BRISBANE CITY COUNCIL'S APPROVAL PACKAGE.



APPLICATION DETAILS

This package relates to the application detailed below
Address of Site: 43 DUNHILL CRES MORNINGSIDE QLD 4170
L 1 COLMSLIE BUSINESS PARK 70 COLMSLIE RD MORNINGSIDE QLD 4170
Real Property Description of Site: L15 SP.303654
L1 SP.283395
Aspects of development and type of approval: DA - PA - Material Change of Use Development Permit - high impact industry
DA - PA - Building Work Development Permit - high impact industry
Council File Reference: A007020756
Permit Reference Number/s: DAMC362265118; DABW362265018.
Package Status: APPROVED - Version 3 (23rd of June, 2026 3:16:47 PM)
Package Generated: 23/06/2026


PROJECT TEAM

The assessment of this application has been undertaken by:
Katrina BOGOEVSKI
Senior Urban Planner
Planning Services South
katrina.bogoevski@brisbane.qld.gov.au
(07) 3178 7654
Rory KELLY
Team Manager
Specialist Services
rory.kelly@brisbane.qld.gov.au
(07) 3403 4975
Sonia VENTURA
Development Officer, Engineering
Engineering Services South
sonia.ventura@brisbane.qld.gov.au
(07) 3403 4811
Harrison GORDON-BROWN
Senior Urban Planner
Planning Services North
Harrison.GordonBrown@brisbane.qld.gov.au
(07) 3178 2507
Matthew BOYD
Principal Urban Planner
Planning Services Prelodgement
matt.c.boyd@brisbane.qld.gov.au
31780585
Richard WELCH
Senior Engineer
Engineering Scoping
Richard.Welch@brisbane.qld.gov.au
34070603
Diana AVERY
Landscape Architect
Landscape Architecture Team
Diana.Avery@brisbane.qld.gov.au
3403 8888
Patrick COSTELLO
Ecologist
Ecology Services
Patrick.Costello@brisbane.qld.gov.au
0731787460
Michael O'REILLY
Environmental Management Officer
Environmental Management Services
Michael.O'Reilly@brisbane.qld.gov.au
3403 9517
Jodie RYAN
Urban Planner
House & Homes
Jodie.Ryan@brisbane.qld.gov.au
31782445
Matthew WATT
Principal Building and Construction Management Officer
Building and Construction Management Team - Coordination
Matthew.Watt@brisbane.qld.gov.au
3178 8877
Ben CLOTHIER
Team Manager (Acting)
Planning Services House & Homes
Ben.Clothier@brisbane.qld.gov.au
(07) 3403 7185
Katrina BOGOEVSKI
Senior Urban Planner
Planning Services South
katrina.bogoevski@brisbane.qld.gov.au
(07) 3178 7654
Kim ROGERS
Principal Urban Planner
Planning Services South
kim.rogers@brisbane.qld.gov.au
34071304


DRAWINGS AND DOCUMENTS



The term 'drawings and documents' or similar expressions mean:
Drawing or Document Number Plan Date
Ground Floor Plan AB1.3 Rev 2 05-MAY-2026 (Received)
Site Plan AB1.2 Rev 2 (Amended In Red 26-JUN-2026) 05-MAY-2026 (Received)
Mezzanine Floor Plan AB1.4 Rev 2 05-MAY-2026 (Received)
Elevations AB1.5 Rev 2 05-MAY-2026 (Received)
Hydraulic Services Stormwater Services Site & Ground Floor Plan 18188-H1SW Issue P1 (Amended In Red 12-JUN-2026) 13-DEC-2018 (Received)


Advice

Please see the attached document(s) for any advices.

APPROVAL CONDITIONS



Permit to Which These Conditions Relate: DA - PA - Material Change of Use
Activity(ies): high impact industry
Stage: S81 Minor Change to High impact industry (Brewery) with an ancillary administration area

General/Planning Requirements
 
Timing
1)   Approved Drawings and Documents

A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers.

Note: This condition is imposed to ensure compliance with the conditions of development approval.

 
While site/operational/building work is occurring
 
2)   Carry Out the Approved Development

Carry out the approved development generally in accordance with the approved DRAWINGS AND DOCUMENTS.

