| Address of Site: | 23 MAUD ST NEWSTEAD QLD 4006 25 MAUD ST NEWSTEAD QLD 4006 |
| Real Property Description of Site: | L71 RP.9348 L72/73 RP.9348 |
| Aspects of development and type of approval: | DA - PA - Building Work Development Permit - multiple dwelling DA - PA - Material Change of Use Development Permit - multiple dwelling |
| Council File Reference: | A007057524 Permit Reference Number/s: DABW415223121; DAMC415223221. |
| Package Status: | APPROVED - Version 5 (21st of August, 2026 8:08:54 PM) |
| Package Generated: | 21/08/2026 |
| Jack WOOLSTON Senior Urban Planner Planning Services Special Assessment Jack.Woolston@brisbane.qld.gov.au 07 3178 5033 |
Llewellyn BATSON Principal Urban Planner Planning Services Special Assessment Llewellyn.Batson@brisbane.qld.gov.au (07) 340 34980 |
Rhea CONNOLLY Principal Urban Planner Planning Services North Rhea.Connolly@brisbane.qld.gov.au 3178 0651 |
| Brigette DAHM Landscape Architect Landscape Architecture Team brigette.dahm@brisbane.qld.gov.au (07) 3178 3981 |
Fabrienne Michelle YU Principal Environmental Management Officer - Air Quality Environmental Management Services Michelle.Yu@brisbane.qld.gov.au 07 3403 0258 |
Katrina KONTOS Environmental Management Officer Environmental Management Services katrina.s.kontos@brisbane.qld.gov.au (07) 3403 8888 |
| Callan BENNETT Principal Architect Architecture Team Callan.Bennett@brisbane.qld.gov.au 07 31780595 |
Llewellyn BATSON Principal Urban Planner Planning Services Special Assessment Llewellyn.Batson@brisbane.qld.gov.au (07) 340 34980 |
Peter RICHARDS Principal Urban Planner Planning Services Prelodgement prelodgementservices@brisbane.qld.gov.au (07) 3403 6302 |
| Alessio ZANCOLICH Principal Urban Planner Planning Services South alessio.zancolich@brisbane.qld.gov.au (07) 3407 8514 |
Andrew BLAKE Principal Engineer Engineering Services Hydraulics andrew.blake@brisbane.qld.gov.au (07) 3403 5018 |
Rodney KING Plumbing Services Rodney.King@brisbane.qld.gov.au |
| Paul STONE WaRRS Assessment paul.stone@brisbane.qld.gov.au 317 85854 |
Ken LEOWARDI Engineer Engineering Services North Ken.Leowardi@brisbane.qld.gov.au (07) 3403 5689 |
Natasha GOULD Planning Paratech Trunk Infrastructure & Calculations natasha.gould@brisbane.qld.gov.au 31781742 |
| Rhea CONNOLLY Principal Urban Planner Planning Services North Rhea.Connolly@brisbane.qld.gov.au 3178 0651 |
Llewellyn BATSON Principal Urban Planner Planning Services Special Assessment Llewellyn.Batson@brisbane.qld.gov.au (07) 340 34980 |
DRAWINGS AND DOCUMENTS
| Drawing or Document | Number | Plan Date |
|---|---|---|
| Environment Noise Assessment (Figure 1) | 21BRA0207 L01_1 | 16-NOV-2021 |
| Landscape Concept Plan | 25 Maud St Rev H | 28-OCT-2024 (Received) |
| Cover Sheet | 0.00 Rev 19 | 25-JUN-2026 (Received) |
| Site Plan Proposed | 1.03 Rev 11 | 25-JUN-2026 (Received) |
| Basement 3 Plan | 2.00 Rev 11 | 25-JUN-2026 (Received) |
| Basement 2 Plan | 2.01 Rev 22 | 25-JUN-2026 (Received) |
| Basement 1 Plan | 2.02 Rev 22 | 25-JUN-2026 (Received) |
| Ground Plan | 2.03 Rev 24 | 25-JUN-2026 (Received) |
| Level 1 Plan | 2.04 Rev 24 (Amended In Red 18-AUG-2026) | 25-JUN-2026 (Received) |
| Level 2 Plan | 2.05 Rev 12 (Amended In Red 18-AUG-2026) | 25-JUN-2026 (Received) |
| Level 3 Plan | 2.06 Rev 19 (Amended In Red 18-AUG-2026) | 25-JUN-2026 (Received) |
| Level 4 Plan | 2.07 Rev 12 (Amended In Red 18-AUG-2026) | 25-JUN-2026 (Received) |
| Level 5 Plan | 2.08 Rev 12 (Amended In Red 18-AUG-2026) | 25-JUN-2026 (Received) |
| Level 6 Plan | 2.09 Rev 12 (Amended In Red 18-AUG-2026) | 25-JUN-2026 (Received) |
| Level 7 Plan | 2.10 Rev 14 (Amended In Red 18-AUG-2026) | 25-JUN-2026 (Received) |
| Level 8 Plan | 2.11 Rev 16 (Amended In Red 18-AUG-2026) | 25-JUN-2026 (Received) |
| Level 9 Plan | 2.12 Rev 10 (Amended In Red 18-AUG-2026) | 25-JUN-2026 (Received) |
| Sub Penthouse Plan | 2.13 Rev 4 (Amended In Red 18-AUG-2026) | 25-JUN-2026 (Received) |
| Penthouse Plan | 2.14 Rev 4 (Amended In Red 18-AUG-2026) | 25-JUN-2026 (Received) |
| Roof Plan | 2.15 Rev 4 | 25-JUN-2026 (Received) |
| North Elevation | 3.01 Rev 16 | 25-JUN-2026 (Received) |
| East Elevation | 3.02 Rev 16 | 25-JUN-2026 (Received) |
| South Elevation | 3.03 Rev 16 | 25-JUN-2026 (Received) |
| West Elevation | 3.04 Rev 16 | 25-JUN-2026 (Received) |
| Section 1 | 4.01 Rev 15 | 25-JUN-2026 (Received) |
| Section 2 | 4.02 Rev 13 | 25-JUN-2026 (Received) |
| Section 3 | 4.03 Rev 12 | 25-JUN-2026 (Received) |
| Interface Section | 5.01 Rev 11 | 25-JUN-2026 (Received) |
| Interface Section | 5.02 Rev 11 | 25-JUN-2026 (Received) |
| Interface Section | 5.03 Rev 11 | 25-JUN-2026 (Received) |
