| Address of Site: | 275 GEORGE ST BRISBANE CITY QLD 4000 64 ADELAIDE ST BRISBANE CITY QLD 4000 69 ANN ST BRISBANE CITY QLD 4000 |
| Real Property Description of Site: | L20 SP.198665 L101 SP.102966 L102 SP.102966 |
| Aspects of development and type of approval: | DA - IPA - Carry Out Building Work Development Permit - Centre Activity
Outside Centre DA - IPA - Material Change of Use Development Permit and Preliminary Approval - Centre Activity Within Centre |
| Council File Reference: | A006992697 Permit Reference Number/s: DABW167948607; DAMC167948507. |
| Package Status: | APPROVED - Version 3 (29th of May, 2026 2:29:30 PM) |
| Package Generated: | 29/05/2026 |
| Ben CLOTHIER Principal Urban Planner Planning Services North Ben.Clothier@brisbane.qld.gov.au (07) 3403 7185 |
Kirstin BURROWES Senior Architect Architecture Team Kirstin.Burrowes@brisbane.qld.gov.au 0731785363 |
Craig SLACK Engineer Engineering Scoping craig.slack@brisbane.qld.gov.au (07) 3403 8888 |
| ASHLEY LANE DA Central BSQ (07) 3403 6650 |
MALCOLM ELLIOTT DA Central BSQ (07) 3403 5213 |
DARRELL CZISLOWSKI DA Central BSQ (07) 3403 6603 |
| JOS RUHLAND DA Central BSQ (07) 3403 5817 |
ROSALYN DERBIN DA West BSQ (07) 3403 4349 |
CHAD RYAN DA Central BSQ (07)3403 6116 |
| PHIL EASTGATE DA Central BSQ (07) 3403 5818 |
CASSANDRA SUN DA Central BSQ (07) 3403 5051 |
Llewellyn BATSON Principal Urban Planner Planning Services Special Assessment Llewellyn.Batson@brisbane.qld.gov.au (07) 340 34980 |
| Joseph SELWOOD Urban Planner Planning Services City West Joseph.Selwood@brisbane.qld.gov.au (07) 3178 1491 |
JAMES HEADING Principal Urban Planner Partnerships Team james.heading@brisbane.qld.gov.au (07) 3403 5591 |
John PIETRYSZYN Senior Engineering Officer Engineering Services South John.Pietryszyn@brisbane.qld.gov.au (07) 3178 7555 |
| Abby BANNAN Urban Planner Planning Services North Abby.Bannan@brisbane.qld.gov.au 31782418 |
DRAWINGS AND DOCUMENTS
| Drawing or Document | Number | Plan Date |
|---|---|---|
| Level 2 Plan / Package: 1 | 1006 REV E | 05-FEB-2007 |
| Level 4 Plan / Package: 1 | 1008 REV E | 05-FEB-2007 |
| Level 3 Plan / Package: 1 | 1007 REV E | 05-FEB-2007 |
| Level 1 Plan / Package: 1 | 1005 REV E | 05-FEB-2007 |
| Level 5 Plan / Package: 1 | 1009 REV E | 05-FEB-2007 |
| Level 6 Plan / Package: 1 | 1010 REV E | 05-FEB-2007 |
| Level 7-10 Plan / Package: 1 | 1011 REV E | 05-FEB-2007 |
| Level 11-13 Plan / Package: 1 | 1012 REV E | 05-FEB-2007 |
| Level 14 Plan / Package: 1 | 1013 REV E | 05-FEB-2007 |
| Level 31 Plan / Package: 1 | 1016 REV E | 05-FEB-2007 |
| Roof Plan / Package: 1 | 1018 REV E | 05-FEB-2007 |
| Section D / Package: 1 | 3004 REV E | 05-FEB-2007 |
| Section C / Package: 1 | 3003 REV E | 05-FEB-2007 |
| Section B / Package: 1 | 3002 REV E | 05-FEB-2007 |
| Section A / Package: 1 | 3001 REV E | 05-FEB-2007 |
| North Elevation - Ann Street / Package: 1 | 2001 REV E | 05-FEB-2007 |
| Level 32 Plan / Package: 1 | 1017 REV E | 05-FEB-2007 |
| Level 16-30 Plan / Package: 1 | 1015 REV E | 05-FEB-2007 |
| Pedestrian Access Volumetric Easement / Package: 1 | SK1 (Amended In Red 12-FEB-2007) | 07-FEB-2007 |
| Proposed Volumetric Easement / Package: 1 | 7467-7 (Amended In Red 12-FEB-2007) | 04-OCT-2006 |
| Level 15 Plan / Package: 1 | 1014 REV E | 05-FEB-2007 |
| Finishes Schedule - North Elevation / Package: 1 | 2101 | 10-JUL-2006 |
| Finishes Schedule - South Elevation / Package: 1 | 2102 | 10-JUL-2006 |
| Facade Detail 1 - Tower (Type A) / Package: 1 | 3101 (Amended In Red 12-FEB-2007) | 10-JUL-2006 |
| Facade Detail 3 - Tower (Type C) / Package: 1 | 3103 (Amended In Red 12-FEB-2007) | 10-JUL-2006 |
| Facade Detail 2 - Tower (Type B) / Package: 1 | 3102 (Amended In Red 12-FEB-2007) | 10-JUL-2006 |
| Finishes Schedule - East Elevation / Package: 1 | 2103 (Amended In Red 12-FEB-2007) | 10-JUL-2006 |
| Finishes Schedule - West Elevation / Package: 1 | 2104 (Amended In Red 12-FEB-2007) | 10-JUL-2006 |
| Facade Detail 4 - Tower (Type D) / Package: 1 | 3104 (Amended In Red 12-FEB-2007) | 10-JUL-2006 |
| Facade Detail 6 - Podium (Type F) / Package: 1 | 3106 (Amended In Red 12-FEB-2007) | 10-JUL-2006 |
| Facade Detail 7 - Podium (Type G) / Package: 1 | 3107 (Amended In Red 12-FEB-2007) | 10-JUL-2006 |
| Photomontages 1 / Package: 1 | 3152 | 10-JUL-2006 |
| Street Paving and Landscape Plan / Package: 1 | 706042/DA/LA01 REV A (Amended In Red 12-FEB-2007) | 18-AUG-2006 |
| Photomontages 3 / Package: 1 | 3154 | 10-JUL-2006 |
| Facade Detail 8 - Podium (Type H) / Package: 1 | 3108 (Amended In Red 12-FEB-2007) | 10-JUL-2006 |
| Facade Detail 5 - Podium (Type E) / Package: 1 | 3105 (Amended In Red 12-FEB-2007) | 10-JUL-2006 |
| Ground Level Plan / Package: 1 | 1004 REV E (Amended In Red 12-FEB-2007) | 05-FEB-2007 |
| Photomontages 2 / Package: 1 | 3153 REV A | 26-FEB-2007 |
| Basement Level 3 | TP-21-10_REV 2 | 10-APR-2018 |
| Basement Level 2 | TP-21-11_REV 2 | 10-APR-2018 |
| Basement Level 1 | TP-21-12_REV 3 | 10-APR-2018 |
| General Arrangement - North Elevation | DUR-1118-GS-SK01 Rev B | 14-MAY-2026 (Received) |
| General Arrangement - South Elevation | DUR-1118-GS-SK02 Rev B | 14-MAY-2026 (Received) |
| General Arrangement - East Elevation | DUR-1118-GS-SK03 Rev B (Amended In Red 29-MAY-2026) | 14-MAY-2026 (Received) |
