| Address of Site: | 10 BANK ST WEST END QLD 4101 14 BANK ST WEST END QLD 4101 4 BANK ST WEST END QLD 4101 8 BANK ST WEST END QLD 4101 |
| Real Property Description of Site: | L45 RP.10779 L44 RP.10779 L47/48 RP.10779 L46 RP.10779 |
| Aspects of development and type of approval: | DA - SPA - Carry out Building Work Preliminary Approval under s241 - Multi-
Unit Dwelling DA - SPA - Material Change of Use Development Permit - Multi-Unit Dwelling |
| Council File Reference: | A007007144 Permit Reference Number/s: DABW296090914; DAMC296091014. |
| Package Status: | APPROVED - Version 3 (25th of June, 2026 2:56:23 PM) |
| Package Generated: | 25/06/2026 |
| Diana SUN Urban Planner Planning Services South Diana.Sun@brisbane.qld.gov.au 0731785179 |
Ashleigh COOMBES Principal Urban Planner Planning Services South Ashleigh.Coombes@brisbane.qld.gov.au (07) 3403 1937 |
Peter MCDONALD WaRRS Assessment Peter.McDonald@brisbane.qld.gov.au |
| Andrew BLAKE Principal Engineer Engineering Services Hydraulics andrew.blake@brisbane.qld.gov.au (07) 3403 5018 |
Daniel SPILLANE Senior Engineer Engineering Services South Daniel.Spillane@brisbane.qld.gov.au 3403 5285 |
Daniel SPILLANE Senior Engineer Engineering Services South Daniel.Spillane@brisbane.qld.gov.au 3403 5285 |
| David HOOPER Principal Urban Planner Planning Services South Dave.Hooper@brisbane.qld.gov.au (07) 3403 9889 |
Roger GREENWAY Principal Urban Planner Development Assurance & Outcomes roger.greenway@brisbane.qld.gov.au 34034392 |
David HOOPER Principal Urban Planner Planning Services South Dave.Hooper@brisbane.qld.gov.au (07) 3403 9889 |
| Roger GREENWAY Principal Urban Planner Development Assurance & Outcomes roger.greenway@brisbane.qld.gov.au 34034392 |
Callan BENNETT Principal Architect Architecture Team Callan.Bennett@brisbane.qld.gov.au 07 31780595 |
Phil EASTGATE Principal Technical Officer Engineering Compliance philip.eastgate@brisbane.qld.gov.au (07) 3403 9432 |
| Daniel SPILLANE Senior Engineer Engineering Services South Daniel.Spillane@brisbane.qld.gov.au 3403 5285 |
Katrina KONTOS Environmental Management Officer Environmental Management Services katrina.s.kontos@brisbane.qld.gov.au (07) 3403 8888 |
Carina FIESELER Landscape Architect Landscape Architecture Team carina.fieseler@brisbane.qld.gov.au 3403 5235 |
DRAWINGS AND DOCUMENTS
| Drawing or Document | Number | Plan Date |
|---|---|---|
| Noise Impact Assessment_8 Bank St West End | 7247R02V06 Prepared by Ask Consulting | 30-JUL-2014 |
| Extract from Stormwater Management Report - 4-14 Bank Street West End, Section 4.1 pp2-4, Prepared by Westera Partners | Job No. B14-037 | 17-JUL-2014 (Received) |
| Appendix B: Stormwater Management Plan | Sheet 1 of 4 Revision B (Amended In Red 06-AUG-2014) | 30-JUN-2014 |
| GROUND FLOOR PLAN | NRA-84113-3000-GF00 Rev 1 | 17-APR-2026 (Received) |
| LoadingDock Ramp 01 | 25061 1.01 (Amended In Red 23-JUN-2026) | 17-APR-2026 (Received) |
| LoadingDock Ramp 02 | 25061 1.02 (Amended In Red 23-JUN-2026) | 17-APR-2026 (Received) |
| Coversheet | BD 200 Issue A | 30-JUN-2015 |
| Legend, Notes, Schedules | BD 201 Issue A | 30-JUN-2015 |
| Surface Finishes Ground Floor | BD 301 Issue A (Amended In Red 23-JUN-2026) | 30-JUN-2015 |
| Surface Finishes Level 1 | BD 302 Issue A | 30-JUN-2015 |
| Surface Finishes Roof | BD 303 Issue A | 30-JUN-2015 |
| Planting Plan Ground Floor | BD 401 Issue A | 30-JUN-2015 |
| Planting Plan Level 1 | BD 402 Issue A | 30-JUN-2015 |
| Planting Plan Roof | BD 403 Issue A | 30-JUN-2015 |
| Landscape Details | BD 601 Issue A | 13-JUL-2015 |
| Landscape Details | BD 602 Issue A | 30-JUN-2015 |
| Landscape Details | BD 603 Issue A | 30-JUN-2015 |
| Basement 03 | NRA-84113-2010-BS03 Rev 4 | 01-FEB-2016 |
| Basement 2 | NRA-84113-2020-BS02 Rev. 4 | 01-FEB-2016 |
| Basement 1 | NRA-84113-2030-BS01 Rev. 4 | 01-FEB-2016 |
| Level 01 Plan | NRA-84113-3010-LV01 Rev 2 (Amended In Red 16-MAR-2015) | 17-DEC-2015 |
| Level 02 Plan | NRA-84113-3020-LV02 Rev 2 (Amended In Red 16-MAR-2016) | 17-DEC-2015 |
| Level 03 Plan | NRA-84113-3030-LV03 Rev. 2 (Amended In Red 16-MAR-2016) | 17-DEC-2015 |
| Level 04 Plan | NRA-84113-3040-LV04 Rev 2 (Amended In Red 16-MAR-2016) | 17-DEC-2015 |
| Level 05 Plan | NRA-84113-3050-LV05 Rev 2 (Amended In Red 16-MAR-2016) | 17-DEC-2015 |
| Level 06 Plan | NRA-84113-3060-LV06 Rev. 2 (Amended In Red 16-MAR-2016) | 17-DEC-2015 |
| Level 07 Plan | NRA-84113-3070-LV07 Rev. 2 (Amended In Red 16-MAR-2016) | 17-DEC-2015 |
| Roof Plan | NRA-84113-3080-ROOF Rev. 3 (Amended In Red 16-MAR-2016) | 19-JAN-2016 |
| South East Elevation | NRA-84113-4010-ELEV Rev. 3 | 19-JAN-2016 |
| North East Elevation | NRA-84113-4020-ELEV Rev. 3 | 19-JAN-2016 |
| South West Elevation | NRA-84113-4030-ELEV Rev. 1 (Amended In Red 16-MAR-2016) | 27-OCT-2015 |
| North West Elevation | NRA-84113-4040-ELEV Rev. 3 | 19-JAN-2016 |
| Section C-C | NRA-84113-5030-SECT Rev. 4 | 01-FEB-2016 |
| Section B-B | NRA-84113-5020-SECT Rev. 4 | 01-FEB-2016 |
| Rooftop Vent Detail | NRA-84113-8090-DET Rev. 3 | 19-JAN-2016 |
APPROVAL CONDITIONS
| Permit to Which These Conditions Relate: | DA - SPA - Carry out Building Work |
| Activity(ies): | Multi-Unit Dwelling |
| Stage: |
| 1) Further Development Permit required This
Preliminary Approval (Carry Out Building Works) does
not include assessment against the Building Act and does not permit building
work to occur. Prior to the
commencement of any building work, Development Permit(s) for Carrying Out Building Work will be required. |
As indicated |
| Permit to Which These Conditions Relate: | DA - SPA - Material Change of Use |
| Activity(ies): | Multi-Unit Dwelling |
| Stage: |
| 2) Demolish or Relocate Buildings Demolish or relocate
all existing buildings/structures on the site. The removal of
buildings/structures includes the removal of all existing concrete slabs,
