| Address of Site: | 95 MAINS RD SUNNYBANK QLD 4109 |
| Real Property Description of Site: | L10 SP.138451 |
| Aspects of development and type of approval: | DA - PA - Material Change of Use Development Permit - health care
service,shop,food and drink outlet,office |
| Council File Reference: | A006923374 Permit Reference Number/s: DAMC419854822. |
| Package Status: | APPROVED - Version 2 (28th of May, 2026 5:07:35 PM) |
| Package Generated: | 28/05/2026 |
| Dane HOFFMANN Senior Urban Planner Planning Services South Dane.Hoffmann@brisbane.qld.gov.au 07 3178 5678 |
Alessio ZANCOLICH Principal Urban Planner Planning Services South alessio.zancolich@brisbane.qld.gov.au (07) 3407 8514 |
Margaret ORR Team Manager Planning Services South margaret.orr@brisbane.qld.gov.au (07) 34070751 |
| Paul STONE WaRRS Assessment paul.stone@brisbane.qld.gov.au 317 85854 |
Richard DITCHFIELD Technical Officer Engineering Services South richard.ditchfield@brisbane.qld.gov.au 34036751 |
Martin MOLLEE Senior Environmental Management Officer Environmental Management Services Martin.Mollee@brisbane.qld.gov.au (07) 3403 8888 |
| Zarndra PIPER Principal Urban Planner Planning Services South Zarndra.Piper@brisbane.qld.gov.au 0731780370 |
Timothy BYRNE Principal Urban Planner Planning Services South Timothy.Byrne@brisbane.qld.gov.au (07) 3403 0314 |
DRAWINGS AND DOCUMENTS
| Drawing or Document | Number | Plan Date |
|---|---|---|
| Proposed Floor Plan | A104 Rev G (Amended In Red 26-MAY-2026) | 21-MAY-2026 (Received) |
| Proposed Roof Plan | A105 Rev C | 21-MAY-2026 (Received) |
| Elevations | A400 Rev C (Amended In Red 26-MAY-2026) | 21-MAY-2026 (Received) |
| Elevations | A401 Rev C | 21-MAY-2026 (Received) |
| Cover Sheet & Schedules | CP01 B | 28-APR-2026 (Received) |
| Landscape Concept Plan | CP01 B | 28-APR-2026 (Received) |
| Noise Impact Assessment | V.2 | 11-AUG-2022 (Received) |
APPROVAL CONDITIONS
| Permit to Which These Conditions Relate: | DA - PA - Material Change of Use |
| Activity(ies): | health care service office food and drink outlet shop |
| Stage: | Food and Drink Outlet, Office, Health Care Service and Shop |
| 1) Maintain the Approved Development Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions. |
At all times |
| 2) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers. Note: This condition is imposed to ensure compliance with the conditions of development approval. |
While site/operational/building work is occurring |
| 3) Carry Out the Approved Development Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS. Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners. |
While site/operational/building work is occurring |
| 4) Complete All Building Work Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS. Note: Building work must also be completed in accordance with any other current development approval. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 5) Security Lighting - On Site Install and maintain a suitable system of security lighting to operate from dusk to dawn within all areas where the public may gain access, including car parking areas, building entrances and vegetated areas. Ensure that all external lighting is in accordance with Australian Standard - AS4282- Control of the Obtrusive Effects of Outdoor Lighting. Ensure lighting over publicly accessible internal pathways covered by permanent awnings is in accordance with Australian Standard - AS/NZS 1158.3.1 Lighting for roads and public spaces - Pedestrian area lighting - Performance and design requirements. Lighting must be maintained in safe and good working order.
