BRISBANE CITY COUNCIL'S APPROVAL PACKAGE.



APPLICATION DETAILS

This package relates to the application detailed below
Address of Site: 95 MAINS RD SUNNYBANK QLD 4109
Real Property Description of Site: L10 SP.138451
Aspects of development and type of approval: DA - PA - Material Change of Use Development Permit - health care service,shop,food and drink outlet,office
Council File Reference: A006923374
Permit Reference Number/s: DAMC419854822.
Package Status: APPROVED - Version 2 (28th of May, 2026 5:07:35 PM)
Package Generated: 28/05/2026


PROJECT TEAM

The assessment of this application has been undertaken by:
Dane HOFFMANN
Senior Urban Planner
Planning Services South
Dane.Hoffmann@brisbane.qld.gov.au
07 3178 5678
Alessio ZANCOLICH
Principal Urban Planner
Planning Services South
alessio.zancolich@brisbane.qld.gov.au
(07) 3407 8514
Margaret ORR
Team Manager
Planning Services South
margaret.orr@brisbane.qld.gov.au
(07) 34070751
Paul STONE

WaRRS Assessment
paul.stone@brisbane.qld.gov.au
317 85854
Richard DITCHFIELD
Technical Officer
Engineering Services South
richard.ditchfield@brisbane.qld.gov.au
34036751
Martin MOLLEE
Senior Environmental Management Officer
Environmental Management Services
Martin.Mollee@brisbane.qld.gov.au
(07) 3403 8888
Zarndra PIPER
Principal Urban Planner
Planning Services South
Zarndra.Piper@brisbane.qld.gov.au
0731780370
Timothy BYRNE
Principal Urban Planner
Planning Services South
Timothy.Byrne@brisbane.qld.gov.au
(07) 3403 0314


DRAWINGS AND DOCUMENTS



The term 'drawings and documents' or similar expressions mean:
Drawing or Document Number Plan Date
Proposed Floor Plan A104 Rev G (Amended In Red 26-MAY-2026) 21-MAY-2026 (Received)
Proposed Roof Plan A105 Rev C 21-MAY-2026 (Received)
Elevations A400 Rev C (Amended In Red 26-MAY-2026) 21-MAY-2026 (Received)
Elevations A401 Rev C 21-MAY-2026 (Received)
Cover Sheet & Schedules CP01 B 28-APR-2026 (Received)
Landscape Concept Plan CP01 B 28-APR-2026 (Received)
Noise Impact Assessment V.2 11-AUG-2022 (Received)


Advice

Please see the attached document(s) for any advices.

APPROVAL CONDITIONS



Permit to Which These Conditions Relate: DA - PA - Material Change of Use
Activity(ies): health care service
office
food and drink outlet
shop
Stage: Food and Drink Outlet, Office, Health Care Service and Shop

General/Planning Requirements
 
Timing
1)   Maintain the Approved Development

Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions.

 
At all times
 
2)   Approved Drawings and Documents

A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers.

Note: This condition is imposed to ensure compliance with the conditions of development approval.

 
While site/operational/building work is occurring
 
3)   Carry Out the Approved Development

Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS.

Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks).  Permission to enter neighbouring properties must be obtained from the relevant property owners.

 
While site/operational/building work is occurring
 
4)   Complete All Building Work

Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS.

Note: Building work must also be completed in accordance with any other current development approval.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
5)   Security Lighting - On Site

Install and maintain a suitable system of security lighting to operate from dusk to dawn within all areas where the public may gain access, including car parking areas, building entrances and vegetated areas.

Ensure that all external lighting is in accordance with Australian Standard - AS4282- Control of the Obtrusive Effects of Outdoor Lighting. 

Ensure lighting over publicly accessible internal pathways covered by permanent awnings is in accordance with Australian Standard - AS/NZS 1158.3.1 Lighting for roads and public spaces - Pedestrian area lighting - Performance and design requirements.  