Note. This development approval may include the location of fences, retaining walls and/or external walls of buildings on the boundary of a lot. This approval does not imply permission to enter neighbouring properties to carry out the construction (including associated drainage and earthworks) or maintenance activities. Permission to enter neighbouring properties must be obtained from relevant property owners.

 
While site/operational/building work is occurring and then to be maintained
 
3)   Complete All Building Work

Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out generally in accordance with the approved DRAWINGS AND DOCUMENTS, and, where the building work is assessable development, in accordance with a current development approval.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
 
4)   Maintain the Approved Development

Maintain the approved development generally in accordance with the approved DRAWINGS AND DOCUMENTS, and any relevant Council engineering or other approval required by the conditions.

 
To be maintained
 
5)   Hotel, Shop and Adminstration area

i. The ancillary administration and storage area of the High impact industry use on the mezzanine is to be a maximum of 234m square .

 
At all times
 
6)   Staff Recreation Area

In accordance with the Brisbane City Plan 2014 - Industry Code, provide on-site recreation area(s) as shown in the north eastern corner of the site as shown on Ground Floor Plan AB1.3 Rev 1, received 20-JUL-2022, Amended in Red 31-AUG-2022, and incorporating the following:

      i.         seating, a table and rubbish bin;

     ii.        adequate protection from the weather (sun and rain);

    iii.        is safely accessible to all staff employed on the site;

   iv.        is appropriately screened from noise and/or odorous activities carried out on the site or adjoining the site;

    v.         is appropriately screened from public areas; and

   vi.        the recreation area is designed and sited incorporating Crime Prevention Through Environmental Design (CPTED) principles identified in the Crime Prevention Through Environmental Design Planning Scheme Policy.

 
Prior to the commencement of the use and then to be maintained
 
7)   Security Lighting

Install and maintain a suitable system of security lighting to operate from dusk to dawn within all areas where the public may gain access, including car parking areas, building entrances and vegetated areas

Ensure that all external lighting is in accordance with Australian Standard - AS4282- Control of the Obtrusive Effects of Outdoor Lighting so as not to cause nuisance to nearby residents or passing motorists.

Ensure lighting over publicly accessible pathways covered by permanent awnings is in accordance with Australian Standard - AS/NZS 1158.3.1 Lighting for roads and public spaces - Pedestrian area (Category P) lighting - Performance and design requirements.

Lighting must be maintained by the owner of the building in a safe and good working order.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
Architecture
 
Timing
8)   Overall Height

The overall height of the proposed building(s) must be in accordance with the floor and roof levels and overall height shown on the APPROVED DRAWINGS AND DOCUMENTS.

 
While site/operational/building work is occurring and then to be maintained
8(a) Submit Certification

Submit to Development Services certification from a registered surveyor confirming that the “as constructed” floor and roof levels and overall height are in accordance with the requirements of this condition.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
9)   Screen Air Conditioning and Other Plant Enclosures

Install and maintain suitable screening to all air conditioning, lift motor rooms, plant and service facilities located at the top of or on the external face of the building. The screening structures must be constructed from materials that are consistent with materials used elsewhere on the facade of the building.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
Landscape Architecture and Open Space Planning
 
Timing
10)   Landscape the Site - Self Certification

Landscape the site in accordance with the requirements of this condition.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
10(a) Prepare a detailed Landscape Plan for Self Certification

Prepare a detailed Landscape Plan for areas nominated on the approved drawings, in accordance with the approved Site Plan (Drawing No. AB1.2 Rev 1, received 20-JUL-2022, amended in red 31-AUG-2022), the relevant Brisbane Planning Scheme Codes/Policies and the following conditions:

PLANTING
-  Provide columnar trees at 3m intervals where possible along site boundaries
-  Provide a minimum 2m wide landscape strip along the frontage planted with trees, shrubs and groundcovers
-  Provide flowering /shade trees within the frontage at maximum centres of 6m, provided as 25 litre stock or larger - staked and tied
-  Provide shade trees to driveways and car parking to achieve a minimum 50% shade to hardstand areas
-  Provide a 3 tier landscape structure to all landscape areas ie. Trees, shrubs and groundcovers

ADDITIONAL REQUIREMENTS
-  Maximise opportunities for stormwater infiltration into landscaped areas

SPECIFICATIONS
-  Provide mulch and soil to meet AS4454 and AS4419
-  Ensure that soil media is ameliorated to increase its water holding capabilities.

