| Address of Site: | 317 STAFFORD RD STAFFORD QLD 4053 |
| Real Property Description of Site: | L1 RP.158655 |
| Aspects of development and type of approval: | DA - PA - Material Change of Use Development Permit - warehouse,shop,food
and drink outlet,health care service DA - PA - Building Work Development Permit - warehouse,shop,food and drink outlet,health care service |
| Council File Reference: | A006915428 Permit Reference Number/s: DAMC404164621; DABW418737422. |
| Package Status: | APPROVED - Version 3 (12th of June, 2026 3:19:43 PM) |
| Package Generated: | 23/06/2026 |
| Bijal SHAH Senior Urban Planner Planning Services North bijal.shah@brisbane.qld.gov.au (07) 31789229 |
Joe MCSHANE Principal Urban Planner Planning Services North CPAS-DS-PS-North@brisbane.qld.gov.au (07) 3407 1306 |
Tamara BERGMANS Urban Planner City Planning tamara.bergmans@brisbane.qld.gov.au 31780720 |
| Kathy BAGULEY Principal Urban Planner Planning Services North DSPlanningSupport@brisbane.qld.gov.au 07 3403 5510 |
Katrina KONTOS Environmental Management Officer Environmental Management Services katrina.s.kontos@brisbane.qld.gov.au (07) 3403 8888 |
Jolanta KRAWUS Principal Engineer, Development Assessment Engineering Scoping jolanta.krawus@brisbane.qld.gov.au 34036190 |
| Radmila SUBOTIC Senior Landscape Architect Landscape Architecture Team Radmila.Subotic@brisbane.qld.gov.au 31780113 |
Elrico KOEBERG Senior Urban Planner Planning Services North Elrico.Koeberg@brisbane.qld.gov.au (07) 3178 7346 |
Margaret ORR Team Manager Planning Services South margaret.orr@brisbane.qld.gov.au (07) 34070751 |
| Mark MARKONDA Engineer Engineering Compliance Mark.Markonda@brisbane.qld.gov.au (07) 340 35447 |
Kaye ATKINS Team Manager Planning Application Review Service Kaye.ATKINS@brisbane.qld.gov.au (07) 31780015 |
DRAWINGS AND DOCUMENTS
| Drawing or Document | Number | Plan Date |
|---|---|---|
| Traffic Statement | 1842_MEW10 | 15-AUG-2023 (Received) |
| Lower Level - Basement Carpark | SD-02 Issue E (Amended In Red 16-FEB-2022) | 16-AUG-2021 (Received) |
| Upper Level - Ground Floor | SD-03 Issue E (Amended In Red 16-FEB-2022) | 16-AUG-2021 (Received) |
| Planting Calculation | SD-04 Issue E | 16-AUG-2021 (Received) |
| Landscape Sections | SD-05 Issue E | 16-AUG-2021 (Received) |
| Landscape Sections - Pg 2 | SD-06 Issue E | 16-AUG-2021 (Received) |
| Indicative Planting Palette | SD-09 Issue E | 16-AUG-2021 (Received) |
| Minor Hydraulic Flood Report | 8974 | 13-DEC-2021 (Received) |
| Section 8.4 of Engineering Services Report | 8974 Page 18 of 30 | 16-AUG-2021 (Received) |
| Section 9 - Recommendations of Acoustic Report | R01J (Amended In Red 16-FEB-2022) | 04-FEB-2022 (Received) |
| Webster Road Perspective | SD0201 Issue D (Amended In Red 24-NOV-2023) | 15-AUG-2023 (Received) |
| Stafford Road Perspective | SD0202 Issue D (Amended In Red 24-NOV-2023) | 15-AUG-2023 (Received) |
| Site Plan | WD-1003 Issue B (Amended In Red 05-JUN-2026) | 03-DEC-2025 (Received) |
| Floor Plan - Lower Level | WD-2002 Issue K (Amended In Red 12-JUN-2026) | 10-JUN-2026 (Received) |
| Floor Plan - Upper Floor | WD-2003 Issue H (Amended In Red 05-JUN-2026) | 03-DEC-2025 (Received) |
| West and South Elevation | WD-3002 Issue D (Amended In Red 05-JUN-2026) | 03-DEC-2025 (Received) |
| North and East Elevations | WD-3001 Issue C (Amended In Red 05-JUN-2026) | 03-DEC-2025 (Received) |
| Roof Plan | SD2101 Issue D | 15-AUG-2023 (Received) |
| Sections | SD3101 Issue D (Amended In Red 24-NOV-2023) | 15-AUG-2023 (Received) |
| Detail Sections | SD3102 Issue C (Amended In Red 24-NOV-2023) | 15-AUG-2023 (Received) |
| Undercroft Stormwarter Layout Plan | SK010 Revision A | 16-AUG-2021 (Received) |
| Contents Page | SD-01 Issue E | 16-AUG-2021 (Received) |
APPROVAL CONDITIONS
| Permit to Which These Conditions Relate: | DA - PA - Material Change of Use |
| Activity(ies): | warehouse health care service food and drink outlet shop |
| Stage: | Health Care Service, Food and Drink Outlet, Shop and warehouse |
| 1) Car Parking The car parking within the premises must be maintained exclusively for the ancillary use of the development. The parking must not be made available to the general public and there must not be signage erected on or in the vicinity of the site advertising the availability of car parking to the general public. |
At all times |
| 2) Maintain the Approved Development Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions. |
At all times |
| 3) Hours of Operation Hours of operation for the approved development must be in accordance with the following: Hours of operation, for the approved Shop and Food and drink outlet uses must be limited from 6:00AM to 8:00PM. Hours of operation, for the approved Warehouse use must be limited from 7:00AM to10:00PM. |
At all times |
| 4) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers. Note: This condition is imposed to ensure compliance with the conditions of development approval. |
While site/operational/building work is occurring |
| 5) Carry Out the Approved Development Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS. Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners. |
While site/operational/building work is occurring |
| 6) Complete All Building Work Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS. Note: Building work must also be completed in accordance with any other current development approval. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 7) Security Lighting Install and maintain a suitable system of security
lighting to operate from dusk to dawn within all areas where the public may
gain access, including car parking areas, building entrances and vegetated
areas |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 8) Limitation of Approval The Health Care Service is limited to a maximum of 18 staff members at any one time on site. The
Shop and warehouse use is limited to
activities associated with a Pharmacy The
Shop (Pharmacy), Food and Drink Outlet use and warehouse use must operate in
accordance with this approval and in conjunction with a Health Care Service use
on this site, at
all times. In the event the Health Care
Service use is discontinued on this site, the Shop (Pharmacy) Food and Drink
Outlet and warehouse use is to cease
immediately. |
To be maintained |
| 9) External Details External details of the building, facade treatment and external materials and finishes must be consistent with the approved DRAWINGS AND DOCUMENTS. Note: The requirement to use particular materials and finishes is imposed only for the purpose of achieving a built form outcome that displays architectural merit. Council has not assessed the materials and finishes for compliance with the Building Act, the Building Fire Safety Regulation, the Building Regulation, the Building Code of Australia, the Queensland Development Code, relevant Australian Standards, fire safety standards or any other relevant requirement of a statutory authority with regard to building work. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 10) Overall Height The overall height of the building(s) must be in accordance with the floor and roof levels and overall height shown on the APPROVED DRAWINGS AND DOCUMENTS. This condition should be read in conjunction with any other relevant condition requiring minimum height clearances for basement or undercover car parking and manoeuvring areas. |
While site/operational/building work is occurring and then to be maintained |
