| Address of Site: | 11 PICOT ST KELVIN GROVE QLD 4059 |
| Real Property Description of Site: | L10 RP.10601 |
| Aspects of development and type of approval: | DA - PA - Building Work Development Permit - dwelling house,Demolition DA - PA - Material Change of Use Development Permit - rooming accommodation DA - PA - Building Work Development Permit - rooming accommodation |
| Council File Reference: | A006871612 Permit Reference Number/s: DABW382597019; DAMC382597119; DABW382682619. |
| Package Status: | APPROVED - Version 2 (10th of June, 2026 1:06:48 PM) |
| Package Generated: | 10/06/2026 |
| Roger GREENWAY Principal Urban Planner Development Assurance & Outcomes roger.greenway@brisbane.qld.gov.au 34034392 |
Ann-Marie KYRANIS Senior Urban Planner Development Assurance & Outcomes Ann-Marie.Kyranis@brisbane.qld.gov.au 31780671 |
Justin SELLARS Senior Urban Planner Planning Services House & Homes justin.sellars@brisbane.qld.gov.au 3403 6546 |
| JAMES HEADING Principal Urban Planner Partnerships Team james.heading@brisbane.qld.gov.au (07) 3403 5591 |
George KOUPARITSAS Architect Architecture Team George.Kouparitsas@brisbane.qld.gov.au 31787245 |
Matthew O'DEA Principal Landscape Architect Landscape Architecture Team Matthew.ODea@brisbane.qld.gov.au 31789513 |
| Craig SLACK Engineer Engineering Scoping craig.slack@brisbane.qld.gov.au (07) 3403 8888 |
Emma MEZZINA Team Manager Planning Services South Emma.Mezzina@brisbane.qld.gov.au 3178 0049 |
Vernon ANDERSON Team Manager (Acting) Planning Services Coordination Vernon.Anderson@brisbane.qld.gov.au 31780808 |
| Scott RUHLAND Technical Officer Engineering Services North scott.ruhland@brisbane.qld.gov.au (07) 3403 9459 |
Jacqueline PATON Senior Architect Architecture Team Jacqueline.Paton@brisbane.qld.gov.au 07 3178 0389 |
Chris.M DIXON Senior Urban Planner Planning Services North chris.m.dixon@brisbane.qld.gov.au 31787264 |
| MAISIE TANG Principal Urban Planner Planning Services North maisie.tang@brisbane.qld.gov.au (07) 31789048 |
DRAWINGS AND DOCUMENTS
| Drawing or Document | Number | Plan Date |
|---|---|---|
| Existing | 2.00 Issue J | 31-MAR-2026 |
| Existing Elevations | 3.00 Issue J | 31-MAR-2026 |
| Flood Investigation Report | 19123 Rev 0 | 06-NOV-2019 (Received) |
| Waste Assessment | 20BRW0003 | 10-MAR-2020 |
| Site Plan | 1.00 Issue J | 31-MAR-2026 |
| Proposed | 2.10 Issue J (Amended In Red 23-APR-2026) | 31-MAR-2026 |
| Landscape / POS Plan | 1.10 Issue J | 31-MAR-2026 |
| Proposed Elevations | 3.10 Issue J (Amended In Red 23-APR-2026) | 31-MAR-2026 |
| Sections | 4.00 Issue J | 31-MAR-2026 |
| Area Plan | 1.01 Issue J | 31-MAR-2026 |
APPROVAL CONDITIONS
| Permit to Which These Conditions Relate: | DA - PA - Building Work |
| Activity(ies): | dwelling house Demolition |
| Stage: | Relocate pre-1947 Dwelling house |
| 1) Maintain the Approved Development Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions. |
At all times |
| 2) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers. Note: This condition is imposed to ensure compliance with the conditions of development approval. |
While site/operational/building work is occurring |
| 3) Carry Out the Approved Development Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS. Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners. |
While site/operational/building work is occurring |
| 4) Complete All Building Work Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS. Note: Building work must also be completed in accordance with any other current development approval. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 5) Partial Demolition of Building Partial demolition resulting
from this approval must be in accordance with the APPROVED DRAWINGS AND
DOCUMENTS and all building work must comply with this
condition. |
While site/operational/building work is occurring and then to be maintained |
5(a) Adequate Bracing Provide adequate bracing from
the commencement of any demolition work and throughout the demolition and
construction phases of the project, to ensure that all parts of the building
not specifically designated for demolition on the APPROVED DRAWINGS AND
DOCUMENTS are retained and protected. |
As indicated |
5(b) Retain Original Fabric Retain all existing external
original fabric in the sections of the building which are not being demolished.
This will include, but is not limited to, existing decorative detailing,
balustrading, wall cladding, windows, doors, stairs and roof sheeting. |
As indicated |
5(c) Submit Certification Submit to Development
Services certification by a Registered Architect / Building Designer (holding a
Queensland Building and Construction Commission Licence appropriate to the
scale of the approved development) confirming that the partial demolition has
been carried out in accordance with the requirements of this condition. |
As indicated |
| 6) On-site Erosion (medium risk) Minimise on-site erosion and
the release of sediment or sediment laden stormwater from the site at all
times. |
As indicated |
6(a) Prepare Erosion and Sediment Control
Plan Prepare
Erosion and Sediment Control (ESC) Plan(s), and provide design certificates for
the site in accordance with the relevant Brisbane Planning Scheme Codes. |
As indicated |
6(b) Attend a Pre-Start meeting Arrange and attend a
pre-start meeting with an Erosion & Sediment Control Officer from
Council’s Compliance and Regulatory Services. Requests are to be
made when submitting copies of all required documentation, including design
certificates to: CARS-
ESC@brisbane.qld.gov.au |
As indicated |
6(c) Implement Certified Erosion and Sediment
Control Plan Implement the certified ESC plan(s) to maintain compliance with all
parts of the relevant Brisbane Planning Scheme Codes, while site works are
occurring and until all exposed soil areas are permanently stabilised against
erosion. |
As indicated |
| 7) Information Signage Erect an "Information Sign" on the subject property in accordance with Council’s general requirements for signage and in accordance with the requirements outlined below: a) The sign should provide a brief description of the development
proposed; |
As indicated |
| 8) Construction Management Plan (Minor) Carry out development in accordance with a Construction Management Plan (Minor) prepared in accordance with the requirements of this condition. |
While site/operational/building work is occurring |
8(a) Prepare Management Plan
(minor) Prepare a Construction Management Plan for the subject site.
The Construction Management Plan must be available on site at all times and must show, but not be limited to the following details where applicable, for the demolition (where in a Centre zone, a Mixed use zone or where the demolition is otherwise assessable development), excavation and construction phases of the approved development. Separate Construction Management Plans may be appropriate for the individual components:
- Provision of alternative pedestrian route/s, past or around the site - Existing and proposed kerbside allocation signs and line marking (such as bus stops, loading zones and parking meters and/or ticket dispensers) - Temporary vehicular access points - Management and mitigation strategies for the impact of dust, noise and vibration upon adjoining and nearby properties - Employee and visitor parking areas (if provided) - Provision for loading and unloading materials including the location of any remote loading sites - The location of materials, structures, plant and equipment to be stored or placed on the construction site - The anticipated staging and programming - Allowable work times as set by the Queensland Environmental Protection Act 1994 (section 440). A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management Delegate Development Services.
The Construction Management Plan must be supported by Permits or written approvals from the relevant Council sections or other body listed below (where applicable to the Plan) to ensure all potential impacts to Council and other infrastructure have been addressed: (i) Work Zones / Temporary Road Closures / Taxi Ranks - (Congestion Reduction Unit, Planned Incident Management / Temporary Road Closures); (ii) Full/Partial Footway-Footpath Closures – (Brisbane Infrastructure – Congestion Reduction Unit); (iii) Street Lighting - (Brisbane Infrastructure - Asset Services-City Lighting); (iv) City Cycle bike stations and JCDecaux Advertising Signage (including obstruction to sight lines for such advertising - owned by JCDecaux)- (Brisbane Infrastructure - Transport Planning and Strategy, Contract Management section); (v) Street Furniture (excluding bus stops) - (Brisbane Infrastructure, Transport Network Operations, Roads and Drainage); (vi) Waste Bins - (Brisbane Infrastructure, Waste Service); (vii) Bus Stops/Shelters - (Brisbane infrastructure - Transport Planning and Strategy-Strategic Planning; and Brisbane Transport - Network Planning & Bus Operations); (viii) Street Trees - (Brisbane Infrastructure - Asset Services - Arboriculture); (ix) Parking Meters/Spaces - (Brisbane Infrastructure - City Parking); (x) Traffic Signals - (Brisbane Infrastructure - Traffic Signals Operations); (xi) Stormwater Gullies/Pits etc - (Brisbane Infrastructure - Roads and Drainage); (xii) Other service providers - (e.g. Energex, Telstra, Optus, Queensland Urban Utilities, AGL).
Note: The Construction Management Plan is not required to be approved by Development Services.
At least 10 days prior to commencement of site works, submit a copy of the Construction Management Plan to Council’s Development Services Branch at the following mailbox: engineeringservices@brisbane.qld.gov.au quoting the planning development approval reference number.
