BRISBANE CITY COUNCIL'S APPROVAL PACKAGE.



APPLICATION DETAILS

This package relates to the application detailed below
Address of Site: 26 YARALLA ST CHERMSIDE QLD 4032
27 BINKAR ST CHERMSIDE QLD 4032
U 1 BUNAVUE RESIDENCES 27 BINKAR ST CHERMSIDE QLD 4032
U 10 BUNAVUE RESIDENCES 26 YARALLA ST CHERMSIDE QLD 4032
U 2 BUNAVUE RESIDENCES 23 BUNA ST CHERMSIDE QLD 4032
U 3 BUNAVUE RESIDENCES 23 BUNA ST CHERMSIDE QLD 4032
U 4 BUNAVUE RESIDENCES 23 BUNA ST CHERMSIDE QLD 4032
U 5 BUNAVUE RESIDENCES 23 BUNA ST CHERMSIDE QLD 4032
U 6 BUNAVUE RESIDENCES 23 BUNA ST CHERMSIDE QLD 4032
U 7 BUNAVUE RESIDENCES 23 BUNA ST CHERMSIDE QLD 4032
U 8 BUNAVUE RESIDENCES 23 BUNA ST CHERMSIDE QLD 4032
U 9 BUNAVUE RESIDENCES 23 BUNA ST CHERMSIDE QLD 4032
Real Property Description of Site: L81 RP.67189
L56 RP.67189
L1 SP.346920
L10 SP.346920
L2 SP.346920
L3 SP.346920
L4 SP.346920
L5 SP.346920
L6 SP.346920
L7 SP.346920
L8 SP.346920
L9 SP.346920
Aspects of development and type of approval: DA - SPA - Material Change of Use Development Permit - Multiple Dwelling
DA - SPA - Carry out Building Work Preliminary Approval under s241 - Multiple Dwelling
DA - PA - Reconfiguring a Lot Development Permit - Subdivision of Land
Council File Reference: A006963215
Permit Reference Number/s: DAMC334630416; DABW334752316; DARL438705823.
Package Status: APPROVED - Version 6 (29th of May, 2026 3:20:55 PM)
Package Generated: 01/06/2026


PROJECT TEAM

The assessment of this application has been undertaken by:
Joe MCSHANE
Principal Urban Planner
Planning Services North
CPAS-DS-PS-North@brisbane.qld.gov.au
(07) 3407 1306
Leanne GREEN
Principal Engineer
Engineering Services
Leanne.Green@brisbane.qld.gov.au
Kathy BAGULEY
Principal Urban Planner
Planning Services North
DSPlanningSupport@brisbane.qld.gov.au
07 3403 5510
Barbara MARIC
Urban Planner
City Planning
Barbara.Maric@brisbane.qld.gov.au
(07) 3403 4249
Richard WELCH
Senior Engineer
Engineering Scoping
Richard.Welch@brisbane.qld.gov.au
34070603
Angela BAZZANA
Urban Planner
Planning Services North
angela.bazzana@brisbane.qld.gov.au
(07) 3407 0886
Callan BENNETT
Principal Architect
Architecture Team
Callan.Bennett@brisbane.qld.gov.au
07 31780595
Gabriel DE LA JARA
Senior Technical Officer
Engineering Services North
Gabriel.DeLaJara@brisbane.qld.gov.au
07 3403 9560
Lani ROBERTS
Landscape Architect
Landscape Architecture Team
Lani.Roberts@brisbane.qld.gov.au
07 3403 8888
Shiri RAJU
Principal Engineer
Engineering Services South
shiri.raju@brisbane.qld.gov.au
3403 6544
Angela BAZZANA
Urban Planner
Planning Services North
angela.bazzana@brisbane.qld.gov.au
(07) 3407 0886
Mark VINEY
Team Manager
Planning Services North
Mark.Viney@brisbane.qld.gov.au
(07) 3403 0289
Luke HADRICK
Urban Planner
Planning Services North
Luke.Hadrick@brisbane.qld.gov.au
(07) 3178 9403
Luke HADRICK
Urban Planner
Planning Services North
Luke.Hadrick@brisbane.qld.gov.au
(07) 3178 9403
Rhea CONNOLLY
Principal Urban Planner
Planning Services North
Rhea.Connolly@brisbane.qld.gov.au
3178 0651


DRAWINGS AND DOCUMENTS



The term 'drawings and documents' or similar expressions mean:
Drawing or Document Number Plan Date
Site Plan (Carport) SK1 (Amended In Red 22-MAY-2026) 13-FEB-2026 (Received)
Plan View (Carport) SK2 (Amended In Red 22-MAY-2026) 13-FEB-2026 (Received)
Elevation (Carport) SK3 (Amended In Red 22-MAY-2026) 13-FEB-2026 (Received)
Concept Engineering Services Plan SK02 P4 31-OCT-2023 (Received)
Ground Floor Plan DD A.002 Issue F 19-MAR-2024 (Received)
Site Plans DD A.001 Issue E 19-MAR-2024 (Received)
Upper Floor Plan DD A.003 Issue D 19-MAR-2024 (Received)
Roof Plan DD A.004 Issue C 19-MAR-2024 (Received)
Elevations - Building 1 DD A.005 Issue C 19-MAR-2024 (Received)
Elevations - Building 2 DD A.006 Issue C 19-MAR-2024 (Received)
Landscape Plan Dwg No.1 Issue F 19-MAR-2024 (Received)
Planting Schedule & Images Dwg No.2 Issue F 19-MAR-2024 (Received)
Landscape Notes Dwg No.3 Issue F 19-MAR-2024 (Received)
Landscape Details Dwg No.4 Issue F 19-MAR-2024 (Received)


Advice

Please see the attached document(s) for any advices.

