| Address of Site: | 621 GYMPIE RD CHERMSIDE QLD 4032 621 GYMPIE RD CHERMSIDE QLD 4032 |
| Real Property Description of Site: | L100 SP.328508 |
| Aspects of development and type of approval: | DA - PA - Material Change of Use Development Permit - indoor sport and
recreation |
| Council File Reference: | A006967148 Permit Reference Number/s: DAMC473712526. |
| Package Status: | APPROVED - Version 1 (12th of June, 2026 8:12:20 AM) |
| Package Generated: | 12/06/2026 |
| Abby BANNAN Urban Planner Planning Services North Abby.Bannan@brisbane.qld.gov.au 31782418 |
Ben CLOTHIER Team Manager (Acting) Planning Services House & Homes Ben.Clothier@brisbane.qld.gov.au (07) 3403 7185 |
Jeremy FARROW Urban Planner Trunk Infrastructure & Calculations Jeremy.Farrow@brisbane.qld.gov.au |
| Katrina KONTOS Environmental Management Officer Environmental Management Services katrina.s.kontos@brisbane.qld.gov.au (07) 3403 8888 |
Biraj DANGOLE Principal Engineering Officer Engineering Services North Biraj.Dangole@brisbane.qld.gov.au (07) 3178 2607 |
Ben COVE Principal Engineer Engineering Services Traffic Ben.Cove@brisbane.qld.gov.au |
| Michael PICKERILL Network Planning Michael.Pickerill@brisbane.qld.gov.au |
John GRIMSEY Built Environment Officer WaRRS Assessment john.grimsey@brisbane.qld.gov.au 34071331 |
Dominic PERRY Senior Engineer Engineering Scoping dominic.perry@brisbane.qld.gov.au (07) 3403 8888 |
| Dalina HOWDEN Senior Urban Planner Trunk Infrastructure & Calculations dalina.howden@brisbane.qld.gov.au (07) 3178 3895 |
DRAWINGS AND DOCUMENTS
| Drawing or Document | Number | Plan Date |
|---|---|---|
| Site Plan | 02 | 19-FEB-2026 (Received) |
| Floor Plan - Ground | 6214.1W.A204 Rev 21 (Amended In Red 27-MAY-2026) | 25-MAR-2026 (Received) |
| Furnished Floor Plan | 03 | 19-FEB-2026 (Received) |
APPROVAL CONDITIONS
| Permit to Which These Conditions Relate: | DA - PA - Material Change of Use |
| Activity(ies): | indoor sport and recreation |
| Stage: | Indoor Sport and Recreation |
| 1) Maintain the Approved Development Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions. |
At all times |
| 2) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers. Note: This condition is imposed to ensure compliance with the conditions of development approval. |
While site/operational/building work is occurring |
| 3) Carry Out the Approved Development Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS. Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners. |
While site/operational/building work is occurring |
| 4) Complete All Building Work Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS. Note: Building work must also be completed in accordance with any other current development approval. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 5) Hours of Operation Hours of operation for the approved Indoor Sport and Recreation use must be in accordance with the following: - 5:15AM to 10:45PM |
At all times |
| 6) Protect Existing Infrastructure Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure. Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations. The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements. |
While site/operational/building work is occurring |
6(a) As Constructed Drawings - Alterations to
Existing Infrastructure Submit to Development Services As Constructed drawings showing all new and/or rectification works and an asset register, prepared by a Registered Professional Engineer Queensland. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 7) Repair Damage to Kerb, Footpath or Road Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
7(a) Interim Repairs If at any time during the construction phase of the approved development, damage to the existing kerb and channel, footpath or roadway creates unsafe, unreasonable and/or not fit for purpose conditions as assessed by Council, interim repairs must be undertaken as directed by Program Planning and Integration. Note: Any interim repairs required to be undertaken shall not be considered to satisfy the requirements of this condition for the permanent repair of the infrastructure prior to the issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. Timing: While site / operational / building works is occurring. |
As indicated |
| 8) Construction Noise and Dust Emissions Pursuant to the
Environmental Protection Act 1994, all development involving the emission of
noise and dust from building and/or construction activities, must ensure that
the emissions are in accordance with the requirements of the Act. |
As indicated |
| 9) Further Development Permit Required Further Development Permit(s) to carry out assessable building work under the Building Act may be required. |
As indicated |
| 10) Plumbing and Drainage Work Pursuant to the Plumbing and Drainage Act 2018, any plumbing and drainage work must be carried out in compliance with the Plumbing and Drainage Regulation 2019. Note: All new and existing plumbing services should be located within the lot that they serve. Compliance assessable plumbing and drainage work requires approval by Brisbane City Council prior to the work being carried out. |
As indicated |
| 11) Currency Period The currency period for this development approval is stated in the Decision Notice and is expressed as a date. This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016. |
As indicated |
| 12) Referral Agency Requirements SARA as Concurrence agency has not imposed any requirements, as detailed in the letter dated 28th April 2026. |
As indicated |
| 13) Water and Wastewater Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. For further information about any necessary Water Approvals contact Urban Utilities. |
As indicated |