| Address of Site: | 149 ROGHAN RD TAIGUM QLD 4018 |
| Real Property Description of Site: | L11 RP.78605 |
| Aspects of development and type of approval: | DA - PA - Reconfiguring a Lot Development Permit - Subdivision of
Land,Access Easement |
| Council File Reference: | A006894684 Permit Reference Number/s: DARL469848825. |
| Package Status: | APPROVED - Version 1 (29th of May, 2026 12:50:23 PM) |
| Package Generated: | 29/05/2026 |
| Ben COVE Principal Engineer Engineering Services Traffic Ben.Cove@brisbane.qld.gov.au |
Michael CHOU Network Planning Michael.Chou@brisbane.qld.gov.au |
John GRIMSEY Built Environment Officer WaRRS Assessment john.grimsey@brisbane.qld.gov.au 34071331 |
| Biraj DANGOLE Principal Engineering Officer Engineering Services North Biraj.Dangole@brisbane.qld.gov.au (07) 3178 2607 |
Craig SLACK Engineer Engineering Scoping craig.slack@brisbane.qld.gov.au (07) 3403 8888 |
Tahlie PAGE Ecologist Ecology Services Tahlie.Page@brisbane.qld.gov.au 0731785966 |
| Justin LEE Principal Engineer Engineering Services North Justin.Lee@brisbane.qld.gov.au 34038888 |
Lucy TING Senior Engineer Engineering Services Hydraulics lucy.ting@brisbane.qld.gov.au (07) 3403 5005 |
JOANNE LOVE-SLOMAN Landscape Architect Landscape Architecture Team joanne.lovesloman@brisbane.qld.gov.au (07) 3403 8888 |
| Chris.M DIXON Senior Urban Planner Planning Services North chris.m.dixon@brisbane.qld.gov.au 31787264 |
MAISIE TANG Principal Urban Planner Planning Services North maisie.tang@brisbane.qld.gov.au (07) 31789048 |
DRAWINGS AND DOCUMENTS
| Drawing or Document | Number | Plan Date |
|---|---|---|
| Engineering Concept - Services Layout Plan | CS01 Issue B (Amended In Red 27-APR-2026) | 30-JAN-2026 |
| Engineering Concept - Functional Traffic Layout Sheet 1 of 2 | CT01 Issue C (Amended In Red 27-APR-2026) | 12-MAR-2026 |
| Engineering Concept - Earthworks Layout Plan | CE01 Issue C (Amended In Red 27-APR-2026) | 12-MAR-2026 |
| Engineering Concept - Earthworks Sections | CE03 Issue C | 12-MAR-2026 |
| Tree Retention Plan | TR02 Issue C (Amended In Red 26-FEB-2026) | 02-FEB-2026 |
| Tree Retention Plan | TR03 Issue C (Amended In Red 26-FEB-2026) | 02-FEB-2026 |
| Tree Retention Plan Schedule | TR04 Issue C (Amended In Red 26-FEB-2026) | 02-FEB-2026 |
| Rehabilitation Concept | B4002L A1_DA3 [A] (Amended In Red 26-FEB-2026) | 24-OCT-2025 |
| Reconfiguration Plan | R1 Issue E (Amended In Red 27-APR-2026) | 29-JAN-2026 |
| Building Envelope Plan | B4002PA1_DA3 B1 Issue C (Amended In Red 27-APR-2026) | 29-JAN-2026 |
APPROVAL CONDITIONS
| Permit to Which These Conditions Relate: | DA - PA - Reconfiguring a Lot |
| Activity(ies): | Subdivision of Land Access Easement |
| Stage: | Reconfiguration of a Lot (1 into 12 lots), new road and access easement |
| 1) Building Envelope Plan Notify all prospective purchasers of the site(s) that a 'Building Envelope Plan' has been approved over lot/s 1 – 7 and lot/s 10 –12 and that a ‘Development Footprint Plan’ has been approved over lot/s 8 & 9 in accordance with the approved Building Envelope Plan, drawing no. B4002PA1_DA3 B1 Issue C, dated 29 January 2026 and received 6 February 2026 (amended in red 27 April 2026). |
As indicated |
| 2) Maintain the Approved Development Maintain the approved development generally in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions. |
At all times |
| 3) Approved Drawings and Documents A legible copy of the Council approved
DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained
on site and kept available for inspection by site workers and Council
officers. |
While site/operational/building work is occurring |
| 4) Carry Out the Approved Development Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS. Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners. |
While site/operational/building work is occurring |
| 5) Complete All Operational Work Complete all operational work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such operational work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS or, if requiring a further approval from the Council, in accordance with the relevant further approval(s). |
Prior to Council's notation on the plan of subdivision and then to be maintained |
| 6) Register Plan of Subdivision The plan of subdivision shall not be notated by Council until the plan of subdivision of the development approval (ref: A006216521, and any subsequent change applications), has been registered with the Registrar of Titles for the relevant Queensland State Government Authority. |
As indicated |
| 7) Development Footprint Plan The 'Development Footprint' is restricted to the areas within the approved Development Footprint Plan shown on the approved Building Envelope Plan (Drawing no: B4002PA1_DA3 B1 Issue C, dated 29 January 2026 and received 6 February 2026) (amended in red 27 April 2026). The following requirements must be met and maintained to support the Development Footprint Plan. |
At all times |
7(a) Development Footprint Plan Set
Out A Registered Surveyor (Qld) must survey and peg the approved Development Footprint Plan. Timing: Prior to site/operational works commencing and to be maintained. |
As indicated |
7(b) Vegetation Retention Retain and protect all existing vegetation outside of the approved Development Footprint Plan/s. Timing: While site/operational work is occurring and then to be maintained. |
As indicated |
7(c) No Development Outside DFP No part of any building or structure (including but not limited to swimming pools, tennis courts, retaining walls, tanks), no facilities associated with the development, no open space, no recreation areas, no landscaping, no on-site stormwater drainage, no on-site wastewater treatment, no areas of disturbance (including excavation and filling), no storage/stockpiles of materials, no on-site parking, no access and no manoeuvring areas must be located on any part of the site outside the approved Development Footprint Plan whether for temporary, short-term or long- term periods unless in accordance with this approval or subsequent approvals. Timing: At all times. |
As indicated |
7(d) Notification to Prospective
Purchasers Provide written notification of the requirements and effects of this condition to all prospective purchasers. Retain a copy of this notification at the property and make it available to view upon request of any Council officer. Timing: At the time of marketing a lot for sale. |
As indicated |
| 8) Environmental Offset Delivery (Ecology) Provide an environmental offset for the loss of land of local environmental significance identified in Brisbane City Plan 2014. The offset must be based on the loss of the area of MLES3 as determined by a Vegetation Management Plan submitted and approved in accordance with the Vegetation Management Plan condition of this approval. The offset must be delivered in accordance with the provisions of the Environmental Offsets Act 2014 and Offsets Planning Scheme Policy. Note: Vegetation may only be removed in accordance with the Vegetation Management Plan approved pursuant to the Vegetation Management Plan condition of this approval. Note: The deemed conditions in sections 19B, 22, 24 and 25 of the Environmental Offsets Act 2014 are also imposed on this approval. Timing: Prior to any vegetation removal commencing. |
As indicated |
| 9) Fauna Management - Fauna Spotter Catcher Engage a licensed Fauna Spotter Catcher (qualified by the relevant Queensland State Government Authority) to manage the protection and relocation of any fauna prior to and during vegetation/ecological feature clearing. |
While site/operational/building work is occurring |
9(a) Prior to Vegetation/ Ecological Feature
Clearing Submit to Development Services certification from the licensed Fauna Spotter Catcher that the site has been fully inspected and any necessary fauna protection measures or relocation procedures have been implemented. Certification must include: Certification is to be provided via the Compliance with Development Conditions online form, available on Council's website, including the following details: Site address, Development Approval number (A00), and relevant stage/s (if appropriate). Timing: Prior to vegetation/ ecological feature clearing commencing. |
As indicated |
9(b) During Vegetation/ Ecological Feature
Clearing The licensed Fauna Spotter Catcher must be present on site during all clearing operations to monitor works and to respond to any fauna situations that may arise. If any fauna is identified in vegetation or ecological features to be removed during clearing operations, work must cease immediately on that vegetation or ecological feature. The licensed Fauna Spotter Catcher must supervise the relocation of any identified fauna prior to vegetation/ ecological feature clearing recommencing. Timing: While vegetation/ecological feature clearing is occurring. |
As indicated |
