BRISBANE CITY COUNCIL'S APPROVAL PACKAGE.



APPLICATION DETAILS

This package relates to the application detailed below
Address of Site: 103 CAVENDISH RD COORPAROO QLD 4151
Real Property Description of Site: L268/269 RP.12739
Aspects of development and type of approval: DA - PA - Material Change of Use Development Permit - rooming accommodation
Council File Reference: A006924426
Permit Reference Number/s: DAMC471556625.
Package Status: APPROVED - Version 1 (12th of June, 2026 1:22:58 PM)
Package Generated: 12/06/2026


PROJECT TEAM

The assessment of this application has been undertaken by:
Richard DITCHFIELD
Technical Officer
Engineering Services South
richard.ditchfield@brisbane.qld.gov.au
34036751
Glyn CHISHOLM
Senior Landscape Architect
Landscape Architecture Team
Glyn.Chisholm@brisbane.qld.gov.au
07 3403 0117
Kirstin BURROWES
Senior Architect
Architecture Team
Kirstin.Burrowes@brisbane.qld.gov.au
0731785363
Diana SUN
Urban Planner
Planning Services South
Diana.Sun@brisbane.qld.gov.au
0731785179
Timothy BYRNE
Principal Urban Planner
Planning Services South
Timothy.Byrne@brisbane.qld.gov.au
(07) 3403 0314
Kellie HILTON
Senior Urban Planner
Planning Services South
kellie.hilton@brisbane.qld.gov.au
(07)3403 7226


DRAWINGS AND DOCUMENTS



The term 'drawings and documents' or similar expressions mean:
Drawing or Document Number Plan Date
Road Widening Plan RC16041 Issue 1 25-AUG-2025
Landscape Concept Plan Sheet No. 1 Issue C (Amended In Red 02-JUN-2026) 13-APR-2026 (Received)
Landscape Elevations Sheet No. 2 Issue C 13-APR-2026 (Received)
Landscpae Elevations Sheet No. 3 Issue C 13-APR-2026 (Received)
Proposed Planting Schedule Sheet No. 4 Issue C 13-APR-2026 (Received)
Proposed Planting Schedule Sheet No. 5 Issue C 13-APR-2026 (Received)
Site Plan 03 13-APR-2026 (Received)
Site Cover Plans 04 13-APR-2026 (Received)
Floor Plan 05 (Amended In Red 01-JUN-2026) 13-APR-2026 (Received)
Upper Floor Plan 06 13-APR-2026 (Received)
Elevations 07 13-APR-2026 (Received)
Elevations 08 13-APR-2026 (Received)
Landscape Plan 11 13-APR-2026 (Received)
Landscaping Details 12 13-APR-2026 (Received)
Site Services Plan SK01 Rev A 17-DEC-2025 (Received)


Advice

Please see the attached document(s) for any advices.

APPROVAL CONDITIONS



Permit to Which These Conditions Relate: DA - PA - Material Change of Use
Activity(ies): rooming accommodation
Stage: Rooming Accommodation (20 rooms)

General/Planning Requirements
 
Timing
1)   Approved Drawings and Documents

A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be available on site.

Note.  This condition is imposed to ensure compliance with the conditions of development approval. The copy of the conditions and drawings should be located in a site management office or with the site foreman.

 
While site/operational/building work is occurring
 
2)   Carry Out the Approved Development

Carry out the approved development generally in accordance with the approved DRAWINGS AND DOCUMENTS.

Note.  This development approval may include the location of fences, retaining walls and/or external walls of buildings on the boundary of a lot. This approval does not imply permission to enter neighbouring properties to carry out the construction (including associated drainage and earthworks) or maintenance activities.  Permission to enter neighbouring properties must be obtained from relevant property owners.

 
While site/operational/building work is occurring and then to be maintained
 
3)   Complete All Building Work

Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out generally in accordance with the approved DRAWINGS AND DOCUMENTS, and, where the building work is assessable development, in accordance with a current development approval.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
 
4)   Maintain the Approved Development

Maintain the approved development generally in accordance with the approved DRAWINGS AND DOCUMENTS, and any relevant Council engineering or other approval required by the conditions.

 
To be maintained
 
5)   Landscaping of Vacant Site

If construction for the approved development does not commence within 3 months of the demolition of the existing building(s) on site, the site must be landscaped in accordance with a landscape drawing that has been submitted to and approved by Development Services.

Timing:  Within 3 months of the demolition of the existing building(s).

 
As indicated
 
6)   Building Format Plan

Where the timing of a condition, or part thereof , states 'Prior to issue of Certificate of Occupancy/Final Inspection Certificate' or 'Prior to commencement of use' and the development involves the creation of a Building Format Plan, the timing of the condition, or part thereof, is taken to mean 'prior to Council's endorsement of any plan of subdivision'.

 
As indicated
 
7)   Bicycle Parking

Install and maintain secure bicycle parking and associated support facilities consistent with the approved DRAWINGS AND DOCUMENTS and in accordance with the relevant Brisbane Planning Scheme Codes.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
8)   Security Lighting

Install and maintain a suitable system of security lighting to operate from dusk to dawn within all areas where the public may gain access, including car parking areas, building entrances and vegetated areas

Ensure that all external lighting is in accordance with Australian Standard - AS4282- Control of the Obtrusive Effects of Outdoor Lighting so as not to cause nuisance to nearby residents or passing motorists.

Ensure lighting over publicly accessible pathways covered by permanent awnings is in accordance with Australian Standard - AS/NZS 1158.3.1 Lighting for roads and public spaces - Pedestrian area (Category P) lighting - Performance and design requirements.

