| Address of Site: | 43 WAMBOOL ST BULIMBA QLD 4171 |
| Real Property Description of Site: | L69 RP.12589 |
| Aspects of development and type of approval: | DA - PA - Material Change of Use Development Permit - multiple dwelling DA - PA - Building Work Development Permit - multiple dwelling |
| Council File Reference: | A006971368 Permit Reference Number/s: DAMC434549223; DABW434549323. |
| Package Status: | APPROVED - Version 2 (10th of April, 2026 1:32:38 PM) |
| Package Generated: | 10/04/2026 |
| Kayal CHANDRASEKAR Senior Urban Planner Planning Services South Kayal.Chandrasekar@brisbane.qld.gov.au 34030086 |
Kim ROGERS Principal Urban Planner Planning Services South kim.rogers@brisbane.qld.gov.au 34071304 |
Richard DITCHFIELD Technical Officer Engineering Services South richard.ditchfield@brisbane.qld.gov.au 34036751 |
| Scott RUHLAND Technical Officer Engineering Services North scott.ruhland@brisbane.qld.gov.au (07) 3403 9459 |
Glyn CHISHOLM Senior Landscape Architect Landscape Architecture Team Glyn.Chisholm@brisbane.qld.gov.au 07 3403 0117 |
Mario FURLAN Architect Architecture Team Mario.Furlan@brisbane.qld.gov.au (07) 3403 5698 |
| Tim DWYER WaRRS Assessment Tim.Dwyer@brisbane.qld.gov.au |
Rodney KING Plumbing Services Rodney.King@brisbane.qld.gov.au |
Amir POURFARZAD Principal Engineer Engineering Services Traffic Amir.Pourfarzad@brisbane.qld.gov.au |
| Binu JOSE Network Planning Binu.Jose@brisbane.qld.gov.au |
Joyce LAW Architect Architecture Team Joyce.Law@brisbane.qld.gov.au 0731781325 |
Angela CLEARY Urban Planner Planning Services Special Assessment Angela.Cleary@brisbane.qld.gov.au 31785733 |
| Nicola MEWING Principal Urban Planner Planning Services Special Assessment Nicola.Mewing@brisbane.qld.gov.au 31781002 |
DRAWINGS AND DOCUMENTS
| Drawing or Document | Number | Plan Date |
|---|---|---|
| Traffic Impact Assessment Report | 001 Revision 01 | 20-MAR-2023 (Received) |
| Site Plan | DA1.00 Issue 2 (Amended In Red 02-APR-2026) | 25-JUL-2023 (Received) |
| Basement Floor Plan | DA1.01 Issue 3 | 26-FEB-2026 (Received) |
| Ground Floor Plan | DA1.02 Issue 3 (Amended In Red 02-APR-2026) | 26-FEB-2026 (Received) |
| Level 01 Floor Plan | DA1.03 Issue 2 | 25-JUL-2023 (Received) |
| Level 02 Floor Plan | DA1.04 Issue 2 | 25-JUL-2023 (Received) |
| Roof Plan | DA1.05 Issue 2 | 25-JUL-2023 (Received) |
| Front Elevation (West) | DA2.00 Issue 3 | 26-FEB-2026 (Received) |
| Side Elevation (South) | DA2.01 Issue 2 (Amended In Red 02-APR-2026) | 25-JUL-2023 (Received) |
| Side Elevation (North) | DA2.02 Issue 2 (Amended In Red 02-APR-2026) | 25-JUL-2023 (Received) |
| Rear Elevation (East) | DA2.03 Issue 2 | 25-JUL-2023 (Received) |
| Long Section 01 | DA3.00 Issue 2 | 25-JUL-2023 (Received) |
| Long Section 02 | DA3.01 Issue 2 | 25-JUL-2023 (Received) |
| Short Section 01 | DA3.02 Issue 2 (Amended In Red 02-APR-2026) | 25-JUL-2023 (Received) |
| Short Section 02 | DA3.03 Issue 2 (Amended In Red 02-APR-2026) | 25-JUL-2023 (Received) |
| Landscape Concept Plan - Ground Floor | 23.035-Sheet 1-Issue E (Amended In Red 02-APR-2026) | 25-JUL-2023 (Received) |
| Landscape Concept Plan - Level 1 | 23.035-Sheet 2- Issue E | 25-JUL-2023 (Received) |
| Landscape Concept Plan - Level 2 | 23.035-Sheet 3- Issue E | 25-JUL-2023 (Received) |
| Landscape Sections | 23.035-Sheet 5- Issue E (Amended In Red 02-APR-2026) | 25-JUL-2023 (Received) |
| Existing Tree Schedule | 23.035 - Sheet 8- Issue E | 25-JUL-2023 (Received) |
| Proposed Planting Schedule | 23.035 - Sheet 12- Issue E | 25-JUL-2023 (Received) |
| Proposed Planting Schedule | 23.035 - Sheet 10- Issue E | 25-JUL-2023 (Received) |
| Proposed Planting Schedule | 23.035 - Sheet 9- Issue E | 25-JUL-2023 (Received) |
| Proposed Planting Schedule | 23.035 - Sheet 11- Issue E | 25-JUL-2023 (Received) |
| Concept Services Plan | 23012/SK10 Rev A | 20-MAR-2023 (Received) |
APPROVAL CONDITIONS
| Permit to Which These Conditions Relate: | DA - PA - Material Change of Use |
| Activity(ies): | multiple dwelling |
| Stage: | Multiple Dwelling (8 Units) |
| 1) Building Format Plan Where the timing of a condition, or part thereof , states 'Prior to issue of Certificate of
Occupancy/Final Inspection Certificate' or 'Prior to commencement of use' and
the development involves the creation of a Building Format Plan, the timing of
the condition, or part thereof, is taken to mean 'prior to Council's
endorsement of any plan of subdivision'. |
As indicated |
| 2) Approved Drawings and Documents A legible copy of the
Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package
must be maintained on site and kept available for inspection by site workers
and Council officers. |
While site/operational/building work is occurring |
| 3) Carry Out the Approved Development Carry out the approved
development generally in accordance with the approved DRAWINGS AND
DOCUMENTS. |
While site/operational/building work is occurring and then to be maintained |
| 4) Complete All Building Work Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out generally in accordance with the approved DRAWINGS AND DOCUMENTS, and, where the building work is assessable development, in accordance with a current development approval. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
| 5) Maintain the Approved Development Maintain the approved
development generally in accordance with the approved DRAWINGS AND DOCUMENTS,
and any relevant Council engineering or other approval required by the
conditions. |
To be maintained |
| 6) Visitor Parking Visitor car parking spaces must: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 7) External Details External details of the building, facade treatment and external materials, colours and finishes must be consistent with the approved DRAWINGS AND DOCUMENTS. Note: The requirement to use particular materials and finishes is imposed only for the purpose of achieving a built form outcome that displays architectural merit. Council has not assessed the materials and finishes for compliance with the Building Act, the Building Fire Safety Regulation, the Building Regulation, the Building Code of Australia, the Queensland Development Code, relevant Australian Standards, fire safety standards or any other relevant requirement of a statutory authority with regard to building work. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 8) Overall Height The overall height of the proposed building(s) must