| Interface Section | 5.04 Rev 11 | 25-JUN-2026 (Received) |
| Interface Section | 5.05 Rev 11 | 25-JUN-2026 (Received) |
| Interface Section | 5.06 Rev 11 | 25-JUN-2026 (Received) |
| Interface Section | 5.07 Rev 11 | 25-JUN-2026 (Received) |
| Interface Section | 5.08 Rev 11 | 25-JUN-2026 (Received) |
| Perspectives - Maud St NW | 9.01 Rev 9 | 25-JUN-2026 (Received) |
| Perspectives - Maud St NE | 9.02 Rev 9 | 25-JUN-2026 (Received) |
APPROVAL CONDITIONS
| Permit to Which These Conditions Relate: | DA - PA - Building Work |
| Activity(ies): | multiple dwelling |
| Stage: |
| 1) Maintain the Approved Development Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions. |
At all times |
| 2) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers. Note: This condition is imposed to ensure compliance with the conditions of development approval. |
While site/operational/building work is occurring |
| 3) Carry Out the Approved Development Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS. Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners. |
While site/operational/building work is occurring |
| 4) Complete All Building Work Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS. Note: Building work must also be completed in accordance with any other current development approval. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 5) Protect Adjoining Heritage Place Implement suitable protection measures to ensure that the adjoining heritage place is retained and protected. The protection measures must include but not be limited to protecting the footings, wall cladding and roof sheeting of the adjoining heritage place. Note: This development approval does not imply approval for any works on the adjoining heritage place. Timing: Prior to site / operational / building work commencing and while site / operational / building works is occurring |
As indicated |
| 6) Construction Noise and Dust Emissions Pursuant to the Environmental
Protection Act 1994, all development involving the emission of noise and dust
from building and/or construction activities, must ensure that the emissions
are in accordance with the requirements of the Act. |
As indicated |
| 7) Further Development Permit Required Further Development Permit(s) to carry out assessable building work under the Building Act may be required. |
As indicated |
| 8) Plumbing and Drainage Work Pursuant to the Plumbing and Drainage Act 2018, any plumbing and drainage work must be carried out in compliance with the Plumbing and Drainage Regulation 2019. Plumbing and drainage permit work requires approval by Brisbane City Council prior to the work being carried out. |
As indicated |
| 9) Currency Period The currency period for this development approval is stated in the Decision Notice and is expressed as a date. This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016. |
As indicated |
| 10) Fire Ant Movement Controls To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected. These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products. Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014. For further information contact the relevant Queensland State Government department on 13 QGOV. |
As indicated |
| 11) Water and Wastewater Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. For further information about any necessary Water Approvals contact Urban Utilities. |
As indicated |
| Permit to Which These Conditions Relate: | DA - PA - Material Change of Use |
| Activity(ies): | multiple dwelling |
| Stage: | Multiple Dwelling (8 additional units) |
| 12) Landscaping of Vacant Site If construction for the approved development does not commence within 3 months of the demolition of the existing building(s) on site, the site must be covered in grass in accordance with the approved drawings and documents. Timing: Within 3 months of the demolition of the existing building(s). |
As indicated |
| 13) Security Lighting - On Site Install and maintain a suitable system of security lighting to operate from dusk to dawn within all areas where the public may gain access, including car parking areas, building entrances and vegetated areas. Ensure that all external lighting is in accordance with Australian Standard - AS4282- Control of the Obtrusive Effects of Outdoor Lighting. Ensure lighting over publicly accessible internal pathways covered by permanent awnings is in accordance with Australian Standard - AS/NZS 1158.3.1 Lighting for roads and public spaces - Pedestrian area lighting - Performance and design requirements. Lighting must be maintained in safe and good working order.