APPROVAL CONDITIONS



Permit to Which These Conditions Relate: DA - SPA - Material Change of Use
Activity(ies): Multiple Dwelling
Stage:  

General/Planning Requirements
 
Timing
1)   Time for Completion of Development

The works authorised by this change application are limited to a patio roof structure attached to 27 Binkar Street also described as Lot 0 on SP346920 (Council address) as shown on approved DRAWINGS and DOCUMENTS. The works must be completed within 2 years of this change application taking effect.

Note: If the development is started but not completed within the time specified above, the approval (to the extent it relates to any development not completed) lapses.

 
As indicated
 
2)   Approved Drawings and Documents

A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be available on site.

Note.  This condition is imposed to ensure compliance with the conditions of development approval. The copy of the conditions and drawings should be located in a site management office or with the site foreman.

 
While site/operational/building work is occurring
 
3)   Carry Out the Approved Development

Carry out the approved development generally in accordance with the approved DRAWINGS AND DOCUMENTS.

Note.  This development approval may include the location of fences, retaining walls and/or external walls of buildings on the boundary of a lot. This approval does not imply permission to enter neighbouring properties to carry out the construction (including associated drainage and earthworks) or maintenance activities.  Permission to enter neighbouring properties must be obtained from relevant property owners.

 
While site/operational/building work is occurring and then to be maintained
 
4)   Complete All Building Work

Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out generally in accordance with the approved DRAWINGS AND DOCUMENTS, and, where the building work is assessable development, in accordance with a current development approval.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
 
5)   Maintain the Approved Development

Maintain the approved development generally in accordance with the approved DRAWINGS AND DOCUMENTS, and any relevant Council engineering or other approval required by the conditions.

 
To be maintained
 
6)   Landscaping of Vacant Site

If construction for the approved development does not commence within 3 months of the demolition of the existing building(s) on site, the site must be landscaped in accordance with a landscape drawing that has been submitted to and approved by Development Services.

Timing:  Within 3 months of the demolition of the existing building(s).

 
As indicated
 
7)   Erect Screen Fence

Erect a screen fence along the southern (rear) boundary of the site as shown on the approved DRAWINGS AND DOCUMENTS. Unless an alternative design for the fence is agreed to with the owner of adjoining land, the screen fence must be 1.8 metres in height and be constructed from timber.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
8)   Bicycle Parking

Install and maintain secure bicycle parking and associated support facilities consistent with the approved DRAWINGS AND DOCUMENTS and in accordance with the relevant Brisbane Planning Scheme Codes.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
9)   Security Lighting

Install and maintain a suitable system of security lighting to operate from dusk to dawn within all areas where the public may gain access, including car parking areas, building entrances and vegetated areas

Ensure that all external lighting is in accordance with Australian Standard - AS4282- Control of the Obtrusive Effects of Outdoor Lighting so as not to cause nuisance to nearby residents or passing motorists.

Ensure lighting over publicly accessible pathways covered by permanent awnings is in accordance with Australian Standard - AS/NZS 1158.3.1 Lighting for roads and public spaces - Pedestrian area (Category P) lighting - Performance and design requirements.

Lighting must be maintained by the owner of the building in a safe and good working order.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
10)   Car Parking

The car parking within the premises must be maintained exclusively for the ancillary use of the development. The parking must not be made available to the general public and there must not be signage erected on or in the vicinity of the site advertising the availability of car parking to the general public.

 
To be maintained
 
Architecture
 
Timing
11)   External Details

External details of the building, facade treatment and external materials, colours and finishes must be consistent with the approved DRAWINGS AND DOCUMENTS.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
12)   Overall Height

The overall height of the proposed building(s) must be in accordance with the floor and roof levels and overall height shown on the APPROVED DRAWINGS AND DOCUMENTS.

 
While site/operational/building work is occurring and then to be maintained
12(a) Submit Certification

Submit to Development Services certification from a registered surveyor confirming that the “as constructed” floor and roof levels and overall height are in accordance with the requirements of this condition.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
13)   Provide Pedestrian Prioritised Pathway

Provide a pedestrian prioritised pathway from the street frontage to the front door of each unit. The pathway must be differentiated in colour and texture from the driveway surface.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
14)   Balconies/Verandahs/Terraces

No balconies/verandahs/terraces may be enclosed with solid balustrades, solid walls, fixed and/or operable, moveable or adjustable screening unless these features are clearly shown on the APPROVED DRAWINGS AND DOCUMENTS.