10(a) Submit Certification Submit to Development Services certification from a registered surveyor confirming that the 'as constructed' floor and roof levels and overall height are in accordance with the requirements of this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 11) Light Reflectivity and Solar (Heat)
Reflectivity Submit to Development Services documentary evidence that the level of light reflectivity from the glazing incorporated in the approved development does not exceed 20%. Timing: Prior to building work above ground level commencing. |
As indicated |
11(a) Install Glazing Install and maintain glazing in accordance with the above specification. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained. |
As indicated |
| 12) Driveway Material and Finishes Provide materials and
finishes to the driveway and external carparking
surfaces that reduce the visual impact of these areas when viewed from the
street. One or a combination of the following must be used: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 13) Awning Lighting System Install a lighting system to the underside of the awning over the footpath in accordance with the requirements of this condition. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
13(a) Submit Lighting Plan Submit to, and obtain approval, from Program Planning and Integration (City Lighting) a detailed Lighting Plan demonstrating that the under awning lighting complies with Australian Standard - AS/NZS 1158.3.1 - sub category P6, within - Road Lighting Part 3.1: Pedestrian area (Category P) lighting - Performance and installation design requirements and achieves glare control to ensure zero candelas (cd) at 90 degrees. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
13(b) Implement Approved Lighting
Plan Carry out the works in accordance with the approved Lighting Plan. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
13(c) Certification Submit to Program Planning and Intergration (City Lighting) certification from a licensed electrical contractor that the awning lighting has been installed in accordance with the approved Lighting Plan. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
As indicated |
13(d) Maintain the Work Maintain the awning lighting, (including operating costs) in accordance with the approved Lighting Plan from dusk to dawn. Timing: To be maintained. |
As indicated |
| 14) Screen Air Conditioning and Other Plant
Enclosures Install and maintain suitable screening to all air conditioning, lift motor rooms, plant and service facilities located at the top of or on the external face of the building and within the Private Open Spaces. The screening structures must be constructed from materials that are consistent with materials used elsewhere on the facade of the building. There must be no individual external air conditioning units. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 15) Streetscape Works - Subtropical Boulevard (Out of
Centre) Carry out
streetscape improvement works including concrete path (where required by this
condition), turf and street trees to the verge to a 3.75m wide Subtropical
Boulevard (Out of Centre) standard in accordance with the relevant Brisbane
Planning Scheme Codes, Brisbane Standard Drawings (BSD), the requirements of
this condition and the Infrastructure Design Planning Scheme Policy including
sections 3.7.4.2.2 and 3.7.5. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
15(a) Install Concrete Path Install a 1.8m wide
broom finished standard Portland grey concrete path. The edge of the path is to
be setback from the back of kerb 1.3m. The path is to transition to existing
paths on verges that adjoin the development. |
As indicated |
15(b) Submit As-Constructed
Drawings Submit to Development Services "As Constructed" plans
including an asset register, checked by a Registered Professional Engineer
Queensland, certifying that the concrete path works have been completed in
accordance with relevant Brisbane Planning Scheme Codes/Policies. |
As indicated |
15(c) Install Turf Install turf to the
full width of the verge excluding any concrete path required by this
condition. |
As indicated |
15(d) Street Tree(s) Contact the call centre
on 3403 8888 and request that Council undertake street tree planting in
accordance with the Infrastructure Design Planning Scheme Policy including
section 3.7.5 to the frontage of the development. Provide the call centre with
the Development Approval number and obtain a reference number for the phone
call for your record. |
As indicated |
| 16) Landscape the Site - Self Certification Landscape the site in accordance with the requirements of this condition. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
16(a) Detailed Landscape Plan for Self-
Certification Prepare a Detailed Landscape Plan at a scale of 1:100 for all on-site landscape works including planting areas identified on the approved DRAWINGS AND DOCUMENTS. The plan must be prepared by a Qualified Landscape Architect and must comply with the relevant Brisbane Planning Scheme Codes. The plan must include the following: Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT A detailed landscape plan accompanied by Brisbane City Council Form CC10616 - Landscape Design Certificate. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
16(b) Centre or Mixed Use In addition to the
requirements listed above, the plan must include the following: Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT A detailed landscape plan accompanied by Brisbane City Council Form CC10616 - Landscape Design Certificate. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
16(c) Certify Detailed Landscape
Plan On completion of the Detailed Landscape Plan, submit to Development
Services: Timing: Prior to building work commencing. PROOF OF FULFILMENT A detailed landscape plan accompanied by Brisbane City Council Form CC10616 - Landscape Design Certificate. Timing: Prior to building work commencing. |
As indicated |
16(d) Implement Certified Detailed Landscape
Plan Carry out the landscape work in accordance with the above certified detailed Landscape Plan. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
16(e) Certify Work On completion of the
landscape work, submit to Development Services: Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT An as constructed landscape plan accompanied by Brisbane City Council Form CC10613 - Landscape Works Certificate. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
16(f) Maintain Landscape Work Maintain the landscape work, including deep planting, in accordance with the certified Detailed Landscape Plan. Timing: To be maintained. |
As indicated |
| 17) Hours of Operation Hours of operation for deliveries (associated with
the Health care service use and Warehouse) and waste collection must be limited
from 7:00AM to 6:00PM. Hours of operation for
deliveries, for the approved Shop and Food and drink outlet uses must be
limited from 6:00AM to 8:00PM. |
At all times |
| 18) Plant and Equipment Certification Submit to Development Services certification that the installation of all mechanical plant and equipment (e.g. air conditioning, mechanical ventilation and refrigeration equipment and heat pump hot water systems), is adequately noise-attenuated and is in accordance with the criteria of the relevant Brisbane Planning Scheme Codes. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 19) Mechanical Plant or Equipment - Acoustically
