| Address of Site: | 17 MOLLISON ST SOUTH BRISBANE QLD 4101 35 BANK ST WEST END QLD 4101 39 BANK ST WEST END QLD 4101 |
| Real Property Description of Site: | L22/23 RP.10790 L48 RP.10778 L2 RP.51672 |
| Aspects of development and type of approval: | DA - PA - Material Change of Use Development Permit - community
use,multiple dwelling,food and drink outlet,office,shop |
| Council File Reference: | A007048617 Permit Reference Number/s: DAMC435283823. |
| Package Status: | APPROVED - Version 3 (23rd of July, 2026 3:55:32 PM) |
| Package Generated: | 23/07/2026 |
| Dalina HOWDEN Trunk Infrastructure & Calculations dalina.howden@brisbane.qld.gov.au (07) 3178 3895 |
Jenevere HEADING Principal Urban Planner Planning Services Governance Jenevere.Heading@brisbane.qld.gov.au (07) 3403 0124 |
Emma MEZZINA Team Manager Planning Services South Emma.Mezzina@brisbane.qld.gov.au 3178 0049 |
| Roger GREENWAY Principal Urban Planner Development Assurance & Outcomes roger.greenway@brisbane.qld.gov.au 34034392 |
Andrew BLAKE Principal Engineer Engineering Services Hydraulics andrew.blake@brisbane.qld.gov.au (07) 3403 5018 |
Rodney KING Plumbing Services Rodney.King@brisbane.qld.gov.au |
| Michael PICKERILL Network Planning Michael.Pickerill@brisbane.qld.gov.au |
Paul STONE WaRRS Assessment paul.stone@brisbane.qld.gov.au 317 85854 |
Daniel SPILLANE Senior Engineer Engineering Services South Daniel.Spillane@brisbane.qld.gov.au 3403 5285 |
| Karen HILTON Environmental Management Officer Environmental Management Services karen.hilton@brisbane.qld.gov.au (07) 3403 7102 |
Kirstin BURROWES Senior Architect Architecture Team Kirstin.Burrowes@brisbane.qld.gov.au 0731785363 |
Radmila SUBOTIC Senior Landscape Architect Landscape Architecture Team Radmila.Subotic@brisbane.qld.gov.au 31780113 |
| Fabrienne Michelle YU Principal Environmental Management Officer - Air Quality Environmental Management Services Michelle.Yu@brisbane.qld.gov.au 07 3403 0258 |
Chani ASHA Urban Planner Planning Services Special Assessment Chani.Asha@brisbane.qld.gov.au 07 3178 5178 |
Jian-Min CHEN Principal Urban Planner Planning Services Special Assessment jianmin.chen@brisbane.qld.gov.au (07) 3178 0821 |
DRAWINGS AND DOCUMENTS
| Drawing or Document | Number | Plan Date |
|---|---|---|
| Statement of Landscape Design Intent | 220302 DA02 (Amended In Red 15-FEB-2024) | 23-JUN-2023 (Received) |
| On-Street Parking | B23024-SK-005 Sheet Size A1 Rev. A (Amended In Red 15-FEB-2024) | 06-APR-2023 (Received) |
| Cover Sheet | TP00.00 C (Amended In Red 15-FEB-2024) | 03-NOV-2023 (Received) |
| Proposed Site Plan | TP00.11 C | 03-NOV-2023 (Received) |
| Basement 04 | TP01.01 C | 03-NOV-2023 (Received) |
| Basement 03 | TP01.02 C | 03-NOV-2023 (Received) |
| Basement 02 | TP01.03 C | 03-NOV-2023 (Received) |
| Basement 01 | TP01.04 C | 03-NOV-2023 (Received) |
| Ground Floor | TP01.05 C (Amended In Red 27-MAR-2024) | 03-NOV-2023 (Received) |
| Services Mezzanine | TP01.06 C | 03-NOV-2023 (Received) |
| Level 02 | TP01.07 C | 03-NOV-2023 (Received) |
| Level 03 | TP01.08 B | 03-NOV-2023 (Received) |
| Level 04-05 | TP01.09 A | 03-NOV-2023 (Received) |
| Level 06-10 | TP01.10 C | 03-NOV-2023 (Received) |
| Level 11 | TP01.16 C | 03-NOV-2023 (Received) |
| Level 12 | TP01.17 C | 03-NOV-2023 (Received) |
| Level 13-14 | TP01.18 C | 03-NOV-2023 (Received) |
| Level 15 | TP01.20 C | 03-NOV-2023 (Received) |
| Level 16-17 | TP01.21 C | 03-NOV-2023 (Received) |
| Level 18 | TP01.23 C | 03-NOV-2023 (Received) |
| Roof Terrace | TP01.24 C | 03-NOV-2023 (Received) |
| North East & North West Elevations | TP02.01 C (Amended In Red 26-MAR-2024) | 03-NOV-2023 (Received) |
| South West & South East Elevation | TP02.02 C (Amended In Red 26-MAR-2024) | 03-NOV-2023 (Received) |
| Section A & B | TP03.01 D (Amended In Red 26-MAR-2024) | 21-NOV-2023 (Received) |
| Section C & D | TP03.02 D (Amended In Red 15-FEB-2024) | 21-NOV-2023 (Received) |
| Section E & F | TP03.03 D | 21-NOV-2023 (Received) |
| Development Statistics - Deep Planting | TP04.01 C | 03-NOV-2023 (Received) |
| Development Statistics - Landscaping | TP04.02 C | 03-NOV-2023 (Received) |
| Development Statistics - Site Cover | TP04.03 C | 03-NOV-2023 (Received) |
| Development Statistics - COS, Public & GFA | TP04.04 C | 03-NOV-2023 (Received) |
| Ground Plane Elevations | TP05.01 A | 03-NOV-2023 (Received) |
| Onyx & Carpark Interface Elevation | TP05.02 A | 03-NOV-2023 (Received) |
| Existing Site Plan | TP00.10 C | 03-NOV-2023 (Received) |
| Onyx Interface (Level 2-3) - Privacy Screening | Item 4. Privacy Impacts for Adjoining Properties p19 | 03-NOV-2023 (Received) |
| Onyx Interface (Level 4-5) - Privacy Screening | Item 4. Privacy Impacts for Adjioning Properties p20 | 03-NOV-2023 (Received) |
| Arcadia Interface (Lower) - Building Separation & View Lines | Item 4. Arcadia Interface - Building Separation and View Lines p21 | 03-NOV-2023 (Received) |
| Arcadia Interface (Upper) - Building Separation & View Lines | Item 4. Arcadia Interface (Upper) - Building Separation & View Lines p22 | 03-NOV-2023 (Received) |
| Onyx Interface Section | Item 3. c) i & ii Arcadia & Onyx Interface Section p14 (Amended In Red 21- NOV-2023) | 23-JUN-2023 (Received) |
| Arcadia Interface Sections | Item 3. c) i & ii Arcadia & Onyx Interface Section p15 | 23-JUN-2023 (Received) |
| Ground Plane (Materials and finishes palette) | p52 (Amended In Red 15-FEB-2024) | 12-APR-2023 (Received) |
| Tower (Materials and finishes palette) | p53 | 12-APR-2023 (Received) |
| Food & Beverage Detail | TP05.21 A | 29-NOV-2023 (Received) |
| Screen & Blind Elevations | TP05.31 A | 29-NOV-2023 (Received) |
| Screen & Blind Elevations | TP05.32 A | 29-NOV-2023 (Received) |
APPROVAL CONDITIONS
| Permit to Which These Conditions Relate: | DA - PA - Material Change of Use |
| Activity(ies): | community use shop office food and drink outlet multiple dwelling |
| Stage: | Multiple dwelling (103 units) |
| 1) Building Management Statement Ensure a Building Management Statement is registered on the title for each proposed lot. The Building Management Statement must cover common
building management items including but not limited to any shared: Timing: As part of the registration of the plan of subdivision notated by Council and then to be maintained. |
As indicated |
1(a) Submit Building Management
Statement The Building Management Statement must be submitted to, and the content endorsed by, Development Services. Timing: Prior to Council's notation on the plan of subdivision. |
As indicated |
1(b) Lodge Building Management
Statement Lodge the accepted Building Management Statement with the Registrar of Titles for the relevant Queensland State Government Authority. Timing: As part of the registration of the plan of subdivision notated by Council. |
As indicated |
1(c) Submit Evidence of
Registration Submit to Development Services, evidence of the registration of the endorsed Building Management Statement. Timing: Within one month of the registration of the Building Management Statement. |
As indicated |
| 2) Security Lighting - On Site Install and maintain a suitable system of security lighting to operate from dusk to dawn within all areas where the public may gain access, including car parking areas, building entrances and vegetated areas. Ensure that all external lighting is in accordance with Australian Standard - AS4282- Control of the Obtrusive Effects of Outdoor Lighting. Ensure lighting over publicly accessible internal pathways covered by permanent awnings is in accordance with Australian Standard - AS/NZS 1158.3.1 Lighting for roads and public spaces - Pedestrian area (Category P) lighting - Performance and design requirements. Lighting must be maintained in safe and good working order.