Timing: ‘Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first’ |
As indicated |
| 14) Car Parking The car parking within the premises must be maintained exclusively for the ancillary use of the development. The parking must not be made available to the general public and there must not be signage erected on or in the vicinity of the site advertising the availability of car parking to the general public. |
At all times |
| 15) Maintain the Approved Development Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions. |
At all times |
| 16) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers. Note: This condition is imposed to ensure compliance with the conditions of development approval. |
While site/operational/building work is occurring |
| 17) Carry Out the Approved Development Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS. Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners. |
While site/operational/building work is occurring |
| 18) Complete All Operational Work Complete all operational work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such operational work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS or, if requiring a further approval from the Council, in accordance with the relevant further approval(s). |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 19) Complete All Building Work Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS. Note: Building work must also be completed in accordance with any other current development approval. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 20) Visitor Parking Visitor car parking spaces must: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 21) Final External Detailing of Building Construct the development in accordance with architectural drawings approved pursuant to this condition. The architectural drawings must be in accordance with the APPROVED DRAWINGS AND DOCUMENTS, relevant Brisbane Planning Scheme Codes and the requirements of this condition. |
To be maintained |
21(a) Submit Architectural
Drawings Submit to, and obtain approval from, Development Services architectural
drawings prepared and certified by a Registered Architect or Queensland
Building Construction Commission Open Licence Class Building Designer showing
the final developed details of the facade treatment, the ground interface and
the roof top/building capping elements which depict a higher level of
documentation detail than that shown on the APPROVED DRAWINGS AND DOCUMENTS,
including: The architectural
drawings must: Timing: Prior to building works commencing |
As indicated |
21(b) Implement Approved Architectural
Drawings Carry out the building work in accordance with the approved architectural drawings. Note: The requirement to use particular materials and finishes is imposed only for the purpose of achieving a built form outcome that displays architectural merit. Council has not assessed the materials and finishes for compliance with the Building Act, the Building Fire Safety Regulation, the Building Regulation, the Building Code of Australia, the Queensland Development Code, relevant Australian Standards, fire safety standards or any other relevant requirement of a statutory authority with regard to building work. Timing: While building work is occurring and then to be maintained. |
As indicated |
21(c) Submit Certification Submit to Development Services certification by a Registered Architect or Queensland Building Construction Commission Open Licence Class Building Designer confirming that the building has been constructed in accordance with the approved architectural drawings. Timing: Prior to the Final Certificate/Certificate of Occupancy or commencement of the use, whichever comes first. |
As indicated |
| 22) Overall Height The overall height of the building(s) must be in accordance with the floor and roof levels and overall height shown on the APPROVED DRAWINGS AND DOCUMENTS. NOTE: This condition should be read in conjunction with any other relevant condition requiring minimum height clearances for basement or undercover car parking and manoeuvring areas. |
While site/operational/building work is occurring and then to be maintained |
22(a) Submit Certification Submit to Development Services certification from a registered surveyor confirming that the 'as constructed' floor and roof levels and overall height are in accordance with the requirements of this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 23) Protect Adjoining Heritage Place Implement suitable protection measures to ensure that the adjoining heritage place is retained and protected. The protection measures must include but not be limited to protecting the footings, wall cladding and roof sheeting of the adjoining heritage place. Note: This development approval does not imply approval for any works on the adjoining heritage place. Timing: Prior to site / operational / building work commencing and while site / operational / building works is occurring |
As indicated |
| 24) Driveway Material and Finishes Provide materials and
finishes to the driveway and external carparking
surfaces that reduce the visual impact of these areas when viewed from the
street. One or a combination of the following must be used: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 25) Provide Pedestrian Prioritised Pathway Provide a pedestrian prioritised pathway from the street frontage to the building. The pathway must be differentiated in colour and texture from the driveway surface. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 26) Balconies/Verandahs/Terraces
Note: Any Community Management Statement that may apply to this approval must contain a by-law which reflects the requirements of this condition. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 27) Screen Air Conditioning and Other Plant
Enclosures Install and maintain suitable screening to all air conditioning, lift motor rooms, plant and service facilities located at the top of or on the external face of the building and within the Private Open Spaces. The screening structures must be constructed from materials that are consistent with materials used elsewhere on the facade of the building. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 28) Sun Shading Devices Provide sun shading in accordance with the approved DRAWINGS AND DOCUMENTS. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 29) Screening Provide suitable privacy screening to windows of habitable rooms, balconies, landings, terraces and decks of the proposed dwelling(s) in accordance with the approved DRAWINGS AND DOCUMENTS. Suitable screening options must be: For windows: For balconies, landings, terraces and decks: Note: Screening devices must be either solid translucent screens, perforated or slatted panels, or fixed louvres that are permanent, be durable and fixed. Screening devices must have a maximum of 25% openings, with a maximum opening of 50mm. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 30) Provide Detailed and Textured Model Submit to Virtual Brisbane, a digital model for inclusion into the Brisbane City Council Virtual Brisbane 3D model. This must be a high quality, detailed and textured 3D exterior model of the approved development at a standard which can be publicly viewable. This must be of a compatible file format, include property boundaries and show heights in Australian Height Datum (AHD). For information on the submission and a complete list of requirements' visit: www.brisbane.qld.gov.au/virtualbrisbane3Drequirements Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate |
As indicated |
| 31) Streetscape Works - Neighbourhood Street
Minor Carry out streetscape improvement works including concrete path (where required by this condition), turf and street trees to the verge to a Neighbourhood Street Minor standard in accordance with the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD), the requirements of this condition and the Infrastructure Design Planning Scheme Policy including sections 3.7.4.4 and 3.7.5. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
31(a) Concrete Path Install a 1.2m wide broom finished standard Portland grey concrete path. The edge of the path is to be setback 1300mm from the back of kerb.
