BRISBANE CITY COUNCIL'S APPROVAL PACKAGE.



APPLICATION DETAILS

This package relates to the application detailed below
Address of Site: 11 PICOT ST KELVIN GROVE QLD 4059
Real Property Description of Site: L10 RP.10601
Aspects of development and type of approval: DA - PA - Building Work Development Permit - dwelling house,Demolition
DA - PA - Material Change of Use Development Permit - rooming accommodation
DA - PA - Building Work Development Permit - rooming accommodation
Council File Reference: A006871612
Permit Reference Number/s: DABW382597019; DAMC382597119; DABW382682619.
Package Status: APPROVED - Version 2 (10th of June, 2026 1:06:48 PM)
Package Generated: 10/06/2026


PROJECT TEAM

The assessment of this application has been undertaken by:
Roger GREENWAY
Principal Urban Planner
Development Assurance & Outcomes
roger.greenway@brisbane.qld.gov.au
34034392
Ann-Marie KYRANIS
Senior Urban Planner
Development Assurance & Outcomes
Ann-Marie.Kyranis@brisbane.qld.gov.au
31780671
Justin SELLARS
Senior Urban Planner
Planning Services House & Homes
justin.sellars@brisbane.qld.gov.au
3403 6546
JAMES HEADING
Principal Urban Planner
Partnerships Team
james.heading@brisbane.qld.gov.au
(07) 3403 5591
George KOUPARITSAS
Architect
Architecture Team
George.Kouparitsas@brisbane.qld.gov.au
31787245
Matthew O'DEA
Principal Landscape Architect
Landscape Architecture Team
Matthew.ODea@brisbane.qld.gov.au
31789513
Craig SLACK
Engineer
Engineering Scoping
craig.slack@brisbane.qld.gov.au
(07) 3403 8888
Emma MEZZINA
Team Manager
Planning Services South
Emma.Mezzina@brisbane.qld.gov.au
3178 0049
Vernon ANDERSON
Team Manager (Acting)
Planning Services Coordination
Vernon.Anderson@brisbane.qld.gov.au
31780808
Scott RUHLAND
Technical Officer
Engineering Services North
scott.ruhland@brisbane.qld.gov.au
(07) 3403 9459
Jacqueline PATON
Senior Architect
Architecture Team
Jacqueline.Paton@brisbane.qld.gov.au
07 3178 0389
Chris.M DIXON
Senior Urban Planner
Planning Services North
chris.m.dixon@brisbane.qld.gov.au
31787264
MAISIE TANG
Principal Urban Planner
Planning Services North
maisie.tang@brisbane.qld.gov.au
(07) 31789048


DRAWINGS AND DOCUMENTS



The term 'drawings and documents' or similar expressions mean:
Drawing or Document Number Plan Date
Existing 2.00 Issue J 31-MAR-2026
Existing Elevations 3.00 Issue J 31-MAR-2026
Flood Investigation Report 19123 Rev 0 06-NOV-2019 (Received)
Waste Assessment 20BRW0003 10-MAR-2020
Site Plan 1.00 Issue J 31-MAR-2026
Proposed 2.10 Issue J (Amended In Red 23-APR-2026) 31-MAR-2026
Landscape / POS Plan 1.10 Issue J 31-MAR-2026
Proposed Elevations 3.10 Issue J (Amended In Red 23-APR-2026) 31-MAR-2026
Sections 4.00 Issue J 31-MAR-2026
Area Plan 1.01 Issue J 31-MAR-2026


Advice

Please see the attached document(s) for any advices.

APPROVAL CONDITIONS



Permit to Which These Conditions Relate: DA - PA - Building Work
Activity(ies): dwelling house
Demolition
Stage: Relocate pre-1947 Dwelling house

General/Planning Requirements
 
Timing
1)   Maintain the Approved Development

Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions.

 
At all times
 
2)   Approved Drawings and Documents

A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers.

Note: This condition is imposed to ensure compliance with the conditions of development approval.

 
While site/operational/building work is occurring
 
3)   Carry Out the Approved Development

Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS.

Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks).  Permission to enter neighbouring properties must be obtained from the relevant property owners.

 
While site/operational/building work is occurring
 
4)   Complete All Building Work

Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS.

Note: Building work must also be completed in accordance with any other current development approval.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
Architecture
 
Timing
5)   Partial Demolition of Building

Partial demolition resulting from this approval must be in accordance with the APPROVED DRAWINGS AND DOCUMENTS and all building work must comply with this condition.

 
While site/operational/building work is occurring and then to be maintained
5(a) Adequate Bracing

Provide adequate bracing from the commencement of any demolition work and throughout the demolition and construction phases of the project, to ensure that all parts of the building not specifically designated for demolition on the APPROVED DRAWINGS AND DOCUMENTS are retained and protected.

Timing: While site/operational/building work is occurring.

 
As indicated
5(b) Retain Original Fabric

Retain all existing external original fabric in the sections of the building which are not being demolished. This will include, but is not limited to, existing decorative detailing, balustrading, wall cladding, windows, doors, stairs and roof sheeting.

Timing: While site/operational/building work is occurring and then to be maintained.

 
As indicated
5(c) Submit Certification

Submit to Development Services certification by a Registered Architect / Building Designer (holding a Queensland Building and Construction Commission Licence appropriate to the scale of the approved development) confirming that the partial demolition has been carried out in accordance with the requirements of this condition.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use

 
As indicated
 
Engineering
 
Timing
6)   On-site Erosion (medium risk)

Minimise on-site erosion and the release of sediment or sediment laden stormwater from the site at all times.

Timing: While site works are occurring and until all exposed soil areas are permanently stabilised against erosion.

 
As indicated
6(a) Prepare Erosion and Sediment Control Plan

Prepare Erosion and Sediment Control (ESC) Plan(s), and provide design certificates for the site in accordance with the relevant Brisbane Planning Scheme Codes.
The plan(s) and design certificates must be certified by a Certified Professional in Erosion and Sediment Control (CPESC) or a Registered Professional Engineer Qld (RPEQ) with suitable qualifications and experience in erosion and sediment control.
Documentary evidence demonstrating appropriate qualifications in erosion and sediment control must be provided to the Council upon request.
At least 10 days prior to either the pre-start meeting or commencement of site works, submit copies of design certificates to Council’s Compliance and Regulatory Services at:
CARS-ESC@brisbane.qld.gov.au

Timing: Prior to pre-start meeting or commencement of any site works and to be maintained until all exposed soil areas are permanently stabilised against erosion.

 
As indicated
6(b) Attend a Pre-Start meeting

Arrange and attend a pre-start meeting with an Erosion & Sediment Control Officer from Council’s Compliance and Regulatory Services.  Requests are to be made when submitting copies of all required documentation, including design certificates to: CARS- ESC@brisbane.qld.gov.au

Timing: Prior to commencement of any site works causing exposure of soil.

 
As indicated
6(c) Implement Certified Erosion and Sediment Control Plan

Implement the certified ESC plan(s) to maintain compliance with all parts of the relevant Brisbane Planning Scheme Codes, while site works are occurring and until all exposed soil areas are permanently stabilised against erosion.
The plan(s) and design certifications must be available on site at all times for inspection by Council officers until all exposed soil areas are permanently stabilised against erosion.
Minimise on-site erosion and the release of sediment or sediment laden stormwater from the site at all times.

Timing: While site works are occurring and until all exposed soil areas are permanently stabilised against erosion.

 
As indicated
 
7)   Information Signage

Erect an "Information Sign" on the subject property in accordance with Council’s general requirements for signage and in accordance with the requirements outlined below:

a)  The sign should provide a brief description of the development proposed;
b)  The sign is to list the name, postal and/or email address and a contact telephone number for the following parties (where relevant) that are undertaking work on the site:

     Developer;
     Project Coordinator;
     Architect/Building Designer;
     Builder;
     Civil Engineer;
     Civil Contractor/s; and
     Landscape Architect;

c)  The lettering on the sign is to be at least 25 millimetres in height, be of regular weight and in sentence case;
d)  The sign is to be a minimum size of 1,200 millimetres by 900 millimetres;
e)  The maximum area of the sign is to be 2.0m2;
f)  The sign is to be positioned as follows:

     located centrally along the road frontage of the site to Picot Street;
     located on or within 1.5 metres of the road frontage;
     mounted at least 300 millimetres above ground level; and
     clearly visible from the street for a pedestrian;

g)  The sign is to contain no commercial or corporate advertising other than the name, logo or slogan of the parties outlined in part (b) of this condition;
h)  The sign is to be non-illuminated; and
i)  Both the sign and the supporting structure are to be made of weatherproof material and to be properly maintained at all times;

Timing: Prior to site works commencing and then to be maintained until completion of the development for all stages.

 
As indicated
 
8)   Construction Management Plan (Minor)

Carry out development in accordance with a Construction Management Plan (Minor) prepared in accordance with the requirements of this condition.

 
While site/operational/building work is occurring
8(a) Prepare Management Plan (minor)

Prepare a Construction Management Plan for the subject site.

 

The Construction Management Plan must be available on site at all times and must show, but not be limited to the following details where applicable, for the demolition (where in a Centre zone, a Mixed use zone or where the demolition is otherwise assessable development), excavation and construction phases of the approved development. Separate Construction Management Plans may be appropriate for the individual components:

 

-  Provision of alternative pedestrian route/s, past or around the site

-   Existing and proposed kerbside allocation signs and line marking (such as bus stops, loading zones and parking meters and/or ticket dispensers)

-  Temporary vehicular access points

-  Management and mitigation strategies for the impact of dust, noise and vibration upon adjoining and nearby properties

-   Employee and visitor parking areas (if provided)

-   Provision for loading and unloading materials including the location of any remote loading sites

-  The location of materials, structures, plant and equipment to be stored or placed on the construction site

-  The anticipated staging and programming

-  Allowable work times as set by the Queensland Environmental Protection Act 1994 (section 440).  A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management Delegate Development Services.

 

The Construction Management Plan must be supported by Permits or written approvals from the relevant Council sections or other body listed below (where applicable to the Plan) to ensure all potential impacts to Council and other infrastructure have been addressed:

(i) Work Zones / Temporary Road Closures / Taxi Ranks - (Congestion Reduction Unit, Planned Incident Management / Temporary Road Closures);

(ii) Full/Partial Footway-Footpath Closures – (Brisbane Infrastructure – Congestion Reduction Unit);

(iii) Street Lighting - (Brisbane Infrastructure - Asset Services-City Lighting);

(iv) City Cycle bike stations and JCDecaux Advertising Signage (including obstruction to sight lines for such advertising - owned by JCDecaux)- (Brisbane Infrastructure - Transport Planning and Strategy, Contract Management section);

(v) Street Furniture (excluding bus stops) - (Brisbane Infrastructure, Transport Network Operations, Roads and Drainage);

(vi) Waste Bins - (Brisbane Infrastructure, Waste Service);

(vii) Bus Stops/Shelters - (Brisbane infrastructure - Transport Planning and Strategy-Strategic Planning; and Brisbane Transport - Network Planning & Bus Operations);

(viii) Street Trees - (Brisbane Infrastructure - Asset Services - Arboriculture);

(ix) Parking Meters/Spaces - (Brisbane Infrastructure - City Parking);

(x) Traffic Signals - (Brisbane Infrastructure - Traffic Signals Operations);

(xi) Stormwater Gullies/Pits etc - (Brisbane Infrastructure - Roads and Drainage);

(xii) Other service providers - (e.g. Energex, Telstra, Optus, Queensland Urban Utilities, AGL).

 

Note: The Construction Management Plan is not required to be approved by Development Services.

 

At least 10 days prior to commencement of site works, submit a copy of the Construction Management Plan to Council’s Development Services Branch at the following mailbox: engineeringservices@brisbane.qld.gov.au quoting the planning development approval reference number.

 

Timing: Prior to site/operational/building work commencing

 
As indicated
8(b) Construction Management Plan (Minor) - Documentation on Site

Legible copies of the Construction Management Plan and current permits must be kept on site and be made available on request at all times.

Timing: While site/operational/building work is occurring

 
As indicated
8(c) Construction Management Plan (Minor) - Works to be Performed Out of Hours

Obtain approval from Development Services for any work that is proposed to be undertaken outside of normal business hours - 6:30am to 6:30pm, Monday to Saturday.
Timing: Prior to site/operational/building work commencing.