Timing: Prior to site/operational/building work commencing |
As indicated |
8(b) Construction Management Plan (Minor) -
Documentation on Site Legible copies
of the Construction Management Plan and current permits must be kept on site
and be made available on request at all times. |
As indicated |
8(c) Construction Management Plan (Minor) -
Works to be Performed Out of Hours Obtain approval from Development Services for any work that is proposed
to be undertaken outside of normal business hours - 6:30am to 6:30pm, Monday to
Saturday. |
As indicated |
8(d) Implement Construction Management Plan
(Minor) Carry out the
development in accordance with the Construction Management Plan prepared in
accordance with this condition. |
As indicated |
| 9) Protect Existing Infrastructure Where there is existing infrastructure in the vicinity of the proposed
work, the new work must not damage or compromise the working ability of the
existing infrastructure. Where alterations to public utility mains, existing
mains, services or installations are necessitated by the development, prior to
alterations commencing, the developer must notify Council or the relevant
infrastructure provider and obtain agreement to the alterations. The developer
must meet the costs of the alterations. The alterations must be carried out in
accordance with the relevant Brisbane Planning Scheme Codes or infrastructure
providers requirements. |
While site/operational/building work is occurring |
9(a) As Constructed Drawings Where alterations to
existing infrastructure are required, submit to Development Services "As
Constructed" drawings showing all new and/or rectification works and an
asset register, prepared by a Registered Professional Engineer Queensland. |
As indicated |
9(b) Submit Certification Where alterations to existing
infrastructure are required, submit to Development Services certification from
a Registered Professional Engineer Queensland, confirming that the alterations
have been completed in accordance with the relevant Brisbane Planning Scheme
Codes and any other relevant infrastructure requirements. |
As indicated |
| 10) Remove Improvements & Obstructions From Truncation
and Dedication Remove all improvements (fences, gates, letter boxes, garden beds and plots and other constructed items, etc.) and obstructions (existing earth banks, vegetation, etc.) from the area of the dedicated road and reinstate the area as footway in accordance with the relevant Brisbane Planning Scheme Codes. Any new or existing installations of electrical pillar boxes, pad mounted transformers (PMTs), water meters and the like, must be installed/relocated to their ultimate alignment relative to the new property boundary and clear of the usable footpath areas irrespective of the alignment of the existing services/conduits. Note: - The cost of moving services, utilities and assets is the responsibility of the Developer. The permission of the service, utility or asset owner will be required. Council permission is required if street trees, stormwater gullies/drains, and swales are affected. Queensland Urban Utilities permission is required if water supply and sewerage services are affected   ; - Standard utility alignments may be found on Council’s ‘Brisbane Standard Drawings’ 1013 to 1016 inclusive. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
10(a) Certify the Work Submit to Development
Services certification from a Registered Surveyor or Registered Professional
Engineer Queensland that the above work has been completed in accordance with
this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 11) Filling and / or Excavation (Minor) Filling and/or excavation works on the site must be in accordance with the relevant Brisbane Planning Scheme Codes. No earthworks whether cut or fill are to be undertaken within the new 6 metre wide overland flow easement at the east boundary of the site. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
11(a) Prepare Earthworks
Drawings Earthworks drawings must be prepared and certified by either: a
Registered Professional Engineer Queensland or a suitably qualified
geotechnical and structural consultant, in accordance with the relevant
Brisbane Planning Scheme Codes. |
As indicated |
11(b) Implement and Maintain the
Earthworks Carry
out and maintain the earthworks in accordance with the certified drawings. |
As indicated |
| 12) Repair Damage to Kerb, Footpath Or Road Repair any damage to the
existing kerb and channel, footpath or roadway (including removal of concrete
slurry from footways, roads, kerb and channel, stormwater gullies and
drainlines) and re-instate existing traffic signs and pavement markings that
have been removed or damaged during any works carried out in association with
the approved development. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
12(a) Interim Repairs If at any time during the construction phase of the
approved development, damage to the existing kerb and channel, footpath or
roadway creates unsafe, unreasonable and/or not fit for purpose conditions as
assessed by Council, interim repairs must be undertaken as directed by Asset
Services. Note: Any interim repairs required to be undertaken shall not be
considered to satisfy the requirements of this condition for the permanent
repair of the infrastructure prior to the issue of Certificate of
Classification/Final Inspection Certificate or prior to commencement of use,
whichever comes first (MCU or BW), or prior to Council's notation of the plan
of subdivision (ROL). Timing: While site / operational / building works is
occurring |
As indicated |
| 13) Remove Redundant Drainage Outlets Remove any redundant drainage outlets from the kerb and channel
including any associated pipe work across the footway and reinstate the kerb
and channel and the footway area in accordance with the relevant Brisbane
Planning Scheme Codes. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 14) Construction Noise and Dust Emissions Pursuant to the Environmental
Protection Act 1994, all development involving the emission of noise and dust
from building and/or construction activities, must ensure that the emissions
are in accordance with the requirements of the Act. |
As indicated |
| 15) Currency Period The currency period for this development approval is stated in the Decision Notice and is expressed as a date. This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016. |
As indicated |
| 16) Damage to Trees on Adjoining Land Please note that any damage caused to vegetation on adjoining land as a result of exercising this development approval may result in an offence under other legislation (e.g. Natural Assets Local Law) and/or civil action. |
As indicated |
| 17) Further Development Permit Required Further Development Permit(s) to carry out assessable building work under the Building Act may be required. |
As indicated |
| 18) Cultural Heritage Aboriginal cultural heritage is protected under the Aboriginal Cultural Heritage Act 2003. This Act establishes a cultural heritage duty of care and in section 23(1) mandates that a person who carries out an activity must take all reasonable and practicable measures for ensuring activities are managed to avoid or minimise harm to Aboriginal cultural heritage. The Duty of Care Guidelines gazetted pursuant to the Aboriginal Cultural Heritage Act 2003 provide guidance on identifying and protecting Aboriginal cultural heritage to fulfil the duty of care. For further information contact the relevant Queensland State Government Department (Department of Aboriginal and Torres Strait Islander Partnerships). |
As indicated |
| 19) Fire Ant Movement Controls To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected. These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products. Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014. For further information contact the relevant Queensland State Government department on 13 QGOV. |
As indicated |
| Permit to Which These Conditions Relate: | DA - PA - Material Change of Use |
| Activity(ies): | rooming accommodation |
| Stage: | Rooming accommodation |
| 20) Maintain the Approved Development Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions. |
At all times |
| 21) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers. Note: This condition is imposed to ensure compliance with the conditions of development approval. |
While site/operational/building work is occurring |
| 22) Carry Out the Approved Development Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS. Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners. |
While site/operational/building work is occurring |
| 23) Complete All Building Work Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS. Note: Building work must also be completed in accordance with any other current development approval. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 24) Visitor Parking Visitor car parking spaces must: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 25) Outdoor lighting Outdoor lighting is to be in compliance with AS 4282-1997 - Control of the obtrusive effects of outdoor lighting. |
At all times |
| 26) Limitation of use The approved Rooming accommodation must operate in accordance with the definition of ‘suite’ in the Brisbane Infrastructure Charges Resolution (No. 9) 2020, as detailed below: ‘Suite’ means a number of connected rooms one of which is a bedroom in which an individual or a group of two or more related or unrelated people reside with the common intention to live together on a long term basis and who make common provision for food or other essentials for living. The approved Rooming accommodation is to have a maximum of 4 dwelling suites with a total of 24 rooms.
|
Prior to the commencement of the use and then to be maintained |
| 27) External Details External details of the building, facade treatment and external materials and finishes must be consistent with the approved DRAWINGS AND DOCUMENTS. Note: The requirement to use particular materials and finishes is imposed only for the purpose of achieving a built form outcome that displays architectural merit. Council has not assessed the materials and finishes for compliance with the Building Act, the Building Fire Safety Regulation, the Building Regulation, the Building Code of Australia, the Queensland Development Code, relevant Australian Standards, fire safety standards or any other relevant requirement of a statutory authority with regard to building work. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 28) Overall Height The overall height of the building(s) must be in accordance with the floor and roof levels and overall height shown on the APPROVED DRAWINGS AND DOCUMENTS. NOTE: Where there is a conflict with the floor heights shown on the APPROVED DRAWINGS and the conditions in this approval that stipulate minimum height clearance for undercover car parking, the height clearance conditions prevail. |
While site/operational/building work is occurring and then to be maintained |
28(a) Submit Certification Submit to Development Services certification from a registered surveyor confirming that the 'as constructed' floor and roof levels and overall height are in accordance with the requirements of this condition. Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 29) Provide Pedestrian Prioritised Pathway Provide a pedestrian prioritised pathway from the street frontage to Buildings A, B, C and D. The pathway must be differentiated in colour and texture from the driveway surface. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 30) Screen Air Conditioning and Other Plant
Enclosures Install and maintain suitable screening to all air conditioning, lift
motor rooms, plant and service facilities located at the top of or on the
external face of the building. The screening structures must be constructed
from materials that are consistent with materials used elsewhere on the facade
of the building. There must be no individual external air conditioning units
located on balconies. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 31) Screening Provide screening to windows of habitable rooms, balconies, landings, terraces and decks of the proposed dwelling(s) in accordance with the approved DRAWINGS AND DOCUMENTS and the following requirements. Where any windows of habitable rooms of the proposed dwelling(s) are within 2m at ground floor level or 9m above ground floor level of adjoining neighbouring dwellings' windows to habitable rooms, provide suitable screening in accordance with the following: Suitable screening must be: For windows: For balconies, landings, terraces
and decks facing the side boundaries of the site: Note: Screening devices must be either solid translucent screens, perforated or slatted panels, or fixed louvres that are permanent, be durable and fixed. Screening devices must have a maximum of 25% openings, with a maximum opening of 50mm. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 32) Streetscape Works - Neighbourhood Street Carry out streetscape improvement works including concrete path, turf and street trees to the verge to a Neighbourhood Street Minor standard in accordance with the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD), the requirements of this condition and the Infrastructure Design Planning Scheme Policy including sections 3.7.4.4 and 3.7.5. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
32(a) Concrete Path Install a 1.2m wide broom finished standard Portland grey concrete
path. The path on the southern side of the driveway is to be setback 1.3m from
the back of kerb. The path on the northern side of the driveway is to align
with the existing path on the verge that adjoins the development to the
north. Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL). |
As indicated |
32(b) Submit As-Constructed
Drawings Submit
to Development Services "As Constructed" plans including an asset
register, checked by a Registered Professional Engineer Queensland, certifying
that the concrete path works have been completed in accordance with relevant
Brisbane Planning Scheme Codes/Policies. |
As indicated |
32(c) Turf Install turf to the full
width of the verge excluding any concrete path required by this condition. |
As indicated |
| 33) Landscape the Site - Self Certification Landscape the site in accordance with the requirements of this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
33(a) Detailed Landscape Plan for Self
Certification Prepare a Detailed Landscape Plan at a scale of 1:100 for all on-site landscape works including planting areas identified on the approved DRAWINGS AND DOCUMENTS. The plan must be prepared by a Registered Landscape Architect and must comply with the relevant Brisbane Planning Scheme Codes. In addition to the requirements listed above, the plan must include the following: . Deep planting areas · Deep planting areas as shown on the approved drawings, open to the sky and with no underground development including retaining wall footings with the exception of existing underground infrastructure. · Provide tree planting in accordance with the approved drawing numbered 2.10 Issue J, received 2 April 2026 and amended in red 23 April 2026.