| General Arrangement - West Elevation | DUR-1118-GS-SK04 Rev B (Amended In Red 29-MAY-2026) | 14-MAY-2026 (Received) |
APPROVAL CONDITIONS
| Permit to Which These Conditions Relate: | DA - IPA - Carry Out Building Work |
| Activity(ies): | Centre Activity Outside Centre |
| Stage: | Centre Activities (Office, Shop & Restaurant) & Building Work On The Site Of & On Land Adjoining A Heritage Place |
| Permit to Which These Conditions Relate: | DA - IPA - Material Change of Use |
| Activity(ies): | Centre Activity Within Centre |
| Stage: | Centre Activities (Office, Shop & Restaurant) & Building Work On The Site Of & On Land Adjoining A Heritage Place |
| 1) COPY OF PLANS ON SITE A legible copy of the approved drawings and documents bearing "Council Approval" and the Development Approval Conditions package is to be available on site at all times during construction and earthworks. GUIDELINE This condition is imposed to ensure compliance with the development conditions of approval. The copy of the conditions and plans should be located in any site management office or with the site foreman. Any copies of conditions or plans that are illegible shall be deemed to be non compliance with this condition of approval. |
As indicated |
| 2) CARRY OUT THE APPROVED DEVELOPMENT Carry out the approved development generally in accordance with the approved drawing(s) and/or document(s). GUIDELINE This condition refers to the approved plans, drawings and documents to which the approval relates and is the primary means of defining the extent of the approval. Approved plans, drawings and documents are stamped PLANS and DOCUMENTS referred to in the APPROVAL and are dated to reflect the date of approval of the application by Council's Delegate. |
While development is occurring on the site and then to be maintained |
| 3) COMPLETE ALL BUILDING WORK Complete all building work associated with this development approval, including work required by any of the following conditions. Such building work is to be carried out generally in accordance with the approved plans, drawing(s), and/or documents and, where the building work is assessable development, in accordance with a current development permit. GUIDELINE This condition is imposed to ensure all building work associated with the use are in place before the use commences. It is not appropriate that the site be used without such work being completed. Please note that the work referred to in this condition involves operational work and may therefore constitute 'assessable development'. The Council informs you there fore that this condition does not authorise assessable development to occur and a development permit may therefore be necessary. Please refer to the Council's information sheets. For any enquiries about this condition, please contact the Assessment Manager. |
Prior to commencement of use |
| 4) WIND STUDY Incorporate into the development the findings and recommendations of the 'Wind Assessment' report prepared by Wind Engineering Services and dated 28 June 2006. GUIDELINE This condition is imposed to protect the comfort of pedestrian areas particularly footpaths and open plaza areas from potential arising effects of wind tunnelling and updraught/down draught impacts from the construction of tower development. |
Prior to commencement of use |
| 5) MAINTAIN THE APPROVED DEVELOPMENT Maintain the approved development (including landscaping, parking, driveways and other external spaces) in accordance with the approved drawing(s) and/or documents, and any relevant Council engineering or other approval required by the conditions. GUIDELINE This condition restricts changes that can be made to the approved development. Approved plans and documents are stamped PLANS and DOCUMENTS referred to in the APPROVAL and are dated to reflect the date of determination of the application by the Council's delegate. The extent to which plans can be modified is constrained by the definition of 'minor change' in schedule 10 and the requirements of section 3.5.24 of the "Integrated Planning Act 1997". It will be necessary to make a new application if the change is not a minor change. For any enquires about this condition, please contact the Assessment Manager. |
To be maintained |
| 6) PUBLIC ACCESS - 24 HRS THROUGH SITE Provide and maintain unimpeded and safe 24-hour public access through the subject site (to link Ann, Adelaide and George Streets), and ensure that access ways are designed to cater for disabled persons in accordance with "Australian Standard AS1428.1". GUIDELINE This condition is imposed to ensure on-going safe public access to designated public pedestrian spaces within the development. |
To be maintained |
| 7) MODIFY EASEMENTS The owner of Lot 102 on SP102966 and Brisbane City Council shall execute a deed of agreement regarding shared access and servicing arrangements between City Hall and development the subject of this application (incorporating amendments to Easement A on SP102966 in Lot 101 on SP102966 and Easement F on SP107657 in Lot 102 on SP102966) as outlined in the 'Access and Waste Management Deed' prepared by McCullough Robertson Lawyers and forwarded to Brisbane City Council on 28 February 2007.
