| Address of Site: | 1300 OLD CLEVELAND RD CARINDALE QLD 4152 1304 OLD CLEVELAND RD CARINDALE QLD 4152 |
| Real Property Description of Site: | L100 SP.127475 L1 RP.168799 |
| Aspects of development and type of approval: | DA - PA - Material Change of Use Development Permit - food and drink
outlet DA - PA - Building Work Development Permit - food and drink outlet DA - PA - Referral Agency for Building Work Referral Response - Flood hazard area |
| Council File Reference: | A006983478 Permit Reference Number/s: DAMC351700517; DABW359779718; DAEB359779818. |
| Package Status: | APPROVED - Version 2 (21st of May, 2026 9:12:40 AM) |
| Package Generated: | 21/05/2026 |
| Michael O'REILLY Environmental Management Officer Environmental Management Services Michael.O'Reilly@brisbane.qld.gov.au 3403 9517 |
Hayley STEEL Team Manager (Acting) Planning Services Special Assessment Hayley.Steel@brisbane.qld.gov.au (07) 3178 0022 |
Kathy BAGULEY Principal Urban Planner Planning Services North DSPlanningSupport@brisbane.qld.gov.au 07 3403 5510 |
| Errin Xiaofang LU Senior Urban Planner Planning Services South Errin.Lu@brisbane.qld.gov.au (07) 3403 3694 |
Richard HANSON Ecologist Ecology Services Richard.Hanson@brisbane.qld.gov.au (07) 3403 5611 |
Nikolee ANSELL Landscape Architect Green Space Services Nikolee.Ansell@brisbane.qld.gov.au |
| Karolina SZENCZI Senior Urban Planner House & Homes karolina.szenczi@brisbane.qld.gov.au 0731782655 |
Kellie HILTON Senior Urban Planner Planning Services South kellie.hilton@brisbane.qld.gov.au (07)3403 7226 |
Timothy BYRNE Principal Urban Planner Planning Services South Timothy.Byrne@brisbane.qld.gov.au (07) 3403 0314 |
DRAWINGS AND DOCUMENTS
| Drawing or Document | Number | Plan Date |
|---|---|---|
| Acoustic Report | Report No. 4279 R2 | 15-DEC-2017 (Received) |
| Flood Study | Job Reference Number - 7707 | 15-DEC-2017 (Received) |
| Proposed Site Plan | Drawing No. SK2 amdt 9 (Amended In Red 15-MAY-2026) | 12-MAR-2018 (Received) |
| Stormwater Layout Plan | DWG. No. SK004 Revision 3 | 15-DEC-2017 (Received) |
| Road Widening Plan | Concept Design Number RC 16076 Issue 1 | 17-JAN-2018 |
| Landscape Concept Plan | Drawing Number 1802-LCP1 Issue A (Amended In Red 05-MAY-2026) | 17-MAR-2026 (Received) |
| Landscape Concept Plan | Drawing Number 1802-LCP2 Issue A | 12-MAR-2018 (Received) |
| Proposed Site Plan | GYG-CR-DA-S01 Rev DA1 (Amended In Red 15-MAY-2026) | 17-MAR-2026 (Received) |
| Proposed Site Plan | GYG-CR-DA-S02 Rev DA1 (Amended In Red 15-MAY-2026) | 17-MAR-2026 (Received) |
| External Elevations West | GYG-CR-DA-200 Rev DA1 | 17-MAR-2026 (Received) |
| External Elevations North | GYG-CR-DA-201 Rev DA1 | 17-MAR-2026 (Received) |
| External Elevations South | GYG-CR-DA-202 Rev DA1 | 17-MAR-2026 (Received) |
| External Elevations East | GYG-CR-DA-203 Rev DA1 | 17-MAR-2026 (Received) |
APPROVAL CONDITIONS
| Permit to Which These Conditions Relate: | DA - PA - Material Change of Use |
| Activity(ies): | food and drink outlet |
| Stage: |
| 1) Approved Drawings and Documents A legible copy of the
Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package
must be maintained on site and kept available for inspection by site workers
and Council officers. |
While site/operational/building work is occurring |
| 2) Carry Out the Approved Development Carry out the approved
development generally in accordance with the approved DRAWINGS AND
DOCUMENTS. |
While site/operational/building work is occurring and then to be maintained |
| 3) Complete All Building Work Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out generally in accordance with the approved DRAWINGS AND DOCUMENTS, and, where the building work is assessable development, in accordance with a current development approval. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
| 4) Maintain the Approved Development Maintain the approved
development generally in accordance with the approved DRAWINGS AND DOCUMENTS,
and any relevant Council engineering or other approval required by the
conditions. |
To be maintained |
| 5) Public Access - 24 Hours Through Site Provide and maintain unimpeded and safe 24-hour public access through the subject site and ensure that access ways are designed to cater for people with disabilities in accordance with Australian Standard - AS1428.1Design for Access and Mobility - Part 1: General requirements for access - New building work. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 6) Security Lighting Install and maintain a suitable system of security
lighting to operate from dusk to dawn within all areas where the public may
gain access, including car parking areas, building entrances and vegetated
areas |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 7) Car Parking The car parking within the premises must be