Timing: 'Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first' |
As indicated |
| 3) Building Format Plan Where the timing of a condition, or part thereof , states 'Prior to issue of Certificate of Occupancy/Final Inspection Certificate' or 'Prior to commencement of use' and the development involves the creation of a Building Format Plan, the timing of the condition, or part thereof, is taken to mean 'prior to Council's endorsement of any plan of subdivision'. |
As indicated |
| 4) Public Access - 24 Hours Through Site Provide and maintain unimpeded and safe 24-hour public access through
the subject site and ensure that access ways are designed to cater for people
with disabilities in accordance with Australian Standard - AS1428.1Design for
Access and Mobility - Part 1: General requirements for access - New
building work. This thoroughfare must provide a high standard of amenity, incorporating generous landscaping, seating, and opportunities for small meeting points. Where possible, the thoroughfare should incorporate design elements that facilitate enjoyment of the space to the general community. At a minimum, the thoroughfare must provide the following: - Clear signage at entry and exit points to the site
to assist with wayfinding. - Lighting. (Note: Lighting must be installed and maintained so that it does not create a nuisance to adjoining properties.) - Quality landscaping in accordance with the landscaping conditions of this approval. - Seating. - Areas for small congregations. - Drinking fountain. - Community noticeboard. The thoroughfare must be designed applying the principles of Crime prevention through environmental design (CPTED). (Note: Refer to the Crime prevention through environmental design Planning scheme policy of City Plan 2014 (v26).) Note. This condition is imposed to ensure the
provision and maintenance of public access through the site between Bank Street
and Mollison Street which is a relevant matter for the purpose of assessing the
development application the subject of the development
approval. |
At all times |
| 5) Car Parking The car parking within the premises must be maintained exclusively for the ancillary use of the Multiple dwelling use. The parking must not be made available to the general public and there must not be signage erected on or in the vicinity of the site advertising the availability of car parking to the general public. |
At all times |
| 6) Maintain the Approved Development Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions. |
At all times |
| 7) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers. Note: This condition is imposed to ensure compliance with the conditions of development approval. |
While site/operational/building work is occurring |
| 8) Carry Out the Approved Development Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS. Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners. |
While site/operational/building work is occurring |
| 9) Complete All Operational Work Complete all operational work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such operational work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS or, if requiring a further approval from the Council, in accordance with the relevant further approval(s). |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 10) Complete All Building Work Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS. Note: Building work must also be completed in accordance with any other current development approval. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 11) Visitor Parking Visitor car parking spaces must: - Be clearly labelled as 'Visitor Parking'; - Where located on the ground level, remain unimpeded by landscaping, water tanks, storage (temporary or otherwise), gates or any other fitting, fixture of structure; - Where located in basement 1, access is to be provided through the use of a managed intercom or other similar system at security gates. - Provide 24 hour unrestricted access for all bona fide visitors to the Multiple dwelling use on site. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 12) Community use The use of
the area indicated as ‘multi-purpose space’ on the approved plan
titled Ground Floor with reference TP01.05 C received 3-NOV-2023 as amended in
red on 27-MAR-2024 is to be leased as Community use for a minimum of 12 months.
Timing: From the commencement of use of the development Guideline: This condition is imposed to ensure the
provision of public benefit for this development, which is a relevant matter
for the purpose of assessing the development application the subject of the
development approval. This community use space is to provide community benefit
associated with the approved use. Operation of Community
Use The use of the area indicated as ‘multi-purpose space’ on
the approved plan titled Ground Floor with reference TP01.05 C received 3-NOV-
2023 as amended in red on 27-MAR-2024 is to be used for community related
activities. This area designated on the approved plans is for providing
artistic, social or cultural facilities
or community services to the public in accordance with City Plan 2014 (v26).
Timing: When the ‘multi-purpose space’ is a Community use. |
As indicated |
| 13) Communal Areas The communal areas on level 11, 12 and 15 are limited to the Multiple dwelling use only and are to be available for all residents. |
At all times |
| 14) Architecture - Creative Lighting Provide creative lighting to the new elements of the facade and publicly accessible pedestrian areas of the ground plane in accordance with the requirements of this condition. Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
14(a) Submit Creative Lighting
Strategy |
As indicated |
14(b) Implement Approved Creative Lighting
Strategy Carry out the approved creative lighting strategy in accordance with the drawings and documents approved as part of this condition. Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained. |
As indicated |
| 15) External Details External details of the building, facade treatment and external materials and finishes must be consistent with the approved DRAWINGS AND DOCUMENTS. Note: The requirement to use particular materials and finishes is imposed only for the purpose of achieving a built form outcome that displays architectural merit. Council has not assessed the materials and finishes for compliance with the Building Act, the Building Fire Safety Regulation, the Building Regulation, the Building Code of Australia, the Queensland Development Code, relevant Australian Standards, fire safety standards or any other relevant requirement of a statutory authority with regard to building work. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 16) Overall Height The overall height of the building(s) must be in accordance with the floor and roof levels and overall height shown on the APPROVED DRAWINGS AND DOCUMENTS. NOTE: This condition should be read in conjunction with any other relevant condition requiring minimum height clearances for basement or undercover car parking and manoeuvring areas. |
While site/operational/building work is occurring and then to be maintained |
16(a) Submit Certification Submit to Development Services certification from a Registered Surveyor (Qld) confirming that the 'as constructed' floor and roof levels and overall height are in accordance with the requirements of this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 17) Light Reflectivity and Solar (Heat)
Reflectivity Submit to Development Services documentary evidence that the level of light reflectivity from the glazing incorporated in the approved development does not exceed 20%. Timing: Prior to building work above ground level commencing. |
As indicated |
17(a) Install Glazing Install and maintain glazing in accordance with the above specification. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained. |
As indicated |
| 18) Environmental Sustainability Construct and maintain the building(s) in accordance with 'Best Practice' environmentally sustainable measures. |
While site/operational/building work is occurring and then to be maintained |
18(a) Submit Sustainability Management
Plan Submit to, and obtain approval from, Development Services a Sustainability Management Plan prepared by a Registered Architect / Registered Professional Engineer Queensland (suitably qualified and experienced in sustainability management) incorporating measures for the development to achieve at least a 'Best Practice' environmentally sustainable rating for the building in accordance with a recognised Environmental Rating System suitable for the approved development (such as Green Star). Note: For the purpose of this condition 'Best Practice' outcomes must exceed the requirements of the Building Code of Australia and achieve the equivalent of a Green Star 4 star rating. Timing: Prior to commencement of building work above ground level. |
As indicated |
18(b) Implement Sustainability Management
Plan Implement and maintain the approved Sustainability Management Plan. Timing: While site/operational/building work is occurring and then to be maintained. |
As indicated |
18(c) Submit Certification Submit to Development Services certification by a Registered Architect / Registered Professional Engineer Queensland (suitably qualified and experienced in sustainability management) confirming that the approved Sustainability Management Plan has been implemented in accordance with the requirements of this condition. Timing: Prior to the commencement of the use. |
As indicated |
| 19) Mitigate Wind Impacts Mitigate any adverse wind impacts arising from the implementation of the development in accordance with a Wind Impact Assessment Report and Architectural Drawings approved pursuant to this condition. |
While site/operational/building work is occurring and then to be maintained |
19(a) Submit Wind Impact Assessment
Report Submit to, and obtain approval from, Development Services a detailed Wind Impact Assessment Report, including any outcomes obtained from an in-depth assessment such as a wind tunnel test or comprehensive computational fluid dynamics model, prepared by a Registered Professional Engineer, Queensland (experienced in assessing building wind impacts), demonstrating that wind impacts arising from the implementation of the development, will not adversely affect pedestrian comfort levels and stationary activities within the development and for the public realm at street level. Note: This condition is imposed to protect the amenity of the public realm and communal areas within the development from adverse wind conditions created by the development. Timing: Prior to site/operational/building work commencing above ground. |
As indicated |
19(b) Submit Architectural
Drawings Submit to, and obtain approval from, Development Services revised and properly made Architectural Drawings indicating any alterations to the approved building design and/or mitigation measures identified as being necessary to ensure the amenity of these areas meets the standards for comfort for their use, as advised in the Wind Impact Assessment Report approved pursuant to (a) above. Timing: Prior to site/operational/building work commencing above ground |
As indicated |
19(c) Implement Wind Impact Assessment Report
and Architectural Drawings Carry out the works in accordance with the approved Wind Impact Assessment Report and approved Architectural Drawings. Timing: While site/operational/building work is occurring. |
As indicated |
19(d) Submit Certification Submit to Development Services, certification from a Registered Professional Engineer, Queensland (experienced in assessing building wind impacts), certifying that the work(s) have been carried out in accordance with the approved Wind Impact Assessment Report and approved Architectural Drawings. Timing: Prior to commencement of use. |
As indicated |
| 20) Artworks Provide and maintain artworks in accordance with this condition.
|
Prior to the commencement of the use and then to be maintained |
20(a) Budget and Art Opportunities
Report Submit to, and obtain approval from the Principal Architect, Design Brisbane, via Development Services email dalodgement@brisbane.qld.gov.au
(i) A Quantity Surveyor's letter stating the artwork budget allocation of no less than 0.25% of the total cost of building and construction work.
(ii) An Art Opportunities Report, prepared by a suitably qualified art consultant or curator that provides: · The site's context, history, and description · Curatorial rationale for the artwork program · Proposed artwork locations within an area determined by the Principal Architect, Design Brisbane that meet the criteria of being readily viewable within the public domain. · Any artwork should not be delivered to fulfil compliance for any other condition contained within this development approval and the approved drawings and documents. Note: Artworks for podium screening shall not achieve compliance with this condition. · A long- list of recognised artists or craftspeople which includes descriptions of each artist's practice, and relevant examples of their artwork that indicates the potential artforms and mediums under consideration for each location · Indicative budget breakdown · Indicative program · Contact details of the art consultant or curator.
