| Address of Site: | 77 MINIMINE ST STAFFORD QLD 4053 |
| Real Property Description of Site: | L78 RP.74875 |
| Aspects of development and type of approval: | DA - PA - Reconfiguring a Lot Development Permit - Subdivision of Land |
| Council File Reference: | A006957882 Permit Reference Number/s: DARL473215726. |
| Package Status: | APPROVED - Version 1 (24th of June, 2026 4:52:39 PM) |
| Package Generated: | 24/06/2026 |
| James LANGSTON Principal Engineer Engineering Services Hydraulics james.langston@brisbane.qld.gov.au 34034918 |
Tim WRAFTER Principal Engineer Engineering Services Hydraulics Tim.Wrafter@brisbane.qld.gov.au |
Richard WELCH Senior Engineer Engineering Scoping Richard.Welch@brisbane.qld.gov.au 34070603 |
| Lani ROBERTS Landscape Architect Landscape Architecture Team Lani.Roberts@brisbane.qld.gov.au 07 3403 8888 |
Luke HADRICK Urban Planner Planning Services North Luke.Hadrick@brisbane.qld.gov.au (07) 3178 9403 |
Rhea CONNOLLY Principal Urban Planner Planning Services North Rhea.Connolly@brisbane.qld.gov.au 3178 0651 |
DRAWINGS AND DOCUMENTS
| Drawing or Document | Number | Plan Date |
|---|---|---|
| Site Plan Proposed Subdivision Plan | 100-01 Issue F (Amended In Red 18-JUN-2026) | 05-JUN-2026 (Received) |
| Preliminary Services Plan | S25-243-P01 (Amended In Red 18-JUN-2026) | 05-JUN-2026 (Received) |
APPROVAL CONDITIONS
| Permit to Which These Conditions Relate: | DA - PA - Reconfiguring a Lot |
| Activity(ies): | Subdivision of Land |
| Stage: | Reconfiguration of a Lot (1 into 2) |
| 1) Maintain the Approved Development Maintain the approved development generally
in accordance with the approved DRAWINGS AND DOCUMENTS, and any
other relevant
Council approval required by the conditions. |
At all times |
| 2) Carry Out the Approved Development Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS. Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners. |
While site/operational/building work is occurring |
| 3) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers. Note: This condition is imposed to ensure compliance with the conditions of development approval. |
While site/operational/building work is occurring |
| 4) Demolish or Relocate Buildings/Structures Demolish buildings/structures on the site in accordance with the approved DRAWINGS AND DOCUMENTS and where applicable, the approved Construction Management Plan. The removal of buildings/structures includes the removal of all existing concrete slabs, foundations and footings. |
Prior to Council's notation on the plan of subdivision |
| 5) Complete All Operational Work Complete all operational work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such operational work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS or, if requiring a further approval from the Council, in accordance with the relevant further approval(s). |
Prior to Council's notation on the plan of subdivision and then to be maintained |
| 6) Retain and Protect Existing Street Tree(s) Identify, retain and protect the
existing street trees including the roots unless otherwise agreed in writing
with Public Space Operations (PSO Arb-PLANNING). Note:
Street trees are protected under the Natural Assets Local Law. Street trees
must not be removed or pruned without prior approval from PSO Arb-
PLANNING. Where driveway crossovers occur within the Tree
Protection Zone (TPZ) of existing street trees, seek approval from PSO Arb
PLANNING for the final driveway crossover design and construction methodology
to ensure the successful retention of the existing street
trees. Note: Should ultimate
access to Lot 2 be installed as indicatively illustrated on the approved plans,
then in-principle support for the removal of Street
Tree 1 and Street Tree 2 is supported. However, removal of these trees is not
supported until access is required. This will require a separate driveway
permit. PROOF OF FULFILMENT Contextual photographic evidence that trees have been retained in equal or greater health than before development commenced. OR, evidence in writing from PSO Arb PLANNING that an alternative arrangement has been made. |
At all times |
6(a) Implement Protection
Measures Install tree protection measures in accordance with Australian Standard - AS4970 Protection of Trees on Development Sites. There must be no excavation, filling or storage of materials or plant within the drip line of the tree(s). Where works are within the canopy drip line of existing street trees, contact PSO Arb PLANNING in relation to the required provision of protection measures. Note: If fencing is to protect street trees, a permit to temporarily occupy the footway will be required from Compliance and Regulatory Services. Timing: Prior to site/operational work occurring. |