maintained exclusively for the ancillary use of the development. The parking
must not be made available to the general public and there must not be signage
erected on or in the vicinity of the site advertising the availability of car
parking to the general public. |
To be maintained |
| 8) Screen Air Conditioning and Other Plant
Enclosures Install and maintain suitable screening to all air conditioning, lift motor rooms, plant and service facilities located at the top of or on the external face of the building. The screening structures must be constructed from materials that are consistent with materials used elsewhere on the facade of the building. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 9) Landscape the Site - Self Certification Landscape the site in accordance with the
requirements of this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
9(a) Landscape Plan for Self
Certification Prepare a detailed
Landscape Plan at a scale of 1:100 for all on-site landscape works identified
on the approved Landscape Concept Plan (Drawing Number 1802-LCP1 Revision A,
received 17 March 2026, amended in red 5 May 2026). The plan must be prepared
by a registered Landscape Architect and must comply with the relevant Brisbane
Planning Scheme Code. The plan must be certified by the registered Landscape
Architect using Brisbane City Council Form CC10616 - Landscape Design
Certification and the form must be submitted to Development Services. Amenity |
As indicated |
9(b) Implement Certified Landscape
Plan Carry out the landscaping work in
accordance with the above certified detailed Landscape Plan. |
As indicated |
9(c) Certify Work On completion of the
landscaping work, submit to Development Services Brisbane City Council Form
CC10613 - Landscape Works Certificate prepared by a registered Landscape
Architect or licensed Landscape Contractor to certify the completed landscaping
work complies with the certified detailed Landscape Plan. |
As indicated |
9(d) Maintain Landscape Work Maintain the landscape work generally in accordance
with the certified detailed Landscape Plan. |
As indicated |
| 10) Commercial Air Emissions
Commercial uses/development are to ensure that food/cooking odours are released via exhaust vent outlets which are discharged vertically and directed away from any sensitive use and include the following: · food/cooking air emissions exhausts are to be separated by a minimum of 6m from a sensitive use, including any outdoor air intake of a sensitive use; · air emissions are not to cause an odour or air emission which is detectable and disturbing at a sensitive use; and
|
Prior to the commencement of the use and then to be maintained |
| 11) Mechanical Ventilation Certification Mechanical ventilation and exhaust vents
associated with the approved Food and Drink Outlet use shall be designed and installed in accordance with relevant sections of
AS1668.2 -2012: The use
of ventilation and air conditioning in buildings - Mechanical ventilation in
buildings. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
11(a) Submit Certification - Mechanical
Ventilation System - Food and Drink Outlet Submit to
Development Assessment certification that the exhaust vents and mechanical ventilation systems
associated with a Food and
Drink Outlet are installed in accordance
with AS1668.2 - 2012: The use of
ventilation and air conditioning in buildings - Mechanical ventilation in
buildings. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 12) Noise Attenuation - Amplified Music General
Limit A sound limiting device must be installed into the amplification system of the proposed drive through to ensure the noise criteria for amplified sound for this approval is achieved at nearby noise-sensitive places. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
12(a) Certification Submit to Development Services certification from an appropriately qualified acoustic consultant demonstrating that a noise limiting device has been installed into the amplification system of the proposed drive through to achieve the criteria. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 13) Deliveries Deliveries to the site are limited to the hours of 07:00 to 22:00, daily. |
As indicated |
| 14) Dampening of Grilles And Metal Plates All metal grilles, metal plates or similar
subject to vehicular traffic must be acoustically damped to prevent
environmental nuisance. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 15) Acoustic Barrier - General Erect an Acoustic
Canopy in the dimensions (3m high, 4m wide) outlined in the Approved Acoustic
Report No.4279 R2, prepared by Noise Measurements Service, received 15 December
2017 (relative to the finished RL of the drive through) along the northern
