| Address of Site: | 25 GOLDEN CREST PL BELLBOWRIE QLD 4070 25 GOLDEN CREST PL BELLBOWRIE QLD 4070 U 1 HILLTOP PLACE BELLBOWRIE 25 GOLDEN CREST PL BELLBOWRIE QLD 4070 U 2 HILLTOP PLACE BELLBOWRIE 25 GOLDEN CREST PL BELLBOWRIE QLD 4070 |
| Real Property Description of Site: | L3 SP.167682 LCommon Property SP.192478 L1 SP.192478 L2 SP.192478 |
| Aspects of development and type of approval: | DA - IPA - Material Change of Use Development Permit - Multi-Unit
Dwelling |
| Council File Reference: | A006976435 Permit Reference Number/s: DAMC167259707. |
| Package Status: | APPROVED - Version 2 (14th of May, 2026 8:49:55 AM) |
| Package Generated: | 14/05/2026 |
| MARIA LOCKLEY DA West BSQ (07) 3407 0102 |
KATHY BAGULEY DA West BSQ (07) 3407 0164 |
DAVID WILLIAMS DA West BSQ 34070142 |
| Luke HADRICK Urban Planner Planning Services North Luke.Hadrick@brisbane.qld.gov.au (07) 3178 9403 |
Rhea CONNOLLY Principal Urban Planner Planning Services North Rhea.Connolly@brisbane.qld.gov.au 3178 0651 |
Joe MCSHANE Principal Urban Planner Planning Services North CPAS-DS-PS-North@brisbane.qld.gov.au (07) 3407 1306 |
DRAWINGS AND DOCUMENTS
| Drawing or Document | Number | Plan Date |
|---|---|---|
| Site Plan | DA01 (Amended In Red 13-MAY-2026) | 03-MAR-2026 (Received) |
| Front Elevation | DA02 (Amended In Red 13-MAY-2026) | 03-MAR-2026 (Received) |
| Left Elevation | DA03 (Amended In Red 13-MAY-2026) | 03-MAR-2026 (Received) |
| Column Locations | DA04 (Amended In Red 13-MAY-2026) | 03-MAR-2026 (Received) |
| Floor Plan / Package: 1 | 19481 | 26-JUL-2005 |
| Elevations / Package: 1 | 19481-2 | 26-JUL-2005 |
| Landscape Intent Plan / Package: 1 | P328-01 | 26-JUL-2005 |
| Contour and Feature Survey / Package: 1 | 05-00176 (RV A) (Amended In Red 05-OCT-2005) | 26-JUL-2005 |
APPROVAL CONDITIONS
| Permit to Which These Conditions Relate: | DA - IPA - Material Change of Use |
| Activity(ies): | Multi-Unit Dwelling |
| Stage: | Multi Unit Dwelling - 2 units |
| 1) Time for Completion of Development The works authorised by this change application are
limited to a patio roof structure attached to Unit 2 also described as Lot 2 on
SP192478 (Council address) as shown on approved DRAWINGS and DOCUMENTS. The
works must be completed within 2 years of this change application taking
effect. All previous plans of development approval
DRS/USE/H05-919110 (A001758006) remain applicable unless modified by
this approval. Note: If the development is started but not completed within the time specified above, the approval (to the extent it relates to any development not completed) lapses. |
As indicated |
| 2) COPY OF PLANS ON SITE A legible copy of the approved drawings and documents bearing "Council Approval" and the Development Approval Conditions package is to be available on site at all times during construction and earthworks. GUIDELINE This condition is imposed to ensure compliance with the development conditions of approval. The copy of the conditions and plans should be located in any site management office or with the site foreman. Any copies of conditions or plans that are illegible shall be deemed to be non compliance with this condition of approval. |
As indicated |
| 3) CURRENCY PERIOD FOR APPROVAL The currency period for this approval is 48 months. GUIDELINE This condition is imposed where the currency period for the development approval is other than as is specified in s.3.5.21 of the Integrated Planning Act. |
As indicated |
| 4) CARRY OUT THE APPROVED DEVELOPMENT Carry out the approved development generally in accordance with the approved drawing(s) and/or document(s). GUIDELINE This condition refers to the approved plans, drawings and documents to which the approval relates and is the primary means of defining the extent of the approval. Approved plans, drawings and documents are stamped PLANS and DOCUMENTS referred to in the APPROVAL and are dated to reflect the date of approval of the application by Council's Delegate. |
While development is occurring on the site and then to be maintained |