Note: Any Community Management Statement that may apply to this approval must contain a by-law which reflects the requirements of this condition.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
15)   Driveway Material and Finishes

Provide materials and finishes to the driveway and external carparking surfaces that reduce the visual impact of these areas when viewed from the street. One or a combination of the following must be used:

- Exposed aggregate;

- Concrete pavers; and/or

- Banding and patterns in the surface design.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
16)   Screen Air Conditioning and Other Plant Enclosures

Install and maintain suitable screening to all air conditioning, lift motor rooms, plant and service facilities located at the top of or on the external face of the building. The screening structures must be constructed from materials that are consistent with materials used elsewhere on the facade of the building.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
17)   Solar Screening

Provide solar screening in accordance with the approved DRAWINGS AND DOCUMENTS.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
18)   Screening Multiple Dwelling / Dual Occupancy

Provide screening in accordance with the approved DRAWINGS AND DOCUMENTS and the following:

a) Where any windows of habitable rooms of the proposed dwelling(s) are within 2m at ground floor level or 9m above ground floor level of adjoining neighbouring dwellings' windows to habitable rooms, provide suitable screening in accordance with the following:

- Sill heights of 1.5m above floor level; or

- Fixed obscure glazing in any part of the window below 1.5m above floor level; or

- Fixed external screens, or

- Fencing to a minimum 1.8m above ground floor level (only applies to overlooking from windows at ground floor level).

b) Where a direct view is available from balconies, landings, terraces and decks of the proposed dwelling(s) into windows, balconies, landings, terraces and decks of an adjacent dwelling house, that view must be screened from floor level to a height 1.5m above floor level

c) Translucent screens, perforated or slatted panels, or fixed louvres that are permanent, durable and fixed and have a maximum of 25% openings, with a maximum opening of 50mm.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
Landscape Architecture and Open Space Planning
 
Timing
19)   Landscape the Site - Self Certification

Landscape the site in accordance with the requirements of this condition.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
19(a) Prepare a detailed Landscape Plan for Self Certification

Prepare a detailed Landscape Plan for areas nominated on the approved drawings, in accordance with the approved Landscape Plans: Dwg Nos.1 to 4 Issue F, prepared by Andrew Gold Landscape Architecture, the relevant Brisbane Planning Scheme Codes/Policies and the following conditions:

PLANTING
- Provide columnar trees at 3m intervals where possible along site boundaries
- Provide columnar screening trees at 6m intervals along the rear boundary
- Provide a minimum 2m wide landscape strip along the frontage planted with trees, shrubs and groundcovers
- Provide flowering /shade trees within the frontage at maximum centres of 6m, provided as 25 litre stock or larger - staked and tied
- Provide shade trees to driveways and car parking to achieve a minimum 50% shade to hardstand areas
- Provide a 3 tier landscape structure to all landscape areas ie. Trees, shrubs and groundcovers

ADDITIONAL REQUIREMENTS
- Retain existing vegetation, except for environmental weeds, which are to be removed and replaced
- Trees to be retained are documented, protected and integrated into the landscape design in accordance with AS4970 (the Australian Standard for the Protection of Trees on Development sites)
- Maximise opportunities for stormwater infiltration into landscaped areas

SPECIFICATIONS
- Provide mulch and soil to meet AS4454 and AS4419
- Ensure that soil media is ameliorated to increase its water holding capabilities.

Note: The requirements outlined by this condition do not require an application to be made with Council.

 
Prior to site/operational/building work commencing
19(b) Construct Approved Work

Construct landscaping in accordance with the prepared detailed Landscape Plan.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first
19(c) Certify Work

On completion of works, submit to Development Services certification from:

-  A registered Landscape Architect or Landscape Designer that the detailed Landscape Plan complies with the City Plan (Form CC10616 Landscape Design Certificate); and
-  A registered Landscape Architect and registered Landscape Contractor that the completed landscape work complies with the detailed Landscape Plan, (Form CC10613 Landscape Works Certificate).

Note: A copy of the as-constructed detailed Landscape Plan must accompany the completed Compliance Certificates.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
19(d) Maintain Landscape Work

Maintain the landscape generally in accordance with the detailed plans.

 
To be maintained
 
20)   Retain and Protect Existing Street Tree(s)

Identify, retain and protect the existing street trees unless otherwise agreed in writing with Asset Services.

Note: Street trees are protected under the Natural Assets Local Law. Street trees must not be removed or pruned without prior approval from Asset Services.

 
While site/operational/building work is occurring
20(a) Implement Protection Measures

Install tree protection measures in accordance with Australian Standard - AS4970 Retention of Trees on Development Site.

There must be no excavation, filling or storage of materials or plant within the drip line of the tree(s).

Note: If fencing is proposed to protect street trees, a permit to temporarily occupy the footway will be required from Compliance and Regulatory Services.

Timing: Prior to site / operational / building work occurring

 
As indicated
20(b) Maintain Protection Measures

Maintain protection measures while development is occurring and remove protection measures prior to commencement of the use.

Timing: While to site / operational / building work is occurring

 
As indicated
 
21)   Street Tree Replacement

Provide for replacement planting of an existing street tree on the Buna St frontage of the development site.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
21(a) Enter Arrangement

Enter into an arrangement with Asset Services to pay the cost or undertake works, as agreed with Asset Services, for the removal and replacement planting of the existing street tree(s) fronting the development site.