Note: The requirements outlined by this condition do not require an application to be made with Council.

 
Prior to site/operational/building work commencing
10(b) Construct Approved Work

Construct landscaping in accordance with the prepared detailed Landscape Plan.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first
10(c) Certify Work

On completion of works, submit to Development Services certification from:

-  A registered Landscape Architect or Landscape Designer that the detailed Landscape Plan complies with the City Plan (Form CC10616 Landscape Design Certificate); and
-  A registered Landscape Architect and registered Landscape Contractor that the completed landscape work complies with the detailed Landscape Plan, (Form CC10613 Landscape Works Certificate).

Note: A copy of the as-constructed detailed Landscape Plan must accompany the completed Compliance Certificates.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
10(d) Maintain Landscape Work

Maintain the landscape generally in accordance with the detailed plans.

 
To be maintained
 
Pollution
 
Timing
11)   Air Quality Management

Brewing kettle outlets are to be fitted with vapour condensing systems.

 

 
Prior to the commencement of the use and then to be maintained
11(a) Submit Certification

Submit Certification to Council by a suitably qualified consultant, demonstrating that the condensation systems have been installed.

 
Prior to commencement of use
 
12)   Hours of Operation

High Impact Industry operations are able to operate 24 hours, daily.

 
As indicated
 
Engineering
 
Timing
13)   On-site Erosion (low risk)

Minimise on-site erosion and the release of sediment or sediment laden stormwater from the site at all times by implementing best industry practice for sediment and erosion control.
Note: Guidelines and factsheets to assist with this are available from the ‘Healthy Waterways – Water by Design’ website at
http://hlw.org.au/initiatives/esc/house-sites

Timing: While site works are occurring and until all exposed soil areas are permanently stabilised against erosion.

 
As indicated
 
14)   Information Signage

Erect an "Information Sign" on the subject property in accordance with Council’s general requirements for signage and in accordance with the requirements outlined below:

a)  The sign should provide a brief description of the development proposed;
b)  The sign is to list the name, postal and/or email address and a contact telephone number for the following parties (where relevant) that are undertaking work on the site:

     Developer;
     Project Coordinator;
     Architect/Building Designer;
     Builder;
     Civil Engineer;
     Civil Contractor/s; and
     Landscape Architect;

c)  The lettering on the sign is to be at least 25 millimetres in height, be of regular weight and in sentence case;
d)  The sign is to be a minimum size of 1,200 millimetres by 900 millimetres;
e)  The maximum area of the sign is to be 2.0m2;
f)  The sign is to be positioned as follows:

     located centrally along each road frontage of the site to the new public road frontage (Dunhill Crescent);
     located on or within 1.5 metres of the road frontage;
     mounted at least 300 millimetres above ground level; and
     clearly visible from the street for a pedestrian;

g)  The sign is to contain no commercial or corporate advertising other than the name, logo or slogan of the parties outlined in part (b) of this condition;
h)  The sign is to be non- illuminated; and
i)  Both the sign and the supporting structure are to be made of weatherproof material and to be properly maintained at all times;

Timing: Prior to site works commencing and then to be maintained until completion of the development for all stages.

 
As indicated
 
15)   Retaining Walls

Design and construct all retaining walls and associated fences, in accordance with the relevant Brisbane Planning Scheme Codes and including the following:

-  All retaining walls including the footings, must be located wholly within the property boundary of the site where works are occurring
-  Retaining walls to stabilise excavation must be set back off property boundaries to accommodate subsoil drainage without encroachment into the neighbouring property. This set back may vary depending on the height, structure and design of the retaining wall, including loadings from neighbouring properties, and to provide a surface drain along the top of the retaining wall
-  Retaining walls that are greater than 1.0m in height must be vertically and horizontally tiered by a ratio of 1:1 unless an alternative has been approved by Development Services
-  Runoff from surface drains and subsoil drainage associated with the retaining wall must be collected and conveyed to a lawful point of discharge and must not cause any ponding, nuisance or disturbance to adjacent property owners
-  Retaining walls in excess of 1.0m in height must be designed and certified by a Registered Professional Engineer Queensland
-  Retaining walls facing onto Council property (including the road reserve and parkland) must not be constructed from timber.