Where the path cannot be installed on this alignment due to conflicts such as
street trees, or power poles, ensure the path is installed a minimum distance
of: If the above requirements cannot be achieved, contact the Landscape Architecture Team via email: specialistservices@brisbane.qld.gov.au. Transition to existing paths on verges that adjoin the development. The transition is to occur fronting the adjoining developments, not the subject site. Note: standard path alignments are shown on Brisbane Standard Drawing BSD-5201 sheet 2 but will vary depending on verge width and location. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Photographic evidence of concrete path. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
31(b) Submit As-Constructed
Drawings Submit to Development Services As Constructed plans including an asset register, checked by a Registered Professional Engineer Queensland, certifying that the concrete path works have been completed in accordance with relevant Brisbane Planning Scheme Codes/Policies. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT As constructed drawings signed by an RPEQ. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
31(c) Turf Install turf to the full width of the verge excluding any concrete path required by this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Photographic evidence of installed turf. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
31(d) Street Tree(s) Enter into and implement an arrangement with the Program Planning and Integration Regional Coordinator Arboriculture in relation to the required provision of the street tree planting in accordance with the above sections of the Infrastructure Design Planning Scheme Policy, including the number, species, location, installation and maintenance of the required street tree(s) as determined by Program Planning and Integration. Note: Street trees should not be planted until all utilities have been installed. Timing: Prior to issue of Certificate of Occupancy / Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT A copy of the agreement with Program Planning and Integration and/or photographic evidence of installed trees. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 32) Landscape the Site - Self Certification Landscape the site in accordance with the requirements of this condition. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
32(a) Detailed Landscape Plan for Self-
Certification Prepare a Detailed Landscape Plan at a scale of 1:100 for all on-site landscape works including planting areas identified on the APPROVED Landscape Concept Design, 25 Maud Street Rev H, dated 28 October 2024. The plan must be prepared by a Qualified Landscape Architect and must comply with the relevant Brisbane Planning Scheme Codes. The
plan must include the following: Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
32(b) Multiple Unit Dwelling In addition to the
requirements listed above, the plan must include the following: Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
32(c) Certify Detailed Landscape
Plan On completion of the Detailed Landscape Plan, submit to Development
Services: Timing: Prior to building work commencing. PROOF OF FULFILMENT A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to building work commencing. |
As indicated |
32(d) Implement Certified Detailed Landscape
Plan Carry out the landscape work in accordance with the above certified detailed Landscape Plan. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
32(e) Certify Work On completion of the
landscape work, submit to Development Services: Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT An as constructed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
32(f) Maintain Landscape Work Maintain the landscape work, including deep planting, in accordance with the certified Detailed Landscape Plan. Timing: To be maintained. |
As indicated |
| 33) Acid Sulfate Soils - Management Plan Acid Sulfate Soils must be managed in accordance with this condition. |
As indicated |
33(a) Submit Management Plan Submit for approval an Acid Sulfate Soils Management Plan prepared in accordance with the Potential and actual acid sulfate soils overlay Code, City Plan 2014. |
Prior to site/operational/building work commencing |
33(b) Implement Management Plan Implement the approved Acid Sulphate Soils Management Plan. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first |
33(c) Submit Certification Submit certification to Development Services that the
requirements of the approved Acid Sulphate Soils management plan have been
carried out. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 34) Mechanical Plant or Equipment - Acoustically
Screened Mechanical plant or equipment is to be acoustically screened from an adjoining sensitive use. Mechanical plant includes generators, motors, compressors and pumps such as air-conditioning, refrigeration and cold room motors. Acoustically screened is defined in City Plan 2014. NOTE: This condition does not authorise environmental nuisance under the Environmental Protection Act 1994. PROOF OF FULFILMENT Submit to Development Services, certification that all mechanical plant or equipment, is acoustically screened. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 35) Acoustic Fence - General Erect a 2.0m high acoustic fence,
(relative to the finished RL of the building pad) in accordance with Figure 1
of the Environment Noise Assessment by TTM Consulting P/L dated 16 November
2021, reference 21BRA0207 L01_1.
|
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
35(a) Certification Submit to Development Services certification from a person who is a Member or eligible to be a Member of the Australian Acoustic Society that the constructed acoustic fence complies with the above requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 36) Dwelling Unit Construction General Design and construct
the development with a minimum acoustic performance of: a.
Rw 35 for glazing (windows and
doors) where total area of glazing is greater than 1.8m2; b.