9(c) Submit Certification Submit to Development Services certification from the licensed Fauna Spotter Catcher that vegetation/ecological feature clearing was carried out in accordance with this condition. Certification must include: Certification is to be provided via the Compliance with Development Conditions online form, available on Council's website, including the following details: Site address, Development Approval number (A00), and relevant stage/s (if appropriate). Timing: Prior to Council's notation of the plan of subdivision. |
As indicated |
| 10) Vegetation Management (Submit Plan) Manage vegetation on the site in accordance with a Vegetation Management Plan approved pursuant to this condition. |
While site/operational/building work is occurring and then to be maintained |
10(a) Submit Vegetation Management
Plan Submit and obtain approval for a Vegetation Management Plan from Development Services. This plan must be prepared by a suitably qualified and experienced environmental practitioner (minimum 5 years' experience), with supporting documentation from the Project Arborist (minimum AQF Level 5 in Arboriculture with a minimum of 5 years' experience in arboricultural principles and practices, including tree risk hazard assessment and reporting with current public liability insurance to $20 million, and a professional indemnity of $2 million), where works are required within the Tree Protection Zone (TPZ) of retained trees. The Vegetation Management Plan must be in the form of scaled plans and supporting documentation that are generally in accordance with the approved Tree Retention Plan (Drawing no: TR02 Issue C, dated 02/02/2026, received 06/02/2026 and amended in red 26/02/2026), relevant Brisbane Planning Scheme Code and include the following: - The extent of the Vegetation Management Plan must include evaluation of all areas including road reserves, external works and development areas. - The location and description of existing vegetation including species, botanical name, height, invasive pest plant status, canopy spread and Tree Protection Zones (as per AS 4970-2009) of canopy trees, as well as a description of vegetation communities and species compositions for ground, shrub and subcanopy layers. Any species or vegetation communities of State / National significance to be clearly identified. - The location and extent of all site works including all infrastructure and areas of earthworks. - Detailed design of all civil works including required changes to protect vegetation (e.g. alternative service alignments, variations to batter slopes and tunnel boring). - The location and description of all vegetation to be retained or to be removed. - Methods of physical identification of trees/vegetation to be retained or to be removed. - A description of all measures to protect vegetation and habitat features to be retained during construction, including protective fencing (as per AS 4970-2009), site protocols, etc. - An assessment of hollows in vegetation being removed. Where vegetation removal results in loss of any tree hollows, provision of one (1) equivalently sized compensatory nestbox is to be installed in the Environmental Protection Zone. The assessment is to detail the number, type and current species usage of hollows being removed, proposed nestbox types and locations, installation requirements, and monitoring and maintenance schedule. Note: nestboxes must be installed prior to pre-start meeting for inspection. - A description of all pruning and tree surgery works (to AS 4373-2007) to maintain the health and stability of trees and reduce potential hazards for future site users (e.g. residents and workers). - The location and extent of storage and stockpile areas for cleared vegetation and site mulch. - A description of all methods to salvage and/or re-use cleared vegetation. Generally, cleared vegetation must be mulched for reuse in landscape/rehabilitation works - Details of all measures to protect and recover fauna during clearing operations, including; presence of a qualified fauna spotter catcher during clearing operations, pre-clearing inspections, staging and sequence of clearing and recovery procedures. - Ongoing monitoring and certification requirements (e.g. Project Arborist and/or Fauna Spotter Catcher, nestboxes). Timing: Prior to site/operational commencing and prior to or concurrently with any other operational works application. |
As indicated |
10(b) Project Arborist Appoint as Project Arborist, a qualified Arborist (minimum AQF Level 5 in Arboriculture with a minimum of 5 years' experience in arboricultural principles and practices, including tree risk hazard assessment and reporting with current public liability insurance to $20 million, and a professional indemnity of $2 million). Provide evidence of this appointment to the Ecologist Development Services via the Compliance with Development Conditions online form, available on Council's website. Details to be provided: Site address, Development Approval number (A00), and relevant stage/s (if appropriate). Timing: Prior to arranging a pre- start meeting. |
As indicated |
10(c) Pre-Start Meeting Arrange and attend a pre-start meeting with Ecology Services, Development Services. Council will only attend the pre-start meeting once all vegetation protection measures are in place (e.g. Tree protection fencing). The Project Manager, Site Manager, Project Arborist and a qualified Fauna Spotter Catcher must attend the pre-start meeting. Council will only attend the pre-start meeting once all applicable compliance and inspection fees have been paid. Note: To request a pre-start meeting refer to Council's website and search 'Pre-start meeting'. Timing: Prior to site / operational / building work commencing. |
As indicated |
10(d) Implement Approved Vegetation
Management Plan Carry out the works in accordance with the approved Vegetation Management Plan. NOTE: The Project Arborist must: - Direct and supervise all contractors in relation
to any works within the Tree Protection Zone (as per AS4970-2009) of retained
trees and use of alternative technologies (e.g. vacuum excavation) or alternate
alignments. Timing: While site/operational work is occurring. |
As indicated |
10(e) Submit Certification Submit to Development Services, certification from the qualified and experienced environmental practitioner and the Project Arborist (minimum AQF Level 5 in Arboriculture with a minimum of 5 years' experience in arboricultural principles and practices, including tree risk hazard assessment and reporting with current public liability insurance to $20 million, and a professional indemnity of $2 million.), certifying that the work(s) have been carried out in accordance with the approved Vegetation Management Plan. Certification must include: - Inspection log of
works; Certification is to be provided via the Compliance with Development Conditions online form, available on Council's website. Details to be provided: Site address, Development Approval number (A00), and relevant stage/s (if appropriate). Timing: Upon completion of each phase of the approved Vegetation Management Plan and prior to Council's notation of the plan of subdivision. |
While site/operational/building work is occurring and then to be maintained |
10(f) Retain and Protect
Vegetation Retain and protect vegetation in accordance with the approved Vegetation Management Plan. Timing: To be maintained. |
While site/operational/building work is occurring and then to be maintained |
| 11) Environmental Protection Zone Retain, protect and maintain all ecological values within the approved Environmental Protection Zone shown on the approved Rehabilitation Concept (Drawing no: B4002L A1_DA3 (A), dated 24/10/2025, received 31/10/2025 and amended in red 26/02/2026). The following requirements must be met and maintained to support the approved Environmental Protection Zone. |
While site/operational/building work is occurring and then to be maintained |
11(a) Restrictions within an approved
EPZ No part of any building or structure (including but not limited to swimming pools, tennis courts, retaining walls, tanks), no facilities associated with the development, no open space, no recreation areas, no landscaping, no on-site stormwater drainage, no on-site wastewater treatment, no areas of disturbance (including excavation and filling), no storage/stockpiles of materials, no on-site parking, no vehicle access and no manoeuvring areas and no bushfire management measures must be located on any part of the site within the approved Environmental Protection Zone whether for temporary, short-term or long-term periods unless approved in this Development Approval or subsequent approvals from Council. Timing: To be maintained. |
As indicated |
11(b) EPZ Set Out A Registered Surveyor (Qld) must survey and peg the approved Environmental Protection Zone. Timing: Prior to Council's notation of the plan of subdivision. |
As indicated |