 
As indicated
8(d) Implement Construction Management Plan (Minor)

Carry out the development in accordance with the Construction Management Plan prepared in accordance with this condition.
Timing: While site/operational/building work is occurring.

 
As indicated
 
9)   Protect Existing Infrastructure

Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure. Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations. The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements.

 
While site/operational/building work is occurring
9(a) As Constructed Drawings

Where alterations to existing infrastructure are required, submit to Development Services "As Constructed" drawings showing all new and/or rectification works and an asset register, prepared by a Registered Professional Engineer Queensland.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
As indicated
9(b) Submit Certification

Where alterations to existing infrastructure are required, submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
As indicated
 
10)   Remove Improvements & Obstructions From Truncation and Dedication

Remove all improvements (fences, gates, letter boxes, garden beds and plots and other constructed items, etc.) and obstructions (existing earth banks, vegetation, etc.) from the area of the dedicated road and reinstate the area as footway in accordance with the relevant Brisbane Planning Scheme Codes.

Any new or existing installations of electrical pillar boxes, pad mounted transformers (PMTs), water meters and the like, must be installed/relocated to their ultimate alignment relative to the new property boundary and clear of the usable footpath areas irrespective of the alignment of the existing services/conduits. 

 Note:   - The cost of moving services, utilities and assets is the responsibility of the Developer. The permission of the service, utility or asset owner will be required. Council permission is required if street trees, stormwater gullies/drains, and swales are affected. Queensland Urban Utilities permission is required if water supply and sewerage services are affected

            ; - Standard utility alignments may be found on Council’s ‘Brisbane Standard Drawings’ 1013 to 1016 inclusive.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
10(a) Certify the Work

Submit to Development Services certification from a Registered Surveyor or Registered Professional Engineer Queensland that the above work has been completed in accordance with this condition.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
11)   Filling and / or Excavation (Minor)

Filling and/or excavation works on the site must be in accordance with the relevant Brisbane Planning Scheme Codes.

No earthworks whether cut or fill are to be undertaken within the new 6 metre wide overland flow easement at the east boundary of the site.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
11(a) Prepare Earthworks Drawings

Earthworks drawings must be prepared and certified by either: a Registered Professional Engineer Queensland or a suitably qualified geotechnical and structural consultant, in accordance with the relevant Brisbane Planning Scheme Codes.

The drawings must include the following:

-  maintenance of access roads to and from the site such that they remain free of all fill material and are cleaned as necessary
-  preservation of all drainage structures from the effects of structural loading generated by the earthworks
-  protection of adjoining properties and roads from ponding or nuisance from stormwater.

Timing: Prior to site/operational/building work commencing.

Note: The Earthworks drawings are not required to be submitted for Council approval.

 
As indicated
11(b) Implement and Maintain the Earthworks

Carry out and maintain the earthworks in accordance with the certified drawings.

Note: A copy of the certified Earthworks Drawings must be available on- site for inspection by Council Officers during these works.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
As indicated
 
12)   Repair Damage to Kerb, Footpath Or Road

Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
12(a) Interim Repairs

If at any time during the construction phase of the approved development, damage to the existing kerb and channel, footpath or roadway creates unsafe, unreasonable and/or not fit for purpose conditions as assessed by Council, interim repairs must be undertaken as directed by Asset Services.

Note: Any interim repairs required to be undertaken shall not be considered to satisfy the requirements of this condition for the permanent repair of the infrastructure prior to the issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

Timing: While site / operational / building works is occurring

 
As indicated
 
13)   Remove Redundant Drainage Outlets

Remove any redundant drainage outlets from the kerb and channel including any associated pipe work across the footway and reinstate the kerb and channel and the footway area in accordance with the relevant Brisbane Planning Scheme Codes.

Note: Guidance for the preparation of drawings and/or documents to comply with this condition is provided in the Brisbane Planning Scheme Policies.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
Standard Advice
 
Timing
14)   Construction Noise and Dust Emissions

Pursuant to the Environmental Protection Act 1994, all development involving the emission of noise and dust from building and/or construction activities, must ensure that the emissions are in accordance with the requirements of the Act.
The Environmental Protection Act 1994 prescribes that:

1. A person must not carry out building work in a way that makes an audible noise-
-  on a business day or Saturday, before 6.30a.m. or after 6.30p.m; or
-   on any other day, at any time. 
2. The reference in subsection (1) to a person carrying out building work-
-  includes a person carrying out building work under an owner-builder permit; and
-  otherwise does not include a person carrying out building work at premises used by the person only for residential purposes.

Note: A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management delegate Development Services.

 
As indicated
 
15)   Currency Period

The currency period for this development approval is stated in the Decision Notice and is expressed as a date.

This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016.

 
As indicated
 
16)   Damage to Trees on Adjoining Land

Please note that any damage caused to vegetation on adjoining land as a result of exercising this development approval may result in an offence under other legislation (e.g. Natural Assets Local Law) and/or civil action.

 
As indicated
 
17)   Further Development Permit Required

Further Development Permit(s) to carry out assessable building work under the Building Act may be required.

 
As indicated
 
18)   Cultural Heritage

Aboriginal cultural heritage is protected under the Aboriginal Cultural Heritage Act 2003.  This Act establishes a cultural heritage duty of care and in section 23(1) mandates that a person who carries out an activity must take all reasonable and practicable measures for ensuring activities are managed to avoid or minimise harm to Aboriginal cultural heritage.

The Duty of Care Guidelines gazetted pursuant to the Aboriginal Cultural Heritage Act 2003 provide guidance on identifying and protecting Aboriginal cultural heritage to fulfil the duty of care.

For further information contact the relevant Queensland State Government Department (Department of Aboriginal and Torres Strait Islander Partnerships).

 
As indicated
 
19)   Fire Ant Movement Controls

To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected.

These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products.

Breaches of these controls can potentially impact the community, economy and the environment.  Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014.

For further information contact the relevant Queensland State Government department on 13 QGOV.

 
As indicated
 



Permit to Which These Conditions Relate: DA - PA - Material Change of Use
Activity(ies): rooming accommodation
Stage: Rooming accommodation

General/Planning Requirements
 
Timing
20)   Maintain the Approved Development

Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions.

 
At all times
 
21)   Approved Drawings and Documents

A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers.

Note: This condition is imposed to ensure compliance with the conditions of development approval.

 
While site/operational/building work is occurring
 
22)   Carry Out the Approved Development

Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS.

Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks).  Permission to enter neighbouring properties must be obtained from the relevant property owners.

 
While site/operational/building work is occurring
 
23)   Complete All Building Work

Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS.

Note: Building work must also be completed in accordance with any other current development approval.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
24)   Visitor Parking

Visitor car parking spaces must:
-  Be clearly labelled as 'Visitor Parking';
-  Remain unimpeded by landscaping, water tanks, storage (temporary or otherwise), gates or any other fitting, fixture or structure; and
-  Provide 24 hour unrestricted access for all bona fide visitors to the whole site.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
25)   Outdoor lighting

Outdoor lighting is to be in compliance with AS 4282-1997 - Control of the obtrusive effects of outdoor lighting.

 
At all times
 
26)   Limitation of use

The approved Rooming accommodation must operate in accordance with the definition of ‘suite’ in the Brisbane Infrastructure Charges Resolution (No. 9) 2020, as detailed below:

‘Suite’ means a number of connected rooms one of which is a bedroom in which an individual or a group of two or more related or unrelated people reside with the common intention to live together on a long term basis and who make common provision for food or other essentials for living.

The approved Rooming accommodation is to have a maximum of 4 dwelling suites with a total of 24 rooms.

 

 

 
Prior to the commencement of the use and then to be maintained
 
Architecture
 
Timing
27)   External Details

External details of the building, facade treatment and external materials and finishes must be consistent with the approved DRAWINGS AND DOCUMENTS.

Note: The requirement to use particular materials and finishes is imposed only for the purpose of achieving a built form outcome that displays architectural merit. Council has not assessed the materials and finishes for compliance with the Building Act, the Building Fire Safety Regulation, the Building Regulation, the Building Code of Australia, the Queensland Development Code, relevant Australian Standards, fire safety standards or any other relevant requirement of a statutory authority with regard to building work.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
28)   Overall Height

The overall height of the building(s) must be in accordance with the floor and roof levels and overall height shown on the APPROVED DRAWINGS AND DOCUMENTS.

NOTE: Where there is a conflict with the floor heights shown on the APPROVED DRAWINGS and the conditions in this approval that stipulate minimum height clearance for undercover car parking, the height clearance conditions prevail.

 
While site/operational/building work is occurring and then to be maintained
28(a) Submit Certification

Submit to Development Services certification from a registered surveyor confirming that the 'as constructed' floor and roof levels and overall height are in accordance with the requirements of this condition.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
29)   Provide Pedestrian Prioritised Pathway

Provide a pedestrian prioritised pathway from the street frontage to Buildings A, B, C and D. The pathway must be differentiated in colour and texture from the driveway surface.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
30)   Screen Air Conditioning and Other Plant Enclosures

Install and maintain suitable screening to all air conditioning, lift motor rooms, plant and service facilities located at the top of or on the external face of the building. The screening structures must be constructed from materials that are consistent with materials used elsewhere on the facade of the building. There must be no individual external air conditioning units located on balconies.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
31)   Screening

Provide screening to windows of habitable rooms, balconies, landings, terraces and decks of the proposed dwelling(s) in accordance with the approved DRAWINGS AND DOCUMENTS and the following requirements.

Where any windows of habitable rooms of the proposed dwelling(s) are within 2m at ground floor level or 9m above ground floor level of adjoining neighbouring dwellings' windows to habitable rooms, provide suitable screening in accordance with the following:

Suitable screening must be:

For windows:
-  Sill heights of 1.5m above floor level; or
-  Fixed obscure glazing in any part of the window below 1.5m above floor level; or
-  Fixed external screens to any part of the window below 1.5m above floor level, or
-  Fencing to a minimum 1.8m above ground floor level (only applies to overlooking from windows at ground floor level).

For balconies, landings, terraces and decks facing the side boundaries of the site:
-  Fixed screening as shown on the approved DRAWINGS AND DOCUMENTS.

Note: Screening devices must be either solid translucent screens, perforated or slatted panels, or fixed louvres that are permanent, be durable and fixed. Screening devices must have a maximum of 25% openings, with a maximum opening of 50mm.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
Landscape Architecture and Open Space Planning
 
Timing
32)   Streetscape Works - Neighbourhood Street

Carry out streetscape improvement works including concrete path, turf and street trees to the verge to a Neighbourhood Street Minor standard in accordance with the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD), the requirements of this condition and the Infrastructure Design Planning Scheme Policy including sections 3.7.4.4 and 3.7.5.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
32(a) Concrete Path

Install a 1.2m wide broom finished standard Portland grey concrete path. The path on the southern side of the driveway is to be setback 1.3m from the back of kerb. The path on the northern side of the driveway is to align with the existing path on the verge that adjoins the development to the north.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
As indicated
32(b) Submit As-Constructed Drawings

Submit to Development Services "As Constructed" plans including an asset register, checked by a Registered Professional Engineer Queensland, certifying that the concrete path works have been completed in accordance with relevant Brisbane Planning Scheme Codes/Policies.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
As indicated
32(c) Turf

Install turf to the full width of the verge excluding any concrete path required by this condition.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
As indicated
 
33)   Landscape the Site - Self Certification

Landscape the site in accordance with the requirements of this condition.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
33(a) Detailed Landscape Plan for Self Certification

Prepare a Detailed Landscape Plan at a scale of 1:100 for all on-site landscape works including planting areas identified on the approved DRAWINGS AND DOCUMENTS. The plan must be prepared by a Registered Landscape Architect and must comply with the relevant Brisbane Planning Scheme Codes.

In addition to the requirements listed above, the plan must include the following:

. Deep planting areas

· Deep planting areas as shown on the approved drawings, open to the sky and with no underground development including retaining wall footings with the exception of existing underground infrastructure.

· Provide tree planting in accordance with the approved drawing numbered 2.10 Issue J, received 2 April 2026 and amended in red 23 April 2026.

