated
39(e) Implement Construction Management Plan (Minor)

Carry out the development in accordance with the submitted Construction Management Plan.

 
While site/operational/building work is occurring
 
40)   Protect Existing Infrastructure

Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure.

Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations.

The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements.

 
While site/operational/building work is occurring
40(a) As Constructed Drawings - Alterations to Existing Infrastructure

Submit to Development Services As Constructed drawings showing all new and/or rectification works and an asset register, prepared by a Registered Professional Engineer Queensland.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

PROOF OF FULFILMENT
Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
41)   Filling and / or Excavation (Minor)

Filling and/or excavation works on the site must be in accordance with the APPROVED PLANS and the relevant Brisbane Planning Scheme Codes.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
41(a) Prepare Earthworks Drawings

Earthworks drawings must be prepared and certified by a Registered Professional Engineer Queensland in accordance with the relevant Brisbane Planning Scheme Codes.

The drawings must include the following:
- The location of any cut and/or fill;
- The quantity of fill to be deposited and finished fill levels;
- The existing and future finished levels in reference to the Australian Height Datum (including cross- sections or long sections into the adjacent properties);
- maintenance of access roads to and from the site such that they remain free of all fill material and are cleaned as necessary
- preservation of all drainage structures from the effects of structural loading generated by the earthworks
- protection of adjoining properties and roads from adverse impacts as a result of proposed works.
- That all vehicles exiting from the site will be cleaned and treated so as to prevent material being tracked or deposited on public roads.

Timing: Prior to site/operational/building work commencing.

Note: The Earthworks drawings are not required to be submitted for Council approval.

 
As indicated
41(b) Implement and Maintain the Earthworks

Carry out and maintain the earthworks in accordance with the certified drawings.

Note: A copy of the certified Earthworks Drawings must be available on-site for inspection by Council Officers during these works.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
42)   Access, Grades, Manoeuvring, Carparks, Signs and Line Marking

Construct and maintain access, parking and manoeuvring for vehicles on site in accordance with the relevant Brisbane Planning Scheme Codes, as indicated on the approved DRAWINGS AND DOCUMENTS, including the following:

i. A pavement of minimum local road standard or equivalent surface material (including associated drainage) to the area on which motor vehicles will be driven and/or parked.

ii. Manoeuvring on site for an Articulated Vehicle and for the loading and unloading of vehicle(s);

iii. Parking on the site for 25 cars, including 1 parking space for people with disabilities and for the loading and unloading of vehicle(s) within the site. There must a minimum number of 25 total number of spaces provided on site.

iv. A minimum of 2.3 metres height clearance to all undercover parking areas, including the entry and access to these areas, and a minimum of 2.5 metres above parking spaces for people with disabilities. The minimum clear height must be measured to the lowest protrusion from the ceiling (e.g. fire sprinklers, services, lighting fixtures, signs, etc).

v. A height clearance sign located at the entrance(s) to undercover car parking areas and a directional visitor parking sign clearly visible from the vehicle entrance to the site.

vi. An appropriate area for the storage and collection of refuse, including recyclables, in a position which is accessible to service vehicles on the site.

vii. Prepare and implement signs and line markings drawings that show the internal paved areas signed and delineated in accordance with the approved drawings and documents. The drawings must be prepared and certified by a Registered Professional Engineer Queensland in accordance with the relevant Brisbane Planning Scheme Codes and the Manual of Uniform Traffic Control Devices.

PROOF OF FULFILMENT
Certification from a Registered Professional Engineer Queensland, that the above requirements have been implemented in accordance with this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
43)   Repair Damage to Kerb, Footpath or Road

Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
43(a) Interim Repairs

If at any time during the construction phase of the approved development, damage to the existing kerb and channel, footpath or roadway creates unsafe, unreasonable and/or not fit for purpose conditions as assessed by Council, interim repairs must be undertaken as directed by Program Planning and Integration.

Note: Any interim repairs required to be undertaken shall not be considered to satisfy the requirements of this condition for the permanent repair of the infrastructure prior to the issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

Timing: While site / operational / building works is occurring.