 
Prior to site/operational/building work commencing
15(a) Certification of Retaining Walls

For retaining walls over 1.0m in height, obtain certification from a Registered Professional Engineer Queensland that the design and construction of the retaining wall and ancillary drainage is in accordance with this condition.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
As indicated
 
16)   Protect Existing Infrastructure

Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure. Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations. The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements.

 
While site/operational/building work is occurring
16(a) As Constructed Drawings

Where alterations to existing infrastructure are required, submit to Development Services "As Constructed" drawings showing all new and/or rectification works and an asset register, prepared by a Registered Professional Engineer Queensland.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
While site/operational/building work is occurring
16(b) Submit Certification

Where alterations to existing infrastructure are required, submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
While site/operational/building work is occurring
 
17)   Filling and / or Excavation (Minor)

Filling and/or excavation works on the site must be in accordance with the relevant Brisbane Planning Scheme Codes.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
17(a) Prepare Earthworks Drawings

Earthworks drawings must be prepared and certified by either: a Registered Professional Engineer Queensland or a suitably qualified geotechnical and structural consultant, in accordance with the relevant Brisbane Planning Scheme Codes.

The drawings must include the following:

-  maintenance of access roads to and from the site such that they remain free of all fill material and are cleaned as necessary
-  preservation of all drainage structures from the effects of structural loading generated by the earthworks
-  protection of adjoining properties and roads from ponding or nuisance from stormwater.

Timing: Prior to site/operational/building work commencing.

Note: The Earthworks drawings are not required to be submitted for Council approval.

 
As indicated
17(b) Implement and Maintain the Earthworks

Carry out and maintain the earthworks in accordance with the certified drawings.

Note: A copy of the certified Earthworks Drawings must be available on- site for inspection by Council Officers during these works.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
As indicated
 
18)   Repair Damage to Kerb, Footpath Or Road

Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
18(a) Interim Repairs

If at any time during the construction phase of the approved development, damage to the existing kerb and channel, footpath or roadway creates unsafe, unreasonable and/or not fit for purpose conditions as assessed by Council, interim repairs must be undertaken as directed by Asset Services.

Note: Any interim repairs required to be undertaken shall not be considered to satisfy the requirements of this condition for the permanent repair of the infrastructure prior to the issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

Timing: While site / operational / building works is occurring

 
As indicated
 
19)   Access, Grades, Manoeuvring, Carparks, Signs and Line Marking

Construct access, parking and manoeuvring for vehicles on site in accordance with the relevant Brisbane Planning Scheme Codes, as indicated on the approved DRAWINGS AND DOCUMENTS as amended in red, including the following:

i. A pavement of minimum Local road standard or equivalent surface material (including associated drainage) to the area on which motor vehicles will be driven and/or parked.

ii. Manoeuvring on site for a refuse collection vehicle (RCV) and for the loading and unloading of vehicles.

iii. Parking on the site for 20 cars of which 4 are small car, one (1) medium car and one (1) space for people with disabilities;

iv. The internal paved areas must be signed and delineated in accordance with the approved drawings and Manual of Uniform Traffic Control Devices - Queensland Department of Transport and Main Roads - Transport Operations (Road Use Management) Act 1995.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
19(a) Submit certification

Submit to Development Services, certification from a Registered Professional Engineer Queensland, that the above requirements have been implemented in accordance with this condition.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
20)   Refuse Collection - On Site

Provide for the installation and collection of waste/recycling bins by Brisbane City Council's Waste Services or a private waste company.

 
At all times
20(a) Arrange Refuse Collection

Arrange for the installation of waste/recycling bins by Brisbane City Council's Waste Services or a private waste company and for the subsequent collection of waste including recycling from the site.

Timing: A minimum of four weeks prior to the commencement of use and then to be maintained.

 
As indicated
20(b) Notify Future Owner

The owner must notify any future owner/body corporate that the development has been approved on the basis that an indemnity must be provided for refuse collection vehicles to enter the property.

Timing: At time of a change of ownership.

