BRISBANE CITY COUNCIL'S APPROVAL PACKAGE.



APPLICATION DETAILS

This package relates to the application detailed below
Address of Site: 10 BANK ST WEST END QLD 4101
14 BANK ST WEST END QLD 4101
4 BANK ST WEST END QLD 4101
8 BANK ST WEST END QLD 4101
Real Property Description of Site: L45 RP.10779
L44 RP.10779
L47/48 RP.10779
L46 RP.10779
Aspects of development and type of approval: DA - SPA - Carry out Building Work Preliminary Approval under s241 - Multi- Unit Dwelling
DA - SPA - Material Change of Use Development Permit - Multi-Unit Dwelling
Council File Reference: A007007144
Permit Reference Number/s: DABW296090914; DAMC296091014.
Package Status: APPROVED - Version 3 (25th of June, 2026 2:56:23 PM)
Package Generated: 25/06/2026


PROJECT TEAM

The assessment of this application has been undertaken by:
Diana SUN
Urban Planner
Planning Services South
Diana.Sun@brisbane.qld.gov.au
0731785179
Ashleigh COOMBES
Principal Urban Planner
Planning Services South
Ashleigh.Coombes@brisbane.qld.gov.au
(07) 3403 1937
Peter MCDONALD

WaRRS Assessment
Peter.McDonald@brisbane.qld.gov.au
Andrew BLAKE
Principal Engineer
Engineering Services Hydraulics
andrew.blake@brisbane.qld.gov.au
(07) 3403 5018
Daniel SPILLANE
Senior Engineer
Engineering Services South
Daniel.Spillane@brisbane.qld.gov.au
3403 5285
Daniel SPILLANE
Senior Engineer
Engineering Services South
Daniel.Spillane@brisbane.qld.gov.au
3403 5285
David HOOPER
Principal Urban Planner
Planning Services South
Dave.Hooper@brisbane.qld.gov.au
(07) 3403 9889
Roger GREENWAY
Principal Urban Planner
Development Assurance & Outcomes
roger.greenway@brisbane.qld.gov.au
34034392
David HOOPER
Principal Urban Planner
Planning Services South
Dave.Hooper@brisbane.qld.gov.au
(07) 3403 9889
Roger GREENWAY
Principal Urban Planner
Development Assurance & Outcomes
roger.greenway@brisbane.qld.gov.au
34034392
Callan BENNETT
Principal Architect
Architecture Team
Callan.Bennett@brisbane.qld.gov.au
07 31780595
Phil EASTGATE
Principal Technical Officer
Engineering Compliance
philip.eastgate@brisbane.qld.gov.au
(07) 3403 9432
Daniel SPILLANE
Senior Engineer
Engineering Services South
Daniel.Spillane@brisbane.qld.gov.au
3403 5285
Katrina KONTOS
Environmental Management Officer
Environmental Management Services
katrina.s.kontos@brisbane.qld.gov.au
(07) 3403 8888
Carina FIESELER
Landscape Architect
Landscape Architecture Team
carina.fieseler@brisbane.qld.gov.au
3403 5235


DRAWINGS AND DOCUMENTS



The term 'drawings and documents' or similar expressions mean:
Drawing or Document Number Plan Date
Noise Impact Assessment_8 Bank St West End 7247R02V06 Prepared by Ask Consulting 30-JUL-2014
Extract from Stormwater Management Report - 4-14 Bank Street West End, Section 4.1 pp2-4, Prepared by Westera Partners Job No. B14-037 17-JUL-2014 (Received)
Appendix B: Stormwater Management Plan Sheet 1 of 4 Revision B (Amended In Red 06-AUG-2014) 30-JUN-2014
GROUND FLOOR PLAN NRA-84113-3000-GF00 Rev 1 17-APR-2026 (Received)
LoadingDock Ramp 01 25061 1.01 (Amended In Red 23-JUN-2026) 17-APR-2026 (Received)
LoadingDock Ramp 02 25061 1.02 (Amended In Red 23-JUN-2026) 17-APR-2026 (Received)
Coversheet BD 200 Issue A 30-JUN-2015
Legend, Notes, Schedules BD 201 Issue A 30-JUN-2015
Surface Finishes Ground Floor BD 301 Issue A (Amended In Red 23-JUN-2026) 30-JUN-2015
Surface Finishes Level 1 BD 302 Issue A 30-JUN-2015
Surface Finishes Roof BD 303 Issue A 30-JUN-2015
Planting Plan Ground Floor BD 401 Issue A 30-JUN-2015
Planting Plan Level 1 BD 402 Issue A 30-JUN-2015
Planting Plan Roof BD 403 Issue A 30-JUN-2015
Landscape Details BD 601 Issue A 13-JUL-2015
Landscape Details BD 602 Issue A 30-JUN-2015
Landscape Details BD 603 Issue A 30-JUN-2015
Basement 03 NRA-84113-2010-BS03 Rev 4 01-FEB-2016
Basement 2 NRA-84113-2020-BS02 Rev. 4 01-FEB-2016
Basement 1 NRA-84113-2030-BS01 Rev. 4 01-FEB-2016
Level 01 Plan NRA-84113-3010-LV01 Rev 2 (Amended In Red 16-MAR-2015) 17-DEC-2015
Level 02 Plan NRA-84113-3020-LV02 Rev 2 (Amended In Red 16-MAR-2016) 17-DEC-2015
Level 03 Plan NRA-84113-3030-LV03 Rev. 2 (Amended In Red 16-MAR-2016) 17-DEC-2015
Level 04 Plan NRA-84113-3040-LV04 Rev 2 (Amended In Red 16-MAR-2016) 17-DEC-2015
Level 05 Plan NRA-84113-3050-LV05 Rev 2 (Amended In Red 16-MAR-2016) 17-DEC-2015
Level 06 Plan NRA-84113-3060-LV06 Rev. 2 (Amended In Red 16-MAR-2016) 17-DEC-2015
Level 07 Plan NRA-84113-3070-LV07 Rev. 2 (Amended In Red 16-MAR-2016) 17-DEC-2015
Roof Plan NRA-84113-3080-ROOF Rev. 3 (Amended In Red 16-MAR-2016) 19-JAN-2016
South East Elevation NRA-84113-4010-ELEV Rev. 3 19-JAN-2016
North East Elevation NRA-84113-4020-ELEV Rev. 3 19-JAN-2016
South West Elevation NRA-84113-4030-ELEV Rev. 1 (Amended In Red 16-MAR-2016) 27-OCT-2015
North West Elevation NRA-84113-4040-ELEV Rev. 3 19-JAN-2016
Section C-C NRA-84113-5030-SECT Rev. 4 01-FEB-2016
Section B-B NRA-84113-5020-SECT Rev. 4 01-FEB-2016
Rooftop Vent Detail NRA-84113-8090-DET Rev. 3 19-JAN-2016


Advice

Please see the attached document(s) for any advices.

APPROVAL CONDITIONS



Permit to Which These Conditions Relate: DA - SPA - Carry out Building Work
Activity(ies): Multi-Unit Dwelling
Stage:  

Standard Advice
 
Timing
1)   Further Development Permit required

This Preliminary Approval (Carry Out Building Works) does not include assessment against the Building Act and does not permit building work to occur.  Prior to the commencement of any building work, Development Permit(s) for Carrying Out Building Work will be required.

 
As indicated
 



Permit to Which These Conditions Relate: DA - SPA - Material Change of Use
Activity(ies): Multi-Unit Dwelling
Stage:  

General/Planning Requirements
 
Timing
2)   Demolish or Relocate Buildings

Demolish or relocate all existing buildings/structures on the site. The removal of buildings/structures includes the removal of all existing concrete slabs, foundations and footings.

Timing: Prior to any new building work occurring (MCU or BW) or prior to Council's notation on the plan of subdivision (ROL)

 
As indicated
 
3)   Landscaping of Vacant Site

If construction for the approved development does not commence within 3 months of the demolition of the existing building(s) on site, the site is to be landscaped in accordance with a landscape drawing that has been submitted to and approved by Development Assessment.

Timing:  Within 3 months of the demolition of the existing building(s).

 
As indicated
 
4)   Approved Drawings & Documents

A legible copy of the approved drawings and documents bearing "Council Approval" and the Development Approval Conditions package is to be available on site.

Note.  This condition is imposed to ensure compliance with the development conditions of approval. The copy of the conditions and drawings should be located in any site management office or with the site foreman. Any copies of conditions or drawings that are illegible shall be deemed to be non compliance with this condition of approval.

 
While site/operational/building work is occurring
 
5)   Carry Out The Approved Development

Carry out the approved development generally in accordance with the approved drawing(s) and/or document(s) as amended in red:

·         The roof top communal open space area shall remain open to the sky with no roof above including impervious roofing.

·         Not Part of This Approval – Storage in Basement (areas highlighted in red in red are not approved for general storage only for the storage of bicycles).

·         Screening required on the East and West Elevations.

  
Note.  This development approval may include the location of fences, retaining walls and/or external walls of buildings on the boundary of a lot. This approval does not constitute permission to enter neighbouring properties to carry out the construction (including associated drainage and earthworks) or maintenance activities.  Permission to enter neighbouring properties must be obtained from relevant property owners.

.

 
While site/operational/building work is occurring and then to be maintained
 
6)   Complete All Building Work

Complete all building work associated with this development approval, including work required by any of the conditions included in the Conditions Package. Such building work is to be carried out generally in accordance with the approved drawing(s), and/or documents and, where the building work is assessable development, in accordance with a current development permit.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
 
7)   Bicycle Parking

Install and maintain secure bicycle parking and associated support facilities consistent with the approved drawings and generally in accordance with the relevant Brisbane Planning Scheme Codes/Policies.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
8)   Car Parking

Provide 216 (including 42 tandem spaces) onsite resident car parking spaces within the building to be maintained exclusively for the residential use of the development. The parking is not to be made available to the general public and there is to be no advertising signage erected on or in the vicinity of the site advertising the availability of car parking to the general public. Parking on site is to be provided and maintained for the exclusive use of the residents of the approved development and their visitors only. Requirements of this condition shall be contained within any Community Management Statement

 
To be maintained
 
9)   Maintain the Approved Development

Maintain the approved development (including landscaping, parking, driveways and other external spaces) generally in accordance with the approved drawing(s) and/or documents, and any relevant Council engineering or other approval required by the conditions.

Note.  This condition restricts changes that can be made to the approved development (approved drawings,documents and conditions to which the approval relates). The extent to which the approved development may be modified is constrained by the requirements of the relevant planning legislation. It will be necessary to make a new application if the change does not meet the specifications of the relevant planning legislation.

 
To be maintained
 
10)   Information Signage

Prior to any works commencing on the site and then to be maintained until completion of the development for all stages , erect an "Information Sign" as outlined below:

a) A brief description of the development proposed;

b) The sign is to list the name, postal and/or email address and a contact telephone number for the following parties (where relevant) that are undertaking work on the site:

Developer;
Project Coordinator;
Architect/Building Designer;
Builder;
Civil Engineer;
Civil Contractor/s; and
Landscape Architect;

c) The lettering on the sign is to be at least 25 millimetres in height, be of regular weight and in sentence case;

d) The sign is to be a minimum size of 1,200 millimetres by 900 millimetres;

e) The maximum area of the sign is to be 2.0m2;

f) The sign must be placed on or within 1.5 metres of the road frontage for the site at the following locations:

  • Bank Street frontage;  and

The site is to be mounted at least 300 millimetres above ground level;

g) The sign is to contain no commercial or corporate advertising other than the name, logo or slogan of the parties outlined in part (b) of this condition;

h) The sign is to be non-illuminated;

i) Both the sign and the supporting structure are to be made of weatherproof material and to be properly maintained at all times; and

j) The sign/s are to be located on the subject property and is to be comply with the General Requirements for Signage contained within the Local Laws Policy "Control of Outdoor Advertising" specifically with regard to Traffic Safety, Clearances and Structural Systems;

 

 
As indicated
 
11)   Community Management Statement

Any Community Management Statement is to contain the following requirements:

 

  • Maintain 187 (including 42 tandem spaces) onsite resident car parking spaces.
  • Maintain 29 on site Visitor car parking spaces. All Visitor car parking spaces are to be clearly labelled as ‘Visitor Parking’, Not to be included in any private lot entitlement and/or designated for the exclusive use of any dwelling unit or commercial tenancy and Remain unimpeded by landscaping, water tanks, storage (temporary or otherwise), gates or any other fitting, fixture or structure between the hours of 7.00am to 10pm for bona fide visitors. Ongoing access is to be provided for bona fide visitors to all visitor parking spaces through the use of managed intercom system at security gates between the hours of 10.00pm to 7.00am.
  • Parking spaces are not to be made available to the general public and there is to be no advertising signage erected on or in the vicinity of the site advertising the availability of car parking to the general public.
  • Maintain a suitable system of lighting, to operate from dusk to dawn, within all areas where the public will be given access including between vehicle entrances to the site and visitors car parking spaces.
  • Maintain all on site landscaping.
  • All privacy screening devices are to remain fitted at all times.
  • The internal footpaths/pedestrian circulation routes, landscaping, driveway, and car/vehicle turning area as shown on the approved plans of layout is to be included in common property and is not to be included in any private lot entitlement and/or designated for the exclusive use of any dwelling unit or tenancy;
  • The roof terrace level (communal use areas) is limited to residential use only and shall not be used between 10pm to 7am;
 
As indicated
 
12)   Roof Decks / Terraces

The roof terrace level (communal use areas) is limited to residential use only and shall not be used between the hours of 10pm to 7am. The roof top communal open space area shall remain open to the sky with no roof above including impervious roofing.

 

Requirements of this condition shall be contained within any Community Management Statement.

 
At all times
 
13)   Overall Height - Survey Certification

The overall height of the proposed building(s) is to be constructed in accordance with the floor and roof levels nominated on the approved drawings.  The building height is not to exceed RL32900m (Excluding lift overrun, plant level and carpark vent). An allowance of an additional 500mm in height above RL32900m for the pool deck only is acceptable.  

 
While site/operational/building work is occurring and then to be maintained
13(a) Submit Certification

Submit certification from a licensed surveyor that the as constructed floor and roof levels are in accordance with this condition.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
14)   Building Management Statement

With any subsequent volumetric subdivision application ensure a Building Management Statement is registered on the title for each proposed lot.  The Building Management Statement is to cover common building management items (e.g. support, shared services/utilities, pedestrian and vehicle access).  The Building Management Statement is to be submitted to and approved by Development Assessment.

Provide an undertaking that the Building Management Statement is to be registered at the same time as, the survey plan is registered.

 
Prior to Council's notation on the plan of subdivision and then to be maintained
 
15)   Visitor Parking

Provide 29 on site visitor car parking spaces within the building as follows

 

  • To be maintained exclusively for the residential use of the development;
  • Be used by bona fide visitors to the premises only;
  • Not to be included in any private lot entitlement and/or designated for the exclusive use of any dwelling unit or commercial tenancy
  • Be clearly labelled as ‘Visitor Parking’; and
  • Remain unimpeded by landscaping, water tanks, storage (temporary or otherwise), gates or any other fitting, fixture or structure between the hours of 7.00am to 10pm for bona fide visitors. Ongoing access is to be provided for bona fide visitors to all visitor parking spaces through the use of managed intercom system at security gates between the hours of 10.00pm to 7.00am.

 

The above requirements are to be included within any Community Management Statement.

 
Prior to the commencement of the use or prior to the endorsement of a Community Management Statement, whichever is sooner
 
16)   Mechanical Ventilation of Car Parking Areas

Vents associated with the mechanical ventilation of car parking areas are not permitted to be located where facing the boundary of any adjoining property. Any exhaust vents associated with the mechanical ventilation of the car parking areas must be located on the Bank Street frontage of the building only or to the roof top.

 
Prior to the commencement of the use and then to be maintained
 
17)   Lighting To Public Areas

Install and maintain a suitable system of lighting, to operate from dusk to dawn, within all areas where the public may gain access.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
Architecture
 
Timing
18)   Submit External Details

Submit for the approval of Development Assessment, further details of the building, facade treatment and external materials, colours and finishes (in particular on the proposed painted pre-cast concrete) generally consistent with the approved drawings.

Timing: Prior to building work above ground level commencing.

 
As indicated
18(a) Implement Approved External Details

Implement the above detailed design treatments.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
19)   Balconies and Terraces to Remain Unenclosed

All balconies and terraces shown on the approved drawings and documents, are to remain unenclosed with no shutters, glazing, louvres or similar permanent fixtures other than those consistent with the relevant Brisbane Planning Scheme Codes/Policies and clearly depicted on the approved drawings.  Any Community Management Statement is to contain a by-law which reflects the requirements of this condition.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
20)   Driveway Material and Finishes

Provide materials and finishes to the driveway and external carparking surfaces that reduce the visual impact of these areas when viewed from the street. In order to achieve this outcome, one or a combination of the following is to be used:

-  Coloured aggregate;
-  Cement pavers; and/or
-  Banding and patterns in the surface design.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
21)   Screen A/C and Other Plant Enclosures

Install and maintain suitable screening to all air conditioning, lift motor rooms, plant and service facilities located at the top of or on the external face of the building. The screening structures must be constructed from materials that are consistent with materials used elsewhere on the facade of the building.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
22)   Solar Screening

Provide solar screening to all western facing windows.  Screening is to include a vertical screening element and be positioned in conjunction with a window hood.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
23)   Screening

Provide screening in accordance with the following:

Where any window of a habitable room is within 5 metres of the property boundaries other than a road frontage, provide:

 

  • high level window (sill height above 1.8m); or
  • vertical window with fixed opaque glazing treatment in any part of the window below 1.8m above floor level; or
  • an alternative form of window screening as agreed to in writing by the Team Manager, Planning Services South, Development Assessment Branch.

Any Community Management Statement is to contain a by-law which reflects the requirements of this condition.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
24)   Light Reflectivity and Solar (Heat) Reflectivity

Submit to Development Assessment documentary evidence that:

- The level of specular light reflectance from the glazing incorporated into the approved development will not exceed twenty (20) per cent; and
-   The level of solar (heat) reflectance from the glazing incorporating into the approved development will not exceed twenty (20) per cent.

Timing: Prior to building work above ground level commencing.

 
As indicated
24(a) Install Glazing

Install and maintain glazing in accordance with the Manufacturer's specification.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
25)   Provide Detailed and Textured Model

Submit to Development Assessment, a detailed and textured digital 3D model in Autodesk compatible format for incorporation into the Brisbane City Council Virtual Brisbane 3D Model. The digital model shall be a high quality 3D Exterior Detailed Model to the extent of the development at a standard which can be publicly viewable and include:

1.  1:1 Unit measurements in millimetres.
2.  Image texture maps, materials and colours included with 3D model.
3.  Survey settings provided to AHD.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
Landscape Architecture and Open Space Planning
 
Timing
26)   Landscape the Site - Self Certification

Landscape the site in accordance with the requirements of this condition.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
26(a) Construct Approved Work

Construct landscaping in accordance with the approved detailed Landscape Plan prepared by CUSP, Dwg No.’s BD 200, BD201, BD301(as amended in red 23-06-2026), BD302, BD303, BD 401, BD402, BD 403, BD601, BD 602 and BD 603, dated 30-06-2015 (received on 02-11-2015).

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first
26(b) Certify Work

On completion of works, submit to Development Assessment certification from:

-  A registered Landscape Architect or Landscape Designer that the detailed Landscape Plan complies with the City Plan (Form CC10616 Landscape Design Certificate); and
-  A registered Landscape Architect and registered Landscape Contractor that the completed landscape work complies with the detailed Landscape Plan, (Form CC10613 Landscape Works Certificate).

Note: A copy of the as- constructed detailed Landscape Plan must accompany the completed Compliance Certificates.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
26(c) Maintain Landscape Work

Maintain the landscape generally in accordance with the detailed plans.

 
To be maintained
 
27)   Retain and Protect Existing Street Trees(s)

Identify, retain and protect the existing street trees unless otherwise determined in writing by Asset Services.

Note: Street trees are protected under the Natural Assets Local Law. Street trees must not be removed or pruned without prior approval from Asset Services.

 
While site/operational/building work is occurring
27(a) Implement Protection Measures

Install tree protection measures in accordance with Australian Standard AS4970 (Retention of Trees on Development Site).

There must be no excavation, filling or storage of materials or plant within the drip line of the tree.

Note: If fencing is proposed to protect street trees, a permit to temporarily occupy the footway will be required from Compliance and Regulatory Services.

 
While site/operational/building work is occurring
27(b) Maintain Protection Measures

Maintain protection measures while development is occurring and remove protection measures prior to commencement of the use.

 
While site/operational/building work is occurring
 
28)   Pedestrian Lighting

Submit a Pedestrian Lighting Design in accordance with the requirements of this condition.

 
Prior to site/operational/building work commencing
28(a) Obtain An Electrical Connection

Obtain an electrical connection from Energex prior to installing the lighting.

Timing:  Prior to building work above ground level commencing

 
As indicated
28(b) Submit a Pedestrian Lighting Design

Submit a Pedestrian Lighting Design (including Details) for the full street frontage of the development for approval by the City Lighting, Asset Services.  The lighting is to be in accordance with AS/NZS 1158.3.1, 1999 Pedestrian Area (Subcategory P3) lighting and the relevant Brisbane Planning Scheme codes/policies.

Timing: Prior to building work above ground level commencing

 
As indicated
28(c) Install the Lighting

Install the lighting in accordance with the approved Pedestrian Lighting Design and the approved Landscape Works in Streetscape Plan.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)

 
As indicated
28(d) Provide Certification of Connection and Operation

Provide to City Lighting, Asset Services certification from a licensed electrical contractor that the electrical connection has been installed in accordance with the approved Pedestrian Lighting Design and that the lighting is fully operational. In addition, the certification is to specify that the electrical installation has been tested to ensure it is electrically safe and is in accordance with the requirements of Australian / New Zealand Standard 3000 Electrical Installations (known as the "Wiring Rules") and any other standard applying to the electrical installation under the Electrical Safety Regulation 2002.

Note: A copy of the as-constructed detailed Landscape Plan must accompany the completed Compliance Certificates.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)

 
As indicated
28(e) On Maintenance Inspection

Contact City Lighting, Asset Services to arrange an On Maintenance inspection.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)

 
As indicated
28(f) Maintenance Period

Provide 12 months' maintenance to the works from the time the works are accepted On-Maintenance by Council.  Maintain the lighting and rectify all defects identified at the On-Maintenance inspection and those arising during the maintenance period.

Timing:  From acceptance of On Maintenance period.

 
As indicated
28(g) Off-Maintenance Inspection

On completion of the maintenance period contact Development Assessment, to arrange an Off- Maintenance inspection and release of the Bond.  Ensure all defects are rectified prior to making an appointment for Off-Maintenance Inspection.

Timing: On completion of the maintenance period

 
As indicated
 
29)   Streetscape Works

Provide improvement works to the road reserve pavement in accordance with the requirements of this condition.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
29(a) Submit Level Details (MCU)

For a material change of use, submit to Development Assessment and receive approval for details on the finished levels of the sire and building entries (both pedestrian and vehicular) to demonstrate compatibility with acceptable footpath/footway grades. The details must be provided by a suitably qualified and experienced Landscape Architect or other relevant professional and include at least the following information:

-  Finished surface levels at the site/lot boundary;
-  Finished ground floor levels;
-  Crossfall and longitudinal grades including sections demonstrating compliance with Australian Standards for Access and Mobility (maximum crossfall of 1:50); and
-  Existing kerb heights.

Timing: Prior to building works commencing

 
As indicated
29(b) Submit Plan for Works in the Road Reserve

Submit to Development Assessment and receive approval for a detailed Landscape Works in Streetscape Plan for required works to be undertaken within the road reserve fronting the development site. The plan is to be prepared at a scale of 1:100 by a suitably qualified and experienced Landscape Architect and the works are to be constructed to a standard and of materials consistent with the requirements of relevant Brisbane Planning Scheme Codes/Policies.  The plans are to include the following:

-   all works in the verge to be in accordance with the guidelines for a Neighbourhood St Major (NS1) as outlined in the Centres Detail Design Manual;

-  Pavement treatment in the required materials and pattern
-  Street trees integrated into the proposed pavement pattern
-  Conceptual location of pedestrian lighting where under awning lighting is not provided
-  Location of underground and above-ground services
-  Location of service pits (replaced with Cast Iron Lids or as approved by Development Assessment)
-  Location and description of street furniture
-  Finished surface levels at lot boundary and kerb
-  Cross-fall and longitudinal grades including sections demonstrating compliance with Australian Standards for Access and Mobility (maximum crossfall of 1:50)
-  Existing kerb materials and heights
-  Tactile pavers as required in accordance with AS1428.4 and located in accordance with Council’s Standard Drawings, particularly UMS 213 (kerb ramps) and 221 (crossovers)
-   Proposed road use adjacent to the kerb (e.g. bus stops, parking bays)
-  Details of awnings including location, height, materials. Ensure a clearance of 1.5m is provided between tree trunk and the awning
-  Balustrades or any other structures
-  Location and details of any artwork.

Timing: Prior to building work above ground level commencing (MCU) or prior to operational work commencing (ROL) to comply with this condition

 
As indicated
29(c) Construct Approved Works

Carry out the works documented in the approved Landscape Works in Streetscape Plan.

Note: Lodge and receive approval for an ‘Application for Permits Relating to Roads and Footway’ prior to carrying out the approved works.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to the commencement of use, whichever comes first (MCU or BW), or prior to Council’s notation of the plan of subdivision (ROL)

 
As indicated
29(d) Remove Existing Footway

Remove the existing footway including affected street signage for the full length of the frontages to Bank Street in accordance with Council standards and complying with the terms and conditions of the footway permit.

Note: All existing artworks and regulatory signage is to be secured and repositioned to Councils satisfaction.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council’s notation of the plan of subdivision (ROL)

 
As indicated
29(e) Certify the Footway Works

Provide to Development Assessment certification from a Registered Professional Engineer of Queensland that footway works have been carried out as documented on the approved Streetscape Works Plan, including the following:

-  Construction of footway and associated works including all sub-surface works, kerb and channel, footings for pedestrian and road lights, installation of furniture and any other construction associated with the footway works
-  Shade structures associated with the footway works
-  All electrical works located and constructed in accordance with the approved Pedestrian Lighting Design.

Timing: At the On Maintenance Inspection

 
As indicated
29(f) On-Maintenance Inspection

Contact Development Assessment to arrange an On-Maintenance inspection.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council’s notation of the plan of subdivision (ROL)

 
As indicated
29(g) Maintenance Period

Provide 12 months maintenance to the streetscape works and rectify any defects identified at the On-Maintenance inspection.

Lodge a bond for the maintenance period of the works. The bond is to be calculated in accordance with the relevant Brisbane Planning Scheme Codes/Policies (5% of total value of the landscape works or minimum of $5,000.00 whichever is greater). A maintenance bond can consist of either a bank guarantee or monetary payment lodged with Council.

Timing: From acceptance of On-Maintenance period

 
As indicated
29(h) Off-Maintenance Inspection

On completion of the maintenance period, contact Development Assessment to arrange an Off-Maintenance inspection and release of the bond. Ensure all defects are rectified prior to making an appointment for Off-Maintenance inspection.

Timing: On completion of the maintenance period

 
As indicated
 
Pollution
 
Timing
30)   Noise Attenuation - Adjacent Uses

Design and construct the proposed development in accordance with the following method as per the information provided by ASK Consulting Engineers P/L dated 19 August 2014.

 

  • Glazing, south western façade, Rw 36
  • Remaining glazing, Rw 28
  • Roof, Rw 43
  • Walls, Rw 40

GUIDELINE
This condition is set to reduce noise emissions from nearby and surrounding uses.

 
To be maintained
30(a) Certification

Submit certification to the Assessment Manager (from a qualified acoustic consultant) that the above design and construction methods have been incorporated into the development.

 
To be maintained
 
31)   Hours of Operation - Vehicle movements

Operation of trucks, commercial vehicles and/or waste collection vehicles during the operational phase of the development must only occur between 7am - 7pm Monday to Saturday.

 
To be maintained
 
32)   Air Conditioning to Noise Affected Rooms

Air-conditioning must be provided to all living and sleeping areas, as windows and doors are required to remain closed to maintain acceptable indoor noise levels.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
33)   Plant and Equipment Certification

Following the installation of all mechanical plant and equipment (e.g. air conditioning, mechanical ventilation and refrigeration equipment and heat pump hot water systems), submit to Development Assessment certification that the plant and equipment is adequately noise- attenuated and is in accordance with the criteria of the relevant Brisbane Planning Scheme Codes/Policies.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
34)   Stormwater Quality (High Risk)

Implement and maintain the recommendations of Section 4.1 and drawing within Appendix B of the Site Based Stormwater Quality Management Plan prepared by Westera Partners P/L, Received 14 July 2014 to achieve the requirements of the State Planning Policy 2013 (Qld) Water Quality.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
34(a) Certification

Submit to Development Assessment certification from a Registered Professional Engineer Queensland, that all the treatments and measures recommended in the approved Site Based Stormwater Quality Management Plan have been implemented and constructed into the development.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
Engineering
 
Timing
35)   Filling and Excavation

All proposed earthworks are to be carried out in accordance with the relevant Brisbane Planning Scheme Codes/Policies and the following requirements:

 
As indicated
35(a) Submit Earthworks Plan

Submit and obtain endorsement from Development Assessment an earthworks plan prepared in accordance with the relevant Brisbane Planning Scheme Codes/Policies and Reference Specifications, checked and certified by a Registered Professional Engineer of Queensland- Civil (RPEQ- Civil).

The Earthworks Plan should include the following:

-   The location of any cut and/or fill;
-  The quantity of fill to be deposited and finished fill levels;
-  Maintenance of access roads to and from the site such that they remain free of all fill material and are cleaned as necessary;
-  The existing and proposed finished levels in reference to the Australian Height Datum (extending into the adjacent properties);
-  Preservation of all drainage structures from the effects of structural loading generated by the earthworks;
-  Protection of adjoining properties and roads from ponding or nuisance from stormwater;
-  That all vehicles exiting from the site will be cleaned and treated so as to prevent material being tracked or deposited on public roads.
-  Suitable fill material is that deemed to comply with the requirements of AS 3798, Guidelines on Earthworks for Commercial and Residential Developments.

Note.  If the earthworks impact on the road reserve, the Developer must obtain applicable footpath and road permits prior to commencing any works.  Such impacts may include footpath occupation, road closures, reprofiling, ground anchors and/or relocation of services.  If the excavation has to be stabilised using ground anchors or similar then the submitted plans are to show the location of these in relation to all services. The cost of moving services, utilities and assets is the responsibility of the Developer. The permission of the service/utility/asset owner will be required.

 
Prior to site/operational/building work commencing
35(b) Suitable Fill Material

All fill material placed on the site is to comprise only natural earth and rock and is to be free of contaminants (as defined by Section 11 of the Environmental Protection Act 1994) and noxious, hazardous, deleterious and organic materials.

 
While site/operational/building work is occurring
35(c) Implement Endorsed Plan

Construct and maintain the earthworks works in accordance with the endorsed engineering plans and with the relevant Brisbane Planning Scheme Codes/Policies.

 
While site/operational/building work is occurring and then to be maintained
 
36)   Construction Management Plan

Prepare a Construction Management Plan for the subject site in accordance with the following requirements.

Note.  This condition is imposed when construction activities need to be limited to manage the impact on the surrounding area. This condition is intended to apply throughout the period of site preparation to the completion of the development.

 
As indicated
36(a) Construction Management Plan - For Endorsement

Submit to Development Assessment for endorsement, a Construction Management Plan for the demolition, excavation and construction phases of the approved development.  Separate Construction Management Plans may be appropriate for the individual components.  The Construction Management Plan is to be in accordance with the relevant Brisbane Planning Scheme Codes/Policies, Workplace Health and Safety Legislation requirements, Environmental Protection Act, the requirements of any Concurrence Agency and any other relevant legislative requirements.  The Construction Management Plan is to provide the following details and address impacts, where applicable:

-  Provision for pedestrian management including alternative pedestrian routes, past or around the site;
-  Location of and impacts on any Council or other authority's assets on and external to the site.  Council assets include water, sewer, stormwater, street trees and kerb side allocation signs and line marking such as bus stops, loading zones and parking meters and/or ticket dispensers. Details of street trees are to include location, species, trunk and canopy size;
-  Temporary vehicular access points and frequency of use;
-  Existing and proposed kerb-side allocation signs and line marking (such as bus stops, loading zones and parking meters and or ticket dispensers);
-  Provision for loading and unloading materials including the location of any remote loading sites;
-  Location of materials, structures, plant and equipment to be stored or placed on the construction site;
-  How materials are to be loaded/unloaded and potential impacts on existing street trees;
-  Location of materials, structures, plant and equipment to be stored or placed on the construction site;
-  Location of proposed external hoardings and gantries;
-  Employee and visitor parking areas;
-  Anticipated staging, programming;
-  Provision for fire exit routes for other uses on the subject or adjoining sites;
-  Details that identify and define phases of construction considered necessary to be conducted out of normal business hours (where normal hours are defined as Monday to Saturday between 6:30am and 6:30pm excluding public holidays).


Notes.
-  Approval for footpath closures and/or temporary vehicle access will only be considered where it can be demonstrated that no reasonable alternative can be provided due to site constraints and that safety, capacity and/or operation of public transport, vehicle and pedestrian traffic are not compromised.
-   Proposed arrangements utilising any part of the road reserve for construction related activities, for example, on street work zones, overhead gantries, hoardings or pedestrian diversions, are subject to separate application fees and rental fees.
-  The Construction Management Plan may require modification, at Council's discretion, to reflect changes in relevant legislation and industry best practice prevailing at the time of the permit application and throughout the construction program.
-  Endorsement of the Construction Management Plan does not allow the carrying out of specific work activities for any phase of construction outside of normal hours.

 
Prior to site/operational/building work commencing
36(b) Construction Management Plan - Pre- start Meeting

Arrange a pre- start meeting with the Development Assessment.

 
Prior to site/operational/building work commencing
36(c) Construction Management Plan - Works in Road

Obtain relevant approvals to carry out any works within the road reserve required by the approved Construction Management Plan:

- Temporary lane closures;
- Restricted work zones (subject to relaxation of clearway hours and resolution of alternate kerb side allocation including bus zones);
- Overcoming clearway restrictions;
- Gantry erection.

Notes.
- Applications will be assessed on the basis of road and footpath network operating conditions prevailing at the time. Council will consider impacts of other construction works or events that occur during the life of the permit.
- All fees are to be paid in full prior to any permit being granted by Council.  Council may revoke any permits at any time for non-compliance with requirements or if it considers that safety, capacity and /or operation of public transport, vehicle and pedestrian traffic are likely to be compromised during the construction project.

 
Prior to site/operational/building work commencing
36(d) Construction Management Plan - Plans on Site

Legible copies of the Construction Management Plan and current permits are to be kept on site and be made available on request at all times during construction.

 
While site/operational/building work is occurring
36(e) Construction Management Plan - Out of Hours Works to be Performed

Notify Development Assessment for any work activity identified broadly in the endorsed Construction Management Plan to be conducted out of normal business hours 6:30am and 6:30pm Monday to Saturday.

 
While site/operational/building work is occurring
36(f) Construction Management Plan - Implement the Plan

Subject to the provisions of this condition, implement and maintain the approved Construction Management Plan.

 
While site/operational/building work is occurring
 
37)   Protect Existing Infrastructure

Where there is existing infrastructure in the vicinity of the proposed work, then the new work must not damage or compromise the working ability of the existing infrastructure. Should it be required to provide alterations to public utility mains, existing mains, services or installations, then the developer is required to meet the costs of the alteration/s, which is to be carried out in accordance with the relevant Brisbane Planning Scheme Codes/Policies.

 
While site works are occurring and then to be maintained
37(a) As Constructed Drawings

Submit to Development Assessment "As Constructed" drawings including an asset register, showing all new and/or rectification works required by this condition.  These works must be certified by a Registered Professional Engineer of Queensland-Civil that they are in accordance with the relevant Brisbane Planning Scheme Codes/Policies and any other relevant infrastructure requirements.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
38)   On-site Erosion (Low Risk)

Minimise on-site erosion and the release of sediment or sediment-laden stormwater from the site at all times.

 
While site/operational/building work is occurring
38(a) Prepare an Erosion and Sediment Control (ESC) Management Plan - On-site Erosion (Low Risk)

Prepare an Erosion and Sediment Control (ESC) Management Plan for the site in accordance with the Healthy Waterways document Controlling Stormwater Pollution on Your Building Site 2006 (or later version) and in accordance with the relevant Brisbane Planning Scheme Codes/Policies.

Note. An Erosion and Sediment Control Management plan is not required to be submitted for Council endorsement.

 
Prior to site/operational/building work commencing
38(b) Implement and Maintain the ESC Management Plan - On-site Erosion (low Risk)

Implement and maintain the ESC Management Plan on-site for the duration of the operational or building works, and until all exposed soil areas are permanently stabilised (e.g. turfed, hydro-mulched, concreted, landscaped).  The prepared ESC Management Plan must be available on-site for inspection by Council Officers during these works.

 
While site/operational/building work is occurring
 
39)   Retaining Walls

Design and construct all retaining walls and associated fences, in accordance with the relevant Brisbane Planning Scheme Codes/Policies and to ensure the following:

-  All retaining walls including the footing structure, must be located wholly within the property boundary of the site where works are occurring.
-  Retaining walls to stabilise excavation are to be set back off property boundaries to accommodate subsoil drainage without encroachment into the neighbouring property.  This set back may vary depending on the height, structure and design of the retaining wall, including loadings from neighbouring properties, and to provide a surface drain along the top of the retaining wall.
-  Retaining walls that retain fill and are greater than 1.5m in height are to be vertically and horizontally tiered by a dimension of half of the height of the retaining wall unless an alternative has been approved by Council.
-  Runoff from surface drains and subsoil drainage associated with the retaining wall is to be collected and conveyed to a lawful point of discharge and must not cause any ponding, nuisance or disturbance to adjacent property owners.
-  Retaining walls in excess of 1.0m in height are to be designed and certified by a Registered Professional Engineer of Queensland
-  Retaining walls facing onto Council property (including the road reserve and parkland) must not be constructed from timber.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
39(a) Certification of Retaining Walls

For retaining walls over 1.0 metre in height, provide certification from a Registered Professional Engineer Queensland that the design and construction of the retaining wall and ancillary drainage comply with this condition.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
40)   Granting Easements

Grant easements for underground drainage, overland flow and access purposes as may be required, in favour of Brisbane City Council.

Note:-This condition is imposed to provide access, maintenance of services and to protect drainage paths if required. Easements in favour of the Brisbane City Council are required to have the necessary easement documentation prepared (free of costs and compensation to Council) by the Brisbane City Council. Easements not in favour of the Brisbane City Council are required to have the necessary documentation prepared by the applicant's private solicitors. Easements are to be shown on a Survey Plan and lodged with the Plan Sealing Unit. Enquiries regarding any legal documentation can be directed to the Plan Sealing Unit, Development Assessment (ph: 3403 8888).

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
41)   Rock and Ground Anchors

Where Rock and Ground anchors are required they must be designed, constructed and certified by an Registered Professional Engineer Queensland (RPEQ) in accordance with the requirements of the relevant Brisbane Planning Scheme Codes/Policies, and the notes of this condition.

Notes. The rock anchor plan and submission is to include the following as a stand alone document as part of a Fill and Excavation Operational Work or Compliance Assessment application.

1. The ground anchoring system is to be designed and certified by a RPEQ. Ground anchors should not be located closer than 1.2m vertically or 1.0m below or 1.0m horizontally from existing Council Infrastructure.

2. Provide both pre and post construction CCTV survey of pipe lines adjacent to the site. Provide Pre Construction CCTV inspection of all pipes in the vicinity of anchors, to be carried out prior to commencement of site works. Provide Post Construction CCTV inspection of all pipes in the vicinity of the anchors, one month after de-stressing of anchors. CCTV surveys should be carried out using a camera with the capacity to pan and tilt. The applicant is to submit a digital report and video of the inspection.

3. Provide geotechnical certification that the construction phase building loads and the final building loads will not impact or endanger Council’s infrastructure.  This will involve demonstrating the effect of the load imposed pressure bulb, both prior to the de-stressing of the temporary ground anchors and upon final completion of the building.

4. Provide a geo-technical report which relates to the position of rock anchors, to be submitted with the design plans.  Geological formation and borehole data should be included as part of this report.

5. Submit documentation of the approval of any adjacent property owners where the anchoring system is proposed to encroach into neighbouring properties.

6. Obtain the approval from the providers of affected services and plot the level and line of these services on the sections and plans.

7. Provide an emergency management plan that includes procedures to reinstate any services which may be damaged as a result of works on the site.

8. Piers and drainage system shall be located wholly within the property.

9. Structural certification is required for retaining walls greater than 1.0m in height.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
41(a) Submit Drawings for approval

Submit to Development Assessment for endorsement as part of an earthworks plan a Ground or Rock anchor system designed, checked and certified by a Registered Professional Engineer Queensland and in accordance with this condition and the relevant Brisbane Planning Scheme Codes/Policies. The following drawings and details are required:

-  Locality plan, Site plan, layout, elevation, levels of contours and sections, depicting details of the anchoring system (position, length, inclination angle, lock-off load and typical anchor block).  All bored piers are to be shown on the Plan view as well as on the Elevations. Construction procedures are also to be indicated. Shoring and Bored Piling details are to be provided.  Only bored piles will be approved. Permanent ground anchors will not be approved.
-  Provide a survey plan of existing BCC infrastructure (water, stormwater, sewer, street trees, signs and markings etc.) and utility services (telecommunications, electricity, and gas) and adjacent foundation details.  Ensure that all of the Brisbane City Council pipe lines and Maintenance Holes (including depths of Maintenance Holes and clearances to anchors) in public and in private properties are surveyed and plotted on the Shoring Plan and the Shoring Wall Sections.

 
Prior to site/operational/building work commencing
41(b) Implement approved drawings

Construct and maintain the earthworks works in accordance with the endorsed engineering plans and with the relevant Brisbane Planning Scheme Codes/Policies.

 
While site/operational/building work is occurring
41(c) Post Construction Certification

Provide Certification by a Registered Professional Engineer Queensland that the rock anchors have been installed in compliance with the endorsed plans, the relevant Brisbane Planning Scheme Codes/Policies, and the requirements of this condition. Provide geotechnical certification that the construction phase building loads and the final building loads will not impact or endanger Council infrastructure.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
 
42)   Access, Grades, Manoeuvring, Carparks, Signs, and Lines

Provide access, parking and manoeuvring for vehicles on-site in accordance with the relevant Brisbane Planning Scheme Codes/Policies, as indicated on the approved drawing(s), and including to the following:

i. A pavement of minimum Type A standard or equivalent surface material (including associated drainage) to the area on which motor vehicles will be driven and/or parked.

ii. Manoeuvring on site for a RCV and for the loading and unloading of the vehicles.

iii. Parking on the site for 216 cars and for the loading and unloading of vehicles within the site.  29 of these parking spaces are to be provided for visitor parking and 1 of the parking spaces is to be provided for people with disabilities.

iv. Provide 207 number of secure bicycle parking spaces.


v. A minimum of 2.3 metres height clearance to all undercover parking areas and a minimum of 2.5 metres above parking spaces for people with disabilities.  The minimum clear height must be measured to the lowest protrusion from the ceiling (e.g. fire sprinklers, services, lighting fixtures, signs, etc).

vi. A height clearance sign located at the entrance(s) to undercover car parking areas and a directional visitor parking sign clearly visible from the vehicle entrance to the site.

vii. An appropriate area for the storage and collection of refuse, including recyclables, in a position which is accessible to service vehicles on the site.

viii. The internal paved areas must be signed and delineated in accordance with the approved drawings and Qld Manual of Uniform Traffic Control Devices.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
42(a) Provide certification

Submit to Development Assessment, certification from a relevant discipline Registered Professional Engineer Queensland, that the above works have been constructed in accordance with this condition.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
43)   Flood Risk Management Plan

Prepare, implement and maintain a Flood Risk Management Plan in accordance with the requirements of this condition.

 
As indicated
43(a) Prepare and Certify a Flood Risk Management Plan

Submit to Development Assessment, a Flood Risk Management Plan (FRMP) prepared and certified by a qualified and experienced practitioner in flood risk management for the approved development.  The FRMP must address the risk of impacts from flood inundation and adopt measures to mitigate potential adverse impacts including:

1.       Procedures for flood monitoring and identification of warning times based on flooding type and catchments characteristics;

2.       Procedures on notification and identification of responsibilities; and

3.       Emergency excavation procedures.

 

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
43(b) Implement and Maintain the Certified Flood Risk Management Plan

Implement and maintain the development in accordance with the certified Flood Risk Management Plan.

Update the FERP as required reflecting current standards, best practices, or any future approved modifications to this development. The Manager, Development Assessment is to be notified by email to edasouth@brisbane.qld.gov.au

 within 14 business days of any alterations to the FERP for the site.
 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
44)   Minimum Floor or Pad Levels

Design and construct all proposed pad levels, building levels, floor levels and ancillary structures to have the appropriate freeboard in accordance with Brisbane Planning Scheme Codes/Policies to ensure they will not be flooded during a 50 year ARI local flood event or a 100 year ARI Creek, River or Storm Tide flood event, whichever is the higher flood level. 

The minimum building/habitable floor level is to be 6.8 metres AHD.
The minimum non habitable floor level is to be 6.6 metres AHD.

Basement entry 6.5m AHD

Essential services – 6.7m AHD

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
44(a) Certification

Provide certification and/or As-Constructed plans from a Registered Surveyor that confirm the development complies with the requirements of this condition.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
45)   Basements in flood affected areas

All new construction and substantial improvements of basements below the 100 year ARI flood or storm tide level (and/or Brisbane River Defined Flood level) together with stormwater, electrical and sanitary facilities are and designed in accordance with the following:

(i)   Ensure the structure is suitably flood proof to minimise and/or manage ingress of floodwater to prevent significant flooding of basements during floods.

(ii)   All ventilation openings, driveway entry/exit ramps and pedestrian entrances into the basement are constructed in accordance with the minimum levels as stated in the relevant Brisbane Planning Scheme Codes/Policies.

(iii)   All essential electrical services (refer to the relevant Brisbane Planning Scheme Codes/Policies) are to be located 500mm above the higher of the January 2011 flood level (IRFL) or 100 year ARI waterway level.  Where such services have been approved in a basement through a risk management approach to flooding, a completely watertight tanked basement is required with floors and walls designed and certified by a Registered Professional Engineer Queensland (RPEQ) to resist hydrostatic pressures expected during floods.

(iv)   Where any part of a basement is below 2.0m AHD or determined to be subject to saline groundwater conditions, an RPEQ is to certify that the design of concrete structures and construction techniques are suitable to withstand corrosive effects of salt water in accordance with relevant Australian Standards.

(v)   Where a sump/pump basement drainage system is used to manage stormwater & flooding for the basement (note: NOT APPLICABLE where any essential electrical services or rooms for such services are proposed in a basement) the following are required:
   (a)   A dual pump system that is connected to a backup power supply located above the 2011 Brisbane River flood level (IRFL).
   (b)   Backup power supply and fuel capacity must be sufficient to run both pumps for a period of no less than 48 hours.
   (c)   The basement subsoil and stormwater drainage/flow management must be designed and certified by a RPEQ to manage sub-surface water flows associated with peak flood levels, ground water inflows and tides where applicable to ensure the basement is suitably flood proof.
   Note: basement drainage designs must design for peak flow rates in soils, backfill and subsoil drainage expected during flood events and also account for drowned pump discharge points that may reduce its ability to dewater the sump.  Such conditions may result in very high subsoil flow rates and possibly require the use of a tanked and watertight basement design.  RPEQ with structural, geotechnical and stormwater experience will need to determine the suitability of any basement flood proofing design.

(vi)   All stormwater pump systems are to utilise backflow prevention devices to ensure no flooding of the basement, and designed to gravity drain into a Council stormwater system.

(vii)   All sewer connections are to include backflow prevention devices.

(viii)   The driveway aisle into a basement is to be designed and constructed to minimise local driveway stormwater runoff entering the basement.  The drainage is to accommodate 10 year ARI rainfall events and gravity feed to a lawful point of discharge.

(ix)   Vehicle access into any basement from a Council road will require the basement driveway to ramp up a minimum of 200mm above the adjacent road channel invert to maintain road major flow capacity.

 

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
45(a) Registered Professional Engineer Queensland certification of basement in flood affected areas

Where a basement is required to be made suitably flood proof below the 100 year ARI flood level or River Defined Flood Event, a Registered Professional Engineer of Queensland (RPEQ) shall; 

a)             ;      Submit certification to the Private Building Certifier of the stormwater and sewer hydraulic design, specifications, and plans for the construction.  Certification must verify that the basement design and methods of construction are in accordance with accepted standards of practice for meeting the applicable provisions of the relevant standards and this condition, ensuring the basement structural design or subsoil drainage system (including flow rate assumptions) will ensure it is suitably flood proof.

b)             ;      Submit certification to the Private Building Certifier to ensure structural integrity of the building from hydrostatic pressures resulting from floodwaters and groundwater.  Certification must verify that the structural design of the basement and methods of construction are in accordance with accepted standards of practice for meeting the applicable provisions of the relevant standards and this condition.

c)             ;      Submit As Constructed Plans and provide certification (RPEQ) to Councils Engineering Delegate that the works have been completed in accordance with the approved design, conditions and any approved modifications.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
46)   Refuse Collection - On Site

Arrange for the installation of waste/recycling bins by Brisbane City Council's Waste Services and for the subsequent collection of waste including recycling from the site.

The applicant/owner including any subsequent owners are to indemnify Council and its agents in respect of any damage to the pavement and other driving surfaces. The applicant is to notify future owners/body corporate that the development has been approved on the basis that an indemnity is provided for refuse collection vehicles to enter the property.

Timing:
A minimum of four weeks prior to the commencement of use and to be maintained

 
As indicated
 
47)   Repair Damage To Kerb, Footpath Or Road

Repair any damage to existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel and stormwater gullies and drainlines) and re-instatement existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
48)   On Site Drainage - Major

Stormwater run-off from all proposed lots, roof and developed surface areas and any run-off onto the site from adjacent areas, must be collected internally and conveyed to a lawful point of discharge in accordance with the relevant Brisbane Planning Scheme Codes/Policies and Standard Drawings.

Note.  The stormwater design must ensure the stormwater runoff from the site does not adversely impact on flooding or drainage (peak discharge and duration for all events up to the 100 year Average Recurrence Interval (ARI)) of properties that are upstream, downstream or adjacent to the site.  Some developments may require implementation of one or more mitigation measures to offset adverse impacts. For example, detention storage, rainwater tanks, and pipe upgrades.

Timing: Prior to Council's endorsement of a Community Management Statement or prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
As indicated
48(a) Submit drawings for Endorsement

Submit and obtain endorsement from Development Assessment, drainage plans and engineering calculations, prepared by a Registered Professional Engineer of Queensland- Civil, in accordance with the relevant Brisbane Planning Scheme Codes/Policies showing the design of the stormwater infrastructure.

Timing: Prior to site/operational/building work commencing

Notes.
-  QBSA licensed Hydraulic Consultants may design the stormwater system for sites less than 2000m2 with an upstream catchment servicing no more than 4 residential lots.  This excludes Stormwater drainage design (including subsoil drainage) of basements in floodplains and the design of any onsite detention system.
-  The plans must show adequate survey information on areas adjoining the site with particular attention to any nuisance or annoyance to adjoining property owners.
-  All constructed stormwater outlets that are proposed to discharge directly to a waterway must ensure an appropriate waterway setback, reduction in flow outlet velocity and concentration and include any supplementary planting works that may be required as detailed the relevant Brisbane Planning Scheme Codes/Policies.

 
As indicated
48(b) Implement Endorsed Drawings

Construct and maintain the works in accordance with the endorsed engineering drawings.

Timing: Prior to Council's endorsement of a Community Management Statement or prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
As indicated
48(c) Submit As Constructed Plans

Submit "As Constructed" plans prepared by a Registered Professional Engineer Queensland or Registered Surveyor.

Timing: Prior to Council's endorsement of a Community Management Statement or prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL).

 
As indicated
 
49)   Remove Redundant Drainage Outlets

Remove any redundant drainage outlets from the kerb and channel including any associated pipe work across the footway and reinstate the kerb and channel and the footway area in accordance with the relevant Brisbane Planning Scheme Codes/Policies.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
50)   Ponding of stormwater

Adjoining properties and roads are to be protected from ponding or nuisance from stormwater as a result of the works.  Ensure the stormwater runoff from the site does not adversely impact on flooding or drainage (peak discharge and duration for all events up to the 100 year Average Recurrence Interval (ARI)) of properties that are upstream, downstream or adjacent to the site.

Notes.
-  If remedial works are required that involve drainage, drawings are to be submitted and approval obtained from Development Assessment, to provide a means to rectify the site drainage.

-  This condition is imposed to ensure that the developer is aware that they are responsible for all remedial works required as a result of any site works and, that they must protect neighbouring properties and roads from ponding and nuisance water from the proposed development.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
 
51)   Service Conduits and Mains

Supply and install all service conduits and meet the cost of any alterations to public utility mains, existing mains, services or installations required in connection with the approved development in accordance with the relevant Brisbane Planning Scheme Codes/Policies.  This includes:

- the provision of all services and/or conduits along the full length of any rear allotment access or access easement.
- the relocation of any fire hydrant and/or valves from the development's vehicular footway crossings if applicable.
- the retention and/or relocation of any existing foul water lines that currently exist within the site.

Note.  Applicants should liaise with the appropriate service authorities. Typical underground services and/or conduits to be constructed include power, phone, telecommunications, sewer, stormwater and gas if applicable.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
51(a) As Constructed Drawings

Submit to Development Assessment "As Constructed" drawings including an asset register, approved by a Registered Professional Engineer Queensland that are in accordance with the relevant Brisbane Planning Scheme Codes/Policies, and any other relevant infrastructure requirements, showing the works required by this condition.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
52)   Telecommunications

Enter into an agreement with a telecommunication carrier to provide underground telecommunication services within and adjacent to the proposed development in accordance with the relevant Brisbane Planning Scheme Codes/Policies.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
53)   Agreement with Electricity Supplier

Enter into an agreement with an electricity supplier to provide necessary services to the development in accordance with the relevant Brisbane Planning Scheme Codes/Policies.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
54)   Construct Permanent Vehicle Crossover

Provide a 10.6 metre wide Type B1 permanent vehicular crossover to the Bank St frontage of the site in accordance with the relevant Brisbane Planning Scheme Codes/Policies and Standard Drawings and located as shown on the approved drawings.

Note: No further permits are required to carry out the crossover works. Street trees must not be removed or pruned without prior approval from Council’s Asset Services Branch.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
55)   Remove Redundant Crossover

Remove the existing vehicular crossing(s) on the frontage(s) of the site and reinstate the kerb and channel, road pavement, footways and footpaths in accordance with the relevant Brisbane Planning Scheme Codes/Policies.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
Standard Advice
 
Timing
56)   Natural Light and Ventilation

The assessment of the development application has not considered whether the provision of natural light and ventilation to habitable rooms in the building, satisfies the requirements of the Building Code of Australia.

 
As indicated
 
57)   Cultural Heritage

Aboriginal cultural heritage is protected under the Aboriginal Cultural Heritage Act 2003. It is an offence for a person or corporation to damage or destroy cultural heritage. The duty of care provisions are outlined in Section 28 - Duty of Care Guidelines of the Aboriginal Cultural Heritage Act 2003. It is the responsibility of the person/corporation carrying out the development approval to follow these duty of care provisions in relation to protection of Aboriginal cultural heritage.

 
As indicated
 
58)   Contaminated Land

Pursuant to the Environmental Protection Act 1994 in relation to Contaminated Land, if the owner or occupier of land becomes aware a notifiable activity is being carried out on the land, the owner or occupier must, within 22 business days after becoming aware the activity is being carried out, give notice to the relevant State administering authority in the approved form.

 
As indicated
 
59)   Construction Noise and Dust Emissions

Pursuant to the Environmental Protection Act 1994, all development involving the emission of noise and dust from building and/or construction activities, must ensure that the emission are accordance with the requirements of the Act.

The Environmental Protection Act 1994 prescribes that:

(1) A person must not carry out building work in a way that makes an audible noise—
(a) on a business day or Saturday, before 6.30a.m. or after 6.30p.m; or
(b) on any other day, at any time.

(2) The reference in subsection (1) to a person carrying out building work—
(a) includes a person carrying out building work under an owner-builder permit; and
(b) otherwise does not include a person carrying out building work at premises used by the person only for residential purposes.

 
As indicated
 
60)   Equitable Access

Provision must be made for equitable access for persons with disabilities to and within the site in accordance with the Queensland Anti- Discrimination Act 1991, the Federal Disability Discrimination Act 1992 and Australian Standard AS1428 Parts 1-4, Australian Standard for Access and Mobility and the Building Code of Australia Access Code.

 
As indicated
 
Water and Wastewater Services - Concurrence Agency Requirements
 
Timing
61)   Construct Sewer

Construct Trunk Sewer Infrastructure

Construct either Option 1 or Option 2

Option 1

       Replace the existing 150mm diameter sewer in Montague Road from manhole (MH172668) to the nearest manhole in under construction Mollison Street trunk sewer in Hocking Street., approximate length – 157m with a DN250mm sewer.

 

       This condition for trunk infrastructure has been applied in accordance with the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009 s99BRCR as the item is not identified in the Queensland Urban Utilities schedule of works. This is identified as a trunk infrastructure and is offsetable against the sewerage component of the infrastructure charges for the development.

 

 

Option 2

 

       Construct a DN250mm diversion sewer from manhole (MH172616) in Bank Street to the nearest manhole in under construction trunk sewer in Mollison Street. Construction of this diversion sewer will divert the flow from upstream catchment to Mollison sewer. After the DN250mm sewer in Bank Street is constructed, the existing 150mm dia. sewer in Montague Road will have adequate capacity to service the proposed development in accordance with SEQ WS & S D & C Code (2013).

 

       This condition for trunk infrastructure has been applied in accordance with the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009 s99BRCR as the item is not identified in the Queensland Urban Utilities schedule of works. This is identified as a trunk infrastructure and is offsetable against the sewerage component of the infrastructure charges for the development

 

 

 

 

 

 

 

GUIDELINE
This condition has been imposed to ensure that sewerage infrastructure is in place to serve the development. This condition has been imposed on behalf of Central SEQ Distribution - Retailer Authority, Queensland Urban Utilities, under the delegated concurrence agency agreement. For any enquiries about this condition, please contact the Water and Sewerage Assessment Team, Development Assessment.

PROOF OF FULFILMENT
Work constructed and accepted on maintenance / off maintenance.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
61(a) Submit Plans

Submit engineering plans in accordance with the current Central SEQ Distribution - Retailer Authority, Queensland Urban Utilities Incorporating WSAA Standards (formerly BCC Standards) showing the design of the works.

Obtain endorsement from the Delegate, Development Assessment.

Timing: Prior to site/operational/building work commencing

GUIDELINE
This condition is imposed to ensure that the required works are designed in accordance with this development permit and relevant standards. This condition has been imposed on behalf of Central SEQ Distribution - Retailer Authority, Queensland Urban Utilities, under the delegated concurrence agency agreement. For any enquiries about this condition, please contact the Water and Sewerage Assessment Team, Development Assessment.

PROOF OF FULFILMENT
Plans checked and certified by a Registered Professional Engineer of Queensland (RPEQ) and endorsed by the Delegate, Development Assessment.

 
As indicated
61(b) Implement Approved Plans

Construct the works in accordance with the endorsed engineering plans and the current Central SEQ Distribution - Retailer Authority, Queensland Urban Utilities (QUU) Incorporating WSAA Standards (formerly BCC Standards).

Timing: Prior to on-maintenance inspection

Note.  All live works must be undertaken by QUU at the developer’s expense

GUIDELINE
This condition is imposed to ensure that the required works are carried out in accordance with this development permit, relevant standards and endorsed plans. This condition has been imposed on behalf of Central SEQ Distribution - Retailer Authority, Queensland Urban Utilities, under the delegated concurrence agency agreement. For any enquiries about this condition, please contact the Water and Sewerage Assessment Team, Development Assessment.

PROOF OF FULFILMENT
Plans checked and certified by a Registered Professional Engineer of Queensland (RPEQ) and endorsed by the Delegate, Development Assessment.

 
As indicated
61(c) Submit As Constructed Drawings and Supporting Documentation

Submit As Constructed plans certified by a Registered Professional Engineer Queensland-Civil (RPEQ-Civil), that are a true record of the constructed works and are in accordance with the endorsed plans, approved modifications and in accordance with the current Central SEQ Distribution - Retailer Authority, Queensland Urban Utilities Incorporating WSAA Standards (formerly BCC Standards).

Submit a Certificate of Completion, supporting test results, reports, product and material certificates, structural certificates and a copy of the pipe layer’s accreditation.

Lodge a copy of the above documentation with the Delegate, Development Assessment.

Timing: Prior to on-maintenance inspection

GUIDELINE
This condition has been imposed to ensure the works have been constructed to the correct standard and that an accurate record of the works has been provided. This condition has been imposed on behalf of Central SEQ Distribution - Retailer Authority, Queensland Urban Utilities, under the delegated concurrence agency agreement. For any enquiries about this condition, please contact the Water and Sewerage Assessment Team, Development Assessment.

PROOF OF FULFILMENT
Documents submitted and accepted by the Delegate, Development Assessment

 
As indicated
 
62)   Grant Easements

Grant the following easement(s) for water supply or sewerage purposes.

         i.            Easements for access, construction and maintenance to and over sewerage gravity manholes in the development lot, in favour of Central SEQ Distribution - Retailer Authority, Queensland Urban Utilities (QUU).

 

Notes.

Queensland Urban Utilities will require 1.000 metre access easement running from the street frontage, alongside the property boundary, to the maintenance structure or manhole in the back yard. Maintenance structures or manholes are to be located in a 2.000 x 3.000 metre easement connected to the access easement.

 

-          Easements in favour of QUU are required to have the necessary easement documentation prepared (free of costs and compensation to QUU) by QUU.

-             ;                       Easements not in favour of the QUU are required to have the necessary documentation prepared by the applicant's private solicitors.

-          Easements are to be shown on a Survey Plan and lodged with the Delegate Plan Sealing, Licensing Sealing and Certificates Unit.

 

 

GUIDELINE
This condition is imposed to ensure that access is provided for the construction and maintenance of QUU infrastructure and services, or that access is provided to QUU infrastructure. Enquiries regarding any legal documentation can be directed to Licensing, Sealing and Certificates Unit, Development Assessment. For any enquiries about this condition, please contact the Water and Sewerage Assessment Team, Development Assessment.

PROOF OF FULFILMENT
Registration of the easement on the plan of survey and on the property title with the Department of Natural Resources.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
63)   Provide / Extend Sewerage Connection(s) - Minor (MCU)

Provide a sewer property connection to serve the development designed and constructed in accordance with endorsed engineering plans and the current Central SEQ Distribution - Retailer Authority, Queensland Urban Utilities (QUU) Design and Construction Standards.


This Condition can only be acted on by endorsed entities under the QUU Certification Scheme for Property Service and Network Connections – Minor Works



 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
64)   General Requirements for Water and Sewerage Works

The following requirements may apply to this development. It is the developer’s responsibility to determine where these requirements apply, and meet the cost of any resulting works.

1)      Construct and/or alter public utilities mains, existing water and sewerage mains, services or installations required in connection with the approved development in accordance with the current Central SEQ Distribution - Retailer Authority, Queensland Urban Utilities Design and Construction Standards.

This includes the relocation of any water meter, fire hydrant, scours and/or valves and sewer connections from within the limits of the development's vehicular footway crossings.

2)      Where an existing sewerage property connection is located under a driveway (in the road reserve) and is unable to be relocated, a 1m x 1m removable slab with suitable lifting arrangements is to be located centrally over the connection with the Delegate’s, Development Assessment written agreement.

3)      Where existing or new sewerage property connections will be located under reinforced concrete slabs on private property, a 1m x 1m removable slab with suitable lifting arrangements is to be located centrally over the connection with the Delegate’s, Development Assessment written agreement.

4)      Where existing sewerage maintenance holes do not have the current standard top slab, cover and frame, or there are changes to the surface levels or there are changes to the loading conditions, the maintenance holes are to be modified in accordance with the current Central SEQ Distribution - Retailer Authority, Queensland Urban Utilities Design and Construction Standards.

5)      Existing water mains and sewers are to be relocated or raised/lowered to the current Central SEQ Distribution - Retailer Authority, Queensland Urban Utilities Design and Construction Standards, if development related works change the depth of cover on these works.

6)      Where a new road opening or widening is required and an existing water main is located in the footpath which will become new roadway, the existing main is to be relocated clear of the proposed carriage way to the depth specified in the current Central SEQ Distribution - Retailer Authority, Queensland Urban Utilities Design and Construction Standards.

7)      Clear, unobstructed, 24 hour access from the street frontage is to be maintained to any sewerage maintenance holes and property connections, on the development site.

8)      Where the property is encumbered by a combined drain, replacement of the existing combined drain may be a requirement of the plumbing Approval. It is recommended that contact be made with the Plumbing Services Group to determine any requirements.

9)      Where a building is demolished on a site the existing sewer property connection is to be sealed and capped. The existing water service and meter is to be sealed off and removed if not required for the future development of the site.

10)  Where a dwelling is located in a declared sewered area then the dwelling is to be provided with an individual water service and meter and sewerage property connection.

GUIDELINE
This condition is imposed to ensure that water and sewer infrastructure is accessible, is protected and can be operated and maintained. The condition also ensures footpaths are kept in a safe condition. This condition has been imposed on behalf of Central SEQ Distribution - Retailer Authority, Queensland Urban Utilities, under the delegated concurrence agency agreement. For any enquiries about this condition, please contact the Water and Sewerage Assessment Team, Development Assessment.

PROOF OF FULFILMENT
Requirements of this condition are complied with to the satisfaction of the Delegate, Development assessment.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
 
65)   Service, Meter Assembly and Meter Box - Minor (MCU)

Provide a water service with approved meter assembly and meter box to the front real property boundary of the development and a water sub meter to each lot or tenement in the development, in accordance with the current Central SEQ Distribution - Retailer Authority, Queensland Urban Utilities (QUU) Design and Construction Standards and an approved QUU water sizing.
 

This Condition can only be acted on by endorsed entities under the QUU Certification Scheme for Property Service and Network Connections – Minor Works

 

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 

** End of Package **