Timing: Prior to site / operational / building work commencing

 
As indicated
21(b) Implement Arrangement

Implement the arrangement agreed with Asset Services.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)

 
As indicated
 
22)   Streetscape Works - Neighbourhood Street

Carry out streetscape improvement works including to all street frontages concrete path (where required by this condition), turf and street trees to the verge to the following standards:


Buna St:

A Neighbourhood Street Minor standard in accordance with the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD), the requirements of this condition and the Infrastructure Design Planning Scheme Policy including sections 3.7.4.4 and 3.7.5

 

Binkar St and Yaralla St:

A Neighbourhood Street Major standard in accordance with the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD), the requirements of this condition and the Infrastructure Design Planning Scheme Policy including sections 3.7.4.4 and 3.7.5

 

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
22(a) Concrete Path

Buna St:
Install a 1.2m wide broom finished standard Portland grey concrete path. The edge of the path is to be setback a minimum of 0.8m from the back of kerb. The path is to transition to existing paths on verges that adjoin the development.


Binkar St and Yaralla St:
Install a 1.2m wide broom finished standard Portland grey concrete path. The edge of the path is to be setback a minimum of 0.8m from the back of kerb. The path is to transition to existing paths on verges that adjoin the development.


Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)

 
As indicated
22(b) Submit As-Constructed Drawings

Submit to Development Services "As Constructed" plans including an asset register, checked by a Registered Professional Engineer Queensland, certifying that the concrete path works have been completed in accordance with relevant Brisbane Planning Scheme Codes/Policies. 

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)

 
As indicated
22(c) Turf

Install turf to the full width of the verge excluding any concrete path required by this condition.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)

 
As indicated
22(d) Street Tree(s)

Contact the call centre on 3403 8888 and request that Council undertake street tree planting in accordance with the Infrastructure Design Planning Scheme Policy including section 3.7.5 to the frontage of the development. Provide the call centre with the Development Approval number and obtain a reference number for the phone call for your record.

Timing: Prior to issue of Certificate of Classification / Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation on the plan of subdivision (ROL)

 
As indicated
 
Pollution
 
Timing
23)   Hours of Operation - Vehicle movements

Operation of trucks and commercial vehicles (excluding waste collection vehicles) during the operational phase of the development must only occur between 7am - 7pm Monday to Saturday.

 
To be maintained
 
24)   Dampening of Grilles And Metal Plates

All metal grilles, metal plates or similar subject to vehicular traffic must be acoustically damped to prevent environmental nuisance.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
25)   Acoustic Barrier - General

Erect a 1.8 metre high acoustic barrier, (relative to the finished RL of the building pad) along the southern boundary (rear) where vehicle driveways, parking, manoeuvring and or hardstand areas and the private open space area, as shown on the approved DRAWINGS AND DOCUMENTS. The acoustic barrier must:

- Be constructed of a material with a minimum surface area density of 10kg/m2
- Be constructed of an aesthetically pleasing weather-resistant material such as earth mound, fibre cement, painted or treated timber, brick, concrete or a combination thereof
- Have returns at any opening or provide some other means of blocking line of site from source to receiver such that the effectiveness of the barrier is not reduced
- Be continuous and gap free

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
25(a) Certification

Submit to Development Services certification from an appropriately qualified professional that the constructed acoustic barrier complies with the above requirements.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
Engineering
 
Timing
26)   On-site Erosion (medium risk)

Minimise on-site erosion and the release of sediment or sediment laden stormwater from the site at all times.

Timing: While site works are occurring and until all exposed soil areas are permanently stabilised against erosion

 
As indicated
26(a) Prepare Erosion and Sediment Control Plan

Prepare Erosion and Sediment Control (ESC) Plan(s), and provide design certificates for the site in accordance with the relevant Brisbane Planning Scheme Codes.

The plan(s) and design certificates must be certified by a Certified Professional in Erosion and Sediment Control (CPESC) or a Registered Professional Engineer Qld (RPEQ) with suitable qualifications and experience in erosion and sediment control.

Documentary evidence demonstrating appropriate qualifications in erosion and sediment control must be provided to the Council upon request.

At least 10 days prior to either the pre-start meeting or commencement of site works, submit copies of design certificates to Council’s Compliance and Regulatory Services at:

CARS-ESC@brisbane.qld.gov.au

Timing: Prior to pre-start meeting or commencement of any site works and to be maintained until all exposed soil areas are permanently stabilised against erosion

 
As indicated
26(b) Attend a Pre-Start meeting

Request and attend a pre-start meeting with an Erosion & Sediment Control Officer from Council’s Compliance and Regulatory Services.  Requests are to be made when submitting copies of all required documentation, including design certificates to: CARS- ESC@brisbane.qld.gov.au

Timing: Prior to commencement of any site works causing exposure of soil.

 
As indicated
26(c) Implement Certified Erosion and Sediment Control Plan

Implement the certified ESC plan(s) to maintain compliance with all parts of the relevant Brisbane Planning Scheme Codes, while site works are occurring and until all exposed soil areas are permanently stabilised against erosion.The plan(s) and design certifications must be available on site at all times for inspection by Council officers until all exposed soil areas are permanently stabilised against erosion.Minimise on-site erosion and the release of sediment or sediment laden stormwater from the site at all times.
Timing: While site works are occurring and until all exposed soil areas are permanently stabilised against erosion.

 

 
As indicated
 
27)   Construction Management Plan (Minor)

Carry out development in accordance with a Construction Management Plan (Minor) prepared in accordance with the requirements of this condition.

 
Prior to site/operational/building work commencing
27(a) Prepare Construction Management Plan (Minor)

Prepare a Construction Management Plan for the subject site.

 

The Construction Management Plan must be available on site at all times and must show, but not be limited to the following details where applicable, for the demolition (where in a Centre zone, the Mixed use zone or where the demolition is otherwise assessable development), excavation and construction phases of the approved development. Separate Construction Management Plans may be appropriate for the individual components:

 

-  Provision of alternative pedestrian route/s, past or around the site

-   Existing and proposed kerbside allocation signs and line marking (such as bus stops, loading zones and parking meters and/or ticket dispensers)

-  Temporary vehicular access points

-  Management and mitigation strategies for the impact of dust, noise and vibration upon adjoining and nearby properties

-   Employee and visitor parking areas (if provided)

-   Provision for loading and unloading materials including the location of any remote loading sites

-  The location of materials, structures, plant and equipment to be stored or placed on the construction site

-  The anticipated staging and programming

-  Allowable work times as those set by the Queensland Environmental Protection Act 1994 (section 440).  A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management Delegate Development Services.

 

The Construction Management Plan must be supported by Permits or written approvals from the relevant Council sections or other body listed below (where applicable to the Plan) to ensure all potential impacts to Council and other infrastructure have been addressed:

 

(i) Work Zones / Temporary Road Closures / Taxi Ranks - (Congestion Reduction Unit, Planned Incident Management / Temporary Road Closures);

(ii) Full/Partial Footway-Footpath Closures – (Brisbane Infrastructure – Congestion Reduction Unit);

(iii) Street Lighting - (Brisbane Infrastructure - Asset Services-City Lighting);

(iv) City Cycle bike stations and JCDecaux Advertising Signage (including obstruction to sight lines for such advertising - owned by JCDecaux)- (Brisbane Infrastructure - Transport Planning and Strategy, Contract Management section);

(v) Street Furniture (excluding bus stops) - (Brisbane Infrastructure, Transport Network Operations, Roads and Drainage);

(vi) Waste Bins - (Brisbane Infrastructure, Waste Service);

(vii) Bus Stops/Shelters - (Brisbane infrastructure - Transport Planning and Strategy- Strategic Planning; and Brisbane Transport - Network Planning & Bus Operations);

(viii) Street Trees - (Brisbane Infrastructure - Asset Services - Arboriculture);

(ix) Parking Meters/Spaces - (Brisbane Infrastructure - City Parking);

(x) Traffic Signals - (Brisbane Infrastructure - Traffic Signals Operations);

(xi) Stormwater Gullies/Pits etc - (Brisbane Infrastructure - Roads and Drainage);

(xii) Other service providers - (e.g. Energex, Telstra, Optus, Queensland Urban Utilities, AGL).

 

Note: The Construction Management Plan is not required to be approved by Development Services.

At least 10 days prior to commencement of site works, submit a copy of the Construction Management Plan to Council’s Development Services Branch at the following mailbox: engineeringservices@brisbane.qld.gov.au quoting the planning development approval reference number.

 

Timing: Prior to site/operational/building work commencing

 
As indicated
 
28)   Retaining Walls

Design and construct all retaining walls and associated fences, in accordance with the relevant Brisbane Planning Scheme Codes and including the following:

- All retaining walls including the footings, must be located wholly within the property boundary of the site where works are occurring
- Retaining walls to stabilise excavation must be set back off property boundaries to accommodate subsoil drainage without encroachment into the neighbouring property. This set back may vary depending on the height, structure and design of the retaining wall, including loadings from neighbouring properties, and to provide a surface drain along the top of the retaining wall
- Retaining walls that are greater than 1.0m in height must be vertically and horizontally tiered by a ratio of 1:1 unless an alternative has been approved by Development Services
- Runoff from surface drains and subsoil drainage associated with the retaining wall must be collected and conveyed to a lawful point of discharge and must not cause any ponding, nuisance or disturbance to adjacent property owners
- Retaining walls in excess of 1.0m in height must be designed and certified by a Registered Professional Engineer Queensland
- Retaining walls facing onto Council property (including the road reserve and parkland) must not be constructed from timber.

 
Prior to site/operational/building work commencing
28(a) Certification of Retaining Walls

For retaining walls over 1.0m in height, obtain certification from a Registered Professional Engineer Queensland that the design and construction of the retaining wall and ancillary drainage is in accordance with this condition.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)

 
As indicated
 
29)   Protect Existing Infrastructure

Where there is existing infrastructure in the vicinity of the proposed work, then the new work must not damage or compromise the working ability of the existing infrastructure. Should it be required to provide alterations to public utility mains, existing mains, services or installations, then the developer is required to meet the costs of the alteration/s, which is to be carried out in accordance with the relevant Brisbane Planning Scheme Codes/Policies.