Side and rear boundaries · Provide tree planting in accordance with the approved drawing numbered 2.10 Issue J, received 2 April 2026 and amended in red 23 April 2026. Containerised planting · Clear identification of the location, width and depth of containerised planting. · Minimum internal depths and widths as shown on approved plans · A reticulated drip irrigation system to all containerised planting areas, with drainage connected to the stormwater system; the irrigation system must be connected to a non-mains water source. Specifications · Plant selection and densities to achieve full surface coverage within 2 years of planting · Unless otherwise specified, trees provided as 45 litre stock or larger, staked and tied, and complying with Australian Standards · Mulch and soil to all garden areas to meet Australian Standards · Soil media ameliorated to increase water-holding abilities · Details of a 12-week establishment period. Timing: Prior to building work commencing.
|
As indicated |
33(b) Certify Detailed Landscape
Plan On completion of the Detailed Landscape Plan, submit to Development Services: · Brisbane City Council Form CC10616 - Landscape Design Certificate prepared by a Registered Landscape Architect to certify that the Detailed Landscape Plan complies with the requirements of this condition · A copy of the certified Detailed Landscape Plan. Timing: Prior to building work commencing. |
As indicated |
33(c) Implement Certified Detailed Landscape
Plan Carry out the landscape work in accordance with the above certified detailed Landscape Plan.
Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
33(d) Certify Work On completion of the landscape work, submit to Development Services: · Brisbane City Council Form CC10613 - Landscape Works Certificate prepared by a Registered Landscape Architect or licensed Landscape Contractor to certify the completed landscape work complies with the certified Detailed Landscape Plan · A copy of the as- constructed certified Detailed Landscape Plan.
Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first.
|
As indicated |
33(e) Maintain Landscape Work Maintain the landscape work generally in accordance with the certified Detailed Landscape Plan.
Timing: To be maintained. |
As indicated |
| 34) Air Emissions
Vehicle exhaust fumes are released via exhaust vent outlets which are
directed away from any sensitive use and include the
following:
- air emissions are not to cause an odour or air emission which is detectable and disturbing at a sensitive use; and - ensures that exhaust vents from any basement/enclosed car park are separated from any sensitive use by a minimum of 15m and 6m from intakes and natural ventilation openings.
|
Prior to the commencement of the use and then to be maintained |
| 35) Acoustic Fence - General Erect a 2.0m high (relative to the finished RL of the driveway /
pathway) acoustic fence along the northern and southern boundaries of the site
adjacent to the driveway / pathway as shown on the approved drawings numbered
2.10 Issue J, received 2 April 2026 and amended in red 23 April 2026. The
acoustic fencing must: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
35(a) Certification Submit to Development Services certification from a person who is a Member or eligible to be a Member of the Australian Acoustic Society that the constructed acoustic fence complies with the above requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 36) Dampening of Grilles and Metal Plates All metal grilles, metal plates or similar located within vehicle parking and manoeuvring areas must be securely fastened and meet the requirements of AS3996:2019, Access covers and grates. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 37) Plant and Equipment Certification Following the installation of all mechanical
plant and equipment (e.g. air conditioning, mechanical ventilation and
refrigeration equipment and heat pump hot water systems), submit to Development
Assessment certification that the plant and equipment is adequately noise-
attenuated and is in accordance with the criteria of the relevant Brisbane
Planning Scheme Codes/Policies. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 38) Retaining Walls Design and construct all
retaining walls and associated fences, in accordance with the relevant Brisbane
Planning Scheme Codes and including the following: |
As indicated |
38(a) Certification of Retaining
Walls For
retaining walls over 1.0m in height, obtain certification from a Registered
Professional Engineer Queensland that the design and construction of the
retaining wall and ancillary drainage is in accordance with this condition. |
As indicated |
| 39) Grant Easements Grant the following easement(s):
|
As indicated |
39(a) Submit Plan of Subdivision and
Documentation (Non-Council Easement) Submit for the approval of Development Services, a
plan of subdivision showing the easement and the necessary easement
documentation to demonstrate compliance with the requirements of this
condition. |
As indicated |
39(b) Submit Plan of Subdivision and
Documentation (Council Easement) Submit for the approval of Development Services, a
plan of subdivision showing the easement and a request for Council to prepare
the necessary easement documentation to demonstrate compliance with the
requirements of this condition. |
As indicated |
39(c) Lodge Notated Plan and
Documentation Lodge
the plan of subdivision notated by Council pursuant to Schedule 18 of the
Planning Regulation 2017 and the necessary easement documentation with the
Registrar of Titles for the relevant Queensland State Government Authority. |
As indicated |
39(d) Submit Evidence of
Registration Submit
to Development Services evidence of the registration of the necessary easement
documentation. |
As indicated |
| 40) On-site Erosion (medium risk) Minimise on-site erosion and
the release of sediment or sediment laden stormwater from the site at all
times. |
As indicated |
40(a) Prepare Erosion and Sediment Control
Plan Prepare
Erosion and Sediment Control (ESC) Plan(s), and provide design certificates for
the site in accordance with the relevant Brisbane Planning Scheme Codes. |
As indicated |
40(b) Attend a Pre-Start
meeting Arrange and attend a pre-start meeting with an Erosion & Sediment
Control Officer from Council’s Compliance and Regulatory Services.
Requests are to be made when submitting copies of all required documentation,
including design certificates to: CARS-ESC@brisbane.qld.gov.au |
As indicated |
40(c) Implement Certified Erosion and
Sediment Control Plan Implement the certified ESC plan(s) to maintain compliance with all
parts of the relevant Brisbane Planning Scheme Codes, while site works are
occurring and until all exposed soil areas are permanently stabilised against
erosion. |
As indicated |
| 41) Information Signage Erect an "Information Sign" on the subject property in accordance with Council’s general requirements for signage and in accordance with the requirements outlined below: a) The sign should provide a brief description of the development
proposed; |
As indicated |
| 42) Construction Management Plan (Minor) Carry out development in accordance with a Construction Management Plan (Minor) prepared in accordance with the requirements of this condition. |
While site/operational/building work is occurring |
42(a) Prepare Management Plan
(minor) Prepare a Construction Management Plan for the subject site.
The Construction Management Plan must be available on site at all times and must show, but not be limited to the following details where applicable, for the demolition (where in a Centre zone, a Mixed use zone or where the demolition is otherwise assessable development), excavation and construction phases of the approved development. Separate Construction Management Plans may be appropriate for the individual components:
- Provision of alternative pedestrian route/s, past or around the site - Existing and proposed kerbside allocation signs and line marking (such as bus stops, loading zones and parking meters and/or ticket dispensers) - Temporary vehicular access points - Management and mitigation strategies for the impact of dust, noise and vibration upon adjoining and nearby properties - Employee and visitor parking areas (if provided) - Provision for loading and unloading materials including the location of any remote loading sites - The location of materials, structures, plant and equipment to be stored or placed on the construction site - The anticipated staging and programming - Allowable work times as set by the Queensland Environmental Protection Act 1994 (section 440). A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management Delegate Development Services.
The Construction Management Plan must be supported by Permits or written approvals from the relevant Council sections or other body listed below (where applicable to the Plan) to ensure all potential impacts to Council and other infrastructure have been addressed: (i) Work Zones / Temporary Road Closures / Taxi Ranks - (Congestion Reduction Unit, Planned Incident Management / Temporary Road Closures); (ii) Full/Partial Footway-Footpath Closures – (Brisbane Infrastructure – Congestion Reduction Unit); (iii) Street Lighting - (Brisbane Infrastructure - Asset Services-City Lighting); (iv) City Cycle bike stations and JCDecaux Advertising Signage (including obstruction to sight lines for such advertising - owned by JCDecaux)- (Brisbane Infrastructure - Transport Planning and Strategy, Contract Management section); (v) Street Furniture (excluding bus stops) - (Brisbane Infrastructure, Transport Network Operations, Roads and Drainage); (vi) Waste Bins - (Brisbane Infrastructure, Waste Service); (vii) Bus Stops/Shelters - (Brisbane infrastructure - Transport Planning and Strategy-Strategic Planning; and Brisbane Transport - Network Planning & Bus Operations); (viii) Street Trees - (Brisbane Infrastructure - Asset Services - Arboriculture); (ix) Parking Meters/Spaces - (Brisbane Infrastructure - City Parking); (x) Traffic Signals - (Brisbane Infrastructure - Traffic Signals Operations); (xi) Stormwater Gullies/Pits etc - (Brisbane Infrastructure - Roads and Drainage); (xii) Other service providers - (e.g. Energex, Telstra, Optus, Queensland Urban Utilities, AGL).
