BRISBANE CITY COUNCIL'S APPROVAL PACKAGE.



APPLICATION DETAILS

This package relates to the application detailed below
Address of Site: 621 GYMPIE RD CHERMSIDE QLD 4032
621 GYMPIE RD CHERMSIDE QLD 4032
Real Property Description of Site:
L100 SP.328508
Aspects of development and type of approval: DA - PA - Material Change of Use Development Permit - indoor sport and recreation
Council File Reference: A006967148
Permit Reference Number/s: DAMC473712526.
Package Status: APPROVED - Version 1 (12th of June, 2026 8:12:20 AM)
Package Generated: 12/06/2026


PROJECT TEAM

The assessment of this application has been undertaken by:
Abby BANNAN
Urban Planner
Planning Services North
Abby.Bannan@brisbane.qld.gov.au
31782418
Ben CLOTHIER
Team Manager (Acting)
Planning Services House & Homes
Ben.Clothier@brisbane.qld.gov.au
(07) 3403 7185
Jeremy FARROW
Urban Planner
Trunk Infrastructure & Calculations
Jeremy.Farrow@brisbane.qld.gov.au
Katrina KONTOS
Environmental Management Officer
Environmental Management Services
katrina.s.kontos@brisbane.qld.gov.au
(07) 3403 8888
Biraj DANGOLE
Principal Engineering Officer
Engineering Services North
Biraj.Dangole@brisbane.qld.gov.au
(07) 3178 2607
Ben COVE
Principal Engineer
Engineering Services Traffic
Ben.Cove@brisbane.qld.gov.au
Michael PICKERILL

Network Planning
Michael.Pickerill@brisbane.qld.gov.au
John GRIMSEY
Built Environment Officer
WaRRS Assessment
john.grimsey@brisbane.qld.gov.au
34071331
Dominic PERRY
Senior Engineer
Engineering Scoping
dominic.perry@brisbane.qld.gov.au
(07) 3403 8888
Dalina HOWDEN
Senior Urban Planner
Trunk Infrastructure & Calculations
dalina.howden@brisbane.qld.gov.au
(07) 3178 3895


DRAWINGS AND DOCUMENTS



The term 'drawings and documents' or similar expressions mean:
Drawing or Document Number Plan Date
Site Plan 02 19-FEB-2026 (Received)
Floor Plan - Ground 6214.1W.A204 Rev 21 (Amended In Red 27-MAY-2026) 25-MAR-2026 (Received)
Furnished Floor Plan 03 19-FEB-2026 (Received)


Advice

Please see the attached document(s) for any advices.

APPROVAL CONDITIONS



Permit to Which These Conditions Relate: DA - PA - Material Change of Use
Activity(ies): indoor sport and recreation
Stage: Indoor Sport and Recreation

General/Planning Requirements
 
Timing
1)   Maintain the Approved Development

Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions.

 
At all times
 
2)   Approved Drawings and Documents

A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers.

Note: This condition is imposed to ensure compliance with the conditions of development approval.

 
While site/operational/building work is occurring
 
3)   Carry Out the Approved Development

Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS.

Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners.

 
While site/operational/building work is occurring
 
4)   Complete All Building Work

Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS.

Note: Building work must also be completed in accordance with any other current development approval.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
Pollution
 
Timing
5)   Hours of Operation

Hours of operation for the approved Indoor Sport and Recreation use must be in accordance with the following:

- 5:15AM to 10:45PM

 
At all times
 
Engineering
 
Timing
6)   Protect Existing Infrastructure

Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure.

Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations.

The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements.

 
While site/operational/building work is occurring
6(a) As Constructed Drawings - Alterations to Existing Infrastructure

Submit to Development Services As Constructed drawings showing all new and/or rectification works and an asset register, prepared by a Registered Professional Engineer Queensland.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

PROOF OF FULFILMENT
Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
7)   Repair Damage to Kerb, Footpath or Road

Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
7(a) Interim Repairs

If at any time during the construction phase of the approved development, damage to the existing kerb and channel, footpath or roadway creates unsafe, unreasonable and/or not fit for purpose conditions as assessed by Council, interim repairs must be undertaken as directed by Program Planning and Integration.

Note: Any interim repairs required to be undertaken shall not be considered to satisfy the requirements of this condition for the permanent repair of the infrastructure prior to the issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

Timing: While site / operational / building works is occurring.

 
As indicated
 
Standard Advice
 
Timing
8)   Construction Noise and Dust Emissions

Pursuant to the Environmental Protection Act 1994, all development involving the emission of noise and dust from building and/or construction activities, must ensure that the emissions are in accordance with the requirements of the Act.
The Environmental Protection Act 1994 prescribes that:

1. A person must not carry out building work in a way that makes an audible noise-
-  on a business day or Saturday, before 6.30a.m. or after 6.30p.m; or
-   on any other day, at any time. 
2. The reference in subsection (1) to a person carrying out building work-
-  includes a person carrying out building work under an owner-builder permit; and
-  otherwise does not include a person carrying out building work at premises used by the person only for residential purposes.

Note: A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management delegate Development Services.

 
As indicated
 
9)   Further Development Permit Required

Further Development Permit(s) to carry out assessable building work under the Building Act may be required.

 
As indicated
 
10)   Plumbing and Drainage Work

Pursuant to the Plumbing and Drainage Act 2018, any plumbing and drainage work must be carried out in compliance with the Plumbing and Drainage Regulation 2019.

Note: All new and existing plumbing services should be located within the lot that they serve.

Compliance assessable plumbing and drainage work requires approval by Brisbane City Council prior to the work being carried out.

 
As indicated
 
11)   Currency Period

The currency period for this development approval is stated in the Decision Notice and is expressed as a date.

This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016.

 
As indicated
 
12)   Referral Agency Requirements

SARA as Concurrence agency has not imposed any requirements, as detailed in the letter dated 28th April 2026.

 
As indicated
 
13)   Water and Wastewater

Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009.

For further information about any necessary Water Approvals contact Urban Utilities.

 
As indicated
 

** End of Package **