Lighting must be maintained in safe and good working order.

 

Timing: ‘Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first’

 
As indicated
 
6)   Car Parking

The car parking within the premises must be maintained exclusively for the ancillary use of the development. The parking must not be made available to the general public and there must not be signage erected on or in the vicinity of the site advertising the availability of car parking to the general public.

 
At all times
 
7)   Limitation of use - Food and drink outlet

The development approval for Food and drink outlet is limited to tenancy 4 and 5 shown on the Proposed Floor Plan, Drawing No. A104 Rev G, received on 21-MAY- 2026 and amended in red on 26-MAY-2026.

 
To be maintained
 
Architecture
 
Timing
8)   External Details

External details of the building, facade treatment and external materials and finishes must be consistent with the approved DRAWINGS AND DOCUMENTS.

Note: The requirement to use particular materials and finishes is imposed only for the purpose of achieving a built form outcome that displays architectural merit. Council has not assessed the materials and finishes for compliance with the Building Act, the Building Fire Safety Regulation, the Building Regulation, the Building Code of Australia, the Queensland Development Code, relevant Australian Standards, fire safety standards or any other relevant requirement of a statutory authority with regard to building work.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
9)   Overall Height

The overall height of the building(s) must be in accordance with the floor and roof levels and overall height shown on the APPROVED DRAWINGS AND DOCUMENTS.

NOTE: This condition should be read in conjunction with any other relevant condition requiring minimum height clearances for basement or undercover car parking and manoeuvring areas.

 
While site/operational/building work is occurring and then to be maintained
9(a) Submit Certification

Submit to Development Services certification from a registered surveyor confirming that the 'as constructed' floor and roof levels and overall height are in accordance with the requirements of this condition.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
10)   Provide Pedestrian Prioritised Pathway

Provide a pedestrian prioritised pathway from the street frontage to the entrance of each tenancy. The pathway must be differentiated in colour and texture from the driveway surface.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
11)   Screen Air Conditioning and Other Plant Enclosures

Install and maintain suitable screening to all air conditioning, lift motor rooms, plant and service facilities located at the top of or on the external face of the building and within the Private Open Spaces. The screening structures must be constructed from materials that are consistent with materials used elsewhere on the facade of the building.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
Landscape Architecture and Open Space Planning
 
Timing
12)   Provide Street Tree(s)

Provide street tree(s) fronting the development site.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
12(a) Street Tree(s)

Enter into and implement an arrangement with Public Space Operations Arboriculture Planning (PSO Arb Planning) Arboriculture in relation to the required provision of the street tree planting in accordance with the Infrastructure Design Planning Scheme Policy, including the number, species, location, installation and maintenance of the required street tree(s) as determined by PSO Arb Planning. Provide to Development Assessment a copy of the agreement signed by PSO Arb Planning.

Note: Street trees should not be planted until all utilities have been installed.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first

PROOF OF FULFILMENT
Submit to Development Services, a copy of the agreement with PSO Arb Planning. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
13)   Landscape the Site - Self Certification

Landscape the site in accordance with the requirements of this condition.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
13(a) Detailed Landscape Plan for Self- Certification

Prepare a Detailed Landscape Plan at a scale of 1:100 for all on-site landscape works including planting areas identified on the approved DRAWINGS AND DOCUMENTS. The plan must be prepared by a Qualified Landscape Architect and must comply with the relevant Brisbane Planning Scheme Codes.

The plan must include the following:
- Planting media and mulch in accordance with AS4454 Composts, soil conditioners and mulches and AS 4419-2003 Soils for landscaping and garden use.
- Unless otherwise specified, trees provided as 45 litre stock or larger, staked and tied, and complying with Australian Standards.
- Plant selection and densities to achieve full surface coverage of garden beds within 2 years of planting.
- A reticulated drip irrigation system to all planting areas, with drainage connected to the stormwater system; the irrigation system must be connected to a non-mains water source.
- Trees required to be retained are documented, integrated into landscape design, and protected in accordance with the relevant sections of Australian Standard AS4970 Protection of trees on development sites.
- Details of a 12 week establishment period.