Timing: ‘Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first’ |
As indicated |
| 6) Car Parking The car parking within the premises must be maintained exclusively for the ancillary use of the development. The parking must not be made available to the general public and there must not be signage erected on or in the vicinity of the site advertising the availability of car parking to the general public. |
At all times |
| 7) Limitation of use - Food and drink outlet The development approval for Food and drink outlet is limited to tenancy 4 and 5 shown on the Proposed Floor Plan, Drawing No. A104 Rev G, received on 21-MAY- 2026 and amended in red on 26-MAY-2026. |
To be maintained |
| 8) External Details External details of the building, facade treatment and external materials and finishes must be consistent with the approved DRAWINGS AND DOCUMENTS. Note: The requirement to use particular materials and finishes is imposed only for the purpose of achieving a built form outcome that displays architectural merit. Council has not assessed the materials and finishes for compliance with the Building Act, the Building Fire Safety Regulation, the Building Regulation, the Building Code of Australia, the Queensland Development Code, relevant Australian Standards, fire safety standards or any other relevant requirement of a statutory authority with regard to building work. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 9) Overall Height The overall height of the building(s) must be in accordance with the floor and roof levels and overall height shown on the APPROVED DRAWINGS AND DOCUMENTS. NOTE: This condition should be read in conjunction with any other relevant condition requiring minimum height clearances for basement or undercover car parking and manoeuvring areas. |
While site/operational/building work is occurring and then to be maintained |
9(a) Submit Certification Submit to Development Services certification from a registered surveyor confirming that the 'as constructed' floor and roof levels and overall height are in accordance with the requirements of this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 10) Provide Pedestrian Prioritised Pathway Provide a pedestrian prioritised pathway from the street frontage to the entrance of each tenancy. The pathway must be differentiated in colour and texture from the driveway surface. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 11) Screen Air Conditioning and Other Plant
Enclosures Install and maintain suitable screening to all air conditioning, lift motor rooms, plant and service facilities located at the top of or on the external face of the building and within the Private Open Spaces. The screening structures must be constructed from materials that are consistent with materials used elsewhere on the facade of the building. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 12) Provide Street Tree(s) Provide street tree(s) fronting the development site. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
12(a) Street Tree(s) Enter into and implement an arrangement with Public Space Operations Arboriculture Planning (PSO Arb Planning) Arboriculture in relation to the required provision of the street tree planting in accordance with the Infrastructure Design Planning Scheme Policy, including the number, species, location, installation and maintenance of the required street tree(s) as determined by PSO Arb Planning. Provide to Development Assessment a copy of the agreement signed by PSO Arb Planning. Note: Street trees should not be planted until all utilities have been installed. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first PROOF OF FULFILMENT Submit to Development Services, a copy of the agreement with PSO Arb Planning. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 13) Landscape the Site - Self Certification Landscape the site in accordance with the requirements of this condition. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
13(a) Detailed Landscape Plan for Self-
Certification Prepare a Detailed Landscape Plan at a scale of 1:100 for all on-site landscape works including planting areas identified on the approved DRAWINGS AND DOCUMENTS. The plan must be prepared by a Qualified Landscape Architect and must comply with the relevant Brisbane Planning Scheme Codes. The plan must include the following: Timing: Prior to building work commencing. PROOF OF FULFILMENT A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to building work commencing. |
As indicated |
13(b) Centre or Mixed Use In addition to the
requirements listed above, the plan must include the following: Timing: Prior to building work commencing. PROOF
OF FULFILMENT A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to building work commencing. |
As indicated |
13(c) Certify Detailed Landscape
Plan On completion of the Detailed Landscape Plan, submit to Development Services a landscape design certification via the Landscape Design and Landscape Works Certification online form. Design certification is to be prepared by a Qualified Landscape Architect, certifying that the Detailed Landscape Plan complies with the requirements of this condition. The Certification must include a copy of the:
NOTE: The landscape design and landscape works certification online form can be found by searching development application forms on Council's website. Timing: Prior to building work commencing. PROOF OF FULFILMENT A copy of the landscape design certification form and certified detailed landscape plan |
As indicated |
13(d) Implement Certified Detailed Landscape
Plan Carry out the landscape work in accordance with the above certified detailed Landscape Plan. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
13(e) Certify Work On completion of the landscape work, submit a Landscape Works Certification via the Landscape Design and Landscape Works Certification online form. The landscape works certification is to be prepared by a Qualified Landscape Architect, certifying that the landscape works comply with the certified Detailed Landscape Plan. The certification must include:
- a copy of the as-constructed landscape drawings. - Photos of installed landscaping.