The executed deed shall be:
|
As indicated |
| 8) ENERGY EFFICIENCY Provide a written statement from a person who is qualified in using a recognisied energy rating system, such as BERS (Building Energy Rating System), Nathers or other recognised system, that the building(s) comply with the "Brisbane City Plan 2000 - Energy Efficiency Code". GUIDELINE This condition is imposed on all building work for offices, hotels and shops with a GFA over 2500m2 and for all new residential buildings except a house. |
Prior to lodging an application for Building Works |
| 9) LIGHTING TO PUBLIC AREAS Install and maintain a suitable system of lighting, to operate
from dusk to dawn, within all areas where the public will be given
access. GUIDELINE This condition is imposed to ensure on-going safe public access to designated public pedestrian spaces within the development |
Prior to the commencement of the use and then to be maintained |
| 10) BICYCLE PARKING (CITY PLAN) Install and maintain secure bicycle parking and associated support facilities generally in accordance with the approved plans and documents, and in accordance with the Centre Amenity and Performance Code as outlined below:
Employee Provide a minimum of:
Customer Provide a minimum of 109 bicycle spaces. GUIDELINE This condition is imposed because bicycle parking and associated facilities are required to provide convenient facilities for cyclists and safe storage of bicycles to encourage cycling as an alternative for car commuting and also cater for short term requirements such as couriers bicycle facilities. |
Prior to the commencement of the use and then to be maintained |
| 11) CAR PARKING The car parking within the building is to be maintained exclusively for the ancillary use of the development. The parking is not to be made available to the general public and there is to be no advertising signage erected on or in the vicinity of the site advertising the availability of car parking to the general public. |
Prior to the commencement of the use and then to be maintained |
| 12) HEIGHT OBSTACLE CASA Air
transport operations are not to be compromised:
The maximum height of the building, including any structures atop the building, must not exceed 184.50 metres AHD; |
Prior to the commencement of the use and then to be maintained |
12(a) HEIGHT OBSTACLE CASA Permanent obstacle lighting for the building is to be adopted in accordance with the requirements of the Civil Aviation Safety Authority (CASA) and the Brisbane Airport Corporation (BAC); |
Prior to the commencement of the use and then to be maintained |
12(b) HEIGHT OBSTACLE CASA Submit a separate application to and obtain approval from the BAC and CASA in relation to the use of any temporary structures (eg. cranes) in the construction of the building. |
Prior to the commencement of the use and then to be maintained |
12(c) HEIGHT OBSTACLE CASA The ongoing monitoring and maintenance of the abovementioned obstacle lights is to be the responsibility of the building owner; and |
Prior to the commencement of the use and then to be maintained |
12(d) HEIGHT OBSTACLE CASA In order to operate any other type of lighting (eg. search or laser type) from the building separate application to CASA's Brisbane Office must be made for a hazard assessment of those lights as required by the Civil Aviation Regulations 1988, Regulation 94 (Dangerous Lights). |
Prior to the commencement of the use and then to be maintained |
| 13) PAY OUTSTANDING CHARGES OR EXPENSES Pay to Council any outstanding charges or expenses levied by
the Council over the subject land. GUIDELINE This condition is imposed to ensure that there are no outstanding charges existing over the subject site, including outstanding rates. If there are out standing monies, they must be paid prior to commencement of the use. |
Prior to commencement of use |
| 14) SEWERAGE: PER ET (EQUIVALENT TENEMENT) Pay to Council a monetary contribution towards the cost of sewerage headworks, as outlined below, at the rate prevailing when the contribution is paid. This payment must be made prior to the permanent sewer connection being made to the site.
The contribution is calculated on 300.219 ETs (Equivalent Tenement) at the current rate of $5,772.00 per ET, for Sewerage Scheme Charge Area - S1 - CITY 1, .
The amount payable is currently assessed at $1,732,864 and comprises of the following :
This headwork charge is the current rate for the 2006/2007 financial year.
GUIDELINE This condition is imposed to require the payment of a proportional contribution towards a satisfactory sewerage treatment system within the locality of the site. For any enquiries about this condition, please contact the Engineering Delegate, Development and Regulatory Services. |
Prior to the permanent water/sewer connection being made to the site or prior to endorsement of a community management statement, whichever is sooner |
| 15) WATER SUPPLY: PER ET (EQUIVALENT TENEMENT) Pay to Council a monetary contribution towards the cost of water supply headworks, as outlined below, at the rate prevailing when the contribution is paid. This payment must be made prior to the permanent water connection being made to the site.
The contribution is calculated on 359.343 ETs (Equivalent Tenement) at the current rate of $4,996.00 per ET, for Water System Infrastructure Charges Plan Area - GREEN HILL W6
The amount payable is currently assessed at $1,795,278 and comprises of the following:
This headwork charge is the current rate for the 2006/2007 financial year. GUIDELINE This condition is imposed to require the payment of a proportional contribution towards a satisfactory water supply treatment system to the site. For any enquiries about this condition, please contact the Engineering Delegate, Development and Regulatory Services. |
Prior to the permanent water/sewer connection being made to the site or prior to endorsement of a community management statement, whichever is sooner |
| 16) PARKLAND Pay to Council a monetary contribution towards the provision of parkland at the rate applicable at the time of payment. The amount is currently calculated at $2.70 per square metre of gross floor area. The required contribution currently totals $107584. This park contribution is the current rate for the 2006/2007 financial year. GUIDELINE This condition is imposed when a monetary contribution for parkland is required. The contribution is calculated in accordance with Planning Scheme Policy 1 - Development Contributions for Parks and Recreational Facilities Arising from Subdivision of Land and from Material Change of Use or Development of Land. |
Prior to the commencement of the use or prior to the endorsement of a Community Management Statement, whichever is sooner |
| 17) DETAILED & COLOURED MODEL Submit to the Delegate, Development Assessment, a detailed and coloured model at a scale of 1:500 for incorporation into the Council's Central City Model. |
Prior to building work commencing |
| 18) EXTERNAL DETAILS Submit for the approval of the Team Leader, Development Assessment Team Central, further details of the building, facade treatment and external materials, colours and finishes generally consistent with the approved plans. |
Prior to building work commencing |
18(a) EXTERNAL DETAILS Implement the above detailed design treatments. |
Prior to building work commencing |
| 19) HERITAGE PLACE- BEST PRACTICE STANDARDS Carry out all conservation, restoration and adaptation work to the existing culturally significant structure in accordance with best heritage conservation practice and with The Burra Charter (Australia ICOMOS Charter for the Conservation of Places of Cultural Significance). GUIDELINE This condition is imposed to ensure best practice for development work to heritage sites. For any enquiries about this condition, please contact the Development Assessment Team Architect. |
Prior to site/building works commencing and then to be maintained |
| 20) SUPPLY/INSTALL ARTWORKS (CITY PLAN) Supply, install and maintain within an area to be determined
by the Delegate, Development Assessment, artworks (including but not
necessarily limited to, sculptures, ceramic works, mosaics and wall reliefs) by
a recognised artist or craftsperson in accordance with the "Brisbane City Plan
2000 - City Centre Local Plan Code".