Screened Mechanical plant or equipment is to be acoustically screened from an adjoining sensitive use. Mechanical plant includes generators, motors, compressors and pumps such as air-conditioning, refrigeration and cold room motors. Acoustically screened is defined in City Plan 2014. NOTE: This condition does not authorise environmental nuisance under the Environmental Protection Act 1994. PROOF OF FULFILMENT Submit to Development Services, certification that all mechanical plant or equipment, is acoustically screened. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 20) Noise Attenuation - Treatment to Carpark Install absorbent lining to the underside slab soffit
above the carpark in accordance with the minimum sound absorption coefficients
in Section 9.1 (as amended in red) of the Acoustic Report by Acoustic Works
dated 4/2/22 with reference number R01J. |
At all times |
| 21) Acoustic Fence - General Erect a 1.80m high
acoustic fence, in the locations shown at Figure 3 and Figure 4 of the Acoustic
Report by Acoustic Works dated 4/2/22 with reference number R01J. The acoustic
fence must: PROOF OF
FULFILMENT The figures mentioned in this condition include a requirement for absorptive material to the underside of the concrete slab, above the carpark. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
21(a) Certification Submit to Development Services certification from a person who is a Member or eligible to be a Member of the Australian Acoustic Society that the constructed acoustic fence complies with the above requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 22) Stormwater Quality (Implement Management
Plan) Manage stormwater quality in accordance with this condition. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
22(a) Implement Management Plan Implement Section 8.4 of the Site Based Stormwater Quality Management Plan by Inertia Revision 4 dated 13/8/21. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
22(b) Certification Submit to Development
Services certification from a relevant professional that all treatments and
measures recommended in Section 8.4 of the Site Based Stormwater Quality
Management Plan by Inertia Revision 4 dated 13/8/21, have been
implemented. A copy of the as-constructed site based stormwater quality measures must accompany the Certification. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
22(c) Maintain Management Plan Maintain Section 8.4 of the Site Based Stormwater Quality Management Plan by Inertia Revision 4 dated 13/8/21. |
As indicated |
| 23) Grant Easements Grant the following easement(s) as may be
required: Note: These easements include the provision for Council to obtain access. Timing: Prior to commencement of use and then to be maintained. |
As indicated |
23(a) Submit Plan of Subdivision and
Documentation (Council Easement in Gross) Submit to, and obtain approval from, Development Services a plan of subdivision showing the easement and a request for Council to prepare the necessary easement documentation to demonstrate compliance with the requirements of this condition. Note: Easements in favour of the Brisbane City Council must have the necessary easement documentation prepared by the Brisbane City Council, free of cost to Council. Timing: Prior to submission of the request pursuant to Schedule 18 of the Planning Regulation 2017 for Council's notation on the plan of subdivision necessary to comply with this condition. |
As indicated |
23(b) Submit Plan of Subdivision and
Documentation (Other Easement) Submit to, and obtain approval from, Development Services, a plan of subdivision showing the easement and the necessary easement documentation to demonstrate compliance with the requirements of this condition. Note: Easements not in favour of the Brisbane City Council must have the necessary documentation prepared by the applicant's private solicitors. Timing: As part of the submission of the request pursuant to Schedule 18 of the Planning Regulation 2017 for Council's notation on the plan of subdivision necessary to comply with this condition. |
As indicated |
23(c) Lodge Notated Plan and
Documentation Lodge the plan of subdivision notated by Council pursuant to Schedule 18 of the Planning Regulation 2017 and the necessary easement documentation with the Registrar of Titles for the relevant Queensland State Government Authority. Timing: Prior to commencement of use. PROOF OF FULFILMENT Evidence of the registration of the necessary easement documentation. Timing: Within one month of the registration of the easement documentation. |
As indicated |
| 24) On-site Erosion (Medium Risk) Manage on-site erosion and the release of sediment or sediment laden water from the site at all times by implementing best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version). Timing: Prior to commencement of any land disturbing activities and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
24(a) Manage earth disturbance on-
site (i) Drainage control measures must be implemented and maintained to minimise water flow onto areas of exposed earth. (ii) Sediment and erosion control measures must be implemented and maintained to prevent soil loss from earth disturbance areas and prevent deposition beyond earth disturbance areas. (iii) No release of contaminants to land beyond on-site area of earth disturbance other than releases that achieve water pollutant concentration release limits of: A. 50mg/L TSS (Total Suspended Solids); B. Turbidity, Nephelometric Turbidity Units (NTU) value less than 10% above background, 75 NTU, or as agreed in writing by an Officer from Councils Erosion and Sediment Control (ESC) Team in Compliance and Regulatory Services; C. pH between 6.5 and 8.5 at all times. (iv) Maintain a written record to demonstrate that water discharges from the site, including any dewatering operations, meet the release limits as detailed in (iii) for water discharge(s) from the site that occur during or immediately after a rainfall event, and during normal business hours. The water quality of the discharge flows must be measured at each discharge point from the site, including but not limited to sediment basin outlets, other applicable sediment control devices, the site water drainage system, and recorded against the release limits at least once on each calendar day until such discharge stops. Timing: Prior to commencement of any earth disturbing activities and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
24(b) Provide Land Occupier Notification to
Council (i) Notify Council's ESC Team of proposed land occupier/s by sending an email to CARS-ESC@Brisbane.qld.gov.au (ii) If the land is to be occupied by any person other than the registered landowner then advice must be provided to Council that confirms the name, contact information and the duration of any proposed occupation of the land. Timing: Prior to commencement of any earth disturbing activities. |
As indicated |
24(c) Prepare Erosion and Sediment Control
Plan Prepare an Erosion and Sediment Control Plan (ESCP) in accordance with best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version) and, to the extent of any inconsistency, relevant Brisbane Planning Scheme Codes and Policies. Obtain a design certificate in accordance with the relevant Brisbane Planning Scheme Codes and Policies. The ESCP and design certificate must be certified by a Certified Professional in Erosion and Sediment Control (CPESC) or a Registered Professional Engineer Qld (RPEQ) with suitable qualifications and experience in erosion and sediment control. Documentary evidence demonstrating appropriate qualifications in erosion and sediment control must be provided to the Council upon request. Timing: Prior to the commencement of any earth disturbing activities. |