 
As indicated
20(c) Indemnify Council

The owner and any subsequent owner must indemnify Council and its agents in respect of any damage to the pavement and other driving surfaces.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
21)   Refuse Storage - On Site Bulk Collection

As amended in red on the APPROVED PLANS AND DOCUMENTS provide a roofed and screened waste enclosure to accommodate the type and quantity of bulk waste/recycling bins required to service the development.
Bins must be located in an area which allows them to be manoeuvred from the bin storage area to the designated internal collection point.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
22)   On Site Drainage - Minor

Provide a stormwater connection to all new or existing allotments and provide drainage infrastructure to ensure stormwater run-off from all roof and developed surface areas will be collected internally and piped in accordance with the relevant Brisbane Planning Scheme Codes as shown on the approved Hydraulic Services Stormwater Services Site & Ground Floor Plan (Drawing No. 18188-H1SW Issue P1), received 13 December 2018.

Note: Guidance for the preparation of drawings and/or documents to comply with this condition is provided in the Brisbane Planning Scheme Policies.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
22(a) Submit As Constructed Drawings

Where reconfiguring a lot, submit to Development Services "As Constructed" drawings prepared by a Registered Professional Engineer Queensland.

Timing: Prior to Council's notation of the plan of subdivision.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
22(b) Submit Certification

Where reconfiguring a lot, submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with this condition.

Timing: Prior to Council's notation of the plan of subdivision.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
 
23)   Telecommunications

Submit to Development Services, certification from an authorised telecommunications carrier/contractor, that the following works and infrastructure have been undertaken and installed in accordance with telecommunications industry standards:

a) Provide telecommunications to the subject buildings, lead-in conduits and equipment space in a suitable location within the buildings, to suit the carrier of choice.
b) If new pits and conduit infrastructure are required to be installed within the road reserve fronting the site, it must be suitably sized to cater for future installation of fibre optic cables.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
24)   Agreement with Electricity Supplier

Submit to Development Services, evidence of an agreement with an electricity supplier to provide necessary services to the development in accordance with the relevant Brisbane Planning Scheme Codes.

Where development is proposed within an established area of overhead electricity supply and the electricity supplier determines that a property pole is the appropriate solution to supply electricity to the development, the developer must be responsible for the installation of the property pole(s).

In the above circumstances, submit to Development Services, certification from the developer’s electrical consultant confirming that the above installation has been completed in accordance with the relevant AS/NZS Standards and the Queensland Electrical Connection and Metering Manual.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
25)   Permanent Vehicle Crossover

Provide a 9.8 metre wide Type B2 permanent vehicle crossover to the new public road frontage (Dunhill Crescent) frontage(s) of the site in accordance with the relevant Brisbane Planning Scheme Codes and located as shown on the approved DRAWINGS AND DOCUMENTS.

Note: No further permits are required to carry out these works and street trees must not be removed without prior approval from Asset Services.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
Standard Advice
 
Timing
26)   Further Development Permit required

This Development Approval to carry out building work made assessable under the planning scheme for Brisbane does not include an assessment of building work against the requirements of the Building Act and does not permit building work to occur unless, prior to the commencement of any building work, a Development Permit(s) to carry out assessable building work under the Building Act has been issued.

 
As indicated
 
27)   Construction Noise and Dust Emissions

Pursuant to the Environmental Protection Act 1994, all development involving the emission of noise and dust from building and/or construction activities, must ensure that the emissions are in accordance with the requirements of the Act.
The Environmental Protection Act 1994 prescribes that:

1. A person must not carry out building work in a way that makes an audible noise-
-  on a business day or Saturday, before 6.30a.m. or after 6.30p.m; or
-   on any other day, at any time. 
2. The reference in subsection (1) to a person carrying out building work-
-  includes a person carrying out building work under an owner-builder permit; and
-  otherwise does not include a person carrying out building work at premises used by the person only for residential purposes.

Note: A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management delegate Development Services.

 
As indicated
 
28)   Currency Period

The currency period for this development approval is stated in the Decision Notice.

The currency period for this development approval is expressed as a date.

This development approval lapses at the end of the currency period (the date stated in the decision notice) if:

  - for a material change of use, the first change of use does not happen;

  - for reconfiguring a lot, the plan of subdivision for the reconfiguration is not given to Council; or

  - for any other development (including building work and operational work), the development does not substantially start.