foundations and footings. |
As indicated |
| 3) Landscaping of Vacant Site If construction for the approved development
does not commence within 3 months of the demolition of the existing building(s)
on site, the site is to be landscaped in accordance with a landscape drawing
that has been submitted to and approved by Development Assessment. |
As indicated |
| 4) Approved Drawings & Documents A legible copy of the approved
drawings and documents bearing "Council Approval" and the Development
Approval Conditions package is to be available on site. |
While site/operational/building work is occurring |
| 5) Carry Out The Approved Development Carry out the
approved development generally in accordance with the approved drawing(s)
and/or document(s) as amended in red: ·
The roof top communal open space
area shall remain open to the sky with no roof above including impervious
roofing. ·
Not Part of This Approval –
Storage in Basement (areas highlighted in red in red are not approved for
general storage only for the storage of bicycles). ·
Screening required on the East and
West Elevations. . |
While site/operational/building work is occurring and then to be maintained |
| 6) Complete All Building Work Complete all building work associated with this
development approval, including work required by any of the conditions included
in the Conditions Package. Such building work is to be carried out generally in
accordance with the approved drawing(s), and/or documents and, where the
building work is assessable development, in accordance with a current
development permit. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
| 7) Bicycle Parking Install and maintain secure bicycle parking and associated
support facilities consistent with the approved drawings and generally in
accordance with the relevant Brisbane Planning Scheme
Codes/Policies. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 8) Car Parking Provide 216 (including 42 tandem spaces) onsite resident car parking
spaces within the building to be maintained exclusively for the residential use
of the development. The parking is not to be made available to the general
public and there is to be no advertising signage erected on or in the vicinity
of the site advertising the availability of car parking to the general public.
Parking on site is to be provided and maintained for the exclusive use of the
residents of the approved development and their visitors only. Requirements of
this condition shall be contained within any Community Management
Statement |
To be maintained |
| 9) Maintain the Approved Development Maintain the approved development
(including landscaping, parking, driveways and other external spaces) generally
in accordance with the approved drawing(s) and/or documents, and any relevant
Council engineering or other approval required by the conditions. |
To be maintained |
| 10) Information Signage Prior to any works commencing on the site and then to be maintained until completion of the development for all stages , erect an "Information Sign" as outlined below: a) A brief description of the development proposed; b) The sign is to list the name, postal and/or email address and a contact telephone number for the following parties (where relevant) that are undertaking work on the site: Developer; c) The lettering on the sign is to be at least 25 millimetres in height, be of regular weight and in sentence case; d) The sign is to be a minimum size of 1,200 millimetres by 900 millimetres; e) The maximum area of the sign is to be 2.0m2; f) The sign must be placed on or within 1.5 metres of the road frontage for the site at the following locations:
The site is to be mounted at least 300 millimetres above ground level; g) The sign is to contain no commercial or corporate advertising other than the name, logo or slogan of the parties outlined in part (b) of this condition; h) The sign is to be non-illuminated; i) Both the sign and the supporting structure are to be made of weatherproof material and to be properly maintained at all times; and j) The sign/s are to be located on the subject property and is to be comply with the General Requirements for Signage contained within the Local Laws Policy "Control of Outdoor Advertising" specifically with regard to Traffic Safety, Clearances and Structural Systems; |
As indicated |
| 11) Community Management Statement Any Community
Management Statement is to contain the following
requirements:
|
As indicated |
| 12) Roof Decks / Terraces The roof
terrace level (communal use areas) is limited to residential use only and shall
not be used between the hours of 10pm to 7am. The roof top communal open space
area shall remain open to the sky with no roof above including impervious
roofing. Requirements of this condition shall be contained within any Community Management Statement. |
At all times |
| 13) Overall Height - Survey Certification The overall height of
the proposed building(s) is to be constructed in accordance with the floor and
roof levels nominated on the approved drawings. The building height is not to exceed RL32900m
(Excluding lift overrun, plant level and carpark vent). An allowance of an
additional 500mm in height above RL32900m for the pool deck only is acceptable.
|
While site/operational/building work is occurring and then to be maintained |
13(a) Submit Certification Submit certification from a licensed surveyor that the as constructed floor and roof levels are in accordance with this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 14) Building Management Statement With any subsequent volumetric subdivision
application ensure a Building Management Statement is registered on the title
for each proposed lot. The Building
Management Statement is to cover common building management items (e.g.
