| Address of Site: | 61 SWANN RD TARINGA QLD 4068 65 SWANN RD TARINGA QLD 4068 |
| Real Property Description of Site: | L440 SL.7291 L2 RP.100573 |
| Aspects of development and type of approval: | DA - PA - Material Change of Use Development Permit - multiple dwelling |
| Council File Reference: | A006967874 Permit Reference Number/s: DAMC403749121. |
| Package Status: | APPROVED - Version 2 (4th of June, 2026 9:07:04 PM) |
| Package Generated: | 04/06/2026 |
| Jack WOOLSTON Senior Urban Planner Planning Services Special Assessment Jack.Woolston@brisbane.qld.gov.au 07 3178 5033 |
Llewellyn BATSON Principal Urban Planner Planning Services Special Assessment Llewellyn.Batson@brisbane.qld.gov.au (07) 340 34980 |
Jacqueline PATON Senior Architect Architecture Team Jacqueline.Paton@brisbane.qld.gov.au 07 3178 0389 |
| Luke MICALLEF Engineer Engineering Compliance Luke.Micallef@brisbane.qld.gov.au 0734038888 |
Jolanta KRAWUS Principal Engineer, Development Assessment Engineering Scoping jolanta.krawus@brisbane.qld.gov.au 34036190 |
Tamara BERGMANS Urban Planner City Planning tamara.bergmans@brisbane.qld.gov.au 31780720 |
| Justin SELLARS Senior Urban Planner Planning Services House & Homes justin.sellars@brisbane.qld.gov.au 3403 6546 |
Emma MEZZINA Team Manager Planning Services South Emma.Mezzina@brisbane.qld.gov.au 3178 0049 |
Callan BENNETT Principal Architect Architecture Team Callan.Bennett@brisbane.qld.gov.au 07 31780595 |
| Tanveer BAINS Engineer Engineering Compliance Tanveer.Bains@brisbane.qld.gov.au 31787301 |
Glyn CHISHOLM Senior Landscape Architect Landscape Architecture Team Glyn.Chisholm@brisbane.qld.gov.au 07 3403 0117 |
Jennifer SNEESBY Team Manager (Acting) Planning Services City West Jennifer.Sneesby@brisbane.qld.gov.au (07) 3403 4436 |
DRAWINGS AND DOCUMENTS
| Drawing or Document | Number | Plan Date |
|---|---|---|
| Traffic Engineering Assessment | 25-683 | 20-FEB-2026 (Received) |
| Landscape Concept Plan | SK001 Revision B | 20-FEB-2026 (Received) |
| Bulk Earthworks Layout Plan | LC25017.C200 Revision C (Amended In Red 05-MAY-2026) | 28-APR-2026 (Received) |
| Site Plan and Project Information | DA-0012 Revision 15 | 20-FEB-2026 (Received) |
| Basement 01 | DA-1200 Revision 31 | 20-FEB-2026 (Received) |
| Ground Level | DA-1201 Revision 27 | 20-FEB-2026 (Received) |
| Level 1 | DA-1202 Revision 26 | 20-FEB-2026 (Received) |
| Level 2 | DA-1203 Revision 20 | 20-FEB-2026 (Received) |
| Level 3 | DA-1204 Revision 21 | 20-FEB-2026 (Received) |
| Level 4 | DA-1205 Revision 27 | 20-FEB-2026 (Received) |
| Level 5 | DA-1206 Revision 27 | 20-FEB-2026 (Received) |
| Level 6 | DA-1207 Revision 26 | 20-FEB-2026 (Received) |
| Roof Plan | DA-1208 Revision 17 | 20-FEB-2026 (Received) |
| Building Elevations | DA-2100 Revision 19 | 20-FEB-2026 (Received) |
| Building Elevations | DA-2101 Revision 18 | 20-FEB-2026 (Received) |
| Building Elevations | DA-2102 Revision 20 | 20-FEB-2026 (Received) |
| Building Elevations | DA-2103 Revision 18 | 20-FEB-2026 (Received) |
| Building Section | DA-3100 Revision 22 | 20-FEB-2026 (Received) |
| Building Section | DA-3101 Revision 20 | 20-FEB-2026 (Received) |
| Building Section | DA-3102 Revision 15 | 20-FEB-2026 (Received) |
APPROVAL CONDITIONS
| Permit to Which These Conditions Relate: | DA - PA - Material Change of Use |
| Activity(ies): | multiple dwelling |
| Stage: | Multiple dwelling (15 units) |
| 1) Maintain the Approved Development Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions. |
At all times |
| 2) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers. Note: This condition is imposed to ensure compliance with the conditions of development approval. |
While site/operational/building work is occurring |
| 3) Carry Out the Approved Development Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS. Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners. |
While site/operational/building work is occurring |
| 4) Security Lighting - On Site Install and maintain a suitable system of security lighting to operate from dusk to dawn within all areas where the public may gain access, including car parking areas, building entrances and vegetated areas. Ensure that all external lighting is in accordance with Australian Standard - AS4282- Control of the Obtrusive Effects of Outdoor Lighting. Ensure lighting over publicly accessible internal pathways covered by permanent awnings is in accordance with Australian Standard - AS/NZS 1158.3.1 Lighting for roads and public spaces - Pedestrian area (Category P) lighting - Performance and design requirements. Lighting must be maintained in safe and good working order. |
Prior to Council's notation on the plan of subdivision and then to be maintained |
