BRISBANE CITY COUNCIL'S APPROVAL PACKAGE.



APPLICATION DETAILS

This package relates to the application detailed below
Address of Site: 14 WELLINGTON RD WOOLLOONGABBA QLD 4102
16 WELLINGTON RD WOOLLOONGABBA QLD 4102
18 WELLINGTON RD WOOLLOONGABBA QLD 4102
25 NILE ST WOOLLOONGABBA QLD 4102
6 WELLINGTON RD EAST BRISBANE QLD 4169
Real Property Description of Site: L1 RP.123545
L3 RP.122636
L1 RP.42898
L1 RP.122636
L2 RP.123545
Aspects of development and type of approval: DA - PA - Material Change of Use Development Permit - multiple dwelling,educational establishment,food and drink outlet,office,shop
DA - PA - Building Work Development Permit - multiple dwelling,educational establishment,food and drink outlet,office,shop
Council File Reference: A006350223
Permit Reference Number/s: DAMC419870522; DABW420399622.
Package Status: APPROVED - Version 2 (27th of November, 2024 3:11:26 PM)
Package Generated: 27/11/2024


PROJECT TEAM

The assessment of this application has been undertaken by:
Nicola MEWING
Principal Urban Planner
Planning Services Special Assessment
Nicola.Mewing@brisbane.qld.gov.au
31781002
Rory KELLY
Team Manager
Planning Services Coordination
rory.kelly@brisbane.qld.gov.au
(07) 3403 4975
Ned MCDOUGALL
Senior Urban Planner
Planning Services North
Ned.McDougall@brisbane.qld.gov.au
(07) 3178 1004
Cameron RUSH
Principal Urban Planner
Planning Services North
Cameron.Rush@brisbane.qld.gov.au
(07) 3407 0850
Katrina KONTOS
Environmental Management Officer
Environmental Management Services
katrina.s.kontos@brisbane.qld.gov.au
(07) 3403 8888
Andrew BLAKE
Principal Engineer
Engineering Services Hydraulics
andrew.blake@brisbane.qld.gov.au
(07) 3403 5018
Chris HENNESSY

Engineering Services Traffic
Chris.Hennessy@brisbane.qld.gov.au
(07) 3403 5768
Adam MEWING
Principal Urban Planner
Planning Services House & Homes
adam.mewing@brisbane.qld.gov.au
07 3178 8674
Kathryn KELLY
Principal Urban Planner
Planning Services South
kathryn.kelly@brisbane.qld.gov.au
07 3407 1308
Callan BENNETT
Principal Architect
Architecture Team
Callan.Bennett@brisbane.qld.gov.au
07 31780595
Matthew O'DEA
Principal Landscape Architect
Landscape Architecture Team
Matthew.ODea@brisbane.qld.gov.au
31789513
Katrina KONTOS
Environmental Management Officer
Environmental Management Services
katrina.s.kontos@brisbane.qld.gov.au
(07) 3403 8888
Hien NGUYEN
Senior Engineering Officer
Engineering Services South
hien.nguyen@brisbane.qld.gov.au
07 3407 0349


DRAWINGS AND DOCUMENTS



The term 'drawings and documents' or similar expressions mean:
Drawing or Document Number Plan Date
Site Plan A1.002 Issue BB 23-NOV-2023 (Received)
Basement -3 Floor Plan A1.101 Issue BB 23-NOV-2024 (Received)
Basement -2 Floor Plan A1.102 Issue BB 23-NOV-2023 (Received)
Basement -1 Floor Plan A1.103 Issue BB 23-NOV-2023 (Received)
Ground Floor Plan A1.104 Issue BB 23-NOV-2023 (Received)
Mezzanine Floor Plan A1.105 Issue BB 23-NOV-2023 (Received)
Level 2 - Podium A1.106 Issue BB 23-NOV-2023 (Received)
Level 3 - Podium A1.107 Issue BB 23-NOV-2023 (Received)
Level 4 - Podium A1.108 Issue BB 23-NOV-2023 (Received)
Level 5 - Podium A1.109 Issue BB 23-NOV-2023 (Received)
Level 6 - Residential A1.110 Issue BB 23-NOV-2023 (Received)
Levels 7-26 A1.111 Issue BB 23-NOV-2023 (Received)
Level 27 A1.112 Issue BB 23-NOV-2023 (Received)
Level 28 A1.113 Issue BB 23-NOV-2023 (Received)
Level 29-36 A1.114 Issue BB 23-NOV-2023 (Received)
Level 37 - Nuage South Roof Terrace A1.115 Issue BB 23-NOV-2023 (Received)
Nuage South Roof A1.116 Issue BB 23-NOV-2023 (Received)
Ground Floor Detail Plan Detail Part A A2.411 Issue CC 23-NOV-2023 (Received)
Ground Floor Detail Plan Detail Part B A2.412 Issue CC 23-NOV-2023 (Received)
Ground Floor Detail Plan Detail Part C A2.413 Issue CC 23-NOV-2023 (Received)
North Elevation A1.201 Issue BB 23-NOV-2023 (Received)
South Elevation A1.202 Issue BB 23-NOV-2023 (Received)
East Elevation A1.203 Issue BB 23-NOV-2023 (Received)
West Elevation A1.204 Issue BB 23-NOV-2023 (Received)
Section A A1.301 Issue BB 23-NOV-2023 (Received)
Section B A1.302 Issue BB 23-NOV-2023 (Received)
Section C A1.303 Issue BB 23-NOV-2023 (Received)
Section D A1.304 Issue BB 23-NOV-2023 (Received)
Detail Section A A2.421 Issue CC 23-NOV-2023 (Received)
Detail Section B A2.422 Issue CC 23-NOV-2023 (Received)
Detail Section C A2.423 Issue CC 23-NOV-2023 (Received)
Detail Section D A2.424 Issue CC 23-NOV-2023 (Received)
Screening Details 01 A2.428 Issue CC 23-NOV-2023 (Received)
Screening Details 02 A2.429 Issue CC 23-NOV-2023 (Received)
Awning Diagram A2.4211 Issue CC 23-NOV-2023 (Received)
Awning Detail Sections A2.4212 Issue CC 23-NOV-2023 (Received)
Ground Floor Plan Page 10 - 21157 LC-01 (K) 23-NOV-2023 (Received)
Mezzanine Page 11 - 21157 LC-01 (K) 23-NOV-2023 (Received)
Level 2 Plan Page 12 - 21157 LC-01 (K) 23-NOV-2023 (Received)
Level 3 Plan Page 13 - 21157 LC-01 (K) 23-NOV-2023 (Received)
Level 4 Plan Page 14 - 21157 LC-01 (K) 23-NOV-2023 (Received)
Level 6 Plan Page 15 - 21157 LC-01 (K) 23-NOV-2023 (Received)
Typical Levels 7-26 Plan Page 16 - 21157 LC-01 (K) 23-NOV-2023 (Received)
Level 27 Plan Page 17 - 21157 LC-01 (K) 23-NOV-2023 (Received)
Level 27 North Building Roof Terrace Plan Page 18 - 21157 LC-01 (K) 23-NOV-2023 (Received)
Level 28-36 Plan Page 19 - 21157 LC-01 (K) 23-NOV-2023 (Received)
Level 37 South Building Roof Terrace Plan Page 20 - 21157 LC-01 (K) 23-NOV-2023 (Received)
Section A-A Page 21 - 21157 LC-01 (K) 23-NOV-2024 (Received)
Section B-B Page 22 - 21157 LC-01 (K) 23-NOV-2023 (Received)
Section C-C Page 23 - 21157 LC-01 (K) 23-NOV-2023 (Received)
Section D-D Page 24 - 21157 LC-01 (K) 23-NOV-2023 (Received)
Section F-F Page 25 - 21157 LC-01 (K) 23-NOV-2023 (Received)
Section G-G Page 26 - 21157 LC-01 (K) 23-NOV-2023 (Received)
Planting Depth - Ground Floor Plan, Mezzanine Floor Plan Page 30 - 21157 LC-01 (K) 23-NOV-2023 (Received)
Planting Depth - Level 2 Plan, Level 3 Plan Page 31 - 21157 LC-01 (K) 23-NOV-2023 (Received)
Planting Depth - Level 4 Plan, Level 5 Plan Page 32 - 21157 LC-01 (K) 23-NOV-2023 (Received)
Planting Depth - Level 6 Plan, Level 7-26 Plan Page 33 - 21157 LC-01 (K) 23-NOV-2023 (Received)
Planting Depth - Level 27 North Building Roof Plan, Typical Levels 28- 36 Page 34 - 21157 LC-01 (K) 23-NOV-2023 (Received)
Planting Depth - Level 37 South Building Roof Terrace Plan Page 35 - 21157 LC-01 (K) 23-NOV-2023 (Received)
Stormwater Management Plan CDA031 P6 04-JUL-2024 (Received)
Services Connection Plan CDA401 P5 23-NOV-2023 (Received)
Bulk Earthworks Plan CDA011 P4 23-NOV-2023 (Received)
Bulk Earthworks Sections CDA021 P4 23-NOV-2023 (Received)


Advice

Please see the attached document(s) for any advices.

APPROVAL CONDITIONS



Permit to Which These Conditions Relate: DA - PA - Material Change of Use
Activity(ies): multiple dwelling
shop
office
food and drink outlet
educational establishment
Stage:  

General/Planning Requirements
 
Timing
1)   Car Parking

The car parking within the premises must be maintained exclusively for the ancillary use of the development. The parking must not be made available to the general public and there must not be signage erected on or in the vicinity of the site advertising the availability of car parking to the general public.

 
At all times
 
2)   Maintain the Approved Development

Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions.

 
At all times
 
3)   Approved Drawings and Documents

A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers.

Note: This condition is imposed to ensure compliance with the conditions of development approval.

 
While site/operational/building work is occurring
 
4)   Carry Out the Approved Development

Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS.

Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks).  Permission to enter neighbouring properties must be obtained from the relevant property owners.

 
While site/operational/building work is occurring
 
5)   Demolish or Relocate Buildings/Structures

Demolish or Relocate buildings/structures on the site in accordance with the approved DRAWINGS AND DOCUMENTS and where applicable, the approved Construction Management Plan.  

The removal of buildings/structures includes the removal of all existing concrete slabs, foundations and footings.

 
Prior to Council's notation on the plan of subdivision
 
6)   Complete All Operational Work

Complete all operational work associated with this development approval, including work required by any of the conditions included in the Development Approval Package.  Such operational work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS or, if requiring a further approval from the Council, in accordance with the relevant further approval(s).

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
7)   Complete All Building Work

Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS.

Note: Building work must also be completed in accordance with any other current development approval.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
8)   Visitor Parking

Visitor car parking spaces must:
-  Be clearly labelled as 'Visitor Parking';
-  Remain unimpeded by landscaping, water tanks, storage (temporary or otherwise), gates or any other fitting, fixture or structure; and
-  Provide 24 hour unrestricted access for all bona fide visitors to the whole site.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
9)   Landscaping of Vacant Site

If construction for the approved development does not commence within 3 months of the demolition of the existing building(s) on site, the site must be covered in grass in accordance with the approved drawings and documents.

Timing: Within 3 months of the demolition of the existing building(s).

 
As indicated
 
10)   Building Management Statement

Ensure a Building Management Statement is registered on the title for each proposed lot.

The Building Management Statement must cover common building management items including but not limited to any shared:
- support, services and utilities;
- pedestrian and vehicle access;
- car parking including visitor and disabled spaces;
- vehicle servicing areas including loading docks;
- refuse storage and collection areas;
- storage areas;
- recreation areas.

The Building Management Statement must address the operation of the observatory.

Timing: As part of the registration of the plan of subdivision notated by Council and then to be maintained.

 
As indicated
10(a) Submit Building Management Statement

The Building Management Statement must be submitted to, and the content endorsed by, Development Services.

Timing: Prior to Council's notation on the plan of subdivision.

 
As indicated
10(b) Lodge Building Management Statement

Lodge the accepted Building Management Statement with the Registrar of Titles for the relevant Queensland State Government Authority.

Timing: As part of the registration of the plan of subdivision notated by Council.

 
As indicated
10(c) Submit Evidence of Registration

Submit to Development Services, evidence of the registration of the endorsed Building Management Statement.

Timing: Within one month of the registration of the Building Management Statement.

 
As indicated
 
11)   Security Lighting - On Site

Install and maintain a suitable system of security lighting to operate from dusk to dawn within all areas where the public may gain access, including car parking areas, building entrances and vegetated areas.

Ensure that all external lighting is in accordance with Australian Standard - AS4282- Control of the Obtrusive Effects of Outdoor Lighting. 

Ensure lighting over publicly accessible internal pathways covered by permanent awnings is in accordance with Australian Standard - AS/NZS 1158.3.1 Lighting for roads and public spaces - Pedestrian area lighting - Performance and design requirements.  

Lighting must be maintained in safe and good working order.

 

Timing: 'Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first'

 
As indicated
 
12)   Public Access - 24 Hours Through Site

Provide and maintain unimpeded and safe 24-hour public access through the subject site, and ensure that access ways are designed to cater for people with disabilities in accordance with Australian Standard - AS1428.1Design for Access and Mobility - Part 1: General requirements for access - New building work.