As indicated |
24(d) Attend a pre-start
meeting Arrange and attend a pre-start meeting for ESC with an Officer from Councils ESC Team in Compliance and Regulatory Services (CARS). Note: To request a pre-start meeting from Council's ESC Team send an email to CARS-ESC@Brisbane.qld.gov.au. All relevant documentation, including both the certified ESCP and the certified design certificate, must be attached to this email. Please allow up to 10 business days for your request to be processed. Timing: Attend the pre- start meeting prior to the commencement of any earth disturbing activities. |
As indicated |
24(e) Implement Certified Erosion and
Sediment Control Plan Implement the certified ESCP and maintain all ESC measures in accordance with best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version) and, to the extent of any inconsistency, relevant Brisbane Planning Scheme Codes and Policies. The ESCP and design certificate must be available on site at all times for inspection by Council officers. Any alteration to supplementary or Type 3 ESC measures must be reflected in the certified ESCP. Any alteration to Type 2 or Type 1 ESC measures will require a revised ESCP and design certificate that has been certified by either the CPESC or RPEQ. Timing: While earth disturbing activities are occurring and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
| 25) Information Signage Erect an information sign on the subject property in
accordance with Council's general requirements for signage and in accordance
with the requirements outlined below: Timing: Prior to site works commencing and then to be maintained until completion of the development for all stages. |
As indicated |
| 26) Engineering Pre-Start Meeting Arrange and attend a pre-start meeting with Development Services and Program Planning and Integration. Applicable compliance and inspection fees must be paid, in full, to Council prior to the meeting being held. Note: To arrange an engineering pre-start meeting with Development Services an email supported by a completed copy of the Pre-Start Meeting Guidelines - Civil Engineering Works kit (https://www.brisbane.qld.gov.au/sites/default/files/20191008-cc11207-pre- start-meeting-guidelines-civil-engineering-works.pdf) must be sent to dalodgement@brisbane.qld.gov.au. Details include (but
are not limited too) the following: Note: Timing: Prior to site/operational/building work commencing. |
As indicated |
| 27) Filling and / or Excavation All earthworks must be carried out in accordance with the relevant Brisbane Planning Scheme Codes. |
Prior to building work commencing |
27(a) Submit Earthworks
Drawings Submit to, and obtain approval from, Development Services earthworks drawings prepared and certified by a Registered Professional Engineer Queensland in accordance with the relevant Brisbane Planning Scheme Codes. The Earthworks Drawings must include the
following: Note: If the earthworks impact on the road reserve, the Developer must obtain applicable footpath and road permits prior to commencing any works. Such impacts may include footpath occupation, road closures, re-profiling, ground anchors and/or relocation of services. If the excavation has to be stabilised using ground anchors or similar, then the submitted plans must show the location of these in relation to all services. The cost of moving services, utilities and assets is the responsibility of the Developer. The permission of the service/utility/asset owner is required. Note: Irrespective of final earthworks, it is the responsibility of the RPEQ to manage any staged works associated with Erosion & Sediment Control. Timing: Prior to site/operational/building work commencing. |
As indicated |
27(b) Fill Material, Placement, Compaction
and Testing All fill material placed on the site must comprise only natural earth and rock and must be free of contaminants (as defined by Part 3, Division 2, Subdivision 2 Environmental contamination, Section 11 of the Environmental Protection Act 1994) and noxious, hazardous, deleterious and organic materials. Fill material, placement, compaction and testing must comply with the requirements of Australian Standard - AS 3798, Guidelines on Earthworks for Commercial and Residential Developments. Timing: While site/operational/building work is occurring. |
As indicated |
27(c) Implement Approved Earthworks
Drawings Construct and maintain the earthworks in accordance with the requirements of AS3798 and the approved earthworks drawings. Timing: While site/operational/building work is occurring and then to be maintained. |
As indicated |
27(d) Submit As Constructed
Drawings Submit to Development Services As Constructed drawings prepared by a Registered Surveyor. Timing: Prior to building work above ground commencing. |
As indicated |
27(e) Submit Certification Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the approved earthworks drawings. Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that all fill material used complies with the quality requirements of this condition and that placement, compaction and testing has been carried out in accordance with AS3798. Timing: Prior to building work above ground commencing. |
As indicated |
| 28) Construction Management Plan - Major Carry out development in a method consistent with a Construction Management Plan (CMP) prepared in accordance with the requirements of this condition. |
While site/operational/building work is occurring |
28(a) Construction Management Plan - Submit
Plan Submit to, and obtain compliance approval from, Development Services a detailed Construction Management Plan for the site preparation, demolition, excavation and construction phases of the approved development. The Construction Management Plan must be in accordance with the relevant Brisbane Planning Scheme Codes and address the following matters, both internal to and external to the development site: (i)
Location of and impacts to any Council vegetation (i.e. street
trees/park trees/garden beds) The Construction Management Plan must be supported by 'approval in principle' or written approvals from the relevant Council sections or other governing bodies responsible for any potentially impacted infrastructure. The list of relevant infrastructure and contacts is available on Council's website - Search 'Constructions Management Plan'. Timing: Prior to site/operational/building work commencing. |
As indicated |
28(b) Construction Management Plan -
Dilapidation Report Submit a dilapidation report to engineeringservices@brisbane.qld.gov.au detailing the pre-existing condition of the roadway, both footways, both verges and Council infrastructure, including vegetation, for 100m from the site entry in both directions or to the next street intersection (if less than 100m from the site entry) in both directions. Timing: Prior to the pre-start meeting. |
As indicated |
28(c) Construction Management Plan -