| 5) Complete All Building Work Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS. Note: Building work must also be completed in accordance with any other current development approval. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 6) Visitor Parking Visitor car parking spaces must: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 7) Construct External Details Construct and maintain external details of the building(s) in accordance with the approved DRAWINGS AND DOCUMENTS. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
7(a) Submit External Details Submit to, and obtain approval from, Development Services further details of the building, facade treatment and external materials, colours and finishes consistent with the approved DRAWINGS AND DOCUMENTS. Timing: Prior to building work above ground level commencing. |
As indicated |
7(b) Implement Approved External
Details Carry out the approved external details treatment in accordance with approved drawings. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained. |
As indicated |
| 8) Overall Height The overall height of the building(s) must be in accordance with the floor and roof levels and overall height shown on the APPROVED DRAWINGS AND DOCUMENTS. NOTE: This condition should be read in conjunction with any other relevant condition requiring minimum height clearances for basement or undercover car parking and manoeuvring areas. |
While site/operational/building work is occurring and then to be maintained |
8(a) Submit Certification Submit to Development Services certification from a registered surveyor confirming that the 'as constructed' floor and roof levels and overall height are in accordance with the requirements of this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 9) Light Reflectivity and Solar (Heat)
Reflectivity Submit to Development Services documentary evidence that the level of light reflectivity from the glazing incorporated in the approved development does not exceed 20%. Timing: Prior to building work above ground level commencing. |
As indicated |
9(a) Install Glazing Install and maintain glazing in accordance with the above specification. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained. |
As indicated |
| 10) Driveway Material and Finishes Provide materials and
finishes to the driveway and external carparking
surfaces that reduce the visual impact of these areas when viewed from the
street. One or a combination of the following must be used: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 11) Provide Pedestrian Prioritised Pathway Provide a pedestrian prioritised pathway from the street frontage to the entry of the building. The pathway must be differentiated in colour and texture from the driveway surface. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 12) Balconies/Verandahs/Terraces No balconies/verandahs/terraces may be enclosed with solid balustrades, solid walls, fixed and/or operable, moveable or adjustable screening unless these features are clearly shown on the APPROVED DRAWINGS AND DOCUMENTS. Note: Any Community Management Statement that may apply to this approval must contain a by-law which reflects the requirements of this condition. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 13) Screen Air Conditioning and Other Plant
Enclosures Install and maintain suitable screening to all air conditioning, lift motor rooms, plant and service facilities located at the top of or on the external face of the building and within the Private Open Spaces. The screening structures must be constructed from materials that are consistent with materials used elsewhere on the facade of the building. There must be no individual external air conditioning units. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 14) Screening Provide suitable privacy screening to windows of habitable rooms, balconies, landings, terraces and decks of the proposed dwelling(s) in accordance with the approved DRAWINGS AND DOCUMENTS. Suitable screening options must be: For windows: For balconies, landings, terraces
and decks: Note: Screening devices must be either solid translucent screens, perforated or slatted panels, or fixed louvres that are permanent, be durable and fixed. Screening devices must have a maximum of 25% openings, with a maximum opening of 50mm unless otherwise shown on the approved DRAWINGS AND DOCUMENTS. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 15) Retain and Protect Existing Street Tree(s) Identify, retain and protect the existing street trees including the roots unless otherwise agreed in writing with Public Space Operation Arboriculture Planning (PSO Arb Planning). Note: Street trees are protected under the Natural Assets Local Law. Street trees must not be removed or pruned without prior approval from PSO Arb Planning. PROOF OF FULFILMENT Contextual photographic evidence that the tree has been retained in equal or greater health than before development commenced. OR, evidence in writing from PSO Arb Planning that an alternative arrangement has been made. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
