BRISBANE CITY COUNCIL'S APPROVAL PACKAGE.



APPLICATION DETAILS

This package relates to the application detailed below
Address of Site: 275 GEORGE ST BRISBANE CITY QLD 4000
64 ADELAIDE ST BRISBANE CITY QLD 4000
69 ANN ST BRISBANE CITY QLD 4000
Real Property Description of Site: L20 SP.198665
L101 SP.102966
L102 SP.102966
Aspects of development and type of approval: DA - IPA - Carry Out Building Work Development Permit - Centre Activity Outside Centre
DA - IPA - Material Change of Use Development Permit and Preliminary Approval - Centre Activity Within Centre
Council File Reference: A006992697
Permit Reference Number/s: DABW167948607; DAMC167948507.
Package Status: APPROVED - Version 3 (29th of May, 2026 2:29:30 PM)
Package Generated: 29/05/2026


PROJECT TEAM

The assessment of this application has been undertaken by:
Ben CLOTHIER
Principal Urban Planner
Planning Services North
Ben.Clothier@brisbane.qld.gov.au
(07) 3403 7185
Kirstin BURROWES
Senior Architect
Architecture Team
Kirstin.Burrowes@brisbane.qld.gov.au
0731785363
Craig SLACK
Engineer
Engineering Scoping
craig.slack@brisbane.qld.gov.au
(07) 3403 8888
ASHLEY LANE

DA Central BSQ

(07) 3403 6650
MALCOLM ELLIOTT

DA Central BSQ

(07) 3403 5213
DARRELL CZISLOWSKI

DA Central BSQ

(07) 3403 6603
JOS RUHLAND

DA Central BSQ

(07) 3403 5817
ROSALYN DERBIN

DA West BSQ

(07) 3403 4349
CHAD RYAN

DA Central BSQ

(07)3403 6116
PHIL EASTGATE

DA Central BSQ

(07) 3403 5818
CASSANDRA SUN

DA Central BSQ

(07) 3403 5051
Llewellyn BATSON
Principal Urban Planner
Planning Services Special Assessment
Llewellyn.Batson@brisbane.qld.gov.au
(07) 340 34980
Joseph SELWOOD
Urban Planner
Planning Services City West
Joseph.Selwood@brisbane.qld.gov.au
(07) 3178 1491
JAMES HEADING
Principal Urban Planner
Partnerships Team
james.heading@brisbane.qld.gov.au
(07) 3403 5591
John PIETRYSZYN
Senior Engineering Officer
Engineering Services South
John.Pietryszyn@brisbane.qld.gov.au
(07) 3178 7555
Abby BANNAN
Urban Planner
Planning Services North
Abby.Bannan@brisbane.qld.gov.au
31782418


DRAWINGS AND DOCUMENTS



The term 'drawings and documents' or similar expressions mean:
Drawing or Document Number Plan Date
Level 2 Plan / Package: 1 1006 REV E 05-FEB-2007
Level 4 Plan / Package: 1 1008 REV E 05-FEB-2007
Level 3 Plan / Package: 1 1007 REV E 05-FEB-2007
Level 1 Plan / Package: 1 1005 REV E 05-FEB-2007
Level 5 Plan / Package: 1 1009 REV E 05-FEB-2007
Level 6 Plan / Package: 1 1010 REV E 05-FEB-2007
Level 7-10 Plan / Package: 1 1011 REV E 05-FEB-2007
Level 11-13 Plan / Package: 1 1012 REV E 05-FEB-2007
Level 14 Plan / Package: 1 1013 REV E 05-FEB-2007
Level 31 Plan / Package: 1 1016 REV E 05-FEB-2007
Roof Plan / Package: 1 1018 REV E 05-FEB-2007
Section D / Package: 1 3004 REV E 05-FEB-2007
Section C / Package: 1 3003 REV E 05-FEB-2007
Section B / Package: 1 3002 REV E 05-FEB-2007
Section A / Package: 1 3001 REV E 05-FEB-2007
North Elevation - Ann Street / Package: 1 2001 REV E 05-FEB-2007
Level 32 Plan / Package: 1 1017 REV E 05-FEB-2007
Level 16-30 Plan / Package: 1 1015 REV E 05-FEB-2007
Pedestrian Access Volumetric Easement / Package: 1 SK1 (Amended In Red 12-FEB-2007) 07-FEB-2007
Proposed Volumetric Easement / Package: 1 7467-7 (Amended In Red 12-FEB-2007) 04-OCT-2006
Level 15 Plan / Package: 1 1014 REV E 05-FEB-2007
Finishes Schedule - North Elevation / Package: 1 2101 10-JUL-2006
Finishes Schedule - South Elevation / Package: 1 2102 10-JUL-2006
Facade Detail 1 - Tower (Type A) / Package: 1 3101 (Amended In Red 12-FEB-2007) 10-JUL-2006
Facade Detail 3 - Tower (Type C) / Package: 1 3103 (Amended In Red 12-FEB-2007) 10-JUL-2006
Facade Detail 2 - Tower (Type B) / Package: 1 3102 (Amended In Red 12-FEB-2007) 10-JUL-2006
Finishes Schedule - East Elevation / Package: 1 2103 (Amended In Red 12-FEB-2007) 10-JUL-2006
Finishes Schedule - West Elevation / Package: 1 2104 (Amended In Red 12-FEB-2007) 10-JUL-2006
Facade Detail 4 - Tower (Type D) / Package: 1 3104 (Amended In Red 12-FEB-2007) 10-JUL-2006
Facade Detail 6 - Podium (Type F) / Package: 1 3106 (Amended In Red 12-FEB-2007) 10-JUL-2006
Facade Detail 7 - Podium (Type G) / Package: 1 3107 (Amended In Red 12-FEB-2007) 10-JUL-2006
Photomontages 1 / Package: 1 3152 10-JUL-2006
Street Paving and Landscape Plan / Package: 1 706042/DA/LA01 REV A (Amended In Red 12-FEB-2007) 18-AUG-2006
Photomontages 3 / Package: 1 3154 10-JUL-2006
Facade Detail 8 - Podium (Type H) / Package: 1 3108 (Amended In Red 12-FEB-2007) 10-JUL-2006
Facade Detail 5 - Podium (Type E) / Package: 1 3105 (Amended In Red 12-FEB-2007) 10-JUL-2006
Ground Level Plan / Package: 1 1004 REV E (Amended In Red 12-FEB-2007) 05-FEB-2007
Photomontages 2 / Package: 1 3153 REV A 26-FEB-2007
Basement Level 3 TP-21-10_REV 2 10-APR-2018
Basement Level 2 TP-21-11_REV 2 10-APR-2018
Basement Level 1 TP-21-12_REV 3 10-APR-2018
General Arrangement - North Elevation DUR-1118-GS-SK01 Rev B 14-MAY-2026 (Received)
General Arrangement - South Elevation DUR-1118-GS-SK02 Rev B 14-MAY-2026 (Received)
General Arrangement - East Elevation DUR-1118-GS-SK03 Rev B (Amended In Red 29-MAY-2026) 14-MAY-2026 (Received)
General Arrangement - West Elevation DUR-1118-GS-SK04 Rev B (Amended In Red 29-MAY-2026) 14-MAY-2026 (Received)


Advice

Please see the attached document(s) for any advices.