Documentation on Site Legible copies of the approved Construction Management Plan and current permits must be kept on site and be made available on request by Council, at all times. The requirements of the CMP must be included in all induction of principal and subcontractors utilised in the development. An outline of the induction provided to contractors may be requested by Council to confirm compliance with this condition. Timing: While site/operational/building work is occurring. |
As indicated |
28(d) Construction Management Plan - Works to
be Performed Out of Hours Obtain an approval from Development Services for any
work that is proposed to be undertaken outside of normal business hours -
6:30am to 6:30pm, Monday to Saturday. |
As indicated |
28(e) Construction Management Plan -
Implement Plan Carry out the development in accordance with the approved Construction
Management Plan. |
As indicated |
| 29) Protect Existing Infrastructure Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure. Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations. The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements. |
While site/operational/building work is occurring |
29(a) As Constructed Drawings - Alterations
to Existing Infrastructure Submit to Development Services As Constructed drawings showing all new and/or rectification works and an asset register, prepared by a Registered Professional Engineer Queensland. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 30) Remove Improvements & Obstructions from Truncation
and Dedication Remove all improvements (fences, gates, letter boxes, garden beds and plots and other constructed items, etc.) and obstructions (existing earth banks, vegetation, etc.) from the area of the corner truncation(s) and/or area of dedicated road and reinstate the area as footway in accordance with the relevant Brisbane Planning Scheme Codes. Any new or existing installations of electrical pillar boxes, pad mounted transformers (PMTs), water meters and the like, must be installed/relocated to their ultimate alignment relative to the new property boundary and clear of the usable footpath areas irrespective of the alignment of the existing services/conduits. Note: The cost of moving services, utilities and assets is the responsibility of the Developer. The permission of the service, utility or asset owner will be required. Council permission is required if street trees, stormwater gullies/drains, and swales are affected. Urban Utilities permission is required if water supply and sewerage services are affected. Standard utility alignments may be found on Council's 'Brisbane Standard Drawings' 1013 to 1016 inclusive. PROOF OF
FULFILMENT Certification from a Registered Surveyor or Registered Professional Engineer Queensland that the above work has been completed in accordance with this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 31) Retaining Walls Design and construct all retaining walls and
associated fences, in accordance with the relevant Brisbane Planning Scheme
Codes and the following: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
31(a) Certification of Retaining
Walls For retaining walls over 1.0m in height, obtain certification from a Registered Professional Engineer Queensland that the design and construction of the retaining walls and ancillary drainage are in accordance with the requirements of this condition. |
As indicated |
| 32) Access, Grades, Manoeuvring, Carparks, Signs and
Line Marking Construct and maintain access, parking and manoeuvring for vehicles on site, generally in accordance with the approved Traffic Statement, Document ref: 1842_MEW10, received on 15 August 2023 in accordance with the relevant Brisbane Planning Scheme Codes, as indicated on the approved DRAWINGS AND DOCUMENTS, including the following: i. A pavement of minimum Local road standard or equivalent surface material (including associated drainage) to the area on which motor vehicles will be driven and/or parked. ii. Manoeuvring on site for a rear loading smaller sized refuse collection vehicle (RCV) by private refuse contractor and for an (Ambulance) Small Rigid Vehicle (SRV) and for the loading and unloading of vehicle(s); Service Vehicle Access for both RCV & Ambulance is permitted from Stafford Road Access only. iii. Parking on the site for minimum seventy-nine (79) cars including two (2) parking spaces for people with disabilities and for the loading and unloading of vehicle(s) within the site. iv. Provide and maintain twenty-two (22) secure bicycle parking spaces for use by staff and visitors. v. A minimum of 2.3 metres height clearance to all undercover parking areas and a minimum of 2.5 metres above parking spaces for people with disabilities. The minimum clear height must be measured to the lowest protrusion from the ceiling (e.g. fire sprinklers, services, lighting fixtures, signs, etc). vi. A height clearance sign located at the entrance(s) to undercover car parking areas and a directional visitor parking sign clearly visible from the vehicle entrance to the site. vii. Prepare and implement signs and line markings drawings that show the internal paved areas signed and delineated in accordance with the approved drawings and documents. The drawings must be prepared and certified by a Registered Professional Engineer Queensland in accordance with the relevant Brisbane Planning Scheme Codes and the Manual of Uniform Traffic Control Devices. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland, that the above requirements have been implemented in accordance with this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 33) Repair Damage to Kerb, Footpath or Road Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
33(a) Interim Repairs If at any time during the construction phase of the approved development, damage to the existing kerb and channel, footpath or roadway creates unsafe, unreasonable and/or not fit for purpose conditions as assessed by Council, interim repairs must be undertaken as directed by Program Planning and Integration. Note: Any interim repairs required to be undertaken shall not be considered to satisfy the requirements of this condition for the permanent repair of the infrastructure prior to the issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. Timing: While site / operational / building works is occurring. |
As indicated |
| 34) Stormwater - Flood Study Construct the development in accordance with the approved “Minor Hydraulic Flood Report” prepared by Inertia Reference Number 8974 Dated 9 December 2021. All fences proposed across an overland flow path are to be constructed with minimum 75% openings to allow for the free passage of overland flows. |
While site works are occurring |
34(a) Certification Submit to Development Services certification from a Registered Professional Engineer Queensland that the development has been constructed in accordance with the approved “Minor Hydraulic Flood Report”. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 35) Minimum Flood Planning Levels Design and construct all building pad levels, floor levels and ancillary structures to the appropriate flood planning level with freeboard (where required) in accordance with the relevant Brisbane Planning Scheme Codes and the approved “Minor Hydraulic Flood Report” prepared by Inertia Reference Number 8974 Dated 9 December 2021. PROOF OF FULFILMENT As-Constructed drawings prepared by a Registered Surveyor. The Registered Surveyor must certify that the development has been constructed in accordance with this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 36) Essential Services within Basements Where essential services are located within a basement or room located below the highest flood level affecting the site in an area affected by the Brisbane River Flood Planning areas or Creek/Waterway Flood Planning areas, the building is to be designed and constructed to provide either: i) A completely watertight tanked basement with walls and floors designed by a Registered Professional Engineer Queensland (Structural) to resist hydrostatic pressures expected during a defined flood event, OR ii) A subsoil drainage system and pump system