At all times |
15(a) Implement Protection
Measures Install tree protection measures in accordance with Australian Standard - AS4970 Retention of Trees on Development Site. There must be no excavation, filling or storage of materials or plant within the drip line of the tree(s). Where works are within the canopy drip line of existing street trees, contact PSO Arb Planning in relation to the required provision of protection measures. Note: If fencing is to protect street trees, a permit to temporarily occupy the footway will be required from Compliance and Regulatory Services. Timing: Prior to site/operational/building work occurring. PROOF OF
FULFILMENT Contextual photographic evidence to demonstrate the installation of protection measures prior to building works commencing. Timing: Prior to site / operational / building work occurring. |
As indicated |
15(b) Maintain Protection
Measures Maintain protection measures while development is occurring and remove protection measures prior to commencement of the use. Timing: While to site/operational/building work is occurring. |
As indicated |
| 16) Streetscape Works - Neighbourhood Street
Minor Carry out streetscape improvement works including concrete path (where required by this condition) and turf to the verge of the Central Avenue frontage of 61 Swann Road, Taringa to a Neighbourhood Street Minor standard in accordance with the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD), the requirements of this condition and the Infrastructure Design Planning Scheme Policy including sections 3.7.4.4 and 3.7.5. Where possible driveway and verge grades are to be generally in accordance with Council standards where possible. The non-standard driveway batter, adjoining non-standard transitional verge batters and associated driveway ramp into the basement on Central Avenue is to be detailed in operational works, filling and excavation design certified by an RPEQ. Refer to the Engineering condition titled - Filling and/or Excavation for further details |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
16(a) Concrete Path Install a 1.2m wide broom finished standard Portland grey concrete path. The front edge of the new footpath is to be set on
the existing alignment with the additional width being taken up between
the rear edge of the new path and the property boundary. Where the path cannot
be installed on this alignment due to conflicts such as street trees, or power
poles, ensure the path is installed a minimum distance of: If the above requirements cannot be achieved, contact the Landscape Architecture Team via email: specialistservices@brisbane.qld.gov.au. Transition to existing paths on verges that adjoin the development. The transition is to occur fronting the adjoining developments, not the subject site. Note: standard path alignments are shown on Brisbane Standard Drawing BSD-5201 sheet 2 but will vary depending on verge width and location. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Photographic evidence of concrete path. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
16(b) Submit As-Constructed
Drawings Submit to Development Services As Constructed plans including an asset register, checked by a Registered Professional Engineer Queensland, certifying that the concrete path works have been completed in accordance with relevant Brisbane Planning Scheme Codes/Policies. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT As constructed drawings signed by an RPEQ. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
16(c) Turf Install turf to the full width of the verge excluding any concrete path required by this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Photographic evidence of installed turf. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 17) Streetscape Works - Neighbourhood Street
Major Carry out streetscape improvement works including concrete path (where required by this condition) and turf to the verge of the Swann Road frontage of 61 Swann Road, Taringa to a Neighbourhood Street Major standard in accordance with the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD), the requirements of this condition and the Infrastructure Design Planning Scheme Policy including sections 3.7.4.4 and 3.7.5. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
17(a) Concrete Path Install a 1.8m wide broom finished standard Portland grey concrete path. The edge of the path is to be setback 1300mm from the back of kerb.