APPROVAL CONDITIONS



Permit to Which These Conditions Relate: DA - IPA - Carry Out Building Work
Activity(ies): Centre Activity Outside Centre
Stage: Centre Activities (Office, Shop & Restaurant) & Building Work On The Site Of & On Land Adjoining A Heritage Place



Permit to Which These Conditions Relate: DA - IPA - Material Change of Use
Activity(ies): Centre Activity Within Centre
Stage: Centre Activities (Office, Shop & Restaurant) & Building Work On The Site Of & On Land Adjoining A Heritage Place

General/Planning Requirements
 
Timing
1)   COPY OF PLANS ON SITE

A legible copy of the approved drawings and documents bearing "Council Approval" and the Development Approval Conditions package is to be available on site at all times during construction and earthworks.

GUIDELINE
This condition is imposed to ensure compliance with the development conditions of approval. The copy of the conditions and plans should be located in any site management office or with the site foreman. Any copies of conditions or plans that are illegible shall be deemed to be non compliance with this condition of approval.

 
As indicated
 
2)   CARRY OUT THE APPROVED DEVELOPMENT

Carry out the approved development generally in accordance with the approved drawing(s) and/or document(s).

GUIDELINE
This condition refers to the approved plans, drawings and documents to which the approval relates and is the primary means of defining the extent of the approval. Approved plans, drawings and documents are stamped PLANS and DOCUMENTS referred to in the APPROVAL and are dated to reflect the date of approval of the application by Council's Delegate.

 
While development is occurring on the site and then to be maintained
 
3)   COMPLETE ALL BUILDING WORK

Complete all building work associated with this development approval, including work required by any of the following conditions. Such building work is to be carried out generally in accordance with the approved plans, drawing(s), and/or documents and, where the building work is assessable development, in accordance with a current development permit.

GUIDELINE
This condition is imposed to ensure all building work associated with the use are in place before the use commences. It is not appropriate that the site be used without such work being completed. Please note that the work referred to in this condition involves operational work and may therefore constitute 'assessable development'. The Council informs you there fore that this condition does not authorise assessable development to occur and a development permit may therefore be necessary. Please refer to the Council's information sheets. For any enquiries about this condition, please contact the Assessment Manager.

 
Prior to commencement of use
 
4)   WIND STUDY

Incorporate into the development the findings and recommendations of the 'Wind Assessment' report prepared by Wind Engineering Services and dated 28 June 2006.

GUIDELINE
This condition is imposed to protect the comfort of pedestrian areas particularly footpaths and open plaza areas from potential arising effects of wind tunnelling and updraught/down draught impacts from the construction of tower development.

 
Prior to commencement of use
 
5)   MAINTAIN THE APPROVED DEVELOPMENT

Maintain the approved development (including landscaping, parking, driveways and other external spaces) in accordance with the approved drawing(s) and/or documents, and any relevant Council engineering or other approval required by the conditions.

GUIDELINE
This condition restricts changes that can be made to the approved development. Approved plans and documents are stamped PLANS and DOCUMENTS referred to in the APPROVAL and are dated to reflect the date of determination of the application by the Council's delegate. The extent to which plans can be modified is constrained by the definition of 'minor change' in schedule 10 and the requirements of section 3.5.24 of the "Integrated Planning Act 1997". It will be necessary to make a new application if the change is not a minor change. For any enquires about this condition, please contact the Assessment Manager.

 
To be maintained
 
6)   PUBLIC ACCESS - 24 HRS THROUGH SITE

Provide and maintain unimpeded and safe 24-hour public access through the subject site (to link Ann, Adelaide and George Streets), and ensure that access ways are designed to cater for disabled persons in accordance with "Australian Standard AS1428.1".

GUIDELINE
This condition is imposed to ensure on-going safe public access to designated public pedestrian spaces within the development.

 
To be maintained
 
7)   MODIFY EASEMENTS

The owner of Lot 102 on SP102966 and Brisbane City Council shall execute a deed of agreement regarding shared access and servicing arrangements between City Hall and development the subject of this application (incorporating amendments to Easement A on SP102966 in Lot 101 on SP102966 and Easement F on SP107657 in Lot 102 on SP102966) as outlined in the 'Access and Waste Management Deed' prepared by McCullough Robertson Lawyers and forwarded to Brisbane City Council on 28 February 2007.

 

The executed deed shall be:

  • lodged with the Titles Office prior to any site works commencing pursuant to this development approval; and
  • registered prior to commencement of the use permitted by this development approval.
 
As indicated
 
8)   ENERGY EFFICIENCY

Provide a written statement from a person who is qualified in using a recognisied energy rating system, such as BERS (Building Energy Rating System), Nathers or other recognised system, that the building(s) comply with the "Brisbane City Plan 2000 - Energy Efficiency Code".

GUIDELINE
This condition is imposed on all building work for offices, hotels and shops with a GFA over 2500m2 and for all new residential buildings except a house.

 
Prior to lodging an application for Building Works
 
9)   LIGHTING TO PUBLIC AREAS
Install and maintain a suitable system of lighting, to operate from dusk to dawn, within all areas where the public will be given access.

GUIDELINE
This condition is imposed to ensure on-going safe public access to designated public pedestrian spaces within the development

 
Prior to the commencement of the use and then to be maintained
 
10)   BICYCLE PARKING (CITY PLAN)

Install and maintain secure bicycle parking and associated support facilities generally in accordance with the approved plans and documents, and in accordance with the Centre Amenity and Performance Code as outlined below:

 

Employee

Provide a minimum of:

  • 160 bicycle spaces;
  • 80 lockers; and
  • 16 showers

Customer

Provide a minimum of 109 bicycle spaces.

GUIDELINE
This condition is imposed because bicycle parking and associated facilities are required to provide convenient facilities for cyclists and safe storage of bicycles to encourage cycling as an alternative for car commuting and also cater for short term requirements such as couriers bicycle facilities.

 
Prior to the commencement of the use and then to be maintained
 
11)   CAR PARKING

The car parking within the building is to be maintained exclusively for the ancillary use of the development. The parking is not to be made available to the general public and there is to be no advertising signage erected on or in the vicinity of the site advertising the availability of car parking to the general public.

 
Prior to the commencement of the use and then to be maintained
 
12)   HEIGHT OBSTACLE CASA
Air transport operations are not to be compromised:

The maximum height of the building, including any structures atop the building, must not exceed 184.50 metres AHD;

 
Prior to the commencement of the use and then to be maintained
12(a) HEIGHT OBSTACLE CASA

Permanent obstacle lighting for the building is to be adopted in accordance with the requirements of the Civil Aviation Safety Authority (CASA) and the Brisbane Airport Corporation (BAC);

 
Prior to the commencement of the use and then to be maintained
12(b) HEIGHT OBSTACLE CASA

Submit a separate application to and obtain approval from the BAC and CASA in relation to the use of any temporary structures (eg. cranes) in the construction of the building.

 
Prior to the commencement of the use and then to be maintained
12(c) HEIGHT OBSTACLE CASA

The ongoing monitoring and maintenance of the abovementioned obstacle lights is to be the responsibility of the building owner; and

 
Prior to the commencement of the use and then to be maintained
12(d) HEIGHT OBSTACLE CASA

In order to operate any other type of lighting (eg. search or laser type) from the building separate application to CASA's Brisbane Office must be made for a hazard assessment of those lights as required by the Civil Aviation Regulations 1988, Regulation 94 (Dangerous Lights).