designed by a Registered Professional Engineer Queensland and constructed to
prevent the basement from flooding and meet the following: Notes: Essential electrical services include any area or room used for fire control panel, telephone PABX, sensitive substation equipment including transformers, low voltage switch gear, high voltage switch gear, battery chargers, protection control and communication equipment, low voltage cables, high voltage cables, and lift or pump controls. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
36(a) Certification to the Private Building
Certifier Provide to the Private Building Certifier, certification from a Registered Professional Engineer Queensland (Structural) that the basement has been designed and constructed to ensure structural integrity during a defined flood event. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
36(b) Certification to Council Submit to Council certification by a Registered Professional Engineer Queensland that the stormwater, subsoil drainage, pump and backup power supply has been constructed in accordance with the requirements of this condition. Note: This certification is required to be provided where a subsoil drainage and pump system has been provided in lieu of a tanked, watertight basement. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 37) Refuse Collection - On Site Provide for the installation and collection of refuse/recycling bins by Brisbane City Council's Waste and Resource Recovery Services or a private waste contractor. |
At all times |
37(a) Arrange Refuse Collection Arrange for the installation of refuse/recycling bins and for the subsequent collection of refuse including recycling from the site by Brisbane City Council's Waste and Resource Recovery Services or a private waste contractor. Timing: A minimum of four weeks prior to the commencement of use and then to be maintained. PROOF OF FULFILMENT Where a private waste contractor is engaged, provide written confirmation from the proposed waste collection contractor of the agreement to service the property. The written agreement must be submitted to Council's Waste and Resource Recovery Services and include full details of the proposed system, bin sizes, number of bins, frequency of collection and the refuse collection vehicle size. Timing: Prior to commencement of use. |
As indicated |
37(b) Notify Future Owner Where Council is engaged as the waste contractor, the owner must notify any future owner/body corporate that the development has been approved on the basis that an indemnity must be provide for refuse collection vehicles to enter the property. Timing: At time of a change of ownership. |
As indicated |
37(c) Indemnify Council The owner and any subsequent owner must, by approved form to Waste and Resource Recovery Services, indemnify Council and its agents in respect of any damage to the pavement and other driving surfaces. Timing: When an arrangement for refuse/recycling collection services is made with Brisbane City Council. |
As indicated |
| 38) Refuse Storage - On Site Collection Provide a roofed and wholly screened refuse enclosure utilising materials consistent with the development or a dedicated refuse storage room, as shown on the approved plans and documents. The enclosure/refuse storage room must be of a design to accommodate the quantity of refuse and recycling including source separation to allow for low servicing collection of the development. Bins must be located in an area which allows them to be manoeuvred from the bin storage area to the designated internal collection point. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 39) Site Drainage - Major Provide an internal drainage system
to collect stormwater run-off from all proposed lots, roofed and developed
surface areas and any run-off onto the site from adjacent areas and convey the
collected run-off to a lawful point of discharge, in accordance with the
relevant Brisbane Planning Scheme Codes. Notes: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
39(a) Submit Site Drainage
Drawings Submit to, and obtain approval from, Development Services, site drainage drawings and engineering calculations, prepared and certified by a Registered Professional Engineer Queensland, in accordance with the relevant Brisbane Planning Scheme Codes. Notes: -
Queensland Building and Construction Commission licensed hydraulic
consultants may design the stormwater system for sites less than 2000m2 with an
upstream catchment servicing no more than 4 residential lots. This
excludes stormwater drainage design (including subsoil drainage) of basements
in flood planning areas and the design of any onsite stormwater detention
system Timing: Prior to site/operational/building work commencing |
As indicated |
39(b) Implement Approved
Drawings Carry out the works in accordance with the approved site drainage drawings. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
39(c) Submit As Constructed
Drawings Submit to Development Services As Constructed drawings prepared and certified by a Registered Professional Engineer Queensland or a Queensland Building and Construction Commission licensed hydraulic consultants (where applicable). Note: To be submitted via da- engineeringcompliance@brisbane.qld.gov.au and include the site address, A00 reference and Condition number in the subject line. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland or Queensland Building or Construction Commission licensed hydraulic consultants (where applicable) confirming that the works have been completed in accordance with the above stormwater drawings. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 40) Ponding of Stormwater Carry out the approved development to ensure that adjoining properties and roads are protected from ponding or nuisance from stormwater during construction. Notes: If remedial works are necessary to comply with this condition, prior approval must be obtained from Development Services. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 41) Stormwater Quality Manage stormwater quality in accordance with this condition. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
41(a) Implement Stormwater Quality
Management Implement the stormwater quality treatment strategy outlined within the APPROVED DRAWINGS AND DOCUMENTS and any engineering drawings and documents approved pursuant to conditions contained in this development approval. Where a proprietary stormwater quality improvement device has been used to meet the water quality objectives, ensure the device has been approved by Brisbane City Council for use in achieving the water quality targets and meets the required manufacturers specifications (in terms of number and size of units and any pre-treatment requirements). Note: This condition does not require any further approval from Council. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained. |