Rw 32 for glazing (windows and
doors) where total area of glazing is less than or equal to
1.8m2. PROOF OF
FULFILMENT Provide Certification that appropriate facade noise mitigation has been provided to the development. Certification must be provided by a member or professional eligible to be a member of the Australian Acoustic Society. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 37) On-site Erosion (Medium Risk) Manage on-site erosion and the release of sediment or sediment laden water from the site at all times by implementing best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version). Timing: Prior to commencement of any land disturbing activities and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
37(a) Manage earth disturbance on-
site (i) Drainage control measures must be implemented and maintained to minimise water flow onto areas of exposed earth. (ii) Sediment and erosion control measures must be implemented and maintained to prevent soil loss from earth disturbance areas and prevent deposition beyond earth disturbance areas. (iii) No release of contaminants to land beyond on-site area of earth disturbance other than releases that achieve water pollutant concentration release limits of: A. 50mg/L TSS (Total Suspended Solids); B. Turbidity, Nephelometric Turbidity Units (NTU) value less than 10% above background, 75 NTU, or as agreed in writing by an Officer from Councils Erosion and Sediment Control (ESC) Team in Compliance and Regulatory Services; C. pH between 6.5 and 8.5 at all times. (iv) Maintain a written record to demonstrate that water discharges from the site, including any dewatering operations, meet the release limits as detailed in (iii) for water discharge(s) from the site that occur during or immediately after a rainfall event, and during normal business hours. The water quality of the discharge flows must be measured at each discharge point from the site, including but not limited to sediment basin outlets, other applicable sediment control devices, the site water drainage system, and recorded against the release limits at least once on each calendar day until such discharge stops. Timing: Prior to commencement of any earth disturbing activities and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
37(b) Provide Land Occupier Notification to
Council (i) Notify Council's ESC Team of proposed land occupier/s by sending an email to CARS-ESC@Brisbane.qld.gov.au (ii) If the land is to be occupied by any person other than the registered landowner then advice must be provided to Council that confirms the name, contact information and the duration of any proposed occupation of the land. Timing: Prior to commencement of any earth disturbing activities. |
As indicated |
37(c) Prepare Erosion and Sediment Control
Plan Prepare an Erosion and Sediment Control Plan (ESCP) in accordance with best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version) and, to the extent of any inconsistency, relevant Brisbane Planning Scheme Codes and Policies. Obtain a design certificate in accordance with the relevant Brisbane Planning Scheme Codes and Policies. The ESCP and design certificate must be certified by a Certified Professional in Erosion and Sediment Control (CPESC) or a Registered Professional Engineer Qld (RPEQ) with suitable qualifications and experience in erosion and sediment control. Documentary evidence demonstrating appropriate qualifications in erosion and sediment control must be provided to the Council upon request. Timing: Prior to the commencement of any earth disturbing activities. |
As indicated |
37(d) Attend a pre-start
meeting Arrange and attend a pre-start meeting for ESC with an Officer from Councils ESC Team in Compliance and Regulatory Services (CARS). Note: To request a pre-start meeting from Council's ESC Team send an email to CARS-ESC@Brisbane.qld.gov.au. All relevant documentation, including both the certified ESCP and the certified design certificate, must be attached to this email. Please allow up to 10 business days for your request to be processed. Timing: Attend the pre- start meeting prior to the commencement of any earth disturbing activities. |
As indicated |
37(e) Implement Certified Erosion and
Sediment Control Plan Implement the certified ESCP and maintain all ESC measures in accordance with best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version) and, to the extent of any inconsistency, relevant Brisbane Planning Scheme Codes and Policies. The ESCP and design certificate must be available on site at all times for inspection by Council officers. Any alteration to supplementary or Type 3 ESC measures must be reflected in the certified ESCP. Any alteration to Type 2 or Type 1 ESC measures will require a revised ESCP and design certificate that has been certified by either the CPESC or RPEQ. Timing: While earth disturbing activities are occurring and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
| 38) Information Signage Erect an information sign on the subject property in
accordance with Council's general requirements for signage and in accordance
with the requirements outlined below: Timing: Prior to site works commencing and then to be maintained until completion of the development for all stages. |
As indicated |
| 39) Engineering Pre-Start Meeting Arrange and attend a pre-start meeting with Development Services and Program Planning and Integration. Applicable compliance and inspection fees must be paid, in full, to Council prior to the meeting being held. Note: To arrange an engineering pre-start meeting with Development Services an email supported by a completed copy of the Pre-Start Meeting Guidelines - Civil Engineering Works kit (https://www.brisbane.qld.gov.au/sites/default/files/20191008-cc11207-pre- start-meeting-guidelines-civil-engineering-works.pdf) must be sent to dalodgement@brisbane.qld.gov.au. Details include (but
are not limited too) the following: Note: Timing: Prior to site/operational/building work commencing. |
As indicated |
| 40) Basement Excavation and Support Basement excavation and support of all exposed walls must be carried out in accordance with the relevant Brisbane Planning Scheme Codes and the requirements of this condition. |
Prior to building work commencing |
40(a) Prepare Engineering
Drawings Engineering drawings for the work required by this condition must be prepared and certified by a Registered Professional Engineer Queensland (Structural), in accordance with the relevant Brisbane Planning Scheme Codes detailing the design of the proposed excavation as well as proposed temporary and permanent support (if no temporary proposed) systems. The design must include at least the following: Notes: Timing: Prior to site/operational/building work commencing. |
As indicated |
40(b) Implement Certified Engineering
Drawings Construct and maintain the basement excavation and proposed support system in accordance with the above certified engineering drawings. Note: A copy of the certified engineering drawings must be available on- site for inspection by Council Officers during these works. Timing: While basement excavation and support system installation is occurring. |
As indicated |
40(c) Submit Post Construction