As indicated |
6(b) Maintain Protection
Measures Maintain protection measures while development is occurring and remove protection measures prior to commencement of the use. Timing: While to site/operational work is occurring. PROOF OF FULFILMENT Contextual photographic evidence to demonstrate the installation of protection measures prior to building works commencing. |
As indicated |
| 7) Grant Easements Grant the following easements as
may be required: Note: These easements include the provision for Council to obtain access. Timing: As part of the plan of subdivision notated by Council, and then to be maintained. |
As indicated |
7(a) Submit Plan of Subdivision and
Documentation (Council Easement in Gross) Submit to, and obtain approval from, Development Services a plan of subdivision showing the easement and a request for Council to prepare the necessary easement documentation to demonstrate compliance with the requirements of this condition. Note: Easements in favour of the Brisbane City Council must have the necessary easement documentation prepared by the Brisbane City Council, free of cost to Council. Timing: Prior to submission of the request pursuant to Schedule 18 of the Planning Regulation 2017 for Council's notation on the plan of subdivision necessary to comply with this condition or give effect to this approval. |
As indicated |
7(b) Submit Plan of Subdivision and
Documentation (other Easement) Submit to, and obtain approval from, Development Services, a plan of subdivision showing the easement and the necessary easement documentation to demonstrate compliance with the requirements of this condition. Note: Easements not in favour of the Brisbane City Council must have the necessary documentation prepared by the applicant's private solicitors. Timing: As part of the submission of the request pursuant to Schedule 18 of the Planning Regulation 2017 for Council's notation on the plan of subdivision necessary to comply with this condition or give effect to this approval. |
As indicated |
7(c) Lodge Notated Plan and
Documentation Lodge the plan of subdivision notated by Council pursuant to Schedule 18 of the Planning Regulation 2017 and the necessary easement documentation with the Registrar of Titles for the relevant Queensland State Government Authority. Timing: As part of the registration of the plan of subdivision notated by Council. PROOF OF FULFILMENT Evidence of the registration of the necessary easement documentation. Timing: Within one month of the registration of the easement documentation. |
As indicated |
| 8) On-site Erosion (low risk) Manage on-site erosion and the release of sediment or sediment laden water from the site at all times by implementing best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version). Including but not limited to: (i) Drainage control measures must be implemented
and maintained to minimise water flow across areas of exposed earth. Note: Guidelines and factsheets to assist with this are available from the 'Healthy Waterways - Water by Design' website at http://hlw.org.au/initiatives/esc/house-sites. Timing: Prior to commencement of any earth disturbing activities and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
8(a) Provide Land Occupier Notification to
Council (i) Notify Council's ESC Team of proposed land occupier/s by sending an
email to CARS-ESC@Brisbane.qld.gov.au. Note: Occupier is any principal contractor occupying the land exercising a right under the development approval. Timing: Prior to commencement of any earth disturbing activities. |
As indicated |
| 9) Information Signage Erect an information sign on the subject property in accordance with Council's general requirements for signage and in accordance with the requirements outlined below: a) The sign should provide a brief description of the development proposed; b) The sign is to list the name, postal and/or email address and a contact telephone number for the following parties (where relevant) that are undertaking work on the site: - Developer;
c) The lettering on the sign is to be at least 25 millimetres in height, be of regular weight and in sentence case; d) The sign is to be a minimum size of 1,200 millimetres by 900 millimetres; e) The maximum area of the sign is to be 2.0m2; f) The sign is to be positioned as follows: - located centrally along each road frontage of the
site; g) The sign is to contain no commercial or corporate advertising other than the name, logo or slogan of the parties outlined in part (b) of this condition; h) The sign is to be non-illuminated; and i) Both the sign and the supporting structure are to be made of weatherproof material and to be properly maintained at all times. Timing: Prior to site works commencing and then to be maintained until completion of the development for all stages. |