Side and rear boundaries

· Provide tree planting in accordance with the approved drawing numbered 2.10 Issue J, received 2 April 2026 and amended in red 23 April 2026.

Containerised planting

· Clear identification of the location, width and depth of containerised planting.

· Minimum internal depths and widths as shown on approved plans

· A reticulated drip irrigation system to all containerised planting areas, with drainage connected to the stormwater system; the irrigation system must be connected to a non-mains water source.

Specifications

· Plant selection and densities to achieve full surface coverage within 2 years of planting

· Unless otherwise specified, trees provided as 45 litre stock or larger, staked and tied, and complying with Australian Standards

· Mulch and soil to all garden areas to meet Australian Standards

· Soil media ameliorated to increase water-holding abilities

· Details of a 12-week establishment period.

Timing: Prior to building work commencing.

 
As indicated
33(b) Certify Detailed Landscape Plan

On completion of the Detailed Landscape Plan, submit to Development Services:

·         Brisbane City Council Form CC10616 - Landscape Design Certificate prepared by a Registered Landscape Architect to certify that the Detailed Landscape Plan complies with the requirements of this condition

·         A copy of the certified Detailed Landscape Plan.

Timing: Prior to building work commencing.

 
As indicated
33(c) Implement Certified Detailed Landscape Plan

Carry out the landscape work in accordance with the above certified detailed Landscape Plan.

 

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
33(d) Certify Work

On completion of the landscape work, submit to Development Services:

·         Brisbane City Council Form CC10613 - Landscape Works Certificate prepared by a Registered Landscape Architect or licensed Landscape Contractor to certify the completed landscape work complies with the certified Detailed Landscape Plan

·         A copy of the as- constructed certified Detailed Landscape Plan.

 

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 

 
As indicated
33(e) Maintain Landscape Work

Maintain the landscape work generally in accordance with the certified Detailed Landscape Plan.

 

Timing: To be maintained.

 
As indicated
 
Pollution
 
Timing
34)   Air Emissions

 

Vehicle exhaust fumes are released via exhaust vent outlets which are directed away from any sensitive use and include the following:            

-       air emissions are not to cause an odour or air emission which is detectable and disturbing at a sensitive use; and

-        ensures that exhaust vents from any basement/enclosed car park are separated from any sensitive use by a minimum of 15m and 6m from intakes and natural ventilation openings.

 

 

 

 
Prior to the commencement of the use and then to be maintained
 
35)   Acoustic Fence - General

Erect a 2.0m high (relative to the finished RL of the driveway / pathway) acoustic fence along the northern and southern boundaries of the site adjacent to the driveway / pathway as shown on the approved drawings numbered 2.10 Issue J, received 2 April 2026 and amended in red 23 April 2026. The acoustic fencing must:
- Be constructed of a material with a minimum surface area density of 12.5kg/m2;
- Be constructed of an aesthetically pleasing weather-resistant material such as fibre cement, painted or treated timber, brick, concrete or a combination thereof;
- Have returns at any opening or provide some other means of blocking line of site from source to receiver such that the effectiveness of the fence is not reduced;
- Be continuous and gap free.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
35(a) Certification

Submit to Development Services certification from a person who is a Member or eligible to be a Member of the Australian Acoustic Society that the constructed acoustic fence complies with the above requirements.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
36)   Dampening of Grilles and Metal Plates

All metal grilles, metal plates or similar located within vehicle parking and manoeuvring areas must be securely fastened and meet the requirements of AS3996:2019, Access covers and grates.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
37)   Plant and Equipment Certification

Following the installation of all mechanical plant and equipment (e.g. air conditioning, mechanical ventilation and refrigeration equipment and heat pump hot water systems), submit to Development Assessment certification that the plant and equipment is adequately noise- attenuated and is in accordance with the criteria of the relevant Brisbane Planning Scheme Codes/Policies.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
Engineering
 
Timing
38)   Retaining Walls

Design and construct all retaining walls and associated fences, in accordance with the relevant Brisbane Planning Scheme Codes and including the following:

-  All retaining walls including the footings, must be located wholly within the property boundary of the site where works are occurring
-  Retaining walls to stabilise excavation must be set back off property boundaries to accommodate subsoil drainage without encroachment into the neighbouring property. This set back may vary depending on the height, structure and design of the retaining wall, including loadings from neighbouring properties, and to provide a surface drain along the top of the retaining wall
-  Retaining walls that are greater than 1.0m in height must be vertically and horizontally tiered by a ratio of 1:1 unless an alternative has been approved by Development Services
-  Runoff from surface drains and subsoil drainage associated with the retaining wall must be collected and conveyed to a lawful point of discharge and must not cause any ponding, nuisance or disturbance to adjacent property owners
-  Retaining walls in excess of 1.0m in height must be designed and certified by a Registered Professional Engineer Queensland
-  Retaining walls facing onto Council property (including the road reserve and parkland) must not be constructed from timber.

 
As indicated
38(a) Certification of Retaining Walls

For retaining walls over 1.0m in height, obtain certification from a Registered Professional Engineer Queensland that the design and construction of the retaining wall and ancillary drainage is in accordance with this condition.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
As indicated
 
39)   Grant Easements

Grant the following easement(s):

i) A 0.9 metre wide easement for underground drainage, and access purposes as may be required, in favour of Brisbane City Council.

iii) A 6 metre wide volumetric easement limited to 12 m AHD along the east boundary for open cut, overland flow and access purposes for the 2% AEP for overland flow flooding, in favour of Brisbane City Council.
Note: These easements include the provision for Council to obtain access.


Timing: Prior to commencement of use (MCU) or as part of the registration of the plan of subdivision notated by Council (ROL), and then to be maintained.

 
As indicated
39(a) Submit Plan of Subdivision and Documentation (Non-Council Easement)

Submit for the approval of Development Services, a plan of subdivision showing the easement and the necessary easement documentation to demonstrate compliance with the requirements of this condition.

Note: Easements not in favour of the Brisbane City Council must have the necessary documentation prepared by the applicant's private solicitors.

Timing: As part of the submission of the request pursuant to Schedule 18 of the Planning Regulation 2017 for Council's notation on the plan of subdivision necessary to comply with this condition (MCU) or give effect to this approval (ROL).

 
As indicated
39(b) Submit Plan of Subdivision and Documentation (Council Easement)

Submit for the approval of Development Services, a plan of subdivision showing the easement and a request for Council to prepare the necessary easement documentation to demonstrate compliance with the requirements of this condition.

Note: Easements in favour of the Brisbane City Council must have the necessary easement documentation prepared by the Brisbane City Council, free of cost to Council.

Timing: Prior to submission of the request pursuant to Schedule 18 of the Planning Regulation 2017 for Council’s notation on the plan of subdivision necessary to comply with this condition (MCU) or give effect to this approval (ROL).

 
As indicated
39(c) Lodge Notated Plan and Documentation

Lodge the plan of subdivision notated by Council pursuant to Schedule 18 of the Planning Regulation 2017 and the necessary easement documentation with the Registrar of Titles for the relevant Queensland State Government Authority.

Timing: Prior to commencement of use (MCU) or as part of the registration of the plan of subdivision notated by Council (ROL).

 
As indicated
39(d) Submit Evidence of Registration

Submit to Development Services evidence of the registration of the necessary easement documentation.

Timing: Within one month of the registration of the easement documentation.

 
As indicated
 
40)   On-site Erosion (medium risk)

Minimise on-site erosion and the release of sediment or sediment laden stormwater from the site at all times.

Timing: While site works are occurring and until all exposed soil areas are permanently stabilised against erosion.

 
As indicated
40(a) Prepare Erosion and Sediment Control Plan

Prepare Erosion and Sediment Control (ESC) Plan(s), and provide design certificates for the site in accordance with the relevant Brisbane Planning Scheme Codes.
The plan(s) and design certificates must be certified by a Certified Professional in Erosion and Sediment Control (CPESC) or a Registered Professional Engineer Qld (RPEQ) with suitable qualifications and experience in erosion and sediment control.
Documentary evidence demonstrating appropriate qualifications in erosion and sediment control must be provided to the Council upon request.
At least 10 days prior to either the pre-start meeting or commencement of site works, submit copies of design certificates to Council’s Compliance and Regulatory Services at:
CARS-ESC@brisbane.qld.gov.au

Timing: Prior to pre-start meeting or commencement of any site works and to be maintained until all exposed soil areas are permanently stabilised against erosion.

 
As indicated
40(b) Attend a Pre-Start meeting

Arrange and attend a pre-start meeting with an Erosion & Sediment Control Officer from Council’s Compliance and Regulatory Services.  Requests are to be made when submitting copies of all required documentation, including design certificates to: CARS-ESC@brisbane.qld.gov.au

Timing: Prior to commencement of any site works causing exposure of soil.

 
As indicated
40(c) Implement Certified Erosion and Sediment Control Plan

Implement the certified ESC plan(s) to maintain compliance with all parts of the relevant Brisbane Planning Scheme Codes, while site works are occurring and until all exposed soil areas are permanently stabilised against erosion.
The plan(s) and design certifications must be available on site at all times for inspection by Council officers until all exposed soil areas are permanently stabilised against erosion.
Minimise on-site erosion and the release of sediment or sediment laden stormwater from the site at all times.

Timing: While site works are occurring and until all exposed soil areas are permanently stabilised against erosion.

 
As indicated
 
41)   Information Signage

Erect an "Information Sign" on the subject property in accordance with Council’s general requirements for signage and in accordance with the requirements outlined below:

a)  The sign should provide a brief description of the development proposed;
b)  The sign is to list the name, postal and/or email address and a contact telephone number for the following parties (where relevant) that are undertaking work on the site:

     Developer;
     Project Coordinator;
     Architect/Building Designer;
     Builder;
     Civil Engineer;
     Civil Contractor/s; and
     Landscape Architect;

c)  The lettering on the sign is to be at least 25 millimetres in height, be of regular weight and in sentence case;
d)  The sign is to be a minimum size of 1,200 millimetres by 900 millimetres;
e)  The maximum area of the sign is to be 2.0m2;
f)  The sign is to be positioned as follows:

     located centrally along the road frontage of the site to Picot Street;
     located on or within 1.5 metres of the road frontage;
     mounted at least 300 millimetres above ground level; and
     clearly visible from the street for a pedestrian;

g)  The sign is to contain no commercial or corporate advertising other than the name, logo or slogan of the parties outlined in part (b) of this condition;
h)  The sign is to be non-illuminated; and
i)  Both the sign and the supporting structure are to be made of weatherproof material and to be properly maintained at all times;

Timing: Prior to site works commencing and then to be maintained until completion of the development for all stages.

 
As indicated
 
42)   Construction Management Plan (Minor)

Carry out development in accordance with a Construction Management Plan (Minor) prepared in accordance with the requirements of this condition.

 
While site/operational/building work is occurring
42(a) Prepare Management Plan (minor)

Prepare a Construction Management Plan for the subject site.

 

The Construction Management Plan must be available on site at all times and must show, but not be limited to the following details where applicable, for the demolition (where in a Centre zone, a Mixed use zone or where the demolition is otherwise assessable development), excavation and construction phases of the approved development. Separate Construction Management Plans may be appropriate for the individual components:

 

-  Provision of alternative pedestrian route/s, past or around the site

-   Existing and proposed kerbside allocation signs and line marking (such as bus stops, loading zones and parking meters and/or ticket dispensers)

-  Temporary vehicular access points

-  Management and mitigation strategies for the impact of dust, noise and vibration upon adjoining and nearby properties

-   Employee and visitor parking areas (if provided)

-   Provision for loading and unloading materials including the location of any remote loading sites

-  The location of materials, structures, plant and equipment to be stored or placed on the construction site

-  The anticipated staging and programming

-  Allowable work times as set by the Queensland Environmental Protection Act 1994 (section 440).  A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management Delegate Development Services.