 
Prior to the commencement of the use and then to be maintained
 
Monetary Contributions and Securities
 
Timing
13)   PAY OUTSTANDING CHARGES OR EXPENSES
Pay to Council any outstanding charges or expenses levied by the Council over the subject land.

GUIDELINE
This condition is imposed to ensure that there are no outstanding charges existing over the subject site, including outstanding rates. If there are out standing monies, they must be paid prior to commencement of the use.

 
Prior to commencement of use
 
14)   SEWERAGE: PER ET (EQUIVALENT TENEMENT)

Pay to Council a monetary contribution towards the cost of sewerage headworks, as outlined below, at the rate prevailing when the contribution is paid. This payment must be made prior to the permanent sewer connection being made to the site.

 

The contribution is calculated on 300.219 ETs (Equivalent Tenement) at the current rate of $5,772.00 per ET, for Sewerage Scheme Charge Area - S1 - CITY 1, .

 

The amount payable is currently assessed at $1,732,864 and comprises of the following :

• Treatment Headworks component: $435,318
• System Headworks component: $1,297,546
• Total contribution: $1,732,864

This headwork charge is the current rate for the 2006/2007 financial year.

 

 

 

GUIDELINE
This condition is imposed to require the payment of a proportional contribution towards a satisfactory sewerage treatment system within the locality of the site. For any enquiries about this condition, please contact the Engineering Delegate, Development and Regulatory Services.

 
Prior to the permanent water/sewer connection being made to the site or prior to endorsement of a community management statement, whichever is sooner
 
15)   WATER SUPPLY: PER ET (EQUIVALENT TENEMENT)

Pay to Council a monetary contribution towards the cost of water supply headworks, as outlined below, at the rate prevailing when the contribution is paid. This payment must be made prior to the permanent water connection being made to the site.

 

The contribution is calculated on 359.343 ETs (Equivalent Tenement) at the current rate of $4,996.00 per ET, for Water System Infrastructure Charges Plan Area - GREEN HILL W6

 

The amount payable is currently assessed at $1,795,278 and comprises of the following:

• Treatment Headworks component: $337,782
• Distribution Head works component: $1,457,496
• Total contribution: $1,795,278

This headwork charge is the current rate for the 2006/2007 financial year.

GUIDELINE
This condition is imposed to require the payment of a proportional contribution towards a satisfactory water supply treatment system to the site. For any enquiries about this condition, please contact the Engineering Delegate, Development and Regulatory Services.

 
Prior to the permanent water/sewer connection being made to the site or prior to endorsement of a community management statement, whichever is sooner
 
16)   PARKLAND

Pay to Council a monetary contribution towards the provision of parkland at the rate applicable at the time of payment. The amount is currently calculated at $2.70 per square metre of gross floor area. The required contribution currently totals $107584.

This park contribution is the current rate for the 2006/2007 financial year.

GUIDELINE
This condition is imposed when a monetary contribution for parkland is required. The contribution is calculated in accordance with Planning Scheme Policy 1 - Development Contributions for Parks and Recreational Facilities Arising from Subdivision of Land and from Material Change of Use or Development of Land.

 
Prior to the commencement of the use or prior to the endorsement of a Community Management Statement, whichever is sooner
 
Architecture
 
Timing
17)   DETAILED & COLOURED MODEL

Submit to the Delegate, Development Assessment, a detailed and coloured model at a scale of 1:500 for incorporation into the Council's Central City Model.

 
Prior to building work commencing
 
18)   EXTERNAL DETAILS

Submit for the approval of the Team Leader, Development Assessment Team Central, further details of the building, facade treatment and external materials, colours and finishes generally consistent with the approved plans.

 
Prior to building work commencing
18(a) EXTERNAL DETAILS

Implement the above detailed design treatments.

 
Prior to building work commencing
 
19)   HERITAGE PLACE- BEST PRACTICE STANDARDS

Carry out all conservation, restoration and adaptation work to the existing culturally significant structure in accordance with best heritage conservation practice and with The Burra Charter (Australia ICOMOS Charter for the Conservation of Places of Cultural Significance).

GUIDELINE
This condition is imposed to ensure best practice for development work to heritage sites. For any enquiries about this condition, please contact the Development Assessment Team Architect.

 
Prior to site/building works commencing and then to be maintained
 
20)   SUPPLY/INSTALL ARTWORKS (CITY PLAN)
Supply, install and maintain within an area to be determined by the Delegate, Development Assessment, artworks (including but not necessarily limited to, sculptures, ceramic works, mosaics and wall reliefs) by a recognised artist or craftsperson in accordance with the "Brisbane City Plan 2000 - City Centre Local Plan Code".

Plan for artworks or sculptures that meet the following criteria:

  1. Constitute not less than 0.25 per centum of the total estimated project cost as certified by a recognised Quantity Surveyor;
  2. Be suitable for the setting in terms of design, choice of materials, durability and resistance to vandalism; and,
  3. Be satisfactory to the owner/developer of the subject site and the Delegate, Development Assessment.
 
Prior to commencement of use
20(a) SUPPLY/INSTALL ARTWORKS (CITY PLAN)

Enter into a contractual agreement (to be endorsed by the Delegate, Development Assessment) with a recognised artist or craftsperson to supply and install the artworks required by the above; and

 
Prior to commencement of use
20(b) SUPPLY/INSTALL ARTWORKS (CITY PLAN)
Install the endorsed artworks or sculptures.
 
Prior to commencement of use
 
21)   OVERALL HEIGHT - SURVEY CERTIFICATION
The overall height of the proposed building(s) is to be in accordance with the following requirements:

Construct the floor levels in accordance with the floor levels on the approved drawings; and

GUIDELINE
This condition is imposed to ensure the floor levels and maximum overall height of the proposed building is in accordance with the development approval. For any enquiries about this condition, please contact the Development Assessment Team Architect.

 
Prior to commencement of use
21(a) OVERALL HEIGHT - SURVEY CERTIFICATION

Submit certification from a licensed surveyor that the as constructed floor levels are in accordance with part (a) of this condition and that the maximum overall height of the building does not exceed 184.50 metres AHD.

This information is to be submitted to Licensing and Compliance Team Central.

 
Prior to commencement of use
 
22)   LIGHT REFLECTIVITY & SOLAR (HEAT) REFLECTIVITY
Submit to the Delegate, Development Assessment documentary evidence that:The level of light reflectivity from the approved development will not exceed 20 percent; and

GUIDELINE
This condition is imposed to protect the amenity and appearance of the surrounding area from adverse impacts such as heat transmission and light reflectivity arising from the use of excessively reflective glass in building facades.

 
Prior to the commencement of the use and then to be maintained
22(a) LIGHT REFLECTIVITY & SOLAR (HEAT) REFLECTIVITY
The level of solar (heat) reflectivity from the approved development will not exceed 20 percent.
 
Prior to the commencement of the use and then to be maintained
 
23)   LIGHTING SYSTEM TO AWNING
Install a lighting system to the underside of the proposed awning over the footpath in accordance with the following:

Provides lighting to public footpaths covered by permanent awnings to a minimum of 20 lux (horizontal plane) at footpath level;

GUIDELINE
This condition is intended to ensure that pedestrians can move safely in front of the site. For any enquiries about this condition, please contact the City Lighting Unit, Local Asset Services Central District (pH 3403 0307).