11(c) Fences Any fences erected within or to the perimeter of the Environmental Protection Zone, excluding the interface with the development footprint, must be constructed to allow the free movement of native fauna. Fencing is to be no greater than 1.2m in height, minimum gap of 40cm between ground and first rail and minimum gap between every other rail of 30cm, or otherwise shown in accordance with an approved Rehabilitation Plan. Note: For further information, refer to the Brisbane City Plan 2014 supporting information Wildlife movement fencing guidelines on Council's website. Timing: To be maintained. |
As indicated |
11(d) Pet Exclusion Fencing Permanent fences must be erected to contain pets at the interface between Lots 8 and 9 and the Environmental Protection Zone, as shown on approved plans or approved rehabilitation plan. Pet exclusion fencing must be continuous with no gaps greater than 50mm and be a minimum of 1.5m in height or otherwise shown in accordance with an approved Rehabilitation Plan. Self-closing pedestrian gate is permitted to the Environmental Protection Zone for maintenance access. Note: For further information, refer to the Brisbane City Plan 2014 supporting information Wildlife movement fencing guidelines on Council's website. Timing: Prior to Council's notation of the plan of subdivision and to be maintained. |
As indicated |
11(e) Notification to Prospective
Purchasers Notify all prospective purchasers of the site(s) of the requirements and effects of this condition. Timing: At the time of marketing a lot for sale. |
As indicated |
| 12) Statutory Environmental Covenant Enter an environmental covenant with Brisbane City Council pursuant to Section 97A of the Land Title Act 1994 to ensure the appropriate management of the identified ecological values within the Environmental Protection Zone identified on the approved Rehabilitation Concept (Drawing no: B4002L A1_DA3 (A), dated 24/10/2025, received 31/10/2025 and amended in red 26/02/2026). |
Prior to Council's notation on the plan of subdivision |
12(a) Submit Plan of Survey Submit to Development Services, and obtain approval for, a plan of survey showing the land to be covered by the covenant to demonstrate compliance with the requirements of this condition. Timing: Prior to submission of the request pursuant to Schedule 18 of the Planning Regulation 2017 for Council's notation of the plan of subdivision necessary to give effect to this approval. |
As indicated |
12(b) Request Preparation of
Covenant Submit a request for Council to prepare the necessary covenant documentation to demonstrate compliance with the requirements of this condition. The covenant must detail the responsibilities, liabilities, measures, remedies and intents as necessary to ensure the management of the identified vegetation and ecological features on the land and must address the following: 1. Maintenance of vegetation and
ecological features including: 2. Exclusion from the covenant area of all buildings and structures (including swimming pools, tennis courts, retaining walls), open space, all associated facilities, landscaping, on-site stormwater infrastructure, on-site wastewater treatment, all areas of disturbance (including excavation and filling), on-site parking, vehicle access and manoeuvring areas, unless otherwise specified in this development approval or subsequent approvals from Council. Note: Covenants to be entered into with the Brisbane City Council must have the necessary covenant documentation prepared by the Brisbane City Council, free of cost to Council. Timing: Prior to submission of the request pursuant to Schedule 18 of the Planning Regulation 2017 for Council's notation on the plan of subdivision necessary to give effect to this approval. |
As indicated |
12(c) Lodge Notated Plan and
Covenant Lodge the plan of survey notated by Council and the necessary covenant documentation prepared by Council with the Registrar of Titles for the relevant Queensland State Government Authority. Timing: Prior to Council's notation of the plan of subdivision. |
As indicated |
12(d) Submit Evidence of
Registration Submit to Development Services evidence of the registration of the plan of survey and the necessary covenant documentation prepared by Council. Timing: Within one month of the registration of the covenant. |
As indicated |
12(e) Maintain Covenant Retain, protect and maintain the environmental covenant in accordance with the terms and conditions of the covenant. Timing: At all times. |
As indicated |
| 13) Rehabilitation (Submit Plan) Rehabilitate the site in accordance with a Rehabilitation Plan approved pursuant to this condition. |
Prior to Council's notation on the plan of subdivision and then to be maintained |
13(a) Submit Rehabilitation
Plan Submit and obtain approval for a Rehabilitation Plan from Development Services. The plan must be prepared by a suitably qualified and experienced environmental practitioner (minimum 5 years' experience). The Rehabilitation Plan must be in the form of scaled drawings and supporting documentation that are generally in accordance with the approved Rehabilitation Concept (Drawing no: B4002L A1_DA3 (A), dated 24/10/2025, received 31/10/2025, amended in red 26/02/2026) and includes the following information for the area identified for rehabilitation (Environmental Protection Zone): Existing Site conditions: Site Preparation: New Works: Maintenance and Costing: Timing: Prior to site/operational works commencing. |
As indicated |
13(b) Implement Approved Rehabilitation
Plan Carry out the rehabilitation works in accordance with the approved Rehabilitation Plan. Timing: Prior to Council's notation of the plan of subdivision, and then to be maintained. |
As indicated |
13(c) Submit Implement
Certification Submit to Development Services, certification from a suitably qualified and experienced environmental practitioner (minimum 5 years' experience), that the rehabilitation works have been carried out in accordance with the approved Rehabilitation Plan. Certification all approved work/s
have been successfully implemented including: Photo monitoring of rehabilitation area (photos facing north, south, east and west at each photo-point) is to be provided with certification. Certification must be submitted via the Compliance with Development Conditions online form, available on Council's website. Include the following details: Site address, Development Approval number (A00), and relevant stage/s (if appropriate). Timing: Prior to Council's notation of the plan of subdivision. |
As indicated |
13(d) Submit Final
Certification Submit to Development Services, certification from a suitably qualified and experienced environmental practitioner (minimum 5 years' experience), certifying that the rehabilitation maintenance works have been carried out in accordance with the approved Rehabilitation Plan and are now complete. Certification all approved work/s have been successfully completed including: - Planting densities
and species are achieved; Photo monitoring of rehabilitation area (photos facing north, south, east and west at each photo-point) is to be provided with certification. Certification is to be submitted via the Compliance with Development Conditions online form, available on Council's website. Include the following details: Site address, Development Approval number (A00), and relevant stage/s (if appropriate). Timing: At completion of maintenance period. |
As indicated |
| 14) Retain and Protect Existing Street Tree(s) Identify, retain and
protect the existing street trees including the roots unless otherwise agreed
in writing with Public Space Operations Arboriculture Planning Team (PSO-Arb
PLANNING).
PROOF OF FULFILMENT Contextual photographic evidence that the tree(s) have been retained in equal or greater health than before development commenced. OR, evidence in writing from Public Space Operations Arboriculture Planning Team that an alternative arrangement has been made. |
At all times |
14(a) Implement Protection
Measures Install tree protection measures in accordance with Australian Standard
- AS4970 - 2025 Protection of trees on development sites. |
As indicated |
14(b) Maintain Protection
Measures Maintain protection measures while development is occurring and remove protection measures prior to commencement of the use. Timing: While to site/operational work is occurring. PROOF OF FULFILMENT Contextual photographic evidence to demonstrate the installation of protection measures prior to building works commencing. |
As indicated |
| 15) Streetscape Works - Neighbourhood Street
Minor Carry out streetscape improvement works including concrete path and turf to the Roghan Road verge to a Neighbourhood Street Minor standard in accordance with the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD), the requirements of this condition and the Infrastructure Design Planning Scheme Policy including sections 3.7.4.4 and 3.7.5. |
Prior to Council's notation on the plan of subdivision |
15(a) Concrete Path Install a 1.2m wide broom finished standard Portland grey concrete path. The new concrete path is to match the existing new constructed path (and
alignment) immediately west of the development site.