Timing: Prior to building work commencing.

PROOF OF FULFILMENT
A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to building work commencing.

 
As indicated
13(b) Centre or Mixed Use

In addition to the requirements listed above, the plan must include the following:
- Deep planting areas as shown on the approved drawings planted with trees capable of growing to a minimum canopy diameter of 5m and a minimum height of 5m within 5 years of planting noting that this is a minimum requirement and trees are expected to grow beyond these measurements.
- A minimum of 25% of all trees as 200L stock or larger.
- Shade trees planted in garden beds abutting car parks.
- A mix of columnar and round canopy trees planted at suitable spacings along front boundaries in planting areas shown on the approved drawings.
- Columnar canopy form or screening tree/shrub species planted at suitable spacings along side and rear boundaries in planting areas shown on the approved drawings.
- Minimum internal depths and widths sufficient to support healthy plant growth, with the following dimensions or other dimensions if achieving the same soil volume; trees – 1200mm width x depth, large shrubs and palms - 800mm width x depth, small shrubs and groundcovers - 600mm width x depth.

Timing: Prior to building work commencing.

PROOF OF FULFILMENT
A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to building work commencing.

 
As indicated
13(c) Certify Detailed Landscape Plan

On completion of the Detailed Landscape Plan, submit to Development Services a landscape design certification via the Landscape Design and Landscape Works Certification online form. Design certification is to be prepared by a Qualified Landscape Architect, certifying that the Detailed Landscape Plan complies with the requirements of this condition. The Certification must include a copy of the:


- Landscape design certification form.


- Certified detailed landscape plan.

NOTE: The landscape design and landscape works certification online form can be found by searching development application forms on Council's website.

Timing: Prior to building work commencing.

PROOF OF FULFILMENT
A copy of the landscape design certification form and certified detailed landscape plan

 
As indicated
13(d) Implement Certified Detailed Landscape Plan

Carry out the landscape work in accordance with the above certified detailed Landscape Plan.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
13(e) Certify Work

On completion of the landscape work, submit a Landscape Works Certification via the Landscape Design and Landscape Works Certification online form. The landscape works certification is to be prepared by a Qualified Landscape Architect, certifying that the landscape works comply with the certified Detailed Landscape Plan. The certification must include:


- a copy of the Landscape works certification form.

- a copy of the as-constructed landscape drawings.

- Photos of installed landscaping.


- Confirmation in writing from the landscape contractor who completed the works, that the works were completed in accordance with best practice landscape construction and horticultural standards.

NOTE: The landscape design and landscape works certification online form can be found by searching development application forms on Council's website.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

PROOF OF FULFILMENT
A copy of the Landscape works certification form, a copy of the as-constructed landscape drawings, photos of installed landscaping, confirmation in writing from the landscape contractor who completed the works, that the works were completed in accordance with best practice landscape construction and horticultural standards.

 
As indicated
13(f) Maintain Landscape Work

Maintain the landscape work, including deep planting, in accordance with the certified Detailed Landscape Plan.

Timing: To be maintained.

 
As indicated
 
Pollution
 
Timing
14)   Kitchen exhaust vents - (emitters)

Kitchen and food preparation area exhaust vent outlets are discharged vertically, directed away from any sensitive use and separated by a minimum of 6m from a sensitive use, including any outdoor air intake of a sensitive use.

Note: This condition does not authorise environmental nuisance under the Environmental Protection Act 1994.