 
As indicated
 
44)   Flood Emergency Management Plan

Prepare, implement and maintain a Flood Emergency Management Plan (FEMP) in accordance with the requirements of this condition.

Note: Guidance for the preparation of drawings and/or documents to comply with this condition is provided in the Flood Planning Scheme Policies.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
44(a) Prepare and Certify a Flood Emergency Management Plan

Submit to Development Services a Flood Emergency Management Plan (FEMP) for the approved development prepared and certified by a Registered Professional Engineer Queensland with experience in flood risk management.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection.

 
As indicated
 
45)   Minimum Flood Planning Levels

Design and construct all building pad levels, floor levels and ancillary structures to the appropriate flood planning level with freeboard (where required) in accordance with the relevant Brisbane Planning Scheme Codes and the approved drawings and documents.

The minimum floor level must be 8.0 metres AHD.

The minimum level for essential electrical services must be 8.0 metres AHD.

PROOF OF FULFILMENT
As-Constructed drawings prepared by a Registered Surveyor (Qld). The Registered Surveyor (Qld) must certify that the development has been constructed in accordance with this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
46)   Non-Residential Refuse Collection - On Site

Provide for the installation and collection of refuse/recycling bins.

 
At all times
46(a) Arrange Refuse Collection

Arrange for the installation of refuse/recycling bins and for the subsequent collection of refuse including recycling from the site by a private waste contractor or Brisbane City Council's Waste and Resource Recovery Services.

Timing: A minimum of four weeks prior to the commencement of use and then to be maintained.

PROOF OF FULFILMENT
Where a private waste contractor is engaged, provide written confirmation from the proposed waste collection contractor of the agreement to service the property. The written agreement must be submitted to Council's Waste and Resource Recovery Services and include full details of the proposed system, bin sizes, number of bins, frequency of collection and the refuse collection vehicle size. Prior to commencement of use

 
As indicated
46(b) Indemnify Council

Where Council is engaged as the waste contractor, the owner and any subsequent owner must, by approved form to Waste and Resource Recovery Services, indemnify Council and its agents in respect of any damage to the pavement and other driving surfaces.

Timing: When an arrangement for refuse/recycling collection services is made with Brisbane City Council.

 
At all times
46(c) Notify Future Owner

Where Council is engaged as the waste contractor, the owner must notify any future owner/body corporate that the development has been approved on the basis that an indemnity must be provide for refuse collection vehicles to enter the property.

Timing: At time of a change of ownership.

 
At all times
 
47)   Refuse Storage - On Site Collection

Provide a roofed and wholly screened refuse enclosure utilising materials consistent with the development or a dedicated refuse storage room, as shown on the approved plans and documents.

The enclosure/refuse storage room must be of a design to accommodate the quantity of refuse and recycling including source separation to allow for low servicing collection of the development.

Bins must be located in an area which allows them to be manoeuvred from the bin storage area to the designated internal collection point.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
48)   Remove Redundant Drainage Outlets

Remove any redundant drainage outlets from the kerb and channel including any associated pipe work across the footway and reinstate the kerb and channel and the footway area in accordance with the relevant Brisbane Planning Scheme Codes.

Note: Guidance for the preparation of drawings and/or documents to comply with this condition is provided in the Brisbane Planning Scheme Policies.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
49)   Ponding of Stormwater

Carry out the approved development to ensure that adjoining properties and roads are protected from ponding or nuisance from stormwater during construction.

Notes: If remedial works are necessary to comply with this condition, prior approval must be obtained from Development Services.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
50)   On Site Drainage - Minor

Provide a stormwater connection to all new or existing allotments and provide drainage infrastructure to ensure stormwater run-off from all roof and developed surface areas will be collected internally and piped in accordance with the relevant Brisbane Planning Scheme Codes to 'a lawful point of discharge' being the existing drainage in the Ipswich Road Service Road.

Note:
- Guidance for the preparation of drawings and/or documents to comply with this condition is provided in the Brisbane Planning Scheme Policies.
- Queensland Building and Construction Commission licensed hydraulic consultants may design the stormwater system for sites less than 2000m2 with an upstream catchment servicing no more than 4 residential lots. This excludes stormwater drainage design (including subsoil drainage) of basements in flood planning areas and the design of any onsite stormwater detention system
- Where external works are required and infrastructure will be handed over to Council (e.g. Stormwater pipes 375mm or greater and/or manholes within the road reserve, etc), the applicant will be required to request a Pre-Start with Council and ensure all future owned Council assets follow the On/Off Maintenance process in accordance with Council's Infrastructure Installation & Construction Requirements Manual.