Note: The Construction Management Plan is not required to be approved by Development Services.
At least 10 days prior to commencement of site works, submit a copy of the Construction Management Plan to Council’s Development Services Branch at the following mailbox: engineeringservices@brisbane.qld.gov.au quoting the planning development approval reference number.
Timing: Prior to site/operational/building work commencing |
As indicated |
42(b) Construction Management Plan (Minor) -
Documentation on Site Legible copies
of the Construction Management Plan and current permits must be kept on site
and be made available on request at all times. |
As indicated |
42(c) Construction Management Plan (Minor) -
Works to be Performed Out of Hours Obtain approval from Development Services for any work that is proposed
to be undertaken outside of normal business hours - 6:30am to 6:30pm, Monday to
Saturday. |
As indicated |
42(d) Implement Construction Management Plan
(Minor) Carry out the
development in accordance with the Construction Management Plan prepared in
accordance with this condition. |
As indicated |
| 43) Protect Existing Infrastructure Where there is existing infrastructure in the vicinity of the proposed
work, the new work must not damage or compromise the working ability of the
existing infrastructure. Where alterations to public utility mains, existing
mains, services or installations are necessitated by the development, prior to
alterations commencing, the developer must notify Council or the relevant
infrastructure provider and obtain agreement to the alterations. The developer
must meet the costs of the alterations. The alterations must be carried out in
accordance with the relevant Brisbane Planning Scheme Codes or infrastructure
providers requirements. |
While site/operational/building work is occurring |
43(a) As Constructed Drawings Where alterations to
existing infrastructure are required, submit to Development Services "As
Constructed" drawings showing all new and/or rectification works and an
asset register, prepared by a Registered Professional Engineer Queensland. |
As indicated |
43(b) Submit Certification Where alterations to existing
infrastructure are required, submit to Development Services certification from
a Registered Professional Engineer Queensland, confirming that the alterations
have been completed in accordance with the relevant Brisbane Planning Scheme
Codes and any other relevant infrastructure requirements. |
As indicated |
| 44) Remove Improvements & Obstructions From Truncation
and Dedication Remove all improvements (fences, gates, letter boxes, garden beds and plots and other constructed items, etc.) and obstructions (existing earth banks, vegetation, etc.) from the area of the dedicated road and reinstate the area as footway in accordance with the relevant Brisbane Planning Scheme Codes. Any new or existing installations of electrical pillar boxes, pad mounted transformers (PMTs), water meters and the like, must be installed/relocated to their ultimate alignment relative to the new property boundary and clear of the usable footpath areas irrespective of the alignment of the existing services/conduits. Note: - The cost of moving services, utilities and assets is the responsibility of the Developer. The permission of the service, utility or asset owner will be required. Council permission is required if street trees, stormwater gullies/drains, and swales are affected. Queensland Urban Utilities permission is required if water supply and sewerage services are affected   ; - Standard utility alignments may be found on Council’s ‘Brisbane Standard Drawings’ 1013 to 1016 inclusive. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
44(a) Certify the Work Submit to Development
Services certification from a Registered Surveyor or Registered Professional
Engineer Queensland that the above work has been completed in accordance with
this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 45) Filling and / or Excavation (Minor) Filling and/or excavation works on the site must be in accordance with the relevant Brisbane Planning Scheme Codes. No earthworks whether cut or fill are to be undertaken within the new 6 metre wide overland flow easement at the east boundary of the site. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
45(a) Prepare Earthworks
Drawings Earthworks drawings must be prepared and certified by either: a
Registered Professional Engineer Queensland or a suitably qualified
geotechnical and structural consultant, in accordance with the relevant
Brisbane Planning Scheme Codes. |
As indicated |
45(b) Implement and Maintain the
Earthworks Carry
out and maintain the earthworks in accordance with the certified drawings. |
As indicated |
| 46) Repair Damage to Kerb, Footpath Or Road Repair any damage to the
existing kerb and channel, footpath or roadway (including removal of concrete
slurry from footways, roads, kerb and channel, stormwater gullies and
drainlines) and re-instate existing traffic signs and pavement markings that
have been removed or damaged during any works carried out in association with
the approved development. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
46(a) Interim Repairs If at any time during the construction phase of the
approved development, damage to the existing kerb and channel, footpath or
roadway creates unsafe, unreasonable and/or not fit for purpose conditions as
assessed by Council, interim repairs must be undertaken as directed by Asset
Services. Note: Any interim repairs required to be undertaken shall not be
considered to satisfy the requirements of this condition for the permanent
repair of the infrastructure prior to the issue of Certificate of
Classification/Final Inspection Certificate or prior to commencement of use,
whichever comes first (MCU or BW), or prior to Council's notation of the plan
of subdivision (ROL). Timing: While site / operational / building works is
occurring |
As indicated |
| 47) Remove Redundant Drainage Outlets Remove any redundant drainage outlets from the kerb and channel
including any associated pipe work across the footway and reinstate the kerb
and channel and the footway area in accordance with the relevant Brisbane
Planning Scheme Codes. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 48) Access, Grades, Manoeuvring, Carparks, Signs and
Line Marking Construct access, parking and manoeuvring for
vehicles on site in accordance with the relevant Brisbane Planning Scheme
Codes, as indicated on the approved DRAWINGS AND DOCUMENTS, including the
following: iv. A minimum of
2.3 metres height clearance to all undercover parking areas and a minimum of
2.5 metres above parking spaces for people with disabilities. The minimum
clear height must be measured to the lowest protrusion from the ceiling (e.g.
fire sprinklers, services, lighting fixtures, signs, etc). |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
48(a) Submit certification Submit to Development
Services, certification from a Registered Professional Engineer Queensland,
that the above requirements have been implemented in accordance with this
condition. |
As indicated |
| 49) Minimum Flood Planning Levels Design and construct
all proposed building pad levels, floor levels and ancillary structures to the
appropriate flood planning level with freeboard (where required) in accordance
with the relevant Brisbane Planning Scheme Codes. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
49(a) Submit Certification Submit to Development Services "As-Constructed" drawings
prepared by a Registered Surveyor. The Registered Surveyor must certify that
the development has been constructed in accordance with this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
| 50) Stormwater - Flood Study Construct the development in accordance with the approved Flood Investigation Report prepared by HCE Engineers numbered 19123 Rev 0, received 6 November 2019. No earthworks whether cut or fill are to be undertaken within the new 6 metre wide overland flow easement at the east boundary of the site. Any fencing in the overland flow path must be open at the bottom for 100mm minimum, and with a minimum of 50% openings above that. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
50(a) Certification Submit to Development
Services certification from a Registered Professional Engineer Queensland that
the development has been constructed in accordance with the approved flood
study. |
As indicated |
| 51) Refuse Collection - Kerb Side (external road or
internal private road) Refuse and recycling bins for the proposed development must be collected from the kerb side by Private Contractor. However, bins must not be left unattended kerbside, generally in accordance with the Waste collection proposal outlined in the approved waste assessment letter prepared by TTM dated 10/3/2020. Waste collection must be undertaken twice weekly as a minimum and bin numbers must be minimised/restricted so they do not impact on neighbours frontage |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 52) Refuse Storage - Kerb Side Collection Provide a covered and screened
waste enclosure to accommodate the type and quantity of waste/recycling bins
required to service the development. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 53) Land for Transport Network - Road (Non-
trunk) Dedicate as road including the following: |
As indicated |
53(a) Submit Plan of Subdivision (MCU
only) Submit
for the approval of Development Services, a plan of subdivision showing the
land to be dedicated for road to demonstrate compliance with the requirements
of this condition. |
As indicated |
53(b) Lodge Notated Plan (MCU
only) Lodge
the plan of subdivision notated by Council pursuant to Schedule 18 of the
Planning Regulation 2017 with the Registrar of Titles for the relevant
Queensland State Government Authority. |
As indicated |
53(c) Submit Evidence of Registration (MCU
only) Submit
to Development Services, evidence of the registration of the required plan of
subdivision. |
As indicated |
| 54) Work for Transport Network - Road (Non-trunk) -
External Construct the following roadwork with any associated
drainage, footpath, site access and services including street lighting for the
Transport Network (Road) in accordance with the relevant Brisbane Planning
Scheme Codes, the Manual of Uniform Traffic Control Devices - Queensland
Department of Transport and Main Roads - Transport Operations (Road Use
Management) Act 1995 and the AUSTROADS design standards: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
54(a) Submit Street Lighting Design
Drawings Submit for the approval of City Lighting, street lighting design drawings prepared and certified by a Registered Professional Engineer of Queensland (electrical) which show the proposed street lighting system in accordance with the relevant Brisbane Planning Scheme Codes.