For further guidance on the Art Opportunity Report content contact the Principal Architect, Design Brisbane via Development Services email dalodgement@brisbane.qld.gov.au |
Prior to the commencement of the use and then to be maintained |
20(b) Final Concept Design
Report Submit to, and obtain approval from, the Principal Architect, Design Brisbane via Development Services email dalodgement@brisbane.qld.gov.au, a Final Concept Design Report, prepared by a suitably qualified art consultant or curator
The Final Concept Design Report must include a minimum of three Concept Designs per artwork opportunity location from suitably qualified artists. The preferred artwork/s concept design must include:
· Artist statement relating to the work · Artist's biography and abridged Curriculum Vitae · Concept drawings or/and render · Materials, scale, dimensions, site context, and any other relevant information · Preliminary budget breakdown · Delivery Program · Maintenance considerations.
|
Prior to the commencement of the use and then to be maintained |
20(c) Implement Approved
Artwork Supply and install approved artwork and attribution plaque including artist statement and artwork credit line.
|
Prior to the commencement of the use and then to be maintained |
20(d) Submit details Submit to the Principal Architect, Design Brisbane via Development Services email dalodgement@brisbane.qld.gov.au
(i) The maintenance manual for the artwork/s, including any supporting documentation.
(ii) The itemised cost breakdown for each artwork including: · Artists fees · Design development costs · Fabrication and installation costs
|
Prior to the commencement of the use and then to be maintained |
20(e) Final Inspection
Arrange for the Principal Architect, Design Brisbane, to carry out a final inspection to confirm that the artwork has been installed in accordance with the requirements of this condition.
|
Prior to the commencement of the use and then to be maintained |
| 21) Driveway Material and Finishes Provide materials and
finishes to the driveway and external carparking
surfaces that reduce the visual impact of these areas when viewed from the
street. One or a combination of the following must be used: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 22) Balconies/Verandahs/Terraces No balconies/verandahs/terraces may be enclosed with solid balustrades, solid walls, fixed and/or operable, moveable or adjustable screening unless these features are clearly shown on the APPROVED DRAWINGS AND DOCUMENTS. Note: Any Community Management Statement that may apply to this approval must contain a by-law which reflects the requirements of this condition. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 23) Screen Air Conditioning and Other Plant
Enclosures Install and maintain suitable screening to all air conditioning units, lift motor rooms, hot water systems plant and service facilities where externally visible or located on top of the building including where visible and/or located within private open space areas, communal open space areas, adjoining properties or public land. The screening structures must be constructed from durable materials that are consistent with materials used elsewhere on the facade of the building. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 24) Sun Shading Devices Provide sun shading in accordance with the approved DRAWINGS AND DOCUMENTS |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 25) Screening Provide suitable privacy screening to windows of habitable rooms, balconies, landings, terraces and decks of the proposed dwelling(s) in accordance with the approved DRAWINGS AND DOCUMENTS.
|
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 26) Retain and Protect Existing Street Tree(s) Identify, retain and protect the existing street tree located on the Bank Street frontage of the site adjacent to current Lot 2 on RP51672 (northern-most tree) including the roots unless otherwise agreed in writing with Program, Planning and Integration Arboriculture (PPI Arb). Note: Street trees are protected under the Natural Assets Local Law. Street trees must not be removed or pruned without prior approval from PPI Arb. Where driveway crossovers occur within the Tree Protection Zone (TPZ) of existing street trees, seek approval from the Arboricultural Team in Program Planning and integration, City Standards for the final driveway crossover design and construction methodology to ensure the successful retention of the existing street tree(s) PROOF OF FULFILMENT Contextual photographic evidence that the tree has been retained in equal or greater health than before development commenced. OR, evidence in writing from Asset Services Arboriculture that an alternative arrangement has been made. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
At all times |
26(a) Implement Protection
Measures Install tree protection measures in accordance with Australian Standard - AS4970 Retention of Trees on Development Site. There must be no excavation, filling or storage of materials or plant within the drip line of the tree(s). Where works are within the canopy drip line of existing street trees, contact PPI Arb Coordinator in relation to the required provision of protection measures. Note: If fencing is to protect street trees, a permit to temporarily occupy the footway will be required from Compliance and Regulatory Services. Timing: Prior to site/operational/building work occurring. PROOF OF
FULFILMENT Contextual photographic evidence to demonstrate the installation of protection measures prior to building works commencing. Timing: Prior to site / operational / building work occurring. |
As indicated |
26(b) Maintain Protection
Measures Maintain protection measures while development is occurring and remove protection measures prior to commencement of the use. Timing: While to site/operational/building work is occurring. |
As indicated |
| 27) Street Tree Replacement Provide for replacement planting on the Mollison Street frontage of the development site for the existing street tree removed from the Bank Street frontage of the development site. PROOF OF
FULFILMENT Contextual photographic evidence of installed replacement trees. OR, evidence in writing from Program Planning and Integration Arboriculture that an alternative arrangement has been made. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
27(a) Enter Arrangement Enter into an arrangement with Program, Planning and Integration Arboriculture (PPI Arb) to pay the cost or undertake works, as agreed with PPI Arb, for the removal and replacement planting of the existing street tree(s) fronting the development site. Timing: Prior to site/operational/building work commencing. |
As indicated |
27(b) Implement Arrangement Implement the arrangement agreed with PPI Arb. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 28) Streetscape Works - Centre Street Carry out streetscape improvement works to the verge to a City Street Major standard in accordance with the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD), the requirements of this condition and the Infrastructure Design Planning Scheme Policy including section 3.7.4.3. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
28(a) Submit Level Details Submit to Development
Services, and obtain approval for, details of the future finished levels of the
site and building entries (both pedestrian and vehicular) to demonstrate verge
levels and crossfalls complying with the Infrastructure Design Planning Scheme
Policy including section 3.7.3.5. The details must be provided by an RPEQ in
consultation with a qualified Landscape Architect and include the
following: Timing: Prior to site/operational/building work occurring. |
As indicated |
28(b) Submit Plan for Works in
Verge Submit, to an obtain approval from, Development Services, a detailed Landscape Works in Streetscape Plan for the required improvement works in accordance with the requirements of the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD) and the Infrastructure Design Planning Scheme Policy including section 3.7.4.3. The detailed Landscape Works in Streetscape Plan must be prepared at a scale of 1:100 by a qualified Landscape Architect and include the following: DOCUMENTATION REQUIREMENTS - Finished surface levels at lot boundary and
kerb. Timing: Prior to building work above ground level commencing. |
As indicated |
28(c) Pre-Start Meeting Arrange and attend a pre-start meeting with Landscape Architecture Team, City Planning and Economic Development. Council will only attend the pre-start meeting once all applicable compliance and inspection fees have been paid. The project landscape architect must be present at the pre-start meeting. Timing: Prior to any work commencing to comply with this condition. |
As indicated |
28(d) Implement Streetscape
Works Remove the existing footway including affected street signage for the full length of the frontage. Carry out the works in accordance with the approved detailed Landscape Works in Streetscape Plan and to a standard and using materials in accordance with the requirements of the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD) and the Infrastructure Design Planning Scheme Policy section 3.7.4.3. Note: All existing artworks and regulatory signage must be secured and repositioned as agreed with Program Planning and Integration. Note: Any existing Brisbane Tuff or granite kerbing that is surplus to requirements must be returned to Program Planning and Integration. Note: At all times during construction provision must be made for people with a visual impairment. Where it is unavoidable that a
section of an existing Braille trail is to be blocked, or an object temporarily
located to intrude within the 1000 mm clearway on either side of the Braille
trail, the following actions must be undertaken to comply with the current
version of AS1428: Note: Lodge with and receive approval from Development Services for an 'Application for Permits Relating to Roads and Footway' prior to carrying out the approved works. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to the commencement of use, whichever comes first. |
As indicated |
28(e) Submit As-Constructed
Drawings Submit to Development Services Specialist Services As Constructed drawings including an asset register, prepared by a Registered Professional Engineer Queensland, certifying that the streetscape works have been completed in accordance with the approved detailed Landscape Works in Streetscape Plan and to a standard and using materials in accordance with the requirements of the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD) and the Infrastructure Design Planning Scheme Policy section 3.7.4.3. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
28(f) On-Maintenance Acceptance Arrange an on- maintenance inspection with Development Services and obtain written confirmation that the works have been accepted on-maintenance. Provide proof of Public Liability Insurance ($20 million) for the on- maintenance period. Lodge a bond for the streetscape works maintenance period of the works. The bond must be calculated in accordance with the relevant Brisbane Planning Scheme Codes (5% of total value of the landscape works or minimum of $5,000.00 whichever is greater). Note: To arrange an on-maintenance inspection with Development Services an email must be sent to specialistservices@brisbane.qld.gov.au. Note: A maintenance bond can consist of either a bank guarantee or monetary payment lodged with Council. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
28(g) On-Maintenance Period Provide a minimum of 12 months maintenance to the streetscape works and rectify any defects identified at the on-maintenance inspection and those arising during the on-maintenance period. Timing: Minimum 12 months from acceptance on- maintenance AND until the works are approved off-maintenance by Council. |
As indicated |
28(h) Off-Maintenance
Acceptance On completion of the on-maintenance period, arrange an off-maintenance inspection with Development Services and obtain written confirmation from Council that the work is accepted off-maintenance. Ensure all defects are rectified prior to making an appointment for off- maintenance inspection. Note: To arrange an off-maintenance inspection with Development Services an email must be sent to specialistservices@brisbane.qld.gov.au. Note: If the off- maintenance inspection is successful the maintenance bond will be released. Timing: On completion of the on-maintenance period. |
As indicated |
| 29) Streetscape Works - Neighbourhood Street
Major Carry out streetscape improvement works including concrete path (where required by this condition), turf and street trees to the verge to a Neighbourhood Street Major standard in accordance with the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD), the requirements of this condition and the Infrastructure Design Planning Scheme Policy including sections 3.7.4.4 and 3.7.5. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
29(a) Concrete Path Install a 1.8m wide broom finished standard Portland grey concrete path. The edge of the path is to be setback 1300mm from the back of kerb.
