| Address of Site: | 319 GARDNER RD ROCHEDALE QLD 4123 319 GARDNER RD ROCHEDALE QLD 4123 319 GARDNER RD ROCHEDALE QLD 4123 |
| Real Property Description of Site: | L1 RP.57560 L900 SP.330332 L99 SP.317513 |
| Aspects of development and type of approval: | DA - PA - Building Work Preliminary Approval under s241 - Multi-Unit
Dwelling DA - PA - Material Change of Use Development Permit - Multi-Unit Dwelling DA - PA - Building Work Preliminary Approval under s241 - Multi- Unit Dwelling DA - PA - Material Change of Use Development Permit - Multi- Unit Dwelling |
| Council File Reference: | A006982146 Permit Reference Number/s: DABW445295124; DAMC445295324; DABW446281224; DAMC446281324. |
| Package Status: | APPROVED - Version 2 (2nd of April, 2026 5:53:25 PM) |
| Package Generated: | 02/04/2026 |
| Eric OWEN Senior Technical Officer Engineering Services South eric.owen@brisbane.qld.gov.au (07) 3178 5195 |
Kayal CHANDRASEKAR Senior Urban Planner Planning Services South Kayal.Chandrasekar@brisbane.qld.gov.au 34030086 |
Kathryn KELLY Principal Urban Planner Planning Services South kathryn.kelly@brisbane.qld.gov.au 07 3407 1308 |
| John GRIMSEY Built Environment Officer WaRRS Assessment john.grimsey@brisbane.qld.gov.au 34071331 |
Kirstin BURROWES Senior Architect Architecture Team Kirstin.Burrowes@brisbane.qld.gov.au 0731785363 |
Chris HENNESSY Engineering Services Traffic Chris.Hennessy@brisbane.qld.gov.au (07) 3403 5768 |
| Michael PICKERILL Network Planning Michael.Pickerill@brisbane.qld.gov.au |
Michael PO SAW Technical Officer Trunk Infrastructure & Calculations michael.posaw@brisbane.qld.gov.au 34036167 |
Lani ROBERTS Landscape Architect Landscape Architecture Team Lani.Roberts@brisbane.qld.gov.au 07 3403 8888 |
| Jack WOOLSTON Senior Urban Planner Planning Services Special Assessment Jack.Woolston@brisbane.qld.gov.au 07 3178 5033 |
Llewellyn BATSON Principal Urban Planner Planning Services Special Assessment Llewellyn.Batson@brisbane.qld.gov.au (07) 340 34980 |
DRAWINGS AND DOCUMENTS
| Drawing or Document | Number | Plan Date |
|---|---|---|
| Site Plan | DA-002 Revision 25 (Amended In Red 25-MAR-2026) | 30-JAN-2026 (Received) |
| Site Plan - Setback | DA-003 Revision 16 (Amended In Red 25-MAR-2026) | 30-JAN-2026 (Received) |
| Site Plan - Ground Floor | DA-100 Revision 10 | 30-JAN-2026 (Received) |
| Site Plan - Level 1 | DA-101 Revision 9 | 30-JAN-2026 (Received) |
| Site Plan - Level 2 | DA-102 Revision 9 | 30-JAN-2026 (Received) |
| Site Plan - Roof | DA-103 Revision 9 | 30-JAN-2026 (Received) |
| Bicycle Parking | DA-110 Revision 4 | 30-JAN-2026 (Received) |
| Site Elevations | DA-200 Revision 11 | 30-JAN-2026 (Received) |
| Site Elevations | DA-201 Revision 7 | 30-JAN-2026 (Received) |
| Site Elevations | DA-202 Revision 7 | 30-JAN-2026 (Received) |
| Site Elevations | DA-203 Revision 8 | 30-JAN-2026 (Received) |
| Building Elevations | DA-300 Revision 9 | 30-JAN-2026 (Received) |
| Building Elevations | DA-301 Revision 10 | 30-JAN-2026 (Received) |
| Building Elevations | DA-302 Revision 9 | 30-JAN-2026 (Received) |
| Building Elevations | DA-303 Revision 9 | 30-JAN-2026 (Received) |
| Building Elevations | DA-304 Revision 11 | 30-JAN-2026 (Received) |
| Building Elevations | DA-305 Revision 11 | 30-JAN-2026 (Received) |
| Building Elevations | DA-306 Revision 11 | 30-JAN-2026 (Received) |
| Building Elevations | DA-307 Revision 9 | 30-JAN-2026 (Received) |
| Building Elevations | DA-308 Revision 9 | 30-JAN-2026 (Received) |
| Building Height Layout | 1710_DA0131 Revision J (Amended In Red 25-MAR-2026) | 18-NOV-2022 (Received) |
| Master - Ground Floor Plan | 1710_DA0211 Revision Y (Amended In Red 12-APR-2024) | 18-NOV-2022 (Received) |
| Site Plan Ground Floor (L1) | 1710_DA5111 Revision R (Amended In Red 12-APR-2024) | 12-APR-2024 (Received) |
| Site Plan Level 2 | 1710_DA5121 Revision M (Amended In Red 12-APR-2024) | 22-MAR-2024 (Received) |
| Site Plan Level 3 | 1710_DA5131 Revision K | 18-NOV-2022 (Received) |
| Site Plan Roof Plan | 1710_DA5132 Revision E | 18-NOV-2022 (Received) |
| Bin Enclosure Detail | 1710_DA5400 Revision A | 12-APR-2024 (Received) |
| Civil Services Concept Sketch | 6212-161124-SK01 (Amended In Red 19-AUG-2021) | 25-JAN-2017 (Received) |
| External Elevations | 1710_DA5211 Revision F | 18-NOV-2022 (Received) |
| Internal Elevations | 1710_DA5212 Revision F | 18-NOV-2022 (Received) |
| Building 1 & 2 (3 & 4 SIM) | 1710_DA5221 Revision C | 18-NOV-2022 (Received) |
| Building 5 & 6 (7 SIM) | 1710_DA5231 Revision C | 18-NOV-2022 (Received) |
| Building 10 to 12 (8 & 9 SIM) | 1710_DA5241 Revision C | 18-NOV-2022 (Received) |
| Building 13 & 14 (15 & 16 SIM) | 1710_DA5251 Revision C | 18-NOV-2022 (Received) |
| Sections | 1710_DA5311 Revision L | 18-NOV-2022 (Received) |
| Environmental Noise Assessment Report | 13GCA0080 R01_3 | 22-MAR-2014 (Received) |
| Landscape Concept Design Report - Introduction | Page 02 | 14-JUN-2021 (Received) |
| Landscape Concept Design Report - Character | Page 03 (Amended In Red 12-APR-2024) | 14-JUN-2021 (Received) |
| Landscape Concept Design Report - Character | Page 04 | 14-JUN-2021 (Received) |
| Landscape Concept Design Report - Character | Page 05 | 14-JUN-2021 (Received) |
| Landscape Concept Design Report - Character | Page 06 | 14-JUN-2021 (Received) |
| Master Site Plan | 1710_DA0201 Revision Q (Amended In Red 25-MAR-2026) | 11-MAY-2017 (Received) |
| Preliminary Roadwork and Drainage Layout Plan | DA13-02 (Amended In Red 24-JUL-2024) | 27-JUN-2024 (Received) |
| VRP01: Cover Page | 16139 VRP01 Issue A | 25-JAN-2017 (Received) |
| VRP02a: Key Map - Tree Survey | 16139 VRP02a Issue A | 25-JAN-2017 (Received) |
| VRP02b: Map A1 - Tree Survey | 16139 VRP02b Issue A (Amended In Red 19-AUG-2021) | 25-JAN-2017 (Received) |
| VRP03a: Map A1 - Tree Protection and Structural Root Zones | 16139 VRP03a Issue A (Amended In Red 19-AUG-2021) | 25-JAN-2017 (Received) |
| VRP04a: Map A1 - Trees Retained and Removed | 16139 VRP04a Issue A (Amended In Red 19-AUG-2021) | 25-JAN-2017 (Received) |
| VRP02c: Map B1 - Tree Survey | 16139 VRP02c Issue A | 25-JAN-2017 (Received) |
| VRP03b: Map B1 - Tree Protection and Structural Root Zones | 16139 VRP03b Issue A (Amended In Red 19-AUG-2021) | 25-JAN-2017 (Received) |
| VRP04b: Map B1 - Trees Retained and Removed | 16139 VRP04b Issue A (Amended In Red 19-AUG-2021) | 25-JAN-2017 (Received) |
| VRP02d: Map C1 - Tree Survey | 16139 VRP02d Issue A | 25-JAN-2017 (Received) |
| VRP03c: Map C1 - Tree Protection and Structural Root Zones | 16139 VRP03c Issue A | 25-JAN-2017 (Received) |
| VRP04c: Map C1 - Trees Retained and Removed | 16139 VRP04c Issue A | 25-JAN-2017 (Received) |
| VRP05a: Management Procedures | 16139 VRP05a Issue A | 25-JAN-2017 (Received) |
| VRP05b: Management Procedures | 16139 VRP05b Issue A | 25-JAN-2017 (Received) |
| VRP06a: Tree Survey Details | 16139 VRP06a Issue A | 25-JAN-2017 (Received) |
| VRP06b: Tree Survey Details | 16139 VRP06b Issue A | 25-JAN-2017 (Received) |
| VRP06c: Tree Survey Details | 16139 VRP06c Issue A | 25-JAN-2017 (Received) |
| VRP06d: Tree Survey Details | 16139 VRP06d Issue A | 25-JAN-2017 (Received) |
| VRP06e: Tree Survey Details | 16139 VRP06e Issue A | 25-JAN-2017 (Received) |
| VRP06f: Tree Survey Details | 16139 VRP06f Issue A | 25-JAN-2017 (Received) |
APPROVAL CONDITIONS
| Permit to Which These Conditions Relate: | DA - PA - Building Work |
| Activity(ies): | Multi-Unit Dwelling |
| Stage: | 2 |
| 1) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS
AND DOCUMENTS and the Development Approval Package must be available on
site. |
While site/operational/building work is occurring |
| 2) Carry Out the Approved Development Carry out the approved development generally in
accordance with the approved DRAWINGS AND DOCUMENTS. |
While site/operational/building work is occurring and then to be maintained |
| 3) Complete All Building Work Complete all building work associated with this
development approval, including work required by any of the conditions included
in the Development Approval Package. Such building work must be carried out
generally in accordance with the approved DRAWINGS AND DOCUMENTS, and, where
the building work is assessable development, in accordance with a current
development approval. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
| 4) Maintain the Approved Development Maintain the approved development generally in
accordance with the approved DRAWINGS AND DOCUMENTS, and any relevant Council
engineering or other approval required by the conditions. |
To be maintained |
| 5) External Details External details of the building, facade treatment and external
materials, colours and finishes must be consistent with the approved DRAWINGS
AND DOCUMENTS. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 6) Further Development Permit required This Preliminary Approval (Carrying Out Building Works) does not include assessment under the
Building Act and does not permit building work to occur. Prior to the commencement of any building work,
Development Permit(s) for Carrying Out Building Work
will be required. |
As indicated |
| 7) Construction Noise and Dust Emissions Pursuant to the
Environmental Protection Act 1994, all development involving the emission of
noise and dust from building and/or construction activities, must ensure that
the emissions are in accordance with the requirements of the Act. The
Environmental Protection Act 1994 prescribes that: 1. A person
must not carry out building work in a way that makes an audible noise-
- on a business day or Saturday, before 6.30a.m. or after 6.30p.m; or
- on any other day, at any time.