Where the path cannot be installed on this alignment due to conflicts such as
street trees, or power poles, ensure the path is installed a minimum distance
of: If the above requirements cannot be achieved, contact the Landscape Architecture Team via email: specialistservices@brisbane.qld.gov.au. Transition to existing paths on verges that adjoin the development. The transition is to occur fronting the adjoining developments, not the subject site. Note: Prior to construction of the footpath, contact Public Space Operations Arboriculture Planning (PSO Arb Planning) via email ISG-CS-PPI-PLANNING- ARB@Brisbane.qld.gov.au and request advice on footpath construction methodology and appropriate clearance between the footpath and street tree. Note: standard path alignments are shown on Brisbane Standard Drawing BSD-5201 sheet 2 but will vary depending on verge width and location. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Photographic evidence of concrete path. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
17(b) Submit As-Constructed
Drawings Submit to Development Services As Constructed plans including an asset register, checked by a Registered Professional Engineer Queensland, certifying that the concrete path works have been completed in accordance with relevant Brisbane Planning Scheme Codes/Policies. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT As constructed drawings signed by an RPEQ. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
17(c) Turf Install turf to the full width of the verge excluding any concrete path required by this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Photographic evidence of installed turf. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 18) Landscape the Site - Self Certification Landscape the site in accordance with the requirements of this condition. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
18(a) Detailed Landscape Plan for Self-
Certification Prepare a Detailed Landscape Plan at a scale of 1:100 for all on-site landscape works including planting areas identified on the approved DRAWINGS AND DOCUMENTS. The plan must be prepared by a Qualified Landscape Architect and must comply with the relevant Brisbane Planning Scheme Codes. The plan must include the following: Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT A detailed landscape plan accompanied by Brisbane City Council Form CC10616 - Landscape Design Certificate. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
18(b) Multiple Unit Dwelling In addition to the requirements listed above, the plan must include the
following: Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT A detailed landscape plan accompanied by Brisbane City Council Form CC10616 - Landscape Design Certificate. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
18(c) Certify Detailed Landscape
Plan On completion of the Detailed Landscape Plan, submit to Development
Services: Timing: Prior to building work commencing. PROOF OF FULFILMENT A detailed landscape plan accompanied by Brisbane City Council Form CC10616 - Landscape Design Certificate. Timing: Prior to building work commencing. |
As indicated |
18(d) Implement Certified Detailed Landscape
Plan Carry out the landscape work in accordance with the above certified detailed Landscape Plan. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
18(e) Certify Work On completion of the
landscape work, submit to Development Services: Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT An as constructed landscape plan accompanied by Brisbane City Council Form CC10613 - Landscape Works Certificate. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
18(f) Maintain Landscape Work Maintain the landscape work, including deep planting, in accordance with the certified Detailed Landscape Plan. Timing: To be maintained. |
As indicated |
| 19) Dampening of Grilles and Metal Plates All metal grilles, metal plates or similar located within vehicle parking and manoeuvring areas must be securely fastened and meet the requirements of AS3996:2019, Access covers and grates. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 20) On-site Erosion (Medium Risk) Manage on-site erosion and the release of sediment or sediment laden water from the site at all times by implementing best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version). Timing: Prior to commencement of any land disturbing activities and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
20(a) Manage earth disturbance on-
site (i) Drainage control measures must be implemented and maintained to minimise water flow onto areas of exposed earth. (ii) Sediment and erosion control measures must be implemented and maintained to prevent soil loss from earth disturbance areas and prevent deposition beyond earth disturbance areas. (iii) No release of contaminants to land beyond on-site area of earth disturbance other than releases that achieve water pollutant concentration release limits of: A. 50mg/L TSS (Total Suspended Solids); B. Turbidity, Nephelometric Turbidity Units (NTU) value less than 10% above background, 75 NTU, or as agreed in writing by an Officer from Councils Erosion and Sediment Control (ESC) Team in Compliance and Regulatory Services; C. pH between 6.5 and 8.5 at all times. (iv) Maintain a written record to demonstrate that water discharges from the site, including any dewatering operations, meet the release limits as detailed in (iii) for water discharge(s) from the site that occur during or immediately after a rainfall event, and during normal business hours. The water quality of the discharge flows must be measured at each discharge point from the site, including but not limited to sediment basin outlets, other applicable sediment control devices, the site water drainage system, and recorded against the release limits at least once on each calendar day until such discharge stops. Timing: Prior to commencement of any earth disturbing activities and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
20(b) Provide Land Occupier Notification to
Council (i) Notify Council's ESC Team of proposed land occupier/s by sending an email to CARS-ESC@Brisbane.qld.gov.au (ii) If the land is to be occupied by any person other than the registered landowner then advice must be provided to Council that confirms the name, contact information and the duration of any proposed occupation of the land. Timing: Prior to commencement of any earth disturbing activities. |
