| Address of Site: | 26 YARALLA ST CHERMSIDE QLD 4032 27 BINKAR ST CHERMSIDE QLD 4032 U 1 BUNAVUE RESIDENCES 27 BINKAR ST CHERMSIDE QLD 4032 U 10 BUNAVUE RESIDENCES 26 YARALLA ST CHERMSIDE QLD 4032 U 2 BUNAVUE RESIDENCES 23 BUNA ST CHERMSIDE QLD 4032 U 3 BUNAVUE RESIDENCES 23 BUNA ST CHERMSIDE QLD 4032 U 4 BUNAVUE RESIDENCES 23 BUNA ST CHERMSIDE QLD 4032 U 5 BUNAVUE RESIDENCES 23 BUNA ST CHERMSIDE QLD 4032 U 6 BUNAVUE RESIDENCES 23 BUNA ST CHERMSIDE QLD 4032 U 7 BUNAVUE RESIDENCES 23 BUNA ST CHERMSIDE QLD 4032 U 8 BUNAVUE RESIDENCES 23 BUNA ST CHERMSIDE QLD 4032 U 9 BUNAVUE RESIDENCES 23 BUNA ST CHERMSIDE QLD 4032 |
| Real Property Description of Site: | L81 RP.67189 L56 RP.67189 L1 SP.346920 L10 SP.346920 L2 SP.346920 L3 SP.346920 L4 SP.346920 L5 SP.346920 L6 SP.346920 L7 SP.346920 L8 SP.346920 L9 SP.346920 |
| Aspects of development and type of approval: | DA - SPA - Material Change of Use Development Permit - Multiple Dwelling DA - SPA - Carry out Building Work Preliminary Approval under s241 - Multiple Dwelling DA - PA - Reconfiguring a Lot Development Permit - Subdivision of Land |
| Council File Reference: | A006963215 Permit Reference Number/s: DAMC334630416; DABW334752316; DARL438705823. |
| Package Status: | APPROVED - Version 6 (29th of May, 2026 3:20:55 PM) |
| Package Generated: | 01/06/2026 |
| Joe MCSHANE Principal Urban Planner Planning Services North CPAS-DS-PS-North@brisbane.qld.gov.au (07) 3407 1306 |
Leanne GREEN Principal Engineer Engineering Services Leanne.Green@brisbane.qld.gov.au |
Kathy BAGULEY Principal Urban Planner Planning Services North DSPlanningSupport@brisbane.qld.gov.au 07 3403 5510 |
| Barbara MARIC Urban Planner City Planning Barbara.Maric@brisbane.qld.gov.au (07) 3403 4249 |
Richard WELCH Senior Engineer Engineering Scoping Richard.Welch@brisbane.qld.gov.au 34070603 |
Angela BAZZANA Urban Planner Planning Services North angela.bazzana@brisbane.qld.gov.au (07) 3407 0886 |
| Callan BENNETT Principal Architect Architecture Team Callan.Bennett@brisbane.qld.gov.au 07 31780595 |
Gabriel DE LA JARA Senior Technical Officer Engineering Services North Gabriel.DeLaJara@brisbane.qld.gov.au 07 3403 9560 |
Lani ROBERTS Landscape Architect Landscape Architecture Team Lani.Roberts@brisbane.qld.gov.au 07 3403 8888 |
| Shiri RAJU Principal Engineer Engineering Services South shiri.raju@brisbane.qld.gov.au 3403 6544 |
Angela BAZZANA Urban Planner Planning Services North angela.bazzana@brisbane.qld.gov.au (07) 3407 0886 |
Mark VINEY Team Manager Planning Services North Mark.Viney@brisbane.qld.gov.au (07) 3403 0289 |
| Luke HADRICK Urban Planner Planning Services North Luke.Hadrick@brisbane.qld.gov.au (07) 3178 9403 |
Luke HADRICK Urban Planner Planning Services North Luke.Hadrick@brisbane.qld.gov.au (07) 3178 9403 |
Rhea CONNOLLY Principal Urban Planner Planning Services North Rhea.Connolly@brisbane.qld.gov.au 3178 0651 |
DRAWINGS AND DOCUMENTS
| Drawing or Document | Number | Plan Date |
|---|---|---|
| Site Plan (Carport) | SK1 (Amended In Red 22-MAY-2026) | 13-FEB-2026 (Received) |
| Plan View (Carport) | SK2 (Amended In Red 22-MAY-2026) | 13-FEB-2026 (Received) |
| Elevation (Carport) | SK3 (Amended In Red 22-MAY-2026) | 13-FEB-2026 (Received) |
| Concept Engineering Services Plan | SK02 P4 | 31-OCT-2023 (Received) |
| Ground Floor Plan | DD A.002 Issue F | 19-MAR-2024 (Received) |
| Site Plans | DD A.001 Issue E | 19-MAR-2024 (Received) |
| Upper Floor Plan | DD A.003 Issue D | 19-MAR-2024 (Received) |
| Roof Plan | DD A.004 Issue C | 19-MAR-2024 (Received) |
| Elevations - Building 1 | DD A.005 Issue C | 19-MAR-2024 (Received) |
| Elevations - Building 2 | DD A.006 Issue C | 19-MAR-2024 (Received) |
| Landscape Plan | Dwg No.1 Issue F | 19-MAR-2024 (Received) |
| Planting Schedule & Images | Dwg No.2 Issue F | 19-MAR-2024 (Received) |
| Landscape Notes | Dwg No.3 Issue F | 19-MAR-2024 (Received) |
| Landscape Details | Dwg No.4 Issue F | 19-MAR-2024 (Received) |
APPROVAL CONDITIONS
| Permit to Which These Conditions Relate: | DA - SPA - Material Change of Use |
| Activity(ies): | Multiple Dwelling |
| Stage: |
| 1) Time for Completion of Development The works authorised by this change application are limited to a patio roof structure attached to 27 Binkar Street also described as Lot 0 on SP346920 (Council address) as shown on approved DRAWINGS and DOCUMENTS. The works must be completed within 2 years of this change application taking effect. Note: If the development is started but not completed within the time specified above, the approval (to the extent it relates to any development not completed) lapses. |