be in accordance with the floor and roof levels and overall height shown on the
APPROVED DRAWINGS AND DOCUMENTS. |
While site/operational/building work is occurring and then to be maintained |
8(a) Submit Certification Submit to Development
Services certification from a registered surveyor confirming that the “as
constructed” floor and roof levels and overall height are in accordance
with the requirements of this condition. |
As indicated |
| 9) Provide Pedestrian Prioritised Pathway Provide a pedestrian
prioritised pathway from the street frontage to the lobby of the building. The
pathway must be differentiated in colour and texture from the driveway
surface. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 10) Balconies/Verandahs/Terraces No
balconies/verandahs/terraces may be enclosed with solid balustrades, solid
walls, fixed and/or operable, moveable or adjustable screening unless these
features are clearly shown on the APPROVED DRAWINGS AND DOCUMENTS. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 11) Driveway Material and Finishes Provide materials and
finishes to the driveway and external carparking
surfaces that reduce the visual impact of these areas when viewed from the
street. One or a combination of the following must be used: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 12) Screen Air Conditioning and Other Plant
Enclosures Install and maintain suitable screening to all air conditioning, lift motor rooms, plant and service facilities located at the top of or on the external face of the building. The screening structures must be constructed from materials that are consistent with materials used elsewhere on the facade of the building. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 13) Screening Multiple Dwelling / Dual
Occupancy Provide screening in accordance with the approved DRAWINGS AND DOCUMENTS
and the following: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 14) Retain and Protect Existing Street Tree(s) Identify, retain and protect the one (x1) existing northernmost street tree on the frontage of 43 Wambool Street, Bulimba including the roots unless otherwise agreed in writing with Program, Planning and Integration Arboriculture (PPI Arb). Note: Street trees are protected under the Natural Assets Local Law. Street trees must not be removed or pruned without prior approval from PPI Arb. Note: Where driveway crossovers occur within the Tree Protection Zone (TPZ) of existing street trees, seek approval from the Arboricultural Team in Program Planning and integration, City Standards for the final driveway crossover design and construction methodology to ensure the successful retention of the existing street tree(s)
PROOF OF FULFILMENT Contextual photographic evidence that the tree has been retained in equal or greater health than before development commenced. OR, evidence in writing from Asset Services Arboriculture that an alternative arrangement has been made. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
At all times |
14(a) Implement Protection
Measures Install tree protection measures in accordance with Australian Standard - AS4970 Retention of Trees on Development Site. There must be no excavation, filling or storage of materials or plant within the drip line of the tree(s). Where works are within the canopy drip line of existing street trees, contact PPI Arb Coordinator in relation to the required provision of protection measures. Note: If fencing is to protect street trees, a permit to temporarily occupy the footway will be required from Compliance and Regulatory Services. Timing: Prior to site/operational/building work occurring. PROOF OF
FULFILMENT Contextual photographic evidence to demonstrate the installation of protection measures prior to building works commencing. Timing: Prior to site / operational / building work occurring. |
As indicated |
14(b) Maintain Protection
Measures Maintain protection measures while development is occurring and remove protection measures prior to commencement of the use. Timing: While to site/operational/building work is occurring. |
As indicated |
| 15) Street Tree Replacement Provide replacement planting for the one (x1) existing southernmost street tree on the frontage of 43 Wambool Street, Bulimba to accommodate a new driveway crossover fronting the development site. PROOF OF FULFILMENT Contextual photographic evidence of installed replacement trees. OR, evidence in writing from Program Planning and Integration Arboriculture that an alternative arrangement has been made. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
15(a) Enter Arrangement Enter into an arrangement with Program, Planning and Integration Arboriculture (PPI Arb) to pay the cost or undertake works, as agreed with PPI Arb, for the removal and replacement planting of the existing street tree(s) fronting the development site. Timing: Prior to site/operational/building work commencing. |
As indicated |
15(b) Implement Arrangement Implement the arrangement agreed with PPI Arb. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 16) Streetscape Works - Neighbourhood Street
Major Carry out streetscape improvement works including concrete path (the frontage of 43 Wambool Street, Bulimba) and turf to the verge to a Neighbourhood Street Major standard in accordance with the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD), the requirements of this condition and the Infrastructure Design Planning Scheme Policy including sections 3.7.4.4 and 3.7.5. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
16(a) Concrete Path Install a 1.8m wide broom finished standard Portland grey concrete path. The edge of the path is to be setback 1300mm from the back of kerb.