 
Prior to the commencement of the use and then to be maintained
23(a) LIGHTING SYSTEM TO AWNING

The lighting system meets the requirement of the City Plan 2000 - Awning Lighting Code;

 
Prior to the commencement of the use and then to be maintained
23(b) LIGHTING SYSTEM TO AWNING

The lighting system adequately illuminates any pedestrian way covered by the subject awning from dusk until dawn; and

 
Prior to the commencement of the use and then to be maintained
23(c) LIGHTING SYSTEM TO AWNING

Is to be maintained by the owner of the building in a safe and good working order.

 
Prior to the commencement of the use and then to be maintained
 
24)   AIR CONDITIONING & OTHER PLANT ENCLOSURES

Install and maintain suitable screening to all air conditioning, lift motor rooms, plant and service facilities located at the top of or on the external face of the building. The screening structures must be constructed from materials that are consistent with materials used elsewhere on the facade of the building. There are to be no individual external air conditioning units.

 
Prior to the commencement of the use and then to be maintained
 
Landscape Architecture and Open Space Planning
 
Timing
25)   DETAILED PLAN-COMMERCIAL
Prepare and landscape the site in accordance with a Landscape Management, Site Works and Planting Plan.

Submit and receive approval by the Delegate, Development Assessment for a detailed Landscape Plan for all on-site landscape works identified on the approved plan(s) of layout 706042/DA/LA01revA. The plan is to be prepared at a scale of 1:100 by a suitably qualified and experienced Landscape Architect/Designer, and must comply with the "Brisbane City Plan 2000- Landscaping Code". The plan should include the following:

i) Siteworks:

  • The extent of soft and hard landscape works;
  • Existing and proposed finished levels to external works particularly in critical areas (eg. top and toe of retaining walls, steps and adjoining boundaries);
  • Extent of basement and roof lines;
  • Details of podium planters to demonstrate adequate width and depth of soil for the proposed planting. Minimum internal planter depths to be as follows: trees - 1200mm (1500mm internal width), large shrubs and palms - 800mm, small shrubs and groundcovers - 600mm;.
  • Description/detail of critical design elements where applicable (eg. stabilisation of batters, retaining walls, podium planters, trees in car park areas, fences etc.);
  • Basic specification notes for soil preparation and planting, including mulching and soil type both existing and imported; and
  • Podium planters to be supplied with reticulated irrigation system connected to a non-town water supply, and drainage is to be connected to stormwater system;

ii) Planting:

  • A planting schedule listing proposed plants by botanical names, numbers, spacing and size at time of planting;
  • Planting palette that reflects the sub-tropical character of Brisbane, and which is appropriate for the planting environment (enclosed planters on podium); and
  • Screen planting to utility spaces.

GUIDELINE
This condition is imposed when there is a landscape component to a High Level development application, and Council requires more details of the proposed landscape works.

 
Prior to commencement of site works
25(a) DETAILED PLAN-COMMERCIAL

Carry out the landscaping and associated works documented in the approved Landscape Management and Site Works Plan in accordance with standard Best Trade Practice.

 
Prior to commencement of site works
25(b) DETAILED PLAN-COMMERCIAL

Advise Council upon completion of the landscape works by completing the development details and Part B of the Compliance Certificate-Landscaping.

 
Prior to commencement of site works
 
26)   RETAIN EXISTING STREET TREES

Existing street trees Caesalpinia ferrea (8 to Adelaide Street, 8 to George Street and 4 to Ann Street) shall be identified, retained and protected whilst any demolition or building works are occuring on the site. Any pruning, trimming or works within the dripline of these trees to accommodate the development must be performed by a qualified arborist in accordance with the Australian Standard for the Pruning of Amenity Trees AS4373, AND WITH PRIOR APPROVAL FROM BCC's VEGETATION AND PEST SERVICES.

 

Street trees are protected under Category 1 of NALL (Council-Controlled Vegetation) and an Application To Carry Out Works (including Interfere with) on Protected Vegetation must be obtained prior to commencing any work which may affect the canopy or root zone of the trees.

GUIDELINE
This condition is imposed where existing vegetation contributes significantly to the character of the existing streetscape and the surrounding amenity of the locality. For any enquiries about this condition, please contact Vegetation and Pest Services on 3403 8888.

 
While site works are occurring and then to be maintained
 
27)   STREETSCAPE WORKS-SCIPS 2
Construct streetscape works in accordance with the following:

Submit a pedestrian lighting design (including details) for the full street frontage of the development for the approval of the City Lighting Officer, Local Asset Services. The lighting is to be in accordance with AS/NZS1158.3.1, 1999 Pedestrian Area (Category P3) Lighting and the ‘Centres Detail Design Manual’. The applicant is to be responsible for the obtaining of all necessary approvals from Energex, all costs associated with the street lighting, the installation, ensuring the system is operational and to provide as-constructed lighting design plans.

GUIDELINE
For any enquiries about this condition, please contact the Landscape Architect, Development Assessment.

 
Prior to the commencement of footpath demolition
27(a) STREETSCAPE WORKS-SCIPS 2

The applicant is required to lodge a permit ‘Application for Permits Relating to Roads and Footway’.

 
Prior to the commencement of footpath demolition
27(b) STREETSCAPE WORKS-SCIPS 2

Remove the existing footpath including affected street signage for the full length of the frontages to Adelaide, George and Ann Streets and construct the required works to a standard and of materials consistent with the approved Streetscape Works Plan and the requirements of the ‘Centres Detail Design Manual’. Reinstate all street signage as directed by Council.

 
Prior to the commencement of footpath demolition
27(c) STREETSCAPE WORKS-SCIPS 2

Provide a letter of Certification for all constructed footpath works as documented on the ‘Approved Plan’ by a Registered Practising Engineer of Queensland (RPEQ). Certification is to cover:

  • Construction of footpath and associated works including, all sub-surface works, kerb and channel, footings for pedestrian and road lights, installation of furniture and any other construction associated with the footpath works.
  • Shade structures associated with the footpath works.
  • All electrical works located and constructed in accordance with submitted electrical plan.
 
Prior to the commencement of footpath demolition
27(d) STREETSCAPE WORKS-SCIPS 2

Maintain the streetscape works, including street trees and landscaping, for a period of 12 months from the date of the On Maintenance inspection in accordance with the ‘Centres Detail Design Manual’.

 
Prior to the commencement of footpath demolition
 
28)   STREETSCAPE WORKS-SCIPS
Provide streetscape works in accordance with the following:

Submit a ‘Streetscape Works Plan’ for detailed design approval of the Landscape Architect, Development Assessment, for required works to be undertaken within the Adelaide Street, George Street and Ann Street footpath reserves as per amended in red Street Paving drawing no. 706042/DA/LA01/revA. The plan is to be prepared at a scale of 1:100 by a suitably qualified and experienced Landscape Architect/Designer and the works are to be constructed to a standard and of materials consistent with the requirements of Council's Centres Detail Design Manual.