Where the path cannot be installed on this alignment due to conflicts such as
street trees, or power poles, ensure the path is installed a minimum distance
of: If the above requirements cannot be achieved, contact the Landscape Architecture Team via email: specialistservices@brisbane.qld.gov.au. Transition to existing paths on verges that adjoin the development. The transition is to occur fronting the adjoining developments, not the subject site. Note: standard path alignments are shown on Brisbane Standard Drawing BSD-5201 sheet 2 but will vary depending on verge width and location. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Photographic evidence of concrete path. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
29(b) Submit As-Constructed
Drawings Submit to Development Services As Constructed plans including an asset register, checked by a Registered Professional Engineer Queensland, certifying that the concrete path works have been completed in accordance with relevant Brisbane Planning Scheme Codes/Policies. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT As constructed drawings signed by an RPEQ. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
29(c) Turf Install turf to the full width of the verge excluding any concrete path required by this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Photographic evidence of installed turf. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
29(d) Street Tree(s) Enter into and implement an arrangement with the Program Planning and Integration Regional Coordinator Arboriculture in relation to the required provision of the street tree planting in accordance with the above sections of the Infrastructure Design Planning Scheme Policy, including the number, species, location, installation and maintenance of the required street tree(s) as determined by Program Planning and Integration. Provide to Development Assessment a copy of the agreement signed by Program Planning and Integration. Note: Street trees should not be planted until all utilities have been installed. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT A copy of the agreement with Program Planning and Integration and/or photographic evidence of installed trees. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 30) Pedestrian and/or Awning Lighting Install Pedestrian and/or Awning Lighting in accordance with the requirements of this condition. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
30(a) Submit a Pedestrian and Awning Lighting
Design Submit to Construction Branch, Citywide Services, City Lighting (CS- LIGHTING@brisbane.qld.gov.au), and obtain approval for, a detailed Pedestrian Lighting Design for the full street frontage of the development, and/or Awning Lighting Design to the underside of the proposed awning over the verge in accordance with the following: Pedestrian Lighting: Provide electrical reticulation plans prepared by a Registered Professional Engineer Queensland certifying that the design complies with Australian Standard - AS/NZS3000 Electrical installations known as the Australian/New Zealand Wiring Rules and Council's standard drawings (BSD-11000 series). Provide pedestrian and cycle lighting plans prepared by a Registered Professional Engineer Queensland or a member of the Illuminating Engineering Society of Australia and New Zealand certifying that the design complies with Australian Standard - AS/NZS 1158.3.1 Lighting for roads and public spaces - Pedestrian area (Lighting Sub-category PP3) lighting - Performance and Design requirements. And/Or Awning Lighting: Submit to Construction Branch, Citywide Services, City Lighting (CS-LIGHTING@brisbane.qld.gov.au), and obtain approval for, a detailed Awning Lighting Plan demonstrating that the under awning lighting complies with Australian Standard - AS/NZS 1158.3.1 - sub category P6, within - Road Lighting Part 3.1: Pedestrian area (Lighting Sub- category PA3) lighting - Performance and installation design requirements and achieves glare control to ensure zero candelas (cd) at 90 degrees. Timing: Prior to commencing building work above ground level and prior to or concurrently with the submission of Landscape Works in Streetscape Plans for approval. |
As indicated |
30(b) Obtain an Electrical
Connection Obtain an electrical connection from the electricity supplier OR Enter into an arrangement with the electricity supplier to service the approved pedestrian lighting. Timing: Prior to commencing building work above ground level. |
As indicated |
30(c) Implement Approved Pedestrian and/or
Awning Lighting Design Install the lighting in accordance with the approved detailed Pedestrian Lighting Design and the approved Landscape Works in Streetscape Plan and/or Awning Lighting Design. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
30(d) Provide Certification of Connection and
Operation Provide to Construction Branch, Citywide Services, City Lighting (CS- LIGHTING@brisbane.qld.gov.au) certification from a licensed electrical contractor that the electrical connection has been installed in accordance with the approved detailed Pedestrian Lighting Design and/or Awning Lighting Design and that the lighting is fully operational. The certification must specify that the electrical installation has been tested to ensure it is electrically safe and in accordance with the requirements of Australian Standard - AS/NZS3000 Electrical installations known as the Australian/New Zealand Wiring Rules and any other standard applying to the electrical installation under the Electrical Safety Regulation 2002. A copy of the as-constructed Pedestrian Lighting Design Drawings must be included with the above certification. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
30(e) On-Maintenance Acceptance Arrange an on- maintenance inspection with Construction Branch, Citywide Services, City Lighting (CS- LIGHTING@brisbane.qld.gov.au) and obtain written confirmation from Council that the work has been completed in accordance with the requirements of the condition and is accepted on-maintenance. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
30(f) On-Maintenance Period Provide a minimum 12 months maintenance to the works from the time the works are accepted on- maintenance by Council. During this period maintain the lighting and rectify any defects identified at the on-maintenance inspection and those arising during the on-maintenance period. Timing: Minimum 12 months from acceptance on-maintenance AND until the works are approved off- maintenance by Council. |
As indicated |
30(g) Off-Maintenance
Acceptance On completion of the on-maintenance period arrange an off-maintenance inspection with Construction Branch, Citywide Services, City Lighting (CS- LIGHTING@brisbane.qld.gov.au) and obtain written confirmation from Council that the work is accepted off-maintenance. Ensure all defects are rectified prior to making an appointment for off-maintenance inspection. Timing: On completion of the on-maintenance period. |
As indicated |
30(h) Maintain the Work (Awning
Lighting) Maintain the awning lighting (including operating costs) in accordance with the approved Lighting Plan from dusk to dawn. Timing: To be maintained. |
As indicated |
| 31) Landscape the Site Landscape the site as indicated on the approved DRAWINGS AND DOCUMENTS and in accordance with the requirements of this condition. This includes the approved Statement of Landscape Design Intent reference 220302 DA02 received 23-JUN-2023 as amended in red on 15-FEB- 2024. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
31(a) Submit Building Layout
Details Submit to Development Services, and obtain approval from for, details of the final building layout below and at ground level to demonstrate that provision has been made for deep planting, perimeter planting, services and existing trees that are required to be retained. The details must be provided by a qualified Landscape Architect or RPEQ. Timing: Prior to building works commencing. |
As indicated |
31(b) Submit Detailed Landscape
Plan Submit to Development Services, and obtain approval for, a detailed Landscape Plan for all on-site landscape works identified on the approved DRAWINGS AND DOCUMENTS. The plan must be prepared at a scale of 1:100 by a qualified Landscape Architect and must comply with the relevant Brisbane Planning Scheme Codes. The plan must include the following: Siteworks Planting Public Thoroughfare Deep Planting Timing: Prior to building work above ground level commencing. |
As indicated |
31(c) Additional Requirements - Multi-Unit
Dwelling/Single Unit Dwelling In addition to the requirements listed above, the plan must include the following: Planting Amenity Containerised Planters Terraced Retaining Walls Specifications Timing: Prior to building work above ground level commencing. |
As indicated |
31(d) Additional Requirements - Containerised
Planting In addition to the requirements listed above, the plan must include the
following: Timing: Prior to building work above ground level commencing. |
As indicated |
31(e) Additional Requirements -
Irrigation In addition to the requirements listed above, the plan must include the
following: Timing: Prior to building work above ground level commencing. |
As indicated |
31(f) Construct Approved Works Carry out the landscaping and associated works in accordance with the approved detailed Landscape Plan. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
31(g) Certify Works On completion of the works, provide Development Services with a copy of the as-constructed detailed Landscape Plan together with certification from a qualified Landscape Architect or qualified Landscape Contractor that the completed landscape work complies with the approved detailed Landscape Plan (Brisbane City Council Form CC10613 Landscape Works Certificate). Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
31(h) Maintain the Landscape
Works Maintain the landscape generally in accordance with the approved detailed Landscape Plan. Timing: Prior to commencement of use, whichever comes first. |
As indicated |
| 32) Landscape the site - Container planting for rooftop
gardens and/or green walls Landscape the site through the provision of container planting in accordance with the requirements of this condition. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
32(a) Prepare Detailed Container Planting
Design for self-certification Prepare a Detailed Container Planting Design for all
container planting identified on the approved DRAWINGS AND DOCUMENTS. The plan
must be prepared and certified by suitably qualified professionals and must
comply with the relevant Brisbane planning scheme codes. In addition to the
above, the design must include the following: Timing: Prior to work commencing above ground level. |
As indicated |
32(b) Implement certified Detailed Landscape
Container Planting Design Carry out the works in accordance with the above certified Detailed Landscape Container Planting Design. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
32(c) Certify work -
Implementation On completion of the work, submit to Development Services the
following: Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
32(d) Certify work - establishment
period On completion of the 12-month establishment period, submit to Development Services certification that planting has been established in accordance with the certified Detailed Landscape Container Planting Design. Timing: 12 months after implementation of the certified Detailed Landscape Container Planting Design. |
As indicated |
32(e) Maintain container
planting Rooftop gardens AND / OR Green Walls Maintain the container planting generally in accordance with the certified Detailed Landscape Container Planting Design. Timing: To be maintained. |
As indicated |