Timing: Prior to site/operational/building work commencing. |
As indicated |
54(b) Pre-Start Meeting Arrange and attend a pre-start meeting with Development Services.
Timing: Prior to site/operational work commencing. |
As indicated |
54(c) Implement Approved
Drawings Construct the works in accordance with the above approved drawings. Timing: Prior to on-maintenance acceptance. |
As indicated |
54(d) Submit As Constructed
Drawings Submit to Development Services "As Constructed" drawings including an asset register and a pre-On-Maintenance Inspection Checklist, prepared by a Registered Professional Engineer Queensland.
Timing: Prior to on-maintenance inspection. |
As indicated |
54(e) Submit Certification Submit to Development Services
certification from a Registered Professional Engineer Queensland, confirming
that the works have been completed in accordance with the above approved
drawings. |
As indicated |
| 55) Lawful Point Of Discharge Submit to Development Services, evidence of written consent for a
lawful point of discharge from the owners of properties affected by any
stormwater discharge from the site. |
Prior to site/operational/building work commencing |
| 56) Ponding of Stormwater Carry out the approved development to ensure that
adjoining properties and roads are protected from ponding or nuisance from
stormwater as a result of the works. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 57) On Site Drainage - Minor Provide a stormwater connection to all new or existing allotments and provide drainage infrastructure to ensure stormwater run-off from all roof and developed surface areas will be collected internally and piped in accordance with the relevant Brisbane Planning Scheme Codes to a lawful point of discharge. The LPD for the front dwelling is the kerb/channel in Picot Street, and
the LPD for the rest of the site is the existing stormwater pipe infrastructure
in the neighbours property. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
57(a) Submit As Constructed
Drawings Where
reconfiguring a lot, submit to Development Services "As Constructed"
drawings prepared by a Registered Professional Engineer Queensland. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
57(b) Submit Certification Where reconfiguring a lot, submit to Development Services certification
from a Registered Professional Engineer Queensland, confirming that the works
have been completed in accordance with this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
| 58) Up Stream Stormwater Drainage Connection -
Minor Provide a stormwater drainage connection for the future development of
the adjoining upstream property at the south boundary designed for ultimate
developed catchment conditions and connected to a lawful point of discharge.
This pipe must be located in a 0.9 metre wide underground drainage
easement. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
58(a) Prepare Stormwater
Drawings Prepare stormwater
drawings and engineering calculations, certified by a Registered Professional
Engineer Queensland in accordance with the relevant Brisbane Planning Scheme
Codes. |
As indicated |
58(b) Implement Certified Stormwater
Drawings Carry out the
works in accordance with the above stormwater drawings. |
As indicated |
58(c) Submit As Constructed
Drawings Submit to Development Services "As Constructed" drawings
prepared by a Registered Professional Engineer Queensland. |
As indicated |
58(d) Submit Certification Submit to Development Services certification from a Registered
Professional Engineer Queensland, confirming that the works have been completed
in accordance with the above stormwater drawings. |
As indicated |
| 59) Service Conduits and Mains Provide and install all
service conduits and meet the cost of any alterations to public utility mains,
existing mains, services, street lighting or installations that are required to
carry out the approved development. These works must be in accordance with the
relevant Brisbane Planning Scheme Codes, and include the following, where
applicable: Note:
- The cost of moving services, utilities and assets is the responsibility of
the Developer. The permission of the service, utility or asset owner will be
required. Council permission is required if street trees, stormwater
gullies/drains, and swales are affected. Queensland Urban Utilities permission
is required if water supply and sewerage services are affected
|
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
59(a) Submit As Constructed
Drawings Submit to Development Services "As
Constructed" drawings, including an asset register, prepared by a
Registered Professional Engineer Queensland. |
As indicated |
59(b) Submit Certification Submit to Development
Services certification from a Registered Professional Engineer Queensland,
confirming that the works have been completed in accordance with the
requirements of this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 60) Telecommunications Submit to Development Services, certification from
an authorised telecommunications carrier/contractor, that the following works
and infrastructure have been undertaken and installed in accordance with
telecommunications industry standards: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 61) Agreement with Electricity Supplier Submit to Development Services, evidence of an agreement with an electricity supplier to provide necessary services to the development in accordance with the relevant Brisbane Planning Scheme Codes. Where development is proposed within an established area of overhead electricity supply and the electricity supplier determines that a property pole is the appropriate solution to supply electricity to the development, the developer must be responsible for the installation of the property pole(s). In the above circumstances, submit to Development Services, certification from the developer’s electrical consultant confirming that the above installation has been completed in accordance with the relevant AS/NZS Standards and the Queensland Electrical Connection and Metering Manual. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 62) Permanent Vehicle Crossover Provide a 3.650 metre wide modified type B1 permanent vehicle crossover to the Picot Street frontage(s) of the site in accordance with the relevant Brisbane Planning Scheme Codes and located as shown on the approved DRAWINGS AND DOCUMENTS. Written consent must be obtained from BCC – Field Services, Asset Services Arborist prior to any works occurring that will either impact on or require removal of a street tree (this includes pruning and excavation within the root zone/ canopy of the tree) At all times during construction of the crossover, safe pedestrian access along the site frontage must be maintained. Note: No further driveway permit is required however additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 63) Redundant Crossover Remove the redundant existing vehicle crossing(s) on
the frontage(s) of the site and reinstate the kerb and channel, road pavement,
footways and footpaths in accordance with the relevant Brisbane Planning Scheme
Codes. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 64) Construction Noise and Dust Emissions Pursuant to the Environmental
Protection Act 1994, all development involving the emission of noise and dust
from building and/or construction activities, must ensure that the emissions
are in accordance with the requirements of the Act. |
As indicated |
| 65) Currency Period The currency period for this development approval is stated in the Decision Notice and is expressed as a date. This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016. |
As indicated |
| 66) Cultural Heritage Aboriginal cultural heritage is protected under the Aboriginal Cultural Heritage Act 2003. This Act establishes a cultural heritage duty of care and in section 23(1) mandates that a person who carries out an activity must take all reasonable and practicable measures for ensuring activities are managed to avoid or minimise harm to Aboriginal cultural heritage. The Duty of Care Guidelines gazetted pursuant to the Aboriginal Cultural Heritage Act 2003 provide guidance on identifying and protecting Aboriginal cultural heritage to fulfil the duty of care. For further information contact the relevant Queensland State Government Department (Department of Aboriginal and Torres Strait Islander Partnerships). |
As indicated |
| 67) Damage to Trees on Adjoining Land Please note that any damage caused to vegetation on adjoining land as a result of exercising this development approval may result in an offence under other legislation (e.g. Natural Assets Local Law) and/or civil action |
As indicated |
| 68) Fire Ant Movement Controls To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected. These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products. Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014. For further information contact the relevant Queensland State Government department on 13 QGOV. |
As indicated |
| 69) Rooming Accommodation - Self-contained unit This approval does not authorise any resident, tenant or provider to occupy a self-contained unit as defined under the Residential Tenancies and Rooming Accommodation Act 2008. Each room identified within the building/s is not to form a self- contained unit which includes a kitchen (cooking facilities), bathroom and toilet facilities. |
As indicated |
| 70) Water and Wastewater Services for water and wastewater (sewerage) are no longer under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections requires a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. Any necessary Water Approval must be obtained from the relevant distributor- retailer (currently operating as Queensland Urban Utilities for the Brisbane City Council area). For the purpose of approving plans of subdivision pursuant to Schedule 18 of the Planning Regulation 2017 (whether in relation to a development permit for Reconfiguring a Lot or a Building Format Plan subsequent to a development permit for a Material Change of Use), documentary evidence, issued by the relevant distributor-retailer, must be provided to Council to verify that the conditions of any necessary Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009, have been complied with. |
As indicated |
| Permit to Which These Conditions Relate: | DA - PA - Building Work |
| Activity(ies): | rooming accommodation |
| Stage: | Rooming accommodation in the Traditional building character overlay |
| 71) Maintain the Approved Development Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions. |
At all times |
| 72) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers. Note: This condition is imposed to ensure compliance with the conditions of development approval. |
While site/operational/building work is occurring |
| 73) Carry Out the Approved Development Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS. Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners. |
While site/operational/building work is occurring |
| 74) Complete All Building Work Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS. Note: Building work must also be completed in accordance with any other current development approval. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 75) Visitor Parking Visitor car parking spaces must: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 76) Outdoor lighting Outdoor lighting is to be in compliance with AS 4282-1997 - Control of the obtrusive effects of outdoor lighting. |
At all times |
| 77) Limitation of use The approved Rooming accommodation must operate in accordance with the definition of ‘suite’ in the Brisbane Infrastructure Charges Resolution (No. 9) 2020, as detailed below: ‘Suite’ means a number of connected rooms one of which is a bedroom in which an individual or a group of two or more related or unrelated people reside with the common intention to live together on a long term basis and who make common provision for food or other essentials for living. The approved Rooming accommodation is to have a maximum of 4 dwelling suites with a total of 24 rooms.