Plan for artworks or sculptures that meet the following criteria:
|
Prior to commencement of use |
20(a) SUPPLY/INSTALL ARTWORKS (CITY
PLAN) Enter into a contractual agreement (to be endorsed by the Delegate, Development Assessment) with a recognised artist or craftsperson to supply and install the artworks required by the above; and |
Prior to commencement of use |
20(b) SUPPLY/INSTALL ARTWORKS (CITY
PLAN) Install the endorsed artworks or
sculptures. |
Prior to commencement of use |
| 21) OVERALL HEIGHT - SURVEY CERTIFICATION The overall height of the proposed building(s) is to be in
accordance with the following requirements:
Construct the floor levels in accordance with the floor levels on the approved drawings; and GUIDELINE This condition is imposed to ensure the floor levels and maximum overall height of the proposed building is in accordance with the development approval. For any enquiries about this condition, please contact the Development Assessment Team Architect. |
Prior to commencement of use |
21(a) OVERALL HEIGHT - SURVEY
CERTIFICATION Submit certification from a licensed surveyor that the as constructed floor levels are in accordance with part (a) of this condition and that the maximum overall height of the building does not exceed 184.50 metres AHD. This information is to be submitted to Licensing and Compliance Team Central. |
Prior to commencement of use |
| 22) LIGHT REFLECTIVITY & SOLAR (HEAT)
REFLECTIVITY Submit to the Delegate, Development
Assessment documentary evidence that:The level of light reflectivity from the
approved development will not exceed 20 percent; and GUIDELINE This condition is imposed to protect the amenity and appearance of the surrounding area from adverse impacts such as heat transmission and light reflectivity arising from the use of excessively reflective glass in building facades. |
Prior to the commencement of the use and then to be maintained |
22(a) LIGHT REFLECTIVITY & SOLAR (HEAT)
REFLECTIVITY The level of solar (heat)
reflectivity from the approved development will not exceed 20
percent. |
Prior to the commencement of the use and then to be maintained |
| 23) LIGHTING SYSTEM TO AWNING Install a lighting system to the underside of the proposed
awning over the footpath in accordance with the following:
Provides lighting to public footpaths covered by permanent awnings to a minimum of 20 lux (horizontal plane) at footpath level; GUIDELINE This condition is intended to ensure that pedestrians can move safely in front of the site. For any enquiries about this condition, please contact the City Lighting Unit, Local Asset Services Central District (pH 3403 0307). |
Prior to the commencement of the use and then to be maintained |
23(a) LIGHTING SYSTEM TO AWNING The lighting system meets the requirement of the City Plan 2000 - Awning Lighting Code; |
Prior to the commencement of the use and then to be maintained |
23(b) LIGHTING SYSTEM TO AWNING The lighting system adequately illuminates any pedestrian way covered by the subject awning from dusk until dawn; and |
Prior to the commencement of the use and then to be maintained |
23(c) LIGHTING SYSTEM TO AWNING Is to be maintained by the owner of the building in a safe and good working order. |
Prior to the commencement of the use and then to be maintained |
| 24) AIR CONDITIONING & OTHER PLANT ENCLOSURES Install and maintain suitable screening to all air conditioning, lift motor rooms, plant and service facilities located at the top of or on the external face of the building. The screening structures must be constructed from materials that are consistent with materials used elsewhere on the facade of the building. There are to be no individual external air conditioning units. |
Prior to the commencement of the use and then to be maintained |
| 25) DETAILED PLAN-COMMERCIAL Prepare and landscape the site in accordance with a Landscape
Management, Site Works and Planting Plan.
Submit and receive approval by the Delegate, Development Assessment for a detailed Landscape Plan for all on-site landscape works identified on the approved plan(s) of layout 706042/DA/LA01revA. The plan is to be prepared at a scale of 1:100 by a suitably qualified and experienced Landscape Architect/Designer, and must comply with the "Brisbane City Plan 2000- Landscaping Code". The plan should include the following: i) Siteworks:
ii) Planting:
GUIDELINE This condition is imposed when there is a landscape component to a High Level development application, and Council requires more details of the proposed landscape works. |
Prior to commencement of site works |
25(a) DETAILED PLAN-COMMERCIAL Carry out the landscaping and associated works documented in the approved Landscape Management and Site Works Plan in accordance with standard Best Trade Practice. |
Prior to commencement of site works |
25(b) DETAILED PLAN-COMMERCIAL Advise Council upon completion of the landscape works by completing the development details and Part B of the Compliance Certificate-Landscaping. |
Prior to commencement of site works |
| 26) RETAIN EXISTING STREET TREES Existing street trees Caesalpinia ferrea (8 to Adelaide Street, 8 to George Street and 4 to Ann Street) shall be identified, retained and protected whilst any demolition or building works are occuring on the site. Any pruning, trimming or works within the dripline of these trees to accommodate the development must be performed by a qualified arborist in accordance with the Australian Standard for the Pruning of Amenity Trees AS4373, AND WITH PRIOR APPROVAL FROM BCC's VEGETATION AND PEST SERVICES.
Street trees are protected under Category 1 of NALL (Council-Controlled Vegetation) and an Application To Carry Out Works (including Interfere with) on Protected Vegetation must be obtained prior to commencing any work which may affect the canopy or root zone of the trees. GUIDELINE This condition is imposed where existing vegetation contributes significantly to the character of the existing streetscape and the surrounding amenity of the locality. For any enquiries about this condition, please contact Vegetation and Pest Services on 3403 8888. |
While site works are occurring and then to be maintained |
| 27) STREETSCAPE WORKS-SCIPS 2 Construct streetscape works in accordance with the following:
Submit a pedestrian lighting design (including details) for the full street frontage of the development for the approval of the City Lighting Officer, Local Asset Services. The lighting is to be in accordance with AS/NZS1158.3.1, 1999 Pedestrian Area (Category P3) Lighting and the Centres Detail Design Manual. The applicant is to be responsible for the obtaining of all necessary approvals from Energex, all costs associated with the street lighting, the installation, ensuring the system is operational and to provide as-constructed lighting design plans. GUIDELINE For any enquiries about this condition, please contact the Landscape Architect, Development Assessment. |
Prior to the commencement of footpath demolition |
27(a) STREETSCAPE WORKS-SCIPS 2 The applicant is required to lodge a permit Application for Permits Relating to Roads and Footway. |
Prior to the commencement of footpath demolition |
27(b) STREETSCAPE WORKS-SCIPS 2 Remove the existing footpath including affected street signage for the full length of the frontages to Adelaide, George and Ann Streets and construct the required works to a standard and of materials consistent with the approved Streetscape Works Plan and the requirements of the Centres Detail Design Manual. Reinstate all street signage as directed by Council. |
Prior to the commencement of footpath demolition |
27(c) STREETSCAPE WORKS-SCIPS 2 Provide a letter of Certification for all constructed footpath works as documented on the Approved Plan by a Registered Practising Engineer of Queensland (RPEQ). Certification is to cover:
|
Prior to the commencement of footpath demolition |
27(d) STREETSCAPE WORKS-SCIPS 2 Maintain the streetscape works, including street trees and landscaping, for a period of 12 months from the date of the On Maintenance inspection in accordance with the Centres Detail Design Manual. |
Prior to the commencement of footpath demolition |
| 28) STREETSCAPE WORKS-SCIPS Provide streetscape works in accordance with the following:
Submit a Streetscape Works Plan for detailed design approval of the Landscape Architect, Development Assessment, for required works to be undertaken within the Adelaide Street, George Street and Ann Street footpath reserves as per amended in red Street Paving drawing no. 706042/DA/LA01/revA. The plan is to be prepared at a scale of 1:100 by a suitably qualified and experienced Landscape Architect/Designer and the works are to be constructed to a standard and of materials consistent with the requirements of Council's Centres Detail Design Manual.