If the above requirements cannot be achieved regarding the placement of the concrete path, contact the Landscape Architecture Team via email: specialistservices@brisbane.qld.gov.au
PROOF
OF FULFILMENT Photographic evidence of concrete path. |
As indicated |
15(b) Submit As Constructed
Drawings Submit to Development Services As Constructed plans including an asset register, checked by a Registered Professional Engineer Queensland, certifying that the concrete path works have been completed in accordance with relevant Brisbane Planning Scheme Codes/Policies. Timing: Prior to Council's notation on the plan of subdivision. PROOF OF FULFILMENT Certificate of completion, Asset register and As constructed drawings signed by an RPEQ. |
As indicated |
15(c) Turf Install turf to the full width of the verge excluding any concrete path required by this condition. Timing: Prior to Council's notation on the plan of subdivision. PROOF OF
FULFILMENT Photographic evidence of installed turf. |
As indicated |
15(d) Street Tree(s) Enter into and
implement an arrangement with the Public Space Operations Arboriculture
Planning Team (PSO-Arb PLANNING) in relation to the required provision of the
street tree planting in accordance with the Infrastructure Design Planning
Scheme Policy, including the number, species, location, installation and
maintenance of the required street tree(s) as determined by PSO-Arb PLANNING.
PROOF OF FULFILMENT Submit to Development Services, a copy of the agreement with Public Space Operations Arboriculture Planning Team (PSO-Arb PLANNING). |
As indicated |
| 16) Grant Easements Grant the following easements in accordance with the approved Engineering Concept – Services Layout Plan CS01 Issue B (received 31/03/2026 and amended in red 27/04/2026): (i) Underground Drainage easement over the alignment of
inter-allotment drainage over Lot 8 in favour of Lot 6 and Lot 7.
(ii) Underground Drainage easement
over the alignment of inter-allotment drainage over Lot 9 in favour of Lot 6,
Lot 7, and Lot 8. (ii)
Easement in gross over Lot 9 in favour of Brisbane City Council and its
agents; (iii) Easement for the purpose of access, construction and maintenance of utility services over Lot 9 in favour of Lot 8. (iv) Easements for access purposes over Lot 9 in favour of Lot 8 as indicated on the approved DRAWINGS AND DOCUMENTS. Timing: As part of the plan of subdivision notated by Council, and then to be maintained. |
As indicated |
16(a) Submit Plan of Subdivision and
Documentation (Council Easement in Gross) Submit to, and obtain approval from, Development Services a plan of subdivision showing the easement and a request for Council to prepare the necessary easement documentation to demonstrate compliance with the requirements of this condition. Note: Easements in favour of the Brisbane City Council must have the necessary easement documentation prepared by the Brisbane City Council, free of cost to Council. Timing: Prior to submission of the request pursuant to Schedule 18 of the Planning Regulation 2017 for Council's notation on the plan of subdivision necessary to comply with this condition or give effect to this approval. |
As indicated |
16(b) Submit Plan of Subdivision and
Documentation (other Easement) Submit to, and obtain approval from, Development Services, a plan of subdivision showing the easement and the necessary easement documentation to demonstrate compliance with the requirements of this condition. Note: Easements not in favour of the Brisbane City Council must have the necessary documentation prepared by the applicant's private solicitors. Timing: As part of the submission of the request pursuant to Schedule 18 of the Planning Regulation 2017 for Council's notation on the plan of subdivision necessary to comply with this condition or give effect to this approval. |
As indicated |
16(c) Lodge Notated Plan and
Documentation Lodge the plan of subdivision notated by Council pursuant to Schedule 18 of the Planning Regulation 2017 and the necessary easement documentation with the Registrar of Titles for the relevant Queensland State Government Authority. Timing: As part of the registration of the plan of subdivision notated by Council. PROOF OF FULFILMENT Evidence of the registration of the necessary easement documentation. Timing: Within one month of the registration of the easement documentation. |
As indicated |
| 17) On-site Erosion (Medium Risk) Manage on-site erosion and the release of sediment or sediment laden water from the site at all times by implementing best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version). Timing: Prior to commencement of any land disturbing activities and until all exposed soil areas are permanently stabilised against erosion |
As indicated |
17(a) Manage earth disturbance on-
site (i) Drainage control measures must be implemented and maintained to minimise water flow onto areas of exposed earth. (ii) Sediment and erosion control measures must be implemented and maintained to prevent soil loss from earth disturbance areas and prevent deposition beyond earth disturbance areas. (iii) No release of
contaminants to land beyond on-site area of earth disturbance other than
releases that achieve water pollutant concentration release limits of: (iv) Maintain a written record to demonstrate that water discharges from the site, including any dewatering operations, meet the release limits as detailed in (iii) for water discharge(s) from the site that occur during or immediately after a rainfall event, and during normal business hours. The water quality of the discharge flows must be measured at each discharge point from the site, including but not limited to sediment basin outlets, other applicable sediment control devices, the site water drainage system, and recorded against the release limits at least once on each calendar day until such discharge stops. Timing: Prior to commencement of any earth disturbing activities and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
17(b) Provide Land Occupier Notification to
Council (i) Notify Council's ESC Team of proposed land occupier/s by sending an email to CARS-ESC@Brisbane.qld.gov.au (ii) If the land is to be occupied by any person other than the registered landowner then advice must be provided to Council that confirms the name, contact information and the duration of any proposed occupation of the land. Timing: Prior to commencement of any earth disturbing activities. |
As indicated |
17(c) Prepare Erosion and Sediment Control
Plan Prepare an Erosion and Sediment Control Plan (ESCP) in accordance with best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version) and, to the extent of any inconsistency, relevant Brisbane Planning Scheme Codes and Policies. Obtain a design certificate in accordance with the relevant Brisbane Planning Scheme Codes and Policies. The ESCP and design certificate must be certified by a Certified Professional in Erosion and Sediment Control (CPESC) or a Registered Professional Engineer Qld (RPEQ) with suitable qualifications and experience in erosion and sediment control. Documentary evidence demonstrating appropriate qualifications in erosion and sediment control must be provided to the Council upon request. Timing: Prior to the commencement of any earth disturbing activities. |
As indicated |
17(d) Attend a pre-start
meeting Arrange and attend a pre-start meeting for ESC with an Officer from Councils ESC Team in Compliance and Regulatory Services (CARS). Note: To request a pre-start meeting from Council's ESC Team send an email to CARS- ESC@Brisbane.qld.gov.au. All relevant documentation, including both the certified ESCP and the certified design certificate, must be attached to this email. Please allow up to 10 business days for your request to be processed. Timing: Attend the pre-start meeting prior to the commencement of any earth disturbing activities. |
As indicated |
17(e) Implement Certified Erosion and
Sediment Control Plan Implement the certified ESCP and maintain all ESC measures in accordance with best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version) and, to the extent of any inconsistency, relevant Brisbane Planning Scheme Codes and Policies. The ESCP and design certificate must be available on site at all times for inspection by Council officers. Any alteration to supplementary or Type 3 ESC measures must be reflected in the certified ESCP. Any alteration to Type 2 or Type 1 ESC measures will require a revised ESCP and design certificate that has been certified by either the CPESC or RPEQ. Timing: While earth disturbing activities are occurring and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
| 18) Maintenance Period for Engineering Work Maintain the work required by the Engineering condition(s) imposed on this development approval and rectify any defects in accordance with the requirements detailed in this condition. NOTE: Guidance for requesting a pre-start and co- ordinating the On/Off Maintenance process can be found on Council's website (https://www.brisbane.qld.gov.au/planning-and-building/applying-and- post-approval/on-and-off-maintenance-approvals) Timing: During the on-maintenance period. |
As indicated |
18(a) On-Maintenance Acceptance Arrange an on- maintenance inspection with Development Services and obtain written confirmation from Council that the work has been completed in accordance with the requirements of the condition and is accepted on-maintenance. Provide proof of Public Liability Insurance ($20 million) for the on- maintenance period. Lodge a maintenance security for the on-maintenance period. The security must be calculated as 5% of the value of the constructed work or $10,000.00, whichever is greater. NOTE: A maintenance security may consist of either a bank guarantee or monetary payment lodged with Council. Refer to Council's Infrastructure Installation and Construction Requirements Manual for further details about the on-maintenance procedure and requirements. Timing: Prior to Council's notation on the plan of subdivision. |