NOTE: The landscape design and landscape works certification online form can be found by searching development application forms on Council's website. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT A copy of the Landscape works certification form, a copy of the as-constructed landscape drawings, photos of installed landscaping, confirmation in writing from the landscape contractor who completed the works, that the works were completed in accordance with best practice landscape construction and horticultural standards. |
As indicated |
13(f) Maintain Landscape Work Maintain the landscape work, including deep planting, in accordance with the certified Detailed Landscape Plan. Timing: To be maintained. |
As indicated |
| 14) Kitchen exhaust vents - (emitters) Kitchen and food preparation area exhaust vent outlets are discharged vertically, directed away from any sensitive use and separated by a minimum of 6m from a sensitive use, including any outdoor air intake of a sensitive use. Note: This condition does not authorise environmental nuisance under the Environmental Protection Act 1994. |
At all times |
| 15) Hours of Operation Hours of operation for the approved uses, indicated as DA approved area,
proposed additional area and DA approved covered outdoor area in the Proposed
Floor Plan, Drawing No. A104 Rev G, received on 21-MAY-2026 and amended in red
on 26-MAY-2026, must be in accordance with the following:
Trading Hours 7am to 10pm Deliveries 7am to 10pm Outdoor Dining 7am to 10pm |
At all times |
| 16) Mechanical Plant or Equipment - Acoustically
Screened Mechanical plant or equipment is to be acoustically screened from an adjoining sensitive use. Mechanical plant includes generators, motors, compressors and pumps such as air-conditioning, refrigeration and cold room motors. Acoustically screened is defined in City Plan 2014. NOTE: This condition does not authorise environmental nuisance under the Environmental Protection Act 1994. PROOF OF FULFILMENT Submit to Development Services, certification that all mechanical plant or equipment, is acoustically screened. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 17) Noise Emission Management Noise emissions are to be managed in accordance with the following: · openings along the eastern facade and northern facade are to remain closed; · the maximum number of patrons in the northern outdoor dining area is limited to 15; and · amplified sound or music is not permitted. |
To be maintained |
| 18) Acoustic Fence - General Erect and/or maintain the 2.5m 3m & 1.9m high acoustic fences, (relative
to the finished RL of the building pad) along the property boundaries as per
the Proposed Floor Plan, Drawing No. A104 Rev G, received on 21-MAY-2026 and
amended in red on 26-MAY-2026. The acoustic fences must: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
18(a) Certification Submit to Development Services certification from a person who is a Member or eligible to be a Member of the Australian Acoustic Society that the constructed acoustic fence complies with the above requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 19) Acoustic Treatments Implement the following acoustic treatments: · the external facades (including wall and ceiling/roof building elements, and glazings if any) are to achieve a minimum Rw acoustic rating of 35; and · a 2 sided acoustic & absorptive screen and roof for the northern outdoor dining area as per Figure 4 of the Noise Impact Assessment, V.2, received on 11-AUG-2022. |
Prior to the commencement of the use and then to be maintained |
19(a) Certification Submit Certification to Council by a suitably qualified acoustic consultant demonstrating the acoustic treatments as detailed above have been implemented. |
Prior to commencement of use |
| 20) On-site Erosion (Low Risk) Manage on-site erosion
and the release of sediment or sediment laden water from the site at all times
by implementing best industry practice for sediment and erosion control as per
the International Erosion Control Association, Best Practice Erosion and
Sediment Control documents (2008 or later version). Including but not limited
to: Note: Guidelines and factsheets to assist with this are available from the 'Healthy Waterways - Water by Design' website at http://hlw.org.au/initiatives/esc/house-sites Timing: Prior to commencement of any earth disturbing activities and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
20(a) Provide Land Occupier Notification to
Council (i) Notify Council's ESC Team of proposed land occupier/s by sending an email to CARS-ESC@Brisbane.qld.gov.au (ii) If the land is to be occupied by any person other than the registered landowner then advice must be provided to Council that confirms the name, contact information and the duration of any proposed occupation of the land. Note: Occupier is any principal contractor occupying the land exercising a right under the development approval. Timing: Prior to commencement of any earth disturbing activities. |
As indicated |
| 21) Information Signage Erect an information sign on the subject property in
accordance with Council's general requirements for signage and in accordance
with the requirements outlined below: Timing: Prior to site works commencing and then to be maintained until completion of the development for all stages. |
As indicated |
| 22) Construction Management Plan (Minor) Carry out development in a method consistent with a Construction Management Plan (Minor) prepared in accordance with the requirements of this condition. |
While site/operational/building work is occurring |
22(a) Construction Management Plan (Minor) -
Prepare Plan Prepare a detailed Construction Management Plan (CMP) for the
construction phase of the approved development. The Construction
Management Plan must be in accordance with the relevant Brisbane Planning