The plans are to include but not be restricted to the following:
GUIDELINE This condition is imposed when the proposed development is located within a Centre, which is covered by the Centres Detail Design Manual. The objective is to ensure that the external spaces are developed in a way that enhances the subject proposal and contributes positively to the streetscape character and overall image and quality of public spaces throughout the City. Streetscape works are to be carried out in accordance with the approved plans and workmanship is to be of acceptable standards and maintained accordingly. The Centres Detail Design Manual is available for purchase at all Council Customer Service Centres. The final locations and number of items of street furniture is to be determined by the Landscape Architect, Development Assessment. For any enquiries about this condition, please contact the Landscape Architect, Development Assessment. The plan (minimum 8 copies), together with the appropriate fee, should be lodged at the Development and Regulatory Services? Counter, Floor 1, Brisbane Administration Centre. Refer to Appendix F of the Centres Detail Design Manual. |
Prior to commencement of operational works/building works |
28(a) STREETSCAPE WORKS-SCIPS Obtain all necessary approvals for the satisfactory construction of these works. |
Prior to commencement of operational works/building works |
| 29) PLANT AND EQUIPMENT Following the installation of all mechanical plant and equipment, an appropiately qualified acoustic consultant must submit certification to the Team Leader Licensing and Compliance Central that the abovementioned plant and equipment is adequately noise attenuated, in accordance with Brisbane City Council's, Noise Impact Assessment Planning Scheme Policy. |
Prior to commencement of use |
| 30) REFUSE BIN WASHING FACILITY Construct an on-site refuse bin washing facility for food outlet refuse bins. The area must be provided with a tap, paved with an impervious material, graded and drained to sewer subject to the requirements and recommendations of Brisbane Water. GUIDELINE This condition is imposed where it is intended to clean refuse containers on site. |
Prior to the commencement of the use and then to be maintained |
| 31) ON SITE EROSION- MINOR WORK Minimise on-site erosion and the release of sediment or
sediment-laden stormwater from the site at all times.
Prepare an Erosion and Sediment Control (ESC) Management Plan for the site in accordance with Council's Best Practice Guidelines for the Control of Stormwater Pollution from Building Sites and accompanying fact sheets, Brisbane City Council and Gold Coast City Council, 2000 (or later version); GUIDELINE This condition is utilised where the potential for soil erosion, sediment loss from the site, and environmental impact on waterways is considered to be medium to low. Whilst not requiring submission of detailed information as defined in Council's "Erosion and Sediment Control Standard (Version 8 or later)", the ESC Management Plan must still satisfy the general requirements of this Standard (ie. minimise soil erosion and sediment loss from the site at all times during the works). No formal ESC Program is to be submitted for Council assessment however a copy of the ESC Management Plan is required on-site. Non-compliance may result in prosecution under Environmental Legislation. For any enquiries regarding this condition please contact the Engineering Delegate, Development and Regulatory Services. |
Prior to site works commencing (ie. any land-disturbing development) |
31(a) ON SITE EROSION- MINOR
WORK Implement and maintain on-site The ESC Management Plan for the duration of the operational or building works, and until exposed soil areas are permanently stabilised (e.g. turfed, concreted). The documented ESC Management Plan must be available on-site for inspection by Council Officers during these works. |
Prior to site works commencing (ie. any land-disturbing development) |
| 32) CONSTRUCTION MANAGEMENT PLAN Prepare a Construction Management Plan for the subject site:
Submit for approval of the Engineering Delegate, Development Assessment, Central Team, a Construction Management Plan for the demolition, excavation and construction phases of the approved development. Separate CMPs may be appropriate for the individual components. The CMP is to be generally in accordance with the Transport, Access. Parking and Servicing Planning Scheme Policy of the Brisbane City Plan 2000. The CMP is to provide the following details and address impacts, where applicable:
NOTES:
GUIDELINE Construction activities need to be limited to manage the impact on the surrounding area., This condition is intended to apply throughout the period of site preparation to the completion of the development. Please note that an operational works application is to be submitted. |
Prior to lodging an application for Building Works |
32(a) CONSTRUCTION MANAGEMENT
PLAN Arrange a pre-start meeting with the Engineering Delegate, Development Assessment, Central Team; |
Prior to lodging an application for Building Works |
32(b) CONSTRUCTION MANAGEMENT
PLAN Obtain relevant permits from the Engineering Delegate, Development Assessment, Central Team, to carry out any works within the road reserve required by the approved Construction Management Plan. Applications for permits will be assessed on the basis of road and footpath network operating conditions prevailing at the time. Council will consider impacts of other construction works or events which occur during the life of the permit. Council may issue permits which vary from the previously approved arrangements or revoke permits at any time if it considers that safety, capacity and/or operation of public transport, vehicle and pedestrian traffic are likely to be compromised during the construction project. |
Prior to lodging an application for Building Works |
32(c) CONSTRUCTION MANAGEMENT
PLAN Implement and maintain the approved Construction Management Plan; |
Prior to lodging an application for Building Works |
32(d) CONSTRUCTION MANAGEMENT
PLAN Legible copies of the approved Construction Management Plan and current permits are to be kept on site and be made available on request. |
Prior to lodging an application for Building Works |
| 33) RETAINING WALLS Any retaining walls greater than 1.0 metre in height are required to be structurally certified for design and construction by a Registered Professional Engineer Queensland (RPEQ). The certification is to include the stormwater drainage (surface and seepage water) associated with the wall ensuring that the water is directed to an acceptable lawful and legal point of discharge and does not cause any ponding, nuisance or disturbance to adjacent property owners. All retaining walls are to comply with the City Plan Filling and Excavation Code. GUIDELINE This condition is intended to ensure that retaining walls associated with the development that are higher than 1 metre, are designed and constructed to industry standards and also, to ensure that no adverse impact is created by the structures on the surrounding properties. The retaining wall designer should note that timber retaining walls facing onto Council property (including the road reserve) will not be permitted. Retaining walls facing onto road reserve or parkland are to be contained entirely within the proposed development site, including the retaining wall's footings. Where retaining walls are proposed to be constructed between adjoining properties, it is also suggested that the use of timber sleeper retaining walls be restricted due to their limited life and the potential problems they may cause to future property owners. Where the combined height of the retaining wall and fence exceeds 2.0 metres, a Development Permit for Building Work will need to be granted. For any enquires about this condition please contact the Engineering Delegate, Development and Regulatory Services. |