As indicated |
20(c) Prepare Erosion and Sediment Control
Plan Prepare an Erosion and Sediment Control Plan (ESCP) in accordance with best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version) and, to the extent of any inconsistency, relevant Brisbane Planning Scheme Codes and Policies. Obtain a design certificate in accordance with the relevant Brisbane Planning Scheme Codes and Policies. The ESCP and design certificate must be certified by a Certified Professional in Erosion and Sediment Control (CPESC) or a Registered Professional Engineer Qld (RPEQ) with suitable qualifications and experience in erosion and sediment control. Documentary evidence demonstrating appropriate qualifications in erosion and sediment control must be provided to the Council upon request. Timing: Prior to the commencement of any earth disturbing activities. |
As indicated |
20(d) Attend a pre-start
meeting Arrange and attend a pre-start meeting for ESC with an Officer from Councils ESC Team in Compliance and Regulatory Services (CARS). Note: To request a pre-start meeting from Council's ESC Team send an email to CARS-ESC@Brisbane.qld.gov.au. All relevant documentation, including both the certified ESCP and the certified design certificate, must be attached to this email. Please allow up to 10 business days for your request to be processed. Timing: Attend the pre- start meeting prior to the commencement of any earth disturbing activities. |
As indicated |
20(e) Implement Certified Erosion and
Sediment Control Plan Implement the certified ESCP and maintain all ESC measures in accordance with best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version) and, to the extent of any inconsistency, relevant Brisbane Planning Scheme Codes and Policies. The ESCP and design certificate must be available on site at all times for inspection by Council officers. Any alteration to supplementary or Type 3 ESC measures must be reflected in the certified ESCP. Any alteration to Type 2 or Type 1 ESC measures will require a revised ESCP and design certificate that has been certified by either the CPESC or RPEQ. Timing: While earth disturbing activities are occurring and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
| 21) Information Signage Erect an information sign on the subject property in
accordance with Council's general requirements for signage and in accordance
with the requirements outlined below: Timing: Prior to site works commencing and then to be maintained until completion of the development for all stages. |
As indicated |
| 22) Filling and / or Excavation All earthworks must be carried out in accordance with the relevant Brisbane Planning Scheme Codes and the approved Bulk Earthworks Layout Plan LC25017.C200 Revision C, received 28-APR-2026 and amended in red 05-MAY-2026. Where possible driveway and verge grades are to be generally in accordance with Council standards. Basement grades and levels are to accommodate for this where possible. The non-standard driveway batter, adjoining non-standard transitional verge batters and associated driveway ramp into the basement on Central Avenue is to be detailed in operational works, filling and excavation design certified by an RPEQ. |
Prior to building work commencing |
22(a) Submit Earthworks
Drawings Submit to, and obtain approval from, Development Services earthworks drawings prepared and certified by a Registered Professional Engineer Queensland in accordance with the approved DRAWINGS AND DOCUMENTS and the relevant Brisbane Planning Scheme Codes. The Earthworks Drawings
must include the following: Note: If the earthworks impact on the road reserve, the Developer must obtain applicable footpath and road permits prior to commencing any works. Such impacts may include footpath occupation, road closures, re-profiling, ground anchors and/or relocation of services. If the excavation has to be stabilised using ground anchors or similar, then the submitted plans must show the location of these in relation to all services. The cost of moving services, utilities and assets is the responsibility of the Developer. The permission of the service/utility/asset owner is required. Note: Irrespective of final earthworks, it is the responsibility of the RPEQ to manage any staged works associated with Erosion & Sediment Control. Timing: Prior to site/operational/building work commencing. |
As indicated |
22(b) Fill Material, Placement, Compaction
and Testing All fill material placed on the site must comprise only natural earth and rock and must be free of contaminants (as defined by Part 3, Division 2, Subdivision 2 Environmental contamination, Section 11 of the Environmental Protection Act 1994) and noxious, hazardous, deleterious and organic materials. Fill material, placement, compaction and testing must comply with the requirements of Australian Standard - AS 3798, Guidelines on Earthworks for Commercial and Residential Developments. Timing: While site/operational/building work is occurring. |
As indicated |
22(c) Implement Approved Earthworks
Drawings Construct and maintain the earthworks in accordance with the requirements of AS3798 and the approved earthworks drawings. Timing: While site/operational/building work is occurring and then to be maintained. |
As indicated |
22(d) Submit As Constructed
Drawings Submit to Development Services As Constructed drawings prepared by a Registered Surveyor. Timing: Prior to building work above ground commencing. |
As indicated |
22(e) Submit Certification Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the approved earthworks drawings. Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that all fill material used complies with the quality requirements of this condition and that placement, compaction and testing has been carried out in accordance with AS3798. Timing: Prior to building work above ground commencing. |
As indicated |
| 23) Basement Excavation and Support Basement excavation and support of all exposed walls must be carried out in accordance with the relevant Brisbane Planning Scheme Codes and the requirements of this condition. |