- Guidance for requesting a pre-start and co-ordinating the On/Off Maintenance process can be found on Council's website (https://www.brisbane.qld.gov.au/planning-and-building/applying-and-post- approval/on-and-off-maintenance-approvals).

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
51)   Service Conduits and Mains

Provide and install all service conduits and meet the cost of any alterations to public utility mains, existing mains, services, street lighting or installations that are required to carry out the approved development. These works must be in accordance with the relevant Brisbane Planning Scheme Codes, and include the following, where applicable:
- the provision of all services and/or conduits along the full length of any rear allotment access or access easement.
- the breaking and/or relocation of any existing sewer combine drains.
- the relocation of any fire hydrant and/or valves from the development's vehicular footway crossings.
- the retention and/or relocation of any existing foul water lines that currently exist within the site.
- any new or existing installations of electrical pillar boxes, pad mounted transformers (PMTs), water reticulation mains, water meters and the like, must be installed/relocated to their ultimate alignment relative to the new property boundary and clear of the usable footpath areas irrespective of the alignment of the existing services/conduits.

Note:
- The cost of moving services, utilities and assets is the responsibility of the Developer. The permission of the service, utility or asset owner will be required. Council permission is required if street trees, stormwater gullies/drains, and swales are affected. Urban Utilities permission is required if water supply and sewerage services are affected.
- Standard utility alignments may be found on Council's 'Brisbane Standard Drawings' 1013 to 1016 inclusive.
- Applicants must liaise with the appropriate service authorities. Typical underground services and/or conduits to be constructed include power, phone, telecommunications, sewer (including private combine drains) stormwater and gas, if applicable.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
51(a) Submit As Constructed Drawings

Submit to Development Services As Constructed drawings, including an asset register, prepared and certified by a Registered Professional Engineer Queensland.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

PROOF OF FULFILMENT
Certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the requirements of this condition. Note: Civil works are to be certified by a RPEQ(Civil) and electrical works are to be certified by a RPEQ (Electrical).

 
As indicated
 
52)   Telecommunications

Submit to Development Services, certification from an authorised telecommunications carrier/contractor, that the following works and infrastructure have been undertaken and installed in accordance with telecommunications industry standards:
- Provide telecommunications to the subject buildings, lead-in conduits and equipment space in a suitable location within the buildings, to suit the carrier of choice.
- If new pits and conduit infrastructure are required to be installed within the road reserve fronting the site, it must be suitably sized to cater for future installation of fibre optic cables.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
53)   Agreement with Electricity Supplier

Submit to Development Services, evidence of an agreement with an electricity supplier to provide necessary services to the development in accordance with the relevant Brisbane Planning Scheme Codes.

Where development is within an established area of overhead electricity supply and the electricity supplier determines that a property pole is the appropriate solution to supply electricity to the development, the developer must be responsible for the installation of the property pole(s).

In the above circumstances, submit to Development Services, certification from the developer's electrical consultant confirming that the above installation has been completed in accordance with the relevant AS/NZS Standards and the Queensland Electricity Connection Manual (QECM) and Queensland Electricity Metering Manual (QEMM).

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
54)   Water and Wastewater

Pursuant to Schedule 18 of the Planning Regulation 2017 submit to Development Services, documentary evidence, issued by the relevant distributor-retailer, to verify that the conditions of any necessary connection certificate under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009, have been complied with.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
Standard Advice
 
Timing
55)   Construction Noise and Dust Emissions

Pursuant to the Environmental Protection Act 1994, all development involving the emission of noise and dust from building and/or construction activities, must ensure that the emissions are in accordance with the requirements of the Act.
The Environmental Protection Act 1994 prescribes that:

1. A person must not carry out building work in a way that makes an audible noise-
-  on a business day or Saturday, before 6.30a.m. or after 6.30p.m; or
-   on any other day, at any time. 
2. The reference in subsection (1) to a person carrying out building work-
-  includes a person carrying out building work under an owner-builder permit; and
-  otherwise does not include a person carrying out building work at premises used by the person only for residential purposes.