| 5) COMPLETE ALL BUILDING WORK Complete all building work associated with this development approval, including work required by any of the following conditions. Such building work is to be carried out generally in accordance with the approved plans, drawing(s), and/or documents and, where the building work is assessable development, in accordance with a current development permit. GUIDELINE This condition is imposed to ensure all building work associated with the use are in place before the use commences. It is not appropriate that the site be used without such work being completed. Please note that the work referred to in this condition involves operational work and may therefore constitute 'assessable development'. The Council informs you there fore that this condition does not authorise assessable development to occur and a development permit may therefore be necessary. Please refer to the Council's information sheets. For any enquiries about this condition, please contact the Assessment Manager. |
Prior to commencement of use |
| 6) COMPLETE ALL OPERATIONAL WORK Complete all operational work associated with this development approval, including work required by any of the following conditions. Such operational work is to be carried out generally in accordance with the approved plans, drawing(s), and/or documents or, if requiring a further approval from the Council, in accordance with the relevent approval(s). GUIDELINE This condition is imposed to ensure all operational works associated with the use are completed before the use commences. It is not appropriate that the site be used without such work being completed in accordance with any detailed design approvals. Please note that the work referred to in this condition involves operational work and may therefore constitute 'assessable development'. The Council informs you there fore that this condition does not authorise assessable development to occur and a development permit may therefore be necessary. Please refer to the Council's information sheets. For any enquiries about this condition, please contact the Assessment Manager. |
Prior to commencement of use |
| 7) MAINTAIN THE APPROVED DEVELOPMENT Maintain the approved development (including landscaping, parking, driveways and other external spaces) in accordance with the approved drawing(s) and/or documents, and any relevant Council engineering or other approval required by the conditions. GUIDELINE This condition restricts changes that can be made to the approved development. Approved plans and documents are stamped PLANS and DOCUMENTS referred to in the APPROVAL and are dated to reflect the date of determination of the application by the Council's delegate. The extent to which plans can be modified is constrained by the definition of 'minor change' in schedule 10 and the requirements of section 3.5.24 of the "Integrated Planning Act 1997". It will be necessary to make a new application if the change is not a minor change. For any enquires about this condition, please contact the Assessment Manager. |
To be maintained |
| 8) COMMUNITY MANAGEMENT STATEMENT Any Community Management Statement is to include the
following:
The communal open space areas, internal footpaths/pedestrian circulation routes, buffer landscaping,and visitor car park, as shown on the approved plans of layout shall form part of the common property and shall not be designated for the exclusive use of any unit. GUIDELINE This condition is imposed to ensure the ongoing operation, appearance and maintenance of the development under a Community Management Statement is in accordance with the development permit and the approved plans and documents. For any enquiries about this condition, please contact the Assessment Manager. |
As indicated |
8(a) COMMUNITY MANAGEMENT
STATEMENT The 1 visitor parking space (1 space as shown on the Contour and Feature Survey Plan and located in front of unit 2) and driveway area indicated on the approved plans of layout shall form part of the common property and shall not be designated for the exclusive use of any unit and available for use by all tenants and where relevant, all visitors. |
As indicated |
8(b) COMMUNITY MANAGEMENT
STATEMENT Screening for any externally mounted airconditioning or
mechanical plant installations in accordance with the following
requirements: |
As indicated |
8(c) COMMUNITY MANAGEMENT