Where the path cannot be installed on this alignment due to conflicts such as
street trees, or power poles, ensure the path is installed a minimum distance
of: If the above requirements cannot be achieved, contact the Landscape Architecture Team via email: specialistservices@brisbane.qld.gov.au. Transition to existing paths on verges that adjoin the development. The transition is to occur fronting the adjoining developments, not the subject site. Note: standard path alignments are shown on Brisbane Standard Drawing BSD-5201 sheet 2 but will vary depending on verge width and location. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Photographic evidence of concrete path. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
16(b) Submit As-Constructed
Drawings Submit to Development Services As Constructed plans including an asset register, checked by a Registered Professional Engineer Queensland, certifying that the concrete path works have been completed in accordance with relevant Brisbane Planning Scheme Codes/Policies. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT As constructed drawings signed by an RPEQ. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
16(c) Turf Install turf to the full width of the verge excluding any concrete path required by this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Photographic evidence of installed turf. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 17) Landscape the Site - Self Certification Landscape the site in accordance with the requirements of this condition. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
17(a) Detailed Landscape Plan for Self-
Certification Prepare a Detailed Landscape Plan at a scale of 1:100 for all on-site landscape works including planting areas identified on the approved DRAWINGS AND DOCUMENTS. The plan must be prepared by a Qualified Landscape Architect and must comply with the relevant Brisbane Planning Scheme Codes. The
plan must include the following: Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
17(b) Multiple Unit Dwelling In addition to the
requirements listed above, the plan must include the following: Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
17(c) Certify Detailed Landscape
Plan On completion of the Detailed Landscape Plan, submit to Development
Services: Timing: Prior to building work commencing. PROOF OF FULFILMENT A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to building work commencing. |
As indicated |
17(d) Implement Certified Detailed Landscape
Plan Carry out the landscape work in accordance with the above certified detailed Landscape Plan. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
17(e) Certify Work On completion of the
landscape work, submit to Development Services: Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT An as constructed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
17(f) Maintain Landscape Work Maintain the landscape work, including deep planting, in accordance with the certified Detailed Landscape Plan. Timing: To be maintained. |
As indicated |
| 18) On-site Erosion (Medium Risk) Manage on-site erosion and the release of sediment or sediment laden water from the site at all times by implementing best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version). Timing: Prior to commencement of any land disturbing activities and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
18(a) Manage earth disturbance on-
site (i) Drainage control measures must be implemented and maintained to minimise water flow onto areas of exposed earth. (ii) Sediment and erosion control measures must be implemented and maintained to prevent soil loss from earth disturbance areas and prevent deposition beyond earth disturbance areas. (iii) No release of contaminants to land beyond on-site area of earth disturbance other than releases that achieve water pollutant concentration release limits of: A. 50mg/L TSS (Total Suspended Solids); B. Turbidity, Nephelometric Turbidity Units (NTU) value less than 10% above background, 75 NTU, or as agreed in writing by an Officer from Councils Erosion and Sediment Control (ESC) Team in Compliance and Regulatory Services; C. pH between 6.5 and 8.5 at all times. (iv) Maintain a written record to demonstrate that water discharges from the site, including any dewatering operations, meet the release limits as detailed in (iii) for water discharge(s) from the site that occur during or immediately after a rainfall event, and during normal business hours. The water quality of the discharge flows must be measured at each discharge point from the site, including but not limited to sediment basin outlets, other applicable sediment control devices, the site water drainage system, and recorded against the release limits at least once on each calendar day until such discharge stops. Timing: Prior to commencement of any earth disturbing activities and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
18(b) Provide Land Occupier Notification to
Council (i) Notify Council's ESC Team of proposed land occupier/s by sending an email to CARS-ESC@Brisbane.qld.gov.au (ii) If the land is to be occupied by any person other than the registered landowner then advice must be provided to Council that confirms the name, contact information and the duration of any proposed occupation of the land. Timing: Prior to commencement of any earth disturbing activities. |
As indicated |
18(c) Prepare Erosion and Sediment Control
Plan Prepare an Erosion and Sediment Control Plan (ESCP) in accordance with best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version) and, to the extent of any inconsistency, relevant Brisbane Planning Scheme Codes and Policies. Obtain a design certificate in accordance with the relevant Brisbane Planning Scheme Codes and Policies. The ESCP and design certificate must be certified by a Certified Professional in Erosion and Sediment Control (CPESC) or a Registered Professional Engineer Qld (RPEQ) with suitable qualifications and experience in erosion and sediment control. Documentary evidence demonstrating appropriate qualifications in erosion and sediment control must be provided to the Council upon request. Timing: Prior to the commencement of any earth disturbing activities. |
As indicated |
18(d) Attend a pre-start
meeting Arrange and attend a pre-start meeting for ESC with an Officer from Councils ESC Team in Compliance and Regulatory Services (CARS). Note: To request a pre-start meeting from Council's ESC Team send an email to CARS-ESC@Brisbane.qld.gov.au. All relevant documentation, including both the certified ESCP and the certified design certificate, must be attached to this email. Please allow up to 10 business days for your request to be processed. Timing: Attend the pre- start meeting prior to the commencement of any earth disturbing activities. |
As indicated |
18(e) Implement Certified Erosion and