support, shared services/utilities, pedestrian and
vehicle access). The Building
Management Statement is to be submitted to and approved by Development
Assessment. |
Prior to Council's notation on the plan of subdivision and then to be maintained |
| 15) Visitor Parking Provide
29 on site visitor car parking spaces within the building as
follows
The above requirements are to be
included within any Community Management Statement. |
Prior to the commencement of the use or prior to the endorsement of a Community Management Statement, whichever is sooner |
| 16) Mechanical Ventilation of Car Parking Areas Vents associated with the mechanical ventilation of car parking areas are not permitted to be located where facing the boundary of any adjoining property. Any exhaust vents associated with the mechanical ventilation of the car parking areas must be located on the Bank Street frontage of the building only or to the roof top. |
Prior to the commencement of the use and then to be maintained |
| 17) Lighting To Public Areas Install and maintain a suitable system of
lighting, to operate from dusk to dawn, within all areas where the public may
gain access. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 18) Submit External Details Submit for the approval of Development
Assessment, further details of the building, facade treatment and external
materials, colours and finishes (in particular on the proposed painted pre-cast
concrete) generally consistent with the approved drawings. |
As indicated |
18(a) Implement Approved External
Details Implement the
above detailed design treatments. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 19) Balconies and Terraces to Remain Unenclosed All balconies and terraces shown on the approved
drawings and documents, are to remain unenclosed with
no shutters, glazing, louvres or similar permanent
fixtures other than those consistent with the relevant Brisbane Planning Scheme
Codes/Policies and clearly depicted on the approved drawings. Any Community Management Statement is to contain a
by-law which reflects the requirements of this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 20) Driveway Material and Finishes Provide materials and finishes to the driveway
and external carparking surfaces that reduce the
visual impact of these areas when viewed from the street. In order to achieve
this outcome, one or a combination of the following is to be used: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 21) Screen A/C and Other Plant Enclosures Install and maintain suitable screening to all
air conditioning, lift motor rooms, plant and service facilities located at the
top of or on the external face of the building. The screening structures must
be constructed from materials that are consistent with materials used elsewhere
on the facade of the building. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 22) Solar Screening Provide solar screening to all western facing windows. Screening is to include a vertical
screening element and be positioned in conjunction with a window
hood. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 23) Screening Provide
screening in accordance with the following:
Any Community Management Statement is to contain a by-law which
reflects the requirements of this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 24) Light Reflectivity and Solar (Heat)
Reflectivity Submit to
Development Assessment documentary evidence that: |
As indicated |
24(a) Install Glazing Install and maintain glazing in accordance with
the Manufacturer's specification. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 25) Provide Detailed and Textured Model Submit to Development Assessment, a detailed and
textured digital 3D model in Autodesk compatible format for incorporation into
the Brisbane City Council Virtual Brisbane 3D Model. The digital model shall be
a high quality 3D Exterior Detailed Model to the extent of the development at a
standard which can be publicly viewable and include: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 26) Landscape the Site - Self Certification Landscape the site in accordance with the
requirements of this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
26(a) Construct Approved Work Construct landscaping in accordance with the approved detailed Landscape
Plan prepared by CUSP, Dwg No.’s BD 200, BD201, BD301(as amended in red
23-06-2026), BD302, BD303, BD 401, BD402, BD 403, BD601, BD 602 and BD 603,
dated 30-06-2015 (received on 02-11-2015). |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first |
26(b) Certify Work On completion of works, submit to Development
Assessment certification from: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
26(c) Maintain Landscape Work Maintain the landscape generally in accordance
with the detailed plans. |
To be maintained |
| 27) Retain and Protect Existing Street Trees(s) Identify, retain and protect the existing street trees unless
otherwise determined in writing by Asset Services. |
While site/operational/building work is occurring |
27(a) Implement Protection
Measures Install tree protection measures in accordance with
Australian Standard AS4970 (Retention of Trees on Development Site). |
While site/operational/building work is occurring |
27(b) Maintain Protection
Measures Maintain
protection measures while development is occurring and remove protection
measures prior to commencement of the use. |
While site/operational/building work is occurring |
| 28) Pedestrian Lighting Submit a Pedestrian Lighting Design in accordance with the
requirements of this condition. |
Prior to site/operational/building work commencing |
28(a) Obtain An Electrical
Connection Obtain an
electrical connection from Energex prior to
installing the lighting. |
As indicated |
28(b) Submit a Pedestrian Lighting
Design Submit a
Pedestrian Lighting Design (including Details) for the full street frontage of
the development for approval by the City Lighting, Asset Services. The lighting is to be in accordance with
AS/NZS 1158.3.1, 1999 Pedestrian Area (Subcategory P3) lighting and the
relevant Brisbane Planning Scheme codes/policies. |
As indicated |
28(c) Install the Lighting Install the lighting in accordance with the
approved Pedestrian Lighting Design and the approved Landscape Works in
Streetscape Plan. |
As indicated |
28(d) Provide Certification of Connection and
Operation Provide to
City Lighting, Asset Services certification from a licensed electrical
contractor that the electrical connection has been installed in accordance with
the approved Pedestrian Lighting Design and that the lighting is fully
operational. In addition, the certification is to specify that the electrical
installation has been tested to ensure it is electrically safe and is in
accordance with the requirements of Australian / New Zealand Standard 3000 Electrical
Installations (known as the "Wiring Rules") and any other
standard applying to the electrical installation under the Electrical Safety Regulation 2002. |
As indicated |
28(e) On Maintenance Inspection Contact City Lighting, Asset Services to arrange
an On Maintenance inspection. |
As indicated |
28(f) Maintenance Period Provide 12 months' maintenance to the works from
the time the works are accepted On-Maintenance by Council. Maintain the lighting and rectify all defects
identified at the On-Maintenance inspection and those arising during the
maintenance period. Timing:
From acceptance of On Maintenance period. |
As indicated |
28(g) Off-Maintenance
Inspection On completion
of the maintenance period contact Development Assessment, to arrange an Off-
Maintenance inspection and release of the Bond. Ensure all defects are rectified prior to making an
appointment for Off-Maintenance Inspection. |
As indicated |
| 29) Streetscape Works Provide
improvement works to the road reserve pavement in accordance with the
requirements of this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
29(a) Submit Level Details
(MCU) For a material change of use,
submit to Development Assessment and receive approval for details on the
finished levels of the sire and building entries (both pedestrian and
vehicular) to demonstrate compatibility with acceptable footpath/footway
grades. The details must be provided by a suitably qualified and experienced
Landscape Architect or other relevant professional and include at least the
following information: |
As indicated |
29(b) Submit Plan for Works in the Road
Reserve Submit to Development Assessment
and receive approval for a detailed Landscape Works in Streetscape Plan for
required works to be undertaken within the road reserve fronting the
development site. The plan is to be prepared at a scale of 1:100 by a suitably
qualified and experienced Landscape Architect and the works are to be
constructed to a standard and of materials consistent with the requirements of
relevant Brisbane Planning Scheme Codes/Policies. The plans are to include the following: - Pavement treatment in the required materials and
pattern |
As indicated |
29(c) Construct Approved Works Carry out the works documented in the approved Landscape Works in
Streetscape Plan. |
As indicated |
29(d) Remove Existing Footway Remove the existing footway including affected street signage for
the full length of the frontages to Bank Street in accordance with Council
standards and complying with the terms and conditions of the footway
permit. |
As indicated |
29(e) Certify the Footway Works Provide to Development Assessment certification from a Registered
Professional Engineer of Queensland that footway works have been carried out as
documented on the approved Streetscape Works Plan, including the following: |
As indicated |
29(f) On-Maintenance Inspection Contact Development Assessment to arrange an On-Maintenance
inspection. |
As indicated |
29(g) Maintenance Period Provide 12 months maintenance to the streetscape works and rectify
any defects identified at the On-Maintenance inspection. |
As indicated |
29(h) Off-Maintenance
Inspection On completion of the maintenance
period, contact Development Assessment to arrange an Off-Maintenance inspection
and release of the bond. Ensure all defects are rectified prior to making an
appointment for Off-Maintenance inspection. |
As indicated |
| 30) Noise Attenuation - Adjacent Uses Design and construct the proposed development in
accordance with the following method as per the information provided by ASK
Consulting Engineers P/L dated 19 August 2014.
GUIDELINE This condition is set to reduce noise emissions from nearby and surrounding uses. |
To be maintained |
30(a) Certification Submit certification to the Assessment Manager
(from a qualified acoustic consultant) that the above design and construction
methods have been incorporated into the development. |
To be maintained |
| 31) Hours of Operation - Vehicle movements Operation of trucks, commercial vehicles and/or
waste collection vehicles during the operational phase of the development must
only occur between 7am - 7pm Monday to Saturday. |
To be maintained |
| 32) Air Conditioning to Noise Affected Rooms Air-conditioning must be provided to all living
and sleeping areas, as windows and doors are required to remain closed to
maintain acceptable indoor noise levels. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 33) Plant and Equipment Certification Following the installation of all mechanical
plant and equipment (e.g. air conditioning, mechanical ventilation and
refrigeration equipment and heat pump hot water systems), submit to Development
Assessment certification that the plant and equipment is adequately noise-
attenuated and is in accordance with the criteria of the relevant Brisbane
Planning Scheme Codes/Policies. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 34) Stormwater Quality (High Risk) Implement and maintain the recommendations of Section 4.1 and
drawing within Appendix B of the Site Based Stormwater Quality Management Plan
prepared by Westera Partners P/L, Received 14 July
2014 to achieve the requirements of the State Planning Policy 2013 (Qld) Water Quality.
|
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
34(a) Certification Submit to Development Assessment certification
from a Registered Professional Engineer |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 35) Filling and Excavation All proposed earthworks are to be carried out in accordance with the relevant Brisbane Planning Scheme Codes/Policies and the following requirements: |
As indicated |
35(a) Submit Earthworks Plan Submit and obtain endorsement from Development
Assessment an earthworks plan prepared in accordance with the relevant Brisbane
Planning Scheme Codes/Policies and Reference Specifications, checked and
certified by a Registered Professional Engineer of Queensland- Civil (RPEQ-
Civil). |
Prior to site/operational/building work commencing |
35(b) Suitable Fill Material All fill material placed on the site is to comprise only natural earth and rock and is to be free of contaminants (as defined by Section 11 of the Environmental Protection Act 1994) and noxious, hazardous, deleterious and organic materials. |
While site/operational/building work is occurring |
35(c) Implement Endorsed Plan Construct and maintain the earthworks works in
accordance with the endorsed engineering plans and with the relevant Brisbane
Planning Scheme Codes/Policies. |
While site/operational/building work is occurring and then to be maintained |
| 36) Construction Management Plan Prepare a Construction Management Plan for the
subject site in accordance with the following requirements. |
As indicated |
36(a) Construction Management Plan - For
Endorsement Submit to Development Assessment for endorsement, a Construction
Management Plan for the demolition, excavation and construction phases of the
approved development. Separate
Construction Management Plans may be appropriate for the individual
components. The Construction
Management Plan is to be in accordance with the relevant Brisbane Planning
Scheme Codes/Policies, Workplace Health and Safety Legislation requirements, Environmental Protection Act, the
requirements of any Concurrence Agency and any other relevant legislative
requirements. The Construction
Management Plan is to provide the following details and address impacts, where
applicable:
|
Prior to site/operational/building work commencing |
36(b) Construction Management Plan - Pre-
start Meeting Arrange a pre- start meeting with the Development Assessment. |
Prior to site/operational/building work commencing |
36(c) Construction Management Plan - Works in
Road Obtain relevant
approvals to carry out any works within the road reserve required by the
approved Construction Management Plan: |
Prior to site/operational/building work commencing |
36(d) Construction Management Plan - Plans on