| 33) Kitchen exhaust vents - (emitters) Kitchen and food preparation area exhaust vent outlets are discharged vertically, directed away from any sensitive use and separated by a minimum of 6m from a sensitive use, including any outdoor air intake of a sensitive use. Note: This condition does not authorise environmental nuisance under the Environmental Protection Act 1994. |
At all times |
| 34) Fuel Burning Any fuel
burning (e.g. for a backup power generator) is to be in accordance with the
following: - Maximum
installed capacity of 0.1MW or less; - Operating 100 hours per year or less;
and - Not involving coal
combustion. |
As indicated |
| 35) Hours of Operation Hours of operation for the Community use, Food and drink outlet, Shop and Office are limited as follows: - Food and drink outlet, Shop and Office: between 6am and 8pm. - Community use: between 6am and 10pm. - Delivery hours are to be limited between 7am and 6pm. |
At all times |
| 36) Outdoor Communal Areas - Access Hours The following communal open space areas are limited for use between 6am and 10pm: - The outdoor gym, wellness area and plunge pools on Level 11. - The pool and pool deck on Level
12. - The outdoor areas on Level 15. |
At all times |
| 37) Acid Sulfate Soils Submit for the approval of
Development Services, an Acid Sulfate Soils (ASS) Investigation
Report and Management Plan, where soil disturbance (e.g filling, excavation,
drainage works, stripping of topsoil) is greater than 100m3 and the
disturbance level is equal to or less than 5mAHD. The ASS Management Plan must
detail management measures of possible impacts of soil disturbance and
demonstrate the disturbance impact will be appropriately managed. Prepare the
ASS Investigation Report and Management Plan in accordance with the
Potential and Actual Acid Sulfate Soil Overlay Code and
associated Planning Scheme Policy. The Report and Management Plan are to be prepared by a suitably
qualified and experienced professional, with the following qualifications: |
Prior to site/operational/building work commencing |
37(a) Implement Plan Implement and maintain the provisions of the approved 'Acid Sulfate Soil Management Plan'. |
While site/operational/building work is occurring |
37(b) Certification Submit to Development Services certification from a Registered Professional Engineer Queensland, that the measures recommended in the Acid Sulfate Soils (ASS) Management Plan have been implemented into the development. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 38) Mechanical Plant or Equipment - Acoustically
Screened Mechanical plant or equipment is to be acoustically screened from an adjoining sensitive use. Mechanical plant includes generators, motors, compressors and pumps such as air-conditioning, refrigeration and cold room motors. Acoustically screened is defined in City Plan 2014. NOTE: This condition does not authorise environmental nuisance under the Environmental Protection Act 1994. PROOF OF FULFILMENT Submit to Development Services, certification that all mechanical plant or equipment, is acoustically screened. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 39) No Amplified Music Amplified sound or music is not
permitted for non-residential uses. |
At all times |
| 40) No External Dining or Entertainment Area There is to be no external dining or entertainment area for the non- residential uses. |
At all times |
| 41) Acoustic Fence - General Erect a 2m high
acoustic fence, (relative to the finished RL of the building pad) along the
side boundary interface with 11 Boundary Street as indicated in approved plan
titled Ground Floor with reference TP01.05 C received 3-NOV-2023 as amended in
red on 15-FEB-2024. The acoustic fence must: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
41(a) Certification Submit to Development Services certification from a person who is a Member or eligible to be a Member of the Australian Acoustic Society that the constructed acoustic fence complies with the above requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 42) On-site Erosion (Medium Risk) Manage on-site erosion and the release of sediment or sediment laden water from the site at all times by implementing best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version). Timing: Prior to commencement of any land disturbing activities and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
42(a) Manage earth disturbance on-
site (i) Drainage control measures must be implemented and maintained to minimise water flow onto areas of exposed earth. (ii) Sediment and erosion control measures must be implemented and maintained to prevent soil loss from earth disturbance areas and prevent deposition beyond earth disturbance areas. (iii) No release of contaminants to land beyond on-site area of earth disturbance other than releases that achieve water pollutant concentration release limits of: A. 50mg/L TSS (Total Suspended Solids); B. Turbidity, Nephelometric Turbidity Units (NTU) value less than 10% above background, 75 NTU, or as agreed in writing by an Officer from Councils Erosion and Sediment Control (ESC) Team in Compliance and Regulatory Services; C. pH between 6.5 and 8.5 at all times. (iv) Maintain a written record to demonstrate that water discharges from the site, including any dewatering operations, meet the release limits as detailed in (iii) for water discharge(s) from the site that occur during or immediately after a rainfall event, and during normal business hours. The water quality of the discharge flows must be measured at each discharge point from the site, including but not limited to sediment basin outlets, other applicable sediment control devices, the site water drainage system, and recorded against the release limits at least once on each calendar day until such discharge stops. Timing: Prior to commencement of any earth disturbing activities and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
42(b) Provide Land Occupier Notification to
Council (i) Notify Council's ESC Team of proposed land occupier/s by sending an email to CARS-ESC@Brisbane.qld.gov.au (ii) If the land is to be occupied by any person other than the registered landowner then advice must be provided to Council that confirms the name, contact information and the duration of any proposed occupation of the land. Timing: Prior to commencement of any earth disturbing activities. |
As indicated |
42(c) Prepare Erosion and Sediment Control
Plan Prepare an Erosion and Sediment Control Plan (ESCP) in accordance with best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version) and, to the extent of any inconsistency, relevant Brisbane Planning Scheme Codes and Policies. Obtain a design certificate in accordance with the relevant Brisbane Planning Scheme Codes and Policies. The ESCP and design certificate must be certified by a Certified Professional in Erosion and Sediment Control (CPESC) or a Registered Professional Engineer Qld (RPEQ) with suitable qualifications and experience in erosion and sediment control. Documentary evidence demonstrating appropriate qualifications in erosion and sediment control must be provided to the Council upon request. Timing: Prior to the commencement of any earth disturbing activities. |
As indicated |
42(d) Attend a pre-start
meeting Arrange and attend a pre-start meeting for ESC with an Officer from Councils ESC Team in Compliance and Regulatory Services (CARS). Note: To request a pre-start meeting from Council's ESC Team send an email to CARS-ESC@Brisbane.qld.gov.au. All relevant documentation, including both the certified ESCP and the certified design certificate, must be attached to this email. Please allow up to 10 business days for your request to be processed. Timing: Attend the pre- start meeting prior to the commencement of any earth disturbing activities. |
As indicated |
42(e) Implement Certified Erosion and
Sediment Control Plan Implement the certified ESCP and maintain all ESC measures in accordance with best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version) and, to the extent of any inconsistency, relevant Brisbane Planning Scheme Codes and Policies. The ESCP and design certificate must be available on site at all times for inspection by Council officers. Any alteration to supplementary or Type 3 ESC measures must be reflected in the certified ESCP. Any alteration to Type 2 or Type 1 ESC measures will require a revised ESCP and design certificate that has been certified by either the CPESC or RPEQ. Timing: While earth disturbing activities are occurring and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
| 43) Maintenance Period for Engineering Work Maintain the work required by the Engineering condition(s) imposed on this development approval and rectify any defects in accordance with the requirements detailed in this condition. Note: Guidance for requesting a pre-start and co- ordinating the On/Off Maintenance process can be found on Council's website (https://www.brisbane.qld.gov.au/planning-and-building/applying-and-post- approval/on-and-off-maintenance-approvals). Timing: During the on-maintenance period. |
As indicated |
43(a) On-Maintenance Acceptance Arrange an on- maintenance inspection with Development Services and obtain written confirmation from Council that the work has been completed in accordance with the requirements of the condition and is accepted on-maintenance. Provide proof of Public Liability Insurance ($20 million) for the on- maintenance period. Lodge a maintenance security for the on-maintenance period. The security must be calculated as 5% of the value of the constructed work or $10,000.00, whichever is greater. Note: A maintenance security may consist of either a bank guarantee or monetary payment lodged with Council. Refer to Council's Infrastructure Installation and Construction Requirements Manual for further details about the on-maintenance procedure and requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
43(b) On-Maintenance Period Provide a minimum 12 months maintenance to the work from the time the work is accepted on- maintenance by Council. During this period maintain the work and rectify any defects identified at the on-maintenance inspection and those arising during the on-maintenance period. Note: The on-maintenance period may be extended by Council pending concerns and/or unsatisfactory performance during the maintenance period. Timing: A minimum 12 months from acceptance on-maintenance. |
As indicated |
43(c) Off-Maintenance
Acceptance On completion of the maintenance period arrange an off-maintenance inspection with Development Services and obtain written confirmation from Council that the work is accepted off-maintenance. Ensure all defects are rectified prior to making an appointment for off- maintenance Inspection. Note: If the inspection is successful the maintenance security will be released. Timing: On completion of the on-maintenance period. |
As indicated |
| 44) Information Signage Erect an information sign on the subject property in
accordance with Council's general requirements for signage and in accordance
with the requirements outlined below: Timing: Prior to site works commencing and then to be maintained until completion of the development for all stages. |
As indicated |
| 45) Engineering Pre-Start Meeting Arrange and attend a pre-start meeting with Development Services and Program Planning and Integration. Applicable compliance and inspection fees must be paid, in full, to Council prior to the meeting being held. Note: To arrange an engineering pre-start meeting with Development Services an email supported by a completed copy of the Pre-Start Meeting Guidelines - Civil Engineering Works kit (https://www.brisbane.qld.gov.au/sites/default/files/20191008-cc11207-pre- start-meeting-guidelines-civil-engineering-works.pdf) must be sent to dalodgement@brisbane.qld.gov.au. Details include (but
are not limited too) the following: Note: Timing: Prior to site/operational/building work commencing. |
As indicated |
| 46) Filling and / or Excavation All earthworks must be carried out in accordance with the relevant Brisbane Planning Scheme Codes.