Certification Submit certification by a Registered Professional Engineer Queensland that the basement excavation and support have been installed in compliance with the certified engineering drawings, the relevant Brisbane Planning Scheme Codes and the requirements of this condition. Where ground or rock anchors have been installed, submit certification by a Registered Professional Engineer Queensland (Geo-technical) that all anchors have been de- stressed. Timing: Prior to building work commencing above ground. |
As indicated |
| 41) CBD/City Frame Construction Management Plan Carry out development in accordance with a Construction Management Plan (CMP) prepared in accordance with the Central Business District and City Frame Development Services Construction Management Guidelines and the requirements set out in this condition. Note: This condition imposes restrictions on development construction management to regulate increased truck access, on street work zone and closures and all associated activities in the CBD and City Frame as a result of major State and Local Government infrastructure projects occurring in Brisbane. |
While site/operational/building work is occurring |
41(a) Submit Construction Management
Plan Submit to, and obtain approval from, Development Services a Construction Management Plan for the demolition, excavation and construction phases of the approved development. Separate Construction Management Plans may be appropriate for the individual components. The Construction
Management Plan must be in accordance with the Central Business District and
City Frame Development Services Construction Management Guidelines and the
relevant Brisbane Planning Scheme Codes and address the following: The Construction Management Plan must be supported by 'approval in principle' or written approvals from the relevant Council sections or other governing bodies responsible for any potentially impacted infrastructure. Timing: Prior to site/operational/building work commencing. |
As indicated |
41(b) Construction Management Plan -
Dilapidation Report Submit a dilapidation report to engineeringservices@brisbane.qld.gov.au detailing the pre-existing condition of the roadway, both footways, both verges and Council infrastructure, including vegetation, for 100m from the site entry in both directions or to the next street intersection (if less than 100m from the site entry) in both directions. Timing: Prior to the pre-start meeting. |
As indicated |
41(c) Construction Management Plan -
Associated Activities in Road Reserve Obtain relevant approvals, as list in part a of this condition, to carry out any works within the road reserve required by the approved Construction Management Plan identified in the Central Business District and City Frame Development Services Construction Management Guidelines. Note: All fees must be paid in full prior to any permit being granted by Council. Council may revoke any permits at any time for non-compliance with requirements or if it considers that safety, capacity and/or operation of public transport, vehicle and pedestrian traffic are likely to be compromised during the construction phase. Timing: Prior to site/operational/building work commencing. |
As indicated |
41(d) City Frame Construction Management Plan
- Documentation on Site Legible copies of the approved CBD Construction Management Plan and current permits must be kept on site and be made available on request At all times. The requirements of the CMP must be included in all induction of principal and subcontractors utilised in the development. An outline of the induction provided to contractors may be requested by Council to confirm compliance with this condition. Timing: While site/operational/building work is occurring. |
As indicated |
41(e) Construction Management Plan - Works to
be Performed Out of Hours Obtain an approval from Development Services for any
work that is proposed to be undertaken outside of normal business hours -
6:30am to 6:30pm, Monday to Saturday. |
As indicated |
41(f) Implement Approved Construction
Management Plan Carry out the development in accordance with the approved CBD/City Frame Construction Management Plan. |
While site/operational/building work is occurring |
| 42) Protect Existing Infrastructure Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure. Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations. The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements. |
While site/operational/building work is occurring |
42(a) As Constructed Drawings - Alterations
to Existing Infrastructure Submit to Development Services As Constructed drawings showing all new and/or rectification works and an asset register, prepared by a Registered Professional Engineer Queensland. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 43) Access, Grades, Manoeuvring, Carparks, Signs and
Line Marking Construct and maintain access, parking and manoeuvring for vehicles on site in accordance with the relevant Brisbane Planning Scheme Codes, as indicated on the approved DRAWINGS AND DOCUMENTS, including the following: i. A pavement of minimum Local road standard or equivalent surface material (including associated drainage) to the area on which motor vehicles will be driven and/or parked. ii. Manoeuvring on site for a Large Rigid Vehicle and for the loading and unloading of vehicle(s). iii. Parking on the site for 101 resident/tenant cars, six (6) visitor cars including one (1) parking space for people with disabilities and for the loading and unloading of vehicle(s) within the site. Parking spaces for on-site resident cars may be used for resident storage purposes in the following circumstances only: · A minimum of 1 car parking space per 2 bedroom dwelling and a minimum of 2 car parking spaces per 3 bedroom dwelling are maintained at all times. · Where a parking space is used for storage, a storage cage or shed must be constructed to contain stored items. · A storage cage or shed must be located to not impede clearances for any adjacent car parking space in accordance with Figure m of the Transport, access, parking and servicing planning scheme policy. iv. Provide and maintain a minimum of 40 secure bicycle parking spaces for the resident/tenant and ten (10) secure bicycle parking spaces for the visitor. v. Unless otherwise indicated on the Approved Plans and Drawing a minimum of 2.3 metres height clearance is to be maintained to all undercover parking areas and a minimum of 2.5 metres above parking spaces for people with disabilities. The minimum clear height must be measured to the lowest protrusion from the ceiling (e.g. fire sprinklers, services, lighting fixtures, signs, etc). vi. A height clearance sign located at the entrance(s) to undercover car parking areas and a directional visitor parking sign clearly visible from the vehicle entrance to the site. vii. Prepare and implement signs and line markings drawings that show the internal paved areas signed and delineated in accordance with the approved drawings and documents. The drawings must be prepared and certified by a Registered Professional Engineer Queensland in accordance with the relevant Brisbane Planning Scheme Codes and the Manual of Uniform Traffic Control Devices. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland, that the above requirements have been implemented in accordance with this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 44) Repair Damage to Kerb, Footpath or Road Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