|
Prior to the commencement of the use and then to be maintained |
| 78) External Details External details of the building, facade treatment and external materials and finishes must be consistent with the approved DRAWINGS AND DOCUMENTS. Note: The requirement to use particular materials and finishes is imposed only for the purpose of achieving a built form outcome that displays architectural merit. Council has not assessed the materials and finishes for compliance with the Building Act, the Building Fire Safety Regulation, the Building Regulation, the Building Code of Australia, the Queensland Development Code, relevant Australian Standards, fire safety standards or any other relevant requirement of a statutory authority with regard to building work. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 79) Overall Height The overall height of the building(s) must be in accordance with the floor and roof levels and overall height shown on the APPROVED DRAWINGS AND DOCUMENTS. NOTE: Where there is a conflict with the floor heights shown on the APPROVED DRAWINGS and the conditions in this approval that stipulate minimum height clearance for undercover car parking, the height clearance conditions prevail. |
While site/operational/building work is occurring and then to be maintained |
79(a) Submit Certification Submit to Development Services certification from a registered surveyor confirming that the 'as constructed' floor and roof levels and overall height are in accordance with the requirements of this condition. Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 80) Provide Pedestrian Prioritised Pathway Provide a pedestrian prioritised pathway from the street frontage to Buildings A, B, C and D. The pathway must be differentiated in colour and texture from the driveway surface. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 81) Screen Air Conditioning and Other Plant
Enclosures Install and maintain suitable screening to all air conditioning, lift
motor rooms, plant and service facilities located at the top of or on the
external face of the building. The screening structures must be constructed
from materials that are consistent with materials used elsewhere on the facade
of the building. There must be no individual external air conditioning units
located on balconies. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 82) Screening Provide screening to windows of habitable rooms, balconies, landings, terraces and decks of the proposed dwelling(s) in accordance with the approved DRAWINGS AND DOCUMENTS and the following requirements. Where any windows of habitable rooms of the proposed dwelling(s) are within 2m at ground floor level or 9m above ground floor level of adjoining neighbouring dwellings' windows to habitable rooms, provide suitable screening in accordance with the following: Suitable screening must be: For windows: For balconies, landings, terraces
and decks facing the side boundaries of the site: Note: Screening devices must be either solid translucent screens, perforated or slatted panels, or fixed louvres that are permanent, be durable and fixed. Screening devices must have a maximum of 25% openings, with a maximum opening of 50mm. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 83) Streetscape Works - Neighbourhood Street Carry out streetscape improvement works including concrete path, turf and street trees to the verge to a Neighbourhood Street Minor standard in accordance with the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD), the requirements of this condition and the Infrastructure Design Planning Scheme Policy including sections 3.7.4.4 and 3.7.5. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
83(a) Concrete Path Install a 1.2m wide broom finished standard Portland grey concrete
path. The path on the southern side of the driveway is to be setback 1.3m from
the back of kerb. The path on the northern side of the driveway is to align
with the existing path on the verge that adjoins the development to the
north. Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL). |
As indicated |
83(b) Submit As-Constructed
Drawings Submit
to Development Services "As Constructed" plans including an asset
register, checked by a Registered Professional Engineer Queensland, certifying
that the concrete path works have been completed in accordance with relevant
Brisbane Planning Scheme Codes/Policies. |
As indicated |
83(c) Turf Install turf to the full
width of the verge excluding any concrete path required by this condition. |
As indicated |
| 84) Landscape the Site - Self Certification Landscape the site in accordance with the requirements of this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
84(a) Detailed Landscape Plan for Self
Certification Prepare a Detailed Landscape Plan at a scale of 1:100 for all on-site landscape works including planting areas identified on the approved DRAWINGS AND DOCUMENTS. The plan must be prepared by a Registered Landscape Architect and must comply with the relevant Brisbane Planning Scheme Codes. In addition to the requirements listed above, the plan must include the following: . Deep planting areas · Deep planting areas as shown on the approved drawings, open to the sky and with no underground development including retaining wall footings with the exception of existing underground infrastructure. · Provide tree planting in accordance with the approved drawing numbered 2.10 Issue J, received 2 April 2026 and amended in red 23 April 2026.
Side and rear boundaries · Provide tree planting in accordance with the approved drawing numbered 2.10 Issue J, received 2 April 2026 and amended in red 23 April 2026. Containerised planting · Clear identification of the location, width and depth of containerised planting. · Minimum internal depths and widths as shown on approved plans · A reticulated drip irrigation system to all containerised planting areas, with drainage connected to the stormwater system; the irrigation system must be connected to a non-mains water source. Specifications · Plant selection and densities to achieve full surface coverage within 2 years of planting · Unless otherwise specified, trees provided as 45 litre stock or larger, staked and tied, and complying with Australian Standards · Mulch and soil to all garden areas to meet Australian Standards · Soil media ameliorated to increase water-holding abilities · Details of a 12-week establishment period. Timing: Prior to building work commencing.
|
As indicated |
84(b) Certify Detailed Landscape
Plan On completion of the Detailed Landscape Plan, submit to Development Services: · Brisbane City Council Form CC10616 - Landscape Design Certificate prepared by a Registered Landscape Architect to certify that the Detailed Landscape Plan complies with the requirements of this condition · A copy of the certified Detailed Landscape Plan. Timing: Prior to building work commencing. |
As indicated |
84(c) Implement Certified Detailed Landscape
Plan Carry out the landscape work in accordance with the above certified detailed Landscape Plan.
Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
84(d) Certify Work On completion of the landscape work, submit to Development Services: · Brisbane City Council Form CC10613 - Landscape Works Certificate prepared by a Registered Landscape Architect or licensed Landscape Contractor to certify the completed landscape work complies with the certified Detailed Landscape Plan · A copy of the as- constructed certified Detailed Landscape Plan.
Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first.
|
As indicated |
84(e) Maintain Landscape Work Maintain the landscape work generally in accordance with the certified Detailed Landscape Plan.
Timing: To be maintained. |
As indicated |
| 85) Air Emissions
Vehicle exhaust fumes are released via exhaust vent outlets which are
directed away from any sensitive use and include the
following:
- air emissions are not to cause an odour or air emission which is detectable and disturbing at a sensitive use; and - ensures that exhaust vents from any basement/enclosed car park are separated from any sensitive use by a minimum of 15m and 6m from intakes and natural ventilation openings.
|
Prior to the commencement of the use and then to be maintained |
| 86) Acoustic Fence - General Erect a 2.0m high (relative to the finished RL of the driveway /
pathway) acoustic fence along the northern and southern boundaries of the site
adjacent to the driveway / pathway as shown on the approved drawings numbered
2.10 Issue J, received 2 April 2026 and amended in red 23 April 2026. The
acoustic fencing must:
|
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
86(a) Certification Submit to Development Services certification from a person who is a Member or eligible to be a Member of the Australian Acoustic Society that the constructed acoustic fence complies with the above requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 87) Dampening of Grilles and Metal Plates All metal grilles, metal plates or similar located within vehicle parking and manoeuvring areas must be securely fastened and meet the requirements of AS3996:2019, Access covers and grates. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 88) Plant and Equipment Certification Following the installation of all mechanical
plant and equipment (e.g. air conditioning, mechanical ventilation and
refrigeration equipment and heat pump hot water systems), submit to Development
Assessment certification that the plant and equipment is adequately noise-
attenuated and is in accordance with the criteria of the relevant Brisbane
Planning Scheme Codes/Policies. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 89) Retaining Walls Design and construct all
retaining walls and associated fences, in accordance with the relevant Brisbane
Planning Scheme Codes and including the following: |
As indicated |
89(a) Certification of Retaining
Walls For
retaining walls over 1.0m in height, obtain certification from a Registered
Professional Engineer Queensland that the design and construction of the
retaining wall and ancillary drainage is in accordance with this condition. |
As indicated |
| 90) Grant Easements Grant the following easement(s): |
As indicated |
90(a) Submit Plan of Subdivision and
Documentation (Non-Council Easement) Submit for the approval of Development Services, a
plan of subdivision showing the easement and the necessary easement
documentation to demonstrate compliance with the requirements of this
condition. |
As indicated |
90(b) Submit Plan of Subdivision and
Documentation (Council Easement) Submit for the approval of Development Services, a
plan of subdivision showing the easement and a request for Council to prepare
the necessary easement documentation to demonstrate compliance with the
requirements of this condition. |
As indicated |
90(c) Lodge Notated Plan and
Documentation Lodge
the plan of subdivision notated by Council pursuant to Schedule 18 of the
Planning Regulation 2017 and the necessary easement documentation with the
Registrar of Titles for the relevant Queensland State Government Authority. |
As indicated |
90(d) Submit Evidence of
Registration Submit
to Development Services evidence of the registration of the necessary easement
documentation. |
As indicated |
| 91) On-site Erosion (medium risk) Minimise on-site erosion and
the release of sediment or sediment laden stormwater from the site at all
times. |
As indicated |
91(a) Prepare Erosion and Sediment Control
Plan Prepare
Erosion and Sediment Control (ESC) Plan(s), and provide design certificates for
the site in accordance with the relevant Brisbane Planning Scheme Codes. |
As indicated |
91(b) Attend a Pre-Start
meeting Arrange and attend a pre-start meeting with an Erosion & Sediment
Control Officer from Council’s Compliance and Regulatory Services.
Requests are to be made when submitting copies of all required documentation,
including design certificates to: CARS-ESC@brisbane.qld.gov.au |
As indicated |
91(c) Implement Certified Erosion and
Sediment Control Plan Implement the certified ESC plan(s) to maintain compliance with all
parts of the relevant Brisbane Planning Scheme Codes, while site works are
occurring and until all exposed soil areas are permanently stabilised against
erosion. |
As indicated |
| 92) Information Signage Erect an "Information Sign" on the subject property in accordance with Council’s general requirements for signage and in accordance with the requirements outlined below: a) The sign should provide a brief description of the development
proposed; |
As indicated |
| 93) Construction Management Plan (Minor) Carry out development in accordance with a Construction Management Plan (Minor) prepared in accordance with the requirements of this condition. |
While site/operational/building work is occurring |
93(a) Prepare Management Plan
(minor) Prepare a Construction Management Plan for the subject site.