As indicated |
| 10) Protect Existing Infrastructure Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure. Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations. The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements. |
While site/operational/building work is occurring |
10(a) As Constructed Drawings - Alterations
to Existing Infrastructure Submit to Development Services As Constructed drawings showing all new and/or rectification works and an asset register, prepared and certified by a Registered Professional Engineer Queensland. Timing: Prior to Council's notation on the plan of subdivision. PROOF OF
FULFILMENT Certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements. |
As indicated |
| 11) Certified Site Survey Levels Submit to Development Services, "As Constructed" drawings prepared by a Registered Surveyor (Qld). The registered surveyor must certify that the "As Constructed" drawings are in accordance with the APPROVED PLANS and the relevant Brisbane Planning Scheme Codes and show finished surface level information over the completed development. Note: The survey information must show surface levels and site contours at 1 metre intervals. All levels must be shown as Reduced Levels to the "Australian Height Datum" (AHD). |
Prior to Council's notation on the plan of subdivision |
| 12) Filling and/or Excavation (Minor) Filling and/or
excavation works on the site must be in accordance with the APPROVED PLANS and
the relevant Brisbane Planning Scheme Codes. Maintain overland flow path as a new constructed channel through the site and earthworks generally in accordance with approved amended Plan S25-243-PO1. |
Prior to Council's notation on the plan of subdivision |
12(a) Prepare Earthworks
Drawings Earthworks drawings must be prepared and certified by a Registered Professional Engineer Queensland in accordance with the relevant Brisbane Planning Scheme Codes. The drawings must include the following: - The location of any cut and/or fill; Note: The Earthworks drawings are not required to be submitted for Council approval. Timing: Prior to site/operational work commencing. |
As indicated |
12(b) Implement and Maintain the
Earthworks Carry out and maintain the earthworks in accordance with the requirements of AS3798 and the certified drawings. All fill material placed on the site must comprise only natural earth and rock and must be free of contaminants (as defined by Part 3, Division 2, Subdivision 2 Environmental contamination, Section 11 of the Environmental Protection Act 1994) and noxious, hazardous, deleterious and organic materials. Fill material, placement, compaction and testing must comply with the requirements of Australian Standard AS3798, Guidelines on Earthworks for Commercial and Residential Developments. Note: A copy of the certified Earthworks Drawings must be available on- site for inspection by Council Officers during these works. Timing: Prior to Council's notation on the plan of subdivision. |
As indicated |
12(c) Submit As Constructed
Drawings Submit to Development Services As Constructed drawings prepared by a Registered Surveyor (Qld). Timing: Prior to Council's notation on the plan of subdivision. |
As indicated |
12(d) Submit Certification Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with certified earthworks drawings. Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that all fill material used complies with the quality requirements of this condition and that placement, compaction and testing has been carried out in accordance with AS3798. Timing: Prior to Council's notation on the plan of subdivision. |
As indicated |
| 13) Retaining Walls Design and construct all retaining walls and associated fences, in accordance with the relevant Brisbane Planning Scheme Codes and the following: - All retaining walls including the footings, must be located wholly within the property boundaries of the site where works are occurring - Runoff from surface drains and subsoil drainage associated with the retaining walls must be collected and connected to a lawful point of discharge (LPD) where possible. If no LPD is available the surface drains and sub-soil drainage must be designed, installed and discharged to ensure there is no ponding, nuisance or concentration of stormwater discharge to adjacent properties. - Retaining walls to stabilise excavation must be set back from property boundaries to accommodate subsoil drainage without encroachment into the neighbouring property. This set back may vary depending on the height, structure and design of the retaining wall, surcharge loadings from neighbouring properties, and to provide a surface drain along the top of the retaining wall - For retaining walls in excess of