Sediment Control Plan Implement the certified ESCP and maintain all ESC measures in accordance with best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version) and, to the extent of any inconsistency, relevant Brisbane Planning Scheme Codes and Policies. The ESCP and design certificate must be available on site at all times for inspection by Council officers. Any alteration to supplementary or Type 3 ESC measures must be reflected in the certified ESCP. Any alteration to Type 2 or Type 1 ESC measures will require a revised ESCP and design certificate that has been certified by either the CPESC or RPEQ. Timing: While earth disturbing activities are occurring and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
| 19) Information Signage Erect an information sign on the subject property in
accordance with Council's general requirements for signage and in accordance
with the requirements outlined below: Timing: Prior to site works commencing and then to be maintained until completion of the development for all stages. |
As indicated |
| 20) Filling and / or Excavation All earthworks must be carried out in accordance with the relevant Brisbane Planning Scheme Codes. |
Prior to building work commencing |
20(a) Submit Earthworks
Drawings Submit to, and obtain approval from, Development Services earthworks drawings prepared and certified by a Registered Professional Engineer Queensland in accordance with the approved DRAWINGS AND DOCUMENTS and the relevant Brisbane Planning Scheme Codes. The Earthworks Drawings
must include the following: Note: If the earthworks impact on the road reserve, the Developer must obtain applicable footpath and road permits prior to commencing any works. Such impacts may include footpath occupation, road closures, re-profiling, ground anchors and/or relocation of services. If the excavation has to be stabilised using ground anchors or similar, then the submitted plans must show the location of these in relation to all services. The cost of moving services, utilities and assets is the responsibility of the Developer. The permission of the service/utility/asset owner is required. Note: Irrespective of final earthworks, it is the responsibility of the RPEQ to manage any staged works associated with Erosion & Sediment Control. Timing: Prior to site/operational/building work commencing. |
As indicated |
20(b) Fill Material, Placement, Compaction
and Testing All fill material placed on the site must comprise only natural earth and rock and must be free of contaminants (as defined by Part 3, Division 2, Subdivision 2 Environmental contamination, Section 11 of the Environmental Protection Act 1994) and noxious, hazardous, deleterious and organic materials. Fill material, placement, compaction and testing must comply with the requirements of Australian Standard - AS 3798, Guidelines on Earthworks for Commercial and Residential Developments. Timing: While site/operational/building work is occurring. |
As indicated |
20(c) Implement Approved Earthworks
Drawings Construct and maintain the earthworks in accordance with the requirements of AS3798 and the approved earthworks drawings. Timing: While site/operational/building work is occurring and then to be maintained. |
As indicated |
20(d) Submit As Constructed
Drawings Submit to Development Services As Constructed drawings prepared by a Registered Surveyor. Timing: Prior to building work above ground commencing. |
As indicated |
20(e) Submit Certification Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the approved earthworks drawings. Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that all fill material used complies with the quality requirements of this condition and that placement, compaction and testing has been carried out in accordance with AS3798. Timing: Prior to building work above ground commencing. |
As indicated |
| 21) Basement Excavation and Support Basement excavation and support of all exposed walls must be carried out in accordance with the relevant Brisbane Planning Scheme Codes and the requirements of this condition. |
Prior to building work commencing |
21(a) Prepare Engineering
Drawings Engineering drawings for the work required by this condition must be prepared and certified by a Registered Professional Engineer Queensland (Structural), in accordance with the relevant Brisbane Planning Scheme Codes detailing the design of the proposed excavation as well as proposed temporary and permanent support (if no temporary proposed) systems. The design must include at least the following: Notes: Timing: Prior to site/operational/building work commencing. |
As indicated |
21(b) Implement Certified Engineering
Drawings Construct and maintain the basement excavation and proposed support system in accordance with the above certified engineering drawings. Note: A copy of the certified engineering drawings must be available on- site for inspection by Council Officers during these works. Timing: While basement excavation and support system installation is occurring. |
As indicated |
21(c) Submit Post Construction
Certification Submit certification by a Registered Professional Engineer Queensland that the basement excavation and support have been installed in compliance with the certified engineering drawings, the relevant Brisbane Planning Scheme Codes and the requirements of this condition. Where ground or rock anchors have been installed, submit certification by a Registered Professional Engineer Queensland (Geo-technical) that all anchors have been de- stressed. Timing: Prior to building work commencing above ground. |
As indicated |
| 22) Construction Management Plan (Minor) Carry out development in a method consistent with a Construction Management Plan (Minor) prepared in accordance with the requirements of this condition. |
While site/operational/building work is occurring |
22(a) Construction Management Plan (Minor) -
Prepare Plan Prepare a detailed Construction Management Plan (CMP) for the
construction phase of the approved development.The Construction Management Plan
must be in accordance with the relevant Brisbane Planning Scheme Codes and
address the following: The Construction Management Plan must be supported by 'approval in principle' or written approvals from the relevant Council sections or other governing bodies responsible for any potentially impacted infrastructure. The list of relevant infrastructure and contacts is available on Council's website - Search 'Construction Management Plan'. Note: The Construction Management Plan is not required to be approved by Development Services. Timing: Prior to site/operational/building work commencing. |
As indicated |
22(b) Construction Management Plan (Minor) -
Submit Plan Submit a copy of the Construction Management Plan to Council's Development Services Branch at the following mailbox: engineeringservices@brisbane.qld.gov.au quoting the BCC planning development approval reference number. Timing: At least 10 days prior to site works commencing. |
