| Address of Site: | 232 HARCOURT ST NEW FARM QLD 4005 72 JAMES ST FORTITUDE VALLEY QLD 4006 76 JAMES ST FORTITUDE VALLEY QLD 4006 U 1 76 JAMES STREET 76 JAMES ST FORTITUDE VALLEY QLD 4006 U 2 76 JAMES STREET 76 JAMES ST FORTITUDE VALLEY QLD 4006 |
| Real Property Description of Site: | L2 RP.66584 L2 RP.52228 LCommon Property SP.214209 L1 SP.214209 L2 SP.214209 |
| Aspects of development and type of approval: | DA - PA - Building Work Development Permit - Commercial Character Building
- Partial Demolition DA - PA - Material Change of Use Development Permit - food and drink outlet,shop,office DA - PA - Referral Agency for Building Work Referral Response - Flood hazard area |
| Council File Reference: | A006957138 Permit Reference Number/s: DABW399058020; DAMC399058120; DAEB439518823. |
| Package Status: | APPROVED - Version 3 (8th of June, 2026 8:01:13 AM) |
| Package Generated: | 08/06/2026 |
| Julie BONFIELD Senior Architect Architecture Team Julie.Bonfield@brisbane.qld.gov.au 31782575 |
Glyn CHISHOLM Senior Landscape Architect Landscape Architecture Team Glyn.Chisholm@brisbane.qld.gov.au 07 3403 0117 |
Kaye ATKINS Team Manager Planning Application Review Service Kaye.ATKINS@brisbane.qld.gov.au (07) 31780015 |
| Jacqueline PATON Senior Architect Architecture Team Jacqueline.Paton@brisbane.qld.gov.au 07 3178 0389 |
Tim WRAFTER Principal Engineer Engineering Services Hydraulics Tim.Wrafter@brisbane.qld.gov.au |
Dominic PERRY Senior Engineer Engineering Scoping dominic.perry@brisbane.qld.gov.au (07) 3403 8888 |
| Martin MOLLEE Senior Environmental Management Officer Environmental Management Services Martin.Mollee@brisbane.qld.gov.au (07) 3403 8888 |
Rhea CONNOLLY Principal Urban Planner Planning Services North Rhea.Connolly@brisbane.qld.gov.au 3178 0651 |
Patrick LEE Senior Engineer Engineering Services South Patrick.Lee@brisbane.qld.gov.au 0734039050 |
| Peter RICHARDS Principal Urban Planner Planning Services Prelodgement prelodgementservices@brisbane.qld.gov.au (07) 3403 6302 |
Kathy BAGULEY Principal Urban Planner Planning Services North DSPlanningSupport@brisbane.qld.gov.au 07 3403 5510 |
Ken LEOWARDI Engineer Engineering Services North Ken.Leowardi@brisbane.qld.gov.au (07) 3403 5689 |
| Matthew O'DEA Principal Landscape Architect Landscape Architecture Team Matthew.ODea@brisbane.qld.gov.au 31789513 |
George KOUPARITSAS Architect Architecture Team George.Kouparitsas@brisbane.qld.gov.au 31787245 |
Chris.M DIXON Senior Urban Planner Planning Services North chris.m.dixon@brisbane.qld.gov.au 31787264 |
| MAISIE TANG Principal Urban Planner Planning Services North maisie.tang@brisbane.qld.gov.au (07) 31789048 |
Chris.M DIXON Senior Urban Planner Planning Services North chris.m.dixon@brisbane.qld.gov.au 31787264 |
MAISIE TANG Principal Urban Planner Planning Services North maisie.tang@brisbane.qld.gov.au (07) 31789048 |
DRAWINGS AND DOCUMENTS
| Drawing or Document | Number | Plan Date |
|---|---|---|
| Section C | DA-3-013 Revision C | 27-APR-2026 |
| Section D | DA-3-014 Revision B | 27-APR-2026 |
| Section Detail A | DA-3-015 Revision A | 27-APR-2026 |
| Section Detail B | DA-3-016 Revision A | 27-APR-2026 |
| Section Detail C | DA-3-017 Revision A | 27-APR-2026 |
| Section Detail D | DA-3-018 Revision A | 27-APR-2026 |
| Civil Services Pavement Plan | C09-001 Issue C (Amended In Red 20-SEP-2024) | 13-AUG-2024 |
| Civil Public Domain Alignment Control Plan | C11-501 Issue B (Amended In Red 20-SEP-2024) | 07-JUN-2024 |
| Landscape DA 72-76 James Street | 19090 Rev. J (Amended In Red 20-MAY-2026) | 21-JAN-2026 |
| Civil Services Bulk Earthworks Plan | C04-001 Issue B (Amended In Red 20-SEP-2024) | 21-JUN-2024 |
| Civil Services Bulk Earthworks Sections | C04-101 Issue B | 21-JUN-2024 |
| Civil Services General Arrangement Plan | C05-001 Issue D (Amended In Red 20-SEP-2024) | 13-AUG-2024 (Received) |
| Floor Plans Mezzanine + Level 1 | DA-2-003 Revision A | 30-JAN-2026 |
| Ground Floor + Roof Plans - Existing & Demolition | A-SD - 111 Issue: I | 16-AUG-2024 (Received) |
| Elevations - Existing & Demolition | A-SD - 115 Issue: H | 16-AUG-2024 (Received) |
| Floor Plans Basements 2 + 3 | DA-2-001 Revision C | 22-APR-2026 |
| Floor Plans Basement 1 + Ground | DA-2-002 Revision C | 22-APR-2026 |
| Floor Plans Levels 2 + 3 | DA-2-004 Revision A | 30-JAN-2026 |
| Floor Plans Roof | DA-2-005 Revision A | 30-JAN-2026 |
| Elevation James Street | DA-3-001 Revision A | 30-JAN-2026 |
| Elevation Harcourt Street | DA-3-002 Revision A | 30-JAN-2026 |
| Elevation North-East | DA-3-003 Revision A | 30-JAN-2026 |
| Elevation North-West | DA-3-004 Revision A | 30-JAN-2026 |
| Section A | DA-3-011 Revision B | 27-APR-2026 |
| Section B | DA-3-012 Revision B | 27-APR-2026 |
APPROVAL CONDITIONS
| Permit to Which These Conditions Relate: | DA - PA - Building Work |
| Activity(ies): | Commercial Character Building - Partial Demolition |
| Stage: | Partial demolition of a Commercial character building |
| 1) Maintain the Approved Development Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions. |
At all times |
| 2) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers. Note: This condition is imposed to ensure compliance with the conditions of development approval. |
While site/operational/building work is occurring |
| 3) Carry Out the Approved Development Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS. Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners. |
While site/operational/building work is occurring |
| 4) Complete All Building Work Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS. Note: Building work must also be completed in accordance with any other current development approval. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 5) Commercial character building - Submit Evidence of
Completion Submit to Development Services documentary and photographic evidence to demonstrate that the Commercial character building has been reinstated in accordance with the conditions of this component of the approval and is capable of the approved lawful use. Timing: Within 3 months of the Commercial character building being reinstated or prior to commencement of use, whichever comes first. |
As indicated |
| 6) Commercial character building - Structural
Report Submit to Development Services a report prepared and certified by a
Registered Professional Engineer Queensland (Structural) and suitably
experienced in heritage, commercial character building and/or pre-1947
traditional building character assessments to demonstrate: |
Prior to site works commencing |
| 7) Partial Demolition of Building Partial
demolition resulting from this approval must be in accordance with the APPROVED
DRAWINGS AND DOCUMENTS and all building work must comply with this
condition. Provide confirmation from a Building Certifier or
appropriately qualified (RPEQ) Fire Engineer that the external timber elements,
documented on the APPROVED DRAWINGS AND DOCUMENTS, to be retained on the
commercial character building remaining on the site are to be retained and can
satisfy the requirements of the National Construction Code. The confirmation
should describe how timber framed and timber clad building components can be
retained and the method of fire protection. Timing:
Prior to site works and/or building works commencing on
site |
While site/operational/building work is occurring and then to be maintained |
7(a) Adequate Bracing Provide adequate bracing from the commencement of any demolition work and throughout the demolition and construction phases of the project, to ensure that all parts of the commercial character building not specifically designated for demolition on the APPROVED DRAWINGS AND DOCUMENTS are retained and protected. The Commercial character building is to
be reinforced, braced and protected and is not to be relocated within the site
during the course of works for the development. |
As indicated |
7(b) Retain Original Fabric Retain all existing external original fabric in
the sections of the commercial character building which are not being
demolished. This will include, but is not limited to, existing decorative
detailing, wall cladding, windows, doors, stairs, awnings, floor, floor framing
and roof sheeting. |
As indicated |
7(c) Submit Certification Submit to Development Services certification by a Registered Architect / Building Designer (holding a Queensland Building and Construction Commission Licence appropriate to the scale of the approved development) confirming that the partial demolition has been carried out in accordance with the requirements of this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use |
As indicated |
7(d) Prepare a Dilapidation
Report Submit to Development Services a dilapidation
report for the commercial character building which includes; - A set of measured
drawings (floor plans, reflected ceiling plans, roof plans, lateral and
longitudinal sections, elevations) at a scale of 1:100 or 1:50 which depicts
the existing building fabric inclusive of cladding elements, doors and window
configurations and building and roof forms. - A photographic study of
the building which catalogues each building elevation, all internal wall
elevations, all door and window elevations and is cross referenced to a key
plan showing the location from which the photo was taken and the direction of
the view depicted in the photo.