 
While site works are occurring and then to be maintained
29(a) As Constructed Drawings

Submit to Development Services "As Constructed" drawings including an asset register, showing all new and/or rectification works required by this condition.  These works must be certified by a Registered Professional Engineer of Queensland-Civil that they are in accordance with the relevant Brisbane Planning Scheme Codes/Policies and any other relevant infrastructure requirements.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
30)   Filling and excavation (Minor)

Undertake the works on the site in accordance with the relevant Brisbane Planning Scheme Codes/Policies.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
30(a) Prepare Earthworks Plan

A suitably qualified person is to prepare earthworks drawings in accordance with the relevant Brisbane Planning Scheme Codes/Policies.  The drawings are to ensure the following:

-  maintenance of access roads to and from the site such that they remain free of all fill material and are cleaned as necessary
-  preservation of all drainage structures from the effects of structural loading generated by the earthworks
-  protection of adjoining properties and roads from ponding or nuisance from stormwater

 
Prior to site/operational/building work commencing
30(b) Implement and Maintain the Earthworks Plan

Implement and maintain the earthworks plan in accordance with the relevant Brisbane Planning Scheme Codes/Policies.   A copy of the Earthworks Plan must be available on-site for inspection by Council Officers during these works.

 
While site/operational/building work is occurring and then to be maintained
 
31)   Access, Grades, Manoeuvring, Carparks, Signs and Line Marking

Construct access, parking and manoeuvring for vehicles on site in accordance with the relevant Brisbane Planning Scheme Codes, as indicated on the approved DRAWINGS AND DOCUMENTS, including the following:

i. Parking on the site in accordance with the approved drawings, for the loading and unloading of vehicle(s) within the site and in accordance with Approved Drawing DD A.002 Issue F (received dated 19/03/2024).

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
31(a) Submit certification

Submit to Development Services, certification from a Registered Professional Engineer Queensland, that the above requirements have been implemented in accordance with this condition.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first

 
As indicated
 
32)   Refuse Collection - Kerb Side (external road or internal private road)

Refuse and recycling bins for the proposed development are to be collected from the kerb side unless alternative refuse collection arrangements are made with Brisbane City Council’s Waste Services.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
33)   Repair Damage To Kerb, Footpath Or Road

Repair any damage to existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel and stormwater gullies and drainlines) and re-instatement existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
34)   On site drainage - Minor

Provide a stormwater connection to all new or existing allotments and provide drainage infrastructure to ensure stormwater run-off from all roof and developed surface areas will be collected internally and piped in accordance with the relevant Brisbane Planning Scheme Codes/Policies to “a lawful point of discharge” and as shown on the Concept Engineering Services Plan, Drawing No. SK02 P4 (received dated 31/10/2023).

Note: A lawful point of discharge is defined in the relevant Brisbane Planning Scheme Codes/Policies. A soakage pit certified by a Registered Professional Engineer of Queensland-Civil (RPEQ-Civil) may only be considered as an acceptable alternative point of discharge for single detached dwellings on existing lots.

If roofwater reticulation is required for a reconfiguration, provide “As Constructed” plans prepared by an RPEQ or Registered Surveyor.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
 
35)   Service Conduits and Mains

Supply and install all service conduits and meet the cost of any alterations to public utility mains, existing mains, services or installations required in connection with the approved development in accordance with the relevant Brisbane Planning Scheme Codes/Policies.  This includes:

- the provision of all services and/or conduits along the full length of any rear allotment access or access easement.
- the breaking and/or relocation of any existing sewer combine drains.
- the relocation of any fire hydrant and/or valves from the development's vehicular footway crossings.
- the retention and/or relocation of any existing foul water lines that currently exist within the site

Note:  Applicants must liaise with the appropriate service authorities. Typical underground services and/or conduits to be constructed include power, phone, telecommunications, sewer (including private combine drains) stormwater and gas, if applicable.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
35(a) As Constructed Drawings

Submit to Development Services "As Constructed" drawings including an asset register, approved by a Registered Professional Engineer Queensland that are in accordance with the relevant Brisbane Planning Scheme Codes/Policies, and any other relevant infrastructure requirements, showing the works required by this condition.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
36)   Telecommunications

Enter into an agreement with a telecommunication carrier to provide underground telecommunication services within and adjacent to the proposed development in accordance with the relevant Brisbane Planning Scheme Codes.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
37)   Agreement with Electricity Supplier

Enter into an agreement with an electricity supplier to provide necessary services to the development in accordance with the relevant Brisbane Planning Scheme Codes/Policies.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
38)   Remove Redundant Crossover

Remove the existing vehicular crossing(s) on the frontage(s) of the site and reinstate the kerb and channel, road pavement, footways and footpaths in accordance with the relevant Brisbane Planning Scheme Codes/Policies.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
39)   Permanent Driveway Crossover

Lots 1 & 10: Provide 2 * 4.5metre wide Vehicular crossovers to the Binkar and Yaralla Street frontages of the site, as per BSD-2022; and

Lots 2 - 9: Provide 4 * Shared and modified (widened to 6.7metres) Type A Vehicular crossovers to the Buna Street frontage of the site, generally as per BSD-2021; and in accordance with the relevant Brisbane Planning Scheme Codes and located as shown on the approved DRAWINGS AND DOCUMENTS.

To comply with Council’s standard drawings the vehicle crossovers must be perpendicular to the property alignment, to provide safe access to a property, and the edges of the crossover are to be parallel.

The vehicle crossover (including the splays/tapers) must be constructed with the following clearances. If this cannot be achieved, the crossover width is to be reduced:

- a minimum 700mm from power / light pole (in particular, on the Lot 2 Buna Street frontage); and

- The crossovers and splays/tapers must not protrude across property boundaries, or the projection of such a boundary line to the carriageway, except where joint or shared property access is proposed, as per BSD-2022.