As indicated |
| 2) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS
AND DOCUMENTS and the Development Approval Package must be available on
site. |
While site/operational/building work is occurring |
| 3) Carry Out the Approved Development Carry out the approved development generally in
accordance with the approved DRAWINGS AND DOCUMENTS. |
While site/operational/building work is occurring and then to be maintained |
| 4) Complete All Building Work Complete all building work associated with this
development approval, including work required by any of the conditions included
in the Development Approval Package. Such building work must be carried out
generally in accordance with the approved DRAWINGS AND DOCUMENTS, and, where
the building work is assessable development, in accordance with a current
development approval. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
| 5) Maintain the Approved Development Maintain the approved development generally in
accordance with the approved DRAWINGS AND DOCUMENTS, and any relevant Council
engineering or other approval required by the conditions. |
To be maintained |
| 6) Landscaping of Vacant Site If construction for
the approved development does not commence within 3 months of the demolition of
the existing building(s) on site, the site must be landscaped in accordance
with a landscape drawing that has been submitted to and approved by Development
Services. |
As indicated |
| 7) Erect Screen Fence Erect a screen fence along the southern (rear) boundary of the site as shown on the approved DRAWINGS AND DOCUMENTS. Unless an alternative design for the fence is agreed to with the owner of adjoining land, the screen fence must be 1.8 metres in height and be constructed from timber. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 8) Bicycle Parking Install and maintain secure bicycle parking and associated
support facilities consistent with the approved DRAWINGS AND DOCUMENTS and in
accordance with the relevant Brisbane Planning Scheme
Codes. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 9) Security Lighting Install and maintain a suitable system of security
lighting to operate from dusk to dawn within all areas where the public may
gain access, including car parking areas, building entrances and vegetated
areas |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 10) Car Parking The car parking within the premises must be maintained
exclusively for the ancillary use of the development. The parking must not be
made available to the general public and there must not be signage erected on
or in the vicinity of the site advertising the availability of car parking to
the general public. |
To be maintained |
| 11) External Details External details of the building, facade treatment and external
materials, colours and finishes must be consistent with the approved DRAWINGS
AND DOCUMENTS. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 12) Overall Height The overall height of the proposed building(s) must be in accordance with the floor and roof levels and overall height shown on the APPROVED DRAWINGS AND DOCUMENTS. |
While site/operational/building work is occurring and then to be maintained |
12(a) Submit Certification Submit to Development
Services certification from a registered surveyor confirming that the “as
constructed” floor and roof levels and overall height are in accordance
with the requirements of this condition. |
As indicated |
| 13) Provide Pedestrian Prioritised Pathway Provide a pedestrian prioritised
pathway from the street frontage to the front door of each unit. The pathway
must be differentiated in colour and texture from the driveway
surface. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 14) Balconies/Verandahs/Terraces No balconies/verandahs/terraces may be enclosed with solid balustrades, solid walls, fixed and/or operable, moveable or adjustable screening unless these features are clearly shown on the APPROVED DRAWINGS AND DOCUMENTS. Note: Any Community Management Statement that may apply to this approval must contain a by-law which reflects the requirements of this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 15) Driveway Material and Finishes Provide materials and