As indicated |
18(b) On-Maintenance Period Provide a minimum 12 months maintenance to the work from the time the work is accepted on- maintenance by Council. During this period maintain the work and rectify any defects identified at the on-maintenance inspection and those arising during the on-maintenance period. NOTE: The on-maintenance period may be extended by Council pending concerns and/or unsatisfactory performance during the maintenance period. Timing: A minimum 12 months from acceptance on-maintenance. |
As indicated |
18(c) Off-Maintenance
Acceptance On completion of the maintenance period arrange an off-maintenance inspection with Development Services and obtain written confirmation from Council that the work is accepted off-maintenance. Ensure all defects are rectified prior to making an appointment for off- maintenance Inspection. NOTE: If the inspection is successful the maintenance security will be released. Timing: On completion of the on-maintenance period. |
As indicated |
| 19) Information Signage Erect an information sign on the subject property in accordance with Council's general requirements for signage and in accordance with the requirements outlined below: a) The sign should provide a brief description of the development proposed; b) The sign is to list the name, postal and/or email address and a contact telephone number for the following parties (where relevant) that are undertaking work on the site: - Developer;
c) The lettering on the sign is to be at least 25 millimetres in height, be of regular weight and in sentence case; d) The sign is to be a minimum size of 1,200 millimetres by 900 millimetres; e) The maximum area of the sign is to be 2.0m2; f) The sign is to be positioned as follows: - located centrally along the road frontage of the
site to Roghan Road; g) The sign is to contain no commercial or corporate advertising other than the name, logo or slogan of the parties outlined in part (b) of this condition; h) The sign is to be non-illuminated; and i) Both the sign and the supporting structure are to be made of weatherproof material and to be properly maintained at all times. Timing: Prior to site works commencing and then to be maintained until completion of the development for all stages. |
As indicated |
| 20) Engineering Pre-Start Meeting Arrange and attend a pre-start meeting with Development Services. Applicable compliance and inspection fees must be paid, in full, to Council prior to the meeting being held. NOTE: To arrange an engineering pre-start meeting with Development Services an email supported by a completed copy of the Pre-Start Meeting Guidelines - Civil Engineering Works kit (https://www.brisbane.qld.gov.au/sites/default/files/20191008- cc11207-pre-start-meeting-guidelines-civil-engineering-works.pdf) is to be sent to dalodgement@brisbane.qld.gov.au a>. Details include (but are not limited too) the following: - Site address, Development Approval number (A00) and relevant stage/s (if appropriate); - List all Development Approval conditions requiring compliance prior to site/operational work commencing and demonstrate compliance with those conditions; - Payee details (Name and address) for the issue of a development "Compliance and Inspection Fee" quote; - Superintendent (Consultant) name, address and telephone number (including after-hours contact); - Contractor/s and major Sub- Contractor/s, name, address and telephone number (including after-hours contact); - Intended date of commencement of works. NOTE: - All operational works applications are to be approved prior to requesting the pre-start meeting. - A minimum 5 working days' notice is required. - Compliance and Inspection fee to be paid prior to undertaking pre-start meeting. - All operational works approved documents and the Development Approval package (conditions and plans) must be available at the pre-start meeting. - Further guidance for requesting a pre-start and co-ordinating the On/Off Maintenance process can be found on Council's website (https://www.brisbane.qld.gov.au/planning-and-building/applying-and- post-approval/on-and-off-maintenance-approvals). Timing: Prior to site/operational work commencing. |
As indicated |
| 21) Construction Management Plan (Minor) Carry out development in a method
consistent with a Construction Management Plan (Minor) prepared in accordance
with the requirements of this condition. Access via the new road delivered
by the neighbouring development at 159 Roghan Road is
subject to either the road being constructed and accepted on maintenance by
Council, or alternatively consent being obtained from the neighbouring property
owner. |
While site/operational/building work is occurring |
21(a) Construction Management Plan (Minor) -
Prepare Plan Prepare a detailed Construction Management Plan (CMP) for the construction phase of the approved development. The Construction Management Plan must be in accordance with the relevant Brisbane Planning Scheme Codes and address the following: (i) Provision for pedestrian management including alternative pedestrian routes (adjacent to or surrounding the site); (ii) Existing and proposed kerbside allocation signs and line marking (such as bus stops, loading zones and parking meters and/or ticket dispensers); (iii) Location of and impacts to any Council or other public utility or local authority's assets on or within or external to the site; (iv) Location and design of temporary vehicular construction access points, including frequency of use; (v) Management and mitigation strategies for the impact of dust, noise and vibration upon adjoining and nearby properties; (vi) Provision for loading and unloading of materials including the location of any remote loading sites; (vii) Location of materials, structures, plant and equipment to be stored or placed on the construction site; (viii) Location of proposed external hoardings or gantries, including clearances to the impacts of this on existing street furniture and other footpath assets located within the verge as well as impacts on any existing advertising signage located either along or adjacent to the site frontage this includes any potential obstruction of sight lines for such advertising (e.g. 'CityCycle' bicycle stations or bus stops with advertising); (ix) Location of proposed employee and visitor parking areas; (x) Anticipated staging and programming; (xi) Impacts of any actions proposed to address any of the above items or any actions resulting from construction of the development that will impact on existing street trees; (xii) Complaint management processes to be implemented; and (xiii) Compliance with the Management Plans Planning Scheme Policy and other relevant Planning Scheme Policies. The Construction Management Plan must be supported by "approval in principle" or written approvals from the relevant Council sections or other governing bodies responsible for any potentially impacted infrastructure. The list of relevant infrastructure and contacts is available on Council's website - Search "Constructions Management Plan". Note: The Construction Management Plan is not required to be approved by Development Services. Timing: Prior to site/operational work commencing. |
As indicated |
21(b) Construction Management Plan (Minor) -
Submit Plan Submit a copy of the Construction Management Plan to Council's Development Services Branch at the following mailbox: engineeringservices@brisbane.qld.gov.au quoting the BCC planning development approval reference number. Timing: At least 10 days prior to site works commencing |
As indicated |
21(c) Construction Management Plan (Minor) -
Documentation on Site Legible copies of the Construction Management Plan and current permits must be kept on site and be made available on request by Council at all times. The requirements of the CMP must be included in all induction of principal and subcontractors utilised in the development. An outline of the induction provided to contractors may be requested by Council to confirm compliance with this condition. Timing: While site/operational work is occurring. |
As indicated |
21(d) Construction Management Plan - Works to
be Performed Out of Hours Obtain an approval from Development Services for any
work that is proposed to be undertaken outside of normal business hours -
6:30am to 6:30pm, Monday to Saturday. |
As indicated |
21(e) Implement Construction Management Plan
(Minor) Carry out the development in accordance with the submitted Construction Management Plan. |
While site/operational/building work is occurring |
| 22) Protect Existing Infrastructure Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure. Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations. The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements. |
While site/operational/building work is occurring |
22(a) As Constructed Drawings - Alterations
to Existing Infrastructure Submit to Development Services As Constructed drawings showing all new and/or rectification works and an asset register, prepared and certified by a Registered Professional Engineer Queensland. Timing: Prior to Council's notation on the plan of subdivision. PROOF OF
FULFILMENT Certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements. |
As indicated |
| 23) Filling and/or Excavation All earthworks must be carried out generally in accordance with the
relevant Brisbane Planning Scheme Codes and the approved Engineering Concept
– Earthworks Layout Plan CE01 Issue C (received 31/03/2026 and amended in