Site Legible copies of the Construction Management Plan and current permits are to be kept on site and be made available on request at all times during construction. |
While site/operational/building work is occurring |
36(e) Construction Management Plan - Out of
Hours Works to be Performed Notify Development Assessment for any work
activity identified broadly in the endorsed Construction Management Plan to be
conducted out of normal business hours 6:30am and 6:30pm Monday to
Saturday. |
While site/operational/building work is occurring |
36(f) Construction Management Plan -
Implement the Plan Subject to the
provisions of this condition, implement and maintain the approved Construction
Management Plan. |
While site/operational/building work is occurring |
| 37) Protect Existing Infrastructure Where there is existing infrastructure in the vicinity of the proposed work, then the new work must not damage or compromise the working ability of the existing infrastructure. Should it be required to provide alterations to public utility mains, existing mains, services or installations, then the developer is required to meet the costs of the alteration/s, which is to be carried out in accordance with the relevant Brisbane Planning Scheme Codes/Policies. |
While site works are occurring and then to be maintained |
37(a) As Constructed Drawings Submit to Development Assessment "As Constructed" drawings including an asset register, showing all new and/or rectification works required by this condition. These works must be certified by a Registered Professional Engineer of Queensland-Civil that they are in accordance with the relevant Brisbane Planning Scheme Codes/Policies and any other relevant infrastructure requirements. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 38) On-site Erosion (Low Risk) Minimise on-site erosion and the release of
sediment or sediment-laden stormwater from the site at all
times. |
While site/operational/building work is occurring |
38(a) Prepare an Erosion and Sediment Control
(ESC) Management Plan - On-site Erosion (Low Risk) Prepare an Erosion and Sediment Control (ESC)
Management Plan for the site in accordance with the Healthy Waterways document
Controlling Stormwater Pollution on Your
Building Site 2006 (or later version) and in accordance with the relevant
Brisbane Planning Scheme Codes/Policies. |
Prior to site/operational/building work commencing |
38(b) Implement and Maintain the ESC
Management Plan - On-site Erosion (low Risk) Implement and maintain the ESC Management Plan
on-site for the duration of the operational or building works, and until all
exposed soil areas are permanently stabilised (e.g. turfed, hydro-mulched, concreted, landscaped). The prepared ESC Management Plan must be
available on-site for inspection by Council Officers during these
works. |
While site/operational/building work is occurring |
| 39) Retaining Walls Design and construct all retaining walls and associated fences,
in accordance with the relevant Brisbane Planning Scheme Codes/Policies and to
ensure the following: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
39(a) Certification of Retaining
Walls For retaining
walls over 1.0 metre in height, provide certification from a Registered
Professional Engineer Queensland that the design and construction of the
retaining wall and ancillary drainage comply with this
condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 40) Granting Easements Grant easements for underground
drainage, overland flow and access purposes as may be required, in favour of
Brisbane City Council. Note:-This condition is imposed to provide access, maintenance of services and to protect drainage paths if required. Easements in favour of the Brisbane City Council are required to have the necessary easement documentation prepared (free of costs and compensation to Council) by the Brisbane City Council. Easements not in favour of the Brisbane City Council are required to have the necessary documentation prepared by the applicant's private solicitors. Easements are to be shown on a Survey Plan and lodged with the Plan Sealing Unit. Enquiries regarding any legal documentation can be directed to the Plan Sealing Unit, Development Assessment (ph: 3403 8888). |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 41) Rock and Ground Anchors Where Rock and Ground anchors are required they
must be designed, constructed and certified by an
Registered Professional Engineer Queensland (RPEQ) in accordance with the
requirements of the relevant Brisbane Planning Scheme Codes/Policies, and the
notes of this condition. 2. Provide both pre and post construction CCTV
survey of pipe lines adjacent to the site. Provide Pre Construction CCTV
inspection of all pipes in the vicinity of anchors, to be carried out prior to
commencement of site works. Provide Post Construction CCTV inspection of all
pipes in the vicinity of the anchors, one month after de-stressing of anchors.
CCTV surveys should be carried out using a camera with the capacity to pan and
tilt. The applicant is to submit a digital report and video of the
inspection. 3. Provide geotechnical certification that the
construction phase building loads and the final building loads will not impact
or endanger Council’s infrastructure. This will involve demonstrating the effect of the
load imposed pressure bulb, both prior to the de-stressing of the temporary
ground anchors and upon final completion of the building. 4. Provide
a geo-technical report which relates to the position of rock anchors, to be
submitted with the design plans.
Geological formation and borehole data should be included as part of
this report. 5. Submit documentation of the approval of any
adjacent property owners where the anchoring system is proposed to encroach
into neighbouring properties. 6. Obtain the approval from the
providers of affected services and plot the level and line of these services on
the sections and plans. 7. Provide an emergency management
plan that includes procedures to reinstate any services which may be damaged as
a result of works on the site. 8. Piers and drainage system shall
be located wholly within the property. 9. Structural certification is required for retaining walls greater than 1.0m in height. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
41(a) Submit Drawings for
approval Submit to
Development Assessment for endorsement as part of an earthworks plan a Ground
or Rock anchor system designed, checked and certified by a Registered
Professional Engineer Queensland and in accordance with this condition and the
relevant Brisbane Planning Scheme Codes/Policies. The following drawings and
details are required: |
Prior to site/operational/building work commencing |
41(b) Implement approved
drawings Construct and
maintain the earthworks works in accordance with the endorsed engineering plans
and with the relevant Brisbane Planning Scheme
Codes/Policies. |
While site/operational/building work is occurring |
41(c) Post Construction
Certification Provide
Certification by a Registered Professional Engineer |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
| 42) Access, Grades, Manoeuvring, Carparks, Signs, and
Lines Provide access, parking and manoeuvring for vehicles on-site in
accordance with the relevant Brisbane Planning Scheme Codes/Policies, as
indicated on the approved drawing(s), and including to the following: iv. Provide 207 number of secure bicycle parking
spaces.