2. The reference in subsection (1)
to a person carrying out building work- - includes a person carrying out building work under an owner-builder permit; and - otherwise does
not include a person carrying out building work at premises used by the person
only for residential purposes. Note: A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management delegate Development Services. |
As indicated |
| 8) Water and Wastewater Services for water and wastewater (sewerage) are
no longer under the jurisdiction of Brisbane City Council. Authorisation to
connect the approved development to the water/wastewater networks and for
property service connections requires a Water Approval under the South-East
Queensland Water (Distribution and Retail Restructuring) Act 2009. Any
necessary Water Approval must be obtained from the relevant distributor-
retailer (currently operating as Queensland Urban Utilities for the Brisbane
City Council area). For the purpose of compliance assessment of a subdivision plan pursuant to Schedule 19 of the Sustainable Planning Regulation 2009 (whether in relation to a development permit for Reconfiguring a Lot or a Building Format Plan subsequent to a development permit for a Material Change of Use), documentary evidence, issued by the relevant distributor-retailer, must be provided to Council to verify that the conditions of any necessary Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009, have been complied with. |
As indicated |
| 9) Fire Ant Movement Controls To prevent the spread of fire ants, the
Queensland Government has implemented movement controls in areas of Queensland
(biosecurity zones) where this pest species has been detected. These controls
apply to individuals and commercial operators, and restrict the movement of
materials that could carry fire ants which include soil, turf, potted plants,
mulch, baled hay or straw, animal manures, mining or quarry
products. Breaches of these controls can potentially
impact the community, economy and the environment. Penalties for non-compliance
with movement controls within fire ant biosecurity zones apply under the
Biosecurity Act 2014. If you are unsure of your obligations contact the relevant Queensland State Government Department (Biosecurity Queensland, Department of Agriculture and Fisheries) |
As indicated |
| Permit to Which These Conditions Relate: | DA - PA - Material Change of Use |
| Activity(ies): | Multi-Unit Dwelling |
| Stage: | 2 |
| 10) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS
AND DOCUMENTS and the Development Approval Package must be available on
site. |
While site/operational/building work is occurring |
| 11) Carry Out the Approved Development Carry out the approved development generally in
accordance with the approved DRAWINGS AND DOCUMENTS. |
While site/operational/building work is occurring and then to be maintained |
| 12) Complete All Building Work Complete all building work associated with this
development approval, including work required by any of the conditions included
in the Development Approval Package. Such building work must be carried out
generally in accordance with the approved DRAWINGS AND DOCUMENTS, and, where
the building work is assessable development, in accordance with a current
development approval. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
| 13) Maintain the Approved Development Maintain the approved development generally in
accordance with the approved DRAWINGS AND DOCUMENTS, and any relevant Council
engineering or other approval required by the conditions. |
To be maintained |
| 14) External Details External details of the building, facade treatment and external
materials, colours and finishes must be consistent with the approved DRAWINGS
AND DOCUMENTS. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 15) Overall Height The overall height of the proposed building(s) must be in accordance with the floor and roof levels and overall height shown on the APPROVED DRAWINGS AND DOCUMENTS. |
While site/operational/building work is occurring and then to be maintained |
15(a) Submit Certification Submit to Development
Services certification from a registered surveyor confirming that the “as
constructed” floor and roof levels and overall height are in accordance
with the requirements of this condition. |
As indicated |
| 16) Provide Pedestrian Prioritised Pathway Provide a pedestrian prioritised
pathway from the street frontage to the front door of each unit. The pathway
must be differentiated in colour and texture from the driveway
surface. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 17) Driveway Material and Finishes Provide materials and finishes to the driveway
and external carparking surfaces that reduce the
visual impact of these areas when viewed from the street. One or a combination
of the following must be used: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 18) Screen Air Conditioning and Other Plant
Enclosures Install and maintain suitable
screening to all air conditioning, lift motor rooms, plant and service
facilities located at the top of or on the external face of the building. The
screening structures must be constructed from materials that are consistent
with materials used elsewhere on the facade of the building. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 19) Screening Multiple Dwelling / Dual
Occupancy Provide screening in accordance with the approved DRAWINGS AND
DOCUMENTS and the following: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 20) Natural Assets Local Law (NALL) - Protected
Vegetation On Site Ensure
that all necessary permits under the NALL have been issued to carry out works
on protected vegetation on the site. NOTE:
Apply to Development Services for all the necessary permits under the
NALL. Timing: Prior to carrying out works on protected vegetation |
As indicated |
| 21) Fauna Management - Fauna Spotter Catcher (High
Risk) Engage a licensed Fauna Spotter Catcher (qualified by the relevant Queensland State Government Authority) to manage the protection and relocation of any fauna prior to and during vegetation/ecological feature clearing. |
Prior to site/operational/building work commencing and then to be maintained |
21(a) Prior to Vegetation/ Ecological Feature
Clearing Submit
to Development Services certification from the licensed Fauna Spotter Catcher
that the site has been fully inspected and any necessary fauna protection
measures or relocation procedures have been implemented. Timing: Prior to vegetation/ ecological feature clearing commencing. |
As indicated |
21(b) During Vegetation/ Ecological Feature
Clearing The
licensed Fauna Spotter Catcher must be present on site during all clearing
operations to monitor works and to respond to any fauna situations that may
arise. If any fauna is identified in vegetation or ecological features to be
removed during clearing operations, work must cease immediately on that
vegetation or ecological feature. The licensed Fauna Spotter Catcher must
supervise the relocation of any identified fauna prior to vegetation/
ecological feature clearing recommencing. Timing: While vegetation/ ecological feature clearing is occurring |
As indicated |
21(c) Submit Certification Submit to Development Services
certification from the licensed Fauna Spotter Catcher that vegetation/
ecological feature clearing was carried out in accordance with this
condition. Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
As indicated |
| 22) Vegetation Management (Submit Plan) Manage vegetation on the site in accordance with a Vegetation Management Plan approved pursuant to this condition. |
While site/operational/building work is occurring and then to be maintained |
22(a) Submit Vegetation Management
Plan Submit and obtain approval for a Vegetation Management Plan from Development Services. This plan must be prepared by a qualified and experienced environmental practitioner, with supporting documentation from the Project Arborist (minimum AQF Level 5 in Arboriculture with a minimum of 5 years' experience in arboricultural principles and practices, including tree risk hazard assessment and reporting with current public liability insurance to $20 million, and a professional indemnity of $2 million), where works are required within the Tree Protection Zone (TPZ) of retained trees. The Vegetation Management Plan must
be in the form of scaled plans and supporting documentation that are generally
in accordance with the APPROVED DRAWINGS AND DOCUMENTS, relevant Brisbane
Planning Scheme Code and include the following: Timing: Prior to site / operational / building work commencing and prior to or concurrently with any other operational works application. |
As indicated |
22(b) Project Arborist Appoint as Project Arborist, a qualified Arborist (minimum AQF Level 5 in Arboriculture with a minimum of 5 years' experience in arboricultural principles and practices, including tree risk hazard assessment and reporting with current public liability insurance to $20 million, and a professional indemnity of $2 million.). Provide evidence of this appointment to the Ecologist Development Services. Timing: Prior to arranging a pre-start meeting. |
As indicated |
22(c) Pre-Start Meeting When measures are in place to identify and protect vegetation on site (such as tree protection fencing), arrange a pre-start meeting with the Ecologist Development Services. Applicable compliance and inspection fees must be paid to Council, in full, prior to the meeting being held. The Project Arborist and qualified Fauna Spotter Catcher must attend the pre-start meeting. Note: Timing: Prior to site / operational / building work commencing. |
As indicated |
22(d) Implement Approved Vegetation
Management Plan Carry out the works in accordance with the approved Vegetation Management Plan. Note: The Project Arborist
must: Timing: While site / operational / building work is occurring. |
As indicated |
22(e) Submit Certification Submit to Development Services, certification from the qualified and experienced environmental practitioner and the Project Arborist (minimum AQF Level 5 in Arboriculture with a minimum of 5 years' experience in arboricultural principles and practices, including tree risk hazard assessment and reporting with current public liability insurance to $20 million, and a professional indemnity of $2 million.), certifying that the work(s) have been carried out in accordance with the approved Vegetation Management Plan. Certification must
include: Timing: Upon completion of each phase of the approved Vegetation Management Plan and prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
22(f) Retain and Protect
Vegetation Retain and protect vegetation in accordance with the approved Vegetation Management Plan. Timing: To be maintained. |
As indicated |
| 23) Landscape the Site - Self Certification Landscape the site in accordance with the
requirements of this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
23(a) Landscape Plan for Self
Certification Prepare a detailed Landscape Plan at a scale of 1:100 for all on-site landscape works identified on the approved DRAWINGS AND DOCUMENTS including Landscape Concept Design Report Site Plan – pages 02, 03, 04, 05, 06 received 21 June 2021 as amended in red on 12-APR-2024. The plan must be prepared by a registered Landscape Architect and must comply with the relevant Brisbane Planning Scheme Code. The plan must be certified by the registered Landscape Architect using Brisbane City Council Form CC10616 - Landscape Design Certification and the form must be submitted to Development Services. In addition to the requirements
listed above, the plan must include the following: - Provide a minimum 1m of landscaping along the entire length rear boundary of each unit. Landscaping is to consist of screening trees, shade trees, and ground covers. - Provide one small shade tree to each private courtyard
|
As indicated |
23(b) Implement Certified Landscape
Plan Carry out the landscaping work in
accordance with the above certified detailed Landscape Plan. |
As indicated |
23(c) Certify Work On completion of the
landscaping work, submit to Development Services Brisbane City Council Form
CC10613 - Landscape Works Certificate prepared by a registered Landscape
Architect or licensed Landscape Contractor to certify the completed landscaping
work complies with the certified detailed Landscape Plan. Note: A copy of the as-constructed detailed Landscape Plan must
accompany the completed Landscape Works Certificate. Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
23(d) Maintain Landscape Work Maintain the landscape work generally in accordance
with the certified detailed Landscape Plan. |
As indicated |
| 24) Noise Emissions - Res. Road Traffic. Outdoor
Recreation Noise
emissions from road traffic when measured as the equivalent continuous A-
weighted sound pressure level (LAeq,T) at
private/communal recreation areas must not exceed: - LAeq,1hr 60
dB(A) |
To be maintained |
24(a) Certification Submit to Development Assessment certification
from an appropriately qualified consultant that vibration impacts achieve the
above levels. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 25) Dampening of Grilles And Metal Plates All metal grilles, metal plates or similar
subject to vehicular traffic must be acoustically damped to prevent
environmental nuisance. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 26) Air Conditioning to Noise Affected Rooms Air-conditioning/mechanical ventilation must be
provided to all noise affected rooms as detailed in the acoustic report as
windows and doors are required to remain closed to maintain acceptable indoor
noise levels. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 27) Plant and Equipment Certification Following the installation of all mechanical
plant and equipment (e.g. air conditioning, mechanical ventilation and
refrigeration equipment and heat pump hot water systems), submit to Development
Assessment certification that the plant and equipment is adequately noise-
attenuated and is in accordance with the criteria of the relevant Brisbane
Planning Scheme Codes/Policies. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 28) Filling and / or Excavation All proposed earthworks must
be carried out in accordance with the relevant Brisbane Planning Scheme
Codes. Timing: Prior to building work commencing (MCU or BW) or prior to
Council's notation of the plan of subdivision (ROL) |
As indicated |
28(a) Submit Earthworks
Drawings Submit for the approval of Development Services
earthworks drawings prepared and certified by a Registered Professional
Engineer Queensland in accordance with the approved DRAWINGS AND DOCUMENTS, the
relevant Brisbane Planning Scheme Codes. The Earthworks Drawings must include the
following: - The
location of any cut and/or fill; - The quantity of fill to be deposited and
finished fill levels; - Maintenance of access roads to and from the site
such that they remain free of all fill material and
are cleaned as necessary; - The existing and proposed finished levels in reference to the
Australian Height Datum (including cross-sections or long sections into the
adjacent properties); - Preservation of all drainage structures from the effects of
structural loading generated by the earthworks; - Protection of adjoining properties and roads
from ponding or nuisance from stormwater; - That all vehicles exiting from the site will be
cleaned and treated so as to prevent material being tracked or deposited on
public roads. Note: If the
earthworks impact on the road reserve, the Developer must obtain applicable
footpath and road permits prior to commencing any works. Such impacts may include footpath occupation, road
closures, re-profiling, ground anchors and/or relocation of services. If the excavation has to be stabilised
using ground anchors or similar then the submitted plans must show the location
of these in relation to all services. The cost of moving services, utilities
and assets is the responsibility of the Developer. The permission of the
service/utility/asset owner is required. |
As indicated |
28(b) Fill Material, Placement, Compaction
and Testing All fill material placed on the site must comprise
only natural earth and rock and must be free of contaminants (as defined by
Part 3, Division 2, Subdivision 2 Environmental contamination, Section 11 of
the Environmental Protection Act) and noxious, hazardous, deleterious and
organic materials. Fill
material, placement, compaction and testing must comply with the requirements
of Australian Standard - AS 3798, Guidelines on Earthworks for Commercial and
Residential Developments. Timing: While site/operational/building work is occurring |
As indicated |
28(c) Implement Approved Earthworks
Drawings Construct and maintain the earthworks in accordance
with the requirements of AS3798 and the approved earthworks drawings. |
As indicated |
28(d) Submit As Constructed
Drawings Submit to Development Services “As
Constructed” drawings prepared by a Registered
Surveyor. Timing: Prior to building work commencing (MCU or BW) or prior to Council's notation of the plan of subdivision (ROL) |
As indicated |
28(e) Submit Certification Submit to Development Services certification from a Registered
Professional Engineer Queensland, confirming that the works have been completed
in accordance with the approved earthworks drawings. Submit to Development Services certification from a
Registered Professional Engineer Queensland, confirming that all fill material
used complies with the quality requirements of this condition and that
placement, compaction and testing has been carried out in accordance with
AS3798. Timing:
Prior to building work commencing (MCU or BW) or prior to Council's notation of
the plan of subdivision (ROL) |
As indicated |
| 29) Grant Easements Grant the following
easement(s): |
As indicated |
29(a) Submit Plan of Subdivision and
Documentation (Non-Council Easement) Submit for the approval of Development Services, a plan of subdivision showing the easement and the necessary easement documentation to demonstrate compliance with the requirements of this condition. Note: Easements not in favour of the Brisbane City Council must have the necessary documentation prepared by the applicant's private solicitors. Timing: As part of the submission of the request for compliance assessment pursuant to Schedule 19 of the Sustainable Planning Regulation 2009 for Council's notation on the plan of subdivision necessary to comply with this condition (MCU) or give effect to this approval (ROL) |
As indicated |
29(b) Submit Plan of Subdivision and
Documentation (Council Easement) Submit for the approval of Development Services, a
plan of subdivision showing the easement and a request for Council to prepare
the necessary easement documentation to demonstrate compliance with the
requirements of this condition. Note: Easements in favour of
the Brisbane City Council must have the necessary easement documentation
prepared by the Brisbane City Council, free of cost to Council.
Timing: Prior to submission of the request for compliance assessment pursuant to Schedule 19 of the Sustainable Planning Regulation 2009 for Council's notation on the plan of subdivision necessary to comply with this condition (MCU) or give effect to this approval (ROL) |
As indicated |
29(c) Lodge Notated Plan and
Documentation Lodge
the plan of subdivision notated by Council pursuant to Schedule 19 of the
Sustainable Planning Regulation 2009 and the necessary easement documentation
with the Registrar of Titles for the relevant Queensland State Government
Authority. Timing: Prior to commencement of use (MCU) or as part of the registration of the plan of subdivision notated by Council (ROL) |
As indicated |
29(d) Submit Evidence of
Registration Submit
to Development Services evidence of the registration of the necessary easement
documentation. Timing: Within one month of the registration of the easement documentation |
As indicated |
| 30) Maintenance Period for Engineering Work Maintain the work required by the
Engineering condition(s) imposed on this development approval and rectify any
defects in accordance with the requirements detailed in this
condition. Timing: During the on-maintenance period |
As indicated |
30(a) On-Maintenance Acceptance Arrange an on-maintenance inspection
with Development Services and obtain written confirmation from Council that the
work has been completed in accordance with the requirements of the condition
and is accepted on-maintenance. Provide proof of Public
Liability Insurance ($20 million) for the on-maintenance
period. Lodge a maintenance security for the on-
maintenance period. The security must be calculated as 5% of the value of the
constructed work or $10,000.00, whichever is greater. Note: A maintenance security may consist of either a bank guarantee or
monetary payment lodged with Council. Refer to Council’s Infrastructure Installation and Construction Requirements
Manual for further details about the on-maintenance procedure and
requirements. Timing: Prior to issue of Certificate of
Classification/Final Inspection Certificate or prior to commencement of use,
whichever comes first (MCU or BW), or prior to Council's notation of the plan
of subdivision (ROL) |
As indicated |
30(b) On-Maintenance Period Provide a
minimum 12 months maintenance to the work from the time the work is
accepted on-maintenance by Council. During this period maintain the work and
rectify any defects identified at the on-maintenance inspection and those
arising during the on-maintenance period. Timing: A minimum 12 months from acceptance on-maintenance |
As indicated |
30(c) Off-Maintenance
Acceptance On
completion of the maintenance period arrange an off-maintenance inspection with
Development Services, and obtain written confirmation from Council that the
work is accepted off-maintenance. Ensure
all defects are rectified prior to making an appointment for off-maintenance
Inspection. Note: If the inspection is successful the
maintenance security will be released.
Timing: On completion of the on-maintenance period |
As indicated |
| 31) Information Signage Erect an "Information Sign" on the subject
property in accordance with Council’s general requirements for signage
and in accordance with the requirements outlined below: a)
The sign should provide a brief description of the development proposed; Developer; c) The lettering on the sign is to be at least
25 millimetres in height, be of regular weight and in sentence case; located centrally along each road
frontage of the site to Gardner Road; g) The sign is to contain no commercial
or corporate advertising other than the name, logo or slogan of the parties
outlined in part (b) of this condition; Timing: Prior to site works commencing and then to be maintained until completion of the development for all stages. |
As indicated |
| 32) Engineering Pre Start Meeting To arrange an engineering pre-start meeting with Development Service to comply with a condition of this approval, request letter to be emailed to DA- ComplianceEngineering@brisbane.qld.gov.au including the following details: - Site
address, Development Approval number (A00) and relevant stage/s (if
appropriate); Note: Timing: Prior to site/operational/building work commencing |
As indicated |
| 33) On-site Erosion (Medium Risk) Manage on-site erosion and the release of sediment or sediment laden water from the site at all times by implementing best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version). Timing: Prior to commencement of any land disturbing activities and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
33(a) Manage earth disturbance on-
site (i) Drainage control measures must be implemented and maintained to minimise water flow onto areas of exposed earth. (ii) Sediment and erosion control measures must be implemented and maintained to prevent soil loss from earth disturbance areas and prevent deposition beyond earth disturbance areas. (iii) No release of contaminants to land beyond on-site area of earth disturbance other than releases that achieve water pollutant concentration release limits of: A. 50mg/L TSS (Total Suspended Solids); B. Turbidity, Nephelometric Turbidity Units (NTU) value less than 10% above background, 75 NTU, or as agreed in writing by an Officer from Councils Erosion and Sediment Control (ESC) Team in Compliance and Regulatory Services; C. pH between 6.5 and 8.5 at all times. (iv) Maintain a written record to demonstrate that water discharges from the site, including any dewatering operations, meet the release limits as detailed in (iii) for water discharge(s) from the site that occur during or immediately after a rainfall event, and during normal business hours. The water quality of the discharge flows must be measured at each discharge point from the site, including but not limited to sediment basin outlets, other applicable sediment control devices, the site water drainage system, and recorded against the release limits at least once on each calendar day until such discharge stops. Timing: Prior to commencement of any earth disturbing activities and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
33(b) Provide Land Occupier Notification to
Council (i) Notify Council's ESC Team of proposed land occupier/s by sending an email to CARS-ESC@Brisbane.qld.gov.au (ii) If the land is to be occupied by any person other than the registered landowner then advice must be provided to Council that confirms the name, contact information and the duration of any proposed occupation of the land. Timing: Prior to commencement of any earth disturbing activities. |
As indicated |
33(c) Prepare Erosion and Sediment Control
Plan Prepare an Erosion and Sediment Control Plan (ESCP) in accordance with best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version) and, to the extent of any inconsistency, relevant Brisbane Planning Scheme Codes and Policies. Obtain a design certificate in accordance with the relevant Brisbane Planning Scheme Codes and Policies. The ESCP and design certificate must be certified by a Certified Professional in Erosion and Sediment Control (CPESC) or a Registered Professional Engineer Qld (RPEQ) with suitable qualifications and experience in erosion and sediment control. Documentary evidence demonstrating appropriate qualifications in erosion and sediment control must be provided to the Council upon request. Timing: Prior to the commencement of any earth disturbing activities. |
As indicated |
33(d) Attend a pre-start
meeting Arrange and attend a pre-start meeting for ESC with an Officer from Councils ESC Team in Compliance and Regulatory Services (CARS). Note: To request a pre-start meeting from Council's ESC Team send an email to CARS-ESC@Brisbane.qld.gov.au. All relevant documentation, including both the certified ESCP and the certified design certificate, must be attached to this email. Please allow up to 10 business days for your request to be processed. Timing: Attend the pre- start meeting prior to the commencement of any earth disturbing activities. |
As indicated |
33(e) Implement Certified Erosion and
Sediment Control Plan Implement the certified ESCP and maintain all ESC measures in accordance with best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version) and, to the extent of any inconsistency, relevant Brisbane Planning Scheme Codes and Policies. The ESCP and design certificate must be available on site at all times for inspection by Council officers. Any alteration to supplementary or Type 3 ESC measures must be reflected in the certified ESCP. Any alteration to Type 2 or Type 1 ESC measures will require a revised ESCP and design certificate that has been certified by either the CPESC or RPEQ. Timing: While earth disturbing activities are occurring and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
| 34) Retaining Walls Design and construct all
retaining walls and associated fences, in accordance with the relevant Brisbane
Planning Scheme Codes and including the following: |
Prior to site/operational/building work commencing |
34(a) Certification of Retaining
Walls For
retaining walls over 1.0m in height, obtain certification from a Registered
Professional Engineer Queensland that the design and construction of the
retaining wall and ancillary drainage is in accordance with this condition. |
As indicated |
| 35) Construction Management Plan - Major Carry out development in
accordance with a Construction Management Plan prepared in accordance with the
requirements of this condition. |
While site/operational/building work is occurring |
35(a) Submit Construction Management
Plan Submit for the approval
of Development Services a Construction Management Plan for the demolition,
excavation and construction phases of the approved development. Separate
Construction Management Plans may be appropriate for the individual components.
The Construction Management Plan must be in accordance with the relevant
Brisbane Planning Scheme Codes, Workplace Health and Safety Legislation,
Environmental Protection Act, the requirements of any Concurrence Agency, any
other relevant legislative requirements and the following. |
As indicated |
35(b) Construction Management Plan - Pre-
start Meeting Arrange
a Pre-Start meeting with Development Services. |
As indicated |
35(c) Construction Management Plan -
Associated Activities in Road Reserve Obtain relevant approvals to carry out any works
required by the approved Construction Management Plan, including the following,
within the road reserve: |
As indicated |
35(d) Construction Management Plan -
Documentation on Site Legible copies of the approved Construction Management Plan and
current permits must be kept on site and be made available on request at all
times. |
As indicated |
35(e) Construction Management Plan - Works to
be Performed Out of Hours Obtain approval from Development Services for any
work that is to be undertaken outside of normal business hours - 6:30am to
6:30pm, Monday to Saturday. |
As indicated |
35(f) Implement Approved Construction
Management Plan Carry
out the development in accordance with the approved Construction Management
Plan. |
As indicated |
| 36) Protect Existing Infrastructure Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure. Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations. The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements. |
While site/operational/building work is occurring |
36(a) As Constructed Drawings Where alterations to existing infrastructure are required, submit to
Development Services "As Constructed" drawings showing all new and/or
rectification works and an asset register, prepared by a Registered
Professional Engineer Queensland. Timing: Prior to issue of Certificate of
Classification/Final Inspection Certificate or prior to commencement of use,
whichever comes first (MCU or BW), or prior to Council's notation of the plan
of subdivision (ROL) |
As indicated |
36(b) Submit Certification Where alterations to existing
infrastructure are required, submit to Development Services certification from
a Registered Professional Engineer Queensland, confirming that the alterations
have been completed in accordance with the relevant Brisbane Planning Scheme
Codes and any other relevant infrastructure requirements.
Timing: Prior to issue of Certificate of Classification/Final
Inspection Certificate or prior to commencement of use, whichever comes first
(MCU or BW), or prior to Council's notation of the plan of subdivision
(ROL) |
As indicated |
| 37) Certified Site Survey Levels Submit to Development
Services, "As Constructed" drawings prepared by a Registered
Surveyor. The Registered Surveyor must certify that the "As
Constructed" drawings are in accordance with the relevant Brisbane
Planning Scheme Codes and show finished surface level information over the
completed development. Note: The survey information must show surface levels and site contours at 1 metre intervals. All levels must be shown as Reduced Levels to the "Australian Height Datum" (AHD). |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 38) Repair Damage to Kerb, Footpath Or Road Repair any damage to the
existing kerb and channel, footpath or roadway (including removal of concrete
slurry from footways, roads, kerb and channel and stormwater gullies and drainlines) and re-instate existing traffic signs and
pavement markings that have been removed or damaged during any works carried
out in association with the approved development. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 39) Remove Redundant Drainage Outlets Remove any redundant drainage
outlets from the kerb and channel including any associated pipe work across the
footway and reinstate the kerb and channel and the footway area in accordance
with the relevant Brisbane Planning Scheme Codes. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 40) Signs and Line Markings - Internal Prepare signs and line markings drawings. The drawings must be prepared by a Registered Professional Engineer Queensland. The Registered Professional Engineer Queensland must certify that the drawings are in accordance with the relevant Brisbane Planning Scheme Codes and the Manual of Uniform Traffic Control Devices - Queensland Department of Transport and Main Roads -Transport Operations (Road Use Management) Act 1995 showing the traffic signs, pavement markings and traffic control devices. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
40(a) Implement Signs and Line
Marking Carry
out the signs and line marking in accordance with the certified
drawings. |
As indicated |
| 41) Access, Grades, Manoeuvring, Carparks, Signs and
Line Marking Construct
access, parking and manoeuvring for vehicles on site in accordance with the
relevant Brisbane Planning Scheme Codes, as indicated on the approved DRAWINGS
AND DOCUMENTS, including the following: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
41(a) Submit certification Submit to Development
Services, certification from a Registered Professional Engineer Queensland,
that the above requirements have been implemented in accordance with this
condition. |
As indicated |
| 42) Residential Refuse Collection - On Site Provide for the installation and collection of refuse/recycling bins by Brisbane City Council's Waste and Resource Recovery Services. |
At all times |
42(a) Arrange Refuse Collection Arrange for the installation of refuse/recycling bins and for the subsequent collection of refuse including recycling from the site by Brisbane City Council's Waste and Resource Recovery Services. Timing: A minimum of four weeks prior to the commencement of use and then to be maintained. |
As indicated |
42(b) Indemnify Council The owner and any subsequent owner must, by approved form to Waste and Resource Recovery Services, indemnify Council and its agents in respect of any damage to the pavement and other driving surfaces. Timing: When an arrangement for refuse/recycling collection services is made with Brisbane City Council and then to be maintained. |
As indicated |
42(c) Notify Future Owner The owner must notify any future owner/body corporate that the development has been approved on the basis that an indemnity must be provide for refuse collection vehicles to enter the property. Timing: At time of a change of ownership. |
As indicated |
| 43) Refuse Storage - On Site Collection Provide a roofed and wholly screened refuse enclosure utilising materials consistent with the development or a dedicated refuse storage room, as shown on the approved plans and documents. The enclosure/refuse storage room must be of a design to accommodate the quantity of refuse and recycling including source separation to allow for low servicing collection of the development. Bins must be located in an area which allows them to be manoeuvred from the bin storage area to the designated internal collection point. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 44) Work for Transport Network - Road (Non-trunk) -
External Construct the following roadwork with any associated drainage, footpath, site access and services for the Transport Network (Road) shown on the approved plan ‘Site Plan Ground Floor (L1)’, Drawing No. 1710_DA5111 Rev. R , Received 12-APR-2024 (Amended in Red 12-APR-2024), and in accordance with the relevant Brisbane Planning Scheme Codes, the Manual of Uniform Traffic Control Devices - Queensland Department of Transport and Main Roads -Transport Operations (Road Use Management) Act 1995, and the AUSTROADS design standards. Footpath outcome is to be to a City Street Minor Standard as shown on approved Landscape Concept Design Report – Design Intent (Page 02) and Site Plan (Page 03), received 14 June 2021, and associated Brisbane Standard Drawings (BSD) and the Infrastructure Design Planning Scheme Policy: - new type E concrete kerb and channel and associated drainage along the full length of the East/West road frontage of the site on a 4.25 metre alignment (or as indicated otherwise on approved plans taking into account build-outs and intended parking as shown on plans); - a District type road pavement from the lip of the new kerb and channel to the edge of the existing road pavement with any appropriate tapers (the minimum width of road construction/reconstruction must be 1.2 metres); Note: Irrespective of the actual widening, the finished road pavement crown must be located along the centreline of the final pavement width - signs and pavement markings along the East/West road frontage. Note: This condition is imposed under section 665 of the Sustainable Planning Act 2009 |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
44(a) Submit Functional Layout
Drawings Submit
for the approval of Development Services functional layout drawings prepared
and certified by a Registered Professional Engineer Queensland in accordance
with the APPROVED DRAWINGS AND DOCUMENTS and the relevant Brisbane Planning
Scheme Codes.
Note: This approval must be obtained prior to
the submission of drawings for Roadwork and Stormwater Drainage and Signs and
Pavement Marking. Timing: Prior to site/operational/building work commencing |
As indicated |
44(b) Submit Roadworks and Stormwater
Drainage Drawings Submit for the approval of Development Services Roadworks and Stormwater Drainage Drawings prepared and certified by a Registered Professional Engineer Queensland in accordance with the APPROVED DRAWINGS AND DOCUMENTS and the relevant Brisbane Planning Scheme Codes. Timing: Prior to site/operational/building work commencing |
As indicated |
44(c) Submit Traffic Signal Design
Drawings Submit
for the approval of Development Services Traffic Signal Design drawings
prepared and certified by a Registered Professional Engineer Queensland in
accordance with this condition. Note:
The Traffic Signal Design drawings must be endorsed by Brisbane Infrastructure
-Transport & Traffic, prior to submission of the Traffic Signal Design
Drawings. Timing: Prior to site/operational/building work commencing |
As indicated |
44(d) Submit Signs and Pavement
Drawings Submit
for the approval of Development Services Signs and Pavement Marking drawings
prepared and certified by a Registered Professional Engineer of Queensland in
accordance with the APPROVED DRAWINGS AND DOCUMENTS and the relevant Brisbane
Planning Scheme Codes. Timing: Prior to site/operational/building work commencing |
As indicated |
44(e) Pre-Start Meeting Arrange a pre-start meeting with
Development Services. Timing: Prior to site/operational work commencing |
As indicated |
44(f) Implement Approved
Drawings Construct the works in accordance with the above approved
drawings. Timing: Prior to on-maintenance acceptance |
As indicated |
44(g) Submit As Constructed
Drawings Submit to Development Services "As
Constructed" drawings including an asset register and a pre-On-Maintenance
Inspection Checklist, prepared by a Registered Professional Engineer
Queensland. |
As indicated |
44(h) Submit Certification Submit to Development Services
certification from a Registered Professional Engineer Queensland, confirming
that the works have been completed in accordance with the above approved
drawings. Timing: Prior to on-maintenance inspection |
As indicated |
| 45) Site Drainage - Major Provide an internal drainage system to collect
stormwater run-off from all proposed lots, roofed and developed surface areas
and any run-off onto the site from adjacent areas and convey the collected run-
off to a lawful point of discharge, in accordance with the relevant Brisbane
Planning Scheme Codes. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
45(a) Submit Site Drainage
Drawings Submit
and obtain approval from Development Services, site drainage drawings and
engineering calculations, prepared and certified by a Registered Professional
Engineer Queensland, in accordance with the relevant Brisbane Planning Scheme
Codes. |
As indicated |
45(b) Implement Approved
Drawings Carry
out the works in accordance with the approved site drainage drawings. |
As indicated |
45(c) Submit As Constructed
Drawings Submit
to Development Services "As Constructed" drawings prepared by a
Registered Professional Engineer Queensland. Timing:
Prior to issue of Certificate of Classification/Final Inspection Certificate or
prior to commencement of use, whichever comes first (MCU or BW), or prior to
Council's notation of the plan of subdivision (ROL) |
As indicated |
45(d) Submit Certification Development Services certification from
a Registered Professional Engineer Queensland, confirming that the works have
been completed in accordance with the above approved site drainage
drawings. Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
As indicated |
| 46) Ponding of Stormwater Carry out the approved development to ensure that
adjoining properties and roads are protected from ponding or nuisance from
stormwater as a result of the works. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 47) Stormwater Quality (MCU) Manage stormwater quality in
accordance with this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
47(a) Implement Stormwater Quality
Management Implement the stormwater quality treatment strategy outlined within the
APPROVED DRAWINGS AND DOCUMENTS and any engineering drawings and documents
approved pursuant to conditions contained in this development approval.
Note: This condition does not require any further
approval from Council. Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), and then to be maintained |
As indicated |
47(b) Water Quality Maintenance Management
Plan Prepare and implement a Water Quality Maintenance
Management Plan in accordance with the Water by Design ‘WSUD Technical
Design Guidelines for South East Queensland’. The plan must be prepared and certified by a
Registered Professional Engineer Queensland. Note: This condition does not require any further
approval from Council. Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), and then to be maintained |
As indicated |
47(c) Submit Certification Submit to Development Services
certification from a Registered Professional Engineer Queensland confirming
that the stormwater quality treatments strategy required pursuant to part (a)
of this condition has been implemented and where a proprietary stormwater
quality improvement device has been used to meet the water quality objectives,
the device has been approved by Brisbane City Council for use in achieving the
water quality targets.
Note: Manufacturers that have approved devices by Brisbane City
Council will be able to provide evidence of Council approval for
use. Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW) |
As indicated |
47(d) Maintain Management Plans Maintain the certified Water Quality Maintenance Plan
and the stormwater quality treatment strategy required pursuant to part (a) of
this condition. Include the Water Quality Maintenance Plan in any building
management strategy, building management statement or community management
statement. Timing: To be maintained |
As indicated |
| 48) Service Conduits and Mains Provide and install all service conduits and meet
the cost of any alterations to public utility mains, existing mains, services
or installations that are required to carry out the approved development. These
works must be in accordance with the relevant Brisbane Planning Scheme Codes,
and include the following, where applicable: Note: Applicants must
liaise with the appropriate service authorities. Typical underground services
and/or conduits to be constructed include power, phone, telecommunications,
sewer (including private combine drains) stormwater and gas, if
applicable. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
48(a) Submit As Constructed
Drawings Submit to Development Services "As
Constructed" drawings, including an asset register, prepared by a
Registered Professional Engineer Queensland.
|
As indicated |
48(b) Submit Certification Submit to Development Services certification from a
Registered Professional Engineer Queensland, confirming that the works have
been completed in accordance with the requirements of this
condition. Timing: Prior to issue of Certificate of Classification/Final
Inspection Certificate or prior to commencement of use, whichever comes first
(MCU or BW), or prior to Council's notation of the plan of subdivision
(ROL) |
As indicated |
| 49) Telecommunications Submit to Development Services, certification from
an authorised telecommunications carrier/contractor, that the following works
and infrastructure have been undertaken and installed in accordance with
telecommunications industry standards: a) Provide telecommunications to the subject buildings, lead-in conduits and equipment space in a suitable location within the buildings, to suit the carrier of choice. b) If new pits and conduit infrastructure are required to be installed within the road reserve fronting the site, it must be suitably sized to cater for future installation of fibre optic cables. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 50) Agreement with Electricity Supplier Submit to Development
Services, evidence of an agreement with an electricity supplier to provide
necessary services to the development in accordance with the relevant Brisbane
Planning Scheme Codes. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 51) Permanent Vehicle Crossover Provide a 6.5 metre wide Type
B2 permanent vehicle crossover to the North/South road frontage of the site in
accordance with the relevant Brisbane Planning Scheme Codes and located as
shown on the approved DRAWINGS AND DOCUMENTS. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 52) Further Development Permit required This Preliminary Approval (Carrying Out Building Works) does not include assessment under the
Building Act and does not permit building work to occur. Prior to the commencement of any building work,
Development Permit(s) for Carrying Out Building Work
will be required. |
As indicated |
| 53) Construction Noise and Dust Emissions Pursuant to the
Environmental Protection Act 1994, all development involving the emission of
noise and dust from building and/or construction activities, must ensure that
the emissions are in accordance with the requirements of the Act. The
Environmental Protection Act 1994 prescribes that: 1. A person
must not carry out building work in a way that makes an audible noise-
- on a business day or Saturday, before 6.30a.m. or after 6.30p.m; or
- on any other day, at any time.
2. The reference in subsection (1)
to a person carrying out building work- - includes a person carrying out building work under an owner-builder permit; and - otherwise does
not include a person carrying out building work at premises used by the person
only for residential purposes. Note: A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management delegate Development Services. |
As indicated |
| 54) Concurrence Agency Conditions The Department of
Transport and Main Roads as concurrence agency has imposed the conditions
contained in the letter dated 25 September 2013, or as
amended. |
As indicated |
| 55) Water and Wastewater Services for water and wastewater (sewerage) are
no longer under the jurisdiction of Brisbane City Council. Authorisation to
connect the approved development to the water/wastewater networks and for
property service connections requires a Water Approval under the South-East
Queensland Water (Distribution and Retail Restructuring) Act 2009. Any
necessary Water Approval must be obtained from the relevant distributor-
retailer (currently operating as Queensland Urban Utilities for the Brisbane
City Council area). For the purpose of compliance assessment of a subdivision plan pursuant to Schedule 19 of the Sustainable Planning Regulation 2009 (whether in relation to a development permit for Reconfiguring a Lot or a Building Format Plan subsequent to a development permit for a Material Change of Use), documentary evidence, issued by the relevant distributor-retailer, must be provided to Council to verify that the conditions of any necessary Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009, have been complied with. |
As indicated |
| 56) Fire Ant Movement Controls To prevent the spread of fire ants, the
Queensland Government has implemented movement controls in areas of Queensland
(biosecurity zones) where this pest species has been detected. These controls
apply to individuals and commercial operators, and restrict the movement of
materials that could carry fire ants which include soil, turf, potted plants,
mulch, baled hay or straw, animal manures, mining or quarry
products. Breaches of these controls can potentially
impact the community, economy and the environment. Penalties for non-compliance
with movement controls within fire ant biosecurity zones apply under the
Biosecurity Act 2014. If you are unsure of your obligations contact the relevant Queensland State Government Department (Biosecurity Queensland, Department of Agriculture and Fisheries) |
As indicated |
| Permit to Which These Conditions Relate: | DA - PA - Building Work |
| Activity(ies): | Multi-Unit Dwelling |
| Stage: | Stage 3: Multiple dwelling (41 units) |
| 57) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS
AND DOCUMENTS and the Development Approval Package must be available on
site. |
While site/operational/building work is occurring |
| 58) Carry Out the Approved Development Carry out the approved development generally in
accordance with the approved DRAWINGS AND DOCUMENTS. |
While site/operational/building work is occurring and then to be maintained |
| 59) Complete All Building Work Complete all building work associated with this
development approval, including work required by any of the conditions included
in the Development Approval Package. Such building work must be carried out
generally in accordance with the approved DRAWINGS AND DOCUMENTS, and, where
the building work is assessable development, in accordance with a current
development approval. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
| 60) Maintain the Approved Development Maintain the approved development generally in
accordance with the approved DRAWINGS AND DOCUMENTS, and any relevant Council
engineering or other approval required by the conditions. |
To be maintained |
| 61) Further Development Permit required This Preliminary Approval (Carrying Out Building Works) does not include assessment under the
Building Act and does not permit building work to occur. Prior to the commencement of any building work,
Development Permit(s) for Carrying Out Building Work
will be required. |
As indicated |
| 62) Construction Noise and Dust Emissions Pursuant to the
Environmental Protection Act 1994, all development involving the emission of
noise and dust from building and/or construction activities, must ensure that
the emissions are in accordance with the requirements of the Act. The
Environmental Protection Act 1994 prescribes that: 1. A person
must not carry out building work in a way that makes an audible noise-
- on a business day or Saturday, before 6.30a.m. or after 6.30p.m; or
- on any other day, at any time.
2. The reference in subsection (1)
to a person carrying out building work- - includes a person carrying out building work under an owner-builder permit; and - otherwise does
not include a person carrying out building work at premises used by the person
only for residential purposes. Note: A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management delegate Development Services. |
As indicated |
| 63) Water and Wastewater Services for water and wastewater (sewerage) are
no longer under the jurisdiction of Brisbane City Council. Authorisation to
connect the approved development to the water/wastewater networks and for
property service connections requires a Water Approval under the South-East
Queensland Water (Distribution and Retail Restructuring) Act 2009. Any
necessary Water Approval must be obtained from the relevant distributor-
retailer (currently operating as Queensland Urban Utilities for the Brisbane
City Council area). For the purpose of compliance assessment of a subdivision plan pursuant to Schedule 19 of the Sustainable Planning Regulation 2009 (whether in relation to a development permit for Reconfiguring a Lot or a Building Format Plan subsequent to a development permit for a Material Change of Use), documentary evidence, issued by the relevant distributor-retailer, must be provided to Council to verify that the conditions of any necessary Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009, have been complied with. |
As indicated |
| 64) Fire Ant Movement Controls To prevent the spread of fire ants, the
Queensland Government has implemented movement controls in areas of Queensland
(biosecurity zones) where this pest species has been detected. These controls
apply to individuals and commercial operators, and restrict the movement of
materials that could carry fire ants which include soil, turf, potted plants,
mulch, baled hay or straw, animal manures, mining or quarry
products. Breaches of these controls can potentially
impact the community, economy and the environment. Penalties for non-compliance
with movement controls within fire ant biosecurity zones apply under the
Biosecurity Act 2014. If you are unsure of your obligations contact the relevant Queensland State Government Department (Biosecurity Queensland, Department of Agriculture and Fisheries) |
As indicated |
| Permit to Which These Conditions Relate: | DA - PA - Material Change of Use |
| Activity(ies): | Multi-Unit Dwelling |
| Stage: | Stage 3: Multiple dwelling (41 units) |
| 65) Attend a pre-start meeting Arrange and attend a pre-start meeting with Building and Construction Management Team, Development Services. Council will only attend the pre-start meeting once all applicable compliance fees have been paid. Note: To request a pre-start meeting and associated lodgement requirements, refer to Council's website and search 'Pre-start meeting'. Timing: Prior to site/operational/building work commencing. |
As indicated |
| 66) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS
AND DOCUMENTS and the Development Approval Package must be available on
site. |
While site/operational/building work is occurring |
| 67) Carry Out the Approved Development Carry out the approved development generally in
accordance with the approved DRAWINGS AND DOCUMENTS. |
While site/operational/building work is occurring and then to be maintained |
| 68) Complete All Building Work Complete all building work associated with this
development approval, including work required by any of the conditions included
in the Development Approval Package. Such building work must be carried out
generally in accordance with the approved DRAWINGS AND DOCUMENTS, and, where
the building work is assessable development, in accordance with a current
development approval. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
| 69) Maintain the Approved Development Maintain the approved development generally in
accordance with the approved DRAWINGS AND DOCUMENTS, and any relevant Council
engineering or other approval required by the conditions. |
To be maintained |
| 70) External Details External details of the building, facade treatment and external
materials, colours and finishes must be consistent with the approved DRAWINGS
AND DOCUMENTS. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 71) Overall Height The overall height of the proposed building(s) must be in accordance with the floor and roof levels and overall height shown on the APPROVED DRAWINGS AND DOCUMENTS. |
While site/operational/building work is occurring and then to be maintained |
71(a) Submit Certification Submit to Development
Services certification from a registered surveyor confirming that the “as
constructed” floor and roof levels and overall height are in accordance
with the requirements of this condition. |
As indicated |
| 72) Driveway Material and Finishes Provide materials and finishes to the driveway
and external carparking surfaces that reduce the
visual impact of these areas when viewed from the street. One or a combination
of the following must be used: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 73) Screen Air Conditioning and Other Plant
Enclosures Install and maintain suitable
screening to all air conditioning, lift motor rooms, plant and service
facilities located at the top of or on the external face of the building. The
screening structures must be constructed from materials that are consistent
with materials used elsewhere on the facade of the building. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 74) Screening Multiple Dwelling / Dual
Occupancy Provide screening in accordance with the approved DRAWINGS AND
DOCUMENTS and the following: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 75) Natural Assets Local Law (NALL) - Protected
Vegetation On Site Ensure
that all necessary permits under the NALL have been issued to carry out works
on protected vegetation on the site. NOTE:
Apply to Development Services for all the necessary permits under the
NALL. Timing: Prior to carrying out works on protected vegetation |
As indicated |
| 76) Fauna Management - Fauna Spotter Catcher (High
Risk) Engage a licensed Fauna Spotter Catcher (qualified by the relevant Queensland State Government Authority) to manage the protection and relocation of any fauna prior to and during vegetation/ecological feature clearing. |
Prior to site/operational/building work commencing and then to be maintained |
76(a) Prior to Vegetation/ Ecological Feature
Clearing Submit
to Development Services certification from the licensed Fauna Spotter Catcher
that the site has been fully inspected and any necessary fauna protection
measures or relocation procedures have been implemented. Timing: Prior to vegetation/ ecological feature clearing commencing. |
As indicated |
76(b) During Vegetation/ Ecological Feature
Clearing The
licensed Fauna Spotter Catcher must be present on site during all clearing
operations to monitor works and to respond to any fauna situations that may
arise. If any fauna is identified in vegetation or ecological features to be
removed during clearing operations, work must cease immediately on that
vegetation or ecological feature. The licensed Fauna Spotter Catcher must
supervise the relocation of any identified fauna prior to vegetation/
ecological feature clearing recommencing. Timing: While vegetation/ ecological feature clearing is occurring |
As indicated |
76(c) Submit Certification Submit to Development Services
certification from the licensed Fauna Spotter Catcher that vegetation/
ecological feature clearing was carried out in accordance with this
condition. Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
As indicated |
| 77) Vegetation Management (Submit Plan) Manage vegetation on the site in accordance with a Vegetation Management Plan approved pursuant to this condition. |
While site/operational/building work is occurring and then to be maintained |
77(a) Submit Vegetation Management
Plan Submit and obtain approval for a Vegetation Management Plan from Development Services. This plan must be prepared by a qualified and experienced environmental practitioner, with supporting documentation from the Project Arborist (minimum AQF Level 5 in Arboriculture with a minimum of 5 years' experience in arboricultural principles and practices, including tree risk hazard assessment and reporting with current public liability insurance to $20 million, and a professional indemnity of $2 million), where works are required within the Tree Protection Zone (TPZ) of retained trees. The Vegetation Management Plan must
be in the form of scaled plans and supporting documentation that are generally
in accordance with the APPROVED DRAWINGS AND DOCUMENTS, relevant Brisbane
Planning Scheme Code and include the following: Timing: Prior to site / operational / building work commencing and prior to or concurrently with any other operational works application. |
As indicated |
77(b) Project Arborist Appoint as Project Arborist, a qualified Arborist (minimum AQF Level 5 in Arboriculture with a minimum of 5 years' experience in arboricultural principles and practices, including tree risk hazard assessment and reporting with current public liability insurance to $20 million, and a professional indemnity of $2 million.). Provide evidence of this appointment to the Ecologist Development Services. Timing: Prior to arranging a pre-start meeting. |
As indicated |
77(c) Pre-Start Meeting When measures are in place to identify and protect vegetation on site (such as tree protection fencing), arrange a pre-start meeting with the Ecologist Development Services. Applicable compliance and inspection fees must be paid to Council, in full, prior to the meeting being held. The Project Arborist and qualified Fauna Spotter Catcher must attend the pre-start meeting. Note: Timing: Prior to site / operational / building work commencing. |
As indicated |
77(d) Implement Approved Vegetation
Management Plan Carry out the works in accordance with the approved Vegetation Management Plan. Note: The Project Arborist
must: Timing: While site / operational / building work is occurring. |
As indicated |
77(e) Submit Certification Submit to Development Services, certification from the qualified and experienced environmental practitioner and the Project Arborist (minimum AQF Level 5 in Arboriculture with a minimum of 5 years' experience in arboricultural principles and practices, including tree risk hazard assessment and reporting with current public liability insurance to $20 million, and a professional indemnity of $2 million.), certifying that the work(s) have been carried out in accordance with the approved Vegetation Management Plan. Certification must
include: Timing: Upon completion of each phase of the approved Vegetation Management Plan and prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
77(f) Retain and Protect
Vegetation Retain and protect vegetation in accordance with the approved Vegetation Management Plan. Timing: To be maintained. |
As indicated |
| 78) Streetscape Works - Neighbourhood Street
Minor GARDNER RD frontage: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
78(a) Concrete Path Install a 1.2m wide broom finished standard Portland grey concrete path. The edge of the path is to be setback 1300mm from the back of kerb.
Where the path cannot be installed on this alignment due to conflicts such as
street trees, or power poles, ensure the path is installed a minimum distance
of: If the above requirements cannot be achieved, contact the Landscape Architecture Team via email: specialistservices@brisbane.qld.gov.au. Transition to existing paths on verges that adjoin the development. The transition is to occur fronting the adjoining developments, not the subject site. Note: standard path alignments are shown on Brisbane Standard Drawing BSD-5201 sheet 2 but will vary depending on verge width and location. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Photographic evidence of concrete path. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
78(b) Submit As-Constructed
Drawings Submit to Development Services As Constructed plans including an asset register, checked by a Registered Professional Engineer Queensland, certifying that the concrete path works have been completed in accordance with relevant Brisbane Planning Scheme Codes/Policies. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT As constructed drawings signed by an RPEQ. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
78(c) Turf Install turf to the full width of the verge excluding any concrete path required by this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Photographic evidence of installed turf. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
78(d) Street Tree(s) Enter into and implement an arrangement with the Program Planning and Integration Regional Coordinator Arboriculture in relation to the required provision of the street tree planting in accordance with the above sections of the Infrastructure Design Planning Scheme Policy, including the number, species, location, installation and maintenance of the required street tree(s) as determined by Program Planning and Integration. Note: Street trees should not be planted until all utilities have been installed. Timing: Prior to issue of Certificate of Occupancy / Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT A copy of the agreement with Program Planning and Integration and/or photographic evidence of installed trees. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 79) Streetscape Works - Centre Street FARMER ST frontage: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
79(a) Submit Level Details Submit to Development
Services, and obtain approval for, details of the future finished levels of the
site and building entries (both pedestrian and vehicular) to demonstrate verge
levels and crossfalls complying with the Infrastructure Design Planning Scheme
Policy including section 3.7.3.5. The details must be provided by an RPEQ in
consultation with a qualified Landscape Architect and include the
following: Timing: Prior to site/operational/building work occurring. |
As indicated |
79(b) Submit Plan for Works in
Verge Submit, to an obtain approval from, Development Services, a detailed Landscape Works in Streetscape Plan for the required improvement works in accordance with the requirements of the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD) and the Infrastructure Design Planning Scheme Policy including section 3.7.4.3. The detailed Landscape Works in Streetscape Plan must be prepared at a scale of 1:100 by a qualified Landscape Architect and include the following: SPECIFIC REQUIREMENTS - Extend the full width pavement design at the
intersection with Gardner Rd to include the verge fronting the corner
truncation. DOCUMENTATION REQUIREMENTS -
Finished surface levels at lot boundary and kerb. Timing: Prior to building work above ground level commencing. |
As indicated |
79(c) Pre-Start Meeting Arrange and attend a pre-start meeting with Landscape Architecture Team, City Planning and Economic Development. Council will only attend the pre-start meeting once all applicable compliance and inspection fees have been paid. The project landscape architect must be present at the pre-start meeting. Timing: Prior to any work commencing to comply with this condition. |
As indicated |
79(d) Implement Streetscape
Works Remove the existing footway including affected street signage for the full length of the frontage. Carry out the works in accordance with the approved detailed Landscape Works in Streetscape Plan and to a standard and using materials in accordance with the requirements of the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD) and the Infrastructure Design Planning Scheme Policy section 3.7.4.3. Note: All existing regulatory signage must be secured and repositioned as agreed with Program Planning and Integration. Note: At all times during construction provision must be made for people with a visual impairment. Where it is unavoidable that a
section of an existing Braille trail is to be blocked, or an object temporarily
located to intrude within the 1000 mm clearway on either side of the Braille
trail, the following actions must be undertaken to comply with the current
version of AS1428: Note: Lodge with and receive approval from Development Services for an 'Application for Permits Relating to Roads and Footway' prior to carrying out the approved works. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to the commencement of use, whichever comes first. |
As indicated |
79(e) Submit As-Constructed
Drawings Submit to Development Services Specialist Services As Constructed drawings including an asset register, prepared by a Registered Professional Engineer Queensland, certifying that the streetscape works have been completed in accordance with the approved detailed Landscape Works in Streetscape Plan and to a standard and using materials in accordance with the requirements of the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD) and the Infrastructure Design Planning Scheme Policy section 3.7.4.3. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
79(f) On-Maintenance Acceptance Arrange an on- maintenance inspection with Development Services and obtain written confirmation that the works have been accepted on-maintenance. Provide proof of Public Liability Insurance ($20 million) for the on- maintenance period. Lodge a bond for the streetscape works maintenance period of the works. The bond must be calculated in accordance with the relevant Brisbane Planning Scheme Codes (5% of total value of the landscape works or minimum of $5,000.00 whichever is greater). Note: To arrange an on-maintenance inspection with Development Services an email must be sent to specialistservices@brisbane.qld.gov.au. Note: A maintenance bond can consist of either a bank guarantee or monetary payment lodged with Council. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
79(g) On-Maintenance Period Provide a minimum of 12 months maintenance to the streetscape works and rectify any defects identified at the on-maintenance inspection and those arising during the on-maintenance period. Timing: Minimum 12 months from acceptance on- maintenance AND until the works are approved off-maintenance by Council. |
As indicated |
79(h) Off-Maintenance
Acceptance On completion of the on-maintenance period, arrange an off-maintenance inspection with Development Services and obtain written confirmation from Council that the work is accepted off-maintenance. Ensure all defects are rectified prior to making an appointment for off- maintenance inspection. Note: To arrange an off-maintenance inspection with Development Services an email must be sent to specialistservices@brisbane.qld.gov.au. Note: If the off- maintenance inspection is successful the maintenance bond will be released. Timing: On completion of the on-maintenance period. |
As indicated |
| 80) Landscape the Site - Self Certification Landscape the site in accordance with the requirements of this condition. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
80(a) Detailed Landscape Plan for Self-
Certification Prepare a Detailed Landscape Plan at a scale of 1:100 for all on-site landscape works including planting areas identified on the approved Landscape concept plan (amended in red 20/05/2024). The plan must be prepared by a Qualified Landscape Architect and must comply with the relevant Brisbane Planning Scheme Codes. The plan must include the
following: Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
80(b) Multiple Unit Dwelling In addition to the
requirements listed above, the plan must include the following: Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
80(c) Certify Detailed Landscape
Plan On completion of the Detailed Landscape Plan, submit to Development
Services: Timing: Prior to building work commencing. PROOF OF FULFILMENT A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to building work commencing. |
As indicated |
80(d) Implement Certified Detailed Landscape
Plan Carry out the landscape work in accordance with the above certified detailed Landscape Plan. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
80(e) Certify Work On completion of the
landscape work, submit to Development Services: Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT An as constructed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
80(f) Maintain Landscape Work Maintain the landscape work, including deep planting, in accordance with the certified Detailed Landscape Plan. Timing: To be maintained. |
As indicated |
| 81) On-site Erosion (Medium Risk) Manage on-site erosion and the release of sediment or sediment laden water from the site at all times by implementing best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version). Timing: Prior to commencement of any land disturbing activities and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
81(a) Manage earth disturbance on-
site (i) Drainage control measures must be implemented and maintained to minimise water flow onto areas of exposed earth. (ii) Sediment and erosion control measures must be implemented and maintained to prevent soil loss from earth disturbance areas and prevent deposition beyond earth disturbance areas. (iii) No release of contaminants to land beyond on-site area of earth disturbance other than releases that achieve water pollutant concentration release limits of: A. 50mg/L TSS (Total Suspended Solids); B. Turbidity, Nephelometric Turbidity Units (NTU) value less than 10% above background, 75 NTU, or as agreed in writing by an Officer from Councils Erosion and Sediment Control (ESC) Team in Compliance and Regulatory Services; C. pH between 6.5 and 8.5 at all times. (iv) Maintain a written record to demonstrate that water discharges from the site, including any dewatering operations, meet the release limits as detailed in (iii) for water discharge(s) from the site that occur during or immediately after a rainfall event, and during normal business hours. The water quality of the discharge flows must be measured at each discharge point from the site, including but not limited to sediment basin outlets, other applicable sediment control devices, the site water drainage system, and recorded against the release limits at least once on each calendar day until such discharge stops. Timing: Prior to commencement of any earth disturbing activities and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
81(b) Provide Land Occupier Notification to
Council (i) Notify Council's ESC Team of proposed land occupier/s by sending an email to CARS-ESC@Brisbane.qld.gov.au (ii) If the land is to be occupied by any person other than the registered landowner then advice must be provided to Council that confirms the name, contact information and the duration of any proposed occupation of the land. Timing: Prior to commencement of any earth disturbing activities. |
As indicated |
81(c) Prepare Erosion and Sediment Control
Plan Prepare an Erosion and Sediment Control Plan (ESCP) in accordance with best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version) and, to the extent of any inconsistency, relevant Brisbane Planning Scheme Codes and Policies. Obtain a design certificate in accordance with the relevant Brisbane Planning Scheme Codes and Policies. The ESCP and design certificate must be certified by a Certified Professional in Erosion and Sediment Control (CPESC) or a Registered Professional Engineer Qld (RPEQ) with suitable qualifications and experience in erosion and sediment control. Documentary evidence demonstrating appropriate qualifications in erosion and sediment control must be provided to the Council upon request. Timing: Prior to the commencement of any earth disturbing activities. |
As indicated |
81(d) Attend a pre-start
meeting Arrange and attend a pre-start meeting for Erosion and Sediment Team, Compliance and Regulatory Services (CARS). All relevant documentation, including the certified erosion and sediment control plan and the certified design certificate must be submitted with the request. Note: To request a pre-start meeting refer to Council's website and search 'Pre-start meeting'. - A minimum 10 working days' notice is required. Timing: Prior to the commencement of any earth disturbing activities. |
As indicated |
81(e) Implement Certified Erosion and
Sediment Control Plan Implement the certified ESCP and maintain all ESC measures in accordance with best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version) and, to the extent of any inconsistency, relevant Brisbane Planning Scheme Codes and Policies. The ESCP and design certificate must be available on site at all times for inspection by Council officers. Any alteration to supplementary or Type 3 ESC measures must be reflected in the certified ESCP. Any alteration to Type 2 or Type 1 ESC measures will require a revised ESCP and design certificate that has been certified by either the CPESC or RPEQ. Timing: While earth disturbing activities are occurring and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
| 82) Maintenance Period for Engineering Work Maintain the work required by the Engineering condition(s) imposed on this development approval and rectify any defects in accordance with the requirements detailed in this condition. Note: Guidance for requesting a pre-start and co- ordinating the On/Off Maintenance process can be found on Council's website (https://www.brisbane.qld.gov.au/planning-and-building/applying-and-post- approval/on-and-off-maintenance-approvals). Timing: During the on-maintenance period. |
As indicated |
82(a) On-Maintenance Acceptance Arrange an on- maintenance inspection with Development Services and obtain written confirmation from Council that the work has been completed in accordance with the requirements of the condition and is accepted on-maintenance. Provide proof of Public Liability Insurance ($20 million) for the on- maintenance period. Lodge a maintenance security for the on-maintenance period. The security must be calculated as 5% of the value of the constructed work or $10,000.00, whichever is greater. Note: A maintenance security may consist of either a bank guarantee or monetary payment lodged with Council. Refer to Council's Infrastructure Installation and Construction Requirements Manual for further details about the on-maintenance procedure and requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
82(b) On-Maintenance Period Provide a minimum 12 months maintenance to the work from the time the work is accepted on- maintenance by Council. During this period maintain the work and rectify any defects identified at the on-maintenance inspection and those arising during the on-maintenance period. Note: The on-maintenance period may be extended by Council pending concerns and/or unsatisfactory performance during the maintenance period. Timing: A minimum 12 months from acceptance on-maintenance. |
As indicated |
82(c) Off-Maintenance
Acceptance On completion of the maintenance period arrange an off-maintenance inspection with Development Services and obtain written confirmation from Council that the work is accepted off-maintenance. Ensure all defects are rectified prior to making an appointment for off- maintenance Inspection. Note: If the inspection is successful the maintenance security will be released. Timing: On completion of the on-maintenance period. |