 

The Construction Management Plan must be supported by Permits or written approvals from the relevant Council sections or other body listed below (where applicable to the Plan) to ensure all potential impacts to Council and other infrastructure have been addressed:

(i) Work Zones / Temporary Road Closures / Taxi Ranks - (Congestion Reduction Unit, Planned Incident Management / Temporary Road Closures);

(ii) Full/Partial Footway-Footpath Closures – (Brisbane Infrastructure – Congestion Reduction Unit);

(iii) Street Lighting - (Brisbane Infrastructure - Asset Services-City Lighting);

(iv) City Cycle bike stations and JCDecaux Advertising Signage (including obstruction to sight lines for such advertising - owned by JCDecaux)- (Brisbane Infrastructure - Transport Planning and Strategy, Contract Management section);

(v) Street Furniture (excluding bus stops) - (Brisbane Infrastructure, Transport Network Operations, Roads and Drainage);

(vi) Waste Bins - (Brisbane Infrastructure, Waste Service);

(vii) Bus Stops/Shelters - (Brisbane infrastructure - Transport Planning and Strategy-Strategic Planning; and Brisbane Transport - Network Planning & Bus Operations);

(viii) Street Trees - (Brisbane Infrastructure - Asset Services - Arboriculture);

(ix) Parking Meters/Spaces - (Brisbane Infrastructure - City Parking);

(x) Traffic Signals - (Brisbane Infrastructure - Traffic Signals Operations);

(xi) Stormwater Gullies/Pits etc - (Brisbane Infrastructure - Roads and Drainage);

(xii) Other service providers - (e.g. Energex, Telstra, Optus, Queensland Urban Utilities, AGL).

 

Note: The Construction Management Plan is not required to be approved by Development Services.

 

At least 10 days prior to commencement of site works, submit a copy of the Construction Management Plan to Council’s Development Services Branch at the following mailbox: engineeringservices@brisbane.qld.gov.au quoting the planning development approval reference number.

 

Timing: Prior to site/operational/building work commencing

 
As indicated
42(b) Construction Management Plan (Minor) - Documentation on Site

Legible copies of the Construction Management Plan and current permits must be kept on site and be made available on request at all times.

Timing: While site/operational/building work is occurring

 
As indicated
42(c) Construction Management Plan (Minor) - Works to be Performed Out of Hours

Obtain approval from Development Services for any work that is proposed to be undertaken outside of normal business hours - 6:30am to 6:30pm, Monday to Saturday.
Timing: Prior to site/operational/building work commencing.

 
As indicated
42(d) Implement Construction Management Plan (Minor)

Carry out the development in accordance with the Construction Management Plan prepared in accordance with this condition.
Timing: While site/operational/building work is occurring.

 
As indicated
 
43)   Protect Existing Infrastructure

Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure. Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations. The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements.

 
While site/operational/building work is occurring
43(a) As Constructed Drawings

Where alterations to existing infrastructure are required, submit to Development Services "As Constructed" drawings showing all new and/or rectification works and an asset register, prepared by a Registered Professional Engineer Queensland.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
As indicated
43(b) Submit Certification

Where alterations to existing infrastructure are required, submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
As indicated
 
44)   Remove Improvements & Obstructions From Truncation and Dedication

Remove all improvements (fences, gates, letter boxes, garden beds and plots and other constructed items, etc.) and obstructions (existing earth banks, vegetation, etc.) from the area of the dedicated road and reinstate the area as footway in accordance with the relevant Brisbane Planning Scheme Codes.

Any new or existing installations of electrical pillar boxes, pad mounted transformers (PMTs), water meters and the like, must be installed/relocated to their ultimate alignment relative to the new property boundary and clear of the usable footpath areas irrespective of the alignment of the existing services/conduits. 

 Note:   - The cost of moving services, utilities and assets is the responsibility of the Developer. The permission of the service, utility or asset owner will be required. Council permission is required if street trees, stormwater gullies/drains, and swales are affected. Queensland Urban Utilities permission is required if water supply and sewerage services are affected

            ; - Standard utility alignments may be found on Council’s ‘Brisbane Standard Drawings’ 1013 to 1016 inclusive.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
44(a) Certify the Work

Submit to Development Services certification from a Registered Surveyor or Registered Professional Engineer Queensland that the above work has been completed in accordance with this condition.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
45)   Filling and / or Excavation (Minor)

Filling and/or excavation works on the site must be in accordance with the relevant Brisbane Planning Scheme Codes.

No earthworks whether cut or fill are to be undertaken within the new 6 metre wide overland flow easement at the east boundary of the site.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
45(a) Prepare Earthworks Drawings

Earthworks drawings must be prepared and certified by either: a Registered Professional Engineer Queensland or a suitably qualified geotechnical and structural consultant, in accordance with the relevant Brisbane Planning Scheme Codes.

The drawings must include the following:

-  maintenance of access roads to and from the site such that they remain free of all fill material and are cleaned as necessary
-  preservation of all drainage structures from the effects of structural loading generated by the earthworks
-  protection of adjoining properties and roads from ponding or nuisance from stormwater.

Timing: Prior to site/operational/building work commencing.

Note: The Earthworks drawings are not required to be submitted for Council approval.

 
As indicated
45(b) Implement and Maintain the Earthworks

Carry out and maintain the earthworks in accordance with the certified drawings.

Note: A copy of the certified Earthworks Drawings must be available on- site for inspection by Council Officers during these works.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
As indicated
 
46)   Repair Damage to Kerb, Footpath Or Road

Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
46(a) Interim Repairs

If at any time during the construction phase of the approved development, damage to the existing kerb and channel, footpath or roadway creates unsafe, unreasonable and/or not fit for purpose conditions as assessed by Council, interim repairs must be undertaken as directed by Asset Services.

Note: Any interim repairs required to be undertaken shall not be considered to satisfy the requirements of this condition for the permanent repair of the infrastructure prior to the issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

Timing: While site / operational / building works is occurring

 
As indicated
 
47)   Remove Redundant Drainage Outlets

Remove any redundant drainage outlets from the kerb and channel including any associated pipe work across the footway and reinstate the kerb and channel and the footway area in accordance with the relevant Brisbane Planning Scheme Codes.

Note: Guidance for the preparation of drawings and/or documents to comply with this condition is provided in the Brisbane Planning Scheme Policies.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
48)   Access, Grades, Manoeuvring, Carparks, Signs and Line Marking

Construct access, parking and manoeuvring for vehicles on site in accordance with the relevant Brisbane Planning Scheme Codes, as indicated on the approved DRAWINGS AND DOCUMENTS, including the following:

i. A pavement of minimum Local road standard or equivalent surface material (including associated drainage) to the area on which motor vehicles will be driven and/or parked.

ii. Parking on the site for 5 resident/tenant cars (including 1 ride share car and 1 parking space for people with disabilities) and 1 visitor car and provide for the loading and unloading of vehicle(s) within the site. The ride share car must be provided and administered by the facility management and this car space must be identified by signage, accessible 24 hrs/ 7 days/week, and provided for exclusive use for on site residents only.

iii. Provide 12 secure bicycle parking spaces including 4 shared e-bicycles.

iv. A minimum of 2.3 metres height clearance to all undercover parking areas and a minimum of 2.5 metres above parking spaces for people with disabilities. The minimum clear height must be measured to the lowest protrusion from the ceiling (e.g. fire sprinklers, services, lighting fixtures, signs, etc).

v. A height clearance sign located at the entrance(s) to undercover car parking areas and a directional visitor parking sign clearly visible from the vehicle entrance to the site.

vi. An appropriate area for the storage of refuse on the site.

vii. The internal paved areas must be signed and delineated in accordance with the approved drawings and Manual of Uniform Traffic Control Devices - Queensland Department of Transport and Main Roads - Transport Operations (Road Use Management) Act 1995.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
48(a) Submit certification

Submit to Development Services, certification from a Registered Professional Engineer Queensland, that the above requirements have been implemented in accordance with this condition.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
49)   Minimum Flood Planning Levels

Design and construct all proposed building pad levels, floor levels and ancillary structures to the appropriate flood planning level with freeboard (where required) in accordance with the relevant Brisbane Planning Scheme Codes.

The minimum habitable floor level must be 11.87 metres AHD.

The minimum non- habitable floor level must be 11.67 metres AHD.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
49(a) Submit Certification

Submit to Development Services "As-Constructed" drawings prepared by a Registered Surveyor. The Registered Surveyor must certify that the development has been constructed in accordance with this condition.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
 
50)   Stormwater - Flood Study

Construct the development in accordance with the approved Flood Investigation Report prepared by HCE Engineers numbered 19123 Rev 0, received 6 November 2019.

No earthworks whether cut or fill are to be undertaken within the new 6 metre wide overland flow easement at the east boundary of the site.

Any fencing in the overland flow path must be open at the bottom for 100mm minimum, and with a minimum of 50% openings above that.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
50(a) Certification

Submit to Development Services certification from a Registered Professional Engineer Queensland that the development has been constructed in accordance with the approved flood study.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
As indicated
 
51)   Refuse Collection - Kerb Side (external road or internal private road)

Refuse and recycling bins for the proposed development must be collected from the kerb side by Private Contractor. However, bins must not be left unattended kerbside, generally in accordance with the Waste collection proposal outlined in the approved waste assessment letter prepared by TTM dated 10/3/2020.

Waste collection must be undertaken twice weekly as a minimum and bin numbers must be minimised/restricted so they do not impact on neighbours frontage

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
52)   Refuse Storage - Kerb Side Collection

Provide a covered and screened waste enclosure to accommodate the type and quantity of waste/recycling bins required to service the development.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
53)   Land for Transport Network - Road (Non- trunk)

Dedicate as road including the following:

i. A widening along the full length of the Picot Street frontage of the site to provide a 2.5 metre wide verge;


NOTE: This condition is imposed under section 145 of the Planning Act 2016.

Timing: Prior to commencement of use (MCU) or as part of the registration of the plan of subdivision notated by Council (ROL).

 
As indicated
53(a) Submit Plan of Subdivision (MCU only)

Submit for the approval of Development Services, a plan of subdivision showing the land to be dedicated for road to demonstrate compliance with the requirements of this condition.

Timing: As part of the submission of the request pursuant to Schedule 18 of the Planning Regulation 2017 for Council’s notation on the plan of subdivision necessary to comply with this condition.

 
As indicated
53(b) Lodge Notated Plan (MCU only)

Lodge the plan of subdivision notated by Council pursuant to Schedule 18 of the Planning Regulation 2017 with the Registrar of Titles for the relevant Queensland State Government Authority.

Timing: Prior to commencement of use.

 
As indicated
53(c) Submit Evidence of Registration (MCU only)

Submit to Development Services, evidence of the registration of the required plan of subdivision.

Timing: Within one month of the registration of the plan of subdivision.

 
As indicated
 
54)   Work for Transport Network - Road (Non-trunk) - External

Construct the following roadwork with any associated drainage, footpath, site access and services including street lighting for the Transport Network (Road) in accordance with the relevant Brisbane Planning Scheme Codes, the Manual of Uniform Traffic Control Devices - Queensland Department of Transport and Main Roads - Transport Operations (Road Use Management) Act 1995 and the AUSTROADS design standards:


  - Street lighting to a category P4 along the Picot Street frontage.


Note: This condition is imposed under section 145 of the Planning Act 2016.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
54(a) Submit Street Lighting Design Drawings

Submit for the approval of City Lighting, street lighting design drawings prepared and certified by a Registered Professional Engineer of Queensland (electrical) which show the proposed street lighting system in accordance with the relevant Brisbane Planning Scheme Codes.

 

Timing: Prior to site/operational/building work commencing.

 
As indicated
54(b) Pre-Start Meeting

Arrange and attend a pre-start meeting with Development Services.

 

Timing: Prior to site/operational work commencing.

 
As indicated
54(c) Implement Approved Drawings

Construct the works in accordance with the above approved drawings.

Timing: Prior to on-maintenance acceptance.

 
As indicated
54(d) Submit As Constructed Drawings

Submit to Development Services "As Constructed" drawings including an asset register and a pre-On-Maintenance Inspection Checklist, prepared by a Registered Professional Engineer Queensland.

 

Timing: Prior to on-maintenance inspection.

 
As indicated
54(e) Submit Certification

Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the above approved drawings.

Timing: Prior to on-maintenance inspection.

 
As indicated
 
55)   Lawful Point Of Discharge

Submit to Development Services, evidence of written consent for a lawful point of discharge from the owners of properties affected by any stormwater discharge from the site.

Note.  Refer to Council's website for a standard lawful point of discharge agreement template which is acceptable to Council.