Timing: Prior to site works and/or building works commencing on site |
As indicated |
| 8) Engineering Pre-Start Meeting Arrange and attend a pre-start meeting with Development Services and Program Planning and Integration. Applicable compliance and inspection fees must be paid, in full, to Council prior to the meeting being held. Note: To arrange an engineering pre-start meeting with Development Services an email supported by a completed copy of the Pre-Start Meeting Guidelines - Civil Engineering Works kit (https://www.brisbane.qld.gov.au/sites/default/files/20191008-cc11207-pre- start-meeting-guidelines-civil-engineering-works.pdf) must be sent to dalodgement@brisbane.qld.gov.au. Details include (but
are not limited too) the following: Note: Timing: Prior to site/operational/building work commencing. |
As indicated |
| 9) CBD/City Frame Construction Management Plan Carry out development in accordance with a Construction Management Plan (CMP) prepared in accordance with the Central Business District and City Frame Development Services Construction Management Guidelines and the requirements set out in this condition. Note: This condition imposes restrictions on development construction management to regulate increased truck access, on street work zone and closures and all associated activities in the CBD and City Frame as a result of major State and Local Government infrastructure projects occurring in Brisbane. |
While site/operational/building work is occurring |
9(a) Submit Construction Management
Plan Submit to, and obtain approval from, Development Services a Construction Management Plan for the demolition, excavation and construction phases of the approved development. Separate Construction Management Plans may be appropriate for the individual components. The Construction
Management Plan must be in accordance with the Central Business District and
City Frame Development Services Construction Management Guidelines and the
relevant Brisbane Planning Scheme Codes and address the following: The Construction Management Plan must be supported by 'approval in principle' or written approvals from the relevant Council sections or other governing bodies responsible for any potentially impacted infrastructure. Timing: Prior to site/operational/building work commencing. |
As indicated |
9(b) Construction Management Plan -
Dilapidation Report Submit a dilapidation report to engineeringservices@brisbane.qld.gov.au detailing the pre-existing condition of the roadway, both footways, both verges and Council infrastructure, including vegetation, for 100m from the site entry in both directions or to the next street intersection (if less than 100m from the site entry) in both directions. Timing: Prior to the pre-start meeting. |
As indicated |
9(c) Construction Management Plan -
Associated Activities in Road Reserve Obtain relevant approvals, as listed in part (a) of this condition, to carry out any works within the road reserve required by the approved Construction Management Plan identified in the Central Business District and City Frame Development Services Construction Management Guidelines. Note: All fees must be paid in full prior to any permit being granted by Council. Council may revoke any permits at any time for non-compliance with requirements or if it considers that safety, capacity and/or operation of public transport, vehicle and pedestrian traffic are likely to be compromised during the construction phase. Timing: Prior to site/operational/building work commencing. |
As indicated |
9(d) City Frame Construction Management Plan
- Documentation on Site Legible copies of the approved CBD Construction Management Plan and current permits must be kept on site and be made available on request At all times. The requirements of the CMP must be included in all induction of principal and subcontractors utilised in the development. An outline of the induction provided to contractors may be requested by Council to confirm compliance with this condition. Timing: While site/operational/building work is occurring. |
As indicated |
9(e) Construction Management Plan - Works to
be Performed Out of Hours Obtain an approval from Development Services for any
work that is proposed to be undertaken outside of normal business hours -
6:30am to 6:30pm, Monday to Saturday. |
As indicated |
9(f) Implement Approved Construction
Management Plan Carry out the development in accordance with the approved CBD/City Frame Construction Management Plan. |
While site/operational/building work is occurring |
| 10) Construction Noise and Dust Emissions Pursuant to the Environmental
Protection Act 1994, all development involving the emission of noise and dust
from building and/or construction activities, must ensure that the emissions
are in accordance with the requirements of the Act. |
As indicated |
| 11) Contaminated Materials and Soils Any contaminated materials or soils encountered during siteworks, must be handled, stored and disposed of in accordance with the requirements of the relevant authority of the Queensland Government. A person must not dispose of contaminated soil or a hazardous substance at a place other than at a place approved by the relevant authority of the Queensland Government. |
As indicated |
| 12) Management of Asbestos Disposal, handling and restoration of any building materials containing asbestos must be in accordance with current state and federal legislation. |
As indicated |
| 13) Further Development Permit Required Further Development Permit(s) to carry out assessable building work under the Building Act may be required. |
As indicated |
| 14) Currency Period The currency period for this development approval is stated in the Decision Notice and is expressed as a date. This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016. |
As indicated |
| 15) Damage to Trees on Adjoining Land Please note that any damage caused to vegetation on adjoining land as a result of exercising this development approval may result in an offence under other legislation (e.g. Natural Assets Local Law) and/or civil action |
As indicated |
| 16) Fire Ant Movement Controls To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected. These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products. Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014. For further information contact the relevant Queensland State Government department on 13 QGOV. |
As indicated |
| Permit to Which These Conditions Relate: | DA - PA - Material Change of Use |
| Activity(ies): | food and drink outlet office shop |
| Stage: | Food and Drink Outlet, Office, Shop |
| 17) Landscaping of Vacant Site If construction for the approved development does not commence within 3 months of the demolition of the existing building(s) on site, the site must be covered in grass. Timing: Within 3 months of the demolition of the existing building(s). |
As indicated |
| 18) Security Lighting - On Site Install and maintain a suitable system of security lighting to operate from dusk to dawn within all areas where the public may gain access, including car parking areas, building entrances and vegetated areas. Ensure that all external lighting is in accordance with Australian Standard - AS4282- Control of the Obtrusive Effects of Outdoor Lighting. Ensure lighting over publicly accessible internal pathways covered by permanent awnings is in accordance with Australian Standard - AS/NZS 1158.3.1 Lighting for roads and public spaces - Pedestrian area (Category P) lighting - Performance and design requirements. Lighting must be maintained in safe and good working order. Timing: 'Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first', and then to be maintained. |
As indicated |
| 19) Car Parking The car parking within the premises must be maintained exclusively for the ancillary use of the development. The parking must not be made available to the general public and there must not be signage erected on or in the vicinity of the site advertising the availability of car parking to the general public. |
At all times |
| 20) Maintain the Approved Development Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions. |
At all times |
| 21) Limitation of Use All upper level terraces are for
the ancillary use of Tenants/staff of the site only and not to be accessible to
Patrons/visitors of the site. |
At all times |
| 22) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers. Note: This condition is imposed to ensure compliance with the conditions of development approval. |
While site/operational/building work is occurring |
| 23) Carry Out the Approved Development Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS. Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners. |
While site/operational/building work is occurring |
| 24) Complete All Building Work Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS. Note: Building work must also be completed in accordance with any other current development approval. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 25) Final External Detailing of Building Construct the development in accordance with architectural drawings approved pursuant to this condition. The architectural drawings must be in accordance with the APPROVED DRAWINGS AND DOCUMENTS, relevant Brisbane Planning Scheme Codes and the requirements of this condition. |
To be maintained |
25(a) Submit Architectural
Drawings Submit to, and obtain approval from, Development Services architectural
drawings prepared and certified by a Registered Architect or Queensland
Building Construction Commission Open Licence Class Building Designer showing
the final developed details of the facade treatment, the ground interface and
the roof top/building capping elements which depict a higher level of
documentation detail than that shown on the APPROVED DRAWINGS AND DOCUMENTS,
including: The architectural
drawings must: Timing: Prior to works commencing above ground level |
As indicated |
25(b) Pre-Start Meeting Arrange and attend a pre-start meeting with Development Services. Applicable compliance and inspection fees must be paid to Council, in full, prior to the meeting being held. Note: To arrange a pre- start meeting with Development Services an email must be sent to dalodgement@brisbane.qld.gov.au. Timing: Prior to any work commencing above ground level. |
As indicated |
25(c) Implement Approved Architectural
Drawings Carry out the building work in accordance with the approved architectural drawings. Note: The requirement to use particular materials and finishes is imposed only for the purpose of achieving a built form outcome that displays architectural merit. Council has not assessed the materials and finishes for compliance with the Building Act, the Building Fire Safety Regulation, the Building Regulation, the Building Code of Australia, the Queensland Development Code, relevant Australian Standards, fire safety standards or any other relevant requirement of a statutory authority with regard to building work. Timing: While building work is occurring and then to be maintained. |
As indicated |
25(d) Submit Certification Submit to Development Services certification by a Registered Architect or Queensland Building Construction Commission Open Licence Class Building Designer confirming that the building has been constructed in accordance with the approved architectural drawings. Timing: Prior to the Final Certificate/Certificate of Occupancy or commencement of the use, whichever comes first. |
As indicated |
| 26) Overall Height The overall height of the building(s) must be in accordance with the floor and roof levels and overall height shown on the APPROVED DRAWINGS AND DOCUMENTS. NOTE: This condition should be read in conjunction with any other relevant condition requiring minimum height clearances for basement or undercover car parking and manoeuvring areas. |