The Construction Management Plan must be available on site at all times and must show, but not be limited to the following details where applicable, for the demolition (where in a Centre zone, a Mixed use zone or where the demolition is otherwise assessable development), excavation and construction phases of the approved development. Separate Construction Management Plans may be appropriate for the individual components:
- Provision of alternative pedestrian route/s, past or around the site - Existing and proposed kerbside allocation signs and line marking (such as bus stops, loading zones and parking meters and/or ticket dispensers) - Temporary vehicular access points - Management and mitigation strategies for the impact of dust, noise and vibration upon adjoining and nearby properties - Employee and visitor parking areas (if provided) - Provision for loading and unloading materials including the location of any remote loading sites - The location of materials, structures, plant and equipment to be stored or placed on the construction site - The anticipated staging and programming - Allowable work times as set by the Queensland Environmental Protection Act 1994 (section 440). A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management Delegate Development Services.
The Construction Management Plan must be supported by Permits or written approvals from the relevant Council sections or other body listed below (where applicable to the Plan) to ensure all potential impacts to Council and other infrastructure have been addressed: (i) Work Zones / Temporary Road Closures / Taxi Ranks - (Congestion Reduction Unit, Planned Incident Management / Temporary Road Closures); (ii) Full/Partial Footway-Footpath Closures – (Brisbane Infrastructure – Congestion Reduction Unit); (iii) Street Lighting - (Brisbane Infrastructure - Asset Services-City Lighting); (iv) City Cycle bike stations and JCDecaux Advertising Signage (including obstruction to sight lines for such advertising - owned by JCDecaux)- (Brisbane Infrastructure - Transport Planning and Strategy, Contract Management section); (v) Street Furniture (excluding bus stops) - (Brisbane Infrastructure, Transport Network Operations, Roads and Drainage); (vi) Waste Bins - (Brisbane Infrastructure, Waste Service); (vii) Bus Stops/Shelters - (Brisbane infrastructure - Transport Planning and Strategy-Strategic Planning; and Brisbane Transport - Network Planning & Bus Operations); (viii) Street Trees - (Brisbane Infrastructure - Asset Services - Arboriculture); (ix) Parking Meters/Spaces - (Brisbane Infrastructure - City Parking); (x) Traffic Signals - (Brisbane Infrastructure - Traffic Signals Operations); (xi) Stormwater Gullies/Pits etc - (Brisbane Infrastructure - Roads and Drainage); (xii) Other service providers - (e.g. Energex, Telstra, Optus, Queensland Urban Utilities, AGL).
Note: The Construction Management Plan is not required to be approved by Development Services.
At least 10 days prior to commencement of site works, submit a copy of the Construction Management Plan to Council’s Development Services Branch at the following mailbox: engineeringservices@brisbane.qld.gov.au quoting the planning development approval reference number.
Timing: Prior to site/operational/building work commencing |
As indicated |
93(b) Construction Management Plan (Minor) -
Documentation on Site Legible copies
of the Construction Management Plan and current permits must be kept on site
and be made available on request at all times. |
As indicated |
93(c) Construction Management Plan (Minor) -
Works to be Performed Out of Hours Obtain approval from Development Services for any work that is proposed
to be undertaken outside of normal business hours - 6:30am to 6:30pm, Monday to
Saturday. |
As indicated |
93(d) Implement Construction Management Plan
(Minor) Carry out the
development in accordance with the Construction Management Plan prepared in
accordance with this condition. |
As indicated |
| 94) Protect Existing Infrastructure Where there is existing infrastructure in the vicinity of the proposed
work, the new work must not damage or compromise the working ability of the
existing infrastructure. Where alterations to public utility mains, existing
mains, services or installations are necessitated by the development, prior to
alterations commencing, the developer must notify Council or the relevant
infrastructure provider and obtain agreement to the alterations. The developer
must meet the costs of the alterations. The alterations must be carried out in
accordance with the relevant Brisbane Planning Scheme Codes or infrastructure
providers requirements. |
While site/operational/building work is occurring |
94(a) As Constructed Drawings Where alterations to
existing infrastructure are required, submit to Development Services "As
Constructed" drawings showing all new and/or rectification works and an
asset register, prepared by a Registered Professional Engineer Queensland. |
As indicated |
94(b) Submit Certification Where alterations to existing
infrastructure are required, submit to Development Services certification from
a Registered Professional Engineer Queensland, confirming that the alterations
have been completed in accordance with the relevant Brisbane Planning Scheme
Codes and any other relevant infrastructure requirements. |
As indicated |
| 95) Remove Improvements & Obstructions From Truncation
and Dedication Remove all improvements (fences, gates, letter boxes, garden beds and plots and other constructed items, etc.) and obstructions (existing earth banks, vegetation, etc.) from the area of the dedicated road and reinstate the area as footway in accordance with the relevant Brisbane Planning Scheme Codes. Any new or existing installations of electrical pillar boxes, pad mounted transformers (PMTs), water meters and the like, must be installed/relocated to their ultimate alignment relative to the new property boundary and clear of the usable footpath areas irrespective of the alignment of the existing services/conduits. Note: - The cost of moving services, utilities and assets is the responsibility of the Developer. The permission of the service, utility or asset owner will be required. Council permission is required if street trees, stormwater gullies/drains, and swales are affected. Queensland Urban Utilities permission is required if water supply and sewerage services are affected   ; - Standard utility alignments may be found on Council’s ‘Brisbane Standard Drawings’ 1013 to 1016 inclusive. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
95(a) Certify the Work Submit to Development
Services certification from a Registered Surveyor or Registered Professional
Engineer Queensland that the above work has been completed in accordance with
this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 96) Filling and / or Excavation (Minor) Filling and/or excavation works on the site must be in accordance with the relevant Brisbane Planning Scheme Codes. No earthworks whether cut or fill are to be undertaken within the new 6 metre wide overland flow easement at the east boundary of the site. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
96(a) Prepare Earthworks
Drawings Earthworks drawings must be prepared and certified by either: a
Registered Professional Engineer Queensland or a suitably qualified
geotechnical and structural consultant, in accordance with the relevant
Brisbane Planning Scheme Codes. |
As indicated |
96(b) Implement and Maintain the
Earthworks Carry
out and maintain the earthworks in accordance with the certified drawings. |
As indicated |
| 97) Repair Damage to Kerb, Footpath Or Road Repair any damage to the
existing kerb and channel, footpath or roadway (including removal of concrete
slurry from footways, roads, kerb and channel, stormwater gullies and
drainlines) and re-instate existing traffic signs and pavement markings that
have been removed or damaged during any works carried out in association with
the approved development. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
97(a) Interim Repairs If at any time during the construction phase of the
approved development, damage to the existing kerb and channel, footpath or
roadway creates unsafe, unreasonable and/or not fit for purpose conditions as
assessed by Council, interim repairs must be undertaken as directed by Asset
Services. Note: Any interim repairs required to be undertaken shall not be
considered to satisfy the requirements of this condition for the permanent
repair of the infrastructure prior to the issue of Certificate of
Classification/Final Inspection Certificate or prior to commencement of use,
whichever comes first (MCU or BW), or prior to Council's notation of the plan
of subdivision (ROL). Timing: While site / operational / building works is
occurring |
As indicated |
| 98) Remove Redundant Drainage Outlets Remove any redundant drainage outlets from the kerb and channel
including any associated pipe work across the footway and reinstate the kerb
and channel and the footway area in accordance with the relevant Brisbane
Planning Scheme Codes. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 99) Access, Grades, Manoeuvring, Carparks, Signs and
Line Marking Construct access, parking and manoeuvring for
vehicles on site in accordance with the relevant Brisbane Planning Scheme
Codes, as indicated on the approved DRAWINGS AND DOCUMENTS, including the
following: iv. A minimum of
2.3 metres height clearance to all undercover parking areas and a minimum of
2.5 metres above parking spaces for people with disabilities. The minimum
clear height must be measured to the lowest protrusion from the ceiling (e.g.