Note: A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management delegate Development Services.

 
As indicated
 
56)   Further Development Permit Required

Further Development Permit(s) to carry out assessable building work under the Building Act may be required.

 
As indicated
 
57)   Plumbing and Drainage Work

Pursuant to the Plumbing and Drainage Act 2018, any plumbing and drainage work must be carried out in compliance with the Plumbing and Drainage Regulation 2019.

Note: All new and existing plumbing services should be located within the lot that they serve.

Compliance assessable plumbing and drainage work requires approval by Brisbane City Council prior to the work being carried out.

 
As indicated
 
58)   Currency Period

The currency period for this development approval is stated in the Decision Notice and is expressed as a date.

This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016.

 
As indicated
 
59)   Referral Agency Requirements

State Assessment and Referral Agency (SARA) as referral agency has imposed the requirements contained in the letter dated 8 August 2024 (SARA reference: 2306-35319 SRA).

 
As indicated
 
60)   Damage to Trees on Adjoining Land

Please note that any damage caused to vegetation on adjoining land as a result of exercising this development approval may result in an offence under other legislation (e.g. Natural Assets Local Law) and/or civil action

 
As indicated
 
61)   Fire Ant Movement Controls

To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected.

These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products.

Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014.

For further information contact the relevant Queensland State Government department on 13 QGOV.

 
As indicated
 
62)   Water and Wastewater

Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009.

For further information about any necessary Water Approvals contact Urban Utilities.

 
As indicated
 
63)   Flood Resilience and Awareness

This advice is provided for buildings that are on sites that are subject to the flood overlay, as shown within City Plan 2014.

Council makes decisions to minimise flood risk based on the best information available at the time of the development application. Flood studies and applicable flood levels may be updated by Council overtime where new flood information is available or changes to engineering standards/methodology have occurred. Flood levels for various flood events and flooding types are outlined in Council's Floodwise Property Reports available from Councils website.

The minimum flood planning levels that apply to new development do not necessarily mean that the development will never flood. Therefore, when choosing materials for building on sites that are known to be affected by flooding, regardless of whether it is constructed to the minimum flood planning level, it is recommended that flood resilient materials are used to improve the speed of recovery and reduce the cost of repairs if required.

For more information refer to:

Council's website at https://www.brisbane.qld.gov.au/community-and-safety/community- safety/disasters-and-emergencies/be-prepared/flooding-in-brisbane/flooding- support-for-residents/flood-resilient-homes-program

Queensland Reconstruction Authority "Flood Resilient Building Guidance for Queensland Homes"https://www.qra.qld.gov.au/resilient- homes/flood-resilient-building-guidance-queensland-homes

 
As indicated
 
64)   Cultural Heritage

Aboriginal cultural heritage is protected under the Aboriginal Cultural Heritage Act 2003. This Act establishes a cultural heritage duty of care and in section 23(1) mandates that a person who carries out an activity must take all reasonable and practicable measures for ensuring activities are managed to avoid or minimise harm to Aboriginal cultural heritage.

 

The Duty of Care Guidelines gazetted pursuant to the Aboriginal Cultural Heritage Act 2003 provide guidance on identifying and protecting Aboriginal cultural heritage to fulfil the duty of care.

 

For further information contact the relevant Queensland State Government Department (Department of Aboriginal and Torres Strait Islander Partnerships).

 
As indicated
 



Permit to Which These Conditions Relate: DA - PA - Referral Agency for Building Work
Activity(ies): Flood hazard area
Stage: Early Referral Agency Response for Flood Hazard Area

Standard Advice
 
Timing
65)   Early Referral Agency Response (Flood hazard area)

Council has chosen to issue an early referral agency response under section 57 of the Planning Act 2016 for the proposed building work located within a Flood hazard area (Planning Regulation 2017, Schedule 9, Part 3, Division 2, Table 12). The response is attached to this decision notice.

 
As indicated
 

** End of Package **