|
Prior to building work commencing |
46(a) Submit Earthworks
Drawings Where applicable, where the site is utilising temporary Rock and Ground Anchors as the basement excavation support system, earthworks plans are required to be submitted to Development Services, together with the temporary rock and ground anchors system, to obtain approval of the earthworks drawings, prepared and certified by a Registered Professional Engineer Queensland, in accordance with the approved DRAWINGS AND DOCUMENTS and the relevant Brisbane Planning Scheme Codes. The Earthworks Drawings
must include the following: Note: If the earthworks impact on the road reserve, the Developer must obtain applicable footpath and road permits prior to commencing any works. Such impacts may include footpath occupation, road closures, re-profiling, ground anchors and/or relocation of services. If the excavation has to be stabilised using ground anchors or similar, then the submitted plans must show the location of these in relation to all services. The cost of moving services, utilities and assets is the responsibility of the Developer. The permission of the service/utility/asset owner is required. Note: Irrespective of final earthworks, it is the responsibility of the RPEQ to manage any staged works associated with Erosion & Sediment Control. Timing: Prior to site/operational/building work commencing. |
As indicated |
46(b) Fill Material, Placement, Compaction
and Testing All fill material placed on the site must comprise only natural earth and rock and must be free of contaminants (as defined by Part 3, Division 2, Subdivision 2 Environmental contamination, Section 11 of the Environmental Protection Act 1994) and noxious, hazardous, deleterious and organic materials. Fill material, placement, compaction and testing must comply with the requirements of Australian Standard - AS 3798, Guidelines on Earthworks for Commercial and Residential Developments. Timing: While site/operational/building work is occurring. |
As indicated |
46(c) Implement Approved Earthworks
Drawings Construct and maintain the earthworks in accordance with the requirements of AS3798 and the approved earthworks drawings. Timing: While site/operational/building work is occurring and then to be maintained. |
As indicated |
46(d) Submit As Constructed
Drawings Submit to Development Services As Constructed drawings prepared by a Registered Surveyor. Timing: Prior to building work above ground commencing. |
As indicated |
46(e) Submit Certification Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the approved earthworks drawings. Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that all fill material used complies with the quality requirements of this condition and that placement, compaction and testing has been carried out in accordance with AS3798. Timing: Prior to building work above ground commencing. |
As indicated |
| 47) Basement Excavation and Support Basement excavation and support of all exposed walls must be carried out in accordance with the relevant Brisbane Planning Scheme Codes and the requirements of this condition. |
Prior to building work commencing |
47(a) Prepare Engineering
Drawings Engineering drawings for the work required by this condition must be prepared and certified by a Registered Professional Engineer Queensland (Structural), in accordance with the relevant Brisbane Planning Scheme Codes detailing the design of the proposed excavation as well as proposed temporary and permanent support (if no temporary proposed) systems. The design must include at least the following: Notes: Timing: Prior to site/operational/building work commencing. |
As indicated |
47(b) Implement Certified Engineering
Drawings Construct and maintain the basement excavation and proposed support system in accordance with the above certified engineering drawings. Note: A copy of the certified engineering drawings must be available on- site for inspection by Council Officers during these works. Timing: While basement excavation and support system installation is occurring. |
As indicated |
47(c) Submit Post Construction
Certification Submit certification by a Registered Professional Engineer Queensland that the basement excavation and support have been installed in compliance with the certified engineering drawings, the relevant Brisbane Planning Scheme Codes and the requirements of this condition. Where ground or rock anchors have been installed, submit certification by a Registered Professional Engineer Queensland (Geo-technical) that all anchors have been de- stressed. Timing: Prior to building work commencing above ground. |
As indicated |
| 48) CBD/City Frame Construction Management Plan Carry out development in accordance with a Construction Management Plan (CMP) prepared in accordance with the Central Business District and City Frame Development Services Construction Management Guidelines and the requirements set out in this condition. Note: This condition imposes restrictions on development construction management to regulate increased truck access, on street work zone and closures and all associated activities in the CBD and City Frame as a result of major State and Local Government infrastructure projects occurring in Brisbane.
|
While site/operational/building work is occurring |
48(a) Submit Construction Management
Plan Submit to, and obtain approval from, Development Services a Construction Management Plan for the demolition, excavation and construction phases of the approved development. Separate Construction Management Plans may be appropriate for the individual components. The Construction
Management Plan must be in accordance with the Central Business District and
City Frame Development Services Construction Management Guidelines and the
relevant Brisbane Planning Scheme Codes and address the following: (ii) Existing and proposed kerbside allocation signs and line marking (such as bus stops, loading zones and parking meters and/or ticket dispensers); (iii) Location of and impacts to any Council or other public utility or local authority's assets on or within external to the site; (iv) Details of all proposed work zones and/or lane closures, including justification; (v) Location and design of temporary vehicular construction access points, including frequency of use; (vi) Management and mitigation strategies for the impact of dust, noise and vibration upon adjoining and nearby properties; (vii) Provision for loading and unloading of materials including the location of any remote loading sites; (viii) Location of materials, structures, plant and equipment to be stored or placed on the construction site; (ix) Location of proposed external hoardings and/or gantries, and including clearances to the impacts of this on existing street furniture and other footpath assets located within the verge as well as impacts on any existing advertising signage located either along or adjacent to the site frontage - this includes any potential obstruction of sight lines for such advertising (e.g. bus stops with advertising); (x) Location of proposed employee and visitor parking areas; (xi) Anticipated staging and programming; (xii) Impacts of any actions proposed to address any of the above items or any actions resulting from construction of the development that will impact on existing street trees; (xiii) Complaint management processes to be implemented; and (xiv) Compliance with the Management Plans Planning Scheme Policy and other relevant Planning Scheme Policies. Note: Pre-approval of work zones and/or lane closures associated with construction of the development will be managed by Development Services however the Construction Management Plan must be supported by "approvals in principle" or written approvals from other relevant Council sections or other governing bodies responsible for any other potentially impacted infrastructure. Timing: Prior to site/operational/building work commencing. |
As indicated |
48(b) Construction Management Plan -
Dilapidation Report Submit a dilapidation report to engineeringservices@brisbane.qld.gov.au detailing the pre-existing condition of the roadway, both footways, both verges and Council infrastructure, including vegetation, for 100m from the site entry in both directions or to the next street intersection (if less than 100m from the site entry) in both directions. Timing: Prior to the pre-start meeting. |
As indicated |
48(c) Construction Management Plan -
Associated Activities in Road Reserve Obtain relevant approvals, as listed in part (a) of this condition, to carry out any works within the road reserve required by the approved Construction Management Plan identified in the Central Business District and City Frame Development Services Construction Management Guidelines. Note: All fees must be paid in full prior to any permit being granted by Council. Council may revoke any permits at any time for non-compliance with requirements or if it considers that safety, capacity and/or operation of public transport, vehicle and pedestrian traffic are likely to be compromised during the construction phase. Timing: Prior to site/operational/building work commencing. |
As indicated |
48(d) City Frame Construction Management Plan
- Documentation on Site Legible copies of the approved CBD Construction Management Plan and current permits must be kept on site and be made available on request At all times. The requirements of the CMP must be included in all induction of principal and subcontractors utilised in the development. An outline of the induction provided to contractors may be requested by Council to confirm compliance with this condition. Timing: While site/operational/building work is occurring. |
As indicated |
48(e) Construction Management Plan - Works to
be Performed Out of Hours Obtain an approval from Development Services for any
work that is proposed to be undertaken outside of normal business hours -
6:30am to 6:30pm, Monday to Saturday. |
As indicated |
48(f) Implement Approved Construction
Management Plan Carry out the development in accordance with the approved CBD/City Frame Construction Management Plan. |
While site/operational/building work is occurring |
| 49) Protect Existing Infrastructure Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure. Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations. The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements. |
While site/operational/building work is occurring |
49(a) As Constructed Drawings - Alterations
to Existing Infrastructure Submit to Development Services As Constructed drawings showing all new and/or rectification works and an asset register, prepared by a Registered Professional Engineer Queensland. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 50) Rock and Ground Anchors - Temporary Where applicable, where the site is utilising temporary Rock and Ground Anchors as the basement excavation support system, the utilisation of the temporary rock and/or ground anchors must be in accordance with an approved anchor management plan that complies with relevant Brisbane Planning Scheme Codes and includes the following: - Anchors are not located closer than 1.2m to existing Council or other public utility infrastructure. - Provision for both pre and post construction CCTV survey of pipe lines adjacent to the site. Pre-construction CCTV inspection of all pipes in the vicinity of anchors must be carried out prior to the commencement of site works. Post-construction CCTV inspection of all pipes in the vicinity of the anchors must be carried out within one month after de-stressing of anchors. CCTV surveys must be carried out using a camera with the capacity to pan and tilt. Digital reports and videos of the inspections must be submitted to Development Assessment. - Provision of geotechnical/structural certification that the construction phase building loads and the final building loads will not impact or endanger Council's infrastructure. This must include demonstration of the effect of the loads imposed by the pressure bulb, both prior to the de-stressing of the temporary anchors and upon final completion of the building. - Provision of a geotechnical report which relates to the position of anchors, and includes geological information and borehole data. - Submission of documentation of the approval of any adjacent property owners where the anchoring system is proposed to encroach into neighbouring properties. - Submission of approval from the providers of affected services as well as a plot of the level and alignment of these services on the sections and plans. - Provision of an emergency management plan that includes procedures to reinstate any services that may be damaged as a result of works on the site. - Piers and drainage system located wholly within the property. - Structural certification for retaining walls greater than 1.0m in height. |