Prior to building work commencing |
23(a) Prepare Engineering
Drawings Engineering drawings for the work required by this condition must be prepared and certified by a Registered Professional Engineer Queensland (Structural), in accordance with the relevant Brisbane Planning Scheme Codes detailing the design of the proposed excavation as well as proposed temporary and permanent support (if no temporary proposed) systems. The design must include at least the following: Notes: Timing: Prior to site/operational/building work commencing. |
As indicated |
23(b) Implement Certified Engineering
Drawings Construct and maintain the basement excavation and proposed support system in accordance with the above certified engineering drawings. Note: A copy of the certified engineering drawings must be available on- site for inspection by Council Officers during these works. Timing: While basement excavation and support system installation is occurring. |
As indicated |
23(c) Submit Post Construction
Certification Submit certification by a Registered Professional Engineer Queensland that the basement excavation and support have been installed in compliance with the certified engineering drawings, the relevant Brisbane Planning Scheme Codes and the requirements of this condition. Where ground or rock anchors have been installed, submit certification by a Registered Professional Engineer Queensland (Geo-technical) that all anchors have been de- stressed. Timing: Prior to building work commencing above ground. |
As indicated |
| 24) Construction Management Plan - Major Carry out development in a method consistent with a Construction Management Plan (CMP) prepared in accordance with the requirements of this condition. Carry out development in accordance with a Construction Management Plan (CMP) prepared using guidance from the Central Business District and City Frame Development Services Construction Management Guidelines and the requirements set out in this condition due to the sensitive area nearby this development site. The development is to be minimise impact to Council verge and roads and is to be staged to accommodate for this. The project staging and costing is to incorporate that future lane or footway closures may be restricted and at the discretion of the relevant department within Council. Note: This condition imposes restrictions on development construction management to regulate increased truck access, on street work zone and closures, footway closures and all associated activities as a result of several nearby projects occurring near the site. |
While site/operational/building work is occurring |
24(a) Construction Management Plan - Submit
Plan Submit to, and obtain compliance approval from, Development Services a detailed Construction Management Plan for the site preparation, demolition, excavation and construction phases of the approved development. The Construction Management Plan must be in accordance with the relevant Brisbane Planning Scheme Codes and address the following matters, both internal to and external to the development site: (i)
Location of and impacts to any Council vegetation (i.e. street
trees/park trees/garden beds) The Construction Management Plan must be supported by 'approval in principle' or written approvals from the relevant Council sections or other governing bodies responsible for any potentially impacted infrastructure. The list of relevant infrastructure and contacts is available on Council's website - Search 'Constructions Management Plan'. Timing: Prior to site/operational/building work commencing. |
As indicated |
24(b) Construction Management Plan -
Dilapidation Report Submit a dilapidation report to engineeringservices@brisbane.qld.gov.au detailing the pre-existing condition of the roadway, both footways, both verges and Council infrastructure, including vegetation, for 100m from the site entry in both directions or to the next street intersection (if less than 100m from the site entry) in both directions. Timing: Prior to the pre-start meeting. |
As indicated |
24(c) Construction Management Plan -
Documentation on Site Legible copies of the approved Construction Management Plan and current permits must be kept on site and be made available on request by Council, at all times. The requirements of the CMP must be included in all induction of principal and subcontractors utilised in the development. An outline of the induction provided to contractors may be requested by Council to confirm compliance with this condition. Timing: While site/operational/building work is occurring. |
As indicated |
24(d) Construction Management Plan - Works to
be Performed Out of Hours Obtain an approval from Development Services for any
work that is proposed to be undertaken outside of normal business hours -
6:30am to 6:30pm, Monday to Saturday. |
As indicated |
24(e) Construction Management Plan -
Implement Plan Carry out the development in accordance with the approved Construction
Management Plan. |
As indicated |
| 25) Protect Existing Infrastructure Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure. Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations. The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements. |
While site/operational/building work is occurring |
25(a) As Constructed Drawings - Alterations
to Existing Infrastructure Submit to Development Services As Constructed drawings showing all new and/or rectification works and an asset register, prepared by a Registered Professional Engineer Queensland. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 26) Access, Grades, Manoeuvring, Carparks, Signs and