While site/operational/building work is occurring and then to be maintained |
26(a) Submit Certification Submit to Development Services certification from a registered surveyor confirming that the 'as constructed' floor and roof levels and overall height are in accordance with the requirements of this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 27) Awning Lighting System Install a lighting system to the underside of the awning over the footpath in accordance with the requirements of this condition. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
27(a) Submit Lighting Plan Submit to, and obtain approval, from Program Planning and Integration (City Lighting) a detailed Lighting Plan demonstrating that the under awning lighting complies with Australian Standard - AS/NZS 1158.3.1 - sub category P6, within - Road Lighting Part 3.1: Pedestrian area (Category P) lighting - Performance and installation design requirements and achieves glare control to ensure zero candelas (cd) at 90 degrees. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
27(b) Implement Approved Lighting
Plan Carry out the works in accordance with the approved Lighting Plan. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
27(c) Certification Submit to Program Planning and Intergration (City Lighting) certification from a licensed electrical contractor that the awning lighting has been installed in accordance with the approved Lighting Plan. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
As indicated |
27(d) Maintain the Work Maintain the awning lighting, (including operating costs) in accordance with the approved Lighting Plan from dusk to dawn. Timing: To be maintained. |
As indicated |
| 28) Screen Air Conditioning and Other Plant
Enclosures Install and maintain suitable screening to all air conditioning, lift motor rooms, plant and service facilities located at the top of or on the external face of the building. The screening structures must be constructed from materials that are consistent with materials used elsewhere on the facade of the building. There must be no individual external air conditioning units. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 29) Retain and Protect Existing Street Tree(s) Identify, retain and protect the two (x2) existing street trees on the James Street frontage including the roots unless otherwise agreed in writing with Program, Planning and Integration Arboriculture (PPI Arb). Note: Street trees are protected under the Natural Assets Local Law. Street trees must not be removed or pruned without prior approval from PPI Arb. Where driveway crossovers occur within the Tree Protection Zone (TPZ) of existing street trees, seek approval from the Arboricultural Team in Program Planning and integration, City Standards for the final driveway crossover design and construction methodology to ensure the successful retention of the existing street tree(s)
PROOF OF FULFILMENT Contextual photographic evidence that the tree has been retained in equal or greater health than before development commenced. OR, evidence in writing from Asset Services Arboriculture that an alternative arrangement has been made. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
At all times |
29(a) Implement Protection
Measures Install tree protection measures in accordance with Australian Standard - AS4970 Retention of Trees on Development Site. There must be no excavation, filling or storage of materials or plant within the drip line of the tree(s). Where works are within the canopy drip line of existing street trees, contact PPI Arb Coordinator in relation to the required provision of protection measures. Note: If fencing is to protect street trees, a permit to temporarily occupy the footway will be required from Compliance and Regulatory Services. Timing: Prior to site/operational/building work occurring. PROOF OF
FULFILMENT Contextual photographic evidence to demonstrate the installation of protection measures prior to building works commencing. Timing: Prior to site / operational / building work occurring. |
As indicated |
29(b) Maintain Protection
Measures Maintain protection measures while development is occurring and remove protection measures prior to commencement of the use. Timing: While to site/operational/building work is occurring. |
As indicated |
| 30) Street Tree Replacement Provide for replacement planting of the two (x2) existing street trees on the Harcourt Street frontage of the development site to accommodate a new driveway crossover. PROOF OF FULFILMENT Contextual photographic evidence of installed replacement trees. OR, evidence in writing from Program Planning and Integration Arboriculture that an alternative arrangement has been made. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
30(a) Enter Arrangement Enter into an arrangement with Program, Planning and Integration Arboriculture (PPI Arb) to pay the cost or undertake works, as agreed with PPI Arb, for the removal and replacement planting of the existing street tree(s) fronting the development site. Timing: Prior to site/operational/building work commencing. |
As indicated |
30(b) Implement Arrangement Implement the arrangement agreed with PPI Arb. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 31) Streetscape Works - Centre Street Carry out streetscape improvement works to the James Street and Harcourt Street verges to a City Street Minor standard in accordance with the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD), the requirements of this condition and the Infrastructure Design Planning Scheme Policy including section 3.7.4.3. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
31(a) Submit Level Details Submit to Development
Services, and obtain approval for, details of the future finished levels of the
site and building entries (both pedestrian and vehicular) to demonstrate verge
levels and crossfalls complying with the Infrastructure Design Planning Scheme
Policy including section 3.7.3.5. The details must be provided by an RPEQ in
consultation with a qualified Landscape Architect and include the
following: Timing: Prior to site/operational/building work occurring. |
As indicated |
31(b) Submit Plan for Works in
Verge Submit, to an obtain approval from, Development Services, a detailed Landscape Works in Streetscape Plan for the required improvement works in accordance with the requirements of the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD) and the Infrastructure Design Planning Scheme Policy including section 3.7.4.3. The detailed Landscape Works in Streetscape Plan must be prepared at a scale of 1:100 by a qualified Landscape Architect and include the following: DOCUMENTATION REQUIREMENTS - Finished surface levels at lot boundary and
kerb. Timing: Prior to building work above ground level commencing. |
As indicated |
31(c) Pre-Start Meeting Arrange and attend a pre-start meeting with Development Services. Applicable compliance and inspection fees must be paid to Council, in full, prior to the meeting being held. Note: To arrange a pre- start meeting with Development Services an email must be sent to dalodgement@brisbane.qld.gov.au. Timing: Prior to any work commencing to comply with this condition. |
As indicated |
31(d) Implement Streetscape
Works Remove the existing footway including affected street signage for the full length of the frontage. Carry out the works in accordance with the approved detailed Landscape Works in Streetscape Plan and to a standard and using materials in accordance with the requirements of the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD) and the Infrastructure Design Planning Scheme Policy section 3.7.4.3. Note: All existing artworks and regulatory signage must be secured and repositioned as agreed with Program Planning and Integration. Note: Any existing Brisbane Tuff or granite kerbing that is surplus to requirements must be returned to Program Planning and Integration. Note: At all times during construction provision must be made for people with a visual impairment. Where it is unavoidable that a
section of an existing Braille trail is to be blocked, or an object temporarily
located to intrude within the 1000 mm clearway on either side of the Braille
trail, the following actions must be undertaken to comply with the current
version of AS1428: Note: Lodge with and receive approval from Development Services for an 'Application for Permits Relating to Roads and Footway' prior to carrying out the approved works. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to the commencement of use, whichever comes first. |
As indicated |
31(e) Submit As-Constructed
Drawings Submit to Development Services Specialist Services As Constructed drawings including an asset register, prepared by a Registered Professional Engineer Queensland, certifying that the streetscape works have been completed in accordance with the approved detailed Landscape Works in Streetscape Plan and to a standard and using materials in accordance with the requirements of the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD) and the Infrastructure Design Planning Scheme Policy section 3.7.4.3. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
31(f) On-Maintenance Acceptance Arrange an on- maintenance inspection with Development Services and obtain written confirmation that the works have been accepted on-maintenance. Provide proof of Public Liability Insurance ($20 million) for the on- maintenance period. Lodge a bond for the streetscape works maintenance period of the works. The bond must be calculated in accordance with the relevant Brisbane Planning Scheme Codes (5% of total value of the landscape works or minimum of $5,000.00 whichever is greater). Note: To arrange an on-maintenance inspection with Development Services an email must be sent to specialistservices@brisbane.qld.gov.au. Note: A maintenance bond can consist of either a bank guarantee or monetary payment lodged with Council. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
31(g) On-Maintenance Period Provide a minimum of 12 months maintenance to the streetscape works and rectify any defects identified at the on-maintenance inspection and those arising during the on-maintenance period. Timing: Minimum 12 months from acceptance on- maintenance AND until the works are approved off-maintenance by Council. |
As indicated |
31(h) Off-Maintenance
Acceptance On completion of the on-maintenance period, arrange an off-maintenance inspection with Development Services and obtain written confirmation from Council that the work is accepted off-maintenance. Ensure all defects are rectified prior to making an appointment for off- maintenance inspection. Note: To arrange an off-maintenance inspection with Development Services an email must be sent to specialistservices@brisbane.qld.gov.au. Note: If the off- maintenance inspection is successful the maintenance bond will be released. Timing: On completion of the on-maintenance period. |
As indicated |
| 32) Pedestrian and/or Awning Lighting Install Pedestrian and/or Awning Lighting to the James Street and Harcourt Street frontages in accordance with the requirements of this condition. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
32(a) Submit a Pedestrian and Awning Lighting