While site/operational/building work is occurring |
50(a) Submit Anchor Management
Plan Submit to, and obtain approval from, Development Services, in
conjunction with the Earthworks Drawings, required by the Filling &
Excavation Condition, an Anchor Management Plan designed and certified by
a Registered Professional Engineer Queensland in accordance with this condition
and the relevant Brisbane Planning Scheme Codes, including the following
drawings and details: Note: Permanent anchors will not be approved. Only bored piles will be approved. Timing: Prior to site/operational/building work commencing. |
As indicated |
50(b) Implement Approved Anchor Management
Plan Implement the approved Anchor Management Plan in conjunction with the approved earthworks drawings. Timing: While site/operational/building work is occurring. |
As indicated |
50(c) Post Construction
Certification Submit to Development Services certification by a Registered Professional Engineer Queensland that the approved Anchor Management Plan has been implemented in accordance with this condition and that the construction phase building loads and the final building loads will not impact or endanger infrastructure. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate. |
As indicated |
| 51) Retaining Walls Design and construct all retaining walls and associated fences, in accordance with the relevant Brisbane Planning Scheme Codes and the following: - All retaining walls including the footings, must be located wholly within the property boundaries of the site where works are occurring - Runoff from surface drains and subsoil drainage associated with the retaining walls must be collected and connected to a lawful point of discharge (LPD) where possible. If no LPD is available the surface drains and sub-soil drainage must be designed, installed and discharged to ensure there is no ponding, nuisance or concentration of stormwater discharge to adjacent properties. - Retaining walls to stabilise excavation must be set back from property boundaries to accommodate subsoil drainage without encroachment into the neighbouring property. This set back may vary depending on the height, structure and design of the retaining wall, surcharge loadings from neighbouring properties, and to provide a surface drain along the top of the retaining wall - For retaining walls in excess of
1.0m in height: NOTE: Refer to City Plan 2014; Infrastructure Design Planning Scheme Policy (IDPSP) for Council’s definition of a LPD. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
51(a) Certification of Retaining
Walls For retaining walls over 1.0m in height, obtain certification from a Registered Professional Engineer Queensland that the design and construction of the retaining walls and ancillary drainage are in accordance with the requirements of this condition. |
As indicated |
| 52) Repair Damage to Kerb, Footpath or Road Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
52(a) Interim Repairs If at any time during the construction phase of the approved development, damage to the existing kerb and channel, footpath or roadway creates unsafe, unreasonable and/or not fit for purpose conditions as assessed by Council, interim repairs must be undertaken as directed by Program Planning and Integration. Note: Any interim repairs required to be undertaken shall not be considered to satisfy the requirements of this condition for the permanent repair of the infrastructure prior to the issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. Timing: While site / operational / building works is occurring. |
As indicated |
| 53) Access, Grades, Manoeuvring, Carparks, Signs and
Line Marking i. A pavement of minimum Local road standard or equivalent surface material (including associated drainage) to the area on which motor vehicles will be driven and/or parked. ii. Manoeuvring on site for an RCV and for the loading and unloading of the vehicle; iii. Parking on the site for a total of 193 cars, of which 179 are for resident/tenant cars, and 16 are for visitor cars, including 1 parking space for people with disabilities, and areas for the loading and unloading of vehicles within the site. iv. Provide and maintain 101 secure bicycle parking spaces for residence and a minimum of 26 for visitors. v. A minimum of 2.3 metres height clearance to all undercover parking areas and a minimum of 2.5 metres above parking spaces for people with disabilities are to be provided, except for the localised car parks below the ramps in the basement, that are provided with 2.2 metres clear height. However, no services ducting is to be constructed over the car parking spaces that would further reduce the height clearance. The minimum clear height must be measured to the lowest protrusion from the ceiling (e.g. fire sprinklers, services, lighting fixtures, signs, etc). vi. A height clearance sign located at the entrance to undercover car parking areas and a directional visitor parking sign clearly visible from the vehicle entrance to the site. vii. An appropriate area for the storage and collection of refuse, including recyclables, in a position which is accessible to service vehicles on the site. viii. Prepare and implement signs and line marking drawings that show the internal paved areas signed and delineated in accordance with the approved drawings and documents, including Line Marking and Stop Sign to be installed, just within the frontage boundary, on out-bound side facing motorists exiting the site. The drawings must be prepared and certified by a Registered Professional Engineer Queensland in accordance with the relevant Brisbane Planning Scheme Codes and the Manual of Uniform Traffic Control Devices. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland, that the above requirements have been implemented in accordance with this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 54) Flood Emergency Management Plan Prepare, implement and maintain a Flood Emergency Management Plan (FEMP) in accordance with the requirements of this condition. Note: Guidance for the preparation of drawings and/or documents to comply with this condition is provided in the Flood Planning Scheme Policies. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
54(a) Prepare and Certify a Flood Emergency
Management Plan Submit to Development Services a Flood Emergency Management Plan (FEMP) for the approved development prepared and certified by a Registered Professional Engineer Queensland with experience in flood risk management. Timing: Prior to issue of Certificate of Occupancy/Final Inspection. |
As indicated |
| 55) Essential Services within Basements Where essential services are located within a basement or room located below the highest flood level affecting the site in an area affected by the Brisbane River Flood Planning areas or Creek/Waterway Flood Planning areas, the building is to be designed and constructed to provide either: i) A completely watertight tanked basement with walls and floors designed by a Registered Professional Engineer Queensland (Structural) to resist hydrostatic pressures expected during a 1% AEP River or Creek/waterway flood event, or a 1% AEP stormtide flood event. OR ii) A subsoil drainage system and pump system designed by a Registered Professional Engineer Queensland and constructed to prevent the basement from flooding and meet the following: a) The pump system is to utilise a duty and standby pump system that is sized to manage the expected sub-surface flow rate resulting from flooding at the highest defined flood event and/or tidal waters (where applicable) b) The pumps are connected to a backup power supply that is located above the highest defined flood level. The backup power supply is not to be located in the basement. c) The backup power supply is to be a battery (ideally connected to a solar system that can operate with mains power disconnected to recharge and run pumps and other essential services), fuel or gas power source. The battery capacity, generator size and/or fuel storage must be sufficient to run the pumps for a minimum 48h period where the site is affected by the Brisbane River Flood Planning areas. Where fuel storage is required it must be clearly shown on plans and volume specified. Notes: Essential electrical services include any area or room used for fire control panel, telephone PABX, sensitive substation equipment including transformers, low voltage switch gear, high voltage switch gear, battery chargers, protection control and communication equipment, low voltage cables, high voltage cables, lift motors, car stackers, and lift or pump controls. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
55(a) Certification to the Private Building
Certifier Provide to the Private Building Certifier, certification from a Registered Professional Engineer Queensland (Structural) that the basement has been designed and constructed to ensure structural integrity during a defined flood event, and in accordance with the requirements of this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
55(b) Certification to Council Submit to Council certification by a Registered Professional Engineer Queensland that the stormwater, subsoil drainage, pump and backup power supply has been designed and constructed in accordance with the requirements of this condition in order to prevent the basement from flooding during a 1% AEP River or Creek/waterway flood event, or a 1% AEP stormtide flood event. Note: This certification is required to be provided where a subsoil drainage and pump system has been provided in lieu of a tanked, watertight basement. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 56) Refuse Collection - On Site Provide for the installation and collection of refuse/recycling bins by Brisbane City Council's Waste and Resource Recovery Services for residential waste and a private waste contractor for non-residential or commercial waste. |
At all times |
56(a) Arrange Refuse Collection Arrange for the installation of refuse/recycling bins and for the subsequent collection of refuse including recycling from the site by Brisbane City Council's Waste and Resource Recovery Services and a private waste contractor. Timing: A minimum of four weeks prior to the commencement of use and then to be maintained. PROOF OF FULFILMENT Where a private waste contractor is engaged, provide written confirmation from the proposed waste collection contractor of the agreement to service the property. The written agreement must be submitted to Council's Waste and Resource Recovery Services and include full details of the proposed system, bin sizes, number of bins, frequency of collection and the refuse collection vehicle size. Timing: Prior to commencement of use. |
As indicated |
56(b) Indemnify Council The owner and any subsequent owner must, by approved form to Waste and Resource Recovery Services, indemnify Council and its agents in respect of any damage to the pavement and other driving surfaces. Timing: When an arrangement for refuse/recycling collection services is made with Brisbane City Council. |
As indicated |
56(c) Notify Future Owner Where Council is engaged as the waste contractor, the owner must notify any future owner/body corporate that the development has been approved on the basis that an indemnity must be provide for refuse collection vehicles to enter the property. Timing: At time of a change of ownership. |
As indicated |
| 57) Refuse Storage - On Site Collection Provide a roofed and wholly screened refuse enclosure utilising materials consistent with the development or a dedicated refuse storage room, as shown on the approved plans and documents. The enclosure/refuse storage room between residential waste and commercial waste must be segregated from each other, and must be of a design to accommodate the quantity of refuse and recycling including source separation to allow for low servicing collection of the development. Bins must be located in an area which allows them to be manoeuvred from the bin storage area to the designated internal collection point. The trellis proposed on the site must be maintained with a minimum 3.6 metre height clearance in order not to impede movement of RCV.