The currency period is determined by Council pursuant to section 85 of the Planning Act 2016.

 
As indicated
 
29)   Advice

Please note that the information contained in this section under the heading Standard Advice has been provided as advice only and does not form part of the development approval conditions.  This information has been provided to advise of other obligations under state legislation or local laws that may require action to be undertaken prior to commencing the activity approved by this development approval.

 
As indicated
 
30)   Cultural Heritage

Aboriginal cultural heritage is protected under the Aboriginal Cultural Heritage Act 2003 This Act establishes a cultural heritage duty of care and in section 23(1) mandates that a person who carries out an activity must take all reasonable and practicable measures for ensuring activities are managed to avoid or minimise harm to Aboriginal cultural heritage. The Duty of Care Guidelines gazetted pursuant to the Aboriginal Cultural Heritage Act 2003 provide guidance on identifying and protecting Aboriginal cultural heritage to fulfil the duty of care.

If you are unsure of your obligations contact the relevant Queensland State Government Department (Department of Aboriginal and Torres Strait Islander Partnerships).

 
As indicated
 
31)   Fire Ant Movement Controls

To prevent the spread of fire ants, the Queensland Government has implemented movement controls in areas of Queensland (biosecurity zones) where this pest species has been detected. These controls apply to individuals and commercial operators, and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products.
Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014.
If you are unsure of your obligations contact the relevant Queensland State Government Department (Biosecurity Queensland, Department of Agriculture and Fisheries).

 
As indicated
 
32)   Water and Wastewater

Services for water and wastewater (sewerage) are no longer under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections requires a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. Any necessary Water Approval must be obtained from the relevant distributor- retailer (currently operating as Queensland Urban Utilities for the Brisbane City Council area).

For the purpose of approving plans of subdivision pursuant to Schedule 18 of the Planning Regulation 2017 (whether in relation to a development permit for Reconfiguring a Lot or a Building Format Plan subsequent to a development permit for a Material Change of Use), documentary evidence, issued by the relevant distributor-retailer, must be provided to Council to verify that the conditions of any necessary Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009, have been complied with.

 
As indicated
 



Permit to Which These Conditions Relate: DA - PA - Building Work
Activity(ies): high impact industry
Stage: S81 Minor Change to High impact industry (Brewery) with an ancillary administration area

General/Planning Requirements
 
Timing
33)   Approved Drawings and Documents

A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers.

Note: This condition is imposed to ensure compliance with the conditions of development approval.

 
While site/operational/building work is occurring
 
34)   Carry Out the Approved Development

Carry out the approved development generally in accordance with the approved DRAWINGS AND DOCUMENTS.

Note. This development approval may include the location of fences, retaining walls and/or external walls of buildings on the boundary of a lot. This approval does not imply permission to enter neighbouring properties to carry out the construction (including associated drainage and earthworks) or maintenance activities. Permission to enter neighbouring properties must be obtained from relevant property owners.

 
While site/operational/building work is occurring and then to be maintained
 
35)   Complete All Building Work

Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out generally in accordance with the approved DRAWINGS AND DOCUMENTS, and, where the building work is assessable development, in accordance with a current development approval.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
 
Standard Advice
 
Timing
36)   Further Development Permit required

This Development Approval to carry out building work made assessable under the planning scheme for Brisbane does not include an assessment of building work against the requirements of the Building Act and does not permit building work to occur unless, prior to the commencement of any building work, a Development Permit(s) to carry out assessable building work under the Building Act has been issued.

 
As indicated
 
37)   Construction Noise and Dust Emissions

Pursuant to the Environmental Protection Act 1994, all development involving the emission of noise and dust from building and/or construction activities, must ensure that the emissions are in accordance with the requirements of the Act.
The Environmental Protection Act 1994 prescribes that:

1. A person must not carry out building work in a way that makes an audible noise-
-  on a business day or Saturday, before 6.30a.m. or after 6.30p.m; or
-   on any other day, at any time. 
2. The reference in subsection (1) to a person carrying out building work-
-  includes a person carrying out building work under an owner-builder permit; and
-  otherwise does not include a person carrying out building work at premises used by the person only for residential purposes.

Note: A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management delegate Development Services.

 
As indicated
 

** End of Package **