Written consent must be obtained from Program, Planning and Integration Arboriculture (PPI Arb) prior to any works occurring that will either impact on or require removal of a street tree (this includes pruning, excavation or fill within the root zone/canopy of the tree)

At all times during construction of the crossover, safe pedestrian access along the site frontage must be maintained.

Note: No further driveway permit is required however additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
Standard Advice
 
Timing
40)   Construction Noise and Dust Emissions

Pursuant to the Environmental Protection Act 1994, all development involving the emission of noise and dust from building and/or construction activities, must ensure that the emissions are in accordance with the requirements of the Act. 

The Environmental Protection Act 1994 prescribes that: 

1. A person must not carry out building work in a way that makes an audible noise-

  - on a business day or Saturday, before 6.30a.m. or after 6.30p.m; or

  - on any other day, at any time. 

2. The reference in subsection (1) to a person carrying out building work-

  - includes a person carrying out building work under an owner-builder permit; and

  - otherwise does not include a person carrying out building work at premises used by the person only for residential purposes.    

Note:   A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management delegate Development Services.

 
As indicated
 
41)   Plumbing and Drainage Work

Pursuant to the Plumbing and Drainage Act 2002, any plumbing and drainage work must be carried out in compliance with the Standard Plumbing and Drainage Regulation. Compliance assessable plumbing and drainage work requires approval by Brisbane City Council prior to the work being carried out.

 
As indicated
 
42)   Equitable Access

Provision must be made for equitable access for persons with disabilities to and within the site in accordance with the Queensland Anti- Discrimination Act 1991, the Federal Disability Discrimination Act 1992 and Australian Standard AS1428 Parts 1-4, Australian Standard for Access and Mobility and the National Construction Code.

 
As indicated
 
43)   Water and Wastewater

Services for water and wastewater (sewerage) are no longer under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections requires a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. Any necessary Water Approval must be obtained from the relevant distributor- retailer (currently operating as Queensland Urban Utilities for the Brisbane City Council area).

For the purpose of compliance assessment of a subdivision plan pursuant to Schedule 19 of the Sustainable Planning Regulation 2009 (whether in relation to a development permit for Reconfiguring a Lot or a Building Format Plan subsequent to a development permit for a Material Change of Use), documentary evidence, issued by the relevant distributor-retailer, must be provided to Council to verify that the conditions of any necessary Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009, have been complied with.

 
As indicated
 
44)   Damage to Trees on Adjoining Lots

Please note that any damage caused to vegetation on adjoining lots as a result of exercising this development approval may result in civil action.

 
As indicated
 
45)   Fire Ant Movement Controls

To prevent the spread of fire ants, the Queensland Government has implemented movement controls in areas of Queensland (biosecurity zones) where this pest species has been detected. These controls apply to individuals and commercial operators, and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products.

Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014.

If you are unsure of your obligations contact the relevant Queensland State Government Department (Biosecurity Queensland, Department of Agriculture and Fisheries)

 
As indicated
 



Permit to Which These Conditions Relate: DA - SPA - Carry out Building Work
Activity(ies): Multiple Dwelling
Stage:  

Standard Advice
 
Timing
46)   Further Development Permit required

This Preliminary Approval (Carrying Out Building Works) does not include assessment under the Building Act and does not permit building work to occur.  Prior to the commencement of any building work, Development Permit(s) for Carrying Out Building Work will be required.

 
As indicated
 
47)   Construction Noise and Dust Emissions

Pursuant to the Environmental Protection Act 1994, all development involving the emission of noise and dust from building and/or construction activities, must ensure that the emissions are in accordance with the requirements of the Act. 

The Environmental Protection Act 1994 prescribes that: 

1. A person must not carry out building work in a way that makes an audible noise-

  - on a business day or Saturday, before 6.30a.m. or after 6.30p.m; or

  - on any other day, at any time. 

2. The reference in subsection (1) to a person carrying out building work-

  - includes a person carrying out building work under an owner-builder permit; and

  - otherwise does not include a person carrying out building work at premises used by the person only for residential purposes.    

Note:   A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management delegate Development Services.

 
As indicated
 
48)   Plumbing and Drainage Work

Pursuant to the Plumbing and Drainage Act 2002, any plumbing and drainage work must be carried out in compliance with the Standard Plumbing and Drainage Regulation. Compliance assessable plumbing and drainage work requires approval by Brisbane City Council prior to the work being carried out.

 
As indicated
 
49)   Equitable Access

Provision must be made for equitable access for persons with disabilities to and within the site in accordance with the Queensland Anti- Discrimination Act 1991, the Federal Disability Discrimination Act 1992 and Australian Standard AS1428 Parts 1-4, Australian Standard for Access and Mobility and the National Construction Code.

 
As indicated
 
50)   Water and Wastewater

Services for water and wastewater (sewerage) are no longer under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections requires a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. Any necessary Water Approval must be obtained from the relevant distributor- retailer (currently operating as Queensland Urban Utilities for the Brisbane City Council area).