red 27/04/2026) and the Engineering Concept – Earthworks Sections Plan
CE03 Issue C (received 31/03/2026). The interface to the neighbouring property along the western site
boundary (of lots 9 &12) is to be confirmed within subsequent detailed design
operational works application(s). Council’s preference is that retaining outcome is coordinated with
the ultimate finished levels of the adjoining development site to avoid
unnecessary/redundant retaining structures where possible and
practical. |
Prior to Council's notation on the plan of subdivision |
23(a) Submit Earthworks
Drawings Submit to, and obtain approval from, Development Services earthworks drawings prepared and certified by a Registered Professional Engineer Queensland in accordance with the approved DRAWINGS AND DOCUMENTS and the relevant Brisbane Planning Scheme Codes. The Earthworks Drawings must include the following: - The location of any cut and/or fill; Note: - If the earthworks impact on the road reserve, the Developer must obtain
applicable footpath and road permits prior to commencing any works. Such
impacts may include footpath occupation, road closures, re-profiling, ground
anchors and/or relocation of services. If the excavation has to be stabilised
using ground anchors or similar, then the submitted plans must show the
location of these in relation to all services. The cost of moving services,
utilities and assets is the responsibility of the Developer. The permission of
the service/utility/asset owner is required. Timing: Prior to site/operational work commencing. |
As indicated |
23(b) Fill Material, Placement, Compaction
and Testing All fill material placed on the site must comprise only natural earth and rock and must be free of contaminants (as defined by Part 3, Division 2, Subdivision 2 Environmental contamination, Section 11 of the Environmental Protection Act 1994) and noxious, hazardous, deleterious and organic materials. Fill material, placement, compaction and testing must comply with the requirements of Australian Standard - AS 3798, Guidelines on Earthworks for Commercial and Residential Developments. Timing: While site/operational work is occurring. |
As indicated |
23(c) Implement Approved Earthworks
Drawings Construct and maintain
the earthworks in accordance with the requirements of AS3798 and the approved
earthworks drawings. |
As indicated |
23(d) Submit As Constructed
Drawings Submit to Development Services As Constructed drawings prepared by a Registered Surveyor (Qld). Timing: Prior to Council's notation on the plan of subdivision. |
As indicated |
23(e) Submit Certification Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the approved earthworks drawings. Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that all fill material used complies with the quality requirements of this condition and that placement, compaction and testing has been carried out in accordance with AS3798. Timing: Prior to Council's notation on the plan of subdivision. |
As indicated |
| 24) Remove Improvements & Obstructions from Truncation
and Dedication Remove all improvements (fences, gates, letter boxes, garden beds and plots and other constructed items, etc.) and obstructions (existing earth banks, vegetation, etc.) from the area of dedicated road and reinstate the area as footway in accordance with the relevant Brisbane Planning Scheme Codes. Any new or existing installations of electrical pillar boxes, pad mounted transformers (PMTs), water meters and the like, must be installed/relocated to their ultimate alignment relative to the new property boundary and clear of the usable footpath areas irrespective of the alignment of the existing services/conduits. Note: -
The cost of moving services, utilities and assets is the responsibility of the
Developer. The permission of the service, utility or asset owner will be
required. Council permission is required if street trees, stormwater
gullies/drains, and swales are affected. Urban Utilities permission is required
if water supply and sewerage services are affected. PROOF OF
FULFILMENT Certification from a Registered Surveyor (Qld) or Registered Professional Engineer Queensland that the above work has been completed in accordance with this condition. |
Prior to Council's notation on the plan of subdivision |
| 25) Retaining Walls Design and construct all retaining walls and associated fences, in accordance with the relevant Brisbane Planning Scheme Codes and the following: - All retaining walls including the footings, must be located wholly within the property boundaries of the site where works are occurring - Runoff from surface drains and subsoil drainage associated with the retaining walls must be collected and connected to a lawful point of discharge (LPD) where possible. If no LPD is available the surface drains and sub-soil drainage must be designed, installed and discharged to ensure there is no ponding, nuisance or concentration of stormwater discharge to adjacent properties. - Retaining walls to stabilise excavation must be set back from property boundaries to accommodate subsoil drainage without encroachment into the neighbouring property. This set back may vary depending on the height, structure and design of the retaining wall, surcharge loadings from neighbouring properties, and to provide a surface drain along the top of the retaining wall - For retaining walls in excess of
1.0m in height: NOTE: Refer to City Plan 2014; Infrastructure Design Planning Scheme Policy (IDPSP) for Council’s definition of a LPD. |
Prior to Council's notation on the plan of subdivision |
25(a) Certification of Retaining
Walls For retaining walls over 1.0m in height, obtain certification from a Registered Professional Engineer Queensland that the design and construction of the retaining walls and ancillary drainage are in accordance with the requirements of this condition. Timing: Prior to Council notation on the plan of subdivision. |
As indicated |
| 26) Repair Damage to Kerb, Footpath or Road Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development. |
Prior to Council's notation on the plan of subdivision |
26(a) Interim Repairs If at any time during the construction phase of the approved development, damage to the existing kerb and channel, footpath or roadway creates unsafe, unreasonable and/or not fit for purpose conditions as assessed by Council, interim repairs must be undertaken as directed by Program Planning and Integration. Note: Any interim repairs required to be undertaken shall not be considered to satisfy the requirements of this condition for the permanent repair of the infrastructure prior to Council's notation on the plan of subdivision. Timing: While site/operational works is occurring |
As indicated |
| 27) Refuse Collection - Kerb Side (external
road) Refuse and recycling bins for the development must be collected from the kerb side as shown on the APPROVED DRAWINGS AND DOCUMENTS. |
To be maintained |
| 28) Future Road Widening The development must not prejudice the future road reserve widening along the Roghan Road frontage. Keep the area clear of improvements and structures. The extent of the land to be set aside for a future road reserve widening is 3.5 metres wide along the full Roghan Road frontage of the site as shown on the approved Reconfiguration Plan R1 Issue E. |
At all times |
| 29) Land for Transport Network - Road (Non-
trunk) Dedicate as road land shown as new road (non-trunk) on the approved Reconfiguration Plan R1 Issue E (dated 29/01/2026 and amended in red 27/04/2026), including the following: i. A 16.0
metre wide new road corridor maintaining a consistent alignment
with the approved road corridor to the west in accordance with A006216521. NOTE: This condition is imposed under section 145 of the Planning Act 2016. PROOF OF FULFILMENT The plan of subdivision is to clearly show the dimensions of the land dedication(s) required by this condition and certification by a registered surveyor (Qld) is to be provided that the plan of survey meets the requirements of this condition. |
Prior to Council's notation on the plan of subdivision |
| 30) Work for Transport Network - Road (Non-trunk) -
Internal Construct the following roadwork with any associated drainage, footpath, pathways and services including street lighting for the Transport Network (Road) shown on the approved Engineering Concept – Functional Traffic Layout CT01 Issue C (received 31/03/2026 and amended in red 27/04/2026) and the approved Engineering Concept – Services Layout Plan CS01 Issue B (received 31/03/2026 and amended in red 27/04/2026) in accordance with the relevant Brisbane Planning Scheme Codes, the Manual of Uniform Traffic Control Devices and the AUSTROADS design standards: - 16 metre wide road
designed and constructed as Neighbourhood Roads (designed for 85 percentile 50
km/hr maximum) and with street lighting category; - 1.5m wide balance of concrete pathway provided to the pedestrian cross block link. - New stormwater infrastructure within the new “Road 1”
designed and constructed as a herringbone layout to ensure minor and major
flows are captured and are conveyed to a lawful point of discharge. The
neighbouring downslope property must not be impacted by nuisance flows or
ponding. - All stormwater structures are to be designed in
accordance with the Infrastructure Design Planning Scheme Policy and Brisbane
Standard Drawings. The stormwater gully pits are to be BCC Lip-In-Line
Stormwater Gullies in accordance with BSD-8051. - The
construction of the roads and drainage are subject to the downslope
infrastructure provided by the neighbouring development being delivered and
accepted On-Maintenance by Council. Note: This condition is imposed
under section 145 of the Planning Act 2016.