1.0m in height: NOTE: Refer to City Plan 2014; Infrastructure Design Planning Scheme Policy (IDPSP) for Council’s definition of a LPD. |
Prior to Council's notation on the plan of subdivision |
13(a) Certification of Retaining
Walls For retaining walls over 1.0m in height, obtain certification from a Registered Professional Engineer Queensland that the design and construction of the retaining walls and ancillary drainage are in accordance with the requirements of this condition. Timing: Prior to Council notation on the plan of subdivision. |
As indicated |
| 14) Repair Damage to Kerb, Footpath or Road Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development. |
Prior to Council's notation on the plan of subdivision |
14(a) Interim Repairs If at any time during the construction phase of the approved development, damage to the existing kerb and channel, footpath or roadway creates unsafe, unreasonable and/or not fit for purpose conditions as assessed by Council, interim repairs must be undertaken as directed by Program Planning and Integration. Note: Any interim repairs required to be undertaken shall not be considered to satisfy the requirements of this condition for the permanent repair of the infrastructure prior to Council's notation on the plan of subdivision. Timing: While site/operational works is occurring |
As indicated |
| 15) Up Stream Stormwater Drainage Connection Provide a stormwater drainage connection for the future development of the 3 adjoining upstream properties (located at 10, 26, 28 Burrowa Street) designed for ultimate developed catchment conditions and connected to the existing stormwater infrastructure, generally in accordance with approved Preliminary Services Plan (S25-243-P01) dated Jan 2026. Note: - All upslope stormwater connections to existing private properties must extend to the property boundary of the relevant property being ultimately serviced by that connection. |
Prior to Council's notation on the plan of subdivision |
15(a) Submit Stormwater
Drawings Submit to, and obtain approval from, Development Services, stormwater drawings and engineering calculations, prepared and certified by a Registered Professional Engineer Queensland in accordance with the relevant Brisbane Planning Scheme Codes. NOTE: -
Queensland Building and Construction Commission licensed hydraulic consultants
may design the stormwater system for sites less than 2000m2 with an upstream
catchment servicing no more than 4 residential lots. This excludes stormwater
drainage design (including subsoil drainage) of basements in flood planning
areas and the design of any onsite stormwater detention system Timing: Prior to site/operational work commencing. |
As indicated |
15(b) Implement Approved
Drawings Carry out the works in accordance with the above approved stormwater drawings. Timing: Prior to Council's notation on the plan of subdivision. |
As indicated |
15(c) Submit As Constructed
Drawings Submit to Development Services As Constructed drawings prepared and certified by a Registered Professional Engineer Queensland or Queensland Building and Construction Commission licensed hydraulic consultant (where applicable). Timing: Prior to Council's notation on the plan of subdivision. PROOF OF
FULFILMENT Certification from a Registered Professional Engineer Queensland or Queensland Building and Construction Commission licensed hydraulic consultants (where applicable) confirming that the works have been completed in accordance with the above stormwater drawings. Timing: Prior to Council's notation on the plan of subdivision. |
As indicated |
| 16) Site Drainage - Major Provide an internal drainage system to collect
stormwater run-off from all proposed lots, roofed and developed surface areas
and any run-off onto the site from adjacent areas and convey the collected run-
off to a lawful point of discharge, in accordance with the relevant Brisbane
Planning Scheme Codes. Design of
flowpath channel and lot earthworks to be provided by RPEQ and generally in
accordance with amended plan S25-243-PO1. - All upslope stormwater connections to existing
private properties must extend to the property boundary of all relevant
properties being ultimately serviced by that connection. Guidance for requesting a pre-start and co- ordinating the On/Off Maintenance process can be found on Council's website (https://www.brisbane.qld.gov.au/planning-and-building/applying-and- post-approval/on-and-off-maintenance-approvals. |
Prior to Council's notation on the plan of subdivision |
16(a) Submit Site Drainage