Scheme Codes and address the following: The Construction Management Plan must be supported by 'approval in principle' or written approvals from the relevant Council sections or other governing bodies responsible for any potentially impacted infrastructure. The list of relevant infrastructure and contacts is available on Council's website - Search 'Constructions Management Plan'. Note: The Construction Management Plan is not required to be approved by Development Services. Timing: Prior to site/operational/building work commencing. |
As indicated |
22(b) Construction Management Plan (Minor) -
Submit Plan Submit a copy of the Construction Management Plan to Council's Development Services Branch at the following mailbox: engineeringservices@brisbane.qld.gov.au quoting the BCC planning development approval reference number. Timing: At least 10 days prior to site works commencing. |
As indicated |
22(c) Construction Management Plan (Minor) -
Documentation on Site Legible copies of the Construction Management Plan and current permits must be kept on site and be made available on request by Council, At all times. The requirements of the CMP must be included in all induction of principal and subcontractors utilised in the development. An outline of the induction provided to contractors may be requested by Council to confirm compliance with this condition. Timing: While site/operational/building work is occurring. |
As indicated |
22(d) Construction Management Plan - Works to
be Performed Out of Hours Obtain an approval from Development Services for any
work that is proposed to be undertaken outside of normal business hours -
6:30am to 6:30pm, Monday to Saturday. |
As indicated |
22(e) Implement Construction Management Plan
(Minor) Carry out the development in accordance with the submitted Construction Management Plan. |
While site/operational/building work is occurring |
| 23) Protect Existing Infrastructure Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure. Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations. The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements. |
While site/operational/building work is occurring |
23(a) As Constructed Drawings - Alterations
to Existing Infrastructure Submit to Development Services As Constructed drawings showing all new and/or rectification works and an asset register, prepared by a Registered Professional Engineer Queensland. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 24) Access, Grades, Manoeuvring, Carparks, Signs and
Line Marking Construct and maintain access, parking and manoeuvring for vehicles on site in accordance with the relevant Brisbane Planning Scheme Codes, as indicated on the approved DRAWINGS AND DOCUMENTS and with the Proposed Floor Plan, Drawing No. A104 Rev G, received on 21-MAY-2026 and amended in red on 26-MAY-2026, including the following: i. A pavement of minimum Local road standard or equivalent surface material (including associated drainage) to the area on which motor vehicles will be driven and/or parked. ii. Manoeuvring on site for a refuse collection vehicle and a medium rigid vehicle and for the loading and unloading of vehicle(s). iii. Parking on the site for 35 cars, including one car parking space for people with disabilities and for the loading and unloading of vehicle(s) within the site. There must a minimum number of 35 car parking spaces provided on site. iv. An appropriate area for the storage and collection of refuse, including recyclables, in a position which is accessible to service vehicles on the site. v. Construct the modifications to the car parking area, in accordance with the Proposed Floor Plan, Drawing No. A104 Rev G, received on 21-MAY-2026 and amended in red on 26-MAY-2026. vi. Prepare and implement signs and line markings drawings that show the internal paved areas signed and delineated in accordance with the approved drawings and documents and with the Proposed Floor Plan, Drawing No. A104 Rev G, received on 21-MAY- 2026 and amended in red on 26-MAY-2026. The drawings must be prepared and certified by a Registered Professional Engineer Queensland in accordance with the relevant Brisbane Planning Scheme Codes and the Manual of Uniform Traffic Control Devices. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland, that the above requirements have been implemented in accordance with this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 25) Repair Damage to Kerb, Footpath or Road Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
25(a) Interim Repairs If at any time during the construction phase of the approved development, damage to the existing kerb and channel, footpath or roadway creates unsafe, unreasonable and/or not fit for purpose conditions as assessed by Council, interim repairs must be undertaken as directed by Program Planning and Integration. Note: Any interim repairs required to be undertaken shall not be considered to satisfy the requirements of this condition for the permanent repair of the infrastructure prior to the issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. Timing: While site / operational / building works is occurring. |
As indicated |
| 26) Refuse Collection - On Site Provide for the installation and collection of refuse/recycling bins by Brisbane City Council's Waste and Resource Recovery Services or a private waste contractor. |
At all times |
26(a) Arrange Refuse Collection Arrange for the installation of refuse/recycling bins and for the subsequent collection of refuse including recycling from the site by Brisbane City Council's Waste and Resource Recovery Services or a private waste contractor. Timing: A minimum of four weeks prior to the commencement of use and then to be maintained. PROOF OF FULFILMENT Where a private waste contractor is engaged, provide written confirmation from the proposed waste collection contractor of the agreement to service the property. The written agreement must be submitted to Council's Waste and Resource Recovery Services and include full details of the proposed system, bin sizes, number of bins, frequency of collection and the refuse collection vehicle size. Timing: Prior to commencement of use. |
As indicated |