44(a) Interim Repairs If at any time during the construction phase of the approved development, damage to the existing kerb and channel, footpath or roadway creates unsafe, unreasonable and/or not fit for purpose conditions as assessed by Council, interim repairs must be undertaken as directed by Program Planning and Integration. Note: Any interim repairs required to be undertaken shall not be considered to satisfy the requirements of this condition for the permanent repair of the infrastructure prior to the issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. Timing: While site / operational / building works is occurring. |
As indicated |
| 45) Flood Emergency Management Plan Prepare, implement and maintain a Flood Emergency Management Plan (FEMP) in accordance with the requirements of this condition. Note: Guidance for the preparation of drawings and/or documents to comply with this condition is provided in the Flood Planning Scheme Policies. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
45(a) Prepare and Certify a Flood Emergency
Management Plan Submit to Development Services a Flood Emergency Management Plan (FEMP) for the approved development prepared and certified by a Registered Professional Engineer Queensland with experience in flood risk management. Timing: Prior to issue of Certificate of Occupancy/Final Inspection. |
As indicated |
| 46) Minimum Flood Planning Levels Design and construct all building pad levels, floor levels and ancillary structures to the appropriate flood planning level with freeboard (where required) in accordance with the relevant Brisbane Planning Scheme Codes and the approved drawings and documents. The minimum habitable floor level must be 3.6 metres AHD. The minimum non-habitable floor level must be 3.4 metres AHD. The minimum basement entry level must be 3.4 metres AHD. The minimum level for essential electrical services must be 3.6 metres AHD. PROOF OF FULFILMENT As-Constructed drawings prepared by a Registered Surveyor. The Registered Surveyor must certify that the development has been constructed in accordance with this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 47) Basements in Flood Planning Areas Design and construct
all basements affected by flooding within the Brisbane River and Creek/Waterway
Flood Planning Areas, including stormwater, electrical and sanitary facilities,
in accordance with the following: Note: Basement means a space: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
47(a) Submit Certification to
Council Submit to Council certification by a Registered Professional Engineer Queensland that the stormwater, subsoil drainage and sewer hydraulic design, specifications and drawings for the basement construction is in accordance with the requirements of this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
47(b) Submit As Constructed Drawings to
Council Submit to development Services As Constructed drawings certified by a Registered Professional Engineer Queensland showing the surveyed basement entry levels, subsoil drainage details and pump design. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 48) Refuse Collection - On Site Provide for the installation and collection of refuse/recycling bins by Brisbane City Council's Waste and Resource Recovery Services or a private waste contractor. |
At all times |
48(a) Arrange Refuse Collection Arrange for the installation of refuse/recycling bins and for the subsequent collection of refuse including recycling from the site by Brisbane City Council's Waste and Resource Recovery Services or a private waste contractor. Timing: A minimum of four weeks prior to the commencement of use and then to be maintained. PROOF OF FULFILMENT Where a private waste contractor is engaged, provide written confirmation from the proposed waste collection contractor of the agreement to service the property. The written agreement must be submitted to Council's Waste and Resource Recovery Services and include full details of the proposed system, bin sizes, number of bins, frequency of collection and the refuse collection vehicle size. Timing: Prior to commencement of use. |
As indicated |
48(b) Notify Future Owner Where Council is engaged as the waste contractor, the owner must notify any future owner/body corporate that the development has been approved on the basis that an indemnity must be provide for refuse collection vehicles to enter the property. Timing: At time of a change of ownership. |
As indicated |
48(c) Indemnify Council The owner and any subsequent owner must, by approved form to Waste and Resource Recovery Services, indemnify Council and its agents in respect of any damage to the pavement and other driving surfaces. Timing: When an arrangement for refuse/recycling collection services is made with Brisbane City Council. |
As indicated |
| 49) Refuse Storage - On Site Collection Provide a roofed and wholly screened refuse enclosure utilising materials consistent with the development or a dedicated refuse storage room, as shown on the approved plans and documents. The enclosure/refuse storage room must be of a design to accommodate the quantity of refuse and recycling including source separation to allow for low servicing collection of the development. Bins must be located in an area which allows them to be manoeuvred from the bin storage area to the designated internal collection point. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 50) Land for Transport Network - Road (Non-
trunk) Dedicate the following land as road (non-trunk): i. A widening along the full length of the Maud Street frontage of the site to achieve a verge width of 3.75m. Note: This condition is imposed under section 145 of the Planning Act 2016. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
50(a) Submit Plan of
Subdivision Submit to, and obtain approval from, Development Services, a plan of subdivision showing the land to be dedicated for road to demonstrate compliance with the requirements of this condition. Timing: As part of the submission of the request pursuant to Schedule 18 of the Planning Regulation 2017 for Council's notation on the plan of subdivision necessary to comply with this condition. |
As indicated |
50(b) Lodge Notated Plan Lodge the plan of subdivision notated by Council pursuant to Schedule 18 of the Planning Regulation 2017 with the Registrar of Titles for the relevant Queensland State Government Authority. Timing: Prior to commencement of use. PROOF OF FULFILMENT Evidence of the registration of the required plan of subdivision. Timing: Within one month of the registration of the plan of subdivision. |
As indicated |