 
At all times
 
13)   Hours of Operation

Hours of operation for the approved Shop, Office and Food and Drink Outlet must be from 6:00AM to 10:00PM.

 
At all times
 
14)   Limitation of Use

The observatory is to only be used as an educational establishment as defined by the Brisbane City Plan 2014.

The observatory (educational establishment) must operate in accordance with this approval and the following:

- Limit public open days/viewings to a maximum of 1 (one) per month;

- Limit the number of public attendees to a maximum of 8 (eight) persons at any time;

- Must ensure at least 2 (two) observatory staff members are present during public open days/viewings;

- Observatory staff must meet public visitors in the lobby and accompany them to the observatory;

- Must ensure that public visitors are accompanied by staff at all times;

- Must notify residents of upcoming public viewings a minimum of 7 (seven) days prior to occurring.

 
At all times
 
Architecture
 
Timing
15)   Architecture - Creative Lighting

Provide creative lighting to the new elements of the façade, in accordance with the requirements of this condition.

 

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
15(a) Submit Creative Lighting Strategy

Submit for, and obtain approval from Development Services, a creative lighting strategy to deliver quality lighting outcomes to meet functional needs as well as a means of creative expression that contributes lighting for occasion, identity, discovery and safety. The strategy is to include innovative ideas for the illumination of new facade features and entry points along the Wellington Road and Nile Street frontages. To describe the strategy, the application may include reports, concept plans and perspective drawings.

 

Timing:  Prior to site/operational/building work commencing

 
As indicated
15(b) Implement Approved Creative Lighting Strategy

Carry out the approved creative lighting strategy in accordance with the drawings and documents approved as part of this condition.

 

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained.

 
As indicated
 
16)   Final External Detailing of Building

Construct the development in accordance with architectural drawings approved pursuant to this condition. The architectural drawings must be in accordance with the APPROVED DRAWINGS AND DOCUMENTS, relevant Brisbane Planning Scheme Codes and the requirements of this condition.

 
To be maintained
16(a) Submit Architectural Drawings

Submit to, and obtain approval from, Development Services architectural drawings prepared and certified by a Registered Architect or Queensland Building Construction Commission Open Licence Class Building Designer showing the final developed details of the facade treatment, the ground interface and the roof top/building capping elements which depict a higher level of documentation detail than that shown on the APPROVED DRAWINGS AND DOCUMENTS, including:
- Elevation and facade treatment drawings for all ground, podium and typical tower floor levels that demonstrate the final design outcome for all elevations of the built form including:
- Detailed plans, sections and elevations at 1:50 or 1:20 scale for elements at the facade including structural elements and fixed and operable elements such as balustrades, screens, doors, windows, projecting fins and planter beds/trellises
- All servicing and infrastructure, including but not limited to, padmount transformers, pump rooms, fire hydrant boosters etc.
- Roof top or building capping elements, awnings and soffits
- One rendered perspective showing the intended finished built form

The architectural drawings must:
- include dimensions for the extent of projecting elements, balustrade height and door and window/glazing configurations
- nominate materials, colours and finishes
- have title blocks and be cross referenced to larger scaled drawings.

Timing: Prior to building works commencing

 
As indicated
16(b) Pre-Start Meeting

Arrange and attend a pre-start meeting with Development Services.

Applicable compliance and inspection fees must be paid to Council, in full, prior to the meeting being held.

Note: To arrange a pre- start meeting with Development Services an email must be sent to dalodgement@brisbane.qld.gov.au.

Timing: Prior to any work commencing to comply with this condition.

 
As indicated
16(c) Implement Approved Architectural Drawings

Carry out the building work in accordance with the approved architectural drawings.

Note: The requirement to use particular materials and finishes is imposed only for the purpose of achieving a built form outcome that displays architectural merit. Council has not assessed the materials and finishes for compliance with the Building Act, the Building Fire Safety Regulation, the Building Regulation, the Building Code of Australia, the Queensland Development Code, relevant Australian Standards, fire safety standards or any other relevant requirement of a statutory authority with regard to building work.

Timing: While building work is occurring and then to be maintained.

 
As indicated
16(d) Submit Certification

Submit to Development Services certification by a Registered Architect or Queensland Building Construction Commission Open Licence Class Building Designer confirming that the building has been constructed in accordance with the approved architectural drawings.

Timing: Prior to the Final Certificate/Certificate of Occupancy or commencement of the use, whichever comes first.

 
As indicated
 
17)   Overall Height

The overall height of the building(s) must be in accordance with the floor and roof levels and overall height shown on the APPROVED DRAWINGS AND DOCUMENTS.

NOTE: This condition should be read in conjunction with any other relevant condition requiring minimum height clearances for basement or undercover car parking and manoeuvring areas.

 
While site/operational/building work is occurring and then to be maintained
17(a) Submit Certification

Submit to Development Services certification from a registered surveyor confirming that the 'as constructed' floor and roof levels and overall height are in accordance with the requirements of this condition.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
18)   Light Reflectivity and Solar (Heat) Reflectivity

Submit to Development Services documentary evidence that the level of light reflectivity from the glazing incorporated in the approved development does not exceed 20%.

Timing: Prior to building work above ground level commencing.

 
As indicated
18(a) Install Glazing

Install and maintain glazing in accordance with the above specification.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained.

 
As indicated
 
19)   Environmental Sustainability

Construct and maintain the building(s) in accordance with 'Best Practice' environmentally sustainable measures.

 
While site/operational/building work is occurring and then to be maintained
19(a) Submit Sustainability Management Plan

Submit to, and obtain approval from, Development Services a Sustainability Management Plan prepared by a Registered Architect / Registered Professional Engineer Queensland (suitably qualified and experienced in sustainability management) incorporating measures for the development to achieve at least a 'Best Practice' environmentally sustainable rating for the building in accordance with a recognised Environmental Rating System suitable for the approved development (such as Green Star).

Note: For the purpose of this condition 'Best Practice' outcomes must exceed the requirements of the Building Code of Australia and achieve the equivalent of a Green Star 4 star rating.

Timing: Prior to commencement of building work above ground level.

 
As indicated
19(b) Implement Sustainability Management Plan

Implement and maintain the approved Sustainability Management Plan.

Timing: While site/operational/building work is occurring and then to be maintained.

 
As indicated
19(c) Submit Certification

Submit to Development Services certification by a Registered Architect / Registered Professional Engineer Queensland (suitably qualified and experienced in sustainability management) confirming that the approved Sustainability Management Plan has been implemented in accordance with the requirements of this condition.

Timing: Prior to the commencement of the use.

 
As indicated
 
20)   Mitigate Wind Impacts

Mitigate any adverse wind impacts arising from the implementation of the development in accordance with a Wind Impact Assessment Report and Architectural Drawings approved pursuant to this condition.

 
While site/operational/building work is occurring and then to be maintained
20(a) Submit Wind Impact Assessment Report

Submit to, and obtain approval from, Development Services a detailed Wind Impact Assessment Report, including any outcomes obtained from an in-depth assessment such as a wind tunnel test or comprehensive computational fluid dynamics model, prepared by a Registered Professional Engineer, Queensland (experienced in assessing building wind impacts), demonstrating that wind impacts arising from the implementation of the development, will not adversely affect pedestrian comfort levels and stationary activities within the development and for the public realm at street level.

Note: This condition is imposed to protect the amenity of the public realm and communal areas within the development from adverse wind conditions created by the development.

Timing: Prior to site/operational/building work commencing above ground.

 
As indicated
20(b) Submit Architectural Drawings

Submit to, and obtain approval from, Development Services revised and properly made Architectural Drawings indicating any alterations to the approved building design and/or mitigation measures identified as being necessary to ensure the amenity of these areas meets the standards for comfort for their use, as advised in the Wind Impact Assessment Report approved pursuant to (a) above.

Timing: Prior to site/operational/building work commencing above ground

 
As indicated
20(c) Implement Wind Impact Assessment Report and Architectural Drawings

Carry out the works in accordance with the approved Wind Impact Assessment Report and approved Architectural Drawings.

Timing: While site/operational/building work is occurring.

 
As indicated
20(d) Submit Certification

Submit to Development Services, certification from a Registered Professional Engineer, Queensland (experienced in assessing building wind impacts), certifying that the work(s) have been carried out in accordance with the approved Wind Impact Assessment Report and approved Architectural Drawings.

Timing: Prior to commencement of use.

 
As indicated
 
21)   Environmental Sustainability - NATHERS

Construct and maintain the building(s) in accordance with 'Best Practice' environmentally sustainable measures.

PROOF OF FULFILMENT
Provide, to development services, a copy of the NATHERS `Whole of Home' Rating Certificate for each Dwelling Unit and a summary certificate for all units in the Multiple dwelling demonstrating that the units exceed the requirements of the National Construction Code (both for individual units and for the average rating across all units). Timing: Prior to commence of works on site.

 
While site/operational/building work is occurring and then to be maintained
21(a) Submit Sustainability Management Plan

Submit to, and obtain approval from, Development Services a Sustainability Management Plan prepared by a Registered Architect / Registered Professional Engineering Queensland (suitably qualified and experienced in sustainability management) incorporating measures for the development to achieve at least a ‘Best Practice’ environmentally sustainable rating for the building in accordance with a recognised Environmental Rating System suitable for the approved development.

Note: For the purpose of this condition ‘Best Practice’ outcomes, must exceed the current sustainability requirements of the National Construction Code.

Timing: Prior to commencement of building work above ground level.

 
As indicated
21(b) Implement Sustainability Management Plan

Implement and maintain the approved Sustainability Management Plan.

Timing: While site/operational/building work is occurring and then to be maintained.

 
As indicated
21(c) Submit Certification

Submit to Development Services certification by a Registered Architect / Registered Professional Engineer Queensland (suitably qualified and experienced in sustainability management) confirming that the approved Sustainability Management Plan has been implemented in accordance with the requirements of this condition.

Timing: Prior to the commencement of the use.

 
As indicated
 
22)   Artworks

Provide and maintain artworks in accordance with this condition.

 
Prior to the commencement of the use and then to be maintained
22(a) Budget and Art Opportunities Report

Submit to, and obtain approval from the Principal Architect, Design Brisbane, via Development Services email dalodgement@brisbane.qld.gov.au

(i) A Quantity Surveyor's letter stating the artwork budget allocation of no less than 0.25% of the total cost of building and construction work up to the 20th storey for each building.

(ii) A Quantity Surveyor's letter stating the artwork budget allocation of no less than 1.00% of the total cost of building and construction work above the 20th storey for each building.

(iii) An Art Opportunities Report, prepared by a suitably qualified art consultant or curator that provides:

· The site's context, history, and description

· Curatorial rationale for the artwork program

· Proposed artwork locations within an area determined by the Principal Architect, Design Brisbane that meet the criteria of being readily viewable within the public domain.

· Any artwork should not be delivered to fulfil compliance for any other condition contained within this development approval and the approved drawings and documents.

Note: Artworks for podium screening shall not achieve compliance with this condition.

· A long- list of recognised artists or craftspeople which includes descriptions of each artist's practice, and relevant examples of their artwork that indicates the potential artforms and mediums under consideration for each location

· Indicative budget breakdown

· Indicative program

· Contact details of the art consultant or curator.

For further guidance on the Art Opportunity Report content contact the Principal Architect, Design Brisbane via Development Services email dalodgement@brisbane.qld.gov.au

 
Prior to the commencement of the use and then to be maintained
22(b) Final Concept Design Report
 
Prior to the commencement of the use and then to be maintained
22(c) Implement Approved Artwork

Supply and install approved artwork and attribution plaque including artist statement and artwork credit line.

 
Prior to the commencement of the use and then to be maintained
22(d) Submit details

Submit to the Principal Architect, Design Brisbane via Development Services email dalodgement@brisbane.qld.gov.au

(i) The maintenance manual for the artwork/s, including any supporting documentation.

(ii) The itemised cost breakdown for each artwork including:

· Artists fees

· Design development costs

· Fabrication and installation costs

 
Prior to the commencement of the use and then to be maintained
22(e) Final Inspection

Arrange for the Principal Architect, Design Brisbane, to carry out a final inspection to confirm that the artwork has been installed in accordance with the requirements of this condition.

 
Prior to the commencement of the use and then to be maintained
 
23)   Driveway Material and Finishes

Provide materials and finishes to the driveway and external carparking surfaces that reduce the visual impact of these areas when viewed from the street. One or a combination of the following must be used:

-  Coloured aggregate;

-  Concrete pavers; and/or

-  Banding and patterns in the surface design.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
24)   Provide Pedestrian Prioritised Pathway

Provide a pedestrian prioritised pathway from the street frontages to the lobby and lifts. The pathway must be differentiated in colour and texture from the driveway surface.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
25)   Balconies/Verandahs/Terraces

No balconies/verandahs/terraces may be enclosed with solid balustrades, solid walls, fixed and/or operable, moveable or adjustable screening unless these features are clearly shown on the APPROVED DRAWINGS AND DOCUMENTS.