As indicated |
41(b) Water Quality Maintenance Management
Plan Prepare and implement a Water Quality Maintenance Management Plan in accordance with the Water by Design 'WSUD Technical Design Guidelines for South East Queensland'. The plan must be prepared and certified by a Registered Professional Engineer Queensland. Note: This condition does not require any further approval from Council. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained. |
As indicated |
41(c) Submit Certification Submit to Development Services certification from a Registered Professional Engineer Queensland confirming that the stormwater quality treatments strategy required pursuant to part (a) of this condition has been implemented and where a proprietary stormwater quality improvement device has been used to meet the water quality objectives, the device has been approved by Brisbane City Council for use in achieving the water quality targets and meets the required manufacturers specifications (in terms of number and size of units and any pre-treatment requirements). Note: Manufacturers that have approved devices by Brisbane City Council will be able to provide evidence of Council approval for use. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
41(d) Maintain Management Plans Maintain the certified Water Quality Maintenance Plan and the stormwater quality treatment strategy required pursuant to part (a) of this condition. Include the Water Quality Maintenance Plan in any building management strategy, building management statement or community management statement. Timing: At all times |
As indicated |
| 42) Service Conduits and Mains Provide and install all
service conduits and meet the cost of any alterations to public utility mains,
existing mains, services, street lighting or installations that are required to
carry out the approved development. These works must be in accordance with the
relevant Brisbane Planning Scheme Codes, and include the following, where
applicable: Note: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
42(a) Submit As Constructed
Drawings Submit to Development Services As Constructed drawings, including an asset register, prepared and certified by a Registered Professional Engineer Queensland. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the requirements of this condition. Note: Civil works are to be certified by a RPEQ(Civil) and electrical works are to be certified by a RPEQ (Electrical). |
As indicated |
| 43) Telecommunications Submit to Development Services, certification from
an authorised telecommunications carrier/contractor, that the following works
and infrastructure have been undertaken and installed in accordance with
telecommunications industry standards: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 44) Agreement with Electricity Supplier Submit to Development Services, evidence of an agreement with an electricity supplier to provide necessary services to the development in accordance with the relevant Brisbane Planning Scheme Codes. Where development is within an established area of overhead electricity supply and the electricity supplier determines that a property pole is the appropriate solution to supply electricity to the development, the developer must be responsible for the installation of the property pole(s). In the above circumstances, submit to Development Services, certification from the developer's electrical consultant confirming that the above installation has been completed in accordance with the relevant AS/NZS Standards and the Queensland Electricity Connection Manual (QECM) and Queensland Electricity Metering Manual (QEMM). |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 45) Water and Wastewater Pursuant to Schedule 18 of the Planning Regulation 2017 submit to Development Services, documentary evidence, issued by the relevant distributor-retailer, to verify that the conditions of any necessary Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009, have been complied with. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 46) Permanent Driveway Crossover Provide a 10.3-metre- wide Type C2 permanent driveway crossover to the Webster Road frontage of the site in accordance with the relevant Brisbane Planning Scheme Codes and located as shown on the approved DRAWINGS AND DOCUMENTS. Provide a 12.0-metre-wide Type C2 permanent driveway crossover to the Stafford Road frontage of the site in accordance with the relevant Brisbane Planning Scheme Codes and located as shown on the approved DRAWINGS AND DOCUMENTS. Written consent must be obtained from BCC - Field Services, Program Planning and Integration Arborist prior to any works occurring that will either impact on or require removal of a street tree (this includes pruning and excavation within the root zone/canopy of the tree) At all times during construction of the crossover, safe pedestrian access along the site frontage must be maintained. Note: No further driveway permit is required however additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 47) Redundant Driveway Crossover Remove the redundant existing driveway crossover(s) on the frontage(s) of the site and reinstate the kerb and channel, road pavement, footways and footpaths in accordance with the relevant Brisbane Planning Scheme Codes. Note: Additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 48) Construction Noise and Dust Emissions Pursuant to the Environmental
Protection Act 1994, all development involving the emission of noise and dust
from building and/or construction activities, must ensure that the emissions
are in accordance with the requirements of the Act. |
As indicated |
| 49) Further Development Permit Required Further Development Permit(s) to carry out assessable building work under the Building Act may be required. |
As indicated |
| 50) Plumbing and Drainage Work Pursuant to the Plumbing and Drainage Act 2018, any plumbing and drainage work must be carried out in compliance with the Plumbing and Drainage Regulation 2019. Plumbing and drainage permit work requires approval by Brisbane City Council prior to the work being carried out. |
As indicated |
| 51) Currency Period The currency period for this development approval is stated in the Decision Notice and is expressed as a date. This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016. |
As indicated |
| 52) Referral Agency Requirements The Department of State Development, Infrastructure, Local Government and Planning (SARA) as concurrence agency has imposed the requirements contained in the letter dated 17 October 2023 (SARA ref: 2309-36712 SRA) AND 12 February 2026 (SARA:2601-50250 SRA). |
As indicated |
| 53) Cultural Heritage Aboriginal cultural heritage is protected under the Aboriginal Cultural Heritage Act 2003. This Act establishes a cultural heritage duty of care and in section 23(1) mandates that a person who carries out an activity must take all reasonable and practicable measures for ensuring activities are managed to avoid or minimise harm to Aboriginal cultural heritage. The Duty of Care Guidelines gazetted pursuant to the Aboriginal Cultural Heritage Act 2003 provide guidance on identifying and protecting Aboriginal cultural heritage to fulfil the duty of care. For further information contact the relevant Queensland State Government Department (Department of Aboriginal and Torres Strait Islander Partnerships). |
As indicated |
| 54) Equitable Access Provision must be made during and after construction