 

The plans are to include but not be restricted to the following:

  • full width concrete flagstones with trim flagstone pavement treatment as indicated on the drawing number above
  • Identification of the accurate location of the existing street trees to be retained and protected during construction ( 8 Caesalpinia ferrea to Adelaide Street, 8 Caesalpinia ferrea to George Street and 4 Caesalpinia ferrea to Ann Street)
  • Existing street trees and any new street trees in tree grates (with tree guards as appropriate), integrated in the proposed pavement pattern
  • rate 3 pedestrian lights
  • location of all the underground and above ground services
  • all service pits to be supplied with infillable pit lids
  • street furniture to enhance footpath comfort and amenity
  • location of awning in accordance with Section 11.2 AWNINGS within CDDM.
  • all finished surface levels including cross falls and longitudinal grades
  • tactile pavers in "Stylestone" concrete at driveways and kerb ramps in accordance with AS1428.4 and detail UMS-213 rev B
  • porphyry or imitation porphyry kerbing for the full street frontage
  • location of property boundary including the required corner truncation and easments
  • proposed road use adjacent to the kerbing (eg. public transport stops, parking bays, no standing zones)
  • existing and proposed signage.

GUIDELINE
This condition is imposed when the proposed development is located within a Centre, which is covered by the Centres Detail Design Manual. The objective is to ensure that the external spaces are developed in a way that enhances the subject proposal and contributes positively to the streetscape character and overall image and quality of public spaces throughout the City. Streetscape works are to be carried out in accordance with the approved plans and workmanship is to be of acceptable standards and maintained accordingly. The Centres Detail Design Manual is available for purchase at all Council Customer Service Centres. The final locations and number of items of street furniture is to be determined by the Landscape Architect, Development Assessment. For any enquiries about this condition, please contact the Landscape Architect, Development Assessment. The plan (minimum 8 copies), together with the appropriate fee, should be lodged at the Development and Regulatory Services? Counter, Floor 1, Brisbane Administration Centre. Refer to Appendix F of the Centres Detail Design Manual.

 
Prior to commencement of operational works/building works
28(a) STREETSCAPE WORKS-SCIPS

Obtain all necessary approvals for the satisfactory construction of these works.

 
Prior to commencement of operational works/building works
 
Pollution
 
Timing
29)   PLANT AND EQUIPMENT

Following the installation of all mechanical plant and equipment, an appropiately qualified acoustic consultant must submit certification to the Team Leader Licensing and Compliance Central that the abovementioned plant and equipment is adequately noise attenuated, in accordance with Brisbane City Council's, Noise Impact Assessment Planning Scheme Policy.

 
Prior to commencement of use
 
30)   REFUSE BIN WASHING FACILITY

Construct an on-site refuse bin washing facility for food outlet refuse bins. The area must be provided with a tap, paved with an impervious material, graded and drained to sewer subject to the requirements and recommendations of Brisbane Water.

GUIDELINE
This condition is imposed where it is intended to clean refuse containers on site.

 
Prior to the commencement of the use and then to be maintained
 
Engineering
 
Timing
31)   ON SITE EROSION- MINOR WORK
Minimise on-site erosion and the release of sediment or sediment-laden stormwater from the site at all times.

Prepare an Erosion and Sediment Control (ESC) Management Plan for the site in accordance with Council's Best Practice Guidelines for the Control of Stormwater Pollution from Building Sites and accompanying fact sheets, Brisbane City Council and Gold Coast City Council, 2000 (or later version);

GUIDELINE
This condition is utilised where the potential for soil erosion, sediment loss from the site, and environmental impact on waterways is considered to be medium to low. Whilst not requiring submission of detailed information as defined in Council's "Erosion and Sediment Control Standard (Version 8 or later)", the ESC Management Plan must still satisfy the general requirements of this Standard (ie. minimise soil erosion and sediment loss from the site at all times during the works). No formal ESC Program is to be submitted for Council assessment however a copy of the ESC Management Plan is required on-site. Non-compliance may result in prosecution under Environmental Legislation. For any enquiries regarding this condition please contact the Engineering Delegate, Development and Regulatory Services.

 
Prior to site works commencing (ie. any land-disturbing development)
31(a) ON SITE EROSION- MINOR WORK

Implement and maintain on-site The ESC Management Plan for the duration of the operational or building works, and until exposed soil areas are permanently stabilised (e.g. turfed, concreted). The documented ESC Management Plan must be available on-site for inspection by Council Officers during these works.

 
Prior to site works commencing (ie. any land-disturbing development)
 
32)   CONSTRUCTION MANAGEMENT PLAN
Prepare a Construction Management Plan for the subject site:

Submit for approval of the Engineering Delegate, Development Assessment, Central Team, a Construction Management Plan for the demolition, excavation and construction phases of the approved development. Separate CMPs may be appropriate for the individual components. The CMP is to be generally in accordance with the Transport, Access. Parking and Servicing Planning Scheme Policy of the Brisbane City Plan 2000.

The CMP is to provide the following details and address impacts, where applicable:

  1. Provision for pedestrian management including alternative pedestrian routes, past or around the site;
  2. Location of and impacts on any Council or other authority's assets on and external to the site. Council assets include water, sewer, stormwater, street trees and kerbside allocation signs and linemarking such as bus stops, loading zones and parking meters and/or ticket dispensers. Details of street trees are to include location, species, trunk and canopy size;
  3. Temporary vehicular access points and frequency of use;
  4. Location of any external loading areas;
  5. How materials are to be loaded/unloaded and potential impacts on existing street trees;
  6. Location of materials, structures, plant and equipment to be stored or placed on the construction site;
  7. Location of proposed external hoardings and gantries;
  8. Employee and visitor parking areas;
  9. Anticipated staging, programming.

NOTES:

  • Ann and Adelaide Street are not considered suitable for locating kerbside Work Zones.
  • Approval for footpath closures and/or temporary vehicle access will only be considered where it can be demonstrated that no reasonable alternative can be provided due to site constraints and that safety, capacity and/or operation of public transport, vehicle and pedestrian traffic are not compromised.
  • Proposed arrangements utilising any part of the road reserve for construction related activities, for example, overhead gantries, hoardings or pedestrian diversions, are subject to separate application fees and rental fees.
  • The Construction Management Plan may require modification, at Council's discretion, to reflect changes in relevant legislation and industry best practice prevailing at the time of the permit application and throughout the construction program;

 

GUIDELINE
Construction activities need to be limited to manage the impact on the surrounding area., This condition is intended to apply throughout the period of site preparation to the completion of the development. Please note that an operational works application is to be submitted.

 
Prior to lodging an application for Building Works
32(a) CONSTRUCTION MANAGEMENT PLAN

Arrange a pre-start meeting with the Engineering Delegate, Development Assessment, Central Team;

 
Prior to lodging an application for Building Works
32(b) CONSTRUCTION MANAGEMENT PLAN

Obtain relevant permits from the Engineering Delegate, Development Assessment, Central Team, to carry out any works within the road reserve required by the approved Construction Management Plan.

Applications for permits will be assessed on the basis of road and footpath network operating conditions prevailing at the time. Council will consider impacts of other construction works or events which occur during the life of the permit. Council may issue permits which vary from the previously approved arrangements or revoke permits at any time if it considers that safety, capacity and/or operation of public transport, vehicle and pedestrian traffic are likely to be compromised during the construction project.