|
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
42(a) Provide certification Submit to Development Assessment, certification
from a relevant discipline Registered Professional Engineer |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 43) Flood Risk Management Plan Prepare, implement and maintain a Flood Risk Management Plan in accordance with the requirements of this condition. |
As indicated |
43(a) Prepare and Certify a Flood Risk
Management Plan Submit to
Development Assessment, a Flood Risk Management Plan (FRMP) prepared and
certified by a qualified and experienced practitioner in flood risk management
for the approved development. The
FRMP must address the risk of impacts from flood inundation and adopt measures
to mitigate potential adverse impacts including: 1. Procedures for flood
monitoring and identification of warning times based on flooding type and
catchments characteristics; 2. Procedures on notification
and identification of responsibilities; and 3. Emergency excavation
procedures. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
43(b) Implement and Maintain the Certified
Flood Risk Management Plan Implement and
maintain the development in accordance with the certified Flood Risk Management
Plan. Update the FERP as required reflecting current standards, best practices, or any future approved modifications to this development. The Manager, Development Assessment is to be notified by email to edasouth@brisbane.qld.gov.au within 14 business days of any alterations to the FERP for the site. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 44) Minimum Floor or Pad Levels Design and construct all proposed pad levels,
building levels, floor levels and ancillary structures to have the appropriate
freeboard in accordance with Brisbane Planning Scheme Codes/Policies to ensure
they will not be flooded during a 50 year ARI local flood event or a 100 year
ARI Creek, River or Storm Tide flood event, whichever is the higher flood
level. Basement entry
6.5m AHD Essential services – 6.7m
AHD |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
44(a) Certification Provide certification and/or As-Constructed
plans from a Registered Surveyor that confirm the
development complies with the requirements of this
condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 45) Basements in flood affected areas All new construction and substantial
improvements of basements below the 100 year ARI flood or storm tide level
(and/or Brisbane River Defined Flood level) together with stormwater,
electrical and sanitary facilities are and designed in accordance with the
following: (i) Ensure the structure is suitably flood proof
to minimise and/or manage ingress of floodwater to prevent significant flooding
of basements during floods. (ii) All ventilation openings, driveway entry/exit
ramps and pedestrian entrances into the basement are constructed in accordance
with the minimum levels as stated in the relevant Brisbane Planning Scheme
Codes/Policies. (iii)
All essential electrical services (refer to the relevant Brisbane Planning Scheme
Codes/Policies) are to be located 500mm above the higher of the January 2011
flood level (IRFL) or 100 year ARI waterway level. Where such services have been approved in a
basement through a risk management approach to flooding, a completely
watertight tanked basement is required with floors and walls designed and
certified by a Registered Professional Engineer Queensland (RPEQ) to resist
hydrostatic pressures expected during floods. (iv)
Where any
part of a basement is below 2.0m AHD or determined to be subject to saline
groundwater conditions, an RPEQ is to certify that the design of concrete
structures and construction techniques are suitable to withstand corrosive
effects of salt water in accordance with relevant Australian
Standards. (v)
Where a sump/pump basement drainage system is used to manage stormwater
& flooding for the basement (note:
NOT APPLICABLE where any essential electrical services or rooms for such
services are proposed in a basement) the following are required: (vi) All stormwater pump systems are to
utilise backflow prevention devices to ensure no flooding of the basement, and
designed to gravity drain into a Council stormwater
system. (vii)
All sewer connections are to include backflow prevention
devices. (viii) The driveway aisle into a basement is to be
designed and constructed to minimise local driveway stormwater runoff entering
the basement. The drainage is to
accommodate 10 year ARI rainfall events and gravity feed to a lawful point of
discharge. (ix)
Vehicle access into any basement from a Council road will require the
basement driveway to ramp up a minimum of 200mm above the adjacent road channel
invert to maintain road major flow capacity. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
45(a) Registered Professional Engineer
Queensland certification of basement in flood affected areas Where a basement is required to be made suitably
flood proof below the 100 year ARI flood level or River Defined Flood Event, a
Registered Professional Engineer of Queensland (RPEQ) shall; a)  
; Submit certification to the Private
Building Certifier of the stormwater and sewer hydraulic design,
specifications, and plans for the construction. Certification must verify that the basement design
and methods of construction are in accordance with accepted standards of
practice for meeting the applicable provisions of the relevant standards and
this condition, ensuring the basement structural design or subsoil drainage
system (including flow rate assumptions) will ensure it is suitably flood
proof. b)  
; Submit certification to the Private
Building Certifier to ensure structural integrity of the building from
hydrostatic pressures resulting from floodwaters and groundwater. Certification must verify that the
structural design of the basement and methods of construction are in accordance with
accepted standards of practice for meeting the applicable provisions of the
relevant standards and this condition. c)  
; Submit As Constructed Plans and
provide certification (RPEQ) to Councils Engineering Delegate that the works
have been completed in accordance with the approved design, conditions and any
approved modifications. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 46) Refuse Collection - On Site Arrange for the
installation of waste/recycling bins by Brisbane City Council's Waste Services
and for the subsequent collection of waste including recycling from the
site. The applicant/owner including any
subsequent owners are to indemnify Council and its agents in respect of any
damage to the pavement and other driving surfaces. The applicant is to notify
future owners/body corporate that the development has been approved on the
basis that an indemnity is provided for refuse collection vehicles to enter the
property. Timing: |
As indicated |
| 47) Repair Damage To Kerb, Footpath Or Road Repair any damage to existing
kerb and channel, footpath or roadway (including removal of concrete slurry
from footways, roads, kerb and channel and stormwater gullies and drainlines) and re-instatement existing traffic signs and
pavement markings that have been removed or damaged during any works carried
out in association with the approved development. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 48) On Site Drainage - Major Stormwater run-off from all proposed lots, roof
and developed surface areas and any run-off onto the site from adjacent areas, must be collected internally and conveyed to a lawful
point of discharge in accordance with the relevant Brisbane Planning Scheme
Codes/Policies and Standard Drawings. Timing: Prior to Council's
endorsement of a Community Management Statement or prior to issue of
Certificate of Classification/Final Inspection Certificate or prior to
commencement of use, whichever comes first (MCU or BW), or prior to Council's
notation of the plan of subdivision (ROL). |
As indicated |
48(a) Submit drawings for
Endorsement Submit and