Design Submit to Program Planning and Integration (City Lighting), and obtain approval for, a detailed Pedestrian Lighting Design for the full street frontage of the development, and/or Awning Lighting Design to the underside of the proposed awning over the verge in accordance with the following: Pedestrian Lighting: Provide electrical reticulation plans prepared by a Registered Professional Engineer Queensland certifying that the design complies with Australian Standard - AS/NZS3000 Electrical installations known as the Australian/New Zealand Wiring Rules and Council's standard drawings (BSD-11000 series). Provide pedestrian and cycle lighting plans prepared by a Registered Professional Engineer Queensland or a member of the Illuminating Engineering Society of Australia and New Zealand certifying that the design complies with Australian Standard - AS/NZS 1158.3.1 Lighting for roads and public spaces - Pedestrian area (Lighting Sub- category PP3) lighting - Performance and Design requirements. And/Or Awning Lighting: Submit to Program Planning and Integration (City Lighting), and obtain approval for, a detailed Awning Lighting Plan demonstrating that the under awning lighting complies with Australian Standard - AS/NZS 1158.3.1 - sub category P6, within - Road Lighting Part 3.1: Pedestrian area (Lighting Sub- category PA3) lighting - Performance and installation design requirements and achieves glare control to ensure zero candelas (cd) at 90 degrees. Timing: Prior to commencing building work above ground level and prior to or concurrently with the submission of Landscape Works in Streetscape Plans for approval. |
As indicated |
32(b) Obtain an Electrical
Connection Obtain an electrical connection from the electricity supplier / Enter into an arrangement with the electricity supplier to service the approved pedestrian lighting. Timing: Prior to commencing building work above ground level. |
As indicated |
32(c) Implement Approved Pedestrian and/or
Awning Lighting Design Install the lighting in accordance with the approved detailed Pedestrian Lighting Design and the approved Landscape Works in Streetscape Plan and/or Awning Lighting Design. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
32(d) Provide Certification of Connection and
Operation Provide to Program Planning and Integration (City Lighting) certification from a licensed electrical contractor that the electrical connection has been installed in accordance with the approved detailed Pedestrian Lighting Design and/or Awning Lighting Design and that the lighting is fully operational. The certification must specify that the electrical installation has been tested to ensure it is electrically safe and in accordance with the requirements of Australian Standard - AS/NZS3000 Electrical installations known as the Australian/New Zealand Wiring Rules and any other standard applying to the electrical installation under the Electrical Safety Regulation 2002. A copy of the as-constructed Pedestrian Lighting Design Drawings must be included with the above certification. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
32(e) On-Maintenance Acceptance Arrange an on- maintenance inspection with Program Planning and Integration (City Lighting) and obtain written confirmation from Council that the work has been completed in accordance with the requirements of the condition and is accepted on- maintenance. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
32(f) On-Maintenance Period Provide a minimum 12 months maintenance to the works from the time the works are accepted on- maintenance by Council. During this period maintain the lighting and rectify any defects identified at the on-maintenance inspection and those arising during the on-maintenance period. Timing: Minimum 12 months from acceptance on-maintenance AND until the works are approved off- maintenance by Council. |
As indicated |
32(g) Off-Maintenance
Acceptance On completion of the on-maintenance period arrange an off-maintenance inspection with Program Planning and Integration (City Lighting) and obtain written confirmation from Council that the work is accepted off- maintenance. Ensure all defects are rectified prior to making an appointment for off-maintenance inspection. Timing: On completion of the on-maintenance period. |
As indicated |
32(h) Maintain the Work (Awning
Lighting) Maintain the awning lighting (including operating costs) in accordance with the approved Lighting Plan from dusk to dawn. Timing: To be maintained. |
As indicated |
| 33) Landscape the site - Container planting for rooftop
gardens and/or green walls Landscape the site through the provision of container planting in accordance with the requirements of this condition. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
33(a) Prepare Detailed Container Planting
Design for self-certification Prepare a Detailed Container
Planting Design for all container planting identified on the approved DRAWINGS
AND DOCUMENTS. The plan must be prepared and
certified by suitably qualified professionals and must comply with the relevant
Brisbane planning scheme codes. Timing: Prior to building work commencing. |
As indicated |
33(b) Implement certified Detailed Landscape
Container Planting Design Carry out the works in accordance with the above certified Detailed Landscape Container Planting Design. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
33(c) Certify work -
Implementation On completion of the work, submit to Development Services the
following: Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
33(d) Certify work - establishment
period On completion of the 12-month establishment period, submit to Development Services certification that planting has been established in accordance with the certified Detailed Landscape Container Planting Design. Timing: 12 months after implementation of the certified Detailed Landscape Container Planting Design. |
As indicated |
33(e) Maintain container
planting Planting. Maintain the container planting generally in accordance with the certified Detailed Landscape Container Planting Design. Timing: To be maintained. |
As indicated |
| 34) Landscape the Site - Self Certification Landscape the site in accordance with the requirements of this condition. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
34(a) Detailed Landscape Plan for Self-
Certification Prepare a Detailed Landscape Plan at a scale of 1:100 for all on-site landscape works including planting areas identified on the approved DRAWINGS AND DOCUMENTS including ‘Landscape DA 72-76 James Street’, Drawing no. 19090 Rev. J, dated 21/01/2026, received 06/02/2026 and amended in red 20/05/2026. The plan must be prepared by a Qualified Landscape Architect and must comply with the relevant Brisbane Planning Scheme Codes. The plan must include the following: Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
34(b) Centre or Mixed Use In addition to the
requirements listed above, the plan must include the following: -
A minimum of 25% of all trees as 200L stock or larger. PROOF OF FULFILMENT A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
34(c) Certify Detailed Landscape
Plan On completion of the Detailed Landscape Plan, submit to Development
Services: Timing: Prior to building work commencing. PROOF OF FULFILMENT A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to building work commencing. |
As indicated |
34(d) Implement Certified Detailed Landscape
Plan Carry out the landscape work in accordance with the above certified detailed Landscape Plan. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
34(e) Certify Work On completion of the
landscape work, submit to Development Services: Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT An as constructed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
34(f) Maintain Landscape Work Maintain the landscape work, including deep planting, in accordance with the certified Detailed Landscape Plan. Timing: To be maintained. |
As indicated |
| 35) Kitchen exhaust vents - (emitters) Kitchen and food preparation area exhaust vent outlets are discharged vertically, directed away from any sensitive use and separated by a minimum of 6m from a sensitive use, including any outdoor air intake of a sensitive use. Note: This condition does not authorise environmental nuisance under the Environmental Protection Act 1994. |
At all times |
| 36) Car park and bus station exhaust vents -
(emitters) Car park and bus station exhaust vent outlets are separated from any sensitive use by a minimum of 15m. Note: This condition does not authorise environmental nuisance under the Environmental Protection Act 1994. |
At all times |
| 37) Power Generator A power generator or standby generator for the operational phase of the development does not form part of this approval. |
To be maintained |
| 38) Hours of Operation Hours of operation for the approved uses, must be in accordance with the following: - Trading Hours (including deliveries) - 06:00am to 22:00pm |
At all times |
| 39) Mechanical Plant or Equipment - Acoustically
Screened Mechanical plant or equipment is to be acoustically screened from an adjoining sensitive use. Mechanical plant includes generators, motors, compressors and pumps such as air-conditioning, refrigeration and cold room motors. Acoustically screened is defined in City Plan 2014. NOTE: This condition does not authorise environmental nuisance under the Environmental Protection Act 1994. PROOF OF FULFILMENT Submit to Development Services, certification that all mechanical plant or equipment, is acoustically screened. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 40) Dampening of Grilles and Metal Plates All metal grilles, metal plates or similar located on the ramp from the ground level to basement 1 must be securely fastened and meet the requirements of AS3996:2019, Access covers and grates. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 41) Tyre Noise Reduction The driveways and carpark surfaces are to be appropriately treated/surfaced to reduce tyre noise impacts from the development. PROOF OF
FULFILMENT Provide Certification that appropriate treatments/surfacing has been provided to the driveways and carpark areas to reduce tyre noise impact from the development. Certification must be provided by a Member or professional eligible to be a Member of the Australian Acoustic Society. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 42) Acid Sulfate Soils - Management Plan Submit an Acid Sulfate
Soils (ASS) Investigation Report and Management Plan for approval by
Development Assessment. The Investigation Report and Management Plan are
to detail management measures of possible impacts of soil disturbance and
filling if disturbance (e.g. Filling, excavation, drainage works, stripping of
topsoil) is greater than 100m3. The ASS Management Plan must be consistent with
the: |
Prior to site/operational/building work commencing |
42(a) Implement Plan Implement and maintain the provisions of the
approved 'Acid Sulfate Soil Management
Plan'. |
While site/operational/building work is occurring |
| 43) Grant Easements Grant the following easement(s) as may be
required: - Overland Flow and Open Cut as shown on the Approved Civil Services General Arrangement Plan Drawing Number C05-001 Issue D prepared by ACOR Consultants (amended in red 20/09/2024). Note: These easements include the provision for Council to obtain access. Timing: Prior to commencement of use and then to be maintained. |
As indicated |
43(a) Submit Plan of Subdivision and
Documentation (Council Easement in Gross) Submit to, and obtain approval from, Development Services a plan of subdivision showing the easement and a request for Council to prepare the necessary easement documentation to demonstrate compliance with the requirements of this condition. Note: Easements in favour of the Brisbane City Council must have the necessary easement documentation prepared by the Brisbane City Council, free of cost to Council. Timing: Prior to submission of the request pursuant to Schedule 18 of the Planning Regulation 2017 for Council's notation on the plan of subdivision necessary to comply with this condition. |
As indicated |
43(b) Submit Plan of Subdivision and