fire sprinklers, services, lighting fixtures, signs, etc). |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
99(a) Submit certification Submit to Development
Services, certification from a Registered Professional Engineer Queensland,
that the above requirements have been implemented in accordance with this
condition. |
As indicated |
| 100) Minimum Flood Planning Levels Design and construct
all proposed building pad levels, floor levels and ancillary structures to the
appropriate flood planning level with freeboard (where required) in accordance
with the relevant Brisbane Planning Scheme Codes. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
100(a) Submit Certification Submit to Development Services "As-Constructed" drawings
prepared by a Registered Surveyor. The Registered Surveyor must certify that
the development has been constructed in accordance with this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
| 101) Stormwater - Flood Study Construct the development in accordance with the approved Flood Investigation Report prepared by HCE Engineers numbered 19123 Rev 0, received 6 November 2019. No earthworks including cut or fill are to be undertaken within the new 6 metre wide overland flow easement at the east boundary of the site. Any fencing in the overland flow path must be open at the bottom for 100mm minimum, and with a minimum of 50% openings above that. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
101(a) Certification Submit to Development
Services certification from a Registered Professional Engineer Queensland that
the development has been constructed in accordance with the approved flood
study. |
As indicated |
| 102) Refuse Collection - Kerb Side (external road or
internal private road) Refuse and recycling bins for the proposed development must be collected from the kerb side by Private Contractor. However, bins must not be left unattended kerbside, generally in accordance with the Waste collection proposal outlined in the approved waste assessment letter prepared by TTM dated 10/3/2020. Waste collection must be undertaken twice weekly as a minimum and bin numbers must be minimised/restricted so they do not impact on neighbours frontage |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 103) Refuse Storage - Kerb Side Collection Provide a covered and screened
waste enclosure to accommodate the type and quantity of waste/recycling bins
required to service the development. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 104) Land for Transport Network - Road (Non-
trunk) Dedicate as road including the following: |
As indicated |
104(a) Submit Plan of Subdivision (MCU
only) Submit
for the approval of Development Services, a plan of subdivision showing the
land to be dedicated for road to demonstrate compliance with the requirements
of this condition. |
As indicated |
104(b) Lodge Notated Plan (MCU
only) Lodge
the plan of subdivision notated by Council pursuant to Schedule 18 of the
Planning Regulation 2017 with the Registrar of Titles for the relevant
Queensland State Government Authority. |
As indicated |
104(c) Submit Evidence of Registration (MCU
only) Submit
to Development Services, evidence of the registration of the required plan of
subdivision. |
As indicated |
| 105) Work for Transport Network - Road (Non-trunk) -
External Construct the following roadwork with any associated
drainage, footpath, site access and services including street lighting for the
Transport Network (Road) in accordance with the relevant Brisbane Planning
Scheme Codes, the Manual of Uniform Traffic Control Devices - Queensland
Department of Transport and Main Roads - Transport Operations (Road Use
Management) Act 1995 and the AUSTROADS design standards: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
105(a) Submit Street Lighting Design
Drawings Submit for the approval of City Lighting, street lighting design drawings prepared and certified by a Registered Professional Engineer of Queensland (electrical) which show the proposed street lighting system in accordance with the relevant Brisbane Planning Scheme Codes.
Timing: Prior to site/operational/building work commencing. |
As indicated |
105(b) Pre-Start Meeting Arrange and attend a pre-start meeting with Development Services.
Timing: Prior to site/operational work commencing. |
As indicated |
105(c) Implement Approved
Drawings Construct the works in accordance with the above approved drawings. Timing: Prior to on-maintenance acceptance. |
As indicated |
105(d) Submit As Constructed
Drawings Submit to Development Services "As Constructed" drawings including an asset register and a pre-On-Maintenance Inspection Checklist, prepared by a Registered Professional Engineer Queensland.
Timing: Prior to on-maintenance inspection. |
As indicated |
105(e) Submit Certification Submit to Development Services
certification from a Registered Professional Engineer Queensland, confirming
that the works have been completed in accordance with the above approved
drawings. |
As indicated |
| 106) Lawful Point Of Discharge Submit to Development Services, evidence of written consent for a
lawful point of discharge from the owners of properties affected by any
stormwater discharge from the site. |
Prior to site/operational/building work commencing |
| 107) Ponding of Stormwater Carry out the approved
development to ensure that adjoining properties and roads are protected from
ponding or nuisance from stormwater as a result of the works. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 108) On Site Drainage - Minor Provide a stormwater connection to all new or existing allotments and provide drainage infrastructure to ensure stormwater run-off from all roof and developed surface areas will be collected internally and piped in accordance with the relevant Brisbane Planning Scheme Codes to a lawful point of discharge. The LPD for the front dwelling is the kerb/channel in Picot Street, and
the LPD for the rest of the site is the existing stormwater pipe infrastructure
in the neighbours property. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
108(a) Submit As Constructed
Drawings Where
reconfiguring a lot, submit to Development Services "As Constructed"
drawings prepared by a Registered Professional Engineer Queensland. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
108(b) Submit Certification Where reconfiguring a lot, submit to Development Services certification
from a Registered Professional Engineer Queensland, confirming that the works
have been completed in accordance with this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
| 109) Up Stream Stormwater Drainage Connection -
Minor Provide a stormwater drainage connection for the future development of
the adjoining upstream property at the south boundary designed for ultimate
developed catchment conditions and connected to a lawful point of discharge.
This pipe must be located in a 0.9 metre wide underground drainage
easement. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
109(a) Prepare Stormwater
Drawings Prepare stormwater
drawings and engineering calculations, certified by a Registered Professional
Engineer Queensland in accordance with the relevant Brisbane Planning Scheme
Codes. |
As indicated |
109(b) Implement Certified Stormwater
Drawings Carry out the
works in accordance with the above stormwater drawings. |
As indicated |
109(c) Submit As Constructed
Drawings Submit to Development Services "As Constructed" drawings
prepared by a Registered Professional Engineer Queensland. |
As indicated |
109(d) Submit Certification Submit to Development Services certification from a Registered
Professional Engineer Queensland, confirming that the works have been completed
in accordance with the above stormwater drawings. |
As indicated |
| 110) Service Conduits and Mains Provide and install all
service conduits and meet the cost of any alterations to public utility mains,
existing mains, services, street lighting or installations that are required to
carry out the approved development. These works must be in accordance with the
relevant Brisbane Planning Scheme Codes, and include the following, where
applicable: Note:
- The cost of moving services, utilities and assets is the responsibility of
the Developer. The permission of the service, utility or asset owner will be
required. Council permission is required if street trees, stormwater
gullies/drains, and swales are affected. Queensland Urban Utilities permission
is required if water supply and sewerage services are affected
|
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
110(a) Submit As Constructed
Drawings Submit to Development Services "As
Constructed" drawings, including an asset register, prepared by a
Registered Professional Engineer Queensland. |
As indicated |
110(b) Submit Certification Submit to Development
Services certification from a Registered Professional Engineer Queensland,
confirming that the works have been completed in accordance with the
requirements of this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 111) Telecommunications Submit to Development Services, certification from
an authorised telecommunications carrier/contractor, that the following works
and infrastructure have been undertaken and installed in accordance with
telecommunications industry standards: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 112) Agreement with Electricity Supplier Submit to Development Services, evidence of an agreement with an electricity supplier to provide necessary services to the development in accordance with the relevant Brisbane Planning Scheme Codes. Where development is proposed within an established area of overhead electricity supply and the electricity supplier determines that a property pole is the appropriate solution to supply electricity to the development, the developer must be responsible for the installation of the property pole(s). In the above circumstances, submit to Development Services, certification from the developer’s electrical consultant confirming that the above installation has been completed in accordance with the relevant AS/NZS Standards and the Queensland Electrical Connection and Metering Manual. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 113) Permanent Vehicle Crossover Provide a 3.65 metre wide modified type B1 permanent vehicle crossover to the Picot Street frontage(s) of the site in accordance with the relevant Brisbane Planning Scheme Codes and located as shown on the approved DRAWINGS AND DOCUMENTS. Written consent must be obtained from BCC – Field Services, Asset Services Arborist prior to any works occurring that will either impact on or require removal of a street tree (this includes pruning and excavation within the root zone/ canopy of the tree) At all times during construction of the crossover, safe pedestrian access along the site frontage must be maintained. Note: No further driveway permit is required however additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 114) Redundant Crossover Remove the redundant existing vehicle crossing(s) on
the frontage(s) of the site and reinstate the kerb and channel, road pavement,
footways and footpaths in accordance with the relevant Brisbane Planning Scheme
Codes. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 115) Construction Noise and Dust Emissions Pursuant to the Environmental
Protection Act 1994, all development involving the emission of noise and dust
from building and/or construction activities, must ensure that the emissions
are in accordance with the requirements of the Act. |
As indicated |
| 116) Currency Period The currency period for this development approval is stated in the Decision Notice and is expressed as a date. This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016. |
As indicated |
| 117) Cultural Heritage Aboriginal cultural heritage is protected under the Aboriginal Cultural Heritage Act 2003. This Act establishes a cultural heritage duty of care and in section 23(1) mandates that a person who carries out an activity must take all reasonable and practicable measures for ensuring activities are managed to avoid or minimise harm to Aboriginal cultural heritage. The Duty of Care Guidelines gazetted pursuant to the Aboriginal Cultural Heritage Act 2003 provide guidance on identifying and protecting Aboriginal cultural heritage to fulfil the duty of care. For further information contact the relevant Queensland State Government Department (Department of Aboriginal and Torres Strait Islander Partnerships). |
As indicated |
| 118) Damage to Trees on Adjoining Land Please note that any damage caused to vegetation on adjoining land as a result of exercising this development approval may result in an offence under other legislation (e.g. Natural Assets Local Law) and/or civil action |
As indicated |
| 119) Fire Ant Movement Controls To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected. These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products. Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014. For further information contact the relevant Queensland State Government department on 13 QGOV. |
As indicated |
| 120) Rooming Accommodation - Self-contained
unit This approval does not authorise any resident, tenant or provider to occupy a self-contained unit as defined under the Residential Tenancies and Rooming Accommodation Act 2008. Each room identified within the building/s is not to form a self-contained unit which includes a kitchen (cooking facilities), bathroom and toilet facilities. |
As indicated |
| 121) Water and Wastewater Services for water and wastewater (sewerage) are no longer under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections requires a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. Any necessary Water Approval must be obtained from the relevant distributor- retailer (currently operating as Queensland Urban Utilities for the Brisbane City Council area). For the purpose of approving plans of subdivision pursuant to Schedule 18 of the Planning Regulation 2017 (whether in relation to a development permit for Reconfiguring a Lot or a Building Format Plan subsequent to a development permit for a Material Change of Use), documentary evidence, issued by the relevant distributor-retailer, must be provided to Council to verify that the conditions of any necessary Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009, have been complied with. |
As indicated |