obtain endorsement from Development Assessment, drainage plans and engineering
calculations, prepared by a Registered Professional Engineer of Queensland-
Civil, in accordance with the relevant Brisbane Planning Scheme Codes/Policies
showing the design of the stormwater infrastructure. |
As indicated |
48(b) Implement Endorsed
Drawings Construct and
maintain the works in accordance with the endorsed engineering drawings. |
As indicated |
48(c) Submit As Constructed
Plans Submit
"As Constructed" plans prepared by a Registered Professional Engineer
|
As indicated |
| 49) Remove Redundant Drainage Outlets Remove any redundant drainage outlets from the
kerb and channel including any associated pipe work across the footway and
reinstate the kerb and channel and the footway area in accordance with the
relevant Brisbane Planning Scheme Codes/Policies. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 50) Ponding of stormwater Adjoining
properties and roads are to be protected from ponding
or nuisance from stormwater as a result of the works. Ensure the stormwater runoff from the site does not
adversely impact on flooding or drainage (peak discharge and duration for all
events up to the 100 year Average Recurrence Interval (ARI)) of properties that
are upstream, downstream or adjacent to the site. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
| 51) Service Conduits and Mains Supply and install all service conduits and meet the cost of any
alterations to public utility mains, existing mains, services or installations
required in connection with the approved development in accordance with the
relevant Brisbane Planning Scheme Codes/Policies. This includes: Note. Applicants
should liaise with the appropriate service authorities. Typical underground
services and/or conduits to be constructed include power, phone,
telecommunications, sewer, stormwater and gas if
applicable. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
51(a) As Constructed Drawings Submit to Development Assessment "As Constructed" drawings including an asset register, approved by a Registered Professional Engineer Queensland that are in accordance with the relevant Brisbane Planning Scheme Codes/Policies, and any other relevant infrastructure requirements, showing the works required by this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 52) Telecommunications Enter into an agreement with a telecommunication carrier to provide underground telecommunication services within and adjacent to the proposed development in accordance with the relevant Brisbane Planning Scheme Codes/Policies. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 53) Agreement with Electricity Supplier Enter into an agreement with an electricity
supplier to provide necessary services to the development in accordance with
the relevant Brisbane Planning Scheme Codes/Policies. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 54) Construct Permanent Vehicle Crossover Provide a 10.6 metre wide Type B1 permanent
vehicular crossover to the Bank St frontage of the site in accordance with the
relevant Brisbane Planning Scheme Codes/Policies and Standard Drawings and
located as shown on the approved drawings. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 55) Remove Redundant Crossover Remove the existing vehicular crossing(s) on the
frontage(s) of the site and reinstate the kerb and channel, road pavement,
footways and footpaths in accordance with the relevant Brisbane Planning Scheme
Codes/Policies. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 56) Natural Light and Ventilation The assessment of the development application has not considered whether the provision of natural light and ventilation to habitable rooms in the building, satisfies the requirements of the Building Code of Australia. |
As indicated |
| 57) Cultural Heritage Aboriginal cultural heritage
is protected under the Aboriginal
Cultural Heritage Act 2003. It is an offence for a person or corporation to
damage or destroy cultural heritage. The duty of care provisions are outlined
in Section 28 - Duty of Care
Guidelines of the Aboriginal
Cultural Heritage Act 2003. It is the responsibility of the
person/corporation carrying out the development approval to follow these duty of care provisions in relation to protection of
Aboriginal cultural heritage. |
As indicated |
| 58) Contaminated Land Pursuant to the Environmental Protection Act 1994 in
relation to Contaminated Land, if the owner or occupier of land becomes aware a
notifiable activity is being carried out on the land,
the owner or occupier must, within 22 business days after becoming aware the
activity is being carried out, give notice to the relevant State administering
authority in the approved form. |
As indicated |
| 59) Construction Noise and Dust Emissions Pursuant to the Environmental Protection Act 1994, all development involving the
emission of noise and dust from building and/or construction activities, must
ensure that the emission are accordance with the requirements of the Act. |
As indicated |
| 60) Equitable Access Provision must be made for equitable access for persons with disabilities to and within the site in accordance with the Queensland Anti- Discrimination Act 1991, the Federal Disability Discrimination Act 1992 and Australian Standard AS1428 Parts 1-4, Australian Standard for Access and Mobility and the Building Code of Australia Access Code. |
As indicated |
| 61) Construct Sewer Construct Trunk Sewer
Infrastructure Construct either Option 1 or
Option 2 Option
1 Replace the existing
150mm diameter sewer in This condition for trunk infrastructure has been applied in accordance with the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009 s99BRCR as the item is not identified in the Queensland Urban Utilities schedule of works. This is identified as a trunk infrastructure and is offsetable against the sewerage component of the infrastructure charges for the development.
Option 2
Construct a DN250mm
diversion sewer from manhole (MH172616) in This condition for trunk infrastructure has been applied in accordance with the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009 s99BRCR as the item is not identified in the Queensland Urban Utilities schedule of works. This is identified as a trunk infrastructure and is offsetable against the sewerage component of the infrastructure charges for the development GUIDELINE This condition has been imposed to ensure that sewerage infrastructure is in place to serve the development. This condition has been imposed on behalf of Central SEQ Distribution - Retailer Authority, Queensland Urban Utilities, under the delegated concurrence agency agreement. For any enquiries about this condition, please contact the Water and Sewerage Assessment Team, Development Assessment. PROOF OF FULFILMENT Work constructed and accepted on maintenance / off maintenance. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
61(a) Submit Plans Submit
engineering plans in accordance with the current Central SEQ Distribution -
Retailer Authority, Queensland Urban Utilities Incorporating WSAA Standards
(formerly BCC Standards) showing the design of the works. GUIDELINE This condition is imposed to ensure that the required works are designed in accordance with this development permit and relevant standards. This condition has been imposed on behalf of Central SEQ Distribution - Retailer Authority, Queensland Urban Utilities, under the delegated concurrence agency agreement. For any enquiries about this condition, please contact the Water and Sewerage Assessment Team, Development Assessment. PROOF OF FULFILMENT Plans checked and certified by a Registered Professional Engineer of Queensland (RPEQ) and endorsed by the Delegate, Development Assessment. |
As indicated |
61(b) Implement Approved Plans Construct the works in accordance with the endorsed engineering
plans and the current Central SEQ Distribution - Retailer Authority, Queensland
Urban Utilities (QUU) Incorporating WSAA Standards (formerly BCC