section of the site. The acoustic barrier must: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
15(a) Certification Submit to Development
Services certification from an appropriately qualified consultant that the
constructed acoustic barrier complies with the above
requirements. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 16) Plant and Equipment Certification Following the
installation of all mechanical plant and equipment (e.g. air conditioning,
mechanical ventilation and refrigeration equipment and heat pump hot water
systems), submit to Development Services certification that the plant and
equipment is adequately noise-attenuated and is in accordance with the criteria
of the relevant Brisbane Planning Scheme Codes/Policies. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 17) Acid Sulphate Soils Submit for the approval of Development Assessment, an Acid Sulfate Soils (ASS) Investigation Report and Management Plan. The ASS Management Plan must detail management measures of possible impacts of soil disturbance and demonstrate the disturbance impact will be appropriately managed. An ASS Investigation Report must be provided if soil disturbance (e.g. filling, excavation, drainage works, stripping of topsoil) is greater than 100m3. Prepare the ASS Investigation Report and Management Plan in accordance with the following:
- ASS Investigation Report and the ASSMP sections of City Plan - Potential and actual acid sulfate soils PSP; - State Planning Policy 2016 and State Planning Policy State Interest Guideline Water Quality; - Queensland Acid Sulfate Soil Technical Manual: Soil Management Guidelines. - Guidelines for sampling and analysis of lowland acid sulfate soils (ASS) in Queensland 1998 (Ahem et al, 1998); and - Queensland Acid Sulfate Soil Technical Manual: Soil Management Guidelines, Sampling Guidelines, and Laboratory Methods Guideline.
The Management Plan must be prepared by a suitably qualified and experienced professional, with the following qualifications: - qualifications in agricultural or environmental soils science with specialisation in soil chemistry and hydrology; - at least 2 years experience in acid sulfate soil management; and - accreditation by a professional organisation such as the Australian Society of Soil Science. |
"Prior to building works commencing, or prior to making application under Section 401 of SPA 2009, or prior to making application under Schedule 19 of SPR 2009, or where approved under IPA 1997, prior to survey plan endorsement, whichever comes first |
17(a) Certification Submit to Development Assessment certification from a Registered Professional Engineer Queensland, that the measures recommended in the Acid Sulfate Soils (ASS) Management Plan have been implemented into the development. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first |
17(b) Impliment Management Plan Implement and maintain the provisions of the approved Acid Sulfate Soils Management Plan. |
While site/operational works/building works is occurring and until all exposed soil areas are permanently stabilised against erosion |
| 18) Grant Easements Grant the following easement(s): |
As indicated |
18(a) Submit Plan of Subdivision and
Documentation (Non-Council Easement) Submit for the approval of Development Services, a
plan of subdivision showing the easement and the necessary easement
documentation to demonstrate compliance with the requirements of this
condition. |
As indicated |
18(b) Submit Plan of Subdivision and
Documentation (Council Easement) Submit for the approval of Development Services, a
plan of subdivision showing the easement and a request for Council to prepare
the necessary easement documentation to demonstrate compliance with the
requirements of this condition. |
As indicated |
18(c) Lodge Notated Plan and
Documentation Lodge
the plan of subdivision notated by Council pursuant to Schedule 18 of the
Planning Regulation 2017 and the necessary easement documentation with the
Registrar of Titles for the relevant Queensland State Government Authority. |
As indicated |
18(d) Submit Evidence of
Registration Submit
to Development Services evidence of the registration of the necessary easement
documentation. |
As indicated |
| 19) On-site Erosion (medium risk) Minimise on-site erosion and
the release of sediment or sediment laden stormwater from the site at all
times. |
As indicated |
19(a) Prepare Erosion and Sediment Control
Plan Prepare
Erosion and Sediment Control (ESC) Plan(s), and provide design certificates for
the site in accordance with the relevant Brisbane Planning Scheme Codes. |
As indicated |
19(b) Attend a Pre-Start
meeting Arrange and attend a pre-start meeting with an Erosion & Sediment
Control Officer from Council’s Compliance and Regulatory Services.
Requests are to be made when submitting copies of all required documentation,
including design certificates to: CARS-ESC@brisbane.qld.gov.au |
As indicated |
19(c) Implement Certified Erosion and
Sediment Control Plan Implement the certified ESC plan(s) to maintain compliance with all
parts of the relevant Brisbane Planning Scheme Codes, while site works are
occurring and until all exposed soil areas are permanently stabilised against
erosion. |
As indicated |
| 20) Information Signage Erect an "Information Sign" on the subject property in accordance with Council’s general requirements for signage and in accordance with the requirements outlined below: a) The sign should provide a brief description of the development
proposed; |
As indicated |
| 21) Retaining Walls Design and construct all
retaining walls and associated fences, in accordance with the relevant Brisbane
Planning Scheme Codes and including the following: |
Prior to site/operational/building work commencing |
21(a) Certification of Retaining
Walls For
retaining walls over 1.0m in height, obtain certification from a Registered
Professional Engineer Queensland that the design and construction of the
retaining wall and ancillary drainage is in accordance with this condition. |
As indicated |
| 22) Construction Management Plan - Major Carry out development in accordance with a Construction Management Plan prepared in accordance with the requirements of this condition. |
While site/operational/building work is occurring |
22(a) Submit Construction Management
Plan Submit for the approval of Development Services a Construction
Management Plan for the demolition (where in a Centre zone, the Mixed use zone
or where the demolition is otherwise assessable development), excavation and
construction phases of the approved development. Separate Construction
Management Plans may be appropriate for the individual components. The
Construction Management Plan must be in accordance with the relevant Brisbane
Planning Scheme Codes, Workplace Health and Safety Legislation, Environmental
Protection Act, the requirements of any Concurrence Agency, any other relevant
legislative requirements and the following. |
As indicated |
22(b) Construction Management Plan - Pre-
Start Meeting Arrange and attend a pre-start meeting with Development Services. |
As indicated |
22(c) Construction Management Plan -
Associated Activities in Road Reserve Obtain
relevant approvals to carry out any works required by the approved Construction
Management Plan, including the following, within the road reserve: |
As indicated |
22(d) Construction Management Plan -
Documentation on Site Legible copies of the approved Construction Management Plan and current
permits must be kept on site and be made available on request at all times. |
As indicated |
22(e) Construction Management Plan - Works to
be Performed Out of Hours Obtain approval from Development Services for any
work that is to be undertaken outside of normal business hours - 6:30am to
6:30pm, Monday to Saturday. |
As indicated |
22(f) Implement Approved Construction
Management Plan Carry
out the development in accordance with the approved Construction Management
Plan. |
As indicated |
| 23) Protect Existing Infrastructure Where there is existing infrastructure in the vicinity of the proposed
work, the new work must not damage or compromise the working ability of the
existing infrastructure. Where alterations to public utility mains, existing
mains, services or installations are necessitated by the development, prior to
alterations commencing, the developer must notify Council or the relevant
infrastructure provider and obtain agreement to the alterations. The developer
must meet the costs of the alterations. The alterations must be carried out in
accordance with the relevant Brisbane Planning Scheme Codes or infrastructure
providers requirements. |
While site/operational/building work is occurring |
23(a) As Constructed Drawings Where alterations to
existing infrastructure are required, submit to Development Services "As
Constructed" drawings showing all new and/or rectification works and an
asset register, prepared by a Registered Professional Engineer Queensland. |
While site/operational/building work is occurring |
23(b) Submit Certification Where alterations to existing
infrastructure are required, submit to Development Services certification from
a Registered Professional Engineer Queensland, confirming that the alterations
have been completed in accordance with the relevant Brisbane Planning Scheme
Codes and any other relevant infrastructure requirements. |
While site/operational/building work is occurring |
| 24) Certified Site Survey Levels Submit to Development
Services, "As Constructed" drawings prepared by a Registered
Surveyor. The Registered Surveyor must certify that the "As
Constructed" drawings are in accordance with the relevant Brisbane
Planning Scheme Codes and show finished surface level information over the
completed development. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 25) Filling and / or Excavation (Minor) Filling and/or excavation
works on the site must be in accordance with the relevant Brisbane Planning
Scheme Codes. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
25(a) Prepare Earthworks
Drawings Earthworks drawings must be prepared and certified by either: a
Registered Professional Engineer Queensland or a suitably qualified
geotechnical and structural consultant, in accordance with the relevant
Brisbane Planning Scheme Codes. |
As indicated |
25(b) Implement and Maintain the
Earthworks Carry
out and maintain the earthworks in accordance with the certified drawings. |
As indicated |
| 26) Repair Damage to Kerb, Footpath Or Road Repair any damage to the
existing kerb and channel, footpath or roadway (including removal of concrete
slurry from footways, roads, kerb and channel and stormwater gullies and
drainlines) and re-instate existing traffic signs and pavement markings that
have been removed or damaged during any works carried out in association with
the approved development. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 27) Remove Redundant Drainage Outlets Remove any redundant drainage outlets from the kerb and channel
including any associated pipe work across the footway and reinstate the kerb
and channel and the footway area in accordance with the relevant Brisbane
Planning Scheme Codes. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 28) Signs and Line Markings - Internal Prepare
signs and line markings drawings. The drawings must be prepared by a Registered
Professional Engineer Queensland. The Registered Professional Engineer
Queensland must certify that the drawings are in accordance with the relevant
Brisbane Planning Scheme Codes and the Manual of Uniform Traffic Control
Devices - Queensland Department of Transport and Main Roads -Transport
Operations (Road Use Management) Act 1995 showing the traffic signs, pavement
markings and traffic control devices. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
28(a) Implement Signs and Line
Marking Carry
out the signs and line marking in accordance with the certified
drawings. |
As indicated |
| 29) Access, Grades, Manoeuvring, Carparks, Signs and
Line Marking Construct access,
parking and manoeuvring for vehicles on site in accordance with the relevant
Brisbane Planning Scheme Codes, as indicated on the approved DRAWINGS AND
DOCUMENTS, including the following: iv. The driveway is widened to facilitate a through entry lane and a dedicated entry lane for the existing fast food drive thru. v. The queue length on the new drive thru lane can
accommodate 8 cars from the order station. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
29(a) Submit certification Submit to Development
Services, certification from a Registered Professional Engineer Queensland,
that the above requirements have been implemented in accordance with this
condition. |
As indicated |
| 30) Self Certified Structural Design in Flood Planning
Areas Building
works within the following Flood Planning Areas must be designed by a
Registered Professional Engineer Queensland. The Registered Professional
Engineer Queensland must certify that the works are structurally adequate to
resist hydrostatic, hydrodynamic and debris impact loads associated with
flooding up to the DFE: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
30(a) Submit Certification Submit to Development
Services certification from a Registered Professional Engineer Queensland that
the development has been designed and constructed in accordance with this
condition. |
As indicated |
| 31) Minimum Flood Planning Levels Design and construct
all proposed building pad levels, floor levels and ancillary structures to the
appropriate flood planning level with freeboard (where required) in accordance
with the relevant Brisbane Planning Scheme Codes. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
31(a) Submit Certification Submit to Development Services "As-Constructed" drawings
prepared by a Registered Surveyor. The Registered Surveyor must certify that
the development has been constructed in accordance with this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
| 32) Stormwater - Flood Study Construct the development in accordance with the Approved Flood Study prepared by Inertia Engineering (Job Reference Number – 7707, received 15 December 2017). |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
32(a) Certification Submit to Development
Services certification from a Registered Professional Engineer Queensland that
the development has been constructed in accordance with the approved flood
study. |
As indicated |
| 33) Flood Emergency Management Plan Prepare, implement and maintain a Flood Emergency
Management Plan (FEMP) in accordance with the requirements of this
condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
33(a) Prepare and Certify a Flood Emergency
Management Plan Submit
to Development Services a FEMP for the approved development prepared and
certified by a Registered Professional Engineer Queensland with experience in
flood risk management. |
As indicated |
33(b) Implement and Maintain the Certified
Flood Emergency Management Plan Implement and maintain the certified Flood Emergency
Management Plan. |
As indicated |
| 34) Refuse Collection - On Site Provide for the installation
and collection of waste/recycling bins by Brisbane City Council's Waste
Services. |
At all times |
34(a) Arrange Refuse Collection Arrange for the installation
of waste/recycling bins by Brisbane City Council's Waste Services and for the
subsequent collection of waste including recycling from the site. |
As indicated |
34(b) Indemnify Council The owner and any subsequent
owner must indemnify Council and its agents in respect of any damage to the
pavement and other driving surfaces. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 35) Refuse Storage - On Site Bulk Collection Provide a roofed and screened
waste enclosure to accommodate the type and quantity of bulk waste/recycling
bins required to service the development. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 36) Future Road Widening The proposed development must not prejudice the future road reserve widening along the Old Cleveland Rd frontage of the site by keeping the area clear of permanent improvements and structures associated with the approved development. The extent of the land to be set aside for a future road reserve widening is set out on the sketch plan RC16076 Issue 1 dated 17.01.18 forming part of the approved DRAWINGS AND DOCUMENTS. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
| 37) Ponding of Stormwater Carry out the approved development to ensure that
adjoining properties and roads are protected from ponding or nuisance from
stormwater as a result of the works. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 38) On Site Drainage - Minor Provide a stormwater
connection to all new or existing allotments and provide drainage
infrastructure to ensure stormwater run-off from all roof and developed surface
areas will be collected internally and piped in accordance with the relevant
Brisbane Planning Scheme Codes to “a lawful point of discharge” and
as shown on DRG NUMBER SK004 Revision 3 dated 11.12.2017. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
38(a) Submit As Constructed
Drawings Where
reconfiguring a lot, submit to Development Services "As Constructed"
drawings prepared by a Registered Professional Engineer Queensland. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
38(b) Submit Certification Where reconfiguring a lot, submit to Development Services certification
from a Registered Professional Engineer Queensland, confirming that the works
have been completed in accordance with this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
| 39) Service Conduits and Mains Provide and install all
service conduits and meet the cost of any alterations to public utility mains,
existing mains, services or installations that are required to carry out the
approved development. These works must be in accordance with the relevant
Brisbane Planning Scheme Codes, and include the following, where
applicable: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
39(a) Submit As Constructed
Drawings Submit to Development Services "As
Constructed" drawings, including an asset register, prepared by a
Registered Professional Engineer Queensland. |
As indicated |
39(b) Submit Certification Submit to Development
Services certification from a Registered Professional Engineer Queensland,
confirming that the works have been completed in accordance with the
requirements of this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 40) Telecommunications Submit to Development Services, certification from
an authorised telecommunications carrier/contractor, that the following works
and infrastructure have been undertaken and installed in accordance with
telecommunications industry standards: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 41) Agreement with Electricity Supplier Submit to Development Services, evidence of an agreement with an electricity supplier to provide necessary services to the development in accordance with the relevant Brisbane Planning Scheme Codes. Where development is proposed within an established area of overhead electricity supply and the electricity supplier determines that a property pole is the appropriate solution to supply electricity to the development, the developer must be responsible for the installation of the property pole(s). In the above circumstances, submit to Development Services, certification from the developer’s electrical consultant confirming that the above installation has been completed in accordance with the relevant AS/NZS Standards and the Queensland Electrical Connection and Metering Manual. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 42) Permanent Vehicle Crossover Provide a 10.8 metre
wide Type B1 permanent vehicle crossover to the Scrub Rd frontage of the site
and maintain the existing (exit only) vehicle crossover to the Old Cleveland
Road in accordance with the relevant Brisbane Planning Scheme Codes and located
as shown on the approved DRAWINGS AND DOCUMENTS. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 43) Food Hygiene All development involving the preparation, packing,
storing, handling, serving, selling or carrying of food requires that its
design, installation and operation be approved pursuant to the Food Act
2006. The premises must be
registered and the operator must hold a licence with Brisbane City Council to
operate the business under the above provisions. |
As indicated |
| 44) Construction Noise and Dust Emissions Pursuant to the Environmental
Protection Act 1994, all development involving the emission of noise and dust
from building and/or construction activities, must ensure that the emissions
are in accordance with the requirements of the Act. |
As indicated |
| 45) Concurrence Agency Conditions SARA as concurrence agency has advised it has no requirements as contained in the letter dated 1 February 2018. |
As indicated |
| 46) Cultural Heritage Aboriginal cultural heritage is protected under the Aboriginal Cultural Heritage Act 2003 This Act establishes a cultural heritage duty of care and in section 23(1) mandates that a person who carries out an activity must take all reasonable and practicable measures for ensuring activities are managed to avoid or minimise harm to Aboriginal cultural heritage. The Duty of Care Guidelines gazetted pursuant to the Aboriginal Cultural Heritage Act 2003 provide guidance on identifying and protecting Aboriginal cultural heritage to fulfil the duty of care. If you are unsure of your obligations contact the relevant Queensland State Government Department (Department of Aboriginal and Torres Strait Islander Partnerships). |
As indicated |
| 47) Equitable Access Provision must be made for equitable access for
persons with disabilities to and within the site in accordance with the
Queensland Anti-Discrimination Act 1991, the Federal Disability Discrimination
Act 1992 and Australian Standard AS1428 Parts 1-4, Australian Standard for
Access and Mobility and the National Construction Code. |
As indicated |
| 48) Water and Wastewater Services for water and wastewater (sewerage) are
no longer under the jurisdiction of Brisbane City Council. Authorisation to
connect the approved development to the water/wastewater networks and for
property service connections requires a Water Approval under the South-East
Queensland Water (Distribution and Retail Restructuring) Act 2009. Any
necessary Water Approval must be obtained from the relevant distributor-
retailer (currently operating as Queensland Urban Utilities for the Brisbane
City Council area). |
As indicated |
| 49) Damage to Trees on Adjoining Lots Please note that any damage caused to vegetation on adjoining lots as a result of exercising this development approval may result in civil action. |
As indicated |
| 50) Fire Ant Movement Controls To prevent the spread of fire
ants, the Queensland Government has implemented movement controls in areas of
Queensland (biosecurity zones) where this pest species has been detected. These
controls apply to individuals and commercial operators, and restrict the
movement of materials that could carry fire ants which include soil, turf,
potted plants, mulch, baled hay or straw, animal manures, mining or quarry
products. |
As indicated |
| Permit to Which These Conditions Relate: | DA - PA - Building Work |
| Activity(ies): | food and drink outlet |
| Stage: |
| 51) Further Development Permit required This Development Approval to carry out building work made assessable under the planning scheme for Brisbane does not include an assessment of building work against the requirements of the Building Act and does not permit building work to occur unless, prior to the commencement of any building work, a Development Permit(s) to carry out assessable building work under the Building Act has been issued. |
As indicated |
| Permit to Which These Conditions Relate: | DA - PA - Referral Agency for Building Work |
| Activity(ies): | Flood hazard area |
| Stage: |
| 52) Early Referral Agency Response (Flood hazard
area) Council has chosen to issue an early referral agency response under section 57 of the Planning Act 2016 for the proposed building work located within a Flood hazard area (Planning Regulation 2017, Schedule 9, Part 3, Division 2, Table 12). The response is attached to this decision notice. |
As indicated |