Lighting must be maintained by the owner of the building in a safe and good working order.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
9)   Car Parking

The car parking within the premises must be maintained exclusively for the ancillary use of the development. The parking must not be made available to the general public and there must not be signage erected on or in the vicinity of the site advertising the availability of car parking to the general public.

 
To be maintained
 
10)   Limitation of Approval

This approval is limited to the use of the premises for Rooming Accommodation, as defined in the Brisbane City Plan 2014. Rooms are not to be self-contained units and are only to be provided with limited facilities for private use.

The premises is to accommodate a maximum of twenty (20) people at any one time.

The premises and all rooms are not to be used as short term accommodation.

 
To be maintained
 
Architecture
 
Timing
11)   External Details

External details of the building, facade treatment and external materials, colours and finishes must be consistent with the approved DRAWINGS AND DOCUMENTS.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
12)   Front Fence

Construct and maintain any front fence erected to the road frontage in accordance with the following:
- a maximum height of 1.2 metres above the front alignment ground level, if less than 50% transparency; or
- a maximum height of 1.5 metres above the front alignment ground level, with a minimum 50% transparency

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
13)   Overall Height

The overall height of the proposed building(s) must be in accordance with the floor and roof levels and overall height shown on the APPROVED DRAWINGS AND DOCUMENTS.

 
While site/operational/building work is occurring and then to be maintained
13(a) Submit Certification

Submit to Development Services certification from a registered surveyor confirming that the “as constructed” floor and roof levels and overall height are in accordance with the requirements of this condition.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
14)   Balconies/Verandahs/Terraces

No balconies/verandahs/terraces may be enclosed with solid balustrades, solid walls, fixed and/or operable, moveable or adjustable screening unless these features are clearly shown on the APPROVED DRAWINGS AND DOCUMENTS.

 

Note: Any Community Management Statement that may apply to this approval must contain a by-law which reflects the requirements of this condition.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
15)   Provide Pedestrian Prioritised Pathway

Provide a pedestrian prioritised pathway from the street frontage to the entry of the building. The pathway must be differentiated in colour and texture from the driveway surface.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
16)   Screen Air Conditioning and Other Plant Enclosures

Install and maintain suitable screening to all air conditioning, lift motor rooms, plant and service facilities located at the top of or on the external face of the building. The screening structures must be constructed from materials that are consistent with materials used elsewhere on the facade of the building. There must be no individual external air conditioning units.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
17)   Screening Multiple Dwelling / Dual Occupancy

Provide screening in accordance with the approved DRAWINGS AND DOCUMENTS and the following:

a) Where any windows of habitable rooms of the proposed dwelling(s) are within 2m at ground floor level or 9m above ground floor level of adjoining neighbouring dwellings' windows to habitable rooms, provide suitable screening in accordance with the following:

- Sill heights of 1.5m above floor level; or

- Fixed obscure glazing in any part of the window below 1.5m above floor level; or

- Fixed external screens, or

- Fencing to a minimum 1.8m above ground floor level (only applies to overlooking from windows at ground floor level).

b) Where a direct view is available from balconies, landings, terraces and decks of the proposed dwelling(s) into windows, balconies, landings, terraces and decks of an adjacent dwelling house, that view must be screened from floor level to a height 1.5m above floor level

c) Translucent screens, perforated or slatted panels, or fixed louvres that are permanent, durable and fixed and have a maximum of 25% openings, with a maximum opening of 50mm.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
Landscape Architecture and Open Space Planning
 
Timing
18)   Street Tree Replacement

Provide for replacement planting of the one (x1) existing street tree fronting the development site.

PROOF OF FULFILMENT
Contextual photographic evidence of installed replacement trees. OR, evidence in writing from Program Planning and Integration Arboriculture that an alternative arrangement has been made. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
18(a) Enter Arrangement

Enter into an arrangement with Public Space Operations Arboriculture Planning Team (PSO-Arb PLANNING) to pay the cost or undertake works, as agreed with PSO-Arb PLANNING, for the removal and replacement planting of the existing street tree(s) fronting the development site.

Timing: Prior to site/operational/building work commencing.

 
As indicated
18(b) Implement Arrangement

Implement the arrangement agreed with PSO-Arb PLANNING.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
19)   Streetscape Works - Subtropical Boulevard (Out of Centre)

Carry out streetscape improvement works including concrete path (where required by this condition), turf and street trees to the verge to a 3.75m wide Subtropical Boulevard (Out of Centre) standard in accordance with the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD), the requirements of this condition and the Infrastructure Design Planning Scheme Policy including sections 3.7.4.2.2 and 3.7.5.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
19(a) Install Concrete Path

Install a 1.8m wide broom finished standard Portland grey concrete path. The edge of the path is to be setback from the back of kerb 1.3m. The path is to transition to existing paths on verges that adjoin the development.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
As indicated
19(b) Submit As-Constructed Drawings

Submit to Development Services "As Constructed" plans including an asset register, checked by a Registered Professional Engineer Queensland, certifying that the concrete path works have been completed in accordance with relevant Brisbane Planning Scheme Codes/Policies.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
As indicated
19(c) Install Turf

Install turf to the full width of the verge excluding any concrete path required by this condition.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
As indicated
19(d) Street Tree(s)

Enter into and implement an arrangement with the Public Space Operations Arboriculture Planning Team (PSO-Arb PLANNING) in relation to the required provision of the street tree planting in accordance with the above sections of the Infrastructure Design Planning Scheme Policy, including the number, species, location, installation and maintenance of the required street tree(s) as determined by PSO-Arb PLANNING.

Note: Street trees should not be planted until all utilities have been installed.