As indicated |
22(c) Construction Management Plan (Minor) -
Documentation on Site Legible copies of the Construction Management Plan and current permits must be kept on site and be made available on request by Council at all times. The requirements of the CMP must be included in all induction of principal and subcontractors utilised in the development. An outline of the induction provided to contractors may be requested by Council to confirm compliance with this condition. Timing: While site/operational/building work is occurring. |
As indicated |
22(d) Construction Management Plan - Works to
be Performed Out of Hours Obtain an approval from Development Services for any
work that is proposed to be undertaken outside of normal business hours -
6:30am to 6:30pm, Monday to Saturday. |
As indicated |
22(e) Implement Construction Management Plan
(Minor) Carry out the development in accordance with the submitted Construction Management Plan. |
While site/operational/building work is occurring |
| 23) Protect Existing Infrastructure Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure. Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations. The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements. |
While site/operational/building work is occurring |
23(a) As Constructed Drawings - Alterations
to Existing Infrastructure Submit to Development Services As Constructed drawings showing all new and/or rectification works and an asset register, prepared by a Registered Professional Engineer Queensland. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 24) Remove Improvements & Obstructions from Truncation
and Dedication Remove all improvements (fences, gates, letter boxes, garden beds and plots and other constructed items, etc.) and obstructions (existing earth banks, vegetation, etc.) from the area of the dedicated road and reinstate the area as footway in accordance with the relevant Brisbane Planning Scheme Codes. Any new or existing installations of electrical pillar boxes, pad mounted transformers (PMTs), water meters and the like, must be installed/relocated to their ultimate alignment relative to the new property boundary and clear of the usable footpath areas irrespective of the alignment of the existing services/conduits. Note: The cost of moving services, utilities and assets is the responsibility of the Developer. The permission of the service, utility or asset owner will be required. Council permission is required if street trees, stormwater gullies/drains, and swales are affected. Urban Utilities permission is required if water supply and sewerage services are affected. Standard utility alignments may be found on Council's 'Brisbane Standard Drawings' 1013 to 1016 inclusive. PROOF OF
FULFILMENT Certification from a Registered Surveyor (Qld) or Registered Professional Engineer Queensland that the above work has been completed in accordance with this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 25) Retaining Walls Design and construct all retaining walls and associated fences, in accordance with the relevant Brisbane Planning Scheme Codes and the following: - All retaining walls including the footings, must be located wholly within the property boundaries of the site where works are occurring - Runoff from surface drains and subsoil drainage associated with the retaining walls must be collected and connected to a lawful point of discharge (LPD) where possible. If no LPD is available the surface drains and sub-soil drainage must be designed, installed and discharged to ensure there is no ponding, nuisance or concentration of stormwater discharge to adjacent properties. - Retaining walls to stabilise excavation must be set back from property boundaries to accommodate subsoil drainage without encroachment into the neighbouring property. This set back may vary depending on the height, structure and design of the retaining wall, surcharge loadings from neighbouring properties, and to provide a surface drain along the top of the retaining wall - For retaining walls in excess of
1.0m in height: NOTE: Refer to City Plan 2014; Infrastructure Design Planning Scheme Policy (IDPSP) for Council’s definition of a LPD. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
25(a) Certification of Retaining
Walls For retaining walls over 1.0m in height, obtain certification from a Registered Professional Engineer Queensland that the design and construction of the retaining walls and ancillary drainage are in accordance with the requirements of this condition. |
As indicated |
| 26) Access, Grades, Manoeuvring, Carparks, Signs and
Line Marking Construct and maintain access, parking and manoeuvring for vehicles on site in accordance with the relevant Brisbane Planning Scheme Codes, as indicated on the approved DRAWINGS AND DOCUMENTS, including the following: i. A pavement of minimum Local road standard or equivalent surface material (including associated drainage) to the area on which motor vehicles will be driven and/or parked. ii. Standing on site for a Rear Loading Refuse Collection Vehicle and for the loading and unloading of vehicle(s). iii. Parking on the site for 19 resident/tenant cars and two visitor cars, and for the loading and unloading of vehicle(s) within the site. iv. Provide and maintain eight secure resident/tenant bicycle parking spaces and two visitor bicycle parking spaces. v. A minimum of 2.3 metres height clearance to all undercover parking areas, including the entry and access to these areas. The minimum clear height must be measured to the lowest protrusion from the ceiling (e.g. fire sprinklers, services, lighting fixtures, signs, etc). vi. A height clearance sign located at the entrance(s) to undercover car parking areas and a directional visitor parking sign clearly visible from the vehicle entrance to the site. vii. An appropriate area for the storage and collection of refuse, including recyclables, in a position which is accessible to service vehicles on the site. viii. Prepare and implement signs and line markings drawings that show the internal paved areas signed and delineated in accordance with the approved drawings and documents. The drawings must be prepared and certified by a Registered Professional Engineer Queensland in accordance with the relevant Brisbane Planning Scheme Codes and the Manual of Uniform Traffic Control Devices. ix. Install the hold bay and traffic signal system in accordance with the ITE Consulting “Traffic Impact Statement Report”, Report Number 001, Revision Number 01 received 20 March, 2023. x. Install the sight triangles at the start of the internal driveway, in accordance with the ‘Ground Floor Plan’, Drawing Number DA1.02 Issue 3, received by Council on 26/02/2026 and amended in red on 02/04/2026.
PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland, that the above requirements have been implemented in accordance with this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 27) Repair Damage to Kerb, Footpath or Road Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
27(a) Interim Repairs If at any time during the construction phase of the approved development, damage to the existing kerb and channel, footpath or roadway creates unsafe, unreasonable and/or not fit for purpose conditions as assessed by Council, interim repairs must be undertaken as directed by Program Planning and Integration. Note: Any interim repairs required to be undertaken shall not be considered to satisfy the requirements of this condition for the permanent repair of the infrastructure prior to the issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. Timing: While site / operational / building works is occurring. |
As indicated |
| 28) Refuse Collection - On Site Provide for the installation and collection of refuse/recycling bins by Brisbane City Council's Waste and Resource Recovery Services or a private waste contractor. |
At all times |
28(a) Arrange Refuse Collection Arrange for the installation of refuse/recycling bins and for the subsequent collection of refuse including recycling from the site by Brisbane City Council's Waste and Resource Recovery Services or a private waste contractor. Timing: A minimum of four weeks prior to the commencement of use and then to be maintained. PROOF OF FULFILMENT Where a private waste contractor is engaged, provide written confirmation from the proposed waste collection contractor of the agreement to service the property. The written agreement must be submitted to Council's Waste and Resource Recovery Services and include full details of the proposed system, bin sizes, number of bins, frequency of collection and the refuse collection vehicle size. Timing: Prior to commencement of use. |
As indicated |
28(b) Indemnify Council The owner and any subsequent owner must, by approved form to Waste and Resource Recovery Services, indemnify Council and its agents in respect of any damage to the pavement and other driving surfaces. Timing: When an arrangement for refuse/recycling collection services is made with Brisbane City Council. |
As indicated |
28(c) Notify Future Owner Where Council is engaged as the waste contractor, the owner must notify any future owner/body corporate that the development has been approved on the basis that an indemnity must be provide for refuse collection vehicles to enter the property. Timing: At time of a change of ownership. |
As indicated |
| 29) Refuse Storage - On Site Collection Provide a roofed and wholly screened refuse enclosure utilising materials consistent with the development or a dedicated refuse storage room, as shown on the approved plans and documents. The enclosure/refuse storage room must be of a design to accommodate the quantity of refuse and recycling including source separation to allow for low servicing collection of the development. Bins must be located in an area which allows them to be manoeuvred from the bin storage area to the designated internal collection point. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 30) Land for Transport Network - Road (Non-
trunk) Dedicate as road land shown as new road (non-trunk) on the APPROVED ‘Site Plan’, Drawing no. DA1.00 Issue 2, received by Council on 25/07/2023 and amended in red on 02/04/2026, including the following:
i. A widening along the full length of the Wambool Street frontage of the site to achieve a verge width of 3.75 metres measured from the existing nominal face of the kerb in Wambool Street.
Note: This condition is imposed under section 145 of the Planning Act 2016. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
30(a) Submit Plan of
Subdivision Submit to, and obtain approval from, Development Services, a plan of subdivision showing the land to be dedicated for road to demonstrate compliance with the requirements of this condition. Timing: As part of the submission of the request pursuant to Schedule 18 of the Planning Regulation 2017 for Council's notation on the plan of subdivision necessary to comply with this condition. |
As indicated |
30(b) Lodge Notated Plan Lodge the plan of subdivision notated by Council pursuant to Schedule 18 of the Planning Regulation 2017 with the Registrar of Titles for the relevant Queensland State Government Authority. Timing: Prior to commencement of use. PROOF OF FULFILMENT Evidence of the registration of the required plan of subdivision. Timing: Within one month of the registration of the plan of subdivision. |
As indicated |
| 31) Remove Redundant Drainage Outlets Remove any redundant drainage outlets from the kerb and channel
including any associated pipe work across the footway and reinstate the kerb
and channel and the footway area in accordance with the relevant Brisbane
Planning Scheme Codes. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 32) All Basements - Stormwater Runoff Design and construct basements to manage stormwater runoff in accordance with the relevant Brisbane Planning Scheme Codes and the following: (i) All stormwater pump systems must be designed to gravity drain to a Council stormwater system. (ii) The driveway into a basement must be designed and constructed to minimise local driveway stormwater runoff entering the basement. The drainage must be designed to capture runoff from a 10% AEP rainfall event and gravity drain to a lawful point of discharge. (iii) Vehicle access into any basement from a Council road will require the basement driveway to ramp up a minimum of 200mm, above adjacent road channel invert, to maintain road major flow capacity. (iv) All roofwater drainage is to be directed to a lawful point of discharge via gravity drainage, not directed into the basement. (v) Any stormwater within a basement that connects via gravity drainage directly to a council pipe or manhole must incorporate backflow prevention devices. PROOF OF
FULFILMENT Certification from a Registered Professional Engineer Queensland that the development has been designed and constructed in accordance with this condition. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 33) Ponding of Stormwater Carry out the approved development to ensure that adjoining properties and roads are protected from ponding or nuisance from stormwater during construction. Notes: If remedial works are necessary to comply with this condition, prior approval must be obtained from Development Services. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 34) On Site Drainage - Minor Provide a stormwater connection to all new or existing allotments and provide drainage infrastructure to ensure stormwater run-off from all roof and developed surface areas will be collected internally and piped in accordance with the relevant Brisbane Planning Scheme Codes to a lawful point of discharge and as shown on the approved ‘Concept Services Plan’ Drawing reference 23012/SK10, Revision A, received by Council on 20/03/2023. Note: - Guidance for requesting a pre-start and co- ordinating the On/Off Maintenance process can be found on Council's website (https://www.brisbane.qld.gov.au/planning-and- building/applying-and-post-approval/on-and-off-maintenance- approvals). |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 35) Service Conduits and Mains Provide and install all