Prior to commencement of use |
| 34) PEDESTRIAN EASEMENTS Grant volumetric easements for pedestrian access as follows;
The lower limit shall be the finished surface of the waterproof membrane directly below the surface paving material and the upper limit shall be a minimum of 3.0 metres above the finished footpath surface. The easement is to be in favour of Council. GUIDELINE This condition is imposed to provide pedestrian access. Easements in favour of the Brisbane City Council are required to have the necessary easement documentation prepared (free of costs and compensation to Council) by the Brisbane City council. Easements are to be shown on a Survey Plan and lodged with the Delegate Plan Sealing, Licensing Sealing and Certificates Unit. Enquiries regarding any legal documentation can be directed to Licensing, Sealing and Certificates Unit, Development and Regulatory Services (pH 3403 9050). For any other enquiries about this condition, please contact the Engineering Delegate, Development and Regulatory Services. |
Prior to commencement of use |
| 35) ACCESS, GRADES, MANOEUVRING, CARPARKS,
SIGNS, Construct and delineate or sign (as required)
the following requirements as indicated on the approved plan(s) of layout:
Construct a pavement of minimum Type A standard and surface with an impervious material (including associated drainage) to the area on which motor vehicles will be driven and/or parked. {Construction of such pavement is to be certified by a Registered Professional Engineer of Queensland (RPEQ)}; GUIDELINE The "Brisbane City Plan 2000 - Transport, Access, Parking and Servicing Planning Policy" requires adequate on- site provision of parking, servicing and manoeuvring areas. This condition specifies detailed design requirements as indicated on the approved drawings and documents to which the approval relates. |
Prior to the commencement of the use and then to be maintained |
35(a) ACCESS, GRADES, MANOEUVRING, CARPARKS,
SIGNS, The driveways at grades shown on the approved plans and documents (or if not shown at grades not greater than those set out in "Brisbane City Plan 2000 - Transport, Access, Parking and Servicing Planning Policy"). Grades of existing driveways where being retained are acceptable; |
Prior to the commencement of the use and then to be maintained |
35(b) ACCESS, GRADES, MANOEUVRING, CARPARKS,
SIGNS, Manoeuvring and standing on site for 8 Vans, 1 Small Rigid Vehicle, 5 Medium Rigid Vehicles and for the loading and unloading of the vehicle(s); Provision is to be made for Large Rigid Vehicles to be able to access the site outside business hours and utilise standing areas for other service vehicles for manoeuvring. |
Prior to the commencement of the use and then to be maintained |
35(c) ACCESS, GRADES, MANOEUVRING, CARPARKS,
SIGNS, Parking on the site for a maximum of 156 cars for the 'Northbank Plaza' building, a maximum of 235 cars for the new commercial tower and a maximum of 9 cars for the new 3 storey podium building (corner of Ann Street and George Street), and for the loading and unloading of vehicles within the site; |
Prior to the commencement of the use and then to be maintained |
35(d) ACCESS, GRADES, MANOEUVRING, CARPARKS,
SIGNS, 8 of the above parking spaces are to be provided for people with disabilities; |
Prior to the commencement of the use and then to be maintained |
35(e) ACCESS, GRADES, MANOEUVRING, CARPARKS,
SIGNS, A minimum 4.5 metres height clearance to MRV loading dock standing and access areas, a minimum 3.5 metres height clearance to SRV loading dock standing and access areas, a minimum 2.3 metres to Van standing and access areas, a minimum 2.3 metres to all undercover car parking areas and a minimum of 2.5 metres above parking spaces for people with disabilities (Note, The minimum clear height shall be measured to the lowest appurtenance on the ceiling - ie. fire sprinklers, services, lighting fixtures, signs etc.). Height clearances to car parking where constrained by existing structures are acceptable; |
Prior to the commencement of the use and then to be maintained |
35(f) ACCESS, GRADES, MANOEUVRING, CARPARKS,
SIGNS, A height clearance sign located at the entrance(s) to undercover car parking and service vehicle areas; |
Prior to the commencement of the use and then to be maintained |
35(g) ACCESS, GRADES, MANOEUVRING, CARPARKS,
SIGNS, An appropriate area for the storage and collection of refuse, including recyclables, in a position which is accessible to service vehicles on the site; |
Prior to the commencement of the use and then to be maintained |
35(h) ACCESS, GRADES, MANOEUVRING, CARPARKS,
SIGNS, All vehicle access associated with development on Lot 102 on SP102966 shall be restricted to the approved crossover in Ann Street. |
Prior to the commencement of the use and then to be maintained |
35(i) ACCESS, GRADES, MANOEUVRING, CARPARKS,
SIGNS, The internal paved areas are to be signed and delineated in accordance with the approved plans, Manual of Uniform Traffic Control Devices and Austroads. |
Prior to the commencement of the use and then to be maintained |
| 36) LOADING DOCK MANAGER Manage the service vehicle facilities with an On Site Loading Dock Manager to ensure safe, efficient and effective use. Service vehicles larger than Medium Rigid Vehicles are to access the site outside peak traffic hours and business hours. |
Prior to the commencement of the use and then to be maintained |
| 37) REPAIR DAMAGE TO KERB, FOOTPATH OR ROAD Repair any damage to existing kerb and channel, footpath or
roadway (including removal of concrete slurry from footways, roads, kerb and
channel and stormwater gullies and drainlines) that may occur during any works
carried in association with the approved development. GUIDELINE The intention of this condition is to ensure that any works undertaken as part of the approved development do not damage Council assets or leave Council assets in an unacceptable and unsightly manner. For enquiries regarding this condition, please contact the Engineering Delegate, Development and Regulatory Services. |
Prior to commencement of use |
| 38) PROVIDE/EXTEND 150 MM SEWER CONNECTION(S) Provide a sewer property connection to serve the development
designed and constructed in accordance with approved engineering plans and
Council's "Water and Sewerage Reticulation Standards".
NB. The size of the connection shall be determined by the total number of
fixture units.