Documentation (Other Easement) Submit to, and obtain approval from, Development Services, a plan of subdivision showing the easement and the necessary easement documentation to demonstrate compliance with the requirements of this condition. Note: Easements not in favour of the Brisbane City Council must have the necessary documentation prepared by the applicant's private solicitors. Timing: As part of the submission of the request pursuant to Schedule 18 of the Planning Regulation 2017 for Council's notation on the plan of subdivision necessary to comply with this condition. |
As indicated |
43(c) Lodge Notated Plan and
Documentation Lodge the plan of subdivision notated by Council pursuant to Schedule 18 of the Planning Regulation 2017 and the necessary easement documentation with the Registrar of Titles for the relevant Queensland State Government Authority. Timing: Prior to commencement of use. PROOF OF FULFILMENT Evidence of the registration of the necessary easement documentation. Timing: Within one month of the registration of the easement documentation. |
As indicated |
| 44) On-site Erosion (Medium Risk) Manage on-site erosion and the release of sediment or sediment laden water from the site at all times by implementing best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version). Timing: Prior to commencement of any land disturbing activities and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
44(a) Manage earth disturbance on-
site (i) Drainage control measures must be implemented and maintained to minimise water flow onto areas of exposed earth. (ii) Sediment and erosion control measures must be implemented and maintained to prevent soil loss from earth disturbance areas and prevent deposition beyond earth disturbance areas. (iii) No release of contaminants to land beyond on-site area of earth disturbance other than releases that achieve water pollutant concentration release limits of: A. 50mg/L TSS (Total Suspended Solids); B. Turbidity, Nephelometric Turbidity Units (NTU) value less than 10% above background, 75 NTU, or as agreed in writing by an Officer from Councils Erosion and Sediment Control (ESC) Team in Compliance and Regulatory Services; C. pH between 6.5 and 8.5 at all times. (iv) Maintain a written record to demonstrate that water discharges from the site, including any dewatering operations, meet the release limits as detailed in (iii) for water discharge(s) from the site that occur during or immediately after a rainfall event, and during normal business hours. The water quality of the discharge flows must be measured at each discharge point from the site, including but not limited to sediment basin outlets, other applicable sediment control devices, the site water drainage system, and recorded against the release limits at least once on each calendar day until such discharge stops. Timing: Prior to commencement of any earth disturbing activities and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
44(b) Provide Land Occupier Notification to
Council (i) Notify Council's ESC Team of proposed land occupier/s by sending an email to CARS-ESC@Brisbane.qld.gov.au (ii) If the land is to be occupied by any person other than the registered landowner then advice must be provided to Council that confirms the name, contact information and the duration of any proposed occupation of the land. Timing: Prior to commencement of any earth disturbing activities. |
As indicated |
44(c) Prepare Erosion and Sediment Control
Plan Prepare an Erosion and Sediment Control Plan (ESCP) in accordance with best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version) and, to the extent of any inconsistency, relevant Brisbane Planning Scheme Codes and Policies. Obtain a design certificate in accordance with the relevant Brisbane Planning Scheme Codes and Policies. The ESCP and design certificate must be certified by a Certified Professional in Erosion and Sediment Control (CPESC) or a Registered Professional Engineer Qld (RPEQ) with suitable qualifications and experience in erosion and sediment control. Documentary evidence demonstrating appropriate qualifications in erosion and sediment control must be provided to the Council upon request. Timing: Prior to the commencement of any earth disturbing activities. |
As indicated |
44(d) Attend a pre-start
meeting Arrange and attend a pre-start meeting for ESC with an Officer from Councils ESC Team in Compliance and Regulatory Services (CARS). Note: To request a pre-start meeting from Council's ESC Team send an email to CARS-ESC@Brisbane.qld.gov.au. All relevant documentation, including both the certified ESCP and the certified design certificate, must be attached to this email. Please allow up to 10 business days for your request to be processed. Timing: Attend the pre- start meeting prior to the commencement of any earth disturbing activities. |
As indicated |
44(e) Implement Certified Erosion and
Sediment Control Plan Implement the certified ESCP and maintain all ESC measures in accordance with best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version) and, to the extent of any inconsistency, relevant Brisbane Planning Scheme Codes and Policies. The ESCP and design certificate must be available on site at all times for inspection by Council officers. Any alteration to supplementary or Type 3 ESC measures must be reflected in the certified ESCP. Any alteration to Type 2 or Type 1 ESC measures will require a revised ESCP and design certificate that has been certified by either the CPESC or RPEQ. Timing: While earth disturbing activities are occurring and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
| 45) Maintenance Period for Engineering Work Maintain the work required by the Engineering condition(s) imposed on this development approval and rectify any defects in accordance with the requirements detailed in this condition. Note: Guidance for requesting a pre-start and co- ordinating the On/Off Maintenance process can be found on Council's website (https://www.brisbane.qld.gov.au/planning-and-building/applying-and-post- approval/on-and-off-maintenance-approvals). Timing: During the on-maintenance period. |
As indicated |
45(a) On-Maintenance Acceptance Arrange an on- maintenance inspection with Development Services and obtain written confirmation from Council that the work has been completed in accordance with the requirements of the condition and is accepted on-maintenance. Provide proof of Public Liability Insurance ($20 million) for the on- maintenance period. Lodge a maintenance security for the on-maintenance period. The security must be calculated as 5% of the value of the constructed work or $10,000.00, whichever is greater. Note: A maintenance security may consist of either a bank guarantee or monetary payment lodged with Council. Refer to Council's Infrastructure Installation and Construction Requirements Manual for further details about the on-maintenance procedure and requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
45(b) On-Maintenance Period Provide a minimum 12 months maintenance to the work from the time the work is accepted on- maintenance by Council. During this period maintain the work and rectify any defects identified at the on-maintenance inspection and those arising during the on-maintenance period. Note: The on-maintenance period may be extended by Council pending concerns and/or unsatisfactory performance during the maintenance period. Timing: A minimum 12 months from acceptance on-maintenance. |
As indicated |
45(c) Off-Maintenance
Acceptance On completion of the maintenance period arrange an off-maintenance inspection with Development Services and obtain written confirmation from Council that the work is accepted off-maintenance. Ensure all defects are rectified prior to making an appointment for off- maintenance Inspection. Note: If the inspection is successful the maintenance security will be released. Timing: On completion of the on-maintenance period. |
As indicated |
| 46) Information Signage Erect an information sign on the subject property in
accordance with Council's general requirements for signage and in accordance
with the requirements outlined below: Timing: Prior to site works commencing and then to be maintained until completion of the development for all stages. |
As indicated |
| 47) Engineering Pre-Start Meeting Arrange and attend a pre-start meeting with Development Services and Program Planning and Integration. Applicable compliance and inspection fees must be paid, in full, to Council prior to the meeting being held. Note: To arrange an engineering pre-start meeting with Development Services an email supported by a completed copy of the Pre-Start Meeting Guidelines - Civil Engineering Works kit (https://www.brisbane.qld.gov.au/sites/default/files/20191008-cc11207-pre- start-meeting-guidelines-civil-engineering-works.pdf) must be sent to dalodgement@brisbane.qld.gov.au. Details include (but
are not limited too) the following: Note: Timing: Prior to site/operational/building work commencing. |
As indicated |
| 48) Basement Excavation and Support Basement excavation and support of all exposed walls must be carried out in accordance with the relevant Brisbane Planning Scheme Codes and the requirements of this condition, and generally in accordance with the Approved Civil Services Bulk Earthworks Plan C04-001 Issue B (amended in red 20/09/2024). The Commercial character building is to be
reinforced, braced and protected and not is not to be relocated within the site
during the course of earthworks being carried out on the site, other than
temporarily lifted vertically to enable footings to be installed and relocation
of services, and reinstated prior to commencement of use. The design of the
protective measures is to be prepared by RPEQ and approved by Council prior to
the commencement of earthworks. |
Prior to commencement of site works |
48(a) Prepare Engineering
Drawings Engineering drawings for the work required by this condition must be prepared and certified by a Registered Professional Engineer Queensland (Structural), in accordance with the relevant Brisbane Planning Scheme Codes detailing the design of the proposed excavation as well as proposed temporary and permanent support (if no temporary proposed) systems. The design must include at least the following: Notes: Timing: Prior to site/operational/building work commencing. |
As indicated |
48(b) Implement Certified Engineering
Drawings Construct and maintain the basement excavation and proposed support system in accordance with the above certified engineering drawings. Note: A copy of the certified engineering drawings must be available on- site for inspection by Council Officers during these works. Timing: While basement excavation and support system installation is occurring. |
As indicated |
48(c) Submit Post Construction
Certification Submit certification by a Registered Professional Engineer Queensland that the basement excavation and support have been installed in compliance with the certified engineering drawings, the relevant Brisbane Planning Scheme Codes and the requirements of this condition. Where ground or rock anchors have been installed, submit certification by a Registered Professional Engineer Queensland (Geo-technical) that all anchors have been de- stressed. Timing: Prior to building work commencing above ground. |
As indicated |
| 49) Filling and / or Excavation All earthworks must be carried out in accordance with the relevant Brisbane Planning Scheme Codes. The existing Commercial Character Building (CCB) to remain in place and to be protected during all phases of the development including demolition, excavation and construction. Suitable basement excavation and construction methodology is to be used in order that the CCB remains in its current location during works. |