|
Prior to Council's notation on the plan of subdivision |
30(a) Submit Functional Layout
Drawings Submit to, and obtain approval from, Development Services functional layout drawings prepared and certified by a Registered Professional Engineer Queensland in accordance with the APPROVED DRAWINGS AND DOCUMENTS and the relevant Brisbane Planning Scheme Codes. Note: This approval must be obtained prior to the submission of drawings for Roadwork and Stormwater Drainage and Signs and Pavement Marking. Timing: Prior to site/operational work commencing. |
As indicated |
30(b) Submit Roadworks and Stormwater
Drainage Drawings Submit to, and obtain approval from, Development Services Roadworks and Stormwater Drainage Drawings prepared and certified by a Registered Professional Engineer Queensland in accordance with the APPROVED DRAWINGS AND DOCUMENTS and the relevant Brisbane Planning Scheme Codes. Timing: Prior to site/operational work commencing. |
As indicated |
30(c) Submit Signs and Pavement
Drawings Submit to, and obtain approval from, Development Services Signs and Pavement Marking drawings prepared and certified by a Registered Professional Engineer of Queensland in accordance with the APPROVED DRAWINGS AND DOCUMENTS and the relevant Brisbane Planning Scheme Codes. Timing: Prior to site/operational work commencing. |
As indicated |
30(d) Submit Street Lighting Design
Drawings Submit to, and obtain approval from, Construction Branch, Citywide Services, City Lighting (CS-LIGHTING@brisbane.qld.gov.au), street lighting design drawings prepared and certified by a Registered Professional Engineer of Queensland (electrical) which show the proposed street lighting system in accordance with the relevant Brisbane Planning Scheme Codes. Timing: Prior to site/operational work commencing. |
As indicated |
30(e) Implement Approved
Drawings Construct the works in accordance with the above approved drawings. Timing: Prior to on-maintenance acceptance. |
As indicated |
30(f) Submit As Constructed
Drawings Submit to Development Services As Constructed drawings including an asset register and a pre-On-Maintenance Inspection Checklist, prepared and certified by a Registered Professional Engineer Queensland. Timing: Prior to on-maintenance inspection. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the above approved drawings. |
As indicated |
| 31) Streetscape Works - Subdivision New Road Carry out streetscape improvement works, including concrete path (where required by this condition), turf and street trees to the verge of the new road(s). Improvement works must be to an Industrial Street standard for Industrial roads and a Neighbourhood Street Minor standard for all other roads (Suburban/District/Neighbourhood/Local) in accordance with: - the relevant Brisbane Planning Scheme Codes; - Brisbane Standard Drawings (BSD); - the requirements of this condition; and - the Infrastructure Design Planning Scheme Policy including sections 3.7.4.4, 3.7.4.5 and 3.7.5. Note: standard path alignments for new roads are shown on Brisbane Standard Drawing BSD-5201 sheet 2. |
Prior to Council's notation on the plan of subdivision |
31(a) Concrete Path Install a 1.2m wide broom finished standard Portland grey concrete path to both sides of the carriageway of Suburban/District/Neighbourhood (bus route)/Industrial roads and one side of the carriage way of a Neighbourhood (non-bus route) roads and one side of all local streets. The edge of the path is to be setback 1.9m from the back of kerb for industrial roads and 1.48m from the back of kerb for all other roads. Transition to existing paths on verges that adjoin the development. The transition is to occur fronting the adjoining developments, not the subject site. Note: If the above requirements cannot be achieved, contact the Engineering Services Team via email: engineeringservices@brisbane.qld.gov.au Timing: Prior to Council's notation of the plan of subdivision. |
As indicated |
31(b) Submit As Constructed
Drawings Submit to Development Services As Constructed plans including an asset register, checked by a Registered Professional Engineer Queensland, certifying that the concrete path works have been completed in accordance with relevant Brisbane Planning Scheme Codes/Policies. Timing: Prior to Council's notation of the plan of subdivision. |
As indicated |
31(c) Turf Install turf to the full width of the verge excluding any concrete path required by this condition. Timing: Prior Council's notation of the plan of subdivision. |
As indicated |
31(d) Street Tree(s) Enter into and implement an arrangement with the Public Space Operations Arboriculture (PSO- ARB) in relation to the required provision of the street tree planting in accordance with the above sections of the Infrastructure Design Planning Scheme Policy, including the number, species, location, installation and maintenance of the required street tree(s) as determined by Public Space Operations. Provide to Development Services a copy of the agreement signed by Public Space Operations (PSO-ARB). Note: Street trees should not be planted until all utilities have been installed. Timing: Prior to Council's notation on the plan of subdivision. |
As indicated |
| 32) Remove Redundant Drainage Outlets Remove any redundant drainage outlets from
the kerb and channel including any associated pipe work across the footway and
reinstate the kerb and channel and the footway area in accordance with the
relevant Brisbane Planning Scheme Codes. |
Prior to Council's notation on the plan of subdivision |
| 33) Site Drainage - Major Provide a stormwater connection to
all new or existing allotments and provide drainage infrastructure to ensure
stormwater run-off from all roof and developed surface areas will be collected
internally and piped in accordance with the relevant Brisbane Planning Scheme
Codes to a lawful point of discharge as shown on the approved Engineering
Concept – Services Layout Plan CS01 Issue B (amended in red
27/04/2026). - All upslope stormwater
connections to existing private properties must extend to the property boundary
of all relevant properties being ultimately serviced by that connection. Guidance for requesting a pre-start and co-ordinating the On/Off Maintenance process can be found on Council's website (https://www.brisbane.qld.gov.au/planning-and- building/applying-and-post-approval/on-and-off-maintenance-approvals. |
Prior to Council's notation on the plan of subdivision |
33(a) Submit Site Drainage
Drawings Submit to, and obtain approval from, Development Services, site drainage drawings and engineering calculations, prepared and certified by a Registered Professional Engineer Queensland, in accordance with the relevant Brisbane Planning Scheme Codes. Note: -
Queensland Building and Construction Commission licensed hydraulic consultants
may design the stormwater system for sites less than 2000m2 with an upstream
catchment servicing no more than 4 residential lots. This excludes stormwater
drainage design (including subsoil drainage) of basements in flood planning
areas and the design of any onsite stormwater detention system Timing: Prior to site/operational work commencing |
As indicated |
33(b) Implement Approved
Drawings Carry out the works in accordance with the approved site drainage drawings. Timing: Prior to Councils notation on the plan of subdivision. |
As indicated |
33(c) Submit As Constructed
Drawings Submit to Development Services As Constructed drawings prepared and certified by a Registered Professional Engineer Queensland or a Queensland Building and Construction Commission licensed hydraulic consultants (where applicable). Note: To be submitted via DA- ComplianceEngineering@brisbane.qld.gov.au and include the site address, A00 reference and Condition number in the subject line. Timing: Prior to Council's notation on the plan of subdivision. PROOF OF
FULFILMENT Certification (incl. QA documentation, CCTV, etc) from a Registered Professional Engineer Queensland, or a Queensland Building and Construction Commission licensed hydraulic consultants (where applicable), confirming that the works have been completed in accordance with the above stormwater approved site drainage drawings. Timing: Prior to Council's notation on the plan of subdivision. |
As indicated |
| 34) Ponding of Stormwater Carry out the approved development to
ensure that adjoining properties and roads are protected from ponding or
nuisance from stormwater during construction. |
Prior to Council's notation on the plan of subdivision |
| 35) Street Lighting Provide street lighting in accordance with the requirements of this approval and the relevant Brisbane Planning Scheme Codes. Note: for required lighting categories please refer to the roadworks and/or pathway conditions within this conditions package. PROOF OF FULFILMENT Evidence of an agreement with an electricity supply authority to provide a public lighting system in accordance with the approved street lighting design drawings. |