finishes to the driveway and external carparking surfaces that reduce the
visual impact of these areas when viewed from the street. One or a combination
of the following must be used: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 16) Screen Air Conditioning and Other Plant
Enclosures Install and maintain suitable screening to all air conditioning, lift motor rooms, plant and service facilities located at the top of or on the external face of the building. The screening structures must be constructed from materials that are consistent with materials used elsewhere on the facade of the building. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 17) Solar Screening Provide
solar screening in accordance with the approved DRAWINGS AND
DOCUMENTS. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 18) Screening Multiple Dwelling / Dual
Occupancy Provide screening in accordance with the approved DRAWINGS AND DOCUMENTS
and the following: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 19) Landscape the Site - Self Certification Landscape the site in accordance with the
requirements of this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
19(a) Prepare a detailed Landscape Plan for
Self Certification Prepare a detailed Landscape Plan
for areas nominated on the approved drawings, in accordance with the approved
Landscape Plans: Dwg Nos.1 to 4 Issue F, prepared
by Andrew Gold Landscape Architecture, the relevant Brisbane Planning Scheme
Codes/Policies and the following conditions: |
Prior to site/operational/building work commencing |
19(b) Construct Approved Work Construct landscaping in accordance with the
prepared detailed Landscape Plan. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first |
19(c) Certify Work On completion of
works, submit to Development Services certification from: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
19(d) Maintain Landscape Work Maintain the landscape generally in accordance
with the detailed plans. |
To be maintained |
| 20) Retain and Protect Existing Street Tree(s) Identify, retain and protect
the existing street trees unless otherwise agreed in writing with Asset
Services. |
While site/operational/building work is occurring |
20(a) Implement Protection
Measures Install
tree protection measures in accordance with Australian Standard - AS4970
Retention of Trees on Development Site. |
As indicated |
20(b) Maintain Protection
Measures Maintain
protection measures while development is occurring and remove protection
measures prior to commencement of the use. |
As indicated |
| 21) Street Tree Replacement Provide for replacement planting of an existing street tree on the Buna St frontage of the development site. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
21(a) Enter Arrangement Enter into an arrangement
with Asset Services to pay the cost or undertake works, as agreed with Asset
Services, for the removal and replacement planting of the existing street
tree(s) fronting the development site. |
As indicated |
21(b) Implement Arrangement Implement the arrangement
agreed with Asset Services. |
As indicated |
| 22) Streetscape Works - Neighbourhood Street Carry out streetscape improvement works
including to all street frontages concrete path (where required by this
condition), turf and street trees to the verge to the following
standards:
A
Neighbourhood Street Minor standard in accordance with the relevant Brisbane
Planning Scheme Codes, Brisbane Standard Drawings (BSD), the requirements of
this condition and the Infrastructure Design Planning Scheme Policy including
sections 3.7.4.4 and 3.7.5 Binkar St and Yaralla
St: A Neighbourhood Street Major standard in
accordance with the relevant Brisbane Planning Scheme Codes, Brisbane Standard
Drawings (BSD), the requirements of this condition and the Infrastructure
Design Planning Scheme Policy including sections 3.7.4.4 and
3.7.5 |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
22(a) Concrete Path Buna
St:
|
As indicated |
22(b) Submit As-Constructed
Drawings Submit
to Development Services "As Constructed" plans including an asset
register, checked by a Registered Professional Engineer Queensland, certifying
that the concrete path works have been completed in accordance with relevant
Brisbane Planning Scheme Codes/Policies.
Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
As indicated |
22(c) Turf Install turf to the full width of the
verge excluding any concrete path required by this
condition. Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
As indicated |
22(d) Street Tree(s) Contact the call centre on 3403 8888 and
request that Council undertake street tree planting in accordance with the
Infrastructure Design Planning Scheme Policy including section 3.7.5 to the
frontage of the development. Provide the call centre with the Development
Approval number and obtain a reference number for the phone call for your
record. Timing: Prior to issue of Certificate of Classification / Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation on the plan of subdivision (ROL) |
As indicated |
| 23) Hours of Operation - Vehicle movements Operation of trucks and
commercial vehicles (excluding waste collection vehicles) during the
operational phase of the development must only occur between 7am - 7pm Monday
to Saturday. |
To be maintained |
| 24) Dampening of Grilles And Metal Plates All metal grilles, metal plates or similar subject to vehicular traffic
must be acoustically damped to prevent environmental
nuisance. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 25) Acoustic Barrier - General Erect a 1.8 metre high
acoustic barrier, (relative to the finished RL of the building pad) along the
southern boundary (rear) where vehicle driveways, parking, manoeuvring and or hardstand
areas and the private open space area, as shown on the approved DRAWINGS
AND DOCUMENTS. The acoustic barrier must: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
25(a) Certification Submit to Development
Services certification from an appropriately qualified professional that the
constructed acoustic barrier complies with the above requirements. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 26) On-site Erosion (medium risk) Minimise on-site
erosion and the release of sediment or sediment laden stormwater from the site
at all times. Timing: While site works are
occurring and until all exposed soil areas are permanently stabilised against
erosion |
As indicated |
26(a) Prepare Erosion and Sediment Control
Plan Prepare Erosion and Sediment Control (ESC) Plan(s), and provide design
certificates for the site in accordance with the relevant Brisbane Planning
Scheme Codes. The plan(s) and design
certificates must be certified by a Certified Professional in Erosion and
Sediment Control (CPESC) or a Registered Professional Engineer Qld (RPEQ) with
suitable qualifications and experience in erosion and sediment
control. Documentary evidence demonstrating appropriate qualifications in
erosion and sediment control must be provided to the Council upon
request. At least 10 days prior to either
the pre-start meeting or commencement of site works, submit copies of design
certificates to Council’s Compliance and Regulatory Services
at: Timing: Prior to pre-start
meeting or commencement of any site works and to be maintained until all
exposed soil areas are permanently stabilised against
erosion |
As indicated |
26(b) Attend a Pre-Start
meeting Request and attend a pre-start meeting with an Erosion & Sediment
Control Officer from Council’s Compliance and Regulatory Services. Requests are to be made when submitting
copies of all required documentation, including design certificates to:
CARS-
ESC@brisbane.qld.gov.au Timing: Prior to
commencement of any site works causing exposure of soil. |
As indicated |
26(c) Implement Certified Erosion and
Sediment Control Plan Implement the certified ESC
plan(s) to maintain compliance with all parts of the relevant Brisbane Planning
Scheme Codes, while site works are occurring and until all exposed soil areas
are permanently stabilised against erosion.The
plan(s) and design certifications must be available on site at all times for
inspection by Council officers until all exposed soil areas are permanently
stabilised against erosion.Minimise on-site erosion
and the release of sediment or sediment laden stormwater from the site at all
times. |
As indicated |
| 27) Construction Management Plan (Minor) Carry out development in accordance with a Construction Management Plan (Minor) prepared in accordance with the requirements of this condition. |
Prior to site/operational/building work commencing |
27(a) Prepare Construction Management Plan
(Minor) Prepare a Construction Management Plan for the subject site.
The Construction Management Plan must be available on site at all times and must show, but not be limited to the following details where applicable, for the demolition (where in a Centre zone, the Mixed use zone or where the demolition is otherwise assessable development), excavation and construction phases of the approved development. Separate Construction Management Plans may be appropriate for the individual components:
- Provision of alternative pedestrian route/s, past or around the site - Existing and proposed kerbside allocation signs and line marking (such as bus stops, loading zones and parking meters and/or ticket dispensers) - Temporary vehicular access points - Management and mitigation strategies for the impact of dust, noise and vibration upon adjoining and nearby properties - Employee and visitor parking areas (if provided) - Provision for loading and unloading materials including the location of any remote loading sites - The location of materials, structures, plant and equipment to be stored or placed on the construction site - The anticipated staging and programming - Allowable work times as those set by the Queensland Environmental Protection Act 1994 (section 440). A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management Delegate Development Services.