Note: Any Community Management Statement that may apply to this approval must contain a by-law which reflects the requirements of this condition.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
26)   Awning Lighting System

Install a lighting system to the underside of the awning over the footpath in accordance with the requirements of this condition.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
26(a) Submit Lighting Plan

Submit to, and obtain approval, from Construction Branch, Citywide Services, City Lighting (CS-LIGHTING@brisbane.qld.gov.au), a detailed Lighting Plan demonstrating that the under awning lighting complies with Australian Standard - AS/NZS 1158.3.1 - sub category P6, within - Road Lighting Part 3.1: Pedestrian area (Category P) lighting - Performance and installation design requirements and achieves glare control to ensure zero candelas (cd) at 90 degrees.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
26(b) Implement Approved Lighting Plan

Carry out the works in accordance with the approved Lighting Plan.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
26(c) Certification

Submit to Construction Branch, Citywide Services, City Lighting (CS-LIGHTING@brisbane.qld.gov.au), certification from a licensed electrical contractor that the awning lighting has been installed in accordance with the approved Lighting Plan.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first

 
As indicated
26(d) Maintain the Work

Maintain the awning lighting, (including operating costs) in accordance with the approved Lighting Plan from dusk to dawn.

Timing: To be maintained.

 
As indicated
 
27)   Screen Air Conditioning and Other Plant Enclosures

Install and maintain suitable screening to all air conditioning, lift motor rooms, plant and service facilities located at the top of or on the external face of the building and within the Private Open Spaces. The screening structures must be constructed from materials that are consistent with materials used elsewhere on the facade of the building. There must be no individual external air conditioning units.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
28)   Sun Shading Devices

Provide sun shading in accordance with the approved DRAWINGS AND DOCUMENTS.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
29)   Screening

Provide suitable privacy screening to windows of habitable rooms, balconies, landings, terraces and decks of the proposed dwelling(s) in accordance with the approved DRAWINGS AND DOCUMENTS.

Suitable screening options must be:

For windows:
-   Sill heights of 1.5m above floor level; or
-  Fixed obscure glazing in any part of the window below 1.5m above floor level; or
-  Fixed external screens to any part of the window below 1.5m above floor level, or
-  Fencing to a minimum 1.8m above ground floor level (only applies to overlooking from windows at ground floor level).

For balconies, landings, terraces and decks:
-  Fixed screening from floor level to a height of 1.5m above floor level.

Note: Screening devices must be either solid translucent screens, perforated or slatted panels, or fixed louvres that are permanent, be durable and fixed. Screening devices must have a maximum of 25% openings, with a maximum opening of 50mm.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
30)   Provide Detailed and Textured Model

Submit to Virtual Brisbane, a digital model for inclusion into the Brisbane City Council Virtual Brisbane 3D model. This must be a high quality, detailed and textured 3D exterior model of the approved development at a standard which can be publicly viewable. This must be of a compatible file format, include property boundaries and show heights in Australian Height Datum (AHD). For information on the submission and a complete list of requirements' visit: www.brisbane.qld.gov.au/virtualbrisbane3Drequirements

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate

 
As indicated
 
Landscape Architecture and Open Space Planning
 
Timing
31)   Retain and Protect Existing Street Tree(s)

Identify, retain and protect the existing street trees unless otherwise agreed in writing with Asset Services.   

Note: Street trees are protected under the Natural Assets Local Law.  Street trees must not be removed or pruned without prior approval from Asset Services

Where driveway crossovers occur within the Tree Protection Zone (TPZ) of existing street trees, seek approval from the Arboricultural Team in Program Planning and integration, City Standards for the final driveway crossover design and construction methodology to ensure the successful retention of the existing street tree(s)

 

PROOF OF FULFILMENT
Contextual photographic evidence that the tree has been retained in equal or greater health than before development commenced. OR, evidence in writing from Asset Services Arboriculture that an alternative arrangement has been made. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
At all times
31(a) Implement Protection Measures

Install tree protection measures in accordance with Australian Standard - AS4970 Retention of Trees on Development Site.

There must be no excavation, filling or storage of materials or plant within the drip line of the tree(s).

Where works are within the canopy drip line of existing street trees, contact Program Planning and Integration Regional Coordinator Arboriculture in relation to the required provision of protection measures.

Note: If fencing is to protect street trees, a permit to temporarily occupy the footway will be required from Compliance and Regulatory Services.

Timing: Prior to site/operational/building work occurring.

PROOF OF FULFILMENT
Contextual photographic evidence to demonstrate the installation of protection measures prior to building works commencing. Timing: Prior to site / operational / building work occurring.

 
As indicated
31(b) Maintain Protection Measures

Maintain protection measures while development is occurring and remove protection measures prior to commencement of the use.

Timing: While to site/operational/building work is occurring.

 
As indicated
 
32)   Streetscape Works - Centre Street

Carry out streetscape improvement works to the verge of Nile Street to a City Street minor standard in accordance with the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD), the requirements of this condition and the Infrastructure Design Planning Scheme Policy including section 3.7.4.3.

 

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
32(a) Submit Level Details

Submit to Development Services, and obtain approval for, details of the future finished levels of the site and building entries (both pedestrian and vehicular) to demonstrate verge levels and crossfalls complying with the Infrastructure Design Planning Scheme Policy including section 3.7.3.5. The details must be provided by an RPEQ in consultation with a qualified Landscape Architect and include the following:
-  finished surface levels at the site/lot boundary;
-   finished ground floor levels;
-  Existing kerb heights; and
-  crossfall and longitudinal grades.

Timing: Prior to site/operational/building work occurring.

 
As indicated
32(b) Submit Plan for Works in Verge

Submit, to an obtain approval from, Development Services, a detailed Landscape Works in Streetscape Plan for the required improvement works in accordance with the requirements of the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD) and the Infrastructure Design Planning Scheme Policy including section 3.7.4.3. The detailed Landscape Works in Streetscape Plan must be prepared at a scale of 1:100 by a qualified Landscape Architect and include the following:

-  Finished surface levels at lot boundary and kerb.
-  Cross-fall demonstrating compliance with Brisbane Standard Drawings (BSD), including a maximum crossfall of 1:50.
-  Longitudinal grades consistent along the frontage including along the property boundary, and no steeper than the existing gradient of the road at any point.
-  Existing and future kerb materials and heights.
-  Location of underground and above-ground services.
-  Location of service pits.
-  Conceptual location of pedestrian lighting where under awning lighting is not provided.
-  Location and description of street furniture.
-  Existing and future street trees.
-  Tree trench complying with Brisbane Standard Drawings (BSD) as required to ensure that topsoil extends at least 2m, measured along the kerb line, from either side of any tree.
-  Hazard and/or directional tactile ground surface indicators (TGSIs).
-  Reconstruction of kerb and channel.
-  Reconstruction of kerb ramps.
-   road use adjacent to the kerb (e.g. bus stops, parking bays).
-  Details of awnings including location, height, materials. A minimum clearance of 1.5m must be provided between tree trunk and the awning.
-  Balustrades or any other structures.
-  Location and details of any artwork.

Timing: Prior to building work above ground level commencing.

 
As indicated
32(c) Pre-Start Meeting

Arrange and attend a pre-start meeting with Development Services.

Applicable compliance and inspection fees must be paid to Council, in full, prior to the meeting being held.

Note: To arrange a pre- start meeting with Development Services an email must be sent to dalodgement@brisbane.qld.gov.au.

Timing: Prior to any work commencing to comply with this condition.

 
As indicated
32(d) Implement Streetscape Works

Remove the existing footway including affected street signage for the full length of the frontage.

Carry out the works in accordance with the approved detailed Landscape Works in Streetscape Plan and to a standard and using materials in accordance with the requirements of the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD) and the Infrastructure Design Planning Scheme Policy section 3.7.4.3.

Note: All existing artworks and regulatory signage must be secured and repositioned as agreed with Program Planning and Integration.

Note: Any existing Brisbane Tuff or granite kerbing that is surplus to requirements must be returned to Program Planning and Integration.

Note: At all times during construction provision must be made for people with a visual impairment.

Where it is unavoidable that a section of an existing Braille trail is to be blocked, or an object temporarily located to intrude within the 1000 mm clearway on either side of the Braille trail, the following actions must be undertaken to comply with the current version of AS1428:
-  Warning tactile ground surface indicators (TGSIs) must be installed around any temporary obstructions and intrusions to comply with the current version of AS1428 and Brisbane Standard Drawings (BSD), and must remain in place until the temporary obstructions and intrusions are removed; and
-  Brisbane City Council's Community Development Officer - Disability must be informed so that email alerts can be sent out to Vision Impairment agencies. At least one week's notice must be given.

Note: Lodge with and receive approval from Development Services for an 'Application for Permits Relating to Roads and Footway' prior to carrying out the approved works.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to the commencement of use, whichever comes first.

 
As indicated
32(e) Submit As-Constructed Drawings

Submit to Development Services Specialist Services As Constructed drawings including an asset register, prepared by a Registered Professional Engineer Queensland, certifying that the streetscape works have been completed in accordance with the approved detailed Landscape Works in Streetscape

Plan and to a standard and using materials in accordance with the requirements of the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD) and the Infrastructure Design Planning Scheme Policy section 3.7.4.3.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
32(f) On-Maintenance Acceptance

Arrange an on- maintenance inspection with Development Services and obtain written confirmation that the works have been accepted on-maintenance.

Provide proof of Public Liability Insurance ($20 million) for the on- maintenance period.

Lodge a bond for the streetscape works maintenance period of the works. The bond must be calculated in accordance with the relevant Brisbane Planning Scheme Codes (5% of total value of the landscape works or minimum of $5,000.00 whichever is greater).

Note: To arrange an on-maintenance inspection with Development Services an email must be sent to specialistservices@brisbane.qld.gov.au.

Note: A maintenance bond can consist of either a bank guarantee or monetary payment lodged with Council.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
32(g) On-Maintenance Period

Provide a minimum of 12 months maintenance to the streetscape works and rectify any defects identified at the on-maintenance inspection and those arising during the on-maintenance period.

Timing: Minimum 12 months from acceptance on- maintenance AND until the works are approved off-maintenance by Council.

 
As indicated
32(h) Off-Maintenance Acceptance

On completion of the on-maintenance period, arrange an off-maintenance inspection with Development Services and obtain written confirmation from Council that the work is accepted off-maintenance.

Ensure all defects are rectified prior to making an appointment for off- maintenance inspection.

Note: To arrange an off-maintenance inspection with Development Services an email must be sent to specialistservices@brisbane.qld.gov.au.

Note: If the off- maintenance inspection is successful the maintenance bond will be released.

Timing: On completion of the on-maintenance period.

 
As indicated
 
33)   Streetscape Works - Subtropical Boulevard (In Centre)

Carry out streetscape improvement works to the verge of Wellington Road to a Subtropical Boulevard (In Centre) standard in accordance with the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD), the requirements of this condition and the Infrastructure Design Planning Scheme Policy including section 3.7.4.2.1.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
33(a) Submit Level Details

Submit to Development Services, and obtain approval for, details of the future finished levels of the site and building entries (both pedestrian and vehicular) to demonstrate verge levels and crossfalls complying with the Infrastructure Design Planning Scheme Policy including section 3.7.3.5. The details must be provided by a qualified Landscape Architect or RPEQ and include the following:
-  finished surface levels at the site/lot boundary;
-  finished ground floor levels;
-  existing kerb heights; and
-  crossfall and longitudinal grades.

Timing: Prior to site/operational/building work occurring.

 
As indicated
33(b) Submit Plan for Works in Verge

Submit to Development Services, and obtain approval for, a detailed Landscape Works in Streetscape Plan for the required improvement works in accordance with the requirements of the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD) and the Infrastructure Design Planning Scheme Policy including section 3.7.4.2.1. The detailed Landscape Works in Streetscape Plan must be prepared at a scale of 1:100 by a qualified Landscape Architect and include the following:

-  Finished surface levels at lot boundary and kerb.
-  Cross-fall demonstrating compliance with Brisbane Standard Drawings (BSD), including a maximum crossfall of 1:50.
-  Longitudinal grades consistent along the frontage including along the property boundary, and no steeper than the existing gradient of the road at any point.
-  Existing and future kerb materials and heights
-  Location of underground and above-ground services.
-  Location of service pits.
-  Conceptual location of pedestrian lighting where under awning lighting is not provided.
-  Location and description of street furniture.
-  Existing and street trees.
-  Tree trench complying with Brisbane Standard Drawings (BSD) as required to ensure that topsoil extends at least 2m, measured along the kerb line, from either side of any tree.
-  Hazard and/or directional tactile ground surface indicators (TGSIs).
-  Reconstruction of kerb and channel.
-  Reconstruction of kerb ramps.
-  Road use adjacent to the kerb (e.g. bus stops, parking bays).
-  Details of awnings including location, height, materials. A minimum clearance of 1.5m must be provided between tree trunk and the awning.
-  Balustrades or any other structures.
-  Location and details of any artwork.

Timing: Prior to building work above ground level commencing.

 
As indicated
33(c) Pre-Start Meeting

Arrange and attend a pre-start meeting with Development Services.

Applicable compliance and inspection fees must be paid to Council, in full, prior to the meeting being held.

Note: To arrange a pre- start meeting with Development Services an email must be sent to dalodgement@brisbane.qld.gov.au.

Timing: Prior to any work commencing to comply with this condition.

 
As indicated
33(d) Implement Streetscape Works

Remove the existing footway including affected street signage for the full length of the frontage.

Carry out the works in accordance with the approved detailed Landscape Works in Streetscape Plan and to a standard and using materials in accordance with the requirements of the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD) and the Infrastructure Design Planning Scheme Policy section 3.7.4.2.1.

Note: All existing artworks and regulatory signage must be secured and repositioned as agreed with Program Planning and Integration.

Note: Any existing Brisbane Tuff or granite kerbing that is surplus to requirements must be returned to Program Planning and Integration

Note: At all times during construction provision must be made for people with a visual impairment.

Where it is unavoidable that a section of an existing Braille trail is to be blocked, or an object temporarily located to intrude within the 1000 mm clearway on either side of the Braille trail, the following actions must be undertaken to comply with the current version of AS1428:
-  Warning tactile ground surface indicators (TGSIs) must be installed around any temporary obstructions and intrusions to comply with the current version of AS1428 and Brisbane Standard Drawings (BSD), and must remain in place until the temporary obstructions and intrusions are removed; and
-  Brisbane City Council's Community Development Officer - Disability must be informed so that email alerts can be sent out to Vision Impairment agencies. At least one week's notice must be given.

Note: Lodge with and receive approval from Development Services for an 'Application for Permits Relating to Roads and Footway' prior to carrying out the approved works.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to the commencement of use, whichever comes first.

 
As indicated
33(e) Submit As-Constructed Drawings

Submit to Development Services Specialist Services As Constructed drawings including an asset register, prepared by a Registered Professional Engineer Queensland, certifying that the streetscape works have been completed in accordance with the approved detailed Landscape Works in Streetscape Plan and to a standard and using materials in accordance with the requirements of the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD) and the Infrastructure Design Planning Scheme Policy section 3.7.4.2.1.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
33(f) On-Maintenance Acceptance

Arrange an on- maintenance inspection with Development Services and obtain written confirmation that the works have been accepted on-maintenance.

Provide proof of Public Liability Insurance ($20 million) for the on- maintenance period.

Lodge a bond for the streetscape works maintenance period of the works. The bond must be calculated in accordance with the relevant Brisbane Planning Scheme Codes (5% of total value of the landscape works or minimum of $5,000.00 whichever is greater).

Note: To arrange an on-maintenance inspection with Development Services an email must be sent to specialistservices@brisbane.qld.gov.au.

Note: A maintenance bond can consist of either a bank guarantee or monetary payment lodged with Council.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
33(g) On-Maintenance Period

Provide a minimum of 12 months maintenance to the streetscape works and rectify any defects identified at the on-maintenance inspection and those arising during the on-maintenance period.

Timing: Minimum 12 months from acceptance on- maintenance AND until the works are approved off-maintenance by Council.

 
As indicated
33(h) Off-Maintenance Acceptance

On completion of the on-maintenance period, arrange an off-maintenance inspection with the Development Services and obtain written confirmation from Council that the work is accepted off-maintenance.

Ensure all defects are rectified prior to making an appointment for off- maintenance inspection.

Note: To arrange an off-maintenance inspection with Development Services an email must be sent to specialistservices@brisbane.qld.gov.au.

Note: If the off- maintenance inspection is successful the maintenance bond will be released.

Timing: On completion of the on-maintenance period.

 
As indicated
 
34)   Pedestrian and/or Awning Lighting

Install Pedestrian and/or Awning Lighting in accordance with the requirements of this condition.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
34(a) Submit a Pedestrian and Awning Lighting Design

Submit to Program Planning and Integration (City Lighting), and obtain approval for, a detailed Pedestrian Lighting Design for the full street frontage of the development, and/or Awning Lighting Design to the underside of the proposed awning over the verge in accordance with the following:

Pedestrian Lighting:

Provide electrical reticulation plans prepared by a Registered Professional Engineer Queensland certifying that the design complies with Australian Standard - AS/NZS3000 Electrical installations known as the Australian/New Zealand Wiring Rules and Council's standard drawings (BSD-11000 series).

Provide pedestrian and cycle lighting plans prepared by a Registered Professional Engineer Queensland or a member of the Illuminating Engineering Society of Australia and New Zealand certifying that the design complies with Australian Standard - AS/NZS 1158.3.1 Lighting for roads and public spaces - Pedestrian area (Lighting Sub- category PP3) lighting - Performance and Design requirements.

And/Or

Awning Lighting:

Submit to Program Planning and Integration (City Lighting), and obtain approval for, a detailed Awning Lighting Plan demonstrating that the under awning lighting complies with Australian Standard - AS/NZS 1158.3.1 - sub category P6, within - Road Lighting Part 3.1: Pedestrian area (Lighting Sub- category PA3) lighting - Performance and installation design requirements and achieves glare control to ensure zero candelas (cd) at 90 degrees.

Timing: Prior to commencing building work above ground level and prior to or concurrently with the submission of Landscape Works in Streetscape Plans for approval.

 
As indicated
34(b) Obtain an Electrical Connection

Obtain an electrical connection from the electricity supplier / Enter into an arrangement with the electricity supplier to service the approved pedestrian lighting.

Timing: Prior to commencing building work above ground level.

 
As indicated
34(c) Implement Approved Pedestrian and/or Awning Lighting Design

Install the lighting in accordance with the approved detailed Pedestrian Lighting Design and the approved Landscape Works in Streetscape Plan and/or Awning Lighting Design.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
34(d) Provide Certification of Connection and Operation

Provide to Program Planning and Integration (City Lighting) certification from a licensed electrical contractor that the electrical connection has been installed in accordance with the approved detailed Pedestrian Lighting Design and/or Awning Lighting Design and that the lighting is fully operational. The certification must specify that the electrical installation has been tested to ensure it is electrically safe and in accordance with the requirements of Australian Standard - AS/NZS3000 Electrical installations known as the Australian/New Zealand Wiring Rules and any other standard applying to the electrical installation under the Electrical Safety Regulation 2002.

A copy of the as-constructed Pedestrian Lighting Design Drawings must be included with the above certification.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
34(e) On-Maintenance Acceptance

Arrange an on- maintenance inspection with Program Planning and Integration (City Lighting) and obtain written confirmation from Council that the work has been completed in accordance with the requirements of the condition and is accepted on- maintenance.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
34(f) On-Maintenance Period

Provide a minimum 12 months maintenance to the works from the time the works are accepted on- maintenance by Council. During this period maintain the lighting and rectify any defects identified at the on-maintenance inspection and those arising during the on-maintenance period.

Timing: Minimum 12 months from acceptance on-maintenance AND until the works are approved off- maintenance by Council.

 
As indicated
34(g) Off-Maintenance Acceptance

On completion of the on-maintenance period arrange an off-maintenance inspection with Program Planning and Integration (City Lighting) and obtain written confirmation from Council that the work is accepted off- maintenance.

Ensure all defects are rectified prior to making an appointment for off-maintenance inspection.

Timing: On completion of the on-maintenance period.

 
As indicated
34(h) Maintain the Work (Awning Lighting)

Maintain the awning lighting (including operating costs) in accordance with the approved Lighting Plan from dusk to dawn.

Timing: To be maintained.

 
As indicated
 
35)   Landscape the site - Container planting for rooftop gardens and/or green walls

Landscape the site through the provision of container planting in accordance with the requirements of this condition.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
35(a) Prepare Detailed Container Planting Design for self-certification

Prepare a Detailed Container Planting Design for all container planting identified on the approved DRAWINGS AND DOCUMENTS.  The plan must be prepared and certified by suitably qualified professionals and must comply with the relevant Brisbane planning scheme codes.  In addition to the above, the design must include the following:
-  Shade and aspect studies including:
-  Sunshade modelling for 9am, noon and 3pm on June 21, September 22 and December 21;
-   Wind report measuring m/s for the container planting location/s;
-   Detailed estimates of required weekly water consumption for irrigation for each calendar month by an Irrigation Association of Australia certified irrigation designer, holding a Diploma of Irrigation
-  a dedicated rainwater irrigation tank with a minimum storage capacity of 100,000L, with green wall drainage return and overflow connected to the stormwater system;
-  a reticulated drip irrigation system with stand-alone power supply and smart-tech central control and alert;
-  waterproofing;
-  adequate fascia protection and drip tray depth to minimize drips onto the footpath or surrounding properties;
-  for planter boxes:
  -   adequate width, depth and suitability of soil for the planting. Minimum internal depths of planters unless otherwise endorsed by Development Services must be trees 1200mm; large shrubs and palms; 800mm; small shrubs and groundcovers; 600mm;
  -  a plant schedule that demonstrates planting appropriate to container type, size and location, -  considering orientation, shading and wind direction;
-  for vegetation supported by trellises and screens:
-  design to ensure at least 50% coverage of the trellis or screen area with living plants;
for green walls (proprietary items):
  -  construction and planting design to ensure 100% coverage of the wall with living plants;
-  a panel system that utilizes inert (non-soil), non-biodegradable media that creates at least 98% rootable surface area, not comprised of soil/ particulate-based pot or module systems;
-  a plant schedule completed by a specialist green wall designer that demonstrates planting appropriate to container type, size and location, considering orientation, shading and wind direction;
-  structural design by an RPEQ to ensure that the saturated weight of container planting is suitable for the building;
  -  a 12-month establishment period maintenance program for planting;
  -  an ongoing annual maintenance program including clearly defined access plan.

Timing: Prior to building work commencing.

 
As indicated
35(b) Implement certified Detailed Landscape Container Planting Design

Carry out the works in accordance with the above certified Detailed Landscape Container Planting Design.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
35(c) Certify work - Implementation

On completion of the work, submit to Development Services the following:
-  For planter boxes including vegetation supported by trellises and screens, certification by a Qualified Landscape Architect that construction and planting has been carried out in accordance with the conditions of development approval and the approved drawings
-  For green walls, certification of installation and planting by the manufacturer
-  Certification of irrigation design including irrigation tank size by an Irrigation Association of Australia certified irrigation designer, holding a Diploma of Irrigation
-  Certification by a Registered Professional Engineer Queensland that stormwater drainage and structural design have been provided in accordance with the conditions of development approval
-  As-constructed drawings showing:
  -  The extent and internal dimensions of planter boxes
  -  The extent and type of trellises and screens to support planting
  -  The extent of green walls;
  -  Planting layout and species.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
35(d) Certify work - establishment period

On completion of the 12-month establishment period, submit to Development Services certification that planting has been established in accordance with the certified Detailed Landscape Container Planting Design.

Timing: 12 months after implementation of the certified Detailed Landscape Container Planting Design.

 
As indicated
35(e) Maintain container planting

Maintain the container planting generally in accordance with the certified Detailed Landscape Container Planting Design.

Timing: To be maintained.

 
As indicated
 
36)   Landscape the Site - Self Certification

Landscape the site in accordance with the requirements of this condition.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
36(a) Detailed Landscape Plan for Self- Certification

Prepare a Detailed Landscape Plan at a scale of 1:100 for all on-site landscape works including planting areas identified on the approved DRAWINGS AND DOCUMENTS. The plan must be prepared by a Qualified Landscape Architect and must comply with the relevant Brisbane Planning Scheme Codes.

The plan must include the following:
-  Planting media and mulch in accordance with AS4454 Composts, soil conditioners and mulches and AS 4419-2003 Soils for landscaping and garden use.
-  Unless otherwise specified, trees provided as 45 litre stock or larger, staked and tied, and complying with Australian Standards.
-  Plant selection and densities to achieve full surface coverage of garden beds within 2 years of planting.
-  A reticulated drip irrigation system to all planting areas, with drainage connected to the stormwater system; the irrigation system must be connected to a non-mains water source.
-  Trees required to be retained are documented, integrated into landscape design, and protected in accordance with the relevant sections of Australian Standard AS4970 Protection of trees on development sites.
-  Details of a 12 week establishment period.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

PROOF OF FULFILMENT
A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
36(b) Centre or Mixed Use

In addition to the requirements listed above, the plan must include the following:
-  Deep planting areas as shown on the approved drawings planted with trees capable of growing to a minimum canopy diameter of 5m and a minimum height of 5m within 5 years of planting noting that this is a minimum requirement and trees are expected to grow beyond these measurements.
-  a minimum of 25% of all trees as 200L stock or larger.
-  Shade trees planted at 6m intervals where in garden beds abutting car parks.
-  A mix of columnar and round canopy trees planted at suitable spacings along front boundaries in planting areas shown on the approved drawings.
-  Columnar canopy form or screening tree/shrub species planted at suitable spacings alongside and rear boundaries in planting areas shown on the approved drawings.
-  Minimum internal depths and widths sufficient to support healthy plant growth, with the following dimensions or other dimensions if achieving the same soil volume; trees - 1200m width x depth, large shrubs and palms - 800mm width x depth, small shrubs and groundcovers - 600mm width x depth.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

PROOF OF FULFILMENT
A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
36(c) Certify Detailed Landscape Plan

On completion of the Detailed Landscape Plan, submit to Development Services:
-  Brisbane City Council Form CC10616 - Landscape Design Certificate prepared by a Qualified Landscape Architect to certify that the Detailed Landscape Plan complies with the requirements of this condition
-   A copy of the certified Detailed Landscape Plan.

Timing: Prior to building work commencing.

PROOF OF FULFILMENT
A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to building work commencing.

 
As indicated
36(d) Implement Certified Detailed Landscape Plan

Carry out the landscape work in accordance with the above certified detailed Landscape Plan.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
36(e) Certify Work

On completion of the landscape work, submit to Development Services:
-  Brisbane City Council Form CC10613 - Landscape Works Certificate prepared by a Qualified Landscape Architect or licensed Landscape Contractor to certify the completed landscape work complies with the certified Detailed Landscape Plan
-  A copy of the as-constructed certified Detailed Landscape Plan.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

PROOF OF FULFILMENT
An as constructed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
36(f) Maintain Landscape Work

Maintain the landscape work, including deep planting, in accordance with the certified Detailed Landscape Plan.

Timing: To be maintained.

 
As indicated
 
Pollution
 
Timing
37)   Kitchen exhaust vents - (emitters)

Kitchen and food preparation area exhaust vent outlets are discharged vertically, directed away from any sensitive use and separated by a minimum of 6m from a sensitive use, including any outdoor air intake of a sensitive use.

Note: This condition does not authorise environmental nuisance under the Environmental Protection Act 1994.

 
At all times
 
38)   Car park and bus station exhaust vents - (emitters)

Car park exhaust vent outlets are separated from any sensitive use by a minimum of 15m.

Note: This condition does not authorise environmental nuisance under the Environmental Protection Act 1994.

 
At all times
 
39)   Exhaust vents - (sensitive uses)

Dwellings and outdoor air intakes for dwellings, are separated from:
(a) exhaust vent outlets of premises where food or cooking odour is released, by a minimum of 6m; and
(b) exhaust vent outlets from car parks or bus stations, by a minimum of 15m.

Note: This condition does not authorise environmental nuisance under the Environmental Protection Act 1994.

 
At all times
 
40)   Acid Sulfate Soils - Management Plan

Acid Sulfate Soils must be managed in accordance with this condition.

 
As indicated
40(a) Submit Management Plan

Submit for approval an Acid Sulfate Soils Management Plan prepared in accordance with the Potential and actual acid sulfate soils overlay Code, City Plan 2014.

 
Prior to site/operational/building work commencing
40(b) Implement Management Plan

Implement the approved Acid Sulphate Soils Management Plan.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first
40(c) Submit Certification

Submit certification to Development Services that the requirements of the approved Acid Sulphate Soils management plan have been carried out.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
41)   Mechanical Plant or Equipment - Acoustically Screened

Mechanical plant or equipment is to be acoustically screened from an adjoining sensitive use. Mechanical plant includes generators, motors, compressors and pumps such as air-conditioning, refrigeration and cold room motors. Acoustically screened is defined in City Plan 2014.

NOTE: This condition does not authorise environmental nuisance under the Environmental Protection Act 1994.

PROOF OF FULFILMENT
Submit to Development Services, certification that all mechanical plant or equipment, is acoustically screened. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
42)   Dwelling Unit Construction General

Design and construct the development to achieve a minimum reduction in sound pressure level between the exterior of the building and the bedrooms or indoor primary living areas of 30dBA.

PROOF OF FULFILMENT
Provide Certification that appropriate facade noise mitigation has been provided to the development. Certification must be provided by a member or professional eligible to be a member of the Australian Acoustic Society. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
43)   Dampening of Grilles and Metal Plates

All metal grilles, metal plates or similar located within vehicle parking and manoeuvring areas must be securely fastened and meet the requirements of AS3996:2019, Access covers and grates.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
44)   Buildings in Transport Noise Corridors - Acoustic Treatments

All new houses, townhouses, units, hotels and motels (Class 1-4 buildings) on sites located in a designated transport noise corridor are required to comply with the requirements of the Queensland Development Code Mandatory Part 4.4 - Buildings in Transport Noise Corridors. The buildings will need to achieve specific levels of noise mitigation through the use of appropriate materials for floors, walls, roofs, windows and doors for the relevant noise category.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
45)   Stormwater Quality (Implement Management Plan)

Manage stormwater quality in accordance with this condition.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
45(a) Implement Management Plan

Implement the Stormwater Management Plan (CDA031, P6, prepared by EDGE Consulting Engineers) (consisting of at least 1 x SPEL Stormsack filter baskets and 8 x SPEL Filter cartridges), received 04/07/2024.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
45(b) Certification

Submit to Development Services certification from a relevant professional that all treatments and measures recommended in the Stormwater Management Plan (CDA031, P6, prepared by EDGE Consulting Engineers) (consisting of at least 1 x SPEL Stormsack filter baskets and 8 x SPEL Filter cartridges), received 04/07/2024, have been implemented.

A copy of the as-constructed site based stormwater quality measures must accompany the Certification.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
45(c) Maintain Management Plan

Maintain the Stormwater Management Plan (CDA031, P6, prepared by EDGE Consulting Engineers) (consisting of at least 1 x SPEL Stormsack filter baskets and 8 x SPEL Filter cartridges), received 04/07/2024.

 
As indicated
 
Engineering
 
Timing
46)   On-site Erosion (Medium Risk)

Manage on-site erosion and the release of sediment or sediment laden water from the site at all times by implementing best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version).

Timing: Prior to commencement of any land disturbing activities and until all exposed soil areas are permanently stabilised against erosion.

 
As indicated
46(a) Manage earth disturbance on- site

(i)  Drainage control measures must be implemented and maintained to minimise water flow onto areas of exposed earth.

(ii)  Sediment and erosion control measures must be implemented and maintained to prevent soil loss from earth disturbance areas and prevent deposition beyond earth disturbance areas.

(iii)  No release of contaminants to land beyond on-site area of earth disturbance other than releases that achieve water pollutant concentration release limits of:

  A. 50mg/L TSS (Total Suspended Solids);

  B. Turbidity, Nephelometric Turbidity Units (NTU) value less than 10% above background, 75 NTU, or as agreed in writing by an Officer from Councils Erosion and Sediment Control (ESC) Team in Compliance and Regulatory Services;

  C. pH between 6.5 and 8.5 at all times.

(iv)  Maintain a written record to demonstrate that water discharges from the site, including any dewatering operations, meet the release limits as detailed in (iii) for water discharge(s) from the site that occur during or immediately after a rainfall event, and during normal business hours. The water quality of the discharge flows must be measured at each discharge point from the site, including but not limited to sediment basin outlets, other applicable sediment control devices, the site water drainage system, and recorded against the release limits at least once on each calendar day until such discharge stops.

Timing: Prior to commencement of any earth disturbing activities and until all exposed soil areas are permanently stabilised against erosion.

 
As indicated
46(b) Provide Land Occupier Notification to Council

(i) Notify Council's ESC Team of proposed land occupier/s by sending an email to CARS-ESC@Brisbane.qld.gov.au

(ii) If the land is to be occupied by any person other than the registered landowner then advice must be provided to Council that confirms the name, contact information and the duration of any proposed occupation of the land.

Timing: Prior to commencement of any earth disturbing activities.

 
As indicated
46(c) Prepare Erosion and Sediment Control Plan

Prepare an Erosion and Sediment Control Plan (ESCP) in accordance with best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version) and, to the extent of any inconsistency, relevant Brisbane Planning Scheme Codes and Policies.

Obtain a design certificate in accordance with the relevant Brisbane Planning Scheme Codes and Policies.

The ESCP and design certificate must be certified by a Certified Professional in Erosion and Sediment Control (CPESC) or a Registered Professional Engineer Qld (RPEQ) with suitable qualifications and experience in erosion and sediment control.

Documentary evidence demonstrating appropriate qualifications in erosion and sediment control must be provided to the Council upon request.

Timing: Prior to the commencement of any earth disturbing activities.

 
As indicated
46(d) Attend a pre-start meeting

Arrange and attend a pre-start meeting for ESC with an Officer from Councils ESC Team in Compliance and Regulatory Services (CARS).

Note: To request a pre-start meeting from Council's ESC Team send an email to CARS-ESC@Brisbane.qld.gov.au. All relevant documentation, including both the certified ESCP and the certified design certificate, must be attached to this email.

Please allow up to 10 business days for your request to be processed.

Timing: Attend the pre- start meeting prior to the commencement of any earth disturbing activities.

 
As indicated
46(e) Implement Certified Erosion and Sediment Control Plan

Implement the certified ESCP and maintain all ESC measures in accordance with best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version) and, to the extent of any inconsistency, relevant Brisbane Planning Scheme Codes and Policies.

The ESCP and design certificate must be available on site at all times for inspection by Council officers. Any alteration to supplementary or Type 3 ESC measures must be reflected in the certified ESCP. Any alteration to Type 2 or Type 1 ESC measures will require a revised ESCP and design certificate that has been certified by either the CPESC or RPEQ.

Timing: While earth disturbing activities are occurring and until all exposed soil areas are permanently stabilised against erosion.

 
As indicated
 
47)   Maintenance Period for Engineering Work

Maintain the work required by the Engineering condition(s) imposed on this development approval and rectify any defects in accordance with the requirements detailed in this condition.

Note: Guidance for requesting a pre-start and co- ordinating the On/Off Maintenance process can be found on Council's website (https://www.brisbane.qld.gov.au/planning-and-building/applying-and-post- approval/on-and-off-maintenance-approvals).

Timing: During the on-maintenance period.

 
As indicated
47(a) On-Maintenance Acceptance

Arrange an on- maintenance inspection with Development Services and obtain written confirmation from Council that the work has been completed in accordance with the requirements of the condition and is accepted on-maintenance.

Provide proof of Public Liability Insurance ($20 million) for the on- maintenance period.

Lodge a maintenance security for the on-maintenance period. The security must be calculated as 5% of the value of the constructed work or $10,000.00, whichever is greater.

Note: A maintenance security may consist of either a bank guarantee or monetary payment lodged with Council. Refer to Council's Infrastructure Installation and Construction Requirements Manual for further details about the on-maintenance procedure and requirements.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
47(b) On-Maintenance Period

Provide a minimum 12 months maintenance to the work from the time the work is accepted on- maintenance by Council. During this period maintain the work and rectify any defects identified at the on-maintenance inspection and those arising during the on-maintenance period.

Note: The on-maintenance period may be extended by Council pending concerns and/or unsatisfactory performance during the maintenance period.

Timing: A minimum 12 months from acceptance on-maintenance.

 
As indicated
47(c) Off-Maintenance Acceptance

On completion of the maintenance period arrange an off-maintenance inspection with Development Services and obtain written confirmation from Council that the work is accepted off-maintenance.

Ensure all defects are rectified prior to making an appointment for off- maintenance Inspection.

Note: If the inspection is successful the maintenance security will be released.

Timing: On completion of the on-maintenance period.

 
As indicated
 
48)   Information Signage

Erect an information sign on the subject property in accordance with Council's general requirements for signage and in accordance with the requirements outlined below:
a)  The sign should provide a brief description of the development proposed;
b)  The sign is to list the name, postal and/or email address and a contact telephone number for the following parties (where relevant) that are undertaking work on the site:
     -  Developer;
     -   Project Coordinator;
     -  Architect/Building Designer;
     -  Builder;
     -  Civil Engineer;
     -   Civil Contractor/s; and
     -  Landscape Architect;
c)  The lettering on the sign is to be at least 25 millimetres in height, be of regular weight and in sentence case;
d)  The sign is to be a minimum size of 1,200 millimetres by 900 millimetres;
e)  The maximum area of the sign is to be 2.0m2;
f)  The sign is to be positioned as follows:
     -  located centrally along each road frontage of the site to Wellington Road and Nile Street;
     -  located on or within 1.5 metres of the road frontage;
     -  mounted at least 300 millimetres above ground level; and
     -  clearly visible from the street for a pedestrian;
g)  The sign is to contain no commercial or corporate advertising other than the name, logo or slogan of the parties outlined in part (b) of this condition;
h)  The sign is to be non-illuminated; and
i)   Both the sign and the supporting structure are to be made of weatherproof material and to be properly maintained at all times;

Timing: Prior to site works commencing and then to be maintained until completion of the development for all stages.

 
As indicated
 
49)   Engineering Pre-Start Meeting

Arrange and attend a pre-start meeting with Development Services and Program Planning and Integration.

Applicable compliance and inspection fees must be paid, in full, to Council prior to the meeting being held.

Note: To arrange an engineering pre-start meeting with Development Services an email supported by a completed copy of the Pre-Start Meeting Guidelines - Civil Engineering Works kit (https://www.brisbane.qld.gov.au/sites/default/files/20191008-cc11207-pre- start-meeting-guidelines-civil-engineering-works.pdf) must be sent to dalodgement@brisbane.qld.gov.au.

Details include (but are not limited too) the following:
-  Site address, Development Approval number (A00) and relevant stage/s (if appropriate);
-  List all Development Approval conditions requiring compliance prior to site/operational/building work commencing and demonstrate compliance with those conditions;
-  Payee details (Name and address) for the issue of a development 'Compliance and Inspection Fee' quote;
-  Superintendent (Consultant) name, address and telephone number (including after-hours contact);
-  Contractor/s and major Sub-Contractor/s, name, address and telephone number (including after-hours contact);
-  Intended date of commencement of works.

Note:
-  All operational works/compliance assessment applications are to be approved prior to requesting the pre-start meeting.
-  A minimum 5 working days' notice is required.
-  Compliance and Inspection fee to be paid prior to undertaking pre-start meeting.
-  All operational works/compliance assessment approved documents and the Development Approval package (conditions and plans) must be available at the pre-start meeting.
-  Further guidance for requesting a pre-start and co-ordinating the On/Off Maintenance process can be found on Council's website (https://www.brisbane.qld.gov.au/planning-and-building/applying-and-post- approval/on-and-off-maintenance-approvals).

Timing: Prior to site/operational/building work commencing.

 
As indicated
 
50)   Basement Excavation and Support

Basement excavation and support of all exposed walls must be carried out in accordance with the relevant Brisbane Planning Scheme Codes and the requirements of this condition.

 
Prior to building work commencing
50(a) Prepare Engineering Drawings

Engineering drawings for the work required by this condition must be prepared and certified by a Registered Professional Engineer Queensland (Structural), in accordance with the relevant Brisbane Planning Scheme Codes detailing the design of the proposed excavation as well as proposed temporary and permanent support (if no temporary proposed) systems.

The design must include at least the following:
-  The location (in plan and section) of the proposed excavation;
-  Detailed design of proposed temporary support of the excavation;
-  If no temporary support is proposed then detail design of the proposed permanent support of the excavation;
-  Any retention system, including associated drainage, is to be wholly contained within the site unless written approval has been obtained from the affected neighbouring property owner;
-  The existing and proposed finished levels in reference to the Australian Height Datum (including cross-sections or long sections into the adjacent properties);
-  Preservation of all drainage structures from the effects of structural loading generated by the excavation;
-  Protection of adjoining properties and roads from adverse impacts as a result of Building Works;
-  All existing Brisbane City Council stormwater lines and Maintenance Holes, including depths of Maintenance Holes and clearances to retention structures is to be shown.
Where ground or rock anchors are proposed as a temporary support (Note: permanent anchors are not acceptable) the design must include the following in addition to the above:
-  Anchor position/s and length/s (in elevation view and sectional view);
-  Where the anchoring system is proposed to encroach into a neighbouring property, written approval is to be obtained from the affected property owner;
-  Plans must show the location of the ground anchors in relation to all existing services and public utilities. The cost of relocating any existing services, public utilities or BCC assets is the responsibility of the Developer.

Notes:
- The Earthworks drawings are not required to be submitted for Council approval.
-  Where any ground anchors or rock bolts are proposed within 10metres in the vertical plane of a UU sewer, UU water main, BCC stormwater line or combined sanitary drain, assessment will be required against the QDC section MP1.4 by the building certifier.
-  Ground anchors are not to be located closer than 1.0m vertically or 1.0m horizontally from existing or proposed Council Infrastructure.
-  If the basement excavation impacts on the road reserve, the developer must obtain applicable footpath and road permits prior to commencing any works.  Such impacts may include footpath occupation, road closures, re-profiling, ground anchors and/or relocation of services.
-  Where public utilities such as UU sewer or water infrastructure, electricity, telecommunication or gas infrastructure will be affected advice must be obtained from the respective utility owner.

Timing:  Prior to site/operational/building work commencing.

 
As indicated
50(b) Implement Certified Engineering Drawings

Construct and maintain the basement excavation and proposed support system in accordance with the above certified engineering drawings.

Note: A copy of the certified engineering drawings must be available on- site for inspection by Council Officers during these works.

Timing: While basement excavation and support system installation is occurring.

 
As indicated
50(c) Submit Post Construction Certification

Submit certification by a Registered Professional Engineer Queensland that the basement excavation and support have been installed in compliance with the certified engineering drawings, the relevant Brisbane Planning Scheme Codes and the requirements of this condition.

Where ground or rock anchors have been installed, submit certification by a Registered Professional Engineer Queensland (Geo-technical) that all anchors have been de- stressed.

Timing: Prior to building work commencing above ground.

 
As indicated
 
51)   CBD/City Frame Construction Management Plan

Carry out development in accordance with a Construction Management Plan (CMP) prepared in accordance with the Central Business District and City Frame Development Services Construction Management Guidelines and the requirements set out in this condition.

Note:  This condition imposes restrictions on development construction management to regulate increased truck access, on street work zone and closures and all associated activities in the CBD and City Frame as a result of major State and Local Government infrastructure projects occurring in Brisbane.

 
While site/operational/building work is occurring
51(a) Submit Construction Management Plan

Submit to, and obtain approval from, Development Services a Construction Management Plan for the demolition, excavation and construction phases of the approved development.  Separate Construction Management Plans may be appropriate for the individual components.

The Construction Management Plan must be in accordance with the Central Business District and City Frame Development Services Construction Management Guidelines and the relevant Brisbane Planning Scheme Codes and address the following:
(i)      Provision for pedestrian management including alternative pedestrian routes (adjacent to or surrounding the site);
(ii)     Existing and proposed kerbside allocation signs and line marking (such as bus stops, loading zones and parking meters and/or ticket dispensers);
(iii)    Location of and impacts to any Council or other public utility or local authority's assets on or within external to the site;
(iv)    Location and design of temporary vehicular construction access points, including frequency of use;
(v)     Management and mitigation strategies for the impact of dust, noise and vibration upon adjoining and nearby properties;
(vi)    Provision for loading and unloading of materials including the location of any remote loading sites;
(vii)   Location of materials, structures, plant and equipment to be stored or placed on the construction site;
(viii)  Location of proposed external hoardings and/or gantries, and including clearances to the impacts of this on  existing street furniture and other footpath assets located within the verge as well as impacts on any existing advertising signage located either along or adjacent to the site frontage  - this includes any potential obstruction of sight lines for such advertising  (e.g. 'CityCycle' bicycle stations or bus stops with advertising);
(ix)    Location of proposed employee and visitor parking areas;
(x)     Anticipated staging and programming;
(xi)    Impacts of any actions proposed to address any of the above items or any actions resulting from construction of the development that will impact on existing street trees;
(xii)   Complaint management processes to be implemented; and
(xiii)  Compliance with the Management Plans Planning Scheme Policy and other relevant Planning Scheme Policies.

The Construction Management Plan must be supported by 'approval in principle' or written approvals from the relevant Council sections or other governing bodies responsible for any potentially impacted infrastructure.

Timing: Prior to site/operational/building work commencing.

 
As indicated
51(b) Construction Management Plan - Dilapidation Report

Submit a dilapidation report to engineeringservices@brisbane.qld.gov.au detailing the pre-existing condition of the roadway, both footways, both verges and Council infrastructure, including vegetation, for 100m from the site entry in both directions or to the next street intersection (if less than 100m from the site entry) in both directions.

Timing: Prior to the pre-start meeting.

 
As indicated
51(c) Construction Management Plan - Associated Activities in Road Reserve

Obtain relevant approvals, as listed in part (a) of this condition, to carry out any works within the road reserve required by the approved Construction Management Plan identified in the Central Business District and City Frame Development Services Construction Management Guidelines.

Note:  All fees must be paid in full prior to any permit being granted by Council. Council may revoke any permits at any time for non-compliance with requirements or if it considers that safety, capacity and/or operation of public transport, vehicle and pedestrian traffic are likely to be compromised during the construction phase.

Timing: Prior to site/operational/building work commencing.

 
As indicated
51(d) City Frame Construction Management Plan - Documentation on Site

Legible copies of the approved CBD Construction Management Plan and current permits must be kept on site and be made available on request At all times.

The requirements of the CMP must be included in all induction of principal and subcontractors utilised in the development. An outline of the induction provided to contractors may be requested by Council to confirm compliance with this condition.

Timing: While site/operational/building work is occurring.

 
As indicated
51(e) Construction Management Plan - Works to be Performed Out of Hours

Obtain an approval from Development Services for any work that is proposed to be undertaken outside of normal business hours - 6:30am to 6:30pm, Monday to Saturday.

Timing: Prior to site/operational/building work commencing.

 
As indicated
51(f) Implement Approved Construction Management Plan

Carry out the development in accordance with the approved CBD/City Frame Construction Management Plan.

 
While site/operational/building work is occurring
 
52)   Protect Existing Infrastructure

Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure.

Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations.

The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements.

 
While site/operational/building work is occurring
52(a) As Constructed Drawings - Alterations to Existing Infrastructure

Submit to Development Services As Constructed drawings showing all new and/or rectification works and an asset register, prepared by a Registered Professional Engineer Queensland.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

PROOF OF FULFILMENT
Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
53)   Retaining Walls

Design and construct all retaining walls and associated fences, in accordance with the relevant Brisbane Planning Scheme Codes and the following:

-  All retaining walls including the footings, must be located wholly within the property boundaries of the site where works are occurring

-  Runoff from surface drains and subsoil drainage associated with the retaining walls (irrespective of the height of the wall) must be collected and conveyed to a lawful point of discharge and must not cause any ponding, nuisance or disturbance to adjacent property owners.

-  Retaining walls to stabilise excavation must be set back from property boundaries to accommodate subsoil drainage without encroachment into the neighbouring property. This set back may vary depending on the height, structure and design of the retaining wall, surcharge loadings from neighbouring properties, and to provide a surface drain along the top of the retaining wall

- For retaining walls in excess of 1.0m in height:
      - walls must be vertically and horizontally tiered by a ratio of 1:1 unless an alternative has been approved by Development Services
      - walls must be designed and certified by a Registered Professional Engineer Queensland
      - walls facing onto Council property (including the road reserve and parkland) must not be constructed from timber.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
53(a) Certification of Retaining Walls

For retaining walls over 1.0m in height, obtain certification from a Registered Professional Engineer Queensland that the design and construction of the retaining walls and ancillary drainage are in accordance with the requirements of this condition.

 
As indicated
 
54)   Access, Grades, Manoeuvring, Carparks, Signs and Line Marking

Construct and maintain access, parking and manoeuvring for vehicles on site in accordance with the relevant Brisbane Planning Scheme Codes, as indicated on the approved DRAWINGS AND DOCUMENTS, including the following:

i. A pavement of minimum Local road standard or equivalent surface material (including associated drainage) to the area on which motor vehicles will be driven and/or parked.

ii. Suspended concrete parking areas, aisles and driveways are to be designed and certified by an RPEQ to accommodate the required design vehicles/s identified in this condition.

iii. Manoeuvring on site for a RCV and for the loading and unloading of vehicle(s);

iv. Parking on the site for a maximum of 591 resident/tenant cars, a maximum of 87 visitor cars inclusive of 4 parking spaces for people with disabilities and for the loading and unloading of vehicle(s) within the site.

v. Provide and maintain a minimum of 528 secure bicycle parking spaces for residents/tenants, and 146 securable bicycle parking spaces for visitors.

vi. A minimum of 2.3 metres height clearance to all undercover parking areas and a minimum of 2.5 metres above parking spaces for people with disabilities. The minimum clear height must be measured to the lowest protrusion from the ceiling (e.g. fire sprinklers, services, lighting fixtures, signs, etc).

vii. A height clearance sign located at the entrance(s) to undercover car parking areas and a directional visitor parking sign clearly visible from the vehicle entrance to the site.

ix. Prepare and implement signs and line markings drawings that show the internal paved areas signed and delineated in accordance with the approved drawings and documents. The drawings must be prepared and certified by a Registered Professional Engineer Queensland in accordance with the relevant Brisbane Planning Scheme Codes and the Manual of Uniform Traffic Control Devices.

PROOF OF FULFILMENT
Certification from a Registered Professional Engineer Queensland, that the above requirements have been implemented in accordance with this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
55)   Repair Damage to Kerb, Footpath or Road

Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
55(a) Interim Repairs

If at any time during the construction phase of the approved development, damage to the existing kerb and channel, footpath or roadway creates unsafe, unreasonable and/or not fit for purpose conditions as assessed by Council, interim repairs must be undertaken as directed by Program Planning and Integration.

Note: Any interim repairs required to be undertaken shall not be considered to satisfy the requirements of this condition for the permanent repair of the infrastructure prior to the issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

Timing: While site / operational / building works is occurring.

 
As indicated
 
56)   Self-Certified Structural Design in Flood Planning Areas

Structural works within the following Flood Planning Areas must be designed and constructed by a Registered Professional Engineer Queensland (Structural).  The RPEQ (Structural) must certify that the works are structurally adequate to resist hydrostatic, hydrodynamic and debris impact loads associated with flooding up to the Defined Flood Event (DFE):
-  Creek/Waterway Flood Planning Areas - subcategories 1 and 2; or
- Brisbane River Flood Planning Areas - subcategories 1, 2a and 2b.

Notes: The relevant Flood Planning Areas are available from Brisbane City Council's Floodwise Property Report.

Design considerations and methodology are provided in the 'Construction of Buildings in Flood Hazard Areas' standard (Australian Building Codes Board).

Timing: Prior to obtaining building approval from a Private Building Certifier.