service conduits and meet the cost of any alterations to public utility mains,
existing mains, services, street lighting or installations that are required to
carry out the approved development. These works must be in accordance with the
relevant Brisbane Planning Scheme Codes, and include the following, where
applicable: Note: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
35(a) Submit As Constructed
Drawings Submit to Development Services As Constructed drawings, including an asset register, prepared and certified by a Registered Professional Engineer Queensland. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the requirements of this condition. Note: Civil works are to be certified by a RPEQ(Civil) and electrical works are to be certified by a RPEQ (Electrical). |
As indicated |
| 36) Telecommunications Submit to Development Services, certification from
an authorised telecommunications carrier/contractor, that the following works
and infrastructure have been undertaken and installed in accordance with
telecommunications industry standards: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 37) Agreement with Electricity Supplier Submit to Development Services, evidence of an agreement with an electricity supplier to provide necessary services to the development in accordance with the relevant Brisbane Planning Scheme Codes. Where development is within an established area of overhead electricity supply and the electricity supplier determines that a property pole is the appropriate solution to supply electricity to the development, the developer must be responsible for the installation of the property pole(s). In the above circumstances, submit to Development Services, certification from the developer's electrical consultant confirming that the above installation has been completed in accordance with the relevant AS/NZS Standards and the Queensland Electricity Connection Manual (QECM) and Queensland Electricity Metering Manual (QEMM). |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 38) Permanent Driveway Crossover Provide a 6.5 metre wide Type B1 permanent driveway crossover to the Wambool Street frontage of the site in accordance with the relevant Brisbane Planning Scheme Codes and located as shown on the approved DRAWINGS AND DOCUMENTS. Written consent must be obtained from Program, Planning and Integration Arboriculture (PPI Arb) prior to any works occurring that will either impact on or require removal of a street tree (this includes pruning, excavation or fill within the root zone/canopy of the tree). At all times during construction of the crossover, safe pedestrian access along the site frontage must be maintained. Note: No further driveway permit is required however additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 39) Redundant Driveway Crossover Remove the redundant existing driveway crossover(s) on the frontage(s) of the site and reinstate the kerb and channel, road pavement, footways and footpaths in accordance with the relevant Brisbane Planning Scheme Codes. Note: Additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 40) Further Development Permit required This Development Approval to carry out building work made assessable under the planning scheme for Brisbane does not include an assessment of building work against the requirements of the Building Act and does not permit building work to occur unless, prior to the commencement of any building work, a Development Permit(s) to carry out assessable building work under the Building Act has been issued. |
As indicated |
| 41) Construction Noise and Dust Emissions Pursuant to the Environmental
Protection Act 1994, all development involving the emission of noise and dust
from building and/or construction activities, must ensure that the emissions
are in accordance with the requirements of the Act. |
As indicated |
| 42) Currency Period The currency period for this development approval is
stated in the Decision Notice. The currency period for this development approval is
expressed as a date. This development approval lapses at the end of the
currency period (the date stated in the decision notice)
if: - for a material change of
use, the first change of use does not happen;
- for reconfiguring a lot, the plan of subdivision for the reconfiguration is
not given to Council; or
- for any other development (including building work and operational work), the
development does not substantially start. The currency period is determined by Council pursuant to section 85 of
the Planning Act 2016. |
As indicated |
| 43) Water and Wastewater Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. For further information about any necessary Water Approvals contact Urban Utilities. |
As indicated |
| 44) Advice Please note that the information contained in this section under the heading Standard Advice has been provided as advice only and does not form part of the development approval conditions. This information has been provided to advise of other obligations under state legislation or local laws that may require action to be undertaken prior to commencing the activity approved by this development approval. |
As indicated |
| 45) Cultural Heritage Aboriginal cultural heritage is protected under the Aboriginal Cultural Heritage Act 2003 This Act establishes a cultural heritage duty of care and in section 23(1) mandates that a person who carries out an activity must take all reasonable and practicable measures for ensuring activities are managed to avoid or minimise harm to Aboriginal cultural heritage. The Duty of Care Guidelines gazetted pursuant to the Aboriginal Cultural Heritage Act 2003 provide guidance on identifying and protecting Aboriginal cultural heritage to fulfil the duty of care. If you are unsure of your obligations contact the relevant Queensland State Government Department (Department of Aboriginal and Torres Strait Islander Partnerships). |
As indicated |
| 46) Damage to Trees on Adjoining Lots Please note that any damage caused to vegetation on adjoining lots as a result of exercising this development approval may result in civil action. |
As indicated |
| 47) Fire Ant Movement Controls To prevent the spread of fire
ants, the Queensland Government has implemented movement controls in areas of
Queensland (biosecurity zones) where this pest species has been detected. These
controls apply to individuals and commercial operators, and restrict the
movement of materials that could carry fire ants which include soil, turf,
potted plants, mulch, baled hay or straw, animal manures, mining or quarry
products. |
As indicated |
| 48) Water and Wastewater Services for water and wastewater (sewerage) are no longer under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections requires a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. Any necessary Water Approval must be obtained from the relevant distributor- retailer (currently operating as Queensland Urban Utilities for the Brisbane City Council area). For the purpose of approving plans of subdivision pursuant to Schedule 18 of the Planning Regulation 2017 (whether in relation to a development permit for Reconfiguring a Lot or a Building Format Plan subsequent to a development permit for a Material Change of Use), documentary evidence, issued by the relevant distributor-retailer, must be provided to Council to verify that the conditions of any necessary Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009, have been complied with. |