The Construction Management Plan must be supported by Permits or written approvals from the relevant Council sections or other body listed below (where applicable to the Plan) to ensure all potential impacts to Council and other infrastructure have been addressed:
(i) Work Zones / Temporary Road Closures / Taxi Ranks - (Congestion Reduction Unit, Planned Incident Management / Temporary Road Closures); (ii) Full/Partial Footway-Footpath Closures – (Brisbane Infrastructure – Congestion Reduction Unit); (iii) Street Lighting - (Brisbane Infrastructure - Asset Services-City Lighting); (iv) City Cycle bike stations and JCDecaux Advertising Signage (including obstruction to sight lines for such advertising - owned by JCDecaux)- (Brisbane Infrastructure - Transport Planning and Strategy, Contract Management section); (v) Street Furniture (excluding bus stops) - (Brisbane Infrastructure, Transport Network Operations, Roads and Drainage); (vi) Waste Bins - (Brisbane Infrastructure, Waste Service); (vii) Bus Stops/Shelters - (Brisbane infrastructure - Transport Planning and Strategy- Strategic Planning; and Brisbane Transport - Network Planning & Bus Operations); (viii) Street Trees - (Brisbane Infrastructure - Asset Services - Arboriculture); (ix) Parking Meters/Spaces - (Brisbane Infrastructure - City Parking); (x) Traffic Signals - (Brisbane Infrastructure - Traffic Signals Operations); (xi) Stormwater Gullies/Pits etc - (Brisbane Infrastructure - Roads and Drainage); (xii) Other service providers - (e.g. Energex, Telstra, Optus, Queensland Urban Utilities, AGL).
Note: The Construction Management Plan is not required to be approved by Development Services. At least 10 days prior to commencement of site works, submit a copy of the Construction Management Plan to Council’s Development Services Branch at the following mailbox: engineeringservices@brisbane.qld.gov.au quoting the planning development approval reference number.
Timing: Prior to site/operational/building work commencing |
As indicated |
| 28) Retaining Walls Design and construct all
retaining walls and associated fences, in accordance with the relevant Brisbane
Planning Scheme Codes and including the following: |
Prior to site/operational/building work commencing |
28(a) Certification of Retaining
Walls For
retaining walls over 1.0m in height, obtain certification from a Registered
Professional Engineer Queensland that the design and construction of the
retaining wall and ancillary drainage is in accordance with this condition. |
As indicated |
| 29) Protect Existing Infrastructure Where there is existing infrastructure in the vicinity of the proposed work, then the new work must not damage or compromise the working ability of the existing infrastructure. Should it be required to provide alterations to public utility mains, existing mains, services or installations, then the developer is required to meet the costs of the alteration/s, which is to be carried out in accordance with the relevant Brisbane Planning Scheme Codes/Policies. |
While site works are occurring and then to be maintained |
29(a) As Constructed Drawings Submit to Development Services "As Constructed" drawings including an asset register, showing all new and/or rectification works required by this condition. These works must be certified by a Registered Professional Engineer of Queensland-Civil that they are in accordance with the relevant Brisbane Planning Scheme Codes/Policies and any other relevant infrastructure requirements. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 30) Filling and excavation (Minor) Undertake the works on the site in accordance
with the relevant Brisbane Planning Scheme
Codes/Policies. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
30(a) Prepare Earthworks Plan A suitably qualified person is to prepare
earthworks drawings in accordance with the relevant Brisbane Planning Scheme
Codes/Policies. The drawings are to
ensure the following: |
Prior to site/operational/building work commencing |
30(b) Implement and Maintain the Earthworks
Plan Implement and
maintain the earthworks plan in accordance with the relevant Brisbane Planning
Scheme Codes/Policies. A copy
of the Earthworks Plan must be available on-site for inspection by Council
Officers during these works. |
While site/operational/building work is occurring and then to be maintained |
| 31) Access, Grades, Manoeuvring, Carparks, Signs and
Line Marking Construct access, parking and manoeuvring for vehicles on site in
accordance with the relevant Brisbane Planning Scheme Codes, as indicated on
the approved DRAWINGS AND DOCUMENTS, including the following: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
31(a) Submit certification Submit to Development
Services, certification from a Registered Professional Engineer Queensland,
that the above requirements have been implemented in accordance with this
condition. |
As indicated |
| 32) Refuse Collection - Kerb Side (external road or
internal private road) Refuse
and recycling bins for the proposed development are to be collected from the
kerb side unless alternative refuse collection arrangements are made with
Brisbane City Council’s Waste Services. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 33) Repair Damage To Kerb, Footpath Or Road Repair any damage to existing