Drawings Submit to, and obtain approval from, Development Services, site drainage drawings and engineering calculations, prepared and certified by a Registered Professional Engineer Queensland, in accordance with the relevant Brisbane Planning Scheme Codes. Note: -
Queensland Building and Construction Commission licensed hydraulic consultants
may design the stormwater system for sites less than 2000m2 with an upstream
catchment servicing no more than 4 residential lots. This excludes stormwater
drainage design (including subsoil drainage) of basements in flood planning
areas and the design of any onsite stormwater detention system Timing: Prior to site/operational work commencing |
As indicated |
16(b) Implement Approved
Drawings Carry out the works in accordance with the approved site drainage drawings. Timing: Prior to Councils notation on the plan of subdivision. |
As indicated |
16(c) Submit As Constructed
Drawings Submit to Development Services As Constructed drawings prepared and certified by a Registered Professional Engineer Queensland or a Queensland Building and Construction Commission licensed hydraulic consultants (where applicable). Note: To be submitted via DA- ComplianceEngineering@brisbane.qld.gov.au and include the site address, A00 reference and Condition number in the subject line. Timing: Prior to Council's notation on the plan of subdivision. PROOF OF
FULFILMENT Certification (incl. QA documentation, CCTV, etc) from a Registered Professional Engineer Queensland, or a Queensland Building and Construction Commission licensed hydraulic consultants (where applicable), confirming that the works have been completed in accordance with the above stormwater approved site drainage drawings. Timing: Prior to Council's notation on the plan of subdivision. |
As indicated |
| 17) Ponding of Stormwater Carry out the approved development to
ensure that adjoining properties and roads are protected from ponding or
nuisance from stormwater during construction. |
Prior to Council's notation on the plan of subdivision |
| 18) Sealing of Abandoned Existing Sewer Property
Connection Permanently seal the existing sewer property connection, which will be built over or not reused to serve the proposed development. NOTE: Connection permanently abandoned to the satisfaction of the Manager, Plumbing Services or the Delegate, Development Services. |
Prior to site/operational/building work commencing |
| 19) Service Conduits and Mains Provide and install all service conduits, including street lighting as required by Council, and meet the cost of any alterations to public utility mains, existing mains, services, street lighting or installations that are required to carry out the approved development. These works must be in accordance with the relevant Brisbane Planning Scheme Codes, and include the following, where applicable: - the provision of all services and/or conduits along the full length of
any rear allotment access or access easement. Note: -
The cost of moving services, utilities and assets is the responsibility of the
Developer. The permission of the service, utility or asset owner will be
required. Council permission is required if street trees, stormwater
gullies/drains, and swales are affected. Urban Utilities permission is required
if water supply and sewerage services are affected. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the requirements of this condition. Note: Civil works are to be certified by a RPEQ(Civil) and electrical works are to be certified by a RPEQ (Electrical) |
Prior to Council's notation on the plan of subdivision |
19(a) Submit Certification to
Council Submit to Development Services certification by a Registered Professional Engineer Queensland (RPEQ) that the works have been completed in accordance with the requirements of the condition. Note: Where rear allotment accesses or easements exist, the certification is to be supported by As-Constructed drawings certified by a RPEQ showing all services and/or conduits. Civil works are to be certified by a RPEQ (Civil) and electrical works are to be certified by a RPEQ (Electrical)Timing: Prior to Council's notation of the plan of subdivision. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the requirements of this condition. Note: Civil works are to be certified by a RPEQ(Civil) and electrical works are to be certified by a RPEQ (Electrical) |
As indicated |
| 20) Telecommunications Submit to Development Services, evidence of an agreement with a telecommunication carrier to provide underground telecommunication services within and adjacent to the proposed development in accordance with the relevant Brisbane Planning Scheme Codes. |
Prior to Council's notation on the plan of subdivision |