Prior to building work commencing |
49(a) Submit Earthworks
Drawings Submit to, and obtain approval from, Development Services earthworks drawings prepared and certified by a Registered Professional Engineer Queensland in accordance with the approved DRAWINGS AND DOCUMENTS and the relevant Brisbane Planning Scheme Codes. The Earthworks Drawings
must include the following: Note: If the earthworks impact on the road reserve, the Developer must obtain applicable footpath and road permits prior to commencing any works. Such impacts may include footpath occupation, road closures, re-profiling, ground anchors and/or relocation of services. If the excavation has to be stabilised using ground anchors or similar, then the submitted plans must show the location of these in relation to all services. The cost of moving services, utilities and assets is the responsibility of the Developer. The permission of the service/utility/asset owner is required. Note: Irrespective of final earthworks, it is the responsibility of the RPEQ to manage any staged works associated with Erosion & Sediment Control. Timing: Prior to site/operational/building work commencing. |
As indicated |
49(b) Fill Material, Placement, Compaction
and Testing All fill material placed on the site must comprise only natural earth and rock and must be free of contaminants (as defined by Part 3, Division 2, Subdivision 2 Environmental contamination, Section 11 of the Environmental Protection Act 1994) and noxious, hazardous, deleterious and organic materials. Fill material, placement, compaction and testing must comply with the requirements of Australian Standard - AS 3798, Guidelines on Earthworks for Commercial and Residential Developments. Timing: While site/operational/building work is occurring. |
As indicated |
49(c) Implement Approved Earthworks
Drawings Construct and maintain the earthworks in accordance with the requirements of AS3798 and the approved earthworks drawings. Timing: While site/operational/building work is occurring and then to be maintained. |
As indicated |
49(d) Submit As Constructed
Drawings Submit to Development Services As Constructed drawings prepared by a Registered Surveyor. Timing: Prior to building work above ground commencing. |
As indicated |
49(e) Submit Certification Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the approved earthworks drawings. Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that all fill material used complies with the quality requirements of this condition and that placement, compaction and testing has been carried out in accordance with AS3798. Timing: Prior to building work above ground commencing. |
As indicated |
| 50) Construction Management Plan - Major Carry out development in a method consistent with a Construction Management Plan (CMP) prepared in accordance with the requirements of this condition. |
While site/operational/building work is occurring |
50(a) Construction Management Plan - Submit
Plan Submit to, and obtain compliance approval from, Development Services a detailed Construction Management Plan for the site preparation, demolition, excavation and construction phases of the approved development. The Construction Management Plan must be in accordance with the relevant Brisbane Planning Scheme Codes and address the following matters, both internal to and external to the development site: (i) Location of and
impacts to any Council vegetation (i.e. street trees/park trees/garden
beds) (vi) Details of all
proposed work zones and/or lane closures, including justification;
Note: Pre-approval of work zones and/or lane closures associated with construction of the development will be managed by Development Services however the Construction Management Plan must be supported by "approval in principle" or written approvals from other relevant Council sections or other governing bodies responsible for any other potentially impacted infrastructure. The list of relevant infrastructure and contacts is available on Council's website - Search 'Constructions Management Plan'. Timing: Prior to site/operational/building work commencing. |
As indicated |
50(b) Construction Management Plan -
Dilapidation Report Submit a dilapidation report to engineeringservices@brisbane.qld.gov.au detailing the pre-existing condition of the roadway, both footways, both verges and Council infrastructure, including vegetation, for 100m from the site entry in both directions or to the next street intersection (if less than 100m from the site entry) in both directions. Timing: Prior to the pre-start meeting. |
As indicated |
50(c) Construction Management Plan -
Documentation on Site Legible copies of the approved Construction Management Plan and current permits must be kept on site and be made available on request by Council, at all times. The requirements of the CMP must be included in all induction of principal and subcontractors utilised in the development. An outline of the induction provided to contractors may be requested by Council to confirm compliance with this condition. Timing: While site/operational/building work is occurring. |
As indicated |
50(d) Construction Management Plan - Works to
be Performed Out of Hours Obtain an approval from Development Services for any
work that is proposed to be undertaken outside of normal business hours -
6:30am to 6:30pm, Monday to Saturday. |
As indicated |
50(e) Construction Management Plan -
Implement Plan Carry out the development in accordance with the approved Construction
Management Plan. |
As indicated |
| 51) Protect Existing Infrastructure Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure. Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations. The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements. |
While site/operational/building work is occurring |
51(a) As Constructed Drawings - Alterations
to Existing Infrastructure Submit to Development Services As Constructed drawings showing all new and/or rectification works and an asset register, prepared by a Registered Professional Engineer Queensland. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 52) Retaining Walls Design and construct all retaining walls and associated fences, in accordance with the relevant Brisbane Planning Scheme Codes and the following: - All retaining walls including the footings, must be located wholly within the property boundaries of the site where works are occurring - Runoff from surface drains and subsoil drainage associated with the retaining walls must be collected and connected to a lawful point of discharge (LPD) where possible. If no LPD is available the surface drains and sub-soil drainage must be designed, installed and discharged to ensure there is no ponding, nuisance or concentration of stormwater discharge to adjacent properties. - Retaining walls to stabilise excavation must be set back from property boundaries to accommodate subsoil drainage without encroachment into the neighbouring property. This set back may vary depending on the height, structure and design of the retaining wall, surcharge loadings from neighbouring properties, and to provide a surface drain along the top of the retaining wall - For retaining walls in excess of
1.0m in height: NOTE: Refer to City Plan 2014; Infrastructure Design Planning Scheme Policy (IDPSP) for Council’s definition of a LPD. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
52(a) Certification of Retaining
Walls For retaining walls over 1.0m in height, obtain certification from a Registered Professional Engineer Queensland that the design and construction of the retaining walls and ancillary drainage are in accordance with the requirements of this condition. |
As indicated |
| 53) Access, Grades, Manoeuvring, Carparks, Signs and
Line Marking Construct and maintain access, parking and manoeuvring for vehicles on site in accordance with the relevant Brisbane Planning Scheme Codes, as indicated on the approved DRAWINGS AND DOCUMENTS, including the following: i. A pavement of minimum Local road standard or equivalent surface material (including associated drainage) to the area on which motor vehicles will be driven and/or parked. ii. Suspended concrete parking areas, aisles and driveways are to be designed and certified by an RPEQ to accommodate the required design vehicles/s identified in this condition. iii. Manoeuvring on site for a RCV and for the loading and unloading of vehicle(s); iv. Parking on the site for 91 cars including 2 PWD parking spaces for people with disabilities, 2 VAN spaces, 8 motorcycle spaces, and provision for the loading and unloading of vehicle(s) within the site. v. Provide and maintain minimum 34 secure bicycle parking spaces (i.e. 26 employee and 8 visitor spaces) and 36 lockers and 3 shower cubicles with ancillary change rooms for both females and males; vi. A minimum of 2.3 metres height clearance to all undercover parking areas, including the entry and access to these areas, and a minimum of 2.5 metres above parking spaces for people with disabilities. The minimum clear height must be measured to the lowest protrusion from the ceiling (e.g. fire sprinklers, services, lighting fixtures, signs, etc). vii. A minimum of 4.2 metres height clearance to the on-site service vehicle area/s, including the entry and access to these areas. The minimum clear height must be measured to the lowest protrusion from the ceiling (e.g. fire sprinklers, services, lighting fixtures, signs, etc). viii. A
height clearance sign located at the entrance(s) to undercover car parking
areas. ix. A height clearance sign located at the entrance of the servicing area / loading dock, to notify drivers of the 4.2m height clearance available. ix. An appropriate area for the storage and collection of refuse, including recyclables, in a position which is accessible to service vehicles on the site. x. Prepare and implement signs and line markings drawings that show the internal paved areas signed and delineated in accordance with the approved drawings and documents. The drawings must be prepared and certified by a Registered Professional Engineer Queensland in accordance with the relevant Brisbane Planning Scheme Codes and the Manual of Uniform Traffic Control Devices. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland, that the above requirements have been implemented in accordance with this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 54) Repair Damage to Kerb, Footpath or Road Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
54(a) Interim Repairs If at any time during the construction phase of the approved development, damage to the existing kerb and channel, footpath or roadway creates unsafe, unreasonable and/or not fit for purpose conditions as assessed by Council, interim repairs must be undertaken as directed by Program Planning and Integration. Note: Any interim repairs required to be undertaken shall not be considered to satisfy the requirements of this condition for the permanent repair of the infrastructure prior to the issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. Timing: While site / operational / building works is occurring. |
As indicated |
| 55) Minimum Flood Planning Levels Design and construct all building pad levels, floor levels and ancillary structures to the appropriate flood planning level with freeboard (where required) in accordance with the relevant Brisbane Planning Scheme Codes and the approved drawings and documents. The minimum basement parking entry level must be 12.30 metres
AHD. The flood barrier treatment along the frontage of
Harcourt Street, and at the corner of Harcourt Street and James Street is to be
provided as shown on the Approved Civil Services General Arrangement Plan
Drawing No. C05-001 Issue D (amended in red 20/09/2024) and must be
certified by an RPEQ to confirm that: 1.