kerb and channel, footpath or roadway (including removal of concrete slurry
from footways, roads, kerb and channel and stormwater gullies and drainlines) and re-instatement existing traffic signs and
pavement markings that have been removed or damaged during any works carried
out in association with the approved development. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 34) On site drainage - Minor Provide a stormwater connection to all new or existing allotments and provide drainage infrastructure to ensure stormwater run-off from all roof and developed surface areas will be collected internally and piped in accordance with the relevant Brisbane Planning Scheme Codes/Policies to “a lawful point of discharge” and as shown on the Concept Engineering Services Plan, Drawing No. SK02 P4 (received dated 31/10/2023). Note: A lawful point of discharge is defined in the relevant Brisbane Planning Scheme Codes/Policies. A soakage pit certified by a Registered Professional Engineer of Queensland-Civil (RPEQ-Civil) may only be considered as an acceptable alternative point of discharge for single detached dwellings on existing lots. If roofwater reticulation is required for a reconfiguration, provide “As Constructed” plans prepared by an RPEQ or Registered Surveyor. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
| 35) Service Conduits and Mains Supply and install
all service conduits and meet the cost of any alterations to public utility
mains, existing mains, services or installations required in connection with
the approved development in accordance with the relevant Brisbane Planning
Scheme Codes/Policies. This
includes: Note: Applicants must liaise with the appropriate service
authorities. Typical underground services and/or conduits to be constructed
include power, phone, telecommunications, sewer (including private combine
drains) stormwater and gas, if applicable. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
35(a) As Constructed Drawings Submit to Development Services "As Constructed" drawings including an asset register, approved by a Registered Professional Engineer Queensland that are in accordance with the relevant Brisbane Planning Scheme Codes/Policies, and any other relevant infrastructure requirements, showing the works required by this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 36) Telecommunications Enter into an agreement with a telecommunication carrier to provide underground telecommunication services within and adjacent to the proposed development in accordance with the relevant Brisbane Planning Scheme Codes. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 37) Agreement with Electricity Supplier Enter into an agreement with an electricity
supplier to provide necessary services to the development in accordance with
the relevant Brisbane Planning Scheme Codes/Policies. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 38) Remove Redundant Crossover Remove the existing vehicular crossing(s) on the
frontage(s) of the site and reinstate the kerb and channel, road pavement,
footways and footpaths in accordance with the relevant Brisbane Planning Scheme
Codes/Policies. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 39) Permanent Driveway Crossover Lots 1 & 10: Provide 2 * 4.5metre wide Vehicular crossovers to the Binkar and Yaralla Street frontages of the site, as per BSD-2022; and Lots 2 - 9: Provide 4 * Shared and modified (widened to 6.7metres) Type A Vehicular crossovers to the Buna Street frontage of the site, generally as per BSD-2021; and in accordance with the relevant Brisbane Planning Scheme Codes and located as shown on the approved DRAWINGS AND DOCUMENTS.
To comply with Council’s standard drawings the vehicle crossovers must be perpendicular to the property alignment, to provide safe access to a property, and the edges of the crossover are to be parallel. The vehicle crossover (including the splays/tapers) must be constructed with the following clearances. If this cannot be achieved, the crossover width is to be reduced: - a minimum 700mm from power / light pole (in particular, on the Lot 2 Buna Street frontage); and - The crossovers and splays/tapers must not protrude across property boundaries, or the projection of such a boundary line to the carriageway, except where joint or shared property access is proposed, as per BSD-2022.
Written consent must be obtained from Program, Planning and Integration Arboriculture (PPI Arb) prior to any works occurring that will either impact on or require removal of a street tree (this includes pruning, excavation or fill within the root zone/canopy of the tree) At all times during construction of the crossover, safe pedestrian access along the site frontage must be maintained. Note: No further driveway permit is required however additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 40) Construction Noise and Dust Emissions Pursuant to the
Environmental Protection Act 1994, all development involving the emission of
noise and dust from building and/or construction activities, must ensure that
the emissions are in accordance with the requirements of the Act. The
Environmental Protection Act 1994 prescribes that: 1. A person
must not carry out building work in a way that makes an audible noise-
- on a business day or Saturday, before 6.30a.m. or after 6.30p.m; or
- on any other day, at any time.