For the purpose of compliance assessment of a subdivision plan pursuant to Schedule 19 of the Sustainable Planning Regulation 2009 (whether in relation to a development permit for Reconfiguring a Lot or a Building Format Plan subsequent to a development permit for a Material Change of Use), documentary evidence, issued by the relevant distributor-retailer, must be provided to Council to verify that the conditions of any necessary Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009, have been complied with.

 
As indicated
 
51)   Damage to Trees on Adjoining Lots

Please note that any damage caused to vegetation on adjoining lots as a result of exercising this development approval may result in civil action.

 
As indicated
 
52)   Fire Ant Movement Controls

To prevent the spread of fire ants, the Queensland Government has implemented movement controls in areas of Queensland (biosecurity zones) where this pest species has been detected. These controls apply to individuals and commercial operators, and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products.

Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014.

If you are unsure of your obligations contact the relevant Queensland State Government Department (Biosecurity Queensland, Department of Agriculture and Fisheries)

 
As indicated
 



Permit to Which These Conditions Relate: DA - PA - Reconfiguring a Lot
Activity(ies): Subdivision of Land
Stage:  

General/Planning Requirements
 
Timing
53)   Maintain the Approved Development

Maintain the approved development generally in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions. 

 
At all times
 
54)   Approved Drawings and Documents

A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers. 
 
Note: This condition is imposed to ensure compliance with the conditions of development approval.

 
While site/operational/building work is occurring
 
55)   Carry Out the Approved Development

Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS.

Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners.

 
While site/operational/building work is occurring
 
56)   Construction Prior to Notation on Plan of Subdivision

Development authorised by the associated development approval for Material Change of Use must be constructed to framing stage.

 
Prior to Council's notation on the plan of subdivision
 
Engineering
 
Timing
57)   Grant Easements

Grant easement(s) as may be required.

 
As indicated
57(a) Submit Plan of Subdivision and Documentation (other Easement)

Submit to, and obtain approval from, Development Services, a plan of subdivision showing the easement and the necessary easement documentation to demonstrate compliance with the requirements of this condition.

Note: Easements not in favour of the Brisbane City Council must have the necessary documentation prepared by the applicant's private solicitors.

Timing: As part of the submission of the request pursuant to Schedule 18 of the Planning Regulation 2017 for Council's notation on the plan of subdivision necessary to comply with this condition or give effect to this approval.

 
As indicated
57(b) Lodge Notated Plan and Documentation

Lodge the plan of subdivision notated by Council pursuant to Schedule 18 of the Planning Regulation 2017 and the necessary easement documentation with the Registrar of Titles for the relevant Queensland State Government Authority.

Timing: As part of the registration of the plan of subdivision notated by Council.

PROOF OF FULFILMENT
Evidence of the registration of the necessary easement documentation. Timing: Within one month of the registration of the easement documentation.

 
As indicated
 
58)   Information Signage

Erect an information sign on the subject property in accordance with Council's general requirements for signage and in accordance with the requirements outlined below:

a) The sign should provide a brief description of the development proposed;

b) The sign is to list the name, postal and/or email address and a contact telephone number for the following parties (where relevant) that are undertaking work on the site:

- Developer;
- Project Coordinator;
- Architect/Building Designer;
- Builder;
- Civil Engineer;
- Civil Contractor/s; and
- Landscape Architect;

c) The lettering on the sign is to be at least 25 millimetres in height, be of regular weight and in sentence case;

d) The sign is to be a minimum size of 1,200 millimetres by 900 millimetres;

e) The maximum area of the sign is to be 2.0m2;

f) The sign is to be positioned as follows:

- located centrally along each road frontage of the site;
- located on or within 1.5 metres of the road frontage;
- mounted at least 300 millimetres above ground level; and
- clearly visible from the street for a pedestrian;

g) The sign is to contain no commercial or corporate advertising other than the name, logo or slogan of the parties outlined in part (b) of this condition;

h) The sign is to be non-illuminated; and

i) Both the sign and the supporting structure are to be made of weatherproof material and to be properly maintained at all times.

Timing: Prior to site works commencing and then to be maintained until completion of the development for all stages.

 
As indicated
 
59)   Certified Site Survey Levels

Submit to Development Services, "As Constructed" drawings prepared by a Registered Surveyor (Qld). The registered surveyor must certify that the "As Constructed" drawings are in accordance with the APPROVED PLANS and the relevant Brisbane Planning Scheme Codes and show finished surface level information over the completed development.

Note: The survey information must show surface levels and site contours at 1 metre intervals. All levels must be shown as Reduced Levels to the "Australian Height Datum" (AHD).

 
Prior to Council's notation on the plan of subdivision
 
Standard Advice
 
Timing
60)   Standard Advice Disclaimer

The following information is provided to the applicant as advice only and does not form part of the development approval conditions. This advice has been provided to inform the applicant of other obligations they may be required to comply with (under state legislation or local laws) prior to the approved activity commencing.

 
As indicated
 
61)   Currency Period

The currency period for this development approval is stated in the Decision Notice and is expressed as a date.

 

This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016.

 
As indicated
 
62)   Water and Wastewater

Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009.

For further information about any necessary Water Approvals contact Urban Utilities.

 
As indicated
 
63)   Fire Ant Movement Controls

To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected.

These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products.

Breaches of these controls can potentially impact the community, economy and the environment.  Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014.

For further information contact the relevant Queensland State Government department on 13 QGOV.

 
As indicated
 

** End of Package **