 
Prior to lodging an application for Building Works
32(c) CONSTRUCTION MANAGEMENT PLAN

Implement and maintain the approved Construction Management Plan;

 
Prior to lodging an application for Building Works
32(d) CONSTRUCTION MANAGEMENT PLAN

Legible copies of the approved Construction Management Plan and current permits are to be kept on site and be made available on request.

 
Prior to lodging an application for Building Works
 
33)   RETAINING WALLS

Any retaining walls greater than 1.0 metre in height are required to be structurally certified for design and construction by a Registered Professional Engineer Queensland (RPEQ). The certification is to include the stormwater drainage (surface and seepage water) associated with the wall ensuring that the water is directed to an acceptable lawful and legal point of discharge and does not cause any ponding, nuisance or disturbance to adjacent property owners. All retaining walls are to comply with the City Plan Filling and Excavation Code.

GUIDELINE
This condition is intended to ensure that retaining walls associated with the development that are higher than 1 metre, are designed and constructed to industry standards and also, to ensure that no adverse impact is created by the structures on the surrounding properties. The retaining wall designer should note that timber retaining walls facing onto Council property (including the road reserve) will not be permitted. Retaining walls facing onto road reserve or parkland are to be contained entirely within the proposed development site, including the retaining wall's footings. Where retaining walls are proposed to be constructed between adjoining properties, it is also suggested that the use of timber sleeper retaining walls be restricted due to their limited life and the potential problems they may cause to future property owners. Where the combined height of the retaining wall and fence exceeds 2.0 metres, a Development Permit for Building Work will need to be granted. For any enquires about this condition please contact the Engineering Delegate, Development and Regulatory Services.

 
Prior to commencement of use
 
34)   PEDESTRIAN EASEMENTS

Grant volumetric easements for pedestrian access as follows;

  1. 4.5 metres wide for the full length of the George Street frontage with 3.0 metre by 3.0 metre by single chord truncations at the Ann and Adelaide Street intersections generally as shown on the approved drawing by Cronepartners number SK1 dated 7 February 2007 as amended in red.
  2. Provision for a deviation around the passenger setdown area in Ann Street, generally as shown on the approved drawing by PMM number 7467-7 dated 4 October 2006 as amended in red.

The lower limit shall be the finished surface of the waterproof membrane directly below the surface paving material and the upper limit shall be a minimum of 3.0 metres above the finished footpath surface. The easement is to be in favour of Council.

GUIDELINE
This condition is imposed to provide pedestrian access. Easements in favour of the Brisbane City Council are required to have the necessary easement documentation prepared (free of costs and compensation to Council) by the Brisbane City council. Easements are to be shown on a Survey Plan and lodged with the Delegate Plan Sealing, Licensing Sealing and Certificates Unit. Enquiries regarding any legal documentation can be directed to Licensing, Sealing and Certificates Unit, Development and Regulatory Services (pH 3403 9050). For any other enquiries about this condition, please contact the Engineering Delegate, Development and Regulatory Services.

 
Prior to commencement of use
 
35)   ACCESS, GRADES, MANOEUVRING, CARPARKS, SIGNS,
Construct and delineate or sign (as required) the following requirements as indicated on the approved plan(s) of layout:

Construct a pavement of minimum Type A standard and surface with an impervious material (including associated drainage) to the area on which motor vehicles will be driven and/or parked. {Construction of such pavement is to be certified by a Registered Professional Engineer of Queensland (RPEQ)};

GUIDELINE
The "Brisbane City Plan 2000 - Transport, Access, Parking and Servicing Planning Policy" requires adequate on- site provision of parking, servicing and manoeuvring areas. This condition specifies detailed design requirements as indicated on the approved drawings and documents to which the approval relates.

 
Prior to the commencement of the use and then to be maintained
35(a) ACCESS, GRADES, MANOEUVRING, CARPARKS, SIGNS,

The driveways at grades shown on the approved plans and documents (or if not shown at grades not greater than those set out in "Brisbane City Plan 2000 - Transport, Access, Parking and Servicing Planning Policy"). Grades of existing driveways where being retained are acceptable;

 
Prior to the commencement of the use and then to be maintained
35(b) ACCESS, GRADES, MANOEUVRING, CARPARKS, SIGNS,

Manoeuvring and standing on site for 8 Vans, 1 Small Rigid Vehicle, 5 Medium Rigid Vehicles and for the loading and unloading of the vehicle(s);

Provision is to be made for Large Rigid Vehicles to be able to access the site outside business hours and utilise standing areas for other service vehicles for manoeuvring.

 
Prior to the commencement of the use and then to be maintained
35(c) ACCESS, GRADES, MANOEUVRING, CARPARKS, SIGNS,

Parking on the site for a maximum of 156 cars for the 'Northbank Plaza' building, a maximum of 235 cars for the new commercial tower and a maximum of 9 cars for the new 3 storey podium building (corner of Ann Street and George Street), and for the loading and unloading of vehicles within the site;

 
Prior to the commencement of the use and then to be maintained
35(d) ACCESS, GRADES, MANOEUVRING, CARPARKS, SIGNS,

8 of the above parking spaces are to be provided for people with disabilities;

 
Prior to the commencement of the use and then to be maintained
35(e) ACCESS, GRADES, MANOEUVRING, CARPARKS, SIGNS,

A minimum 4.5 metres height clearance to MRV loading dock standing and access areas, a minimum 3.5 metres height clearance to SRV loading dock standing and access areas, a minimum 2.3 metres to Van standing and access areas, a minimum 2.3 metres to all undercover car parking areas and a minimum of 2.5 metres above parking spaces for people with disabilities (Note, The minimum clear height shall be measured to the lowest appurtenance on the ceiling - ie. fire sprinklers, services, lighting fixtures, signs etc.). Height clearances to car parking where constrained by existing structures are acceptable;

 
Prior to the commencement of the use and then to be maintained
35(f) ACCESS, GRADES, MANOEUVRING, CARPARKS, SIGNS,

A height clearance sign located at the entrance(s) to undercover car parking and service vehicle areas;

 
Prior to the commencement of the use and then to be maintained
35(g) ACCESS, GRADES, MANOEUVRING, CARPARKS, SIGNS,

An appropriate area for the storage and collection of refuse, including recyclables, in a position which is accessible to service vehicles on the site;

 
Prior to the commencement of the use and then to be maintained
35(h) ACCESS, GRADES, MANOEUVRING, CARPARKS, SIGNS,

All vehicle access associated with development on Lot 102 on SP102966 shall be restricted to the approved crossover in Ann Street.

 
Prior to the commencement of the use and then to be maintained
35(i) ACCESS, GRADES, MANOEUVRING, CARPARKS, SIGNS,

The internal paved areas are to be signed and delineated in accordance with the approved plans, Manual of Uniform Traffic Control Devices and Austroads.

 
Prior to the commencement of the use and then to be maintained
 
36)   LOADING DOCK MANAGER

Manage the service vehicle facilities with an On Site Loading Dock Manager to ensure safe, efficient and effective use. Service vehicles larger than Medium Rigid Vehicles are to access the site outside peak traffic hours and business hours.

 
Prior to the commencement of the use and then to be maintained
 
37)   REPAIR DAMAGE TO KERB, FOOTPATH OR ROAD
Repair any damage to existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel and stormwater gullies and drainlines) that may occur during any works carried in association with the approved development.