Suitable flood immunity is achieved for ground floor
areas. 2. The structure(s) are
designed to withstand hydrostatic and hydrodynamic forces up to and including
the defined flood event. PROOF OF FULFILMENT As-Constructed drawings prepared by a Registered Surveyor (Qld). The Registered Surveyor (Qld) must certify that the development has been constructed in accordance with this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 56) Refuse Collection - On Site Provide for the installation and collection of refuse/recycling bins by Brisbane City Council's Waste and Resource Recovery Services or a private waste contractor. Prepare and implement an On-site Waste Management Plan outlining the functional requirements of the waste storage and collection facilities, including: - monitoring and rotation of full and empty bins, - transfer of bins between basement bin store and ground floor waste collection area, - equipment required (e.g. bin-tug) and training required, - nomination and responsibilities of authorised person/s regard waste facilities management, - any other reasonable requirement involved in ensuring the provision of safe and efficient on-site waste management. |
At all times |
56(a) Arrange Refuse Collection Arrange for the installation of refuse/recycling bins and for the subsequent collection of refuse including recycling from the site by Brisbane City Council's Waste and Resource Recovery Services or a private waste contractor. Timing: A minimum of four weeks prior to the commencement of use and then to be maintained. PROOF OF FULFILMENT Where a private waste contractor is engaged, provide written confirmation from the proposed waste collection contractor of the agreement to service the property. The written agreement must be submitted to Council's Waste and Resource Recovery Services and include full details of the proposed system, bin sizes, number of bins, frequency of collection and the refuse collection vehicle size. Timing: Prior to commencement of use. |
As indicated |
56(b) Indemnify Council The owner and any subsequent owner must, by approved form to Waste and Resource Recovery Services, indemnify Council and its agents in respect of any damage to the pavement and other driving surfaces. Timing: When an arrangement for refuse/recycling collection services is made with Brisbane City Council. |
As indicated |
56(c) Notify Future Owner Where Council is engaged as the waste contractor, the owner must notify any future owner/body corporate that the development has been approved on the basis that an indemnity must be provide for refuse collection vehicles to enter the property. Timing: At time of a change of ownership. |
As indicated |
| 57) Refuse Storage - On Site Collection Provide a roofed and wholly screened refuse enclosure utilising materials consistent with the development or a dedicated refuse storage room, as shown on the approved plans and documents. The enclosure/refuse storage room must be of a design to accommodate the quantity of refuse and recycling including source separation to allow for low servicing collection of the development. Bins must be located in an area which allows them to be manoeuvred from the bin storage area to the designated internal collection point. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 58) Work for Transport Network - Road (Non-trunk) -
External Construct the following roadwork with any associated drainage, verge, site access and services including street lighting for the Transport Network (Road) shown on the Approved Civil Service Pavement Plan Drawing No. C09-001 Issue C (amended in red 20/09/2024) and the Approved Civil Public Domain Alignment Control Plan Drawing No. C11-501 Issue B (amended in red 20/09/2024) in accordance with the relevant Brisbane Planning Scheme Codes, the Queensland Manual of Uniform Traffic Control Devices and the AUSTROADS design standards: - New type E concrete kerb and channel and
associated drainage to provide a kerb build-out and approximately 5.0 metre wide verge along the James Street site frontage
for a distance of approximately 12 metres, measured from the site boundary at
the intersection with Harcourt Street. If available, construct the new kerb
using Porphry. - Regrade road pavement areas to interface with the new kerb invert level, whilst directing flows to the stormwater infrastructure and flow paths, and provide a consistent road cross-fall gradient from the kerb invert to the road crown where practical and possible. - Provide / maintain / reinstate any required signs and pavement markings along the James Street and Harcourt Street frontages; Note: This condition is imposed under section 145 of the Planning Act 2016. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
58(a) Submit Functional Layout
Drawings Submit to, and obtain approval from, Development Services functional layout drawings prepared and certified by a Registered Professional Engineer Queensland in accordance with the APPROVED DRAWINGS AND DOCUMENTS and the relevant Brisbane Planning Scheme Codes. Note: This approval must be obtained prior to the submission of drawings for Roadwork and Stormwater Drainage and Signs and Pavement Marking. Timing: Prior to site/operational/building work commencing. |
As indicated |
58(b) Submit Roadworks and Stormwater
Drainage Drawings Submit to, and obtain approval from, Development Services Roadworks and Stormwater Drainage Drawings prepared and certified by a Registered Professional Engineer Queensland in accordance with the APPROVED DRAWINGS AND DOCUMENTS and the relevant Brisbane Planning Scheme Codes. Timing: Prior to site/operational/building work commencing. |
As indicated |
58(c) Implement Approved
Drawings Construct the works in accordance with the above approved drawings. Timing: Prior to on-maintenance acceptance. |
As indicated |
58(d) Submit As Constructed
Drawings Submit to Development Services As Constructed drawings including an asset register and a pre-On-Maintenance Inspection Checklist, prepared by a Registered Professional Engineer Queensland. Timing: Prior to on-maintenance inspection. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the above approved drawings. |
As indicated |
| 59) Remove Redundant Drainage Outlets Remove any redundant drainage outlets from the kerb and channel
including any associated pipe work across the footway and reinstate the kerb
and channel and the footway area in accordance with the relevant Brisbane
Planning Scheme Codes. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 60) All Basements - Stormwater Runoff Design and construct basements to manage stormwater runoff in accordance with the relevant Brisbane Planning Scheme Codes and the following: (i) All stormwater pump systems must be designed to gravity drain to a Council stormwater system. (ii) The driveway into a basement must be designed and constructed to minimise local driveway stormwater runoff entering the basement. The drainage must be designed to capture runoff from a 10% AEP rainfall event and gravity drain to a lawful point of discharge. (iii) Vehicle access into any basement from a Council road will require the basement driveway to ramp up a minimum of 200mm, above adjacent road channel invert, to maintain road major flow capacity. (iv) All roofwater drainage is to be directed to a lawful point of discharge via gravity drainage, not directed into the basement. (v) Any stormwater within a basement that connects via gravity drainage directly to a council pipe or manhole must incorporate backflow prevention devices. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 61) Site Drainage - Major Provide an internal drainage system to collect stormwater run-off from all proposed lots, roofed and developed surface areas and any run-off onto the site from adjacent areas and convey the collected run- off to a lawful point of discharge, in accordance with the relevant Brisbane Planning Scheme Codes, and generally in accordance with the Approved Civil Services General Arrangement Plan C05-001 Issue D (amended in red 20/09/2024). Stormwater drainage outcomes shown on
the Approved Civil Services General
Arrangement Plan C05-001 Issue D (amended in red 20/09/2024) are conceptual only and are subject to further amendments as
required within the subsequent Drainage Compliance Assessment Application. The
alignment of stormwater drainage, and the design and location of stormwater
gully pits are subject to further changes. Notes: - All upslope stormwater connections to existing private properties must
extend to the property boundary of all relevant properties being ultimately
serviced by that connection. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
61(a) Submit Site Drainage
Drawings Submit to, and obtain approval from, Development Services, site drainage drawings and engineering calculations, prepared and certified by a Registered Professional Engineer Queensland, in accordance with the relevant Brisbane Planning Scheme Codes. Notes: -
Queensland Building and Construction Commission licensed hydraulic consultants
may design the stormwater system for sites less than 2000m2 with an upstream
catchment servicing no more than 4 residential lots. This excludes stormwater
drainage design (including subsoil drainage) of basements in flood planning
areas and the design of any onsite stormwater detention system Timing: Prior to site/operational/building work commencing |
As indicated |
61(b) Implement Approved
Drawings Carry out the works in accordance with the approved site drainage drawings. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
61(c) Submit As Constructed
Drawings Submit to Development Services As Constructed drawings prepared and certified by a Registered Professional Engineer Queensland or a Queensland Building and Construction Commission licensed hydraulic consultants (where applicable). Note: To be submitted via DA- ComplianceEngineering@brisbane.qld.gov.au and include the site address, A00 reference and Condition number in the subject line. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland or Queensland Building or Construction Commission licensed hydraulic consultants (where applicable) confirming that the works have been completed in accordance with the above stormwater drawings. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 62) Work for Stormwater Network (Non-Trunk) Construct stormwater drainage to
service the development in accordance with the relevant Brisbane Planning
Scheme Codes, ensuring that the works are connected to a lawful point of
discharge, and generally in accordance with the Approved Civil Services
General Arrangement Plan C05-001 Issue D (amended in red
20/09/2024). A minimum of two stormwater gully pits are to be
provided to the Harcourt Street frontage of the site. Stormwater drainage outcomes shown on the Approved Civil Services
General Arrangement Plan C05-001 Issue D (amended in red 20/09/2024) are
conceptual only, and are subject to further amendments
as required within the subsequent Drainage Compliance Assessment Application.