 
At all times
 
15)   Hours of Operation

Hours of operation for the approved uses, indicated as DA approved area, proposed additional area and DA approved covered outdoor area in the Proposed Floor Plan, Drawing No. A104 Rev G, received on 21-MAY-2026 and amended in red on 26-MAY-2026, must be in accordance with the following:

Trading Hours 7am to 10pm

Deliveries 7am to 10pm

Outdoor Dining 7am to 10pm

 
At all times
 
16)   Mechanical Plant or Equipment - Acoustically Screened

Mechanical plant or equipment is to be acoustically screened from an adjoining sensitive use. Mechanical plant includes generators, motors, compressors and pumps such as air-conditioning, refrigeration and cold room motors. Acoustically screened is defined in City Plan 2014.

NOTE: This condition does not authorise environmental nuisance under the Environmental Protection Act 1994.

PROOF OF FULFILMENT
Submit to Development Services, certification that all mechanical plant or equipment, is acoustically screened. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
17)   Noise Emission Management

Noise emissions are to be managed in accordance with the following:

· openings along the eastern facade and northern facade are to remain closed;

· the maximum number of patrons in the northern outdoor dining area is limited to 15; and

· amplified sound or music is not permitted.

 
To be maintained
 
18)   Acoustic Fence - General

Erect and/or maintain the 2.5m 3m & 1.9m high acoustic fences, (relative to the finished RL of the building pad) along the property boundaries as per the Proposed Floor Plan, Drawing No. A104 Rev G, received on 21-MAY-2026 and amended in red on 26-MAY-2026. The acoustic fences must:
- Be constructed of a material with a minimum surface area density of 12.5kg/m2;
- Be constructed of an aesthetically pleasing weather-resistant material such as earth mound, fibre cement, painted or treated timber, brick, concrete or a combination thereof; and
- Be continuous and gap free.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
18(a) Certification

Submit to Development Services certification from a person who is a Member or eligible to be a Member of the Australian Acoustic Society that the constructed acoustic fence complies with the above requirements.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
19)   Acoustic Treatments

Implement the following acoustic treatments:

· the external facades (including wall and ceiling/roof building elements, and glazings if any) are to achieve a minimum Rw acoustic rating of 35; and

· a 2 sided acoustic & absorptive screen and roof for the northern outdoor dining area as per Figure 4 of the Noise Impact Assessment, V.2, received on 11-AUG-2022.

 
Prior to the commencement of the use and then to be maintained
19(a) Certification

Submit Certification to Council by a suitably qualified acoustic consultant demonstrating the acoustic treatments as detailed above have been implemented.

 
Prior to commencement of use
 
Engineering
 
Timing
20)   On-site Erosion (Low Risk)

Manage on-site erosion and the release of sediment or sediment laden water from the site at all times by implementing best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version). Including but not limited to:
(i) Drainage control measures must be implemented and maintained to minimise water flow across areas of exposed earth.
(ii) Sediment and erosion control measures must be implemented and maintained to prevent soil loss from earth disturbance areas and prevent deposition beyond earth disturbance areas.
(iii) No release of contaminants to land beyond on-site area of earth disturbance.

Note: Guidelines and factsheets to assist with this are available from the 'Healthy Waterways - Water by Design' website at http://hlw.org.au/initiatives/esc/house-sites

Timing: Prior to commencement of any earth disturbing activities and until all exposed soil areas are permanently stabilised against erosion.

 
As indicated
20(a) Provide Land Occupier Notification to Council

(i) Notify Council's ESC Team of proposed land occupier/s by sending an email to CARS-ESC@Brisbane.qld.gov.au

(ii) If the land is to be occupied by any person other than the registered landowner then advice must be provided to Council that confirms the name, contact information and the duration of any proposed occupation of the land.

Note: Occupier is any principal contractor occupying the land exercising a right under the development approval.

Timing: Prior to commencement of any earth disturbing activities.