 
Prior to site/operational/building work commencing
 
56)   Ponding of Stormwater

Carry out the approved development to ensure that adjoining properties and roads are protected from ponding or nuisance from stormwater as a result of the works.

Notes: If remedial works are necessary to comply with this condition, prior approval must be obtained from Development Services.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
57)   On Site Drainage - Minor

Provide a stormwater connection to all new or existing allotments and provide drainage infrastructure to ensure stormwater run-off from all roof and developed surface areas will be collected internally and piped in accordance with the relevant Brisbane Planning Scheme Codes to a lawful point of discharge.

The LPD for the front dwelling is the kerb/channel in Picot Street, and the LPD for the rest of the site is the existing stormwater pipe infrastructure in the neighbours property.

Note: Guidance for the preparation of drawings and/or documents to comply with this condition is provided in the Brisbane Planning Scheme Policies.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
57(a) Submit As Constructed Drawings

Where reconfiguring a lot, submit to Development Services "As Constructed" drawings prepared by a Registered Professional Engineer Queensland.

Timing: Prior to Council's notation of the plan of subdivision.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
57(b) Submit Certification

Where reconfiguring a lot, submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with this condition.

Timing: Prior to Council's notation of the plan of subdivision.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
 
58)   Up Stream Stormwater Drainage Connection - Minor

Provide a stormwater drainage connection for the future development of the adjoining upstream property at the south boundary designed for ultimate developed catchment conditions and connected to a lawful point of discharge. This pipe must be located in a 0.9 metre wide underground drainage easement.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
58(a) Prepare Stormwater Drawings

Prepare stormwater drawings and engineering calculations, certified by a Registered Professional Engineer Queensland in accordance with the relevant Brisbane Planning Scheme Codes.

Note:
-  Queensland Building and Construction Commission licensed hydraulic consultants may design the stormwater system for sites less than 2000m2 with an upstream catchment servicing no more than 4 residential lots.  This excludes stormwater drainage design (including subsoil drainage) of basements in flood planning areas and the design of any onsite stormwater detention system
-  Guidance for the preparation of drawings and/or documents to comply with this condition is provided in the Brisbane Planning Scheme Policies
-  A 225mm diameter pipe is the minimum size required to service an upstream development of any kind.

Timing: Prior to site/operational/building work commencing.

 
As indicated
58(b) Implement Certified Stormwater Drawings

Carry out the works in accordance with the above  stormwater drawings.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained.

 
As indicated
58(c) Submit As Constructed Drawings

Submit to Development Services "As Constructed" drawings prepared by a Registered Professional Engineer Queensland.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation on the plan of subdivision (ROL).

 
As indicated
58(d) Submit Certification

Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the above stormwater drawings.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation on the plan of subdivision (ROL).

 
As indicated
 
59)   Service Conduits and Mains

Provide and install all service conduits and meet the cost of any alterations to public utility mains, existing mains, services, street lighting or installations that are required to carry out the approved development. These works must be in accordance with the relevant Brisbane Planning Scheme Codes, and include the following, where applicable:

-  the provision of all services and/or conduits along the full length of any rear allotment access or access easement.
-   the breaking and/or relocation of any existing sewer combine drains.
-  the relocation of any fire hydrant and/or valves from the development's vehicular footway crossings.
-  the retention and/or relocation of any existing foul water lines that currently exist within the site.
-  any new or existing installations of electrical pillar boxes, pad mounted transformers (PMTs), water reticulation mains, water meters and the like, must be installed/relocated to their ultimate alignment relative to the new property boundary and clear of the usable footpath areas irrespective of the alignment of the existing services/conduits. 

 Note:   - The cost of moving services, utilities and assets is the responsibility of the Developer. The permission of the service, utility or asset owner will be required. Council permission is required if street trees, stormwater gullies/drains, and swales are affected. Queensland Urban Utilities permission is required if water supply and sewerage services are affected
 
           - Standard utility alignments may be found on Council’s ‘Brisbane Standard Drawings’ 1013 to 1016 inclusive.
            - Applicants must liaise with the appropriate service authorities. Typical underground services and/or conduits to be constructed include power, phone, telecommunications, sewer (including private combine drains) stormwater and gas, if applicable.

 

 

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
59(a) Submit As Constructed Drawings

Submit to Development Services "As Constructed" drawings, including an asset register, prepared by a Registered Professional Engineer Queensland.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
As indicated
59(b) Submit Certification

Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the requirements of this condition.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
60)   Telecommunications

Submit to Development Services, certification from an authorised telecommunications carrier/contractor, that the following works and infrastructure have been undertaken and installed in accordance with telecommunications industry standards:

a) Provide telecommunications to the subject buildings, lead-in conduits and equipment space in a suitable location within the buildings, to suit the carrier of choice.
b) If new pits and conduit infrastructure are required to be installed within the road reserve fronting the site, it must be suitably sized to cater for future installation of fibre optic cables.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
61)   Agreement with Electricity Supplier

Submit to Development Services, evidence of an agreement with an electricity supplier to provide necessary services to the development in accordance with the relevant Brisbane Planning Scheme Codes.

Where development is proposed within an established area of overhead electricity supply and the electricity supplier determines that a property pole is the appropriate solution to supply electricity to the development, the developer must be responsible for the installation of the property pole(s).

In the above circumstances, submit to Development Services, certification from the developer’s electrical consultant confirming that the above installation has been completed in accordance with the relevant AS/NZS Standards and the Queensland Electrical Connection and Metering Manual.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
62)   Permanent Vehicle Crossover

Provide a 3.650 metre wide modified type B1 permanent vehicle crossover to the Picot Street frontage(s) of the site in accordance with the relevant Brisbane Planning Scheme Codes and located as shown on the approved DRAWINGS AND DOCUMENTS.

Written consent must be obtained from BCC – Field Services, Asset Services Arborist prior to any works occurring that will either impact on or require removal of a street tree (this includes pruning and excavation within the root zone/ canopy of the tree)

At all times during construction of the crossover, safe pedestrian access along the site frontage must be maintained.

Note: No further driveway permit is required however additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
63)   Redundant Crossover

Remove the redundant existing vehicle crossing(s) on the frontage(s) of the site and reinstate the kerb and channel, road pavement, footways and footpaths in accordance with the relevant Brisbane Planning Scheme Codes.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
Standard Advice
 
Timing
64)   Construction Noise and Dust Emissions

Pursuant to the Environmental Protection Act 1994, all development involving the emission of noise and dust from building and/or construction activities, must ensure that the emissions are in accordance with the requirements of the Act.
The Environmental Protection Act 1994 prescribes that:

1. A person must not carry out building work in a way that makes an audible noise-
-  on a business day or Saturday, before 6.30a.m. or after 6.30p.m; or
-   on any other day, at any time. 
2. The reference in subsection (1) to a person carrying out building work-
-  includes a person carrying out building work under an owner-builder permit; and
-  otherwise does not include a person carrying out building work at premises used by the person only for residential purposes.

Note: A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management delegate Development Services.

 
As indicated
 
65)   Currency Period

The currency period for this development approval is stated in the Decision Notice and is expressed as a date.

This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016.

 
As indicated
 
66)   Cultural Heritage

Aboriginal cultural heritage is protected under the Aboriginal Cultural Heritage Act 2003.  This Act establishes a cultural heritage duty of care and in section 23(1) mandates that a person who carries out an activity must take all reasonable and practicable measures for ensuring activities are managed to avoid or minimise harm to Aboriginal cultural heritage.

The Duty of Care Guidelines gazetted pursuant to the Aboriginal Cultural Heritage Act 2003 provide guidance on identifying and protecting Aboriginal cultural heritage to fulfil the duty of care.

For further information contact the relevant Queensland State Government Department (Department of Aboriginal and Torres Strait Islander Partnerships).

 
As indicated
 
67)   Damage to Trees on Adjoining Land

Please note that any damage caused to vegetation on adjoining land as a result of exercising this development approval may result in an offence under other legislation (e.g. Natural Assets Local Law) and/or civil action

 
As indicated
 
68)   Fire Ant Movement Controls

To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected.

These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products.

Breaches of these controls can potentially impact the community, economy and the environment.  Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014.

For further information contact the relevant Queensland State Government department on 13 QGOV.

 
As indicated
 
69)   Rooming Accommodation - Self-contained unit

This approval does not authorise any resident, tenant or provider to occupy a self-contained unit as defined under the Residential Tenancies and Rooming Accommodation Act 2008.  Each room identified within the building/s is not to form a self- contained unit which includes a kitchen (cooking facilities), bathroom and toilet facilities.

 
As indicated
 
70)   Water and Wastewater

Services for water and wastewater (sewerage) are no longer under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections requires a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. Any necessary Water Approval must be obtained from the relevant distributor- retailer (currently operating as Queensland Urban Utilities for the Brisbane City Council area).

For the purpose of approving plans of subdivision pursuant to Schedule 18 of the Planning Regulation 2017 (whether in relation to a development permit for Reconfiguring a Lot or a Building Format Plan subsequent to a development permit for a Material Change of Use), documentary evidence, issued by the relevant distributor-retailer, must be provided to Council to verify that the conditions of any necessary Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009, have been complied with.

 
As indicated
 



Permit to Which These Conditions Relate: DA - PA - Building Work
Activity(ies): rooming accommodation
Stage: Rooming accommodation in the Traditional building character overlay

General/Planning Requirements
 
Timing
71)   Maintain the Approved Development

Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions.

 
At all times
 
72)   Approved Drawings and Documents

A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers.

Note: This condition is imposed to ensure compliance with the conditions of development approval.

 
While site/operational/building work is occurring
 
73)   Carry Out the Approved Development

Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS.

Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks).  Permission to enter neighbouring properties must be obtained from the relevant property owners.

 
While site/operational/building work is occurring
 
74)   Complete All Building Work

Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS.

Note: Building work must also be completed in accordance with any other current development approval.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
75)   Visitor Parking

Visitor car parking spaces must:
-  Be clearly labelled as 'Visitor Parking';
-  Remain unimpeded by landscaping, water tanks, storage (temporary or otherwise), gates or any other fitting, fixture or structure; and
-  Provide 24 hour unrestricted access for all bona fide visitors to the whole site.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
76)   Outdoor lighting

Outdoor lighting is to be in compliance with AS 4282-1997 - Control of the obtrusive effects of outdoor lighting.

 
At all times
 
77)   Limitation of use

The approved Rooming accommodation must operate in accordance with the definition of ‘suite’ in the Brisbane Infrastructure Charges Resolution (No. 9) 2020, as detailed below:

‘Suite’ means a number of connected rooms one of which is a bedroom in which an individual or a group of two or more related or unrelated people reside with the common intention to live together on a long term basis and who make common provision for food or other essentials for living.

The approved Rooming accommodation is to have a maximum of 4 dwelling suites with a total of 24 rooms.

 

 

 
Prior to the commencement of the use and then to be maintained
 
Architecture
 
Timing
78)   External Details

External details of the building, facade treatment and external materials and finishes must be consistent with the approved DRAWINGS AND DOCUMENTS.

Note: The requirement to use particular materials and finishes is imposed only for the purpose of achieving a built form outcome that displays architectural merit. Council has not assessed the materials and finishes for compliance with the Building Act, the Building Fire Safety Regulation, the Building Regulation, the Building Code of Australia, the Queensland Development Code, relevant Australian Standards, fire safety standards or any other relevant requirement of a statutory authority with regard to building work.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
79)   Overall Height

The overall height of the building(s) must be in accordance with the floor and roof levels and overall height shown on the APPROVED DRAWINGS AND DOCUMENTS.

NOTE: Where there is a conflict with the floor heights shown on the APPROVED DRAWINGS and the conditions in this approval that stipulate minimum height clearance for undercover car parking, the height clearance conditions prevail.

 
While site/operational/building work is occurring and then to be maintained
79(a) Submit Certification

Submit to Development Services certification from a registered surveyor confirming that the 'as constructed' floor and roof levels and overall height are in accordance with the requirements of this condition.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
80)   Provide Pedestrian Prioritised Pathway

Provide a pedestrian prioritised pathway from the street frontage to Buildings A, B, C and D. The pathway must be differentiated in colour and texture from the driveway surface.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
81)   Screen Air Conditioning and Other Plant Enclosures

Install and maintain suitable screening to all air conditioning, lift motor rooms, plant and service facilities located at the top of or on the external face of the building. The screening structures must be constructed from materials that are consistent with materials used elsewhere on the facade of the building. There must be no individual external air conditioning units located on balconies.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
82)   Screening

Provide screening to windows of habitable rooms, balconies, landings, terraces and decks of the proposed dwelling(s) in accordance with the approved DRAWINGS AND DOCUMENTS and the following requirements.