2. The reference in subsection (1)
to a person carrying out building work- - includes a person carrying out building work under an owner-builder permit; and - otherwise does
not include a person carrying out building work at premises used by the person
only for residential purposes. Note: A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management delegate Development Services. |
As indicated |
| 41) Plumbing and Drainage Work Pursuant to the Plumbing and Drainage Act 2002,
any plumbing and drainage work must be carried out in compliance with the
Standard Plumbing and Drainage Regulation. Compliance assessable plumbing and
drainage work requires approval by Brisbane City Council prior to the work
being carried out. |
As indicated |
| 42) Equitable Access Provision must be made for equitable access for persons with
disabilities to and within the site in accordance with the Queensland Anti-
Discrimination Act 1991, the Federal Disability Discrimination Act 1992 and
Australian Standard AS1428 Parts 1-4, Australian Standard for Access and
Mobility and the National Construction Code. |
As indicated |
| 43) Water and Wastewater Services for water and wastewater (sewerage) are
no longer under the jurisdiction of Brisbane City Council. Authorisation to
connect the approved development to the water/wastewater networks and for
property service connections requires a Water Approval under the South-East
Queensland Water (Distribution and Retail Restructuring) Act 2009. Any
necessary Water Approval must be obtained from the relevant distributor-
retailer (currently operating as Queensland Urban Utilities for the Brisbane
City Council area). For the purpose of compliance assessment of a subdivision plan pursuant to Schedule 19 of the Sustainable Planning Regulation 2009 (whether in relation to a development permit for Reconfiguring a Lot or a Building Format Plan subsequent to a development permit for a Material Change of Use), documentary evidence, issued by the relevant distributor-retailer, must be provided to Council to verify that the conditions of any necessary Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009, have been complied with. |
As indicated |
| 44) Damage to Trees on Adjoining Lots Please note that any damage caused to vegetation on adjoining lots as a result of exercising this development approval may result in civil action. |
As indicated |
| 45) Fire Ant Movement Controls To prevent the spread of fire ants, the
Queensland Government has implemented movement controls in areas of Queensland
(biosecurity zones) where this pest species has been detected. These controls
apply to individuals and commercial operators, and restrict the movement of
materials that could carry fire ants which include soil, turf, potted plants,
mulch, baled hay or straw, animal manures, mining or quarry
products. Breaches of these controls can potentially
impact the community, economy and the environment. Penalties for non-compliance
with movement controls within fire ant biosecurity zones apply under the
Biosecurity Act 2014. If you are unsure of your obligations contact the relevant Queensland State Government Department (Biosecurity Queensland, Department of Agriculture and Fisheries) |
As indicated |
| Permit to Which These Conditions Relate: | DA - SPA - Carry out Building Work |
| Activity(ies): | Multiple Dwelling |
| Stage: |
| 46) Further Development Permit required This Preliminary Approval (Carrying Out Building Works) does not include assessment under the
Building Act and does not permit building work to occur. Prior to the commencement of any building work,
Development Permit(s) for Carrying Out Building Work
will be required. |
As indicated |
| 47) Construction Noise and Dust Emissions Pursuant to the
Environmental Protection Act 1994, all development involving the emission of
noise and dust from building and/or construction activities, must ensure that
the emissions are in accordance with the requirements of the Act. The
Environmental Protection Act 1994 prescribes that: 1. A person
must not carry out building work in a way that makes an audible noise-
- on a business day or Saturday, before 6.30a.m. or after 6.30p.m; or
- on any other day, at any time.
2. The reference in subsection (1)
to a person carrying out building work- - includes a person carrying out building work under an owner-builder permit; and - otherwise does
not include a person carrying out building work at premises used by the person
only for residential purposes. Note: A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management delegate Development Services. |
As indicated |
| 48) Plumbing and Drainage Work Pursuant to the Plumbing and Drainage Act 2002,
any plumbing and drainage work must be carried out in compliance with the
Standard Plumbing and Drainage Regulation. Compliance assessable plumbing and
drainage work requires approval by Brisbane City Council prior to the work
being carried out. |
As indicated |
| 49) Equitable Access Provision must be made for equitable access for persons with
disabilities to and within the site in accordance with the Queensland Anti-
Discrimination Act 1991, the Federal Disability Discrimination Act 1992 and
Australian Standard AS1428 Parts 1-4, Australian Standard for Access and
Mobility and the National Construction Code. |
As indicated |
| 50) Water and Wastewater Services for water and wastewater (sewerage) are
no longer under the jurisdiction of Brisbane City Council. Authorisation to
connect the approved development to the water/wastewater networks and for
property service connections requires a Water Approval under the South-East
Queensland Water (Distribution and Retail Restructuring) Act 2009. Any
necessary Water Approval must be obtained from the relevant distributor-
retailer (currently operating as Queensland Urban Utilities for the Brisbane
City Council area). For the purpose of compliance assessment of a subdivision plan pursuant to Schedule 19 of the Sustainable Planning Regulation 2009 (whether in relation to a development permit for Reconfiguring a Lot or a Building Format Plan subsequent to a development permit for a Material Change of Use), documentary evidence, issued by the relevant distributor-retailer, must be provided to Council to verify that the conditions of any necessary Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009, have been complied with. |