| 51) All Basements - Stormwater Runoff Design and construct basements to manage stormwater runoff in accordance with the relevant Brisbane Planning Scheme Codes and the following: (i) All stormwater pump systems must be designed to gravity drain to a Council stormwater system. (ii) The driveway into a basement must be designed and constructed to minimise local driveway stormwater runoff entering the basement. The drainage must be designed to capture runoff from a 10% AEP rainfall event and gravity drain to a lawful point of discharge. (iii) Vehicle access into any basement from a Council road will require the basement driveway to ramp up a minimum of 200mm, above adjacent road channel invert, to maintain road major flow capacity. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 52) On Site Drainage - Minor Provide a stormwater connection to all new or existing allotments and provide drainage infrastructure to ensure stormwater run-off from all roof and developed surface areas will be collected internally, piped and connected to the existing diameter 1,050 mm drainage pipe along the site road frontage to Maud Street in accordance with the relevant Brisbane Planning Scheme Codes. Notes: - Guidance for requesting a pre-start and co- ordinating the On/Off Maintenance process can be found on Council's website (https://www.brisbane.qld.gov.au/planning-and-building/applying-and-post- approval/on-and-off-maintenance-approvals). |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 53) Street Lighting Provide street lighting in accordance with the relevant Brisbane Planning Scheme Codes. Note: For the required lighting categories and requirements please contact City Lighting in Council. PROOF OF
FULFILMENT Evidence of an agreement with an electricity supply authority to provide a public lighting system in accordance with the approved street lighting design drawings. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 54) Service Conduits and Mains Provide and install all
service conduits and meet the cost of any alterations to public utility mains,
existing mains, services, street lighting or installations that are required to
carry out the approved development. These works must be in accordance with the
relevant Brisbane Planning Scheme Codes, and include the following, where
applicable: Note: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
54(a) Submit As Constructed
Drawings Submit to Development Services As Constructed drawings, including an asset register, prepared and certified by a Registered Professional Engineer Queensland. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the requirements of this condition. Note: Civil works are to be certified by a RPEQ(Civil) and electrical works are to be certified by a RPEQ (Electrical). |
As indicated |
| 55) Telecommunications Submit to Development Services, certification from
an authorised telecommunications carrier/contractor, that the following works
and infrastructure have been undertaken and installed in accordance with
telecommunications industry standards: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 56) Agreement with Electricity Supplier Submit to Development Services, evidence of an agreement with an electricity supplier to provide necessary services to the development in accordance with the relevant Brisbane Planning Scheme Codes. Where development is within an established area of overhead electricity supply and the electricity supplier determines that a property pole is the appropriate solution to supply electricity to the development, the developer must be responsible for the installation of the property pole(s). In the above circumstances, submit to Development Services, certification from the developer's electrical consultant confirming that the above installation has been completed in accordance with the relevant AS/NZS Standards and the Queensland Electricity Connection Manual (QECM) and Queensland Electricity Metering Manual (QEMM). |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 57) Water and Wastewater Pursuant to Schedule 18 of the Planning Regulation 2017 submit to Development Services, documentary evidence, issued by the relevant distributor-retailer, to verify that the conditions of any necessary Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009, have been complied with. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 58) Permanent Driveway Crossover Provide a 6.5 metre wide modified Type B2 permanent driveway crossover to the Maud Street frontage(s) of the site in accordance with the relevant Brisbane Planning Scheme Codes and located as shown on the approved DRAWINGS AND DOCUMENTS. Written consent must be obtained from BCC - Field Services, Program Planning and Integration Arborist prior to any works occurring that will either impact on or require removal of a street tree (this includes pruning and excavation within the root zone/canopy of the tree) At all times during construction of the crossover, safe pedestrian access along the site frontage must be maintained. Note: No further driveway permit is required however additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 59) Redundant Driveway Crossover Remove the redundant existing driveway crossover(s) on the frontage(s) of the site and reinstate the kerb and channel, road pavement, footways and footpaths in accordance with the relevant Brisbane Planning Scheme Codes. Note: Additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 60) Construction Noise and Dust Emissions Pursuant to the Environmental
Protection Act 1994, all development involving the emission of noise and dust
from building and/or construction activities, must ensure that the emissions
are in accordance with the requirements of the Act. |
As indicated |
| 61) Natural Asset Local Law (NALL) - Protected
Vegetation on Public Land, Road or Park Work on or around protected vegetation on public land, road or park may require a permit under the Natural Assets Local Law (NALL). Arrangements must be made with Program Planning and Integration in relation to the works carried out on protected vegetation on public land, road or park including provision for costs and replacement planting as determined by Program Planning and Integration. Timing: Prior to carrying out any works on protected vegetation. Note: All requirements of a development approval conditions with timing stipulated as ‘prior to site works commencing’ (or equivalent) must be fulfilled before Council can issue a NALL permit. |
As indicated |
| 62) Plumbing and Drainage Work Pursuant to the Plumbing and Drainage Act 2018, any plumbing and drainage work must be carried out in compliance with the Plumbing and Drainage Regulation 2019. Plumbing and drainage permit work requires approval by Brisbane City Council prior to the work being carried out. |
As indicated |
| 63) Currency Period The currency period for this development approval is stated in the Decision Notice and is expressed as a date. This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016. |
As indicated |
| 64) Equitable Access Provision must be made during and after construction
for equitable access for persons with disabilities to and within the site and
on adjoining public areas, in accordance with the following: |
As indicated |
| 65) Fire Ant Movement Controls To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected. These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products. Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014. For further information contact the relevant Queensland State Government department on 13 QGOV. |
As indicated |