GUIDELINE
The intention of this condition is to ensure that any works undertaken as part of the approved development do not damage Council assets or leave Council assets in an unacceptable and unsightly manner. For enquiries regarding this condition, please contact the Engineering Delegate, Development and Regulatory Services.

 
Prior to commencement of use
 
38)   PROVIDE/EXTEND 150 MM SEWER CONNECTION(S)
Provide a sewer property connection to serve the development designed and constructed in accordance with approved engineering plans and Council's "Water and Sewerage Reticulation Standards". NB. The size of the connection shall be determined by the total number of fixture units.

Submit engineering plans prepared by a Registered Professional Engineer Queensland (RPEQ), and in accordance with Council's "Water and Sewerage Reticulation Standards" showing the design the works. Obtain the approval from the Engineering Delegate, Development Assessment, Development and Regulatory Services;

GUIDELINE
This condition is imposed to provide a separate new sewerage connection to the development. For enquiries regarding this condition, please contact the Engineering Delegate, Development and Regulatory Services.

 
Prior to undertaking the works
38(a) PROVIDE/EXTEND 150 MM SEWER CONNECTION(S)

Pay to Council the cost of live connection to the sewer main;

 
Prior to undertaking the works
38(b) PROVIDE/EXTEND 150 MM SEWER CONNECTION(S)

Construct the works in accordance with the approved engineering plans to a standard that will be satisfactory to be accepted "on" and "off" maintenance as a Council asset, by the Engineering Delegate, Development and Regulatory Services;

 
Prior to undertaking the works
38(c) PROVIDE/EXTEND 150 MM SEWER CONNECTION(S)

Submit "As Constructed" plans including an assest register, approved by a Registered Professional Engineer Queensland (RPEQ) (to a standard specified in Council's "Water and Sewerage Reticulation Standards") certifying that the works have been completed in accordance the approved design and any approved modifications.

 
Prior to undertaking the works
 
39)   ON-SITE DRAINAGE
Run-off from roof and developed surface areas of the site, and any run-off onto the site from adjacent areas, are to be collected internally and directed to a lawful point of discharge in accordance with Council's "Subdivision and Development Guidelines".

Submit drainage plans and engineering calculations (as a part of the development’s Site Based Stormwater Quantity Management Plan) in accordance with Council's "Subdivision and Development Guidelines" showing the design of the drainage of the roof and developed surfaces. Obtain approval from the Engineering Delegate, Development Assessment.

Such plans are to show adequate survey information on areas adjoining the site with particular attention to any nuisance or annoyance to adjoining property owners.

Please note all constructed stormwater outlets that are proposed to discharge directly to a waterway, shall ensure an appropriate waterway setback, reduction in flow outlet velocity and concentration and, include any supplementary planting works that may be required (refer "Stormwater Outlets in Parks and Waterways", BCC July 2000);

GUIDELINE
The purpose of this condition is to ensure that stormwater run off from the site and adjacent properties will be handled adequately. Disposal by gravity pipeline is required if practical. Use of pumps for disposal of stormwater may be approved only if the applicant can show evidence to Council of having taken all reasonable steps to obtain written permission from adjacent property owners for construction of a gravity pipeline, and of this being unobtainable.The proposal may include water saving and reuse devices such as rain water tanks provided that the proposal satisfies Council that devices will be satisfactorily maintained by the owners of the property. For any enquiries about this condition, please contact the Engineering Delegate, Development and Regulatory Services.

 
Prior to site works/building works commencing
39(a) ON-SITE DRAINAGE

Complete the works in accordance with the approved engineering plans and other elements of the development’s Site Based Stormwater Management Plan; and

 
Prior to site works/building works commencing
39(b) ON-SITE DRAINAGE

Submit "As Constructed" plans approved by a Registered Professional Engineer of Queensland (RPEQ) (to a standard specified in Council's "Subdivision and Development Guidelines") certifying that the works have been completed in accordance with the approved design and any approved modifications.

 
Prior to site works/building works commencing
 
40)   PONDING OF STORMWATER
Adjoining properties and roads are to be protected from ponding or nuisance from stormwater runoff.

Adjoining properties and roads are to be protected from ponding or nuisance from stormwater as a result of the proposed works;

GUIDELINE
This condition is imposed to ensure that the developer is aware that they are responsible for all remedial works required as a result of any site works and, that they must protect neighbouring properties and roads from ponding and nuisance water from the proposed development. Where this rectification work involved drainage, plans are to be lodged showing the manner in which it is intended to rectify the site drainage. These plans must be approved by the Engineering Delegate. For any enquiries about this condition, please contact the Engineering Delegate, Development and Regulatory Services.

 
Prior to commencement of use
40(a) PONDING OF STORMWATER

Rectify all damage resulting from the ponding of stormwater or nuisance from discharge of stormwater from the site to adjacent properties.

 
Prior to commencement of use
 
41)   SERVICE CONDUITS & MAINS
Supply and install all service conduits and meet the cost of any alterations to public utility mains, existing mains, services or installations required in connection with the approved development. This includes the relocation of any fire hydrants and valves from within the limits of the development's vehicular footway crossings if applicable.

Complete the works required by this condition;

GUIDELINE
This condition is imposed when additions, alterations or extensions to service conduits, mains and other services are required as a result of the approved development. Applicants should liaise with the appropriate service authorities. For any enquiries about this condition, please contact the Engineering Delegate, Development and Regulatory Services (regarding advise on traffic signal conduits, stormwater, water supply and sewerage mains etc.) or the relevant public utility authorities (for advice on other services).

 
Prior to commencement of use
41(a) SERVICE CONDUITS & MAINS

Submit "As Constructed" plans including an asset register (if required), approved by a registered Professional Engineer Queensland (RPEQ) (in accordance with Council's "Subdivision and Development Guidelines" and "Water and Sewerage Reticulation Standards") showing the works required by this condition.

 
Prior to commencement of use
 
42)   TELECOMMUNICATION - UNDERGROUND
Provide underground telecommunication services to the proposed development.

Enter into an agreement with a telecommunication company and provide underground telecommunication services within and adjacent to the proposed development; and

GUIDELINE
This condition is imposed to ensure that the provision of essential communication services are provided to the development. For any enquiries about this condition, please contact relevant service carriers regarding communications or Telstra (pH 132 200).

 
Prior to commencement of use
42(a) TELECOMMUNICATION - UNDERGROUND

Forward a copy of the agreement to the Engineering Delegate, Development and Regulatory Services.

 
Prior to commencement of use
 
43)   ELECTRICITY (UNDERGROUND SUPPLY AREA)
Provide underground electricity services in accordance with an approved electricity reticulation plan and the Council's "Subdivision and Development Guidelines (Public Utilities Section)". Note: Even though the development may be in an area serviced by overhead electricity, UNDERGROUND supply to the development is now required - no additional poles or overhead mains are to be erected.

Lodge electricity reticulation plans showing and the proposed electricity services and obtain approval from the City Lighting Unit, Local Asset Services Central District;

GUIDELINE
This condition is imposed when a proposed development would require the provision of electricity services in accordance with Council's "Guidelines for the Provision of Underground Electricity". Please refer to the Council's information sheet on lodging detailed design applications. For any enquiries about this condition, please contact the City Lighting Unit (pH 3403 0307) regarding electricity reticulation plans or Energex (pH: 131 253) regarding electricity supply.