Standards). GUIDELINE This condition is imposed to ensure that the required works are carried out in accordance with this development permit, relevant standards and endorsed plans. This condition has been imposed on behalf of Central SEQ Distribution - Retailer Authority, Queensland Urban Utilities, under the delegated concurrence agency agreement. For any enquiries about this condition, please contact the Water and Sewerage Assessment Team, Development Assessment. PROOF OF FULFILMENT Plans checked and certified by a Registered Professional Engineer of Queensland (RPEQ) and endorsed by the Delegate, Development Assessment. |
As indicated |
61(c) Submit As Constructed Drawings and
Supporting Documentation Submit As Constructed plans certified by a
Registered Professional Engineer Queensland-Civil (RPEQ-Civil), that are a true
record of the constructed works and are in accordance with the endorsed plans,
approved modifications and in accordance with the current Central SEQ
Distribution - Retailer Authority, Queensland Urban Utilities Incorporating
WSAA Standards (formerly BCC Standards). GUIDELINE This condition has been imposed to ensure the works have been constructed to the correct standard and that an accurate record of the works has been provided. This condition has been imposed on behalf of Central SEQ Distribution - Retailer Authority, Queensland Urban Utilities, under the delegated concurrence agency agreement. For any enquiries about this condition, please contact the Water and Sewerage Assessment Team, Development Assessment. PROOF OF FULFILMENT Documents submitted and accepted by the Delegate, Development Assessment |
As indicated |
| 62) Grant Easements Grant the following easement(s) for water supply or sewerage purposes. i. Easements for access, construction and maintenance to and over sewerage gravity manholes in the development lot, in favour of Central SEQ Distribution - Retailer Authority, Queensland Urban Utilities (QUU). Notes. Queensland Urban Utilities will require 1.000 metre access easement running from the street frontage, alongside the property boundary, to the maintenance structure or manhole in the back yard. Maintenance structures or manholes are to be located in a 2.000 x 3.000 metre easement connected to the access easement. -
Easements in favour of QUU
are required to have the
necessary easement documentation prepared (free of costs and compensation to
QUU) by
QUU. -  
;
Easements not in favour of the QUU are required to have
the necessary documentation prepared by the applicant's private
solicitors. -
Easements are to be shown on a Survey Plan
and lodged with the Delegate Plan Sealing, Licensing Sealing and Certificates
Unit. GUIDELINE This condition is imposed to ensure that access is provided for the construction and maintenance of QUU infrastructure and services, or that access is provided to QUU infrastructure. Enquiries regarding any legal documentation can be directed to Licensing, Sealing and Certificates Unit, Development Assessment. For any enquiries about this condition, please contact the Water and Sewerage Assessment Team, Development Assessment. PROOF OF FULFILMENT Registration of the easement on the plan of survey and on the property title with the Department of Natural Resources. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 63) Provide / Extend Sewerage Connection(s) - Minor
(MCU) Provide a sewer property connection to serve the
development designed and constructed in accordance with endorsed engineering
plans and the current Central SEQ Distribution - Retailer Authority, Queensland
Urban Utilities (QUU) Design and Construction Standards.
|
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 64) General Requirements for Water and Sewerage
Works The following requirements may apply
to this development. It is the developer’s responsibility to determine
where these requirements apply, and meet the cost of any resulting
works. 1)
Construct and/or alter public utilities mains, existing water and
sewerage mains, services or installations required in connection with the
approved development in accordance with the current Central SEQ Distribution -
Retailer Authority, Queensland Urban Utilities Design and Construction
Standards. This includes the
relocation of any water meter, fire hydrant, scours and/or valves and sewer
connections from within the limits of the development's vehicular footway
crossings. 2) Where an
existing sewerage property connection is located under a driveway (in the road
reserve) and is unable to be relocated, a 1m x 1m removable slab with suitable
lifting arrangements is to be located centrally over the connection with the
Delegate’s, Development Assessment written
agreement. 3)
Where existing or new sewerage property connections
will be located under reinforced concrete slabs on private property, a 1m x 1m
removable slab with suitable lifting arrangements is to be located centrally
over the connection with the Delegate’s, Development Assessment written
agreement. 4)
Where existing sewerage
maintenance holes do not have the current standard top slab, cover and frame,
or there are changes to the surface levels or there are changes to the loading
conditions, the maintenance holes are to be modified in accordance with the
current Central SEQ
Distribution - Retailer Authority, Queensland Urban Utilities Design and
Construction Standards. 5)
Existing water mains and sewers are to be relocated
or raised/lowered to the current Central SEQ Distribution - Retailer Authority, Queensland Urban
Utilities Design and Construction Standards, if development related works change the depth of cover on these
works. 6)
Where a new road opening or widening is required
and an existing water main is located in the footpath which will become new
roadway, the existing main is to be relocated clear of
the proposed carriage way to the depth specified in the current Central SEQ Distribution - Retailer
Authority, Queensland Urban Utilities Design and Construction
Standards. 7)
Clear, unobstructed, 24 hour access from the street frontage is
to be maintained to any sewerage maintenance holes and property connections, on
the development site. 8)
Where the property is encumbered by a combined drain, replacement
of the existing combined drain may be a requirement of the plumbing Approval.
It is recommended that contact be made with the Plumbing Services Group to
determine any requirements. 9) Where a building is demolished on a
site the existing sewer property connection is to be sealed and capped. The
existing water service and meter is to be sealed off and removed if not
required for the future development of the site. 10)
Where a dwelling is located in a declared sewered area then the dwelling is to be provided with an
individual water service and meter and sewerage property
connection. GUIDELINE This condition is imposed to ensure that water and sewer infrastructure is accessible, is protected and can be operated and maintained. The condition also ensures footpaths are kept in a safe condition. This condition has been imposed on behalf of Central SEQ Distribution - Retailer Authority, Queensland Urban Utilities, under the delegated concurrence agency agreement. For any enquiries about this condition, please contact the Water and Sewerage Assessment Team, Development Assessment. PROOF OF FULFILMENT Requirements of this condition are complied with to the satisfaction of the Delegate, Development assessment. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
| 65) Service, Meter Assembly and Meter Box - Minor
(MCU) Provide a water service with approved meter assembly
and meter box to the front real property boundary of the development and a
water sub meter to each lot or tenement in the development, in accordance with
the current Central SEQ Distribution - Retailer Authority, Queensland Urban
Utilities (QUU) Design and Construction Standards and an approved QUU water
sizing. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |