BRISBANE CITY COUNCIL'S APPROVAL PACKAGE.



APPLICATION DETAILS

This package relates to the application detailed below
Address of Site: 14 IVANKA ST BRACKEN RIDGE QLD 4017
Real Property Description of Site: L3 SP.348738
Aspects of development and type of approval: DA - PA - Material Change of Use Development Permit - community residence
Council File Reference: A006968046
Permit Reference Number/s: DAMC473804926.
Package Status: APPROVED - Version 1 (18th of June, 2026 9:10:55 AM)
Package Generated: 18/06/2026


PROJECT TEAM

The assessment of this application has been undertaken by:
Mohammed ASLAM
Urban Planner
Planning Services North
mohammed.aslam@brisbane.qld.gov.au
(07) 34037240
Christine GRAY
Principal Urban Planner
Planning Services North
christine.gray@brisbane.qld.gov.au
3407 0160
Joe MCSHANE
Principal Urban Planner
Planning Services North
CPAS-DS-PS-North@brisbane.qld.gov.au
(07) 3407 1306
Dominic PERRY
Senior Engineer
Engineering Scoping
dominic.perry@brisbane.qld.gov.au
(07) 3403 8888
Thomas JONKER
Landscape Architect
Landscape Architecture Team
Thomas.Jonker@brisbane.qld.gov.au
31780712


DRAWINGS AND DOCUMENTS



The term 'drawings and documents' or similar expressions mean:
Drawing or Document Number Plan Date
Site Plan 003FBR Sheet Number 2.101 Revision 2.11 (Amended In Red 10-JUN-2026) 22-FEB-2026 (Received)
Floor Plan 003FBR Sheet Number 2.201 Revision 2.10 (Amended In Red 10-JUN-2026) 22-FEB-2026 (Received)
Elevations 1 003FBR Sheet Number 2.301 Revision 2.10 (Amended In Red 10-JUN-2026) 22-FEB-2026 (Received)
Elevations 2 003FBR Sheet Number 2.302 Revision 2.10 (Amended In Red 10-JUN-2026) 22-FEB-2026 (Received)
Roof Plan 003FBR Sheet Number 2.1301 Revision 2.10 (Amended In Red 10-JUN-2026) 22-FEB-2026 (Received)
Landscaping Plan 003FBR Sheet Number 2.1601 Revision 2.10 (Amended In Red 10-JUN-2026) 22-FEB-2026 (Received)
Hard Landscaping Plan 003FBR Sheet Number 2.1701 Revision 2.11 (Amended In Red 10-JUN-2026) 22-FEB-2026 (Received)


Advice

Please see the attached document(s) for any advices.

APPROVAL CONDITIONS



Permit to Which These Conditions Relate: DA - PA - Material Change of Use
Activity(ies): community residence
Stage:  

General/Planning Requirements
 
Timing
1)   Maintain the Approved Development

Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions.

 
At all times
 
2)   Approved Drawings and Documents

A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers.

Note: This condition is imposed to ensure compliance with the conditions of development approval.

 
While site/operational/building work is occurring
 
3)   Carry Out the Approved Development

Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS.

Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners.

 
While site/operational/building work is occurring
 
4)   Complete All Building Work

Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS.

Note: Building work must also be completed in accordance with any other current development approval.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
Landscape Architecture and Open Space Planning
 
Timing
5)   Landscape the Site - Self Certification

Landscape the site in accordance with the requirements of this condition.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
5(a) Detailed Landscape Plan for Self- Certification

Prepare a Detailed Landscape Plan at a scale of 1:100 for all on-site landscape works including planting areas identified on the approved DRAWINGS AND DOCUMENTS. The plan must be prepared by a Qualified Landscape Architect and must comply with the relevant Brisbane Planning Scheme Codes.

The plan must include the following:
- Planting media and mulch in accordance with AS4454 Composts, soil conditioners and mulches and AS 4419-2003 Soils for landscaping and garden use.
- Unless otherwise specified, trees provided as 45 litre stock or larger, staked and tied, and complying with Australian Standards.
- Plant selection and densities to achieve full surface coverage of garden beds within 2 years of planting.
- Details of a 12 week establishment period.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

PROOF OF FULFILMENT
A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
5(b) Certify Work

On completion of the landscape work, submit a Landscape Works Certification via the Landscape Design and Landscape Works Certification online form. The landscape works certification is to be prepared by a Qualified Landscape Architect, certifying that the landscape works comply with the certified Detailed Landscape Plan. The certification must include:


- a copy of the Landscape works certification form.

- a copy of the as-constructed landscape drawings.

- Photos of installed landscaping.


- Confirmation in writing from the landscape contractor who completed the works, that the works were completed in accordance with best practice landscape construction and horticultural standards.

NOTE: The landscape design and landscape works certification online form can be found by searching development application forms on Council's website.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

PROOF OF FULFILMENT
A copy of the Landscape works certification form, a copy of the as-constructed landscape drawings, photos of installed landscaping, confirmation in writing from the landscape contractor who completed the works, that the works were completed in accordance with best practice landscape construction and horticultural standards.

 
As indicated
5(c) Maintain Landscape Work

Maintain the landscape work, including deep planting, in accordance with the certified Detailed Landscape Plan.

Timing: To be maintained.

 
As indicated
 
Pollution
 
Timing
6)   Acoustic Fence - General

Erect a 2m high acoustic fence, (relative to the finished RL of the building pad) along part of the western boundary and along part of the northern boundary as shown on the approved plans. The acoustic fence must:
- Be constructed of a material with a minimum surface area density of 12.5kg/m2;
- Be constructed of an aesthetically pleasing weather-resistant material such as fibre cement, painted or treated timber, brick, concrete or a combination thereof;
- Be continuous and gap free.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
6(a) Certification

Submit to Development Services certification from a person who is a Member or eligible to be a Member of the Australian Acoustic Society that the constructed acoustic fence complies with the above requirements.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
Engineering
 
Timing
7)   On-site Erosion (Low Risk)

Manage on-site erosion and the release of sediment or sediment laden water from the site at all times by implementing best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version). Including but not limited to:
(i) Drainage control measures must be implemented and maintained to minimise water flow across areas of exposed earth.
(ii) Sediment and erosion control measures must be implemented and maintained to prevent soil loss from earth disturbance areas and prevent deposition beyond earth disturbance areas.
(iii) No release of contaminants to land beyond on-site area of earth disturbance.

Note: Guidelines and factsheets to assist with this are available from the 'Healthy Waterways - Water by Design' website at http://hlw.org.au/initiatives/esc/house-sites

Timing: Prior to commencement of any earth disturbing activities and until all exposed soil areas are permanently stabilised against erosion.

 
As indicated
7(a) Provide Land Occupier Notification to Council

(i) Notify Council's ESC Team of proposed land occupier/s by sending an email to CARS-ESC@Brisbane.qld.gov.au

(ii) If the land is to be occupied by any person other than the registered landowner then advice must be provided to Council that confirms the name, contact information and the duration of any proposed occupation of the land.

Note: Occupier is any principal contractor occupying the land exercising a right under the development approval.

Timing: Prior to commencement of any earth disturbing activities.

 
As indicated
 
8)   Protect Existing Infrastructure

Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure.

Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations.

The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements.

 
While site/operational/building work is occurring
8(a) As Constructed Drawings - Alterations to Existing Infrastructure

Submit to Development Services As Constructed drawings showing all new and/or rectification works and an asset register, prepared by a Registered Professional Engineer Queensland.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

PROOF OF FULFILMENT
Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
9)   Repair Damage to Kerb, Footpath or Road

Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
9(a) Interim Repairs

If at any time during the construction phase of the approved development, damage to the existing kerb and channel, footpath or roadway creates unsafe, unreasonable and/or not fit for purpose conditions as assessed by Council, interim repairs must be undertaken as directed by Program Planning and Integration.

Note: Any interim repairs required to be undertaken shall not be considered to satisfy the requirements of this condition for the permanent repair of the infrastructure prior to the issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

Timing: While site / operational / building works is occurring.

 
As indicated
 
10)   Redundant Driveway Crossover

Remove the redundant existing driveway crossover(s) on the frontage(s) of the site and reinstate the kerb and channel, road pavement, footways and footpaths in accordance with the relevant Brisbane Planning Scheme Codes.

Note:
For kerb and channel reinstatement, the existing channel is required to be removed and the kerb and channel reinstated in one pour.

Additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
11)   Permanent Driveway Crossover

Provide a 3.0 metre wide Single Dwelling Type permanent driveway crossover to the Ivanka Street frontage of the site in accordance with the relevant Brisbane Planning Scheme Codes and located as shown on the approved DRAWINGS AND DOCUMENTS.

Written consent must be obtained from Program, Planning and Integration Arboriculture (PPI Arb) prior to any works occurring that will either impact on or require removal of a street tree (this includes pruning, excavation or fill within the root zone/canopy of the tree)

At all times during construction of the crossover, safe pedestrian access along the site frontage must be maintained.

Note: No further driveway permit is required however additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
Standard Advice
 
Timing
12)   Construction Noise and Dust Emissions

Pursuant to the Environmental Protection Act 1994, all development involving the emission of noise and dust from building and/or construction activities, must ensure that the emissions are in accordance with the requirements of the Act.
The Environmental Protection Act 1994 prescribes that:

1. A person must not carry out building work in a way that makes an audible noise-
-  on a business day or Saturday, before 6.30a.m. or after 6.30p.m; or
-   on any other day, at any time. 
2. The reference in subsection (1) to a person carrying out building work-
-  includes a person carrying out building work under an owner-builder permit; and
-  otherwise does not include a person carrying out building work at premises used by the person only for residential purposes.

Note: A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management delegate Development Services.

 
As indicated
 
13)   Further Development Permit Required

Further Development Permit(s) to carry out assessable building work under the Building Act may be required.

 
As indicated
 
14)   Plumbing and Drainage Work

Pursuant to the Plumbing and Drainage Act 2018, any plumbing and drainage work must be carried out in compliance with the Plumbing and Drainage Regulation 2019.

Note: All new and existing plumbing services should be located within the lot that they serve.

Compliance assessable plumbing and drainage work requires approval by Brisbane City Council prior to the work being carried out.

 
As indicated
 
15)   Currency Period

The currency period for this development approval is stated in the Decision Notice and is expressed as a date.

This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016.

 
As indicated
 
16)   Equitable Access

Provision must be made during and after construction for equitable access for persons with disabilities to and within the site and on adjoining public areas, in accordance with the following:
- Queensland Anti-Discrimination Act 1991;
- Federal Disability Discrimination Act 1992;
- Australian Standards AS1428 Parts 1-4;
- Australian Standard for Access and Mobility; and
- National Construction Code.

 
As indicated
 
17)   Damage to Trees on Adjoining Land

Please note that any damage caused to vegetation on adjoining land as a result of exercising this development approval may result in an offence under other legislation (e.g. Natural Assets Local Law) and/or civil action

 
As indicated
 
18)   Fire Ant Movement Controls

To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected.

These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products.

Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014.

For further information contact the relevant Queensland State Government department on 13 QGOV.

 
As indicated
 
19)   Water and Wastewater

Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009.

For further information about any necessary Water Approvals contact Urban Utilities.

 
As indicated
 
20)   Cultural Heritage

Aboriginal cultural heritage is protected under the Aboriginal Cultural Heritage Act 2003. This Act establishes a cultural heritage duty of care and in section 23(1) mandates that a person who carries out an activity must take all reasonable and practicable measures for ensuring activities are managed to avoid or minimise harm to Aboriginal cultural heritage.

 

The Duty of Care Guidelines gazetted pursuant to the Aboriginal Cultural Heritage Act 2003 provide guidance on identifying and protecting Aboriginal cultural heritage to fulfil the duty of care.

 

For further information contact the relevant Queensland State Government Department (Department of Aboriginal and Torres Strait Islander Partnerships).

 
As indicated
 

** End of Package **