Line Marking Construct and maintain access, parking and manoeuvring for vehicles on site in accordance with the relevant Brisbane Planning Scheme Codes, and the approved Traffic Engineering Assessment, 25-683, received 20-FEB-2026, including the following: i. A pavement of minimum Local road standard or equivalent surface material (including associated drainage) to the area on which motor vehicles will be driven and/or parked. ii. Manoeuvring on site for a MRV and for the loading and unloading of vehicle(s); iii. Parking on the site for 33 resident/tenant cars, 4 visitor cars including 1 parking space for people with disabilities and for the loading and unloading of vehicle(s) within the site. There must a minimum number of 37 spaces provided on site. iv. Provide and maintain 15 resident secure bicycle parking spaces and 4 visitor bicycle parking spaces; v. A minimum of 2.3 metres height clearance to all undercover parking areas and a minimum of 2.5 metres above parking spaces for people with disabilities. The minimum clear height must be measured to the lowest protrusion from the ceiling (e.g. fire sprinklers, services, lighting fixtures, signs, etc). vi. A height clearance sign located at the entrance(s) to undercover car parking areas and a directional visitor parking sign clearly visible from the vehicle entrance to the site. vii. Prepare and implement signs and line markings drawings that show the internal paved areas signed and delineated in accordance with the approved drawings and documents. The drawings must be prepared and certified by a Registered Professional Engineer Queensland in accordance with the relevant Brisbane Planning Scheme Codes and the Manual of Uniform Traffic Control Devices. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland, that the above requirements have been implemented in accordance with this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 27) Repair Damage to Kerb, Footpath or Road Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
27(a) Interim Repairs If at any time during the construction phase of the approved development, damage to the existing kerb and channel, footpath or roadway creates unsafe, unreasonable and/or not fit for purpose conditions as assessed by Council, interim repairs must be undertaken as directed by Asset Services. Note: Any interim repairs required to be undertaken shall not be considered to satisfy the requirements of this condition for the permanent repair of the infrastructure prior to the issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. Timing: While site / operational / building works is occurring. |
As indicated |
| 28) Refuse Collection - On Site Provide for the installation and collection of refuse/recycling bins by Brisbane City Council's Waste and Resource Recovery Services or a private waste contractor. |
At all times |
28(a) Arrange Refuse Collection Arrange for the installation of refuse/recycling bins and for the subsequent collection of refuse including recycling from the site by Brisbane City Council's Waste and Resource Recovery Services or a private waste contractor. Timing: A minimum of four weeks prior to the commencement of use and then to be maintained. PROOF OF FULFILMENT Where a private waste contractor is engaged, provide written confirmation from the proposed waste collection contractor of the agreement to service the property. The written agreement must be submitted to Council's Waste and Resource Recovery Services and include full details of the proposed system, bin sizes, number of bins, frequency of collection and the refuse collection vehicle size. Timing: Prior to commencement of use. |
As indicated |
28(b) Notify Future Owner Where Council is engaged as the waste contractor, the owner must notify any future owner/body corporate that the development has been approved on the basis that an indemnity must be provide for refuse collection vehicles to enter the property. Timing: At time of a change of ownership. |
As indicated |
28(c) Indemnify Council The owner and any subsequent owner must, by approved form to Waste and Resource Recovery Services, indemnify Council and its agents in respect of any damage to the pavement and other driving surfaces. Timing: When an arrangement for refuse/recycling collection services is made with Brisbane City Council. |
As indicated |
| 29) Refuse Storage - On Site Collection Provide a roofed and wholly screened refuse enclosure utilising materials consistent with the development or a dedicated refuse storage room, as shown on the approved plans and documents. The enclosure/refuse storage room must be of a design to accommodate the quantity of refuse and recycling including source separation to allow for low servicing collection of the development. Bins must be located in an area which allows them to be manoeuvred from the bin storage area to the designated internal collection point. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 30) Site Drainage - Major Provide an internal drainage system to collect stormwater run-off from all proposed lots, roofed and developed surface areas and any run-off onto the site from adjacent areas and convey the collected run- off to a lawful point of discharge, in accordance with the relevant Brisbane Planning Scheme Codes. Notes: - Where external works are required and
infrastructure will be handed over to Council (e.g. Stormwater pipes 375mm or
greater and/or manholes within the road reserve, etc), the applicant will be
required to request an on-site Pre-Start with Council and ensure all future
owned Council assets follow the On/Off Maintenance process in accordance with
Councils Infrastructure Installation & Construction Requirements
Manual. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
30(a) Submit Site Drainage
Drawings Submit to, and obtain approval from, Development Services, site drainage drawings and engineering calculations, prepared and certified by a Registered Professional Engineer Queensland, in accordance with the relevant Brisbane Planning Scheme Codes. Notes: -
Queensland Building and Construction Commission licensed hydraulic
consultants may design the stormwater system for sites less than 2000m2 with an
upstream catchment servicing no more than 4 residential lots. This
excludes stormwater drainage design (including subsoil drainage) of basements
in flood planning areas and the design of any onsite stormwater detention
system Timing: Prior to site/operational/building work commencing |
As indicated |
30(b) Implement Approved
Drawings Carry out the works in accordance with the approved site drainage drawings. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
30(c) Submit As Constructed