 
As indicated
 
21)   Information Signage

Erect an information sign on the subject property in accordance with Council's general requirements for signage and in accordance with the requirements outlined below:
a)  The sign should provide a brief description of the development proposed;
b)  The sign is to list the name, postal and/or email address and a contact telephone number for the following parties (where relevant) that are undertaking work on the site:
     -  Developer;
     -   Project Coordinator;
     -  Architect/Building Designer;
     -  Builder;
     -  Civil Engineer;
     -   Civil Contractor/s; and
     -  Landscape Architect;
c)  The lettering on the sign is to be at least 25 millimetres in height, be of regular weight and in sentence case;
d)  The sign is to be a minimum size of 1,200 millimetres by 900 millimetres;
e)  The maximum area of the sign is to be 2.0m2;
f)  The sign is to be positioned as follows:
     -  located centrally along the road frontage of the site to Mains Road;
     -  located on or within 1.5 metres of the road frontage;
     -  mounted at least 300 millimetres above ground level; and
     -  clearly visible from the street for a pedestrian;
g)  The sign is to contain no commercial or corporate advertising other than the name, logo or slogan of the parties outlined in part (b) of this condition;
h)  The sign is to be non-illuminated; and
i)   Both the sign and the supporting structure are to be made of weatherproof material and to be properly maintained at all times;

Timing: Prior to site works commencing and then to be maintained until completion of the development for all stages.

 
As indicated
 
22)   Construction Management Plan (Minor)

Carry out development in a method consistent with a Construction Management Plan (Minor) prepared in accordance with the requirements of this condition.

 
While site/operational/building work is occurring
22(a) Construction Management Plan (Minor) - Prepare Plan

Prepare a detailed Construction Management Plan (CMP) for the construction phase of the approved development.  The Construction Management Plan must be in accordance with the relevant Brisbane Planning Scheme Codes and address the following:
(i)     Provision for pedestrian management including alternative pedestrian routes (adjacent to or surrounding the site);
(ii)    Existing and proposed kerbside allocation signs and line marking (such as bus stops, loading zones and parking meters and/or ticket dispensers);
(iii)   Location of and impacts to any Council or other public utility or local authority's assets on or within external to the site;
(iv)    Location and design of temporary vehicular construction access points, including frequency of use;
(v)     Management and mitigation strategies for the impact of dust, noise and vibration upon adjoining and nearby properties;
(vi)    Provision for loading and unloading of materials including the location of any remote loading sites;
(vii)   Location of materials, structures, plant and equipment to be stored or placed on the construction site;
(viii)  Location of proposed external hoardings and/or gantries, and including clearances to the impacts of this on  existing street furniture and other footpath assets located within the verge as well as impacts on any existing advertising signage located either along or adjacent to the site frontage  - this includes any potential obstruction of sight lines for such advertising  (e.g. 'CityCycle' bicycle stations or bus stops with advertising);
(ix)    Location of proposed employee and visitor parking areas;
(x)     Anticipated staging and programming;
(xi)    Impacts of any actions proposed to address any of the above items or any actions resulting from construction of the development that will impact on existing street trees;
(xii)   Complaint management processes to be implemented; and
(xiii)  Compliance with the Management Plans Planning Scheme Policy and other relevant Planning Scheme Policies.

The Construction Management Plan must be supported by 'approval in principle' or written approvals from the relevant Council sections or other governing bodies responsible for any potentially impacted infrastructure.

The list of relevant infrastructure and contacts is available on Council's website - Search 'Constructions Management Plan'.

Note: The Construction Management Plan is not required to be approved by Development Services.

Timing: Prior to site/operational/building work commencing.

 
As indicated
22(b) Construction Management Plan (Minor) - Submit Plan

Submit a copy of the Construction Management Plan to Council's Development Services Branch at the following mailbox: engineeringservices@brisbane.qld.gov.au quoting the BCC planning development approval reference number.

Timing: At least 10 days prior to site works commencing.

 
As indicated
22(c) Construction Management Plan (Minor) - Documentation on Site

Legible copies of the Construction Management Plan and current permits must be kept on site and be made available on request by Council, At all times.