Where any windows of habitable rooms of the proposed dwelling(s) are within 2m at ground floor level or 9m above ground floor level of adjoining neighbouring dwellings' windows to habitable rooms, provide suitable screening in accordance with the following:

Suitable screening must be:

For windows:
-  Sill heights of 1.5m above floor level; or
-  Fixed obscure glazing in any part of the window below 1.5m above floor level; or
-  Fixed external screens to any part of the window below 1.5m above floor level, or
-  Fencing to a minimum 1.8m above ground floor level (only applies to overlooking from windows at ground floor level).

For balconies, landings, terraces and decks facing the side boundaries of the site:
-  Fixed screening as shown on the approved DRAWINGS AND DOCUMENTS.

Note: Screening devices must be either solid translucent screens, perforated or slatted panels, or fixed louvres that are permanent, be durable and fixed. Screening devices must have a maximum of 25% openings, with a maximum opening of 50mm.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
Landscape Architecture and Open Space Planning
 
Timing
83)   Streetscape Works - Neighbourhood Street

Carry out streetscape improvement works including concrete path, turf and street trees to the verge to a Neighbourhood Street Minor standard in accordance with the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD), the requirements of this condition and the Infrastructure Design Planning Scheme Policy including sections 3.7.4.4 and 3.7.5.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
83(a) Concrete Path

Install a 1.2m wide broom finished standard Portland grey concrete path. The path on the southern side of the driveway is to be setback 1.3m from the back of kerb. The path on the northern side of the driveway is to align with the existing path on the verge that adjoins the development to the north.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
As indicated
83(b) Submit As-Constructed Drawings

Submit to Development Services "As Constructed" plans including an asset register, checked by a Registered Professional Engineer Queensland, certifying that the concrete path works have been completed in accordance with relevant Brisbane Planning Scheme Codes/Policies.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
As indicated
83(c) Turf

Install turf to the full width of the verge excluding any concrete path required by this condition.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
As indicated
 
84)   Landscape the Site - Self Certification

Landscape the site in accordance with the requirements of this condition.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
84(a) Detailed Landscape Plan for Self Certification

Prepare a Detailed Landscape Plan at a scale of 1:100 for all on-site landscape works including planting areas identified on the approved DRAWINGS AND DOCUMENTS. The plan must be prepared by a Registered Landscape Architect and must comply with the relevant Brisbane Planning Scheme Codes.

In addition to the requirements listed above, the plan must include the following:

. Deep planting areas

· Deep planting areas as shown on the approved drawings, open to the sky and with no underground development including retaining wall footings with the exception of existing underground infrastructure.

· Provide tree planting in accordance with the approved drawing numbered 2.10 Issue J, received 2 April 2026 and amended in red 23 April 2026.

Side and rear boundaries

· Provide tree planting in accordance with the approved drawing numbered 2.10 Issue J, received 2 April 2026 and amended in red 23 April 2026.

Containerised planting

· Clear identification of the location, width and depth of containerised planting.

· Minimum internal depths and widths as shown on approved plans

· A reticulated drip irrigation system to all containerised planting areas, with drainage connected to the stormwater system; the irrigation system must be connected to a non-mains water source.

Specifications

· Plant selection and densities to achieve full surface coverage within 2 years of planting

· Unless otherwise specified, trees provided as 45 litre stock or larger, staked and tied, and complying with Australian Standards

· Mulch and soil to all garden areas to meet Australian Standards

· Soil media ameliorated to increase water-holding abilities

· Details of a 12-week establishment period.

Timing: Prior to building work commencing.

 
As indicated
84(b) Certify Detailed Landscape Plan

On completion of the Detailed Landscape Plan, submit to Development Services:

·         Brisbane City Council Form CC10616 - Landscape Design Certificate prepared by a Registered Landscape Architect to certify that the Detailed Landscape Plan complies with the requirements of this condition

·         A copy of the certified Detailed Landscape Plan.

Timing: Prior to building work commencing.

 
As indicated
84(c) Implement Certified Detailed Landscape Plan

Carry out the landscape work in accordance with the above certified detailed Landscape Plan.

 

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
84(d) Certify Work

On completion of the landscape work, submit to Development Services:

·         Brisbane City Council Form CC10613 - Landscape Works Certificate prepared by a Registered Landscape Architect or licensed Landscape Contractor to certify the completed landscape work complies with the certified Detailed Landscape Plan

·         A copy of the as- constructed certified Detailed Landscape Plan.

 

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 

 
As indicated
84(e) Maintain Landscape Work

Maintain the landscape work generally in accordance with the certified Detailed Landscape Plan.

 

Timing: To be maintained.

 
As indicated
 
Pollution
 
Timing
85)   Air Emissions

 

Vehicle exhaust fumes are released via exhaust vent outlets which are directed away from any sensitive use and include the following:            

-       air emissions are not to cause an odour or air emission which is detectable and disturbing at a sensitive use; and

-        ensures that exhaust vents from any basement/enclosed car park are separated from any sensitive use by a minimum of 15m and 6m from intakes and natural ventilation openings.

 

 

 

 
Prior to the commencement of the use and then to be maintained
 
86)   Acoustic Fence - General

Erect a 2.0m high (relative to the finished RL of the driveway / pathway) acoustic fence along the northern and southern boundaries of the site adjacent to the driveway / pathway as shown on the approved drawings numbered 2.10 Issue J, received 2 April 2026 and amended in red 23 April 2026. The acoustic fencing must:
- Be constructed of a material with a minimum surface area density of 12.5kg/m2;
- Be constructed of an aesthetically pleasing weather-resistant material such as fibre cement, painted or treated timber, brick, concrete or a combination thereof;
- Have returns at any opening or provide some other means of blocking line of site from source to receiver such that the effectiveness of the fence is not reduced;
- Be continuous and gap free.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
86(a) Certification

Submit to Development Services certification from a person who is a Member or eligible to be a Member of the Australian Acoustic Society that the constructed acoustic fence complies with the above requirements.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
87)   Dampening of Grilles and Metal Plates

All metal grilles, metal plates or similar located within vehicle parking and manoeuvring areas must be securely fastened and meet the requirements of AS3996:2019, Access covers and grates.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
88)   Plant and Equipment Certification

Following the installation of all mechanical plant and equipment (e.g. air conditioning, mechanical ventilation and refrigeration equipment and heat pump hot water systems), submit to Development Assessment certification that the plant and equipment is adequately noise- attenuated and is in accordance with the criteria of the relevant Brisbane Planning Scheme Codes/Policies.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
Engineering
 
Timing
89)   Retaining Walls

Design and construct all retaining walls and associated fences, in accordance with the relevant Brisbane Planning Scheme Codes and including the following:

-  All retaining walls including the footings, must be located wholly within the property boundary of the site where works are occurring
-  Retaining walls to stabilise excavation must be set back off property boundaries to accommodate subsoil drainage without encroachment into the neighbouring property. This set back may vary depending on the height, structure and design of the retaining wall, including loadings from neighbouring properties, and to provide a surface drain along the top of the retaining wall
-  Retaining walls that are greater than 1.0m in height must be vertically and horizontally tiered by a ratio of 1:1 unless an alternative has been approved by Development Services
-  Runoff from surface drains and subsoil drainage associated with the retaining wall must be collected and conveyed to a lawful point of discharge and must not cause any ponding, nuisance or disturbance to adjacent property owners
-  Retaining walls in excess of 1.0m in height must be designed and certified by a Registered Professional Engineer Queensland
-  Retaining walls facing onto Council property (including the road reserve and parkland) must not be constructed from timber.

 
As indicated
89(a) Certification of Retaining Walls

For retaining walls over 1.0m in height, obtain certification from a Registered Professional Engineer Queensland that the design and construction of the retaining wall and ancillary drainage is in accordance with this condition.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
As indicated
 
90)   Grant Easements

Grant the following easement(s):

i) A 0.9 metre wide easement for underground drainage, and access purposes as may be required, in favour of Brisbane City Council.

ii) A 6 metre wide volumetric easement limited to 12 m AHD along the east boundary for open cut, overland flow and access purposes for the 2% AEP for overland flow flooding, in favour of Brisbane City Council.
Note: These easements include the provision for Council to obtain access.


Timing: Prior to commencement of use (MCU) or as part of the registration of the plan of subdivision notated by Council (ROL), and then to be maintained.

 
As indicated
90(a) Submit Plan of Subdivision and Documentation (Non-Council Easement)

Submit for the approval of Development Services, a plan of subdivision showing the easement and the necessary easement documentation to demonstrate compliance with the requirements of this condition.

Note: Easements not in favour of the Brisbane City Council must have the necessary documentation prepared by the applicant's private solicitors.

Timing: As part of the submission of the request pursuant to Schedule 18 of the Planning Regulation 2017 for Council's notation on the plan of subdivision necessary to comply with this condition (MCU) or give effect to this approval (ROL).

 
As indicated
90(b) Submit Plan of Subdivision and Documentation (Council Easement)

Submit for the approval of Development Services, a plan of subdivision showing the easement and a request for Council to prepare the necessary easement documentation to demonstrate compliance with the requirements of this condition.

Note: Easements in favour of the Brisbane City Council must have the necessary easement documentation prepared by the Brisbane City Council, free of cost to Council.

Timing: Prior to submission of the request pursuant to Schedule 18 of the Planning Regulation 2017 for Council’s notation on the plan of subdivision necessary to comply with this condition (MCU) or give effect to this approval (ROL).

 
As indicated
90(c) Lodge Notated Plan and Documentation

Lodge the plan of subdivision notated by Council pursuant to Schedule 18 of the Planning Regulation 2017 and the necessary easement documentation with the Registrar of Titles for the relevant Queensland State Government Authority.

Timing: Prior to commencement of use (MCU) or as part of the registration of the plan of subdivision notated by Council (ROL).

 
As indicated
90(d) Submit Evidence of Registration

Submit to Development Services evidence of the registration of the necessary easement documentation.

Timing: Within one month of the registration of the easement documentation.

 
As indicated
 
91)   On-site Erosion (medium risk)

Minimise on-site erosion and the release of sediment or sediment laden stormwater from the site at all times.

Timing: While site works are occurring and until all exposed soil areas are permanently stabilised against erosion.

 
As indicated
91(a) Prepare Erosion and Sediment Control Plan

Prepare Erosion and Sediment Control (ESC) Plan(s), and provide design certificates for the site in accordance with the relevant Brisbane Planning Scheme Codes.
The plan(s) and design certificates must be certified by a Certified Professional in Erosion and Sediment Control (CPESC) or a Registered Professional Engineer Qld (RPEQ) with suitable qualifications and experience in erosion and sediment control.
Documentary evidence demonstrating appropriate qualifications in erosion and sediment control must be provided to the Council upon request.
At least 10 days prior to either the pre-start meeting or commencement of site works, submit copies of design certificates to Council’s Compliance and Regulatory Services at:
CARS-ESC@brisbane.qld.gov.au

Timing: Prior to pre-start meeting or commencement of any site works and to be maintained until all exposed soil areas are permanently stabilised against erosion.

 
As indicated
91(b) Attend a Pre-Start meeting

Arrange and attend a pre-start meeting with an Erosion & Sediment Control Officer from Council’s Compliance and Regulatory Services.  Requests are to be made when submitting copies of all required documentation, including design certificates to: CARS-ESC@brisbane.qld.gov.au

Timing: Prior to commencement of any site works causing exposure of soil.

 
As indicated
91(c) Implement Certified Erosion and Sediment Control Plan

Implement the certified ESC plan(s) to maintain compliance with all parts of the relevant Brisbane Planning Scheme Codes, while site works are occurring and until all exposed soil areas are permanently stabilised against erosion.
The plan(s) and design certifications must be available on site at all times for inspection by Council officers until all exposed soil areas are permanently stabilised against erosion.
Minimise on-site erosion and the release of sediment or sediment laden stormwater from the site at all times.