26(b) Notify Future Owner Where Council is engaged as the waste contractor, the owner must notify any future owner/body corporate that the development has been approved on the basis that an indemnity must be provide for refuse collection vehicles to enter the property. Timing: At time of a change of ownership. |
As indicated |
26(c) Indemnify Council The owner and any subsequent owner must, by approved form to Waste and Resource Recovery Services, indemnify Council and its agents in respect of any damage to the pavement and other driving surfaces. Timing: When an arrangement for refuse/recycling collection services is made with Brisbane City Council. |
As indicated |
| 27) Refuse Storage - On Site Collection Provide a roofed and wholly screened refuse enclosure utilising materials consistent with the development or a dedicated refuse storage room, as shown on the approved plans and documents. The refuse bin storage enclosure is to have the minimum dimensions as shown on the Proposed Floor Plan, Drawing No. A104 Rev G, received on 21-MAY-2026 and amended in red on 26-MAY-2026. In particular, the internal clear height is to be a minimum of 2.1 metres, to allow service personnel safe access to handle and manoeuvre the bins. Provide visual and acoustic screening to the refuse enclosure, in accordance with the Refuse Planning Scheme Policy, so as to have no adverse acoustic, odour or visual impacts on the adjoining land. The enclosure/refuse storage room must be of a design to accommodate the quantity of refuse and recycling including source separation to allow for low servicing collection of the development. A minimum total refuse bin storage capacity of 12,187 litres of refuse and recycling is to be provided. Bins must be located in an area which allows them to be manoeuvred from the bin storage area to the designated internal collection point. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 28) Ponding of Stormwater Carry out the approved development to ensure that adjoining properties and roads are protected from ponding or nuisance from stormwater during construction. Notes: If remedial works are necessary to comply with this condition, prior approval must be obtained from Development Services. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 29) On Site Drainage - Minor Provide a stormwater connection to all new or existing allotments and provide drainage infrastructure to ensure stormwater run-off from all roof and developed surface areas will be collected internally and piped in accordance with the relevant Brisbane Planning Scheme Codes to a lawful point of discharge via the existing stormwater drainage system within the site. Note: - Guidance for requesting a pre-start and co- ordinating the On/Off Maintenance process can be found on Council's website (https://www.brisbane.qld.gov.au/planning-and-building/applying-and-post- approval/on-and-off-maintenance-approvals). |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 30) Service Conduits and Mains Provide and install all
service conduits and meet the cost of any alterations to public utility mains,
existing mains, services, street lighting or installations that are required to
carry out the approved development. These works must be in accordance with the
relevant Brisbane Planning Scheme Codes, and include the following, where
applicable: Note: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
30(a) Submit As Constructed
Drawings Submit to Development Services As Constructed drawings, including an asset register, prepared and certified by a Registered Professional Engineer Queensland. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the requirements of this condition. Note: Civil works are to be certified by a RPEQ(Civil) and electrical works are to be certified by a RPEQ (Electrical). |
As indicated |
| 31) Construction Noise and Dust Emissions Pursuant to the Environmental
Protection Act 1994, all development involving the emission of noise and dust
from building and/or construction activities, must ensure that the emissions
are in accordance with the requirements of the Act. |
As indicated |
| 32) Management of Asbestos Disposal, handling and restoration of any building materials containing asbestos must be in accordance with current state and federal legislation. |
As indicated |
| 33) Further Development Permit Required Further Development Permit(s) to carry out assessable building work under the Building Act may be required. Building Approval is to ensure fire escape stair and internal passageways take into account the number, mobility and other characteristics of occupants as detailed in the National Construction Code. |
As indicated |
| 34) Plumbing and Drainage Work Pursuant to the Plumbing and Drainage Act 2018, any plumbing and drainage work must be carried out in compliance with the Plumbing and Drainage Regulation 2019. Plumbing and drainage permit work requires approval by Brisbane City Council prior to the work being carried out. |
As indicated |
| 35) Currency Period The currency period for this development approval is stated in the Decision Notice and is expressed as a date.
This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016. |
As indicated |
| 36) Referral Agency Requirements Energex as Advice agency has imposed the requirements contained in the letter dated 15 December 2025 (reference: ECM 35324857-35321736). |
As indicated |
| 37) Equitable Access Provision must be made during and after construction
for equitable access for persons with disabilities to and within the site and
on adjoining public areas, in accordance with the following: |
As indicated |
| 38) Fire Ant Movement Controls To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected. These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products. Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014. For further information contact the relevant Queensland State Government department on 13 QGOV. |
As indicated |
| 39) Water and Wastewater Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. For further information about any necessary Water Approvals contact Urban Utilities. |
As indicated |