 
Prior to commencement of use
43(a) ELECTRICITY (UNDERGROUND SUPPLY AREA)
Enter into an agreement with an electricity supplier to provide underground electricity services in accordance with the above approved electricity reticulation plans; and
 
Prior to commencement of use
43(b) ELECTRICITY (UNDERGROUND SUPPLY AREA)

Forward a copy of the agreement to the Engineering Delegate, Development and Regulatory Services.

 
Prior to commencement of use
 
44)   PUBLIC LIGHTING
Provide a public lighting system in accordance with an approved street lighting design plan and Council's "Street Lighting Design Guidelines".

Lodge street lighting design plans showing the proposed public lighting system and obtain approval from the City Lighting Unit, Local Asset Services Central District;

GUIDELINE
This condition is imposed when a proposed development requires the provision of public lighting facilities in accordance with the "Street Lighting Design Guidelines". Please refer to the Council's information sheet on lodging detailed design applications. For any enquiries about this condition, please contact the City Lighting Unit (pH 3403 0307) regarding electricity reticulation plans or Energex (pH: 131 253) regarding electricity supply.

 
Prior to commencement of use
44(a) PUBLIC LIGHTING
Enter into an agreement with an electricity supplier to provide a public lighting system in accordance with the above approved lighting design plans; and
 
Prior to commencement of use
44(b) PUBLIC LIGHTING

Forward a copy of the agreement to the Engineering Delegate, Development and Regulatory Services.

 
Prior to commencement of use
 
45)   METERING - MIXED USE DEVELOPMENT
Provide a water service with approved Council meter assembly and meter box to the front real property boundary of the development in accordance with Council's "Water and Sewerage Reticulation Standards". Where a mixed usage site is approved for development and the proposed development comprises mixed classifications as defined by the Building Code of Australia containing any of Classes 5 to 9 and any of Classes 2 to 4, then the developer must provide a separate metered water service for the Class 2 to 4 occupancy as opposed to the Class 5 to 9 occupancy. This requirement is exclusive of any special fire service consideration i.e. internal hydrants, fire hose reels and sprinkler systems.

Submit engineering plans prepared by the RPEQ (Registered Professional Engineer Queensland) , and in accordance with Council’s "Water and Sewerage Reticulation Standards" showing service and meter works. (The size of the service shall be determined by the water supply requirement of the proposed development). Obtain the approval from the Engineering Delegate, Development Assessment, Development and Regulatory Services;

GUIDELINE
This condition is imposed to supply a water service and a meter(s) to a Development / Community Title Development / Standard / Building or Volumetric format. The meter(s) shall be accessible to BCC employees or agents for the purpose of reading and maintaining the meter(s). The meter(s) will become and remain property of the Brisbane City Council.

 
Prior to undertaking the works
45(a) METERING - MIXED USE DEVELOPMENT

Pay to Council the cost of live connection to the water main;

 
Prior to undertaking the works
45(b) METERING - MIXED USE DEVELOPMENT

Such construction is to be to a standard that is satisfactory to be accepted on an off maintenance;

 
Prior to undertaking the works
45(c) METERING - MIXED USE DEVELOPMENT

If the meters are purchased other than from Council, pay to council a documentation fee for each water service provided. If the meters are purchased from Council, forward a copy of the receipt of purchase to the Engineering Delegate, Development and Regulatory Services.

 
Prior to undertaking the works
 
46)   RELOCATE WATER MAIN
Relocate the existing water main as required by streetscape works (footpath works), in accordance with Council's "Water and Sewerage Reticulation Standards".

Submit engineering plans prepared by a Registered Professional Engineer Queensland (RPEQ), and in accordance with Council's "Water and Sewerage Reticulation Standards" showing the design the re-located water main. Obtain the approval from the Engineering Delegate, Development Assessment, Development and Regulatory Services;

GUIDELINE
This condition is imposed when the approved development requires the widening of a road pavement under which is an existing water main. For enquiries regarding this condition, please contact the Engineering Delegate, Development and Regulatory Services.

 
Prior to undertaking the works
46(a) RELOCATE WATER MAIN

Pay to Council the cost of live connection to the water main;

 
Prior to undertaking the works
46(b) RELOCATE WATER MAIN

Construct the works in accordance with the approved engineering plans to a standard that will be satisfactory to be accepted "on" and "off" maintenance as a Council asset, by the Engineering Delegate, Development and Regulatory Services;

 
Prior to undertaking the works
46(c) RELOCATE WATER MAIN

Submit "As Constructed" plans including an assest register, approved by a Registered Professional Engineer Queensland (RPEQ) (to a standard specified in Council's "Water and Sewerage Reticulation Standards") certifying that the works have been completed in accordance the approved design and any approved modifications.

 
Prior to undertaking the works
 
Standard Advice
 
Timing
47)   FOOD HYGIENE

All development involving the preparation, packing, storing, handling, serving, selling or carrying of food requires that its design, installation and operation be approved pursuant to the Food Hygiene Regulations of 1989. The premises is required to be registered and the operator is to hold a licence with Brisbane City Council to operate the business under the above regulations.

 

Licences can be obtained from Brisbane City Council-Licensing & Compliance. To obtain a Licence Information Kit contact the call centre on 3403 8888.

 

Prior to building works plans and specifications are to be lodged for approval to Licensing and Compliance.

 

Please note: The above information has been provided to the applicant as an advice only, and does not form part of the development approval conditions. This advice has been provided to the applicant to inform them of other obligations they may have to comply with (under state legislation or local laws) prior to their activity commencing.

 
As indicated
 
48)   NOISE AND DUST EMISSIONS-ADVICE ONLY

All development involving the emission of noise and dust from building/construction activities requires that the emission be in accordance with the requirements of the Environmental Protection Regulation 1998 Part 2A - Environmental Nuisance.

 

Pursuant to the Environmental Protection Regulation 1998 Part 2A - Environmental Nuisance-

6W. A builder or building contractor must not carry out building work on a building site in a way that makes or causes audible noise to be made from the building work-

(a) on a Sunday or public holiday, at any time; or

(b) on a Saturday or business day, before 6.30 a.m. or after 6.30 p.m.

 

 

Please note: The above information has been provided to the applicant as an advice only, and does not form part of the development approval conditions. This advice has been provided to the applicant to inform them of other obligations they may have to comply with (under state legislation or local laws) prior to their activity commencing.

 
As indicated
 
49)   EQUITABLE ACCESS

Ensure that there is equitable access for disabled persons to and within the site in accordance with the Queensland Anti-Discrimination Act 1991, the Federal Disability Discriminiation Act 1992 and Australian Standard AS1428 Parts 1-4 Australian Standard for Access and Mobility.

You are notified of your responsibility to ensure that access is appropriately designed and constructed for all users as required by relevant legislation and standards. This development approval does not indicate that the proposal complies with these requirements. Determination of compliance with these requirements is the sole responsibility of the owner/builder/developer of the proposal.

Please note: The above information has been provided to the applicant as an advice only, and does not form part of the development approval conditions. This advice has been provided to the applicant to inform them of other obligations they may have to comply with (under state legislation or local laws) prior to their activity commencing.

 
As indicated
 
50)   CONCURRENCE AGENCY CONDITIONS

Brisbane City Council advise that Queensland Transport as concurrence agency has imposed the conditions contained in the letter dated 17 October 2006.

 
As indicated
 

** End of Package **