Timing: While site works are occurring and until all exposed soil areas are permanently stabilised against erosion.

 
As indicated
 
92)   Information Signage

Erect an "Information Sign" on the subject property in accordance with Council’s general requirements for signage and in accordance with the requirements outlined below:

a)  The sign should provide a brief description of the development proposed;
b)  The sign is to list the name, postal and/or email address and a contact telephone number for the following parties (where relevant) that are undertaking work on the site:

     Developer;
     Project Coordinator;
     Architect/Building Designer;
     Builder;
     Civil Engineer;
     Civil Contractor/s; and
     Landscape Architect;

c)  The lettering on the sign is to be at least 25 millimetres in height, be of regular weight and in sentence case;
d)  The sign is to be a minimum size of 1,200 millimetres by 900 millimetres;
e)  The maximum area of the sign is to be 2.0m2;
f)  The sign is to be positioned as follows:

     located centrally along the road frontage of the site to Picot Street;
     located on or within 1.5 metres of the road frontage;
     mounted at least 300 millimetres above ground level; and
     clearly visible from the street for a pedestrian;

g)  The sign is to contain no commercial or corporate advertising other than the name, logo or slogan of the parties outlined in part (b) of this condition;
h)  The sign is to be non-illuminated; and
i)  Both the sign and the supporting structure are to be made of weatherproof material and to be properly maintained at all times;

Timing: Prior to site works commencing and then to be maintained until completion of the development for all stages.

 
As indicated
 
93)   Construction Management Plan (Minor)

Carry out development in accordance with a Construction Management Plan (Minor) prepared in accordance with the requirements of this condition.

 
While site/operational/building work is occurring
93(a) Prepare Management Plan (minor)

Prepare a Construction Management Plan for the subject site.

 

The Construction Management Plan must be available on site at all times and must show, but not be limited to the following details where applicable, for the demolition (where in a Centre zone, a Mixed use zone or where the demolition is otherwise assessable development), excavation and construction phases of the approved development. Separate Construction Management Plans may be appropriate for the individual components:

 

-  Provision of alternative pedestrian route/s, past or around the site

-   Existing and proposed kerbside allocation signs and line marking (such as bus stops, loading zones and parking meters and/or ticket dispensers)

-  Temporary vehicular access points

-  Management and mitigation strategies for the impact of dust, noise and vibration upon adjoining and nearby properties

-   Employee and visitor parking areas (if provided)

-   Provision for loading and unloading materials including the location of any remote loading sites

-  The location of materials, structures, plant and equipment to be stored or placed on the construction site

-  The anticipated staging and programming

-  Allowable work times as set by the Queensland Environmental Protection Act 1994 (section 440).  A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management Delegate Development Services.

 

The Construction Management Plan must be supported by Permits or written approvals from the relevant Council sections or other body listed below (where applicable to the Plan) to ensure all potential impacts to Council and other infrastructure have been addressed:

(i) Work Zones / Temporary Road Closures / Taxi Ranks - (Congestion Reduction Unit, Planned Incident Management / Temporary Road Closures);

(ii) Full/Partial Footway-Footpath Closures – (Brisbane Infrastructure – Congestion Reduction Unit);

(iii) Street Lighting - (Brisbane Infrastructure - Asset Services-City Lighting);

(iv) City Cycle bike stations and JCDecaux Advertising Signage (including obstruction to sight lines for such advertising - owned by JCDecaux)- (Brisbane Infrastructure - Transport Planning and Strategy, Contract Management section);

(v) Street Furniture (excluding bus stops) - (Brisbane Infrastructure, Transport Network Operations, Roads and Drainage);

(vi) Waste Bins - (Brisbane Infrastructure, Waste Service);

(vii) Bus Stops/Shelters - (Brisbane infrastructure - Transport Planning and Strategy-Strategic Planning; and Brisbane Transport - Network Planning & Bus Operations);

(viii) Street Trees - (Brisbane Infrastructure - Asset Services - Arboriculture);

(ix) Parking Meters/Spaces - (Brisbane Infrastructure - City Parking);

(x) Traffic Signals - (Brisbane Infrastructure - Traffic Signals Operations);

(xi) Stormwater Gullies/Pits etc - (Brisbane Infrastructure - Roads and Drainage);

(xii) Other service providers - (e.g. Energex, Telstra, Optus, Queensland Urban Utilities, AGL).

 

Note: The Construction Management Plan is not required to be approved by Development Services.

 

At least 10 days prior to commencement of site works, submit a copy of the Construction Management Plan to Council’s Development Services Branch at the following mailbox: engineeringservices@brisbane.qld.gov.au quoting the planning development approval reference number.

 

Timing: Prior to site/operational/building work commencing

 
As indicated
93(b) Construction Management Plan (Minor) - Documentation on Site

Legible copies of the Construction Management Plan and current permits must be kept on site and be made available on request at all times.

Timing: While site/operational/building work is occurring

 
As indicated
93(c) Construction Management Plan (Minor) - Works to be Performed Out of Hours

Obtain approval from Development Services for any work that is proposed to be undertaken outside of normal business hours - 6:30am to 6:30pm, Monday to Saturday.
Timing: Prior to site/operational/building work commencing.

 
As indicated
93(d) Implement Construction Management Plan (Minor)

Carry out the development in accordance with the Construction Management Plan prepared in accordance with this condition.
Timing: While site/operational/building work is occurring.

 
As indicated
 
94)   Protect Existing Infrastructure

Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure. Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations. The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements.

 
While site/operational/building work is occurring
94(a) As Constructed Drawings

Where alterations to existing infrastructure are required, submit to Development Services "As Constructed" drawings showing all new and/or rectification works and an asset register, prepared by a Registered Professional Engineer Queensland.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
As indicated
94(b) Submit Certification

Where alterations to existing infrastructure are required, submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
As indicated
 
95)   Remove Improvements & Obstructions From Truncation and Dedication

Remove all improvements (fences, gates, letter boxes, garden beds and plots and other constructed items, etc.) and obstructions (existing earth banks, vegetation, etc.) from the area of the dedicated road and reinstate the area as footway in accordance with the relevant Brisbane Planning Scheme Codes.

Any new or existing installations of electrical pillar boxes, pad mounted transformers (PMTs), water meters and the like, must be installed/relocated to their ultimate alignment relative to the new property boundary and clear of the usable footpath areas irrespective of the alignment of the existing services/conduits. 

 Note:   - The cost of moving services, utilities and assets is the responsibility of the Developer. The permission of the service, utility or asset owner will be required. Council permission is required if street trees, stormwater gullies/drains, and swales are affected. Queensland Urban Utilities permission is required if water supply and sewerage services are affected

            ; - Standard utility alignments may be found on Council’s ‘Brisbane Standard Drawings’ 1013 to 1016 inclusive.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
95(a) Certify the Work

Submit to Development Services certification from a Registered Surveyor or Registered Professional Engineer Queensland that the above work has been completed in accordance with this condition.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
96)   Filling and / or Excavation (Minor)

Filling and/or excavation works on the site must be in accordance with the relevant Brisbane Planning Scheme Codes.

No earthworks whether cut or fill are to be undertaken within the new 6 metre wide overland flow easement at the east boundary of the site.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
96(a) Prepare Earthworks Drawings

Earthworks drawings must be prepared and certified by either: a Registered Professional Engineer Queensland or a suitably qualified geotechnical and structural consultant, in accordance with the relevant Brisbane Planning Scheme Codes.

The drawings must include the following:

-  maintenance of access roads to and from the site such that they remain free of all fill material and are cleaned as necessary
-  preservation of all drainage structures from the effects of structural loading generated by the earthworks
-  protection of adjoining properties and roads from ponding or nuisance from stormwater.

Timing: Prior to site/operational/building work commencing.

Note: The Earthworks drawings are not required to be submitted for Council approval.

 
As indicated
96(b) Implement and Maintain the Earthworks

Carry out and maintain the earthworks in accordance with the certified drawings.

Note: A copy of the certified Earthworks Drawings must be available on- site for inspection by Council Officers during these works.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
As indicated
 
97)   Repair Damage to Kerb, Footpath Or Road

Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
97(a) Interim Repairs

If at any time during the construction phase of the approved development, damage to the existing kerb and channel, footpath or roadway creates unsafe, unreasonable and/or not fit for purpose conditions as assessed by Council, interim repairs must be undertaken as directed by Asset Services.

Note: Any interim repairs required to be undertaken shall not be considered to satisfy the requirements of this condition for the permanent repair of the infrastructure prior to the issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

Timing: While site / operational / building works is occurring

 
As indicated
 
98)   Remove Redundant Drainage Outlets

Remove any redundant drainage outlets from the kerb and channel including any associated pipe work across the footway and reinstate the kerb and channel and the footway area in accordance with the relevant Brisbane Planning Scheme Codes.

Note: Guidance for the preparation of drawings and/or documents to comply with this condition is provided in the Brisbane Planning Scheme Policies.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
99)   Access, Grades, Manoeuvring, Carparks, Signs and Line Marking

Construct access, parking and manoeuvring for vehicles on site in accordance with the relevant Brisbane Planning Scheme Codes, as indicated on the approved DRAWINGS AND DOCUMENTS, including the following:

i. A pavement of minimum Local road standard or equivalent surface material (including associated drainage) to the area on which motor vehicles will be driven and/or parked.

ii. Parking on the site for 5 resident/tenant cars (including 1 ride share car and 1 parking space for people with disabilities) and 1 visitor car and provide for the loading and unloading of vehicle(s) within the site. The ride share car must be provided and administered by the facility management and this car space must be identified by signage, accessible 24 hrs/ 7 days/week, and provided for exclusive use for on site residents only.

iii. Provide 12 secure bicycle parking spaces including 4 shared e-bicycles.

iv. A minimum of 2.3 metres height clearance to all undercover parking areas and a minimum of 2.5 metres above parking spaces for people with disabilities.  The minimum clear height must be measured to the lowest protrusion from the ceiling (e.g. fire sprinklers, services, lighting fixtures, signs, etc).

v. A height clearance sign located at the entrance(s) to undercover car parking areas and a directional visitor parking sign clearly visible from the vehicle entrance to the site.

vi. An appropriate area for the storage of refuse on the site.

vii. The internal paved areas must be signed and delineated in accordance with the approved drawings and Manual of Uniform Traffic Control Devices - Queensland Department of Transport and Main Roads - Transport Operations (Road Use Management) Act 1995.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
99(a) Submit certification

Submit to Development Services, certification from a Registered Professional Engineer Queensland, that the above requirements have been implemented in accordance with this condition.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
100)   Minimum Flood Planning Levels

Design and construct all proposed building pad levels, floor levels and ancillary structures to the appropriate flood planning level with freeboard (where required) in accordance with the relevant Brisbane Planning Scheme Codes.

The minimum habitable floor level must be 11.87 metres AHD.

The minimum non- habitable floor level must be 11.67 metres AHD.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
100(a) Submit Certification

Submit to Development Services "As-Constructed" drawings prepared by a Registered Surveyor. The Registered Surveyor must certify that the development has been constructed in accordance with this condition.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
 
101)   Stormwater - Flood Study

Construct the development in accordance with the approved Flood Investigation Report prepared by HCE Engineers numbered 19123 Rev 0, received 6 November 2019.

No earthworks including cut or fill are to be undertaken within the new 6 metre wide overland flow easement at the east boundary of the site.

Any fencing in the overland flow path must be open at the bottom for 100mm minimum, and with a minimum of 50% openings above that.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
101(a) Certification

Submit to Development Services certification from a Registered Professional Engineer Queensland that the development has been constructed in accordance with the approved flood study.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
As indicated
 
102)   Refuse Collection - Kerb Side (external road or internal private road)

Refuse and recycling bins for the proposed development must be collected from the kerb side by Private Contractor. However, bins must not be left unattended kerbside, generally in accordance with the Waste collection proposal outlined in the approved waste assessment letter prepared by TTM dated 10/3/2020.

Waste collection must be undertaken twice weekly as a minimum and bin numbers must be minimised/restricted so they do not impact on neighbours frontage

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
103)   Refuse Storage - Kerb Side Collection

Provide a covered and screened waste enclosure to accommodate the type and quantity of waste/recycling bins required to service the development.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
104)   Land for Transport Network - Road (Non- trunk)

Dedicate as road including the following:

i. A widening along the full length of the Picot Street frontage of the site to provide a 2.5 metre wide verge;


NOTE: This condition is imposed under section 145 of the Planning Act 2016.

Timing: Prior to commencement of use (MCU) or as part of the registration of the plan of subdivision notated by Council (ROL).

 
As indicated
104(a) Submit Plan of Subdivision (MCU only)

Submit for the approval of Development Services, a plan of subdivision showing the land to be dedicated for road to demonstrate compliance with the requirements of this condition.

Timing: As part of the submission of the request pursuant to Schedule 18 of the Planning Regulation 2017 for Council’s notation on the plan of subdivision necessary to comply with this condition.

 
As indicated
104(b) Lodge Notated Plan (MCU only)

Lodge the plan of subdivision notated by Council pursuant to Schedule 18 of the Planning Regulation 2017 with the Registrar of Titles for the relevant Queensland State Government Authority.

Timing: Prior to commencement of use.

 
As indicated
104(c) Submit Evidence of Registration (MCU only)

Submit to Development Services, evidence of the registration of the required plan of subdivision.

Timing: Within one month of the registration of the plan of subdivision.

 
As indicated
 
105)   Work for Transport Network - Road (Non-trunk) - External

Construct the following roadwork with any associated drainage, footpath, site access and services including street lighting for the Transport Network (Road) in accordance with the relevant Brisbane Planning Scheme Codes, the Manual of Uniform Traffic Control Devices - Queensland Department of Transport and Main Roads - Transport Operations (Road Use Management) Act 1995 and the AUSTROADS design standards:


  - Street lighting to a category P4 along the Picot Street frontage.


Note: This condition is imposed under section 145 of the Planning Act 2016.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
105(a) Submit Street Lighting Design Drawings

Submit for the approval of City Lighting, street lighting design drawings prepared and certified by a Registered Professional Engineer of Queensland (electrical) which show the proposed street lighting system in accordance with the relevant Brisbane Planning Scheme Codes.

 

Timing: Prior to site/operational/building work commencing.

 
As indicated
105(b) Pre-Start Meeting

Arrange and attend a pre-start meeting with Development Services.

 

Timing: Prior to site/operational work commencing.

 
As indicated
105(c) Implement Approved Drawings

Construct the works in accordance with the above approved drawings.

Timing: Prior to on-maintenance acceptance.

 
As indicated
105(d) Submit As Constructed Drawings

Submit to Development Services "As Constructed" drawings including an asset register and a pre-On-Maintenance Inspection Checklist, prepared by a Registered Professional Engineer Queensland.

 

Timing: Prior to on-maintenance inspection.

 
As indicated
105(e) Submit Certification

Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the above approved drawings.

Timing: Prior to on-maintenance inspection.

 
As indicated
 
106)   Lawful Point Of Discharge

Submit to Development Services, evidence of written consent for a lawful point of discharge from the owners of properties affected by any stormwater discharge from the site.

Note.  Refer to Council's website for a standard lawful point of discharge agreement template which is acceptable to Council.

 
Prior to site/operational/building work commencing
 
107)   Ponding of Stormwater

Carry out the approved development to ensure that adjoining properties and roads are protected from ponding or nuisance from stormwater as a result of the works.

Notes: If remedial works are necessary to comply with this condition, prior approval must be obtained from Development Services.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
108)   On Site Drainage - Minor

Provide a stormwater connection to all new or existing allotments and provide drainage infrastructure to ensure stormwater run-off from all roof and developed surface areas will be collected internally and piped in accordance with the relevant Brisbane Planning Scheme Codes to a lawful point of discharge.

The LPD for the front dwelling is the kerb/channel in Picot Street, and the LPD for the rest of the site is the existing stormwater pipe infrastructure in the neighbours property.

Note: Guidance for the preparation of drawings and/or documents to comply with this condition is provided in the Brisbane Planning Scheme Policies.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
108(a) Submit As Constructed Drawings

Where reconfiguring a lot, submit to Development Services "As Constructed" drawings prepared by a Registered Professional Engineer Queensland.

Timing: Prior to Council's notation of the plan of subdivision.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
108(b) Submit Certification

Where reconfiguring a lot, submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with this condition.

Timing: Prior to Council's notation of the plan of subdivision.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
 
109)   Up Stream Stormwater Drainage Connection - Minor

Provide a stormwater drainage connection for the future development of the adjoining upstream property at the south boundary designed for ultimate developed catchment conditions and connected to a lawful point of discharge. This pipe must be located in a 0.9 metre wide underground drainage easement.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
109(a) Prepare Stormwater Drawings

Prepare stormwater drawings and engineering calculations, certified by a Registered Professional Engineer Queensland in accordance with the relevant Brisbane Planning Scheme Codes.

Note:
-  Queensland Building and Construction Commission licensed hydraulic consultants may design the stormwater system for sites less than 2000m2 with an upstream catchment servicing no more than 4 residential lots.  This excludes stormwater drainage design (including subsoil drainage) of basements in flood planning areas and the design of any onsite stormwater detention system
-  Guidance for the preparation of drawings and/or documents to comply with this condition is provided in the Brisbane Planning Scheme Policies
-  A 225mm diameter pipe is the minimum size required to service an upstream development of any kind.

Timing: Prior to site/operational/building work commencing.

 
As indicated
109(b) Implement Certified Stormwater Drawings

Carry out the works in accordance with the above  stormwater drawings.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained.

 
As indicated
109(c) Submit As Constructed Drawings

Submit to Development Services "As Constructed" drawings prepared by a Registered Professional Engineer Queensland.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation on the plan of subdivision (ROL).

 
As indicated
109(d) Submit Certification

Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the above stormwater drawings.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation on the plan of subdivision (ROL).

 
As indicated
 
110)   Service Conduits and Mains

Provide and install all service conduits and meet the cost of any alterations to public utility mains, existing mains, services, street lighting or installations that are required to carry out the approved development. These works must be in accordance with the relevant Brisbane Planning Scheme Codes, and include the following, where applicable:

-  the provision of all services and/or conduits along the full length of any rear allotment access or access easement.
-   the breaking and/or relocation of any existing sewer combine drains.
-  the relocation of any fire hydrant and/or valves from the development's vehicular footway crossings.
-  the retention and/or relocation of any existing foul water lines that currently exist within the site.
-  any new or existing installations of electrical pillar boxes, pad mounted transformers (PMTs), water reticulation mains, water meters and the like, must be installed/relocated to their ultimate alignment relative to the new property boundary and clear of the usable footpath areas irrespective of the alignment of the existing services/conduits. 

 Note:   - The cost of moving services, utilities and assets is the responsibility of the Developer. The permission of the service, utility or asset owner will be required. Council permission is required if street trees, stormwater gullies/drains, and swales are affected. Queensland Urban Utilities permission is required if water supply and sewerage services are affected
 
           - Standard utility alignments may be found on Council’s ‘Brisbane Standard Drawings’ 1013 to 1016 inclusive.
            - Applicants must liaise with the appropriate service authorities. Typical underground services and/or conduits to be constructed include power, phone, telecommunications, sewer (including private combine drains) stormwater and gas, if applicable.

 

 

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
110(a) Submit As Constructed Drawings

Submit to Development Services "As Constructed" drawings, including an asset register, prepared by a Registered Professional Engineer Queensland.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
As indicated
110(b) Submit Certification

Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the requirements of this condition.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
111)   Telecommunications

Submit to Development Services, certification from an authorised telecommunications carrier/contractor, that the following works and infrastructure have been undertaken and installed in accordance with telecommunications industry standards:

a) Provide telecommunications to the subject buildings, lead-in conduits and equipment space in a suitable location within the buildings, to suit the carrier of choice.
b) If new pits and conduit infrastructure are required to be installed within the road reserve fronting the site, it must be suitably sized to cater for future installation of fibre optic cables.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
112)   Agreement with Electricity Supplier

Submit to Development Services, evidence of an agreement with an electricity supplier to provide necessary services to the development in accordance with the relevant Brisbane Planning Scheme Codes.

Where development is proposed within an established area of overhead electricity supply and the electricity supplier determines that a property pole is the appropriate solution to supply electricity to the development, the developer must be responsible for the installation of the property pole(s).

In the above circumstances, submit to Development Services, certification from the developer’s electrical consultant confirming that the above installation has been completed in accordance with the relevant AS/NZS Standards and the Queensland Electrical Connection and Metering Manual.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
113)   Permanent Vehicle Crossover

Provide a 3.65 metre wide modified type B1 permanent vehicle crossover to the Picot Street frontage(s) of the site in accordance with the relevant Brisbane Planning Scheme Codes and located as shown on the approved DRAWINGS AND DOCUMENTS.

Written consent must be obtained from BCC – Field Services, Asset Services Arborist prior to any works occurring that will either impact on or require removal of a street tree (this includes pruning and excavation within the root zone/ canopy of the tree)

At all times during construction of the crossover, safe pedestrian access along the site frontage must be maintained.

Note: No further driveway permit is required however additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
114)   Redundant Crossover

Remove the redundant existing vehicle crossing(s) on the frontage(s) of the site and reinstate the kerb and channel, road pavement, footways and footpaths in accordance with the relevant Brisbane Planning Scheme Codes.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
Standard Advice
 
Timing
115)   Construction Noise and Dust Emissions

Pursuant to the Environmental Protection Act 1994, all development involving the emission of noise and dust from building and/or construction activities, must ensure that the emissions are in accordance with the requirements of the Act.
The Environmental Protection Act 1994 prescribes that:

1. A person must not carry out building work in a way that makes an audible noise-
-  on a business day or Saturday, before 6.30a.m. or after 6.30p.m; or
-   on any other day, at any time. 
2. The reference in subsection (1) to a person carrying out building work-
-  includes a person carrying out building work under an owner-builder permit; and
-  otherwise does not include a person carrying out building work at premises used by the person only for residential purposes.

Note: A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management delegate Development Services.

 
As indicated
 
116)   Currency Period

The currency period for this development approval is stated in the Decision Notice and is expressed as a date.

This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016.

 
As indicated
 
117)   Cultural Heritage

Aboriginal cultural heritage is protected under the Aboriginal Cultural Heritage Act 2003.  This Act establishes a cultural heritage duty of care and in section 23(1) mandates that a person who carries out an activity must take all reasonable and practicable measures for ensuring activities are managed to avoid or minimise harm to Aboriginal cultural heritage.

The Duty of Care Guidelines gazetted pursuant to the Aboriginal Cultural Heritage Act 2003 provide guidance on identifying and protecting Aboriginal cultural heritage to fulfil the duty of care.

For further information contact the relevant Queensland State Government Department (Department of Aboriginal and Torres Strait Islander Partnerships).

 
As indicated
 
118)   Damage to Trees on Adjoining Land

Please note that any damage caused to vegetation on adjoining land as a result of exercising this development approval may result in an offence under other legislation (e.g. Natural Assets Local Law) and/or civil action

 
As indicated
 
119)   Fire Ant Movement Controls

To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected.

These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products.

Breaches of these controls can potentially impact the community, economy and the environment.  Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014.

For further information contact the relevant Queensland State Government department on 13 QGOV.

 
As indicated
 
120)   Rooming Accommodation - Self-contained unit

This approval does not authorise any resident, tenant or provider to occupy a self-contained unit as defined under the Residential Tenancies and Rooming Accommodation Act 2008.  Each room identified within the building/s is not to form a self-contained unit which includes a kitchen (cooking facilities), bathroom and toilet facilities.

 
As indicated
 
121)   Water and Wastewater

Services for water and wastewater (sewerage) are no longer under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections requires a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. Any necessary Water Approval must be obtained from the relevant distributor- retailer (currently operating as Queensland Urban Utilities for the Brisbane City Council area).

For the purpose of approving plans of subdivision pursuant to Schedule 18 of the Planning Regulation 2017 (whether in relation to a development permit for Reconfiguring a Lot or a Building Format Plan subsequent to a development permit for a Material Change of Use), documentary evidence, issued by the relevant distributor-retailer, must be provided to Council to verify that the conditions of any necessary Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009, have been complied with.

 
As indicated
 

** End of Package **