for equitable access for persons with disabilities to and within the site and
on adjoining public areas, in accordance with the following: |
As indicated |
| 55) Damage to Trees on Adjoining Land Please note that any damage caused to vegetation on adjoining land as a result of exercising this development approval may result in an offence under other legislation (e.g. Natural Assets Local Law) and/or civil action |
As indicated |
| 56) Fire Ant Movement Controls To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected. These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products. Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014. For further information contact the relevant Queensland State Government department on 13 QGOV. |
As indicated |
| 57) Water and Wastewater Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. For further information about any necessary Water Approvals contact Urban Utilities. |
As indicated |
| Permit to Which These Conditions Relate: | DA - PA - Building Work |
| Activity(ies): | warehouse health care service food and drink outlet shop |
| Stage: | Health Care Service, Food and Drink Outlet, Shop and warehouse |
| 58) Maintain the Approved Development Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions. |
At all times |
| 59) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers. Note: This condition is imposed to ensure compliance with the conditions of development approval. |
While site/operational/building work is occurring |
| 60) Carry Out the Approved Development Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS. Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners. |
While site/operational/building work is occurring |
| 61) Complete All Building Work Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS. Note: Building work must also be completed in accordance with any other current development approval. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 62) Stormwater - Flood Study Construct the development in accordance with the approved “Minor Hydraulic Flood Report” prepared by Inertia Reference Number 8974 Dated 9 December 2021. All fences proposed across an overland flow path are to be constructed with minimum 75% openings to allow for the free passage of overland flows. |
While site works are occurring |
62(a) Certification Submit to Development Services certification from a Registered Professional Engineer Queensland that the development has been constructed in accordance with the approved “Minor Hydraulic Flood Report”. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 63) Minimum Flood Planning Levels Design and construct all building pad levels, floor levels and ancillary structures to the appropriate flood planning level with freeboard (where required) in accordance with the relevant Brisbane Planning Scheme Codes and the approved “Minor Hydraulic Flood Report” prepared by Inertia Reference Number 8974 Dated 9 December 2021. PROOF OF FULFILMENT As-Constructed drawings prepared by a Registered Surveyor. The Registered Surveyor must certify that the development has been constructed in accordance with this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 64) Essential Services within Basements Where essential services are located within a basement or room located below the highest flood level affecting the site in an area affected by the Brisbane River Flood Planning areas or Creek/Waterway Flood Planning areas, the building is to be designed and constructed to provide either: i) A completely watertight tanked basement with walls and floors designed by a Registered Professional Engineer Queensland (Structural) to resist hydrostatic pressures expected during a defined flood event, OR ii) A subsoil drainage system and pump system
designed by a Registered Professional Engineer Queensland and constructed to
prevent the basement from flooding and meet the following: Notes: Essential electrical services include any area or room used for fire control panel, telephone PABX, sensitive substation equipment including transformers, low voltage switch gear, high voltage switch gear, battery chargers, protection control and communication equipment, low voltage cables, high voltage cables, and lift or pump controls. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
64(a) Certification to the Private Building
Certifier Provide to the Private Building Certifier, certification from a Registered Professional Engineer Queensland (Structural) that the basement has been designed and constructed to ensure structural integrity during a defined flood event. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
64(b) Certification to Council Submit to Council certification by a Registered Professional Engineer Queensland that the stormwater, subsoil drainage, pump and backup power supply has been constructed in accordance with the requirements of this condition. Note: This certification is required to be provided where a subsoil drainage and pump system has been provided in lieu of a tanked, watertight basement. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 65) Construction Noise and Dust Emissions Pursuant to the Environmental
Protection Act 1994, all development involving the emission of noise and dust
from building and/or construction activities, must ensure that the emissions
are in accordance with the requirements of the Act. |
As indicated |
| 66) Further Development Permit Required Further Development Permit(s) to carry out assessable building work under the Building Act may be required. |
As indicated |
| 67) Plumbing and Drainage Work Pursuant to the Plumbing and Drainage Act 2018, any plumbing and drainage work must be carried out in compliance with the Plumbing and Drainage Regulation 2019. Plumbing and drainage permit work requires approval by Brisbane City Council prior to the work being carried out. |
As indicated |
| 68) Cultural Heritage Aboriginal cultural heritage is protected under the Aboriginal Cultural Heritage Act 2003. This Act establishes a cultural heritage duty of care and in section 23(1) mandates that a person who carries out an activity must take all reasonable and practicable measures for ensuring activities are managed to avoid or minimise harm to Aboriginal cultural heritage. The Duty of Care Guidelines gazetted pursuant to the Aboriginal Cultural Heritage Act 2003 provide guidance on identifying and protecting Aboriginal cultural heritage to fulfil the duty of care. For further information contact the relevant Queensland State Government Department (Department of Aboriginal and Torres Strait Islander Partnerships). |
As indicated |
| 69) Damage to Trees on Adjoining Land Please note that any damage caused to vegetation on adjoining land as a result of exercising this development approval may result in an offence under other legislation (e.g. Natural Assets Local Law) and/or civil action |
As indicated |
| 70) Fire Ant Movement Controls To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected. These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products. Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014. For further information contact the relevant Queensland State Government department on 13 QGOV. |
As indicated |
| 71) Water and Wastewater Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. For further information about any necessary Water Approvals contact Urban Utilities. |
As indicated |