Submit engineering plans prepared by a Registered Professional Engineer Queensland (RPEQ), and in accordance with Council's "Water and Sewerage Reticulation Standards" showing the design the works. Obtain the approval from the Engineering Delegate, Development Assessment, Development and Regulatory Services; GUIDELINE This condition is imposed to provide a separate new sewerage connection to the development. For enquiries regarding this condition, please contact the Engineering Delegate, Development and Regulatory Services. |
Prior to undertaking the works |
38(a) PROVIDE/EXTEND 150 MM SEWER
CONNECTION(S) Pay to Council the cost of live connection to the sewer main; |
Prior to undertaking the works |
38(b) PROVIDE/EXTEND 150 MM SEWER
CONNECTION(S) Construct the works in accordance with the approved engineering plans to a standard that will be satisfactory to be accepted "on" and "off" maintenance as a Council asset, by the Engineering Delegate, Development and Regulatory Services; |
Prior to undertaking the works |
38(c) PROVIDE/EXTEND 150 MM SEWER
CONNECTION(S) Submit "As Constructed" plans including an assest register, approved by a Registered Professional Engineer Queensland (RPEQ) (to a standard specified in Council's "Water and Sewerage Reticulation Standards") certifying that the works have been completed in accordance the approved design and any approved modifications. |
Prior to undertaking the works |
| 39) ON-SITE DRAINAGE Run-off
from roof and developed surface areas of the site, and any run-off onto the
site from adjacent areas, are to be collected internally and directed to a
lawful point of discharge in accordance with Council's "Subdivision and
Development Guidelines".
Submit drainage plans and engineering calculations (as a part of the developments Site Based Stormwater Quantity Management Plan) in accordance with Council's "Subdivision and Development Guidelines" showing the design of the drainage of the roof and developed surfaces. Obtain approval from the Engineering Delegate, Development Assessment. Such plans are to show adequate survey information on areas adjoining the site with particular attention to any nuisance or annoyance to adjoining property owners. Please note all constructed stormwater outlets that are proposed to discharge directly to a waterway, shall ensure an appropriate waterway setback, reduction in flow outlet velocity and concentration and, include any supplementary planting works that may be required (refer "Stormwater Outlets in Parks and Waterways", BCC July 2000); GUIDELINE The purpose of this condition is to ensure that stormwater run off from the site and adjacent properties will be handled adequately. Disposal by gravity pipeline is required if practical. Use of pumps for disposal of stormwater may be approved only if the applicant can show evidence to Council of having taken all reasonable steps to obtain written permission from adjacent property owners for construction of a gravity pipeline, and of this being unobtainable.The proposal may include water saving and reuse devices such as rain water tanks provided that the proposal satisfies Council that devices will be satisfactorily maintained by the owners of the property. For any enquiries about this condition, please contact the Engineering Delegate, Development and Regulatory Services. |
Prior to site works/building works commencing |
39(a) ON-SITE DRAINAGE Complete the works in accordance with the approved engineering plans and other elements of the developments Site Based Stormwater Management Plan; and |
Prior to site works/building works commencing |
39(b) ON-SITE DRAINAGE Submit "As Constructed" plans approved by a Registered Professional Engineer of Queensland (RPEQ) (to a standard specified in Council's "Subdivision and Development Guidelines") certifying that the works have been completed in accordance with the approved design and any approved modifications. |
Prior to site works/building works commencing |
| 40) PONDING OF STORMWATER Adjoining properties and roads are to be protected from
ponding or nuisance from stormwater runoff.
Adjoining properties and roads are to be protected from ponding or nuisance from stormwater as a result of the proposed works; GUIDELINE This condition is imposed to ensure that the developer is aware that they are responsible for all remedial works required as a result of any site works and, that they must protect neighbouring properties and roads from ponding and nuisance water from the proposed development. Where this rectification work involved drainage, plans are to be lodged showing the manner in which it is intended to rectify the site drainage. These plans must be approved by the Engineering Delegate. For any enquiries about this condition, please contact the Engineering Delegate, Development and Regulatory Services. |
Prior to commencement of use |
40(a) PONDING OF STORMWATER Rectify all damage resulting from the ponding of stormwater or nuisance from discharge of stormwater from the site to adjacent properties. |
Prior to commencement of use |
| 41) SERVICE CONDUITS & MAINS Supply and install all service conduits and meet the cost of
any alterations to public utility mains, existing mains, services or
installations required in connection with the approved development. This
includes the relocation of any fire hydrants and valves from within the limits
of the development's vehicular footway crossings if applicable.
Complete the works required by this condition; GUIDELINE This condition is imposed when additions, alterations or extensions to service conduits, mains and other services are required as a result of the approved development. Applicants should liaise with the appropriate service authorities. For any enquiries about this condition, please contact the Engineering Delegate, Development and Regulatory Services (regarding advise on traffic signal conduits, stormwater, water supply and sewerage mains etc.) or the relevant public utility authorities (for advice on other services). |
Prior to commencement of use |
41(a) SERVICE CONDUITS & MAINS Submit "As Constructed" plans including an asset register (if required), approved by a registered Professional Engineer Queensland (RPEQ) (in accordance with Council's "Subdivision and Development Guidelines" and "Water and Sewerage Reticulation Standards") showing the works required by this condition. |
Prior to commencement of use |
| 42) TELECOMMUNICATION - UNDERGROUND Provide underground telecommunication services to the proposed
development.
Enter into an agreement with a telecommunication company and provide underground telecommunication services within and adjacent to the proposed development; and GUIDELINE This condition is imposed to ensure that the provision of essential communication services are provided to the development. For any enquiries about this condition, please contact relevant service carriers regarding communications or Telstra (pH 132 200). |
Prior to commencement of use |
42(a) TELECOMMUNICATION -
UNDERGROUND Forward a copy of the agreement to the Engineering Delegate, Development and Regulatory Services. |
Prior to commencement of use |
| 43) ELECTRICITY (UNDERGROUND SUPPLY AREA) Provide underground electricity services in accordance with an
approved electricity reticulation plan and the Council's "Subdivision and
Development Guidelines (Public Utilities Section)". Note: Even though the
development may be in an area serviced by overhead electricity, UNDERGROUND
supply to the development is now required - no additional poles or overhead
mains are to be erected.
Lodge electricity reticulation plans showing and the proposed electricity services and obtain approval from the City Lighting Unit, Local Asset Services Central District; GUIDELINE This condition is imposed when a proposed development would require the provision of electricity services in accordance with Council's "Guidelines for the Provision of Underground Electricity". Please refer to the Council's information sheet on lodging detailed design applications. For any enquiries about this condition, please contact the City Lighting Unit (pH 3403 0307) regarding electricity reticulation plans or Energex (pH: 131 253) regarding electricity supply. |
Prior to commencement of use |
43(a) ELECTRICITY (UNDERGROUND SUPPLY
AREA) Enter into an agreement with an
electricity supplier to provide underground electricity services in accordance
with the above approved electricity reticulation plans;
and |
Prior to commencement of use |
43(b) ELECTRICITY (UNDERGROUND SUPPLY
AREA) Forward a copy of the agreement to the Engineering Delegate, Development and Regulatory Services. |
Prior to commencement of use |
| 44) PUBLIC LIGHTING Provide a
public lighting system in accordance with an approved street lighting design
plan and Council's "Street Lighting Design Guidelines".