PROOF OF FULFILMENT
Certification from a Registered Professional Engineer Queensland (Structural) that the development has been designed and constructed in accordance with this condition. Timing: Prior to obtaining building approval from a Private Building Certifier.

 
As indicated
 
57)   Minimum Flood Planning Levels

Design and construct all building pad levels, floor levels and ancillary structures to the appropriate flood planning level with freeboard (where required) in accordance with the relevant Brisbane Planning Scheme Codes and the approved drawings and documents.

The minimum habitable floor level must be 4.70 metres AHD.

The minimum level for essential electrical services must be 4.70 metres AHD.

PROOF OF FULFILMENT
As-Constructed drawings prepared by a Registered Surveyor. The Registered Surveyor must certify that the development has been constructed in accordance with this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
58)   Basements in Flood Planning Areas

Design and construct all basements affected by flooding within the Brisbane River and Creek/Waterway Flood Planning Areas, including stormwater, electrical and sanitary facilities, in accordance with the following:
i) All ventilation openings, driveway entry/exit ramps and pedestrian entrances into the basement must be constructed to achieve the minimum flood planning levels identified in the relevant Brisbane Planning Scheme Codes to prevent the ingress of floodwaters into the basement
ii) The basement subsoil drainage and associated stormwater drainage/flow management must be designed by a Registered Professional Engineer Queensland (RPEQ) to manage the expected sub-surface flow rate resulting from flooding at the highest defined flood event and/or tidal waters (where applicable).
iii) Where any part of a basement is below 2m AHD or subject to saline groundwater conditions, a RPEQ must certify that the design of concrete structures is suitable to withstand the corrosive effects of saline water for the design life of the structure.
iv) All stormwater pump systems must have backflow prevention devices and designed with a discharge point that will gravity drain into a Council stormwater system, or other Lawful Point of Discharge.
v) All sewer connections must include backflow prevention devices.

Note: Basement means a space:
(a) between a floor level in a building and the floor level that is immediately below it; and
(b) no part of which is more than 1m above ground level.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
58(a) Submit Certification to Council

Submit to Council certification by a Registered Professional Engineer Queensland that the stormwater, subsoil drainage and sewer hydraulic design, specifications and drawings for the basement construction is in accordance with the requirements of this condition.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
58(b) Submit As Constructed Drawings to Council

Submit to development Services As Constructed drawings certified by a Registered Professional Engineer Queensland showing the surveyed basement entry levels, subsoil drainage details and pump design.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
59)   Essential Services within Basements

Where essential services are located within a basement or room located below the highest flood level affecting the site in an area affected by the Brisbane River Flood Planning areas or Creek/Waterway Flood Planning areas, the building is to be designed and constructed to provide either:

i) A completely watertight tanked basement with walls and floors designed by a Registered Professional Engineer Queensland (Structural) to resist hydrostatic pressures expected during a defined flood event,

OR

ii) A subsoil drainage system and pump system designed by a Registered Professional Engineer Queensland and constructed to prevent the basement from flooding and meet the following:
a) The pump system is to utilise a duty and standby pump system to manage the expected sub- surface flow rate resulting from flooding at the highest defined flood event and/or tidal waters (where applicable)
b) The pumps are connected to a backup power supply that is located above the highest defined flood level.
c) The backup power supply must be a battery, fuel or gas power source that will run the pumps for a 48h period, where the site is affected by the Brisbane River Flood Planning areas.

Notes:
Basement means a space:
(a) between a floor level in a building and the floor level that is immediately below it; and
(b) no part of which is more than 1m above ground level.

Essential electrical services include any area or room used for fire control panel, telephone PABX, sensitive substation equipment including transformers, low voltage switch gear, high voltage switch gear, battery chargers, protection control and communication equipment, low voltage cables, high voltage cables, and lift or pump controls.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
59(a) Certification to the Private Building Certifier

Provide to the Private Building Certifier, certification from a Registered Professional Engineer Queensland (Structural) that the basement has been designed and constructed to ensure structural integrity during a defined flood event.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
59(b) Certification to Council

Submit to Council certification by a Registered Professional Engineer Queensland that the stormwater, subsoil drainage, pump and backup power supply has been constructed in accordance with the requirements of this condition.

Note: This certification is required to be provided where a subsoil drainage and pump system has been provided in lieu of a tanked, watertight basement.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
60)   Refuse Collection - On Site

Provide for the installation and collection of refuse/recycling bins by Brisbane City Council's Waste and Resource Recovery Services or a private waste contractor.

 
At all times
60(a) Arrange Refuse Collection

Arrange for the installation of refuse/recycling bins and for the subsequent collection of refuse including recycling from the site by Brisbane City Council's Waste and Resource Recovery Services or a private waste contractor.

Timing: A minimum of four weeks prior to the commencement of use and then to be maintained. 

PROOF OF FULFILMENT
Where a private waste contractor is engaged, provide written confirmation from the proposed waste collection contractor of the agreement to service the property. The written agreement must be submitted to Council's Waste and Resource Recovery Services and include full details of the proposed system, bin sizes, number of bins, frequency of collection and the refuse collection vehicle size. Timing: Prior to commencement of use.

 
As indicated
60(b) Indemnify Council

The owner and any subsequent owner must, by approved form to Waste and Resource Recovery Services, indemnify Council and its agents in respect of any damage to the pavement and other driving surfaces.

Timing: When an arrangement for refuse/recycling collection services is made with Brisbane City Council.

 
As indicated
60(c) Notify Future Owner

Where Council is engaged as the waste contractor, the owner must notify any future owner/body corporate that the development has been approved on the basis that an indemnity must be provide for refuse collection vehicles to enter the property.

Timing:  At time of a change of ownership.

 
As indicated
 
61)   Refuse Storage - On Site Collection

Provide a roofed and wholly screened refuse enclosure utilising materials consistent with the development or a dedicated refuse storage room, as shown on the approved plans and documents. 

The enclosure/refuse storage room must be of a design to accommodate the quantity of refuse and recycling including source separation to allow for low servicing collection of the development.

Bins must be located in an area which allows them to be manoeuvred from the bin storage area to the designated internal collection point.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
62)   Future Road Widening

The development must not prejudice the future road reserve widening along the Wellington Road frontage. The development is to keep the area clear the future road reserve of improvements and structures other than where shown on the approved DRAWINGS AND DOCUMENTS.  The extent of the land to be set aside for a future road reserve widening is set out on the Road Widening Plan, RC 16089 Issue 1, forming part of the approved DRAWINGS AND DOCUMENTS.

 
At all times
 
63)   All Basements - Stormwater Runoff

Design and construct basements to manage stormwater runoff in accordance with the relevant Brisbane Planning Scheme Codes and the following:

(i) All stormwater pump systems must be designed to gravity drain to a Council stormwater system.

(ii) The driveway into a basement must be designed and constructed to minimise local driveway stormwater runoff entering the basement. The drainage must be designed to capture runoff from a 10% AEP rainfall event and gravity drain to a lawful point of discharge.

(iii) Vehicle access into any basement from a Council road will require the basement driveway to ramp up a minimum of 200mm, above adjacent road channel invert, to maintain road major flow capacity.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
64)   Site Drainage - Major

Provide an internal drainage system to collect stormwater run-off from all proposed lots, roofed and developed surface areas and any run-off onto the site from adjacent areas and convey the collected run- off to a lawful point of discharge, in accordance with the relevant Brisbane Planning Scheme Codes.

Notes:
-  The stormwater design must ensure the stormwater runoff from the site does not adversely impact on flooding or drainage (peak discharge and duration for all storm events up to the 1% AEP event) of properties that are upstream, downstream or adjacent to the site.  Where a development has not specifically addressed this issue, the development may require implementation of one or more mitigation measures to offset adverse impacts, (e.g. stormwater detention, rainwater tanks, and upgrade of stormwater drainage infrastructure).
   i)  Guidance for the preparation of drawings and/or documents to comply with this condition is provided in the Brisbane Planning Scheme Policies.

-  Where external works are required and infrastructure will be handed over to Council (e.g. Stormwater pipes 375mm or greater and/or manholes within the road reserve, etc), the applicant will be required to request an on-site Pre-Start with Council and ensure all future owned Council assets follow the On/Off Maintenance process in accordance with Councils Infrastructure Installation & Construction Requirements Manual.
   i)  Guidance for requesting a pre-start and co- ordinating the On/Off Maintenance process can be found on Council's website (https://www.brisbane.qld.gov.au/planning-and-building/applying-and-post- approval/on-and-off-maintenance-approvals).

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
64(a) Submit Site Drainage Drawings

Submit to, and obtain approval from, Development Services, site drainage drawings and engineering calculations, prepared and certified by a Registered Professional Engineer Queensland, in accordance with the relevant Brisbane Planning Scheme Codes.

Notes:

-   Queensland Building and Construction Commission licensed hydraulic consultants may design the stormwater system for sites less than 2000m2 with an upstream catchment servicing no more than 4 residential lots.  This excludes stormwater drainage design (including subsoil drainage) of basements in flood planning areas and the design of any onsite stormwater detention system
-  Guidance for the preparation of drawings and/or documents to comply with this condition is provided in the Brisbane Planning Scheme Policies.

Timing: Prior to site/operational/building work commencing

 
As indicated
64(b) Implement Approved Drawings

Carry out the works in accordance with the approved site drainage drawings.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
64(c) Submit As Constructed Drawings

Submit to Development Services As Constructed drawings prepared and certified by a Registered Professional Engineer Queensland or a Queensland Building and Construction Commission licensed hydraulic consultants (where applicable).

Note: To be submitted via DA- ComplianceEngineering@brisbane.qld.gov.au and include the site address, A00 reference and Condition number in the subject line.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. 

PROOF OF FULFILMENT
Certification from a Registered Professional Engineer Queensland or Queensland Building or Construction Commission licensed hydraulic consultants (where applicable) confirming that the works have been completed in accordance with the above stormwater drawings. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
65)   Ponding of Stormwater

Carry out the approved development to ensure that adjoining properties and roads are protected from ponding or nuisance from stormwater during construction.

Notes: If remedial works are necessary to comply with this condition, prior approval must be obtained from Development Services.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
66)   Sealing of Abandoned Existing Sewer Property Connection

Permanently seal the existing sewer property connection, which will be built over or not reused to serve the proposed development.

Note: Connection permanently abandoned to the satisfaction of the Manager, Plumbing Services or the Delegate, Development Services.

 
Prior to site/operational/building work commencing
 
67)   Service Conduits and Mains

Provide and install all service conduits and meet the cost of any alterations to public utility mains, existing mains, services, street lighting or installations that are required to carry out the approved development. These works must be in accordance with the relevant Brisbane Planning Scheme Codes, and include the following, where applicable:
-  the provision of all services and/or conduits along the full length of any rear allotment access or access easement.
-  the breaking and/or relocation of any existing sewer combine drains.
-  the relocation of any fire hydrant and/or valves from the development's vehicular footway crossings.
-  the retention and/or relocation of any existing foul water lines that currently exist within the site.
-  any new or existing installations of electrical pillar boxes, pad mounted transformers (PMTs), water reticulation mains, water meters and the like, must be installed/relocated to their ultimate alignment relative to the new property boundary and clear of the usable footpath areas irrespective of the alignment of the existing services/conduits.

Note:
-  The cost of moving services, utilities and assets is the responsibility of the Developer. The permission of the service, utility or asset owner will be required. Council permission is required if street trees, stormwater gullies/drains, and swales are affected. Urban Utilities permission is required if water supply and sewerage services are affected.
-  Standard utility alignments may be found on Council's 'Brisbane Standard Drawings' 1013 to 1016 inclusive.
-  Applicants must liaise with the appropriate service authorities. Typical underground services and/or conduits to be constructed include power, phone, telecommunications, sewer (including private combine drains) stormwater and gas, if applicable.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
67(a) Submit As Constructed Drawings

Submit to Development Services As Constructed drawings, including an asset register, prepared and certified by a Registered Professional Engineer Queensland.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

PROOF OF FULFILMENT
Certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the requirements of this condition. Note: Civil works are to be certified by a RPEQ(Civil) and electrical works are to be certified by a RPEQ (Electrical).

 
As indicated
 
68)   Telecommunications

Submit to Development Services, certification from an authorised telecommunications carrier/contractor, that the following works and infrastructure have been undertaken and installed in accordance with telecommunications industry standards:
- Provide telecommunications to the subject buildings, lead-in conduits and equipment space in a suitable location within the buildings, to suit the carrier of choice.
- If new pits and conduit infrastructure are required to be installed within the road reserve fronting the site, it must be suitably sized to cater for future installation of fibre optic cables.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
69)   Agreement with Electricity Supplier

Submit to Development Services, evidence of an agreement with an electricity supplier to provide necessary services to the development in accordance with the relevant Brisbane Planning Scheme Codes.

Where development is within an established area of overhead electricity supply and the electricity supplier determines that a property pole is the appropriate solution to supply electricity to the development, the developer must be responsible for the installation of the property pole(s).

In the above circumstances, submit to Development Services, certification from the developer's electrical consultant confirming that the above installation has been completed in accordance with the relevant AS/NZS Standards and the Queensland Electricity Connection Manual (QECM) and Queensland Electricity Metering Manual (QEMM).