The alignment of stormwater drainage, and the design and location of stormwater
gully pits are subject to further changes. Note: Guidance for the preparation of drawings and/or documents to comply with this condition is provided in the Brisbane Planning Scheme Policies. Note: This condition is imposed under section 145 of the Planning Act 2016. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
62(a) Submit Stormwater
Drawings Submit to, and obtain approval from, Development Services, stormwater drawings and engineering calculations, prepared and certified by a Registered Professional Engineer Queensland in accordance with the relevant Brisbane Planning Scheme Codes. Timing: Prior to site/operational/building work commencing. |
As indicated |
62(b) Implement Approved
Drawings Construct the works in accordance with the above approved stormwater drawings. Timing: Prior to On-Maintenance Acceptance. |
As indicated |
62(c) Submit As Constructed
Drawings Submit to Development Services As Constructed drawings including an asset register and a pre-On Maintenance Inspection Checklist, prepared and certified by a Registered Professional Engineer Queensland. Timing: Prior to On-Maintenance Inspection. |
As indicated |
62(d) Submit Certification Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the above approved stormwater drawings. Timing: Prior to on-maintenance inspection. |
As indicated |
| 63) Ponding of Stormwater Carry out the approved development to ensure that adjoining properties and roads are protected from ponding or nuisance from stormwater during construction. Notes: If remedial works are necessary to comply with this condition, prior approval must be obtained from Development Services. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 64) Service Conduits and Mains Provide and install all
service conduits and meet the cost of any alterations to public utility mains,
existing mains, services, street lighting or installations that are required to
carry out the approved development. These works must be in accordance with the
relevant Brisbane Planning Scheme Codes, and include the following, where
applicable: Note: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
64(a) Submit As Constructed
Drawings Submit to Development Services As Constructed drawings, including an asset register, prepared and certified by a Registered Professional Engineer Queensland. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the requirements of this condition. Note: Civil works are to be certified by a RPEQ(Civil) and electrical works are to be certified by a RPEQ (Electrical). |
As indicated |
| 65) Telecommunications Submit to Development Services, certification from
an authorised telecommunications carrier/contractor, that the following works
and infrastructure have been undertaken and installed in accordance with
telecommunications industry standards: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 66) Agreement with Electricity Supplier Submit to Development Services, evidence of an agreement with an electricity supplier to provide necessary services to the development in accordance with the relevant Brisbane Planning Scheme Codes. Where development is within an established area of overhead electricity supply and the electricity supplier determines that a property pole is the appropriate solution to supply electricity to the development, the developer must be responsible for the installation of the property pole(s). In the above circumstances, submit to Development Services, certification from the developer's electrical consultant confirming that the above installation has been completed in accordance with the relevant AS/NZS Standards and the Queensland Electricity Connection Manual (QECM) and Queensland Electricity Metering Manual (QEMM). |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 67) Water and Wastewater Pursuant to Schedule 18 of the Planning Regulation 2017 submit to Development Services, documentary evidence, issued by the relevant distributor-retailer, to verify that the conditions of any necessary connection certificate under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009, have been complied with. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 68) Permanent Driveway Crossover Provide a 10.40 metre wide modified Type B1 permanent driveway crossover to the Harcourt Street frontage(s) of the site in accordance with the relevant Brisbane Planning Scheme Codes and located as shown on the Approved Civil Services Pavement Plan C09-001 Issue C (amended in red 20/09/2024). Ensure the driveway splay/tapers are located minimum 600mm clear of the lintel/s of the adjacent proposed stormwater gullies. The grid crossing must be constructed in accordance with BSD-2023 and must not obstruct overland flows from being conveyed along the Harcourt Street frontage of the site. Written consent must be obtained from Program, Planning and Integration Arboriculture (PPI Arb) prior to any works occurring that will either impact on or require removal of a street tree (this includes pruning, excavation or fill within the root zone/canopy of the tree) At all times during construction of the crossover, safe pedestrian access along the site frontage must be maintained. Note: No further driveway permit is required however additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 69) Redundant Driveway Crossover Remove the redundant existing driveway crossover(s) on the frontage(s) of the site and reinstate the kerb and channel, road pavement, footways and footpaths in accordance with the relevant Brisbane Planning Scheme Codes. Note: Additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 70) Construction Noise and Dust Emissions Pursuant to the Environmental
Protection Act 1994, all development involving the emission of noise and dust
from building and/or construction activities, must ensure that the emissions
are in accordance with the requirements of the Act. |
As indicated |
| 71) Contaminated Materials and Soils Any contaminated materials or soils encountered during siteworks, must be handled, stored and disposed of in accordance with the requirements of the relevant authority of the Queensland Government. A person must not dispose of contaminated soil or a hazardous substance at a place other than at a place approved by the relevant authority of the Queensland Government. |
As indicated |
| 72) Management of Asbestos Disposal, handling and restoration of any building materials containing asbestos must be in accordance with current state and federal legislation. |
As indicated |
| 73) Further Development Permit Required Further Development Permit(s) to carry out assessable building work under the Building Act may be required. |
As indicated |
| 74) Currency Period The currency period for this development approval is stated in the Decision Notice and is expressed as a date. This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016. |
As indicated |
| 75) Equitable Access Provision must be made during and after construction
for equitable access for persons with disabilities to and within the site and
on adjoining public areas, in accordance with the following: |
As indicated |
| 76) Damage to Trees on Adjoining Land Please note that any damage caused to vegetation on adjoining land as a result of exercising this development approval may result in an offence under other legislation (e.g. Natural Assets Local Law) and/or civil action |
As indicated |
| 77) Fire Ant Movement Controls To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected. These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products. Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014. For further information contact the relevant Queensland State Government department on 13 QGOV. |
As indicated |
| Permit to Which These Conditions Relate: | DA - PA - Referral Agency for Building Work |
| Activity(ies): | Flood hazard area |
| Stage: | Early referral agency response for Flood hazard area |
| 78) Early Referral Agency Response (Flood hazard
area) Council has chosen to issue an early referral agency response under section 57 of the Planning Act 2016 for the proposed building work located within a Flood hazard area (Planning Regulation 2017, Schedule 9, Part 3, Division 2, Table 12). The response is attached to this decision notice. |
As indicated |