The requirements of the CMP must be included in all induction of principal and subcontractors utilised in the development. An outline of the induction provided to contractors may be requested by Council to confirm compliance with this condition.

Timing: While site/operational/building work is occurring.

 
As indicated
22(d) Construction Management Plan - Works to be Performed Out of Hours

Obtain an approval from Development Services for any work that is proposed to be undertaken outside of normal business hours - 6:30am to 6:30pm, Monday to Saturday.

Timing: Prior to site/operational/building work commencing.

 
As indicated
22(e) Implement Construction Management Plan (Minor)

Carry out the development in accordance with the submitted Construction Management Plan.

 
While site/operational/building work is occurring
 
23)   Protect Existing Infrastructure

Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure.

Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations.

The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements.

 
While site/operational/building work is occurring
23(a) As Constructed Drawings - Alterations to Existing Infrastructure

Submit to Development Services As Constructed drawings showing all new and/or rectification works and an asset register, prepared by a Registered Professional Engineer Queensland.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

PROOF OF FULFILMENT
Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
24)   Access, Grades, Manoeuvring, Carparks, Signs and Line Marking

Construct and maintain access, parking and manoeuvring for vehicles on site in accordance with the relevant Brisbane Planning Scheme Codes, as indicated on the approved DRAWINGS AND DOCUMENTS and with the Proposed Floor Plan, Drawing No. A104 Rev G, received on 21-MAY-2026 and amended in red on 26-MAY-2026, including the following:

i. A pavement of minimum Local road standard or equivalent surface material (including associated drainage) to the area on which motor vehicles will be driven and/or parked.

ii. Manoeuvring on site for a refuse collection vehicle and a medium rigid vehicle and for the loading and unloading of vehicle(s).

iii. Parking on the site for 35 cars, including one car parking space for people with disabilities and for the loading and unloading of vehicle(s) within the site. There must a minimum number of 35 car parking spaces provided on site.

iv. An appropriate area for the storage and collection of refuse, including recyclables, in a position which is accessible to service vehicles on the site.

v. Construct the modifications to the car parking area, in accordance with the Proposed Floor Plan, Drawing No. A104 Rev G, received on 21-MAY-2026 and amended in red on 26-MAY-2026.

vi. Prepare and implement signs and line markings drawings that show the internal paved areas signed and delineated in accordance with the approved drawings and documents and with the Proposed Floor Plan, Drawing No. A104 Rev G, received on 21-MAY- 2026 and amended in red on 26-MAY-2026. The drawings must be prepared and certified by a Registered Professional Engineer Queensland in accordance with the relevant Brisbane Planning Scheme Codes and the Manual of Uniform Traffic Control Devices.

PROOF OF FULFILMENT
Certification from a Registered Professional Engineer Queensland, that the above requirements have been implemented in accordance with this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
25)   Repair Damage to Kerb, Footpath or Road

Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
25(a) Interim Repairs

If at any time during the construction phase of the approved development, damage to the existing kerb and channel, footpath or roadway creates unsafe, unreasonable and/or not fit for purpose conditions as assessed by Council, interim repairs must be undertaken as directed by Program Planning and Integration.

Note: Any interim repairs required to be undertaken shall not be considered to satisfy the requirements of this condition for the permanent repair of the infrastructure prior to the issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

Timing: While site / operational / building works is occurring.

 
As indicated
 
26)   Refuse Collection - On Site

Provide for the installation and collection of refuse/recycling bins by Brisbane City Council's Waste and Resource Recovery Services or a private waste contractor.

 
At all times
26(a) Arrange Refuse Collection

Arrange for the installation of refuse/recycling bins and for the subsequent collection of refuse including recycling from the site by Brisbane City Council's Waste and Resource Recovery Services or a private waste contractor.

Timing: A minimum of four weeks prior to the commencement of use and then to be maintained. 