| 21) Agreement with Electricity Supplier Submit to Development Services, evidence of an agreement with an electricity supplier to provide necessary services to the development in accordance with the relevant Brisbane Planning Scheme Codes. Where development is within an established area of overhead electricity supply and the electricity supplier determines that a property pole is the appropriate solution to supply electricity to the development, the developer must be responsible for the installation of the property pole(s). In the above circumstances, submit to Development Services, certification from the developer's electrical consultant confirming that the above installation has been completed in accordance with the relevant AS/NZS Standards and the Queensland Electricity Connection Manual (QECM) and Queensland Electricity Metering Manual (QEMM). |
Prior to Council's notation on the plan of subdivision |
| 22) Water and Wastewater Pursuant to Schedule 18 of the Planning Regulation 2017 submit to Development Services, documentary evidence, issued by the relevant distributor-retailer, to verify that the conditions of any necessary connection certificate under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009, have been complied with. |
Prior to Council's notation on the plan of subdivision |
| 23) Permanent Driveway Crossover For Lot 1, provide a modified Dwelling Type permanent driveway crossover to the Burrowa Street frontage of the site in accordance with the relevant Brisbane Planning Scheme Codes and located generally as shown on the approved amended DRAWINGS AND DOCUMENTS. Modified crossover to be 5.0m wide at the property boundary and tapering to 4.3m wide at the kerb. The vehicle crossover (including the wings and apron) must be constructed with the following clearance(s), if these cannot be achieved the crossover width is to be reduced: 600mm
clear of the stormwater gully; and 1.0meters from the power pole; and 2.0metres clear of the street tree; and the verge must be designed/graded to provide an adequate flow path for when the existing stormwater infrastructure exceeds capacity; and directed to 0.9m wide easement on the northern boundary. For Lot 2, provide 5.0metre wide (maximum) Single
Dwelling Type permanent driveway crossover to the Burrowa Street frontage
of the site in accordance with the relevant
Brisbane Planning Scheme Codes and located with a 600mm offset from the western
property boundary. Written consent must be obtained from Public Space
Operations Arboricultural Planning Team (PSO-Arb PLANNING) prior to
any works occurring that will either impact on or require removal of a street
tree (this includes pruning, excavation or fill within the root zone/canopy of
the tree) At all times during construction of the
crossover, safe pedestrian access along the site frontage must be
maintained. Note: No further driveway permit is
required however additional footway permits or lane closure permits may be
required for footpath/verge closures and/or lane closures. These permits must
be obtained prior to construction of the
crossover. |
Prior to Council's notation on the plan of subdivision |
| 24) Redundant Driveway Crossover Remove the redundant existing driveway crossover(s) on the frontage(s) of the site and reinstate the kerb and channel, road pavement, footways and footpaths in accordance with the relevant Brisbane Planning Scheme Codes. Note: |
Prior to Council's notation on the plan of subdivision |
| 25) Construction Noise and Dust Emissions Pursuant to the Environmental
Protection Act 1994, all development involving the emission of noise and dust
from building and/or construction activities, must ensure that the emissions
are in accordance with the requirements of the Act. |
As indicated |
| 26) Natural Assets Local Law (NALL) - Protected
Vegetation On Site Work on or around protected vegetation may require a permit under the Natural Assets Local Law 2003 (NALL). Permits under the NALL are issued by Development Services. To apply for a permit to work on protected vegetation go to Council's website or contact the call centre on 3403 8888. |
As indicated |
| 27) Standard Advice Disclaimer The standard advice is provided to the applicant as advice only and does not form part of the development approval conditions. This advice has been provided to inform the applicant of other obligations they may be required to comply with (under state legislation or local laws) prior to the approved activity commencing. |
As indicated |
| 28) Further Development Permit Required Further Development Permit(s) to carry out assessable building work under the Building Act may be required. |
As indicated |