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
70)   Water and Wastewater

Pursuant to Schedule 18 of the Planning Regulation 2017 submit to Development Services, documentary evidence, issued by the relevant distributor-retailer, to verify that the conditions of any necessary connection certificate under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009, have been complied with.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
71)   Permanent Driveway Crossover

Provide a 6.50 metre wide modified Type B2 permanent driveway crossover to the Nile Street frontage of the site in accordance with the relevant Brisbane Planning Scheme Codes and located as shown on the approved DRAWINGS AND DOCUMENTS

 

Written consent must be obtained from BCC - Field Services, Program Planning and Integration Arborist prior to any works occurring that will either impact on or require removal of a street tree (this includes pruning and excavation within the root zone/canopy of the tree)

At all times during construction of the crossover, safe pedestrian access along the site frontage must be maintained.

Note: No further driveway permit is required however additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
72)   Redundant Driveway Crossover

Remove the redundant existing driveway crossover(s) on the frontage(s) of the site and reinstate the kerb and channel, road pavement, footways and footpaths in accordance with the relevant Brisbane Planning Scheme Codes.

Note: Additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
Standard Advice
 
Timing
73)   Construction Noise and Dust Emissions

Pursuant to the Environmental Protection Act 1994, all development involving the emission of noise and dust from building and/or construction activities, must ensure that the emissions are in accordance with the requirements of the Act.
The Environmental Protection Act 1994 prescribes that:

1. A person must not carry out building work in a way that makes an audible noise-
-  on a business day or Saturday, before 6.30a.m. or after 6.30p.m; or
-   on any other day, at any time. 
2. The reference in subsection (1) to a person carrying out building work-
-  includes a person carrying out building work under an owner-builder permit; and
-  otherwise does not include a person carrying out building work at premises used by the person only for residential purposes.

Note: A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management delegate Development Services.

 
As indicated
 
74)   Management of Asbestos

Disposal, handling and restoration of any building materials containing asbestos must be in accordance with current state and federal legislation.

 
As indicated
 
75)   Entertainment Venues & Events

Any place open to the public for entertainment is required to have an entertainment venue permit under Council's Local Law (Entertainment Venues & Events) 1999. For further information, please contact Council's Business Hotline on 133 BNE.

 
As indicated
 
76)   Further Development Permit Required

Further Development Permit(s) to carry out assessable building work under the Building Act may be required.

 
As indicated
 
77)   Plumbing and Drainage Work

Pursuant to the Plumbing and Drainage Act 2018, any plumbing and drainage work must be carried out in compliance with the Plumbing and Drainage Regulation 2019. Plumbing and drainage permit work requires approval by Brisbane City Council prior to the work being carried out.

 
As indicated
 
78)   Currency Period

The currency period for this development approval is stated in the Decision Notice and is expressed as a date.

This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016.

 
As indicated
 
79)   Referral Agency Requirements

SARA as CONCURRENCE agency has no requirements as stated in the letters dated 12 October 2023 (ref: 2309-36612 SRA) and 30 October 2024 (ref: 2409-42595 SRA).

 
As indicated
 
80)   Cultural Heritage

Aboriginal cultural heritage is protected under the Aboriginal Cultural Heritage Act 2003.  This Act establishes a cultural heritage duty of care and in section 23(1) mandates that a person who carries out an activity must take all reasonable and practicable measures for ensuring activities are managed to avoid or minimise harm to Aboriginal cultural heritage.

The Duty of Care Guidelines gazetted pursuant to the Aboriginal Cultural Heritage Act 2003 provide guidance on identifying and protecting Aboriginal cultural heritage to fulfil the duty of care.

For further information contact the relevant Queensland State Government Department (Department of Aboriginal and Torres Strait Islander Partnerships).

 
As indicated
 
81)   Equitable Access

Provision must be made during and after construction for equitable access for persons with disabilities to and within the site and on adjoining public areas, in accordance with the following:
- Queensland Anti-Discrimination Act 1991;
- Federal Disability Discrimination Act 1992;
- Australian Standards AS1428 Parts 1-4;
- Australian Standard for Access and Mobility; and
- National Construction Code.

 
As indicated
 
82)   Eligibility for on-street residential parking permits in Brisbane

Occupiers of the approved development will not be eligible for on-street residential or visitor parking permits.

 
As indicated
 
83)   Damage to Trees on Adjoining Land

Please note that any damage caused to vegetation on adjoining land as a result of exercising this development approval may result in an offence under other legislation (e.g. Natural Assets Local Law) and/or civil action

 
As indicated
 
84)   Fire Ant Movement Controls

To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected.

These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products.

Breaches of these controls can potentially impact the community, economy and the environment.  Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014.

For further information contact the relevant Queensland State Government department on 13 QGOV.

 
As indicated
 
85)   Water and Wastewater

Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council.  Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009.

For further information about any necessary Water Approvals contact Urban Utilities.

 
As indicated
 
86)   Seqwater

Council does not undertake assessment of Seqwater Bulk Water Supply Infrastructure in any planning application. Please contact Seqwater where development is located within 20 metres of Seqwater infrastructure on (07) 3035 5677 or consents@seqwater.com.au. Seqwater Trunk Water Mains convey bulk supply and operate at extremely high pressures. Seqwater seeks to eliminate risks to the community and to site personnel with works in the vicinity of Seqwater infrastructure.

 
As indicated
 
87)   Flood Resilience and Awareness

This advice is provided for buildings that are on sites that are subject to the flood overlay, as shown within City Plan 2014.

 

Council makes decisions to minimise flood risk based on the best information available at the time of the development application.  Flood studies and applicable flood levels may be updated by Council overtime where new flood information is available or changes to engineering standards/methodology have occurred.  Flood levels for various flood events and flooding types are outlined in Councils Floodwise Property Reports available from Councils website.

 

The minimum flood planning levels that apply to new development do not necessarily mean that the development will never flood.  Therefore, when choosing materials for building on sites that are known to be affected by flooding, regardless of whether it is constructed to the minimum flood planning level, it is recommended that flood resilient materials are used to improve the speed of recovery and reduce the cost of repairs if required. 

 

For more information refer to:

Council's website at https://www.brisbane.qld.gov.au/community-and-safety/community- safety/disasters-and-emergencies/be-prepared/flooding-in-brisbane/flooding- support-for-residents/flood-resilient-homes-program

Queensland Reconstruction Authority "Flood Resilient Building Guidance for Queensland Homes"https://www.qra.qld.gov.au/resilient- homes/flood-resilient-building-guidance-queensland-homes

 
As indicated
 
88)   Cultural Heritage

Aboriginal cultural heritage is protected under the Aboriginal Cultural Heritage Act 2003. This Act establishes a cultural heritage duty of care and in section 23(1) mandates that a person who carries out an activity must take all reasonable and practicable measures for ensuring activities are managed to avoid or minimise harm to Aboriginal cultural heritage.

 

The Duty of Care Guidelines gazetted pursuant to the Aboriginal Cultural Heritage Act 2003 provide guidance on identifying and protecting Aboriginal cultural heritage to fulfil the duty of care.

 

For further information contact the relevant Queensland State Government Department (Department of Aboriginal and Torres Strait Islander Partnerships).

 
As indicated
 
89)   Alcohol Consumption

If the service of alcohol is proposed, a separate approval for an appropriate liquor licence should be obtained from the relevant authority. Liquor licenses are issued by the Queensland Government.

 
At all times
 



Permit to Which These Conditions Relate: DA - PA - Building Work
Activity(ies): multiple dwelling
shop
office
food and drink outlet
educational establishment
Stage:  

General/Planning Requirements
 
Timing
90)   Maintain the Approved Development

Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions.

 
At all times
 
91)   Approved Drawings and Documents

A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers.

Note: This condition is imposed to ensure compliance with the conditions of development approval.

 
While site/operational/building work is occurring
 
92)   Carry Out the Approved Development

Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS.

Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks).  Permission to enter neighbouring properties must be obtained from the relevant property owners.

 
While site/operational/building work is occurring
 
93)   Complete All Building Work

Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS.

Note: Building work must also be completed in accordance with any other current development approval.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
Standard Advice
 
Timing
94)   Construction Noise and Dust Emissions

Pursuant to the Environmental Protection Act 1994, all development involving the emission of noise and dust from building and/or construction activities, must ensure that the emissions are in accordance with the requirements of the Act.
The Environmental Protection Act 1994 prescribes that:

1. A person must not carry out building work in a way that makes an audible noise-
-  on a business day or Saturday, before 6.30a.m. or after 6.30p.m; or
-   on any other day, at any time. 
2. The reference in subsection (1) to a person carrying out building work-
-  includes a person carrying out building work under an owner-builder permit; and
-  otherwise does not include a person carrying out building work at premises used by the person only for residential purposes.

Note: A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management delegate Development Services.

 
As indicated
 
95)   Management of Asbestos

Disposal, handling and restoration of any building materials containing asbestos must be in accordance with current state and federal legislation.

 
As indicated
 
96)   Further Development Permit Required

Further Development Permit(s) to carry out assessable building work under the Building Act may be required.

 
As indicated
 
97)   Plumbing and Drainage Work

Pursuant to the Plumbing and Drainage Act 2018, any plumbing and drainage work must be carried out in compliance with the Plumbing and Drainage Regulation 2019. Plumbing and drainage permit work requires approval by Brisbane City Council prior to the work being carried out.

 
As indicated
 
98)   Currency Period

The currency period for this development approval is stated in the Decision Notice and is expressed as a date.

This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016.

 
As indicated
 
99)   Referral Agency Requirements

SARA as CONCURRENCE agency has no requirements as stated in the letter dated 7 June 2022 (ref: 2204-28274 SRA).

 
As indicated
 
100)   Cultural Heritage

Aboriginal cultural heritage is protected under the Aboriginal Cultural Heritage Act 2003.  This Act establishes a cultural heritage duty of care and in section 23(1) mandates that a person who carries out an activity must take all reasonable and practicable measures for ensuring activities are managed to avoid or minimise harm to Aboriginal cultural heritage.

The Duty of Care Guidelines gazetted pursuant to the Aboriginal Cultural Heritage Act 2003 provide guidance on identifying and protecting Aboriginal cultural heritage to fulfil the duty of care.

For further information contact the relevant Queensland State Government Department (Department of Aboriginal and Torres Strait Islander Partnerships).

 
As indicated
 
101)   Equitable Access

Provision must be made during and after construction for equitable access for persons with disabilities to and within the site and on adjoining public areas, in accordance with the following:
- Queensland Anti-Discrimination Act 1991;
- Federal Disability Discrimination Act 1992;
- Australian Standards AS1428 Parts 1-4;
- Australian Standard for Access and Mobility; and
- National Construction Code.

 
As indicated
 
102)   Damage to Trees on Adjoining Land

Please note that any damage caused to vegetation on adjoining land as a result of exercising this development approval may result in an offence under other legislation (e.g. Natural Assets Local Law) and/or civil action

 
As indicated
 
103)   Fire Ant Movement Controls

To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected.

These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products.

Breaches of these controls can potentially impact the community, economy and the environment.  Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014.

For further information contact the relevant Queensland State Government department on 13 QGOV.

 
As indicated
 
104)   Water and Wastewater

Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council.  Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009.

For further information about any necessary Water Approvals contact Urban Utilities.

 
As indicated
 
105)   Seqwater

Council does not undertake assessment of Seqwater Bulk Water Supply Infrastructure in any planning application. Please contact Seqwater where development is located within 20 metres of Seqwater infrastructure on (07) 3035 5677 or consents@seqwater.com.au. Seqwater Trunk Water Mains convey bulk supply and operate at extremely high pressures. Seqwater seeks to eliminate risks to the community and to site personnel with works in the vicinity of Seqwater infrastructure.

 
As indicated
 
106)   Flood Resilience and Awareness

This advice is provided for buildings that are on sites that are subject to the flood overlay, as shown within City Plan 2014.

 

Council makes decisions to minimise flood risk based on the best information available at the time of the development application.  Flood studies and applicable flood levels may be updated by Council overtime where new flood information is available or changes to engineering standards/methodology have occurred.  Flood levels for various flood events and flooding types are outlined in Councils Floodwise Property Reports available from Councils website.

 

The minimum flood planning levels that apply to new development do not necessarily mean that the development will never flood.  Therefore, when choosing materials for building on sites that are known to be affected by flooding, regardless of whether it is constructed to the minimum flood planning level, it is recommended that flood resilient materials are used to improve the speed of recovery and reduce the cost of repairs if required. 

 

For more information refer to:

Council's website at https://www.brisbane.qld.gov.au/community-and-safety/community- safety/disasters-and-emergencies/be-prepared/flooding-in-brisbane/flooding- support-for-residents/flood-resilient-homes-program

Queensland Reconstruction Authority "Flood Resilient Building Guidance for Queensland Homes"https://www.qra.qld.gov.au/resilient- homes/flood-resilient-building-guidance-queensland-homes

 
As indicated
 
107)   Alcohol Consumption

If the service of alcohol is proposed, a separate approval for an appropriate liquor licence should be obtained from the relevant authority. Liquor licenses are issued by the Queensland Government.

 
At all times
 

** End of Package **