PROOF OF FULFILMENT
Where a private waste contractor is engaged, provide written confirmation from the proposed waste collection contractor of the agreement to service the property. The written agreement must be submitted to Council's Waste and Resource Recovery Services and include full details of the proposed system, bin sizes, number of bins, frequency of collection and the refuse collection vehicle size. Timing: Prior to commencement of use.

 
As indicated
26(b) Notify Future Owner

Where Council is engaged as the waste contractor, the owner must notify any future owner/body corporate that the development has been approved on the basis that an indemnity must be provide for refuse collection vehicles to enter the property.

Timing:  At time of a change of ownership.

 
As indicated
26(c) Indemnify Council

The owner and any subsequent owner must, by approved form to Waste and Resource Recovery Services, indemnify Council and its agents in respect of any damage to the pavement and other driving surfaces. 

Timing:  When an arrangement for refuse/recycling collection services is made with Brisbane City Council.

 
As indicated
 
27)   Refuse Storage - On Site Collection

Provide a roofed and wholly screened refuse enclosure utilising materials consistent with the development or a dedicated refuse storage room, as shown on the approved plans and documents. The refuse bin storage enclosure is to have the minimum dimensions as shown on the Proposed Floor Plan, Drawing No. A104 Rev G, received on 21-MAY-2026 and amended in red on 26-MAY-2026. In particular, the internal clear height is to be a minimum of 2.1 metres, to allow service personnel safe access to handle and manoeuvre the bins.

Provide visual and acoustic screening to the refuse enclosure, in accordance with the Refuse Planning Scheme Policy, so as to have no adverse acoustic, odour or visual impacts on the adjoining land.

The enclosure/refuse storage room must be of a design to accommodate the quantity of refuse and recycling including source separation to allow for low servicing collection of the development. A minimum total refuse bin storage capacity of 12,187 litres of refuse and recycling is to be provided.

Bins must be located in an area which allows them to be manoeuvred from the bin storage area to the designated internal collection point.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
28)   Ponding of Stormwater

Carry out the approved development to ensure that adjoining properties and roads are protected from ponding or nuisance from stormwater during construction.

Notes: If remedial works are necessary to comply with this condition, prior approval must be obtained from Development Services.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
29)   On Site Drainage - Minor

Provide a stormwater connection to all new or existing allotments and provide drainage infrastructure to ensure stormwater run-off from all roof and developed surface areas will be collected internally and piped in accordance with the relevant Brisbane Planning Scheme Codes to a lawful point of discharge via the existing stormwater drainage system within the site.

Note:
-  Guidance for the preparation of drawings and/or documents to comply with this condition is provided in the Brisbane Planning Scheme Policies.
-  Queensland Building and Construction Commission licensed hydraulic consultants may design the stormwater system for sites less than 2000m2 with an upstream catchment servicing no more than 4 residential lots.  This excludes stormwater drainage design (including subsoil drainage) of basements in flood planning areas and the design of any onsite stormwater detention system.
-  Where external works are required and infrastructure will be handed over to Council (for example, Stormwater pipes of 375mm diameter or greater and/or manholes within the road reserve, etc), the applicant will be required to request a Pre-Start with Council and ensure all future owned Council assets follow the On/Off Maintenance process in accordance with Councils Infrastructure Installation and Construction Requirements Manual.

-  Guidance for requesting a pre-start and co- ordinating the On/Off Maintenance process can be found on Council's website (https://www.brisbane.qld.gov.au/planning-and-building/applying-and-post- approval/on-and-off-maintenance-approvals).

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
30)   Service Conduits and Mains

Provide and install all service conduits and meet the cost of any alterations to public utility mains, existing mains, services, street lighting or installations that are required to carry out the approved development. These works must be in accordance with the relevant Brisbane Planning Scheme Codes, and include the following, where applicable:
-  the provision of all services and/or conduits along the full length of any rear allotment access or access easement.
-  the breaking and/or relocation of any existing sewer combine drains.
-  the relocation of any fire hydrant and/or valves from the development's vehicular footway crossings.
-  the retention and/or relocation of any existing foul water lines that currently exist within the site.
-  any new or existing installations of electrical pillar boxes, pad mounted transformers (PMTs), water reticulation mains, water meters and the like, must be installed/relocated to their ultimate alignment relative to the new property boundary and clear of the usable footpath areas irrespective of the alignment of the existing services/conduits.