As indicated |
| 83) Information Signage Erect an information sign on the subject property in
accordance with Council's general requirements for signage and in accordance
with the requirements outlined below: Timing: Prior to site works commencing and then to be maintained until completion of the development for all stages. |
As indicated |
| 84) Engineering Pre-Start Meeting Arrange and attend a pre-start meeting with Engineering Services, Development Services. Council will only attend the pre-start meeting once all applicable compliance and inspection fees have been paid. Note: Prior to arranging an engineering pre-start meeting, review the Pre-start Meeting Guidelines - Civil Engineering Works kit. To request a pre-start meeting and associated lodgement requirements, refer to Council's website and search 'Pre- start meeting'. Timing: Prior to site/operational/building work commencing. |
As indicated |
| 85) Construction Management Plan - Major Carry out development in a method consistent with a Construction Management Plan (CMP) prepared in accordance with the requirements of this condition. |
While site/operational/building work is occurring |
85(a) Construction Management Plan - Submit
Plan Submit to, and obtain compliance approval from, Development Services a detailed Construction Management Plan for the site preparation, demolition, excavation and construction phases of the approved development. The Construction Management Plan must be in accordance with the relevant Brisbane Planning Scheme Codes and address the following matters, both internal to and external to the development site: (i) Location of and
impacts to any Council vegetation (i.e. street trees/park trees/garden
beds) (vi) Details of all
proposed work zones and/or lane closures, including justification; Note: Pre-approval of work zones and/or lane closures associated with construction of the development will be managed by Development Services however the Construction Management Plan must be supported by "approval in principle" or written approvals from other relevant Council sections or other governing bodies responsible for any other potentially impacted infrastructure. The list of relevant infrastructure and contacts is available on Council's website - Search 'Constructions Management Plan'. Timing: Prior to site/operational/building work commencing. |
As indicated |
85(b) Construction Management Plan -
Dilapidation Report Submit a dilapidation report to engineeringservices@brisbane.qld.gov.au detailing the pre-existing condition of the roadway, both footways, both verges and Council infrastructure, including vegetation, for 100m from the site entry in both directions or to the next street intersection (if less than 100m from the site entry) in both directions. Timing: Prior to the pre-start meeting. |
As indicated |
85(c) Construction Management Plan -
Documentation on Site Legible copies of the approved Construction Management Plan and current permits must be kept on site and be made available on request by Council, at all times. The requirements of the CMP must be included in all induction of principal and subcontractors utilised in the development. An outline of the induction provided to contractors may be requested by Council to confirm compliance with this condition. Timing: While site/operational/building work is occurring. |
As indicated |
85(d) Construction Management Plan - Works to
be Performed Out of Hours Obtain an approval from Development Services for any
work that is proposed to be undertaken outside of normal business hours -
6:30am to 6:30pm, Monday to Saturday. |
As indicated |
85(e) Construction Management Plan -
Implement Plan Carry out the development in accordance with the approved Construction
Management Plan. |
As indicated |
| 86) Protect Existing Infrastructure Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure. Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations. The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements. |
While site/operational/building work is occurring |
86(a) As Constructed Drawings - Alterations
to Existing Infrastructure Submit to Development Services As Constructed drawings showing all new and/or rectification works and an asset register, prepared by a Registered Professional Engineer Queensland. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 87) Certified Site Survey Levels Submit to Development
Services, "As Constructed" drawings prepared by a Registered
Surveyor. The Registered Surveyor must certify that the "As
Constructed" drawings are in accordance with the relevant Brisbane
Planning Scheme Codes and show finished surface level information over the
completed development. Note: The survey information must show surface levels and site contours at 1 metre intervals. All levels must be shown as Reduced Levels to the "Australian Height Datum" (AHD). |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 88) Remove Improvements & Obstructions From Truncation
and Dedication Remove
all improvements (fences, gates, letter boxes, garden beds and plots and other
constructed items, etc.) and obstructions (existing earth banks, vegetation,
etc.) from the area of the corner truncation(s) and/or area of dedicated road
and reinstate the area as footway in accordance with the relevant Brisbane
Planning Scheme Codes. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
88(a) Certify the Work Submit to Development
Services certification from a Registered Surveyor or Registered Professional
Engineer Queensland that the above work has been completed in accordance with
this condition. |
As indicated |
| 89) Filling and / or Excavation (Minor) Filling and/or excavation works on the site must be in accordance with the APPROVED PLANS and the relevant Brisbane Planning Scheme Codes. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
89(a) Prepare Earthworks
Drawings Earthworks drawings must be prepared and certified by a Registered Professional Engineer Queensland in accordance with the relevant Brisbane Planning Scheme Codes. The drawings must include the
following: Timing: Prior to site/operational/building work commencing. Note: The Earthworks drawings are not required to be submitted for Council approval. |
As indicated |
89(b) Implement and Maintain the
Earthworks Carry out and maintain the earthworks in accordance with the certified drawings. Note: A copy of the certified Earthworks Drawings must be available on-site for inspection by Council Officers during these works. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 90) Retaining Walls Design and construct all retaining walls and associated fences, in accordance with the relevant Brisbane Planning Scheme Codes and the following: - All retaining walls including the footings, must be located wholly within the property boundaries of the site where works are occurring - Runoff from surface drains and subsoil drainage associated with the retaining walls must be collected and connected to a lawful point of discharge (LPD) where possible. If no LPD is available the surface drains and sub-soil drainage must be designed, installed and discharged to ensure there is no ponding, nuisance or concentration of stormwater discharge to adjacent properties. - Retaining walls to stabilise excavation must be set back from property boundaries to accommodate subsoil drainage without encroachment into the neighbouring property. This set back may vary depending on the height, structure and design of the retaining wall, surcharge loadings from neighbouring properties, and to provide a surface drain along the top of the retaining wall - For retaining walls in excess of
1.0m in height: NOTE: Refer to City Plan 2014; Infrastructure Design Planning Scheme Policy (IDPSP) for Council’s definition of a LPD. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
90(a) Certification of Retaining
Walls For retaining walls over 1.0m in height, obtain certification from a Registered Professional Engineer Queensland that the design and construction of the retaining walls and ancillary drainage are in accordance with the requirements of this condition. |
As indicated |
| 91) Repair Damage to Kerb, Footpath or Road Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
91(a) Interim Repairs If at any time during the construction phase of the approved development, damage to the existing kerb and channel, footpath or roadway creates unsafe, unreasonable and/or not fit for purpose conditions as assessed by Council, interim repairs must be undertaken as directed by Program Planning and Integration. Note: Any interim repairs required to be undertaken shall not be considered to satisfy the requirements of this condition for the permanent repair of the infrastructure prior to the issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. Timing: While site / operational / building works is occurring. |
As indicated |
| 92) Access, Grades, Manoeuvring, Carparks, Signs and
Line Marking Construct and maintain access, parking and manoeuvring for vehicles on site in accordance with the relevant Brisbane Planning Scheme Codes, as indicated on the approved DRAWINGS AND DOCUMENTS, including the following: i. A pavement of minimum Local road standard or equivalent surface material (including associated drainage) to the area on which motor vehicles will be driven and/or parked. ii. Manoeuvring on site for a Refuse Collection Vehicle and for the loading and unloading of vehicle(s); iii. Parking on the site for 85 resident/tenant cars, 11 visitor cars, including 1 parking spaces for people with disabilities and for the loading and unloading of vehicle(s) within the site. There must a minimum number of 96 total number of spaces provided on site. iv. Provide and maintain 52 secure bicycle parking spaces (41 spaces for resident and 11 for visitors). v. Prepare and implement signs and line markings drawings that show the internal paved areas signed and delineated in accordance with the approved drawings and documents. The drawings must be prepared and certified by a Registered Professional Engineer Queensland in accordance with the relevant Brisbane Planning Scheme Codes and the Manual of Uniform Traffic Control Devices. PROOF OF
FULFILMENT Certification from a Registered Professional Engineer Queensland, that the above requirements have been implemented in accordance with this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 93) Residential Refuse Collection - On Site Provide for the installation and collection of refuse/recycling bins by Brisbane City Council's Waste and Resource Recovery Services. |
At all times |
93(a) Arrange Refuse Collection Arrange for the installation of refuse/recycling bins and for the subsequent collection of refuse including recycling from the site by Brisbane City Council's Waste and Resource Recovery Services. Timing: A minimum of four weeks prior to the commencement of use and then to be maintained. |
As indicated |
93(b) Indemnify Council The owner and any subsequent owner must, by approved form to Waste and Resource Recovery Services, indemnify Council and its agents in respect of any damage to the pavement and other driving surfaces. Timing: When an arrangement for refuse/recycling collection services is made with Brisbane City Council and then to be maintained. |
As indicated |
93(c) Notify Future Owner The owner must notify any future owner/body corporate that the development has been approved on the basis that an indemnity must be provide for refuse collection vehicles to enter the property. Timing: At time of a change of ownership. |
As indicated |
| 94) Refuse Storage - On Site Collection Provide a roofed and wholly screened refuse enclosure utilising materials consistent with the development or a dedicated refuse storage room, as shown on the approved plans and documents. The enclosure/refuse storage room must be of a design to accommodate the quantity of refuse and recycling including source separation to allow for low servicing collection of the development. Bins must be located in an area which allows them to be manoeuvred from the bin storage area to the designated internal collection point. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 95) Work for Transport Network - Road (Non-trunk) -
External Construct the following roadwork with any associated drainage, verge, site access and services including street lighting for the Transport Network (Road) shown on the APPROVED DRAWING NUMBER DA13 Revision 02 amended in red 18/07/2024 in accordance with the relevant Brisbane Planning Scheme Codes, the Queensland Manual of Uniform Traffic Control Devices and the AUSTROADS design standards: - new type E concrete kerb and channel and associated drainage along the full length of the Farmers Street frontage of the site on a 4.25 metre alignment (taking into account any road reserve widening if required); - a District Road type road pavement from the lip of the new kerb and channel to the road centre line or edge of the existing road pavement with any appropriate tapers (the minimum width of road construction/reconstruction must be 1.2 metres); Note: Irrespective of the actual widening, the finished road pavement crown must be located along the centreline of the final pavement width. - a new dedicated right-turn lane along the Farmers Street frontage as shown on the APPROVED DRAWINGS AND DOCUMENTS; - signs and pavement markings along the Farmers Street frontage. - Street lighting to a category V5 lighting category along the Farmers Street frontage (unless instructed otherwise by City Lighting, contact: Construction Branch, Citywide Services, City Lighting CS- LIGHTING@brisbane.qld.gov.au). Note: This condition is imposed under section 145 of the Planning Act 2016. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
95(a) Submit Roadworks and Stormwater
Drainage Drawings Submit to, and obtain approval from, Development Services Roadworks and Stormwater Drainage Drawings prepared and certified by a Registered Professional Engineer Queensland in accordance with the APPROVED DRAWINGS AND DOCUMENTS and the relevant Brisbane Planning Scheme Codes. Timing: Prior to site/operational/building work commencing. |
As indicated |
95(b) Submit Signs and Pavement
Drawings Submit to, and obtain approval from, Development Services Signs and Pavement Marking drawings prepared and certified by a Registered Professional Engineer of Queensland in accordance with the APPROVED DRAWINGS AND DOCUMENTS and the relevant Brisbane Planning Scheme Codes. Timing: Prior to site/operational/building work commencing. |
As indicated |
95(c) Submit Street Lighting Design
Drawings Submit to, and obtain approval from, Construction Branch, Citywide Services, City Lighting (CS-LIGHTING@brisbane.qld.gov.au), street lighting design drawings prepared and certified by a Registered Professional Engineer of Queensland (Electrical) which show the proposed street lighting system in accordance with the relevant Brisbane Planning Scheme Codes. Timing: Prior to site/operational/building work commencing. |
As indicated |
95(d) Implement Approved
Drawings Construct the works in accordance with the above approved drawings. Timing: Prior to on-maintenance acceptance. |
As indicated |
95(e) Submit As Constructed
Drawings Submit to Development Services As Constructed drawings including an asset register and a pre-On-Maintenance Inspection Checklist, prepared by a Registered Professional Engineer Queensland. Timing: Prior to on-maintenance inspection. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the above approved drawings. |
As indicated |
| 96) Remove Redundant Drainage Outlets Remove any redundant
drainage outlets from the kerb and channel including any associated pipe work
across the footway and reinstate the kerb and channel and the footway area in