| 29) Plumbing and Drainage Work Pursuant to the Plumbing and Drainage Act 2018, any plumbing and drainage work must be carried out in compliance with the Plumbing and Drainage Regulation 2019. Plumbing and drainage permit work requires approval by Brisbane City Council prior to the work being carried out. |
As indicated |
| 30) Currency Period The currency period for this development approval is stated in the Decision Notice and is expressed as a date. This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016. |
As indicated |
| 31) Cultural Heritage Aboriginal cultural heritage is protected under the Aboriginal Cultural Heritage Act 2003. This Act establishes a cultural heritage duty of care and in section 23(1) mandates that a person who carries out an activity must take all reasonable and practicable measures for ensuring activities are managed to avoid or minimise harm to Aboriginal cultural heritage. The Duty of Care Guidelines gazetted pursuant to the Aboriginal Cultural Heritage Act 2003 provide guidance on identifying and protecting Aboriginal cultural heritage to fulfil the duty of care. For further information contact the relevant Queensland State Government Department (Department of Aboriginal and Torres Strait Islander Partnerships). |
As indicated |
| 32) Fire Ant Movement Controls To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected. These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products. Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014. For further information contact the relevant Queensland State Government department on 13 QGOV. |
As indicated |
| 33) Water and Wastewater Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. For further information about any necessary Water Approvals contact Urban Utilities. |
As indicated |
| 34) Management of Asbestos Disposal, handling and restoration of any building materials containing asbestos must be in accordance with current state and federal legislation. |
As indicated |
| 35) Flood Resilience and Awareness This advice is provided for buildings that are on sites that are subject to the flood overlay, as shown within City Plan 2014. Council makes decisions to minimise flood risk based on the best information available at the time of the development application. Flood studies and applicable flood levels may be updated by Council overtime where new flood information is available or changes to engineering standards/methodology have occurred. Flood levels for various flood events and flooding types are outlined in Councils Floodwise Property Reports available from Councils website. The minimum flood planning levels that apply to new development do not necessarily mean that the development will never flood. Therefore, when choosing materials for building on sites that are known to be affected by flooding, regardless of whether it is constructed to the minimum flood planning level, it is recommended that flood resilient materials are used to improve the speed of recovery and reduce the cost of repairs if required. For more information refer to: Council's website at https://www.brisbane.qld.gov.au/community-and-safety/community- safety/disasters-and-emergencies/be-prepared/flooding-in-brisbane/flooding- support-for-residents/flood-resilient-homes-program Queensland Reconstruction Authority "Flood Resilient Building Guidance for Queensland Homes"https://www.qra.qld.gov.au/resilient- homes/flood-resilient-building-guidance-queensland-homes |
As indicated |
| 36) In Principle support for street tree interference
or removal As street trees are protected vegetation, the interference with or
removal of trees requires a permit under the Natural Assets Local Law (NALL),
issued by Public Space Operations Arboricultural
Planning Team (PSO-Arb PLANNING). Development Services has sought preliminary
advice from PSO-Arb PLANNING regarding the identified removal/interference with
existing street tree/s. Should ultimate access to Lot 2 be installed as indicatively
illustrated on the approved PLANS AND DOCUMENTS, then in-principle support for the removal of Street Tree 1 and
Street Tree 2 is supported. However, removal of these trees is not supported
until access is required. However, a separate NALL permit will be required for
crossover installation at that time. Detailed arrangements must be made
with PSO-Arb PLANNING in relation to the works carried out on protected
vegetation (including provision for tree removal and replacement tree planning
costs as determined by the Arboriculture Team) prior to carrying out any works
on protected vegetation. PSO-Arb PLANNING team can be contacted via ISG-CS-PPI-PLANNING-
ARB@brisbane.qld.gov.au. Note: All requirements of
development approval conditions with timing stipulated as 'prior to site works
commencing' (or equivalent) must be fulfilled before Council can issue a NALL
permit.
|
As indicated |