Note:
-  The cost of moving services, utilities and assets is the responsibility of the Developer. The permission of the service, utility or asset owner will be required. Council permission is required if street trees, stormwater gullies/drains, and swales are affected. Urban Utilities permission is required if water supply and sewerage services are affected.
-  Standard utility alignments may be found on Council's 'Brisbane Standard Drawings' 1013 to 1016 inclusive.
-  Applicants must liaise with the appropriate service authorities. Typical underground services and/or conduits to be constructed include power, phone, telecommunications, sewer (including private combine drains) stormwater and gas, if applicable.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
30(a) Submit As Constructed Drawings

Submit to Development Services As Constructed drawings, including an asset register, prepared and certified by a Registered Professional Engineer Queensland.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

PROOF OF FULFILMENT
Certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the requirements of this condition. Note: Civil works are to be certified by a RPEQ(Civil) and electrical works are to be certified by a RPEQ (Electrical).

 
As indicated
 
Standard Advice
 
Timing
31)   Construction Noise and Dust Emissions

Pursuant to the Environmental Protection Act 1994, all development involving the emission of noise and dust from building and/or construction activities, must ensure that the emissions are in accordance with the requirements of the Act.
The Environmental Protection Act 1994 prescribes that:

1. A person must not carry out building work in a way that makes an audible noise-
-  on a business day or Saturday, before 6.30a.m. or after 6.30p.m; or
-   on any other day, at any time. 
2. The reference in subsection (1) to a person carrying out building work-
-  includes a person carrying out building work under an owner-builder permit; and
-  otherwise does not include a person carrying out building work at premises used by the person only for residential purposes.

Note: A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management delegate Development Services.

 
As indicated
 
32)   Management of Asbestos

Disposal, handling and restoration of any building materials containing asbestos must be in accordance with current state and federal legislation.

 
As indicated
 
33)   Further Development Permit Required

Further Development Permit(s) to carry out assessable building work under the Building Act may be required. Building Approval is to ensure fire escape stair and internal passageways take into account the number, mobility and other characteristics of occupants as detailed in the National Construction Code.

 
As indicated
 
34)   Plumbing and Drainage Work

Pursuant to the Plumbing and Drainage Act 2018, any plumbing and drainage work must be carried out in compliance with the Plumbing and Drainage Regulation 2019. Plumbing and drainage permit work requires approval by Brisbane City Council prior to the work being carried out.

 
As indicated
 
35)   Currency Period

The currency period for this development approval is stated in the Decision Notice and is expressed as a date.

 

This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016.

 
As indicated
 
36)   Referral Agency Requirements

Energex as Advice agency has imposed the requirements contained in the letter dated 15 December 2025 (reference: ECM 35324857-35321736).

 
As indicated
 
37)   Equitable Access

Provision must be made during and after construction for equitable access for persons with disabilities to and within the site and on adjoining public areas, in accordance with the following:
- Queensland Anti-Discrimination Act 1991;
- Federal Disability Discrimination Act 1992;
- Australian Standards AS1428 Parts 1-4;
- Australian Standard for Access and Mobility; and
- National Construction Code.

 
As indicated
 
38)   Fire Ant Movement Controls

To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected.

These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products.

Breaches of these controls can potentially impact the community, economy and the environment.  Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014.

For further information contact the relevant Queensland State Government department on 13 QGOV.

 
As indicated
 
39)   Water and Wastewater

Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council.  Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009.

For further information about any necessary Water Approvals contact Urban Utilities.

 
As indicated
 

** End of Package **