accordance with the relevant Brisbane Planning Scheme Codes. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 97) Site Drainage - Major Provide an internal drainage system to collect stormwater run-off from all proposed lots, roofed and developed surface areas and any run-off onto the site from adjacent areas and convey the collected run- off to a lawful point of discharge, in accordance with the relevant Brisbane Planning Scheme Codes. Where stormwater detention is required provide a minimum stormwater detention storage of 118.6 cubic meters. Notes: - All upslope stormwater connections to existing private properties must
extend to the property boundary of all relevant properties being ultimately
serviced by that connection. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
97(a) Submit Site Drainage
Drawings Submit to, and obtain approval from, Development Services, site drainage drawings and engineering calculations, prepared and certified by a Registered Professional Engineer Queensland, in accordance with the relevant Brisbane Planning Scheme Codes. Notes: -
Queensland Building and Construction Commission licensed hydraulic consultants
may design the stormwater system for sites less than 2000m2 with an upstream
catchment servicing no more than 4 residential lots. This excludes stormwater
drainage design (including subsoil drainage) of basements in flood planning
areas and the design of any onsite stormwater detention system Timing: Prior to site/operational/building work commencing |
As indicated |
97(b) Implement Approved
Drawings Carry out the works in accordance with the approved site drainage drawings. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
97(c) Submit As Constructed
Drawings Submit to Development Services As Constructed drawings prepared and certified by a Registered Professional Engineer Queensland or a Queensland Building and Construction Commission licensed hydraulic consultants (where applicable). Note: To be submitted via DA- ComplianceEngineering@brisbane.qld.gov.au and include the site address, A00 reference and Condition number in the subject line. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland or Queensland Building or Construction Commission licensed hydraulic consultants (where applicable) confirming that the works have been completed in accordance with the above stormwater drawings. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 98) Ponding of Stormwater Carry out the approved development to ensure that adjoining properties and roads are protected from ponding or nuisance from stormwater during construction. Notes: If remedial works are necessary to comply with this condition, prior approval must be obtained from Development Services. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 99) Stormwater Quality Manage stormwater quality in accordance with this condition. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
99(a) Implement Stormwater Quality
Management Implement the stormwater quality treatment strategy outlined within the APPROVED DRAWINGS AND DOCUMENTS and any engineering drawings and documents approved pursuant to conditions contained in this development approval. Where a proprietary stormwater quality improvement device has been used to meet the water quality objectives, ensure the device has been approved by Brisbane City Council for use in achieving the water quality targets and meets the required manufacturers specifications (in terms of number and size of units and any pre- treatment requirements). Note: This condition does not require any further approval from Council. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained. |
As indicated |
99(b) Water Quality Maintenance Management
Plan Prepare and implement a Water Quality Maintenance Management Plan in accordance with the Water by Design 'WSUD Technical Design Guidelines for South East Queensland'. The plan must be prepared and certified by a Registered Professional Engineer Queensland. Note: This condition does not require any further approval from Council. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained. |
As indicated |
99(c) Submit Certification Submit to Development Services certification from a Registered Professional Engineer Queensland confirming that the stormwater quality treatments strategy required pursuant to part (a) of this condition has been implemented and where a proprietary stormwater quality improvement device has been used to meet the water quality objectives, the device has been approved by Brisbane City Council for use in achieving the water quality targets and meets the required manufacturers specifications (in terms of number and size of units and any pre-treatment requirements). Note: Manufacturers that have approved devices by Brisbane City Council will be able to provide evidence of Council approval for use. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
99(d) Maintain Management Plans Maintain the certified Water Quality Maintenance Plan and the stormwater quality treatment strategy required pursuant to part (a) of this condition. Include the Water Quality Maintenance Plan in any building management strategy, building management statement or community management statement. Timing: At all times |
As indicated |
| 100) Service Conduits and Mains Provide and install all
service conduits and meet the cost of any alterations to public utility mains,
existing mains, services, street lighting or installations that are required to
carry out the approved development. These works must be in accordance with the
relevant Brisbane Planning Scheme Codes, and include the following, where
applicable: Note: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
100(a) Submit As Constructed
Drawings Submit to Development Services As Constructed drawings, including an asset register, prepared and certified by a Registered Professional Engineer Queensland. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the requirements of this condition. Note: Civil works are to be certified by a RPEQ(Civil) and electrical works are to be certified by a RPEQ (Electrical). |
As indicated |
| 101) Telecommunications Submit to Development Services, certification from
an authorised telecommunications carrier/contractor, that the following works
and infrastructure have been undertaken and installed in accordance with
telecommunications industry standards: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 102) Agreement with Electricity Supplier Submit to Development Services, evidence of an agreement with an electricity supplier to provide necessary services to the development in accordance with the relevant Brisbane Planning Scheme Codes. Where development is within an established area of overhead electricity supply and the electricity supplier determines that a property pole is the appropriate solution to supply electricity to the development, the developer must be responsible for the installation of the property pole(s). In the above circumstances, submit to Development Services, certification from the developer's electrical consultant confirming that the above installation has been completed in accordance with the relevant AS/NZS Standards and the Queensland Electricity Connection Manual (QECM) and Queensland Electricity Metering Manual (QEMM). |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 103) Construct Private Internal Fire Main and
Hydrant(s) Construct a private internal water main with fire hydrant(s) to serve the development where any point of a possible building envelope is or will be more than 90 metres (when the distance is measured around the perimeter of the building envelope) from a Urban Utilities (UU) hydrant. The main is to be designed and constructed in accordance with the current version of the 'Fire Hydrant and Vehicle Access Guidelines for Residential, Commercial and Industrial Lots' (GuRCIL) by the Queensland Fire and Emergency Services and the relevant Brisbane Planning Scheme Codes. Where the unassisted water supply cannot meet the flow & pressure requirements of the GuRCIL, the design & installation of a Fire Hydrant System is to be in accordance with the current version of AS2419. Accessible hardstand is to be provided for emergency vehicles within 20m of a fire hydrant(s) and the design and installation is to satisfy the requirements for feed hydrants of the current version of GuRCIL. Where emergency vehicles cannot be located within 20m of a fire hydrant(s), the design & installation of the Fire Hydrant System is to be in accordance with the current version of AS2419. The private main shall be supplied from a Urban Utilities (UU) water service and meter. This water service requirement is to be included in the development's Water Approval. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
103(a) Access and Ownership of
Main The hydrants must be located to allow 24 hour access for emergency and maintenance vehicles. Ownership and maintenance responsibility for the private main and hydrant(s) must exist and remain with a single legal entity, which represents the owner(s) of any property served by the private main and hydrant(s). This legal entity is to be to the satisfaction of UU for billing purposes and is to be a requirement of the development's Water Approval. This legal entity must remain in place for the life of the development, be responsible for the cost of water consumption charges at the UU boundary meter and be responsible for maintaining the private main and hydrant(s), for the life of the development. The responsibilities of the legal entity must remain in effect on transfer of the property title. Timing: at all times. |
As indicated |
103(b) Submit Hydraulic Plan Submit detailed hydraulic plans to and obtain Compliance Permit from Plumbing Services for regulated work (Plumbing and Drainage Installation) under the Plumbing and Drainage Act 2018. Timing: Prior to site/operational/building work commencing. |
As indicated |
103(c) Implement Approved Plans Construct the works in accordance with the approved hydraulics plan. Obtain a Compliance Certificate for the constructed works from the Manager, Plumbing Services Group. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
103(d) Notify Future Owners The developer must notify all future and potential property owners of the private fire main and hydrants, and ownership responsibilities for the private fire main and fire hydrant. Timing: At the time of marketing the lot for sale. PROOF OF
FULFILMENT Submit the following documentation to Development Services: - Copy of UU Connection Certificate, indicating all requirements of the developer's Water Approval have been satisfied. - Provide a Statutory Declaration that future and potential property owners will be advised of the private fire fighting infrastructure, who owns that infrastructure and the maintenance responsibilities for the infrastructure. |
As indicated |
| 104) Water and Wastewater Pursuant to Schedule 18 of the Planning Regulation 2017 submit to Development Services, documentary evidence, issued by the relevant distributor-retailer, to verify that the conditions of any necessary connection certificate under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009, have been complied with. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 105) Permanent Driveway Crossover Provide a 7.0-metre- wide Type B2 permanent driveway crossover to the Farmers Street frontage of the site in accordance with the relevant Brisbane Planning Scheme Codes and located as shown on the approved DRAWINGS AND DOCUMENTS. Written consent must be obtained from Program, Planning and Integration Arboriculture (PPI Arb) prior to any works occurring that will either impact on or require removal of a street tree (this includes pruning, excavation or fill within the root zone/canopy of the tree) At all times during construction of the crossover, safe pedestrian access along the site frontage must be maintained. Note: No further driveway permit is required however additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 106) Redundant Driveway Crossover Remove the redundant existing driveway crossover(s) on the frontage(s) of the site and reinstate the kerb and channel, road pavement, footways and footpaths in accordance with the relevant Brisbane Planning Scheme Codes. Note: Additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 107) Further Development Permit required This Preliminary Approval (Carrying Out Building Works) does not include assessment under the
Building Act and does not permit building work to occur. Prior to the commencement of any building work,
Development Permit(s) for Carrying Out Building Work
will be required. |
As indicated |
| 108) Construction Noise and Dust Emissions Pursuant to the
Environmental Protection Act 1994, all development involving the emission of
noise and dust from building and/or construction activities, must ensure that
the emissions are in accordance with the requirements of the Act. The
Environmental Protection Act 1994 prescribes that: 1. A person
must not carry out building work in a way that makes an audible noise-
- on a business day or Saturday, before 6.30a.m. or after 6.30p.m; or
- on any other day, at any time.
2. The reference in subsection (1)
to a person carrying out building work- - includes a person carrying out building work under an owner-builder permit; and - otherwise does
not include a person carrying out building work at premises used by the person
only for residential purposes. Note: A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management delegate Development Services. |
As indicated |
| 109) Plumbing and Drainage Work Pursuant to the Plumbing and Drainage Act 2018, any plumbing and drainage work must be carried out in compliance with the Plumbing and Drainage Regulation 2019. Note: All new and existing plumbing services should be located within the lot that they serve. Compliance assessable plumbing and drainage work requires approval by Brisbane City Council prior to the work being carried out. |
As indicated |
| 110) Concurrence Agency Conditions The Department of
Transport and Main Roads as concurrence agency has imposed the conditions
contained in the letter dated 25 September 2013, or as
amended. |
As indicated |
| 111) Water and Wastewater Services for water and wastewater (sewerage) are
no longer under the jurisdiction of Brisbane City Council. Authorisation to
connect the approved development to the water/wastewater networks and for
property service connections requires a Water Approval under the South-East
Queensland Water (Distribution and Retail Restructuring) Act 2009. Any
necessary Water Approval must be obtained from the relevant distributor-
retailer (currently operating as Queensland Urban Utilities for the Brisbane
City Council area). For the purpose of compliance assessment of a subdivision plan pursuant to Schedule 19 of the Sustainable Planning Regulation 2009 (whether in relation to a development permit for Reconfiguring a Lot or a Building Format Plan subsequent to a development permit for a Material Change of Use), documentary evidence, issued by the relevant distributor-retailer, must be provided to Council to verify that the conditions of any necessary Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009, have been complied with. |
As indicated |
| 112) Fire Ant Movement Controls To prevent the spread of fire ants, the
Queensland Government has implemented movement controls in areas of Queensland
(biosecurity zones) where this pest species has been detected. These controls
apply to individuals and commercial operators, and restrict the movement of
materials that could carry fire ants which include soil, turf, potted plants,
mulch, baled hay or straw, animal manures, mining or quarry
products. Breaches of these controls can potentially
impact the community, economy and the environment. Penalties for non-compliance
with movement controls within fire ant biosecurity zones apply under the
Biosecurity Act 2014. If you are unsure of your obligations contact the relevant Queensland State Government Department (Biosecurity Queensland, Department of Agriculture and Fisheries) |
As indicated |