Timing: Prior to issue of Certificate of Occupancy / Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
20)   Landscape the Site - Self Certification

Landscape the site in accordance with the requirements of this condition.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
20(a) Detailed Landscape Plan for Self- Certification

Prepare a Detailed Landscape Plan at a scale of 1:100 for all on-site landscape works including planting areas identified on the approved DRAWINGS AND DOCUMENTS. The plan must be prepared by a Qualified Landscape Architect and must comply with the relevant Brisbane Planning Scheme Codes.

The plan must include the following:
- Deep planting areas and dimensions as shown on the approved drawings planted with subtropical tree species that at maturity are complementary in scale and height to the building form and respond to the site location and design needs.
- Side and rear boundary landscape buffers are planted with columnar canopy form or screening tree/shrub species and associated groundcover species within the buffer areas and dimensions shown on the approved drawings.
- Site frontage landscape buffer provides shade and/or round canopy trees planted at suitable spacings along front boundary within the buffer areas and dimensions shown on the approved drawings.

- Planting media and mulch in accordance with AS4454 Composts, soil conditioners and mulches and AS 4419-2003 Soils for landscaping and garden use.
- Unless otherwise specified, trees provided as 45 litre stock or larger, staked and tied, and complying with Australian Standards.
- Plant selection and densities to achieve full surface coverage of garden beds within 2 years of planting.
- A reticulated drip irrigation system to all planting areas, with drainage connected to the stormwater system; the irrigation system must be connected to a non-mains water source.
- Details of a 12 week establishment period.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

PROOF OF FULFILMENT
A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
20(b) Certify Detailed Landscape Plan

On completion of the Detailed Landscape Plan, submit to Development Services a landscape design certification via the Landscape Design and Landscape Works Certification online form. Design certification is to be prepared by a Qualified Landscape Architect, certifying that the Detailed Landscape Plan complies with the requirements of this condition. The Certification must include a copy of the:


- Landscape design certification form.


- Certified detailed landscape plan.

NOTE: The landscape design and landscape works certification online form can be found by searching development application forms on Council's website.

Timing: Prior to building work commencing.

PROOF OF FULFILMENT
A copy of the landscape design certification form and certified detailed landscape plan

 
As indicated
20(c) Implement Certified Detailed Landscape Plan

Carry out the landscape work in accordance with the above certified detailed Landscape Plan.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
20(d) Certify Work

On completion of the landscape work, submit a Landscape Works Certification via the Landscape Design and Landscape Works Certification online form. The landscape works certification is to be prepared by a Qualified Landscape Architect, certifying that the landscape works comply with the certified Detailed Landscape Plan. The certification must include:


- a copy of the Landscape works certification form.

- a copy of the as-constructed landscape drawings.

- Photos of installed landscaping.


- Confirmation in writing from the landscape contractor who completed the works, that the works were completed in accordance with best practice landscape construction and horticultural standards.

NOTE: The landscape design and landscape works certification online form can be found by searching development application forms on Council's website.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

PROOF OF FULFILMENT
A copy of the Landscape works certification form, a copy of the as-constructed landscape drawings, photos of installed landscaping, confirmation in writing from the landscape contractor who completed the works, that the works were completed in accordance with best practice landscape construction and horticultural standards.

 
As indicated
20(e) Maintain Landscape Work

Maintain the landscape work, including deep planting, in accordance with the certified Detailed Landscape Plan.

Timing: To be maintained.

 
As indicated
 
Pollution
 
Timing
21)   Acoustic Fence - General

Erect a 2m high acoustic fence, (relative to the finished RL of the building pad) along the northern, southern and western property boundaries. The acoustic fence must:

- Be constructed of a material with a minimum surface area density of 12.5kg/m2;
- Be constructed of any aesthetically pleasing weather-resistant material such as earth mound, fibre cement, painted or treated timber, brick, concrete or a combination thereof;
- Be continuous and gap free.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
21(a) Certification

Submit to Development Services certification from a person who is a Member or eligible to be a Member of the Australian Acoustic Society that the constructed acoustic fence complies with the above requirements.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
22)   Tyre Noise Reduction

The driveways and carpark surfaces are to be appropriately treated/surfaced to reduce tyre noise impacts from the development.

PROOF OF FULFILMENT
Provide Certification that appropriate treatments/surfacing has been provided to the driveways and carpark areas to reduce tyre noise impact from the development. Certification must be provided by a Member or professional eligible to be a Member of the Australian Acoustic Society. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
23)   Buildings in Transport Noise Corridors - Acoustic Treatments

All new houses, townhouses, units, hotels and motels (Class 1-4 buildings) on sites located in a designated transport noise corridor are required to comply with the requirements of the Queensland Development Code Mandatory Part 4.4 - Buildings in Transport Noise Corridors. The buildings will need to achieve specific levels of noise mitigation through the use of appropriate materials for floors, walls, roofs, windows and doors for the relevant noise category.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
24)   Dampening of Grilles And Metal Plates

All metal grilles, metal plates or similar subject to vehicular traffic must be acoustically damped to prevent environmental nuisance.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
25)   Air Conditioning to Noise Affected Rooms

Air- conditioning/mechanical ventilation must be provided to all noise affected rooms as windows and doors are required to remain closed to maintain acceptable indoor noise levels.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
26)   Plant and Equipment Certification

Following the installation of all mechanical plant and equipment (e.g. gym equipment, air conditioning, mechanical ventilation and refrigeration equipment and heat pump hot water systems), submit to Development Services certification that the plant and equipment is adequately noise-attenuated and is in accordance with the criteria of the relevant Brisbane Planning Scheme Codes/Policies.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
27)   Acid Sulphate Soils

