| Address of Site: | 10 WYANDRA ST NEWSTEAD QLD 4006 18 WYANDRA ST NEWSTEAD QLD 4006 20 WYANDRA ST NEWSTEAD QLD 4006 |
| Real Property Description of Site: | L1 RP.170117 L101 SP.292337 LCommon Property SP.274453 |
| Aspects of development and type of approval: | DA - PA - Material Change of Use Development Permit - Extension,multiple
dwelling DA - PA - Building Work Development Permit - multiple dwelling,Extension |
| Council File Reference: | A006989639 Permit Reference Number/s: DAMC449394424; DABW450026324. |
| Package Status: | RECOMMEND - Version 2 |
| Package Generated: | 17/06/2026 |
| Shirley MILLS Senior Urban Planner Planning Services North Shirley.Mills@brisbane.qld.gov.au 3403 6117 |
Rhea CONNOLLY Principal Urban Planner Planning Services North Rhea.Connolly@brisbane.qld.gov.au 3178 0651 |
Luke HADRICK Urban Planner Planning Services North Luke.Hadrick@brisbane.qld.gov.au (07) 3178 9403 |
| Callan BENNETT Principal Architect Architecture Team Callan.Bennett@brisbane.qld.gov.au 07 31780595 |
Carina FIESELER Landscape Architect Landscape Architecture Team carina.fieseler@brisbane.qld.gov.au 3403 5235 |
Craig SLACK Engineer Engineering Scoping craig.slack@brisbane.qld.gov.au (07) 3403 8888 |
| Rhea CONNOLLY Principal Urban Planner Planning Services North Rhea.Connolly@brisbane.qld.gov.au 3178 0651 |
Llewellyn BATSON Principal Urban Planner Planning Services Special Assessment Llewellyn.Batson@brisbane.qld.gov.au (07) 340 34980 |
Scott RUHLAND Technical Officer Engineering Services North scott.ruhland@brisbane.qld.gov.au (07) 3403 9459 |
| Carina FIESELER Landscape Architect Landscape Architecture Team carina.fieseler@brisbane.qld.gov.au 3403 5235 |
DRAWINGS AND DOCUMENTS
| Drawing or Document | Number | Plan Date |
|---|---|---|
| Services Level Plan | DA002 Issue C | 26-MAR-2026 (Received) |
| Roof Terrace Plan | DA003 Issue C | 26-MAR-2026 (Received) |
| Roof Plan | DA004 Issue C | 26-MAR-2026 (Received) |
| Roof Terrace Section B-B | DA007 Issue C | 26-MAR-2026 (Received) |
| Elevation | DA008 Issue A | 26-MAR-2026 (Received) |
| Rooftop Landscape Concept Plan | DA01 (Amended In Red 04-JUN-2026) | 26-MAR-2026 (Received) |
APPROVAL CONDITIONS
| Permit to Which These Conditions Relate: | DA - PA - Material Change of Use |
| Activity(ies): | Extension multiple dwelling |
| Stage: | Multiple Dwelling (Extension to Multiple Dwelling) |
| 1) Maintain the Approved Development Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions. |
At all times |
| 2) Original Condition Package All conditions relating
to the approval issued 24/02/2023 (A005729756), remain applicable, unless
varied by this approval. |
At all times |
| 3) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers. Note: This condition is imposed to ensure compliance with the conditions of development approval. |
While site/operational/building work is occurring |
| 4) Carry Out the Approved Development Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS. Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners. |
While site/operational/building work is occurring |
| 5) Complete All Building Work Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS. Note: Building work must also be completed in accordance with any other current development approval. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 6) Overall Height The overall height of the building(s) must be in accordance with the floor and roof levels and overall height shown on the APPROVED DRAWINGS AND DOCUMENTS. |
While site/operational/building work is occurring and then to be maintained |
6(a) Submit Certification Submit to Development Services certification from a Registered Surveyor (Qld) confirming that the 'as constructed' floor and roof levels and overall height are in accordance with the requirements of this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 7) Construction Noise and Dust Emissions Pursuant to the
Environmental Protection Act 1994, all development involving the emission of
noise and dust from building and/or construction activities, must ensure that
the emissions are in accordance with the requirements of the Act. |
As indicated |
| 8) Further Development Permit Required Further Development Permit(s) to carry out assessable building work under the Building Act may be required. |
As indicated |
| 9) Currency Period The currency period for this development approval is stated in the Decision Notice and is expressed as a date. This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016. |
As indicated |
| 10) Equitable Access Provision must be made during and after construction
for equitable access for persons with disabilities to and within the site and
on adjoining public areas, in accordance with the following: |
As indicated |
| Permit to Which These Conditions Relate: | DA - PA - Building Work |
| Activity(ies): | multiple dwelling Extension |
| Stage: | Multiple Dwelling (Extension to Multiple Dwelling) |
| 11) Maintain the Approved Development Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions. |
At all times |
| 12) Original Condition Package All conditions relating
to the approval issued 24/02/2023 (A005729756), remain applicable, unless
varied by this approval. |
At all times |
| 13) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers. Note: This condition is imposed to ensure compliance with the conditions of development approval. |
While site/operational/building work is occurring |
| 14) Carry Out the Approved Development Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS. Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners. |
While site/operational/building work is occurring |
| 15) Complete All Building Work Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS. Note: Building work must also be completed in accordance with any other current development approval. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 16) Construction Noise and Dust Emissions Pursuant to the
Environmental Protection Act 1994, all development involving the emission of
noise and dust from building and/or construction activities, must ensure that
the emissions are in accordance with the requirements of the Act. |
As indicated |
| 17) Further Development Permit Required Further Development Permit(s) to carry out assessable building work under the Building Act may be required. |
As indicated |
| 18) Currency Period The currency period for this development approval is stated in the Decision Notice and is expressed as a date. This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016. |
As indicated |
| 19) Equitable Access Provision must be made during and after construction
for equitable access for persons with disabilities to and within the site and
on adjoining public areas, in accordance with the following: |
As indicated |