Prior to Council's notation on the plan of subdivision |
| 36) Service Conduits and Mains Provide and install all service conduits, including street lighting as required by Council, and meet the cost of any alterations to public utility mains, existing mains, services, street lighting or installations that are required to carry out the approved development. These works must be in accordance with the relevant Brisbane Planning Scheme Codes, and include the following, where applicable: - the provision of all services and/or conduits along the full length of
any rear allotment access or access easement. Note: -
The cost of moving services, utilities and assets is the responsibility of the
Developer. The permission of the service, utility or asset owner will be
required. Council permission is required if street trees, stormwater
gullies/drains, and swales are affected. Urban Utilities permission is required
if water supply and sewerage services are affected. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the requirements of this condition. Note: Civil works are to be certified by a RPEQ(Civil) and electrical works are to be certified by a RPEQ (Electrical) |
Prior to Council's notation on the plan of subdivision |
36(a) Submit Certification to
Council Submit to Development Services certification by a Registered Professional Engineer Queensland (RPEQ) that the works have been completed in accordance with the requirements of the condition. Note: Where rear allotment accesses or easements exist, the certification is to be supported by As-Constructed drawings certified by a RPEQ showing all services and/or conduits. Civil works are to be certified by a RPEQ (Civil) and electrical works are to be certified by a RPEQ (Electrical)Timing: Prior to Council's notation of the plan of subdivision. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the requirements of this condition. Note: Civil works are to be certified by a RPEQ(Civil) and electrical works are to be certified by a RPEQ (Electrical) |
As indicated |
| 37) Telecommunications Submit to Development Services, evidence of an agreement with a telecommunication carrier to provide underground telecommunication services within and adjacent to the proposed development in accordance with the relevant Brisbane Planning Scheme Codes. |
Prior to Council's notation on the plan of subdivision |
| 38) Agreement with Electricity Supplier Submit to Development Services, evidence of an agreement with an electricity supplier to provide necessary services to the development in accordance with the relevant Brisbane Planning Scheme Codes. Where development is within an established area of overhead electricity supply and the electricity supplier determines that a property pole is the appropriate solution to supply electricity to the development, the developer must be responsible for the installation of the property pole(s). In the above circumstances, submit to Development Services, certification from the developer's electrical consultant confirming that the above installation has been completed in accordance with the relevant AS/NZS Standards and the Queensland Electricity Connection Manual (QECM) and Queensland Electricity Metering Manual (QEMM). |
Prior to Council's notation on the plan of subdivision |
| 39) Water and Wastewater Pursuant to Schedule 18 of the Planning Regulation 2017 submit to Development Services, documentary evidence, issued by the relevant distributor-retailer, to verify that the conditions of any necessary connection certificate under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009, have been complied with. |
Prior to Council's notation on the plan of subdivision |
| 40) Permanent Driveway Crossover Provide a 5.5 metre wide Type B1 permanent driveway crossover to the frontage of Lot 9 in accordance with the relevant Brisbane Planning Scheme Codes and located as shown on the approved Engineering Concept – Functional Traffic Layout Plan CT01 Issue C (amended in red 27/04/2026). Written consent must be obtained from Public Space Operations Arboriculture (PSO Arb) prior to any works occurring that will either impact on or require removal of a street tree (this includes pruning, excavation or fill within the root zone/canopy of the tree). At all times during construction of the crossover, safe pedestrian access along the site frontage must be maintained. Note: No further driveway permit is required however additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover. |
Prior to Council's notation on the plan of subdivision |
| 41) Redundant Driveway Crossover Remove the redundant existing driveway crossover(s) on the frontage(s) of the site and reinstate the kerb and channel, road pavement, footways and footpaths in accordance with the relevant Brisbane Planning Scheme Codes. Note: |
Prior to Council's notation on the plan of subdivision |
| 42) Rear Lot Access Provide access to the rear lots 8 & 9 in accordance with the approved Engineering Concept – Functional Traffic Layout Plan CT01 Issue C (amended in red 27/04/2026) and the following: - Construct a concrete slab, along the full length
of the access strip to the rear allotments Lot 8 & Lot 9; and the driveway
crossover in accordance with the relevant Brisbane Planning Scheme Codes.
- The rear lot accessway corridor
must be a minimum width of 3.5 metres. NOTE: No further driveway permit is required however additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover. |
Prior to Council's notation on the plan of subdivision and then to be maintained |
| 43) Natural Assets Local Law (NALL) - Protected
Vegetation On Site Work on or around protected vegetation may require a permit under the Natural Assets Local Law 2003 (NALL). Permits under the NALL are issued by Development Services. To apply for a permit to work on protected vegetation go to Council's website or contact the call centre on 3403 8888. |
As indicated |
| 44) Natural Asset Local Law (NALL) - Protected
Vegetation on Public Land, Road or Park Work on or around protected vegetation on public land, road or park may require a permit under the Natural Assets Local Law 2003 (NALL). Arrangements must be made with Public Space Operations Arboriculture (PSO-Arb) in relation to the works carried out on protected vegetation on public land, road or park including provision for costs and replacement planting as determined by PSO-Arb. PSO-Arb can be contacted via ISG-CS-PPI-PLANNING-ARB@brisbane.qld.gov.au. Timing: Prior to carrying out any works on protected vegetation. Note: All requirements of a development approval conditions with timing stipulated as 'prior to site works commencing' (or equivalent) must be fulfilled before Council can issue a NALL permit. |
As indicated |
| 45) Currency Period The currency period for this development approval is stated in the Decision Notice and is expressed as a date. This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016. |
As indicated |
| 46) Damage to Trees on Adjoining Land Please note that any damage caused to vegetation on adjoining land as a result of exercising this development approval may result in an offence under other legislation (e.g. Natural Assets Local Law) and/or civil action. |
As indicated |
| 47) Fire Ant Movement Controls To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected. These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products. Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014. For further information contact the relevant Queensland State Government department on 13 QGOV. |
As indicated |
| 48) Water and Wastewater Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. For further information about any necessary Water Approvals contact Urban Utilities. |
As indicated |
| 49) Interfering with Survey Marks Survey marks (including permanent survey marks) are protected from unauthorised removal, disturbance or destruction under Section 42 of the Survey and Mapping Infrastructure Act 2003. Where a development has the potential to interfere with any survey marks, a Registered Cadastral Surveyor (QLD) should be consulted to ensure the works are planned in accordance with the relevant legislation. For further information contact the relevant Queensland State Government department on 13 QGOV. |
As indicated |
| 50) Cultural Heritage Aboriginal cultural heritage is protected under the Aboriginal Cultural Heritage Act 2003. This Act establishes a cultural heritage duty of care and in section 23(1) mandates that a person who carries out an activity must take all reasonable and practicable measures for ensuring activities are managed to avoid or minimise harm to Aboriginal cultural heritage.
The Duty of Care Guidelines gazetted pursuant to the Aboriginal Cultural Heritage Act 2003 provide guidance on identifying and protecting Aboriginal cultural heritage to fulfil the duty of care.
For further information contact the relevant Queensland State Government Department (Department of Aboriginal and Torres Strait Islander Partnerships). |
As indicated |