|
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 58) Work for Transport Network - Road (Non-trunk) -
Self Certification Construct the following work to widen the Transport Network (Road) along the full frontage of the site generally as shown on the approved On-Street Parking Plan No. B23024-SK-005-Sheet A1., prepared by Lambert & Rehbein dated 23 June 2023, and in accordance with the relevant Brisbane Planning Scheme Codes, the Manual of Uniform Traffic Control Devices and the AUSTROADS design standards: - Relocate signs & line marking for on-street parking in Bank Street
frontage of the site, and any associated provision, relocation or modification
of services, other signs and line marking. - Land dedication to achieve 5m wide verge Mollison Street frontage and 3.75m wide verge Bank Street frontage. Note: This condition is imposed under section 145 of the Planning Act 2016. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
58(a) Prepare Engineering
Drawings Engineering drawings for the work required by this condition must be prepared and certified by a Registered Professional Engineer Queensland in accordance with the relevant Brisbane Planning Scheme Codes and the Manual of Uniform Traffic Control Devices and the AUSTROADS design standards. Timing: Prior to site/operational/building work commencing. |
As indicated |
58(b) Implement Certified Engineering
Drawings Construct the works in accordance with the above certified engineering drawings. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
58(c) Submit As Constructed
Drawings Submit to Development Services As Constructed drawings including an asset register, prepared by a Registered Professional Engineer Queensland. Note: To be submitted via DA- ComplianceEngineering@brisbane.qld.gov.au and include the site address, A00 reference and Condition number in the subject line. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the above certified engineering drawings. Note: where required, this includes QA documentation, CCTV, etc. |
As indicated |
| 59) Site Drainage - Major Provide an internal drainage system to collect stormwater run-off from all proposed roofed and developed surface areas and any run-off onto the site from adjacent areas and convey the collected run-off to the existing stormwater drainage infrastructure at Mollison or Bank Street frontage of the site for lawful point of discharge, in accordance with the relevant Brisbane Planning Scheme Codes. Notes: - Where external works are required and
infrastructure will be handed over to Council (e.g. Stormwater pipes 375mm or
greater and/or manholes within the road reserve, etc), the applicant will be
required to request an on-site Pre-Start with Council and ensure all future
owned Council assets follow the On/Off Maintenance process in accordance with
Councils Infrastructure Installation & Construction Requirements
Manual. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
59(a) Submit Site Drainage
Drawings Submit to, and obtain approval from, Development Services, site drainage drawings and engineering calculations, prepared and certified by a Registered Professional Engineer Queensland, in accordance with the relevant Brisbane Planning Scheme Codes. Notes: -
Queensland Building and Construction Commission licensed hydraulic
consultants may design the stormwater system for sites less than 2000m2 with an
upstream catchment servicing no more than 4 residential lots. This
excludes stormwater drainage design (including subsoil drainage) of basements
in flood planning areas and the design of any onsite stormwater detention
system Timing: Prior to site/operational/building work commencing |
As indicated |
59(b) Implement Approved
Drawings Carry out the works in accordance with the approved site drainage drawings. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
59(c) Submit As Constructed
Drawings Submit to Development Services As Constructed drawings prepared and certified by a Registered Professional Engineer Queensland or a Queensland Building and Construction Commission licensed hydraulic consultants (where applicable). Note: To be submitted via DA- ComplianceEngineering@brisbane.qld.gov.au and include the site address, A00 reference and Condition number in the subject line. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland or Queensland Building or Construction Commission licensed hydraulic consultants (where applicable) confirming that the works have been completed in accordance with the above stormwater drawings. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 60) Telecommunications Submit to Development Services, certification from
an authorised telecommunications carrier/contractor, that the following works
and infrastructure have been undertaken and installed in accordance with
telecommunications industry standards: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 61) Agreement with Electricity Supplier Submit to Development Services, evidence of an agreement with an electricity supplier to provide necessary services to the development in accordance with the relevant Brisbane Planning Scheme Codes. Where development is within an established area of overhead electricity supply and the electricity supplier determines that a property pole is the appropriate solution to supply electricity to the development, the developer must be responsible for the installation of the property pole(s). In the above circumstances, submit to Development Services, certification from the developer's electrical consultant confirming that the above installation has been completed in accordance with the relevant AS/NZS Standards and the Queensland Electricity Connection Manual (QECM) and Queensland Electricity Metering Manual (QEMM). |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 62) Permanent Driveway Crossover Provide a 6.5 metre wide Type B1 permanent driveway crossover to the Bank Street frontage of the site, including a 2.5 metre x 2.0 metre Sight Splay Triangle on the exit side of the crossover, in accordance with the relevant Brisbane Planning Scheme Codes and located as shown on the approved DRAWINGS AND DOCUMENTS. Written consent must be obtained from BCC - Field Services, Program Planning and Integration Arborist prior to any works occurring that will either impact on or require removal of a street tree (this includes pruning and excavation within the root zone/canopy of the tree) At all times during construction of the crossover, safe pedestrian access along the site frontage must be maintained. Note: No further driveway permit is required however additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 63) Redundant Driveway Crossover Remove any redundant existing driveway crossover(s) on the frontage(s) of the site and reinstate the kerb and channel, road pavement, footways and footpaths in accordance with the relevant Brisbane Planning Scheme Codes. Note: Additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 64) Construction Noise and Dust Emissions Pursuant to the Environmental
Protection Act 1994, all development involving the emission of noise and dust
from building and/or construction activities, must ensure that the emissions
are in accordance with the requirements of the Act. |
As indicated |
| 65) Management of Asbestos Disposal, handling and restoration of any building materials containing asbestos must be in accordance with current state and federal legislation. |
As indicated |
| 66) Further Development Permit Required Further Development Permit(s) to carry out assessable building work under the Building Act may be required. |
As indicated |
| 67) Currency Period The currency period for this development approval is stated in the Decision Notice and is expressed as a date. This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016. |
As indicated |
| 68) Damage to Trees on Adjoining Land Please note that any damage caused to vegetation on adjoining land as a result of exercising this development approval may result in an offence under other legislation (e.g. Natural Assets Local Law) and/or civil action |
As indicated |
| 69) Fire Ant Movement Controls To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected. These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products. Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014. For further information contact the relevant Queensland State Government department on 13 QGOV. |
As indicated |
| 70) Water and Wastewater Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. For further information about any necessary Water Approvals contact Urban Utilities. |
As indicated |
| 71) Flood Resilience and Awareness This advice is provided for buildings that are on sites that are subject to the flood overlay, as shown within City Plan 2014. Council makes decisions to minimise flood risk based on the best information available at the time of the development application. Flood studies and applicable flood levels may be updated by Council overtime where new flood information is available or changes to engineering standards/methodology have occurred. Flood levels for various flood events and flooding types are outlined in Council's Floodwise Property Reports available from Councils website. The minimum flood planning levels that apply to new development do not necessarily mean that the development will never flood. Therefore, when choosing materials for building on sites that are known to be affected by flooding, regardless of whether it is constructed to the minimum flood planning level, it is recommended that flood resilient materials are used to improve the speed of recovery and reduce the cost of repairs if required. For more information refer to: Council's website at https://www.brisbane.qld.gov.au/community-and-safety/community- safety/disasters-and-emergencies/be-prepared/flooding-in-brisbane/flooding- support-for-residents/flood-resilient-homes-program Queensland Reconstruction Authority "Flood Resilient Building Guidance for Queensland Homes"https://www.qra.qld.gov.au/resilient- homes/flood-resilient-building-guidance-queensland-homes |
As indicated |
| 72) Cultural Heritage Aboriginal cultural heritage is protected under the Aboriginal
Cultural Heritage Act 2003. This Act establishes a cultural heritage duty
of care and in section 23(1) mandates that a person who carries out an activity
must take all reasonable and practicable measures for ensuring activities are
managed to avoid or minimise harm to Aboriginal cultural
heritage. The Duty of Care Guidelines gazetted pursuant to the Aboriginal
Cultural Heritage Act 2003 provide guidance on identifying and protecting
Aboriginal cultural heritage to fulfil the duty of care. For further information contact the
relevant Queensland State Government Department (Department of Aboriginal and
Torres Strait Islander Partnerships). |
As indicated |
| 73) In Principle support for street tree interference
or removal As street trees are protected vegetation, the interference with or removal of these trees requires a permit under the Natural Assets Local Law (NALL), issued by Program Planning and Integration (PPI). Development Services has sought preliminary advice from PPI regarding the identified removal/interference with existing street tree/s. Removal/interference with 1 existing street tree identified on the approved plans where shown as conflicting with the approved crossover fronting Bank Street is supported in principle for this development at this time. However, a separate NALL permit is required. Detailed arrangements must be made with PPI in relation to the works carried out on protected vegetation (including provision for tree removal and replacement tree planning costs as determined by the Arboriculture Team) prior to carrying out any works on protected vegetation. PPI Arboriculture Team can be contacted via BI-CS-PPI-PLANNING- ARB@brisbane.qld.gov.au. Note: All requirements of development approval conditions with timing stipulated as 'prior to site works commencing' (or equivalent) must be fulfilled before Council can issue a NALL permit. |
As indicated |