As indicated |
| Permit to Which These Conditions Relate: | DA - PA - Building Work |
| Activity(ies): | multiple dwelling |
| Stage: | Multiple Dwelling (8 Units) in Traditional Building Character Overlay |
| 49) Building Format Plan Where the timing of a condition, or part thereof , states 'Prior to issue of Certificate of
Occupancy/Final Inspection Certificate' or 'Prior to commencement of use' and
the development involves the creation of a Building Format Plan, the timing of
the condition, or part thereof, is taken to mean 'prior to Council's
endorsement of any plan of subdivision'. |
As indicated |
| 50) Approved Drawings and Documents A legible copy of the
Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package
must be maintained on site and kept available for inspection by site workers
and Council officers. |
While site/operational/building work is occurring |
| 51) Carry Out the Approved Development Carry out the approved
development generally in accordance with the approved DRAWINGS AND
DOCUMENTS. |
While site/operational/building work is occurring and then to be maintained |
| 52) Complete All Building Work Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out generally in accordance with the approved DRAWINGS AND DOCUMENTS, and, where the building work is assessable development, in accordance with a current development approval. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
| 53) Maintain the Approved Development Maintain the approved
development generally in accordance with the approved DRAWINGS AND DOCUMENTS,
and any relevant Council engineering or other approval required by the
conditions. |
To be maintained |
| 54) External Details External details of the building, facade treatment and external materials, colours and finishes must be consistent with the approved DRAWINGS AND DOCUMENTS. Note: The requirement to use particular materials and finishes is imposed only for the purpose of achieving a built form outcome that displays architectural merit. Council has not assessed the materials and finishes for compliance with the Building Act, the Building Fire Safety Regulation, the Building Regulation, the Building Code of Australia, the Queensland Development Code, relevant Australian Standards, fire safety standards or any other relevant requirement of a statutory authority with regard to building work. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 55) Overall Height The overall height of the proposed building(s) must
be in accordance with the floor and roof levels and overall height shown on the
APPROVED DRAWINGS AND DOCUMENTS. |
While site/operational/building work is occurring and then to be maintained |
55(a) Submit Certification Submit to Development
Services certification from a registered surveyor confirming that the “as
constructed” floor and roof levels and overall height are in accordance
with the requirements of this condition. |
As indicated |
| 56) Further Development Permit required This Development Approval to carry out building work made assessable under the planning scheme for Brisbane does not include an assessment of building work against the requirements of the Building Act and does not permit building work to occur unless, prior to the commencement of any building work, a Development Permit(s) to carry out assessable building work under the Building Act has been issued. |
As indicated |
| 57) Construction Noise and Dust Emissions Pursuant to the Environmental
Protection Act 1994, all development involving the emission of noise and dust
from building and/or construction activities, must ensure that the emissions
are in accordance with the requirements of the Act. |
As indicated |
| 58) Currency Period The currency period for this development approval is stated in the
Decision Notice. The currency period for this development approval is
expressed as a date. This development approval lapses at the
end of the currency period (the date stated in the decision notice)
if: - for a material change of use, the first
change of use does not happen; - for
reconfiguring a lot, the plan of subdivision for the reconfiguration is not
given to Council; or - for any other development
(including building work and operational work), the development does not
substantially start. The currency period is determined by
Council pursuant to section 85 of the Planning Act 2016. |
As indicated |
| 59) Water and Wastewater Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. For further information about any necessary Water Approvals contact Urban Utilities. |
As indicated |
| 60) Advice Please note that the information contained in this section under the heading Standard Advice has been provided as advice only and does not form part of the development approval conditions. This information has been provided to advise of other obligations under state legislation or local laws that may require action to be undertaken prior to commencing the activity approved by this development approval. |
As indicated |
| 61) Cultural Heritage Aboriginal cultural heritage is protected under the Aboriginal Cultural Heritage Act 2003 This Act establishes a cultural heritage duty of care and in section 23(1) mandates that a person who carries out an activity must take all reasonable and practicable measures for ensuring activities are managed to avoid or minimise harm to Aboriginal cultural heritage. The Duty of Care Guidelines gazetted pursuant to the Aboriginal Cultural Heritage Act 2003 provide guidance on identifying and protecting Aboriginal cultural heritage to fulfil the duty of care. If you are unsure of your obligations contact the relevant Queensland State Government Department (Department of Aboriginal and Torres Strait Islander Partnerships). |
As indicated |
| 62) Damage to Trees on Adjoining Lots Please note that any damage caused to vegetation on adjoining lots as a result of exercising this development approval may result in civil action. |
As indicated |
| 63) Fire Ant Movement Controls To prevent the spread of fire
ants, the Queensland Government has implemented movement controls in areas of
Queensland (biosecurity zones) where this pest species has been detected. These
controls apply to individuals and commercial operators, and restrict the
movement of materials that could carry fire ants which include soil, turf,
potted plants, mulch, baled hay or straw, animal manures, mining or quarry
products. |
As indicated |
| 64) Water and Wastewater Services for water and wastewater (sewerage) are no longer under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections requires a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. Any necessary Water Approval must be obtained from the relevant distributor- retailer (currently operating as Queensland Urban Utilities for the Brisbane City Council area). For the purpose of approving plans of subdivision pursuant to Schedule 18 of the Planning Regulation 2017 (whether in relation to a development permit for Reconfiguring a Lot or a Building Format Plan subsequent to a development permit for a Material Change of Use), documentary evidence, issued by the relevant distributor-retailer, must be provided to Council to verify that the conditions of any necessary Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009, have been complied with. |
As indicated |