Drawings Submit to Development Services As Constructed drawings prepared and certified by a Registered Professional Engineer Queensland or a Queensland Building and Construction Commission licensed hydraulic consultants (where applicable). Note: To be submitted via da- engineeringcompliance@brisbane.qld.gov.au and include the site address, A00 reference and Condition number in the subject line. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland or Queensland Building or Construction Commission licensed hydraulic consultants (where applicable) confirming that the works have been completed in accordance with the above stormwater drawings. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 31) Ponding of Stormwater Carry out the approved development to ensure that adjoining properties and roads are protected from ponding or nuisance from stormwater during construction. Notes: If remedial works are necessary to comply with this condition, prior approval must be obtained from Development Services. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 32) Service Conduits and Mains Provide and install all
service conduits and meet the cost of any alterations to public utility mains,
existing mains, services, street lighting or installations that are required to
carry out the approved development. These works must be in accordance with the
relevant Brisbane Planning Scheme Codes, and include the following, where
applicable: Note: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
32(a) Submit As Constructed
Drawings Submit to Development Services As Constructed drawings, including an asset register, prepared and certified by a Registered Professional Engineer Queensland. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the requirements of this condition. Note: Civil works are to be certified by a RPEQ(Civil) and electrical works are to be certified by a RPEQ (Electrical). |
As indicated |
| 33) Conduit for Brisbane City Council Provide a single
underground conduit (100mm diameter UPVC class PN9) in favour of Brisbane City
Council on at least one side of all Neighbourhood Access Roads (Bus Route
only), Primary Freight Access Roads and Major Roads. The works must be in
accordance with the relevant Brisbane Planning Scheme Codes and the
following: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
33(a) Submit As Constructed
Drawings Submit to Development Services, As Constructed drawings, including an asset register, prepared and certified by a Registered Professional Engineer Queensland. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the requirements of this condition. |
As indicated |
| 34) Telecommunications Submit to Development Services, certification from
an authorised telecommunications carrier/contractor, that the following works
and infrastructure have been undertaken and installed in accordance with
telecommunications industry standards: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 35) Agreement with Electricity Supplier Submit to Development Services, evidence of an agreement with an electricity supplier to provide necessary services to the development in accordance with the relevant Brisbane Planning Scheme Codes. Where development is within an established area of overhead electricity supply and the electricity supplier determines that a property pole is the appropriate solution to supply electricity to the development, the developer must be responsible for the installation of the property pole(s). In the above circumstances, submit to Development Services, certification from the developer's electrical consultant confirming that the above installation has been completed in accordance with the relevant AS/NZS Standards and the Queensland Electricity Connection Manual (QECM) and Queensland Electricity Metering Manual (QEMM). |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 36) Permanent Driveway Crossover Provide a 6.5 metre wide Type B2 permanent driveway crossover to the Central Ave frontage of the site in accordance with the relevant Brisbane Planning Scheme Codes and located as shown on the approved DRAWINGS AND DOCUMENTS. Written consent must be obtained from BCC - Field Services, Asset Services Arborist prior to any works occurring that will either impact on or require removal of a street tree (this includes pruning and excavation within the root zone/canopy of the tree) At all times during construction of the crossover, safe pedestrian access along the site frontage must be maintained. Note: No further driveway permit is required however additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 37) Redundant Driveway Crossover Remove the redundant existing driveway crossover(s) on the frontage(s) of the site and reinstate the kerb and channel, road pavement, footways and footpaths in accordance with the relevant Brisbane Planning Scheme Codes. Note: Additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 38) Construction Noise and Dust Emissions Pursuant to the Environmental
Protection Act 1994, all development involving the emission of noise and dust
from building and/or construction activities, must ensure that the emissions
are in accordance with the requirements of the Act. |
As indicated |
| 39) Currency Period The currency period for this development approval is stated in the Decision Notice and is expressed as a date. This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016. |
As indicated |
| 40) Equitable Access Provision must be made during and after construction
for equitable access for persons with disabilities to and within the site and
on adjoining public areas, in accordance with the following: |
As indicated |
| 41) Damage to Trees on Adjoining Land Please note that any damage caused to vegetation on adjoining land as a result of exercising this development approval may result in an offence under other legislation (e.g. Natural Assets Local Law) and/or civil action |
As indicated |
| 42) Fire Ant Movement Controls To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected. These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products. Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014. For further information contact the relevant Queensland State Government department on 13 QGOV. |
As indicated |
| 43) Water and Wastewater Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. For further information about any necessary Water Approvals contact Urban Utilities. |
As indicated |