Submit for the approval of Development Assessment, an Acid Sulfate Soils (ASS) Investigation Report and Management Plan, where soil disturbance (e.g filling, excavation, drainage works, stripping of topsoil) is greater than 100m3 and the disturbance level is equal to or less than 5mAHD. The ASS Management Plan must detail management measures of possible impacts of soil disturbance and demonstrate the disturbance impact will be appropriately managed. Prepare the ASS Investigation Report and Management Plan in accordance with the following: 

 

- ASS Investigation Report and the ASSMP sections of City Plan - Potential and actual acid sulfate soils PSP; 

- State Planning Policy 2017 and State Planning Policy State Interest Guideline Water Quality;

- Queensland Acid Sulfate Soil Technical Manual: Soil Management Guidelines. - Guidelines for sampling and analysis of lowland acid sulfate soils (ASS) in Queensland 1998 (Ahem et al, 1998); and

- Queensland Acid Sulfate Soil Technical Manual: Soil Management Guidelines, Sampling Guidelines, and Laboratory Methods Guideline.  

 

The Management Plan must be prepared by a suitably qualified and experienced professional, with the following qualifications:  - qualifications in agricultural or environmental soils science with specialisation in soil chemistry and hydrology; - at least 2 years experience in acid sulfate soil management; and - accreditation by a professional organisation such as the Australian Society of Soil Science.

 
"Prior to building works commencing, or prior to making application under Section 401 of SPA 2009, or prior to making application under Schedule 19 of SPR 2009, or where approved under IPA 1997, prior to survey plan endorsement, whichever comes first
27(a) Certification

Submit to Development Assessment certification from a Registered Professional Engineer Queensland, that the measures recommended in the Acid Sulfate Soils (ASS) Management Plan have been implemented into the development.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first
27(b) Impliment Management Plan

Implement and maintain the provisions of the approved Acid Sulfate Soils Management Plan.

 
While site/operational works/building works is occurring and until all exposed soil areas are permanently stabilised against erosion
 
Engineering
 
Timing
28)   On-site Erosion (Low Risk)

Manage on-site erosion and the release of sediment or sediment laden water from the site at all times by implementing best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version). Including but not limited to:
(i) Drainage control measures must be implemented and maintained to minimise water flow across areas of exposed earth.
(ii) Sediment and erosion control measures must be implemented and maintained to prevent soil loss from earth disturbance areas and prevent deposition beyond earth disturbance areas.
(iii) No release of contaminants to land beyond on-site area of earth disturbance.

Note: Guidelines and factsheets to assist with this are available from the 'Healthy Waterways - Water by Design' website at http://hlw.org.au/initiatives/esc/house-sites

Timing: Prior to commencement of any earth disturbing activities and until all exposed soil areas are permanently stabilised against erosion.

 
As indicated
28(a) Provide Land Occupier Notification to Council

(i) Notify Council's ESC Team of proposed land occupier/s by sending an email to CARS-ESC@Brisbane.qld.gov.au

(ii) If the land is to be occupied by any person other than the registered landowner then advice must be provided to Council that confirms the name, contact information and the duration of any proposed occupation of the land.

Note: Occupier is any principal contractor occupying the land exercising a right under the development approval.

Timing: Prior to commencement of any earth disturbing activities.

 
As indicated
 
29)   Information Signage

Erect an information sign on the subject property in accordance with Council's general requirements for signage and in accordance with the requirements outlined below:
a) The sign should provide a brief description of the development proposed;
b) The sign is to list the name, postal and/or email address and a contact telephone number for the following parties (where relevant) that are undertaking work on the site:
- Developer;
- Project Coordinator;
- Architect/Building Designer;
- Builder;
- Civil Engineer;
- Civil Contractor/s; and
- Landscape Architect;
c) The lettering on the sign is to be at least 25 millimetres in height, be of regular weight and in sentence case;
d) The sign is to be a minimum size of 1,200 millimetres by 900 millimetres;
e) The maximum area of the sign is to be 2.0m2;
f) The sign is to be positioned as follows:
- located centrally along the road frontage of the site to Cavendish Road;
- located on or within 1.5 metres of the road frontage;
- mounted at least 300 millimetres above ground level; and
- clearly visible from the street for a pedestrian;
g) The sign is to contain no commercial or corporate advertising other than the name, logo or slogan of the parties outlined in part (b) of this condition;
h) The sign is to be non-illuminated; and
i) Both the sign and the supporting structure are to be made of weatherproof material and to be properly maintained at all times;

Timing: Prior to site works commencing and then to be maintained until completion of the development for all stages.

 
As indicated
 
30)   Construction Management Plan (Minor)

Carry out development in a method consistent with a Construction Management Plan (Minor) prepared in accordance with the requirements of this condition.

 
While site/operational/building work is occurring
30(a) Construction Management Plan (Minor) - Prepare Plan

Prepare a detailed Construction Management Plan (CMP) for the construction phase of the approved development.The Construction Management Plan must be in accordance with the relevant Brisbane Planning Scheme Codes and address the following:
(i) Provision for pedestrian management including acceptable alternative DDA compliant pedestrian routes (adjacent to or surrounding the site);
(ii) Existing and proposed kerbside allocation signs and line marking (such as bus stops, loading zones and parking meters and/or ticket dispensers);
(iii) Location of and impacts to any Council or other public utility or local authority's assets on or within external to the site;
(iv) Location and design of temporary vehicular construction access points, including frequency of use;
(v) Management and mitigation strategies for the impact of dust, noise and vibration upon adjoining and nearby properties;
(vi) Provision for loading and unloading of materials including the location of any remote loading sites;
(vii) Location of materials, structures, plant and equipment to be stored or placed on the construction site;
(viii) Location of proposed external hoardings and/or gantries, and including clearances to the impacts of this on existing street furniture and other footpath assets located within the verge as well as impacts on any existing advertising signage located either along or adjacent to the site frontage - this includes any potential obstruction of sight lines for such advertising (e.g. bus stops with advertising);
(ix) Location of proposed employee and visitor parking areas;
(x) Anticipated staging and programming;
(xi) Impacts of any actions proposed to address any of the above items or any actions resulting from construction of the development that will impact on existing street trees;
(xii) Complaint management processes to be implemented; and
(xiii) Compliance with the Management Plans Planning Scheme Policy and other relevant Planning Scheme Policies.

The Construction Management Plan must be supported by 'approval in principle' or written approvals from the relevant Council sections or other governing bodies responsible for any potentially impacted infrastructure.

The list of relevant infrastructure and contacts is available on Council's website - Search 'Construction Management Plan'.

Note: The Construction Management Plan is not required to be approved by Development Services.

Timing: Prior to site/operational/building work commencing.

 
As indicated
30(b) Construction Management Plan (Minor) - Submit Plan

Submit a copy of the Construction Management Plan to Council's Development Services Branch at the following mailbox: engineeringservices@brisbane.qld.gov.au quoting the BCC planning development approval reference number.

Timing: At least 10 days prior to site works commencing.

 
As indicated
30(c) Construction Management Plan (Minor) - Documentation on Site

Legible copies of the Construction Management Plan and current permits must be kept on site and be made available on request by Council at all times. The requirements of the CMP must be included in all induction of principal and subcontractors utilised in the development. An outline of the induction provided to contractors may be requested by Council to confirm compliance with this condition.

Timing: While site/operational/building work is occurring.

 
As indicated
30(d) Construction Management Plan - Works to be Performed Out of Hours

Obtain an approval from Development Services for any work that is proposed to be undertaken outside of normal business hours - 6:30am to 6:30pm, Monday to Saturday.

Timing: Prior to site/operational/building work commencing.

 
As indicated
30(e) Implement Construction Management Plan (Minor)

Carry out the development in accordance with the submitted Construction Management Plan.

 
While site/operational/building work is occurring
 
31)   Protect Existing Infrastructure

Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure.

Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations.

The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements.

 
While site/operational/building work is occurring
31(a) As Constructed Drawings - Alterations to Existing Infrastructure

Submit to Development Services As Constructed drawings showing all new and/or rectification works and an asset register, prepared by a Registered Professional Engineer Queensland.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

PROOF OF FULFILMENT
Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
32)   Remove Improvements & Obstructions from Truncation and Dedication

Remove all improvements (fences, gates, letter boxes, garden beds and plots and other constructed items, etc.) and obstructions (existing earth banks, vegetation, etc.) from the area of the dedicated road and reinstate the area as footway in accordance with the relevant Brisbane Planning Scheme Codes.

Any new or existing installations of electrical pillar boxes, pad mounted transformers (PMTs), water meters and the like, must be installed/relocated to their ultimate alignment relative to the new property boundary and clear of the usable footpath areas irrespective of the alignment of the existing services/conduits.

Note: The cost of moving services, utilities and assets is the responsibility of the Developer. The permission of the service, utility or asset owner will be required. Council permission is required if street trees, stormwater gullies/drains, and swales are affected. Urban Utilities permission is required if water supply and sewerage services are affected.

Standard utility alignments may be found on Council's 'Brisbane Standard Drawings' 1013 to 1016 inclusive.

PROOF OF FULFILMENT
Certification from a Registered Surveyor (Qld) or Registered Professional Engineer Queensland that the above work has been completed in accordance with this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
33)   Filling and / or Excavation (Minor)

Filling and/or excavation works on the site must be in accordance with the APPROVED PLANS and the relevant Brisbane Planning Scheme Codes.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
33(a) Prepare Earthworks Drawings

Earthworks drawings must be prepared and certified by a Registered Professional Engineer Queensland in accordance with the relevant Brisbane Planning Scheme Codes.

The drawings must include the following:
- The location of any cut and/or fill;
- The quantity of fill to be deposited and finished fill levels;
- The existing and future finished levels in reference to the Australian Height Datum (including cross- sections or long sections into the adjacent properties);
- maintenance of access roads to and from the site such that they remain free of all fill material and are cleaned as necessary
- preservation of all drainage structures from the effects of structural loading generated by the earthworks
- protection of adjoining properties and roads from adverse impacts as a result of proposed works.
- That all vehicles exiting from the site will be cleaned and treated so as to prevent material being tracked or deposited on public roads.

Timing: Prior to site/operational/building work commencing.

Note: The Earthworks drawings are not required to be submitted for Council approval.

 
As indicated
33(b) Implement and Maintain the Earthworks

Carry out and maintain the earthworks in accordance with the certified drawings.

Note: A copy of the certified Earthworks Drawings must be available on-site for inspection by Council Officers during these works.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
34)   Repair Damage to Kerb, Footpath or Road

Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
34(a) Interim Repairs

If at any time during the construction phase of the approved development, damage to the existing kerb and channel, footpath or roadway creates unsafe, unreasonable and/or not fit for purpose conditions as assessed by Council, interim repairs must be undertaken as directed by Program Planning and Integration.

Note: Any interim repairs required to be undertaken shall not be considered to satisfy the requirements of this condition for the permanent repair of the infrastructure prior to the issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

Timing: While site / operational / building works is occurring.

 
As indicated
 
35)   Retaining Walls

Design and construct all retaining walls and associated fences, in accordance with the relevant Brisbane Planning Scheme Codes and the following:

- All retaining walls including the footings, must be located wholly within the property boundaries of the site where works are occurring

- Runoff from surface drains and subsoil drainage associated with the retaining walls must be collected and connected to a lawful point of discharge (LPD) where possible. If no LPD is available the surface drains and sub-soil drainage must be designed, installed and discharged to ensure there is no ponding, nuisance or concentration of stormwater discharge to adjacent properties.

- Retaining walls to stabilise excavation must be set back from property boundaries to accommodate subsoil drainage without encroachment into the neighbouring property. This set back may vary depending on the height, structure and design of the retaining wall, surcharge loadings from neighbouring properties, and to provide a surface drain along the top of the retaining wall

- For retaining walls in excess of 1.0m in height:
- walls must be vertically and horizontally tiered by a ratio of 1:1 unless an alternative has been approved by Development Services
- walls must be designed and certified by a Registered Professional Engineer Queensland
- walls facing onto Council property (including the road reserve and parkland) must not be constructed from timber.

NOTE: Refer to City Plan 2014; Infrastructure Design Planning Scheme Policy (IDPSP) for Council’s definition of a LPD.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
35(a) Certification of Retaining Walls

For retaining walls over 1.0m in height, obtain certification from a Registered Professional Engineer Queensland that the design and construction of the retaining walls and ancillary drainage are in accordance with the requirements of this condition.

 
As indicated
 
36)   Access, Grades, Manoeuvring, Carparks, Signs and Line Marking

Construct and maintain access, parking and manoeuvring for vehicles on site in accordance with the relevant Brisbane Planning Scheme Codes, as indicated on the approved DRAWINGS AND DOCUMENTS, including the following:

i. A pavement of minimum Local road standard or equivalent surface material (including associated drainage) to the area on which motor vehicles will be driven and/or parked.

ii. Parking on the site for five cars, and for the loading and unloading of vehicle(s) within the site.

iii. A minimum of 2.3 metres height clearance to all undercover parking areas, including the entry and access to these areas. The minimum clear height must be measured to the lowest protrusion from the ceiling (e.g. fire sprinklers, services, lighting fixtures, signs, etc).

iv. A height clearance sign located at the entrance(s) to undercover car parking areas.

v. Prepare and implement signs and line markings drawings that show the internal paved areas signed and delineated in accordance with the approved drawings and documents. The drawings must be prepared and certified by a Registered Professional Engineer Queensland in accordance with the relevant Brisbane Planning Scheme Codes and the Manual of Uniform Traffic Control Devices.

PROOF OF FULFILMENT
Certification from a Registered Professional Engineer Queensland, that the above requirements have been implemented in accordance with this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first and then to be maintained.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
37)   Refuse Collection - Kerb Side (external road or internal private road)

Refuse and recycling bins for the development must be collected from the kerb side as shown on the APPROVED DRAWINGS AND DOCUMENTS.

Arrange for the installation of refuse/recycling bins and for the subsequent collection of refuse including recycling from the site by Brisbane City Council's Waste and Resource Recovery Services.

Timing: At the commencement of use and then to be maintained.

 
As indicated
 
38)   Refuse Storage - Kerb Side Collection

Provide a refuse storage area to accommodate the type and quantity of refuse and recycling bins required to service the development, as shown on the APPROVED DRAWINGS AND DOCUMENTS.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
39)   Land for Transport Network - Road (Trunk)

Dedicate as road the land shown as new road (trunk) on the APPROVED DRAWING NUMBER “103-105 Cavendish Road - RC16041 - Issue 1”, dated 25 August, 2025, for the Transport Network which forms part of LGIP ID COO-RC-006 in the Local Government Infrastructure Plan including the following:

i. A 6.000 metre widening along the full length of the Cavendish Road frontage of the site.

NOTE: This condition is imposed under section 128 of the Planning Act 2016.

 
Prior to commencement of use
39(a) Submit Plan of Subdivision

Submit for the approval of Development Services, a plan of subdivision showing the land to be dedicated for road to demonstrate compliance with the requirements of this condition.

Timing: As part of the submission of request pursuant to Schedule 18 of the Planning Regulation 2017 for Council's notation on the plan of subdivision necessary to comply with this condition.

PROOF OF FULFILMENT
The plan of subdivision is to clearly show the dimensions of the land dedication(s) required by this condition and certification by a registered surveyor (Qld) is to be provided that the plan of survey meets the requirements of this condition.

 
As indicated
39(b) Lodge Notated Plan

Lodge the plan of subdivision notated by Council pursuant to Schedule 18 of the Planning Regulation 2017 with the Registrar of Titles for the relevant Queensland State Government Authority.

Timing: Prior to commencement of use.

PROOF OF FULFILMENT
Evidence of the registration of the required plan of subdivision. Timing: Within one month of the registration of the plan of subdivision.

 
As indicated
 
40)   Remove Redundant Drainage Outlets

Remove any redundant drainage outlets from the kerb and channel including any associated pipe work across the footway and reinstate the kerb and channel and the footway area in accordance with the relevant Brisbane Planning Scheme Codes.

Note: Guidance for the preparation of drawings and/or documents to comply with this condition is provided in the Brisbane Planning Scheme Policies.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
41)   On Site Drainage - Minor

Provide a stormwater connection to the site and provide drainage infrastructure to ensure stormwater run-off from all roof and developed surface areas will be collected internally and piped in accordance with the relevant Brisbane Planning Scheme Codes to a lawful point of discharge and as shown on the Drawing Number 2532 SK01, Revision A, dated 24 November, 2025.

Note:

Where connections are adjacent to a driveway crossover and within the TPZ of a street tree, Rectangular Hollow Section (RHS) is to be used.

Note:


- Guidance for the preparation of drawings and/or documents to comply with this condition is provided in the Brisbane Planning Scheme Policies.


- Queensland Building and Construction Commission licensed hydraulic consultants may design the stormwater system for sites less than 2000m2 with an upstream catchment servicing no more than 4 residential lots. This excludes stormwater drainage design (including subsoil drainage) of basements in flood planning areas and the design of any onsite stormwater detention system.


- Where external works are required and infrastructure will be handed over to Council (e.g. Stormwater pipes 375mm or greater and/or manholes within the road reserve, etc), the applicant will be required to request a Pre-Start with Council and ensure all future owned Council assets follow the On/Off Maintenance process in accordance with Council's Infrastructure Installation & Construction Requirements Manual.

- Guidance for requesting a pre-start and co-ordinating the On/Off Maintenance process can be found on Council's website (https://www.brisbane.qld.gov.au/planning-and-building/applying-and- post-approval/on-and-off-maintenance-approvals).

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
42)   Service Conduits and Mains

Provide and install all service conduits, including street lighting as required by Council,  and meet the cost of any alterations to public utility mains, existing mains, services, street lighting or installations that are required to carry out the approved development. These works must be in accordance with the relevant Brisbane Planning Scheme Codes, and include the following, where applicable:
- the provision of all services and/or conduits along the full length of any rear allotment access or access easement.
- the breaking and/or relocation of any existing sewer combine drains.
- the relocation of any fire hydrant and/or valves from the development's vehicular footway crossings.
- the retention and/or relocation of any existing foul water lines that currently exist within the site.
- any new or existing installations of electrical pillar boxes, pad mounted transformers (PMTs), water reticulation mains, water meters and the like, must be installed/relocated to their ultimate alignment relative to the new property boundary and clear of the usable footpath areas irrespective of the alignment of the existing services/conduits.

Note:
- The cost of moving services, utilities and assets is the responsibility of the Developer. The permission of the service, utility or asset owner will be required. Council permission is required if street trees, stormwater gullies/drains, and swales are affected. Urban Utilities permission is required if water supply and sewerage services are affected.
- Standard utility alignments may be found on Council's 'Brisbane Standard Drawings' 1013 to 1016 inclusive.
- Applicants must liaise with the appropriate service authorities. Typical underground services and/or conduits to be constructed include power, phone, telecommunications, sewer (including private combine drains) stormwater and gas, if applicable.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
42(a) Submit Certification to Council

Submit to Development Services certification by a Registered Professional Engineer Queensland (RPEQ) that the works have been completed in accordance with the requirements of the condition. 

Note: Where rear allotment accesses or easements exist, the certification is to be supported by As-Constructed drawings certified by a RPEQ showing all services and/or conduits. Civil works are to be certified by a RPEQ (Civil) and electrical works are to be certified by a RPEQ (Electrical)

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

PROOF OF FULFILMENT
Certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the requirements of this condition. Note: Civil works are to be certified by a RPEQ(Civil) and electrical works are to be certified by a RPEQ (Electrical).

 
As indicated
 
43)   Telecommunications

Submit to Development Services, certification from an authorised telecommunications carrier/contractor, that the following works and infrastructure have been undertaken and installed in accordance with telecommunications industry standards:
- Provide telecommunications to the subject buildings, lead-in conduits and equipment space in a suitable location within the buildings, to suit the carrier of choice.
- If new pits and conduit infrastructure are required to be installed within the road reserve fronting the site, it must be suitably sized to cater for future installation of fibre optic cables.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
44)   Agreement with Electricity Supplier

Submit to Development Services, evidence of an agreement with an electricity supplier to provide necessary services to the development in accordance with the relevant Brisbane Planning Scheme Codes.

Where development is within an established area of overhead electricity supply and the electricity supplier determines that a property pole is the appropriate solution to supply electricity to the development, the developer must be responsible for the installation of the property pole(s).

In the above circumstances, submit to Development Services, certification from the developer's electrical consultant confirming that the above installation has been completed in accordance with the relevant AS/NZS Standards and the Queensland Electricity Connection Manual (QECM) and Queensland Electricity Metering Manual (QEMM).

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
45)   Redundant Driveway Crossover

Remove the redundant existing driveway crossover(s) on the frontage(s) of the site and reinstate the kerb and channel, road pavement, footways and footpaths in accordance with the relevant Brisbane Planning Scheme Codes.

Note:
For kerb and channel reinstatement, the existing channel is required to be removed and the kerb and channel reinstated in one pour.

Additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
46)   Permanent Driveway Crossover

Provide a 6.2 metre wide Type B1 permanent driveway crossover to the Cavendish Road frontage of the site in accordance with the relevant Brisbane Planning Scheme Codes and located as shown on the approved DRAWINGS AND DOCUMENTS.

Written consent must be obtained from Program, Planning and Integration Arboriculture (PPI Arb) prior to any works occurring that will either impact on or require removal of a street tree (this includes pruning, excavation or fill within the root zone/canopy of the tree).

At all times during construction of the crossover, safe pedestrian access along the site frontage must be maintained.

Note: No further driveway permit is required however additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
Standard Advice
 
Timing
47)   Construction Noise and Dust Emissions

Pursuant to the Environmental Protection Act 1994, all development involving the emission of noise and dust from building and/or construction activities, must ensure that the emissions are in accordance with the requirements of the Act. 

The Environmental Protection Act 1994 prescribes that: 

1. A person must not carry out building work in a way that makes an audible noise-

  - on a business day or Saturday, before 6.30a.m. or after 6.30p.m; or

  - on any other day, at any time. 

2. The reference in subsection (1) to a person carrying out building work-

  - includes a person carrying out building work under an owner-builder permit; and

  - otherwise does not include a person carrying out building work at premises used by the person only for residential purposes.    

Note:   A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management delegate Development Services.

 
As indicated
 
48)   Natural Asset Local Law (NALL) - Protected Vegetation on Public Land, Road or Park

The interference with or removal of protected vegetation on a public land or park requires a permit under the Natural Assets Local Law (NALL), issued by Program Planning and Integration (PPI).

Detailed arrangements must be made with PPI in relation to the works carried out on protected vegetation (including provision for tree removal and replacement tree planning costs as determined by the Arboriculture Team) prior to carrying out any works on protected vegetation. PPI Arboriculture Team can be contacted via BI- PPI-PLANNING-ARB@brisbane.qld.gov.au.

Note: All requirements of development approval conditions with timing stipulated as 'prior to site works commencing' (or equivalent) must be fulfilled before Council can issue a NALL permit.

 
As indicated
 
49)   Further Development Permit Required

Further Development Permit(s) to carry out assessable building work under the Building Act may be required.

 
As indicated
 
50)   Plumbing and Drainage Work

Pursuant to the Plumbing and Drainage Act 2018, any plumbing and drainage work must be carried out in compliance with the Plumbing and Drainage Regulation 2019.

Note: All new and existing plumbing services should be located within the lot that they serve.

Compliance assessable plumbing and drainage work requires approval by Brisbane City Council prior to the work being carried out.

 
As indicated
 
51)   Currency Period

The currency period for this development approval is stated in the Decision Notice and is expressed as a date.

This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016.

 
As indicated
 
52)   Equitable Access

Provision must be made during and after construction for equitable access for persons with disabilities to and within the site and on adjoining public areas, in accordance with the following:
- Queensland Anti-Discrimination Act 1991;
- Federal Disability Discrimination Act 1992;
- Australian Standards AS1428 Parts 1-4;
- Australian Standard for Access and Mobility; and
- National Construction Code.

 
As indicated
 
53)   Damage to Trees on Adjoining Land

Please note that any damage caused to vegetation on adjoining land as a result of exercising this development approval may result in an offence under other legislation (e.g. Natural Assets Local Law) and/or civil action

 
As indicated
 
54)   Fire Ant Movement Controls

To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected.

These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products.

Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014.

For further information contact the relevant Queensland State Government department on 13 QGOV.

 
As indicated
 
55)   Standard Building Regulations

This approval does not include assessment against the siting requirements of the Queensland Development Code. Should the approved development require a siting variation against the Queensland Development Code, an application for a Siting Variation must be submitted for the approval of Brisbane City Council - Development Services.

Note. This development approval does not commit to an approval of any siting variation shown on the approved drawings.

 
As indicated
 
56)   Seqwater

Council does not undertake assessment of Seqwater Bulk Water Supply Infrastructure in any planning application. Please contact Seqwater where development is located within 20 metres of Seqwater infrastructure on (07) 3035 5677 or consents@seqwater.com.au. Seqwater Trunk Water Mains convey bulk supply and operate at extremely high pressures. Seqwater seeks to eliminate risks to the community and to site personnel with works in the vicinity of Seqwater infrastructure.

 
As indicated
 
57)   Rooming Accommodation - Self-contained unit

This approval does not authorise any resident, tenant or provider to occupy a self-contained unit as defined under the Residential Tenancies and Rooming Accommodation Act 2008. Each room identified within the building/s is not to form a self-contained unit which includes a kitchen (cooking facilities), bathroom and toilet facilities.

 
As indicated
 
58)   Cultural Heritage

Aboriginal cultural heritage is protected under the Aboriginal Cultural Heritage Act 2003. This Act establishes a cultural heritage duty of care and in section 23(1) mandates that a person who carries out an activity must take all reasonable and practicable measures for ensuring activities are managed to avoid or minimise harm to Aboriginal cultural heritage.

 

The Duty of Care Guidelines gazetted pursuant to the Aboriginal Cultural Heritage Act 2003 provide guidance on identifying and protecting Aboriginal cultural heritage to fulfil the duty of care.

 

For further information contact the relevant Queensland State Government Department (Department of Aboriginal and Torres Strait Islander Partnerships).

 
As indicated
 
59)   In Principle support for street tree interference or removal

As street trees are protected vegetation, the interference with or removal of these trees requires a permit under the Natural Assets Local Law (NALL), issued by Program Planning and Integration (PPI). Development Services has sought preliminary advice from PPI regarding the identified removal/interference with existing street tree/s.

Removal/interference with one existing street tree identified on the approved plans fronting Duke Street is supported in principle for this development at this time. However, a separate NALL permit is required.

Detailed arrangements must be made with PPI in relation to the works carried out on protected vegetation (including provision for tree removal and replacement tree planning costs as determined by the Arboriculture Team) prior to carrying out any works on protected vegetation. PPI Arboriculture Team can be contacted via BI-CS-PPI-PLANNING- ARB@brisbane.qld.gov.au.

Note: All requirements of development approval conditions with timing stipulated as 'prior to site works commencing' (or equivalent) must be fulfilled before Council can issue a NALL permit.

 
As indicated
 
60)   Water and Wastewater

Services for water and wastewater (sewerage) are no longer under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections requires a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. Any necessary Water Approval must be obtained from the relevant distributor- retailer (currently operating as Queensland Urban Utilities for the Brisbane City Council area).

For the purpose of compliance assessment of a subdivision plan pursuant to Schedule 19 of the Sustainable Planning Regulation 2009 (whether in relation to a development permit for Reconfiguring a Lot or a Building Format Plan subsequent to a development permit for a Material Change of Use), documentary evidence, issued by the relevant distributor-retailer, must be provided to Council to verify that the conditions of any necessary Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009, have been complied with.

 
As indicated
 

** End of Package **