Lodge street lighting design plans showing the proposed public lighting system and obtain approval from the City Lighting Unit, Local Asset Services Central District; GUIDELINE This condition is imposed when a proposed development requires the provision of public lighting facilities in accordance with the "Street Lighting Design Guidelines". Please refer to the Council's information sheet on lodging detailed design applications. For any enquiries about this condition, please contact the City Lighting Unit (pH 3403 0307) regarding electricity reticulation plans or Energex (pH: 131 253) regarding electricity supply. |
Prior to commencement of use |
44(a) PUBLIC LIGHTING Enter into an agreement with an electricity supplier to
provide a public lighting system in accordance with the above approved lighting
design plans; and |
Prior to commencement of use |
44(b) PUBLIC LIGHTING Forward a copy of the agreement to the Engineering Delegate, Development and Regulatory Services. |
Prior to commencement of use |
| 45) METERING - MIXED USE DEVELOPMENT Provide a water service with approved Council meter assembly
and meter box to the front real property boundary of the development in
accordance with Council's "Water and Sewerage Reticulation Standards".
Where a mixed usage site is approved for development and the proposed
development comprises mixed classifications as defined by the Building Code of
Australia containing any of Classes 5 to 9 and any of Classes 2 to 4, then the
developer must provide a separate metered water service for the Class 2 to 4
occupancy as opposed to the Class 5 to 9 occupancy.
This requirement is exclusive of any special fire service consideration i.e.
internal hydrants, fire hose reels and sprinkler systems.
Submit engineering plans prepared by the RPEQ (Registered Professional Engineer Queensland) , and in accordance with Councils "Water and Sewerage Reticulation Standards" showing service and meter works. (The size of the service shall be determined by the water supply requirement of the proposed development). Obtain the approval from the Engineering Delegate, Development Assessment, Development and Regulatory Services; GUIDELINE This condition is imposed to supply a water service and a meter(s) to a Development / Community Title Development / Standard / Building or Volumetric format. The meter(s) shall be accessible to BCC employees or agents for the purpose of reading and maintaining the meter(s). The meter(s) will become and remain property of the Brisbane City Council. |
Prior to undertaking the works |
45(a) METERING - MIXED USE
DEVELOPMENT Pay to Council the cost of live connection to the water main; |
Prior to undertaking the works |
45(b) METERING - MIXED USE
DEVELOPMENT Such construction is to be to a standard that is satisfactory to be accepted on an off maintenance; |
Prior to undertaking the works |
45(c) METERING - MIXED USE
DEVELOPMENT If the meters are purchased other than from Council, pay to council a documentation fee for each water service provided. If the meters are purchased from Council, forward a copy of the receipt of purchase to the Engineering Delegate, Development and Regulatory Services. |
Prior to undertaking the works |
| 46) RELOCATE WATER MAIN Relocate the existing water main as required by streetscape
works (footpath works), in accordance with Council's "Water and Sewerage
Reticulation Standards".
Submit engineering plans prepared by a Registered Professional Engineer Queensland (RPEQ), and in accordance with Council's "Water and Sewerage Reticulation Standards" showing the design the re-located water main. Obtain the approval from the Engineering Delegate, Development Assessment, Development and Regulatory Services; GUIDELINE This condition is imposed when the approved development requires the widening of a road pavement under which is an existing water main. For enquiries regarding this condition, please contact the Engineering Delegate, Development and Regulatory Services. |
Prior to undertaking the works |
46(a) RELOCATE WATER MAIN Pay to Council the cost of live connection to the water main; |
Prior to undertaking the works |
46(b) RELOCATE WATER MAIN Construct the works in accordance with the approved engineering plans to a standard that will be satisfactory to be accepted "on" and "off" maintenance as a Council asset, by the Engineering Delegate, Development and Regulatory Services; |
Prior to undertaking the works |
46(c) RELOCATE WATER MAIN Submit "As Constructed" plans including an assest register, approved by a Registered Professional Engineer Queensland (RPEQ) (to a standard specified in Council's "Water and Sewerage Reticulation Standards") certifying that the works have been completed in accordance the approved design and any approved modifications. |
Prior to undertaking the works |
| 47) FOOD HYGIENE All development involving the preparation, packing, storing, handling, serving, selling or carrying of food requires that its design, installation and operation be approved pursuant to the Food Hygiene Regulations of 1989. The premises is required to be registered and the operator is to hold a licence with Brisbane City Council to operate the business under the above regulations.
Licences can be obtained from Brisbane City Council-Licensing & Compliance. To obtain a Licence Information Kit contact the call centre on 3403 8888.
Prior to building works plans and specifications are to be lodged for approval to Licensing and Compliance.
Please note: The above information has been provided to the applicant as an advice only, and does not form part of the development approval conditions. This advice has been provided to the applicant to inform them of other obligations they may have to comply with (under state legislation or local laws) prior to their activity commencing. |
As indicated |
| 48) NOISE AND DUST EMISSIONS-ADVICE ONLY All development involving the emission of noise and dust from building/construction activities requires that the emission be in accordance with the requirements of the Environmental Protection Regulation 1998 Part 2A - Environmental Nuisance.
Pursuant to the Environmental Protection Regulation 1998 Part 2A - Environmental Nuisance- 6W. A builder or building contractor must not carry out building work on a building site in a way that makes or causes audible noise to be made from the building work- (a) on a Sunday or public holiday, at any time; or (b) on a Saturday or business day, before 6.30 a.m. or after 6.30 p.m.
Please note: The above information has been provided to the applicant as an advice only, and does not form part of the development approval conditions. This advice has been provided to the applicant to inform them of other obligations they may have to comply with (under state legislation or local laws) prior to their activity commencing. |
As indicated |
| 49) EQUITABLE ACCESS Ensure that there is equitable access for disabled persons to and within the site in accordance with the Queensland Anti-Discrimination Act 1991, the Federal Disability Discriminiation Act 1992 and Australian Standard AS1428 Parts 1-4 Australian Standard for Access and Mobility. You are notified of your responsibility to ensure that access is appropriately designed and constructed for all users as required by relevant legislation and standards. This development approval does not indicate that the proposal complies with these requirements. Determination of compliance with these requirements is the sole responsibility of the owner/builder/developer of the proposal. Please note: The above information has been provided to the applicant as an advice only, and does not form part of the development approval conditions. This advice has been provided to the applicant to inform them of other obligations they may have to comply with (under state legislation or local laws) prior to their activity commencing. |
As indicated |
| 50) CONCURRENCE AGENCY CONDITIONS Brisbane City Council advise that Queensland Transport as concurrence agency has imposed the conditions contained in the letter dated 17 October 2006. |
As indicated |