As indicated |
| 51) Damage to Trees on Adjoining Lots Please note that any damage caused to vegetation on adjoining lots as a result of exercising this development approval may result in civil action. |
As indicated |
| 52) Fire Ant Movement Controls To prevent the spread of fire ants, the
Queensland Government has implemented movement controls in areas of Queensland
(biosecurity zones) where this pest species has been detected. These controls
apply to individuals and commercial operators, and restrict the movement of
materials that could carry fire ants which include soil, turf, potted plants,
mulch, baled hay or straw, animal manures, mining or quarry
products. Breaches of these controls can potentially
impact the community, economy and the environment. Penalties for non-compliance
with movement controls within fire ant biosecurity zones apply under the
Biosecurity Act 2014. If you are unsure of your obligations contact the relevant Queensland State Government Department (Biosecurity Queensland, Department of Agriculture and Fisheries) |
As indicated |
| Permit to Which These Conditions Relate: | DA - PA - Reconfiguring a Lot |
| Activity(ies): | Subdivision of Land |
| Stage: |
| 53) Maintain the Approved Development Maintain the approved development generally in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions. |
At all times |
| 54) Approved Drawings and Documents A legible copy of the Council approved
DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained
on site and kept available for inspection by site workers and Council
officers. |
While site/operational/building work is occurring |
| 55) Carry Out the Approved Development Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS. Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners. |
While site/operational/building work is occurring |
| 56) Construction Prior to Notation on Plan of
Subdivision Development authorised by the associated development approval for Material Change of Use must be constructed to framing stage. |
Prior to Council's notation on the plan of subdivision |
| 57) Grant Easements Grant easement(s) as may be required. |
As indicated |
57(a) Submit Plan of Subdivision and
Documentation (other Easement) Submit to, and obtain approval from, Development Services, a plan of subdivision showing the easement and the necessary easement documentation to demonstrate compliance with the requirements of this condition. Note: Easements not in favour of the Brisbane City Council must have the necessary documentation prepared by the applicant's private solicitors. Timing: As part of the submission of the request pursuant to Schedule 18 of the Planning Regulation 2017 for Council's notation on the plan of subdivision necessary to comply with this condition or give effect to this approval. |
As indicated |
57(b) Lodge Notated Plan and
Documentation Lodge the plan of subdivision notated by Council pursuant to Schedule 18 of the Planning Regulation 2017 and the necessary easement documentation with the Registrar of Titles for the relevant Queensland State Government Authority. Timing: As part of the registration of the plan of subdivision notated by Council. PROOF OF FULFILMENT Evidence of the registration of the necessary easement documentation. Timing: Within one month of the registration of the easement documentation. |
As indicated |
| 58) Information Signage Erect an information sign on the subject property in accordance with Council's general requirements for signage and in accordance with the requirements outlined below: a) The sign should provide a brief description of the development proposed; b) The sign is to list the name, postal and/or email address and a contact telephone number for the following parties (where relevant) that are undertaking work on the site: - Developer;
c) The lettering on the sign is to be at least 25 millimetres in height, be of regular weight and in sentence case; d) The sign is to be a minimum size of 1,200 millimetres by 900 millimetres; e) The maximum area of the sign is to be 2.0m2; f) The sign is to be positioned as follows: - located centrally along each road frontage of the
site; g) The sign is to contain no commercial or corporate advertising other than the name, logo or slogan of the parties outlined in part (b) of this condition; h) The sign is to be non-illuminated; and i) Both the sign and the supporting structure are to be made of weatherproof material and to be properly maintained at all times. Timing: Prior to site works commencing and then to be maintained until completion of the development for all stages. |
As indicated |
| 59) Certified Site Survey Levels Submit to Development Services, "As Constructed" drawings prepared by a Registered Surveyor (Qld). The registered surveyor must certify that the "As Constructed" drawings are in accordance with the APPROVED PLANS and the relevant Brisbane Planning Scheme Codes and show finished surface level information over the completed development. Note: The survey information must show surface levels and site contours at 1 metre intervals. All levels must be shown as Reduced Levels to the "Australian Height Datum" (AHD). |
Prior to Council's notation on the plan of subdivision |
| 60) Standard Advice Disclaimer The following information is provided to the applicant as advice only and does not form part of the development approval conditions. This advice has been provided to inform the applicant of other obligations they may be required to comply with (under state legislation or local laws) prior to the approved activity commencing. |
As indicated |
| 61) Currency Period The currency period for this development approval is stated in the Decision Notice and is expressed as a date. This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016. |
As indicated |
| 62) Water and Wastewater Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. For further information about any necessary Water Approvals contact Urban Utilities. |
As indicated |
| 63) Fire Ant Movement Controls To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected. These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products. Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014. For further information contact the relevant Queensland State Government department on 13 QGOV. |
As indicated |