STATEMENT External sun control devices to all western facing windows,
such devices shall meet the following requirements: (ii) The devices are to be constructed from materials
complimentary to those of the building; and |
As indicated |
8(d) COMMUNITY MANAGEMENT
STATEMENT Air conditioning and/or mechanical ventilation must be provided and maintained to all sleeping and living areas of residential dwellings affected by road traffic, mechanical plant, where noise attenuation measures assumes windows and doors to be closed to achieve designed noise levels; |
As indicated |
8(e) COMMUNITY MANAGEMENT
STATEMENT No gates, roller-doors or other barriers are to be installed at the entrance point to the site preventing unfettered access to the designated visitor car parking spaces. |
As indicated |
8(f) COMMUNITY MANAGEMENT
STATEMENT All sealed traffic areas must be cleaned as necessary to prevent emissions of particulate matter. |
As indicated |
8(g) COMMUNITY MANAGEMENT
STATEMENT Any Community Management Statement is to contain by-laws which reflect the requirements in this condition. |
As indicated |
8(h) COMMUNITY MANAGEMENT
STATEMENT Any potential purchasers are to be advised of the above requirements prior to purchase of any unit. |
As indicated |
| 9) LIGHTING TO PUBLIC AREAS Install and maintain a suitable system of lighting, to operate
from dusk to dawn, within all areas where the public will be given
access. GUIDELINE This condition is imposed to ensure on-going safe public access to designated public pedestrian spaces within the development |
Prior to the commencement of the use and then to be maintained |
| 10) Original conditions package The conditions and plans of the
original approval issued on 06 October 2005 under Council references
DRS/USE/H05-919110 remain applicable,
unless varied by this approval. |
To be maintained |
| 11) PAY OUTSTANDING CHARGES OR EXPENSES Pay to Council any outstanding charges or expenses levied by
the Council over the subject land. GUIDELINE This condition is imposed to ensure that there are no outstanding charges existing over the subject site, including outstanding rates. If there are out standing monies, they must be paid prior to commencement of the use. |
Prior to commencement of use |
| 12) SEWERAGE: PER ET (EQUIVALENT TENEMENT) Pay to Council a monetary contribution towards the cost of sewerage headworks, as outlined below, at the rate prevailing when the contribution is paid.
The contribution is calculated on 2.05 ETs (Equivalent Tenement) at the current rate of $2,653 per ET, for Sewerage Scheme Charge Area - S6, WEKS01. The credit is calculated as 0.86 ET's. The amount payable is currently assessed at $3,179 and comprises of the following :
This headwork charge is the current rate for the 2004/2005 financial year.
GUIDELINE This condition is imposed to require the payment of a proportional contribution towards a satisfactory sewerage treatment system within the locality of the site. For any enquiries about this condition, please contact the Engineering Delegate, Development and Regulatory Services. |
Prior to the commencement of the use or prior to the endorsement of a Community Management Statement, whichever is sooner |
| 13) WATER SUPPLY: PER ET (EQUAVILENT TENEMENT) Pay to Council a monetary contribution towards the cost of water supply headworks, as outlined below, at the rate prevailing when the contribution is paid.
The contribution is calculated on 2.05 ETs (Equivalent Tenement) at the current rate of $3,139 per ET, for Water System Infrastructure Charges Plan Area - Mt Crosby North - W7. A credit of 0.86 ET has been applied. The amount payable is currently assessed at $3,761.78 and comprises of the following:
This headwork charge is the current rate for the 2004/2005 financial year. GUIDELINE This condition is imposed to require the payment of a proportional contribution towards a satisfactory water supply treatment system to the site. For any enquiries about this condition, please contact the Engineering Delegate, Development and Regulatory Services. |
Prior to the commencement of the use or prior to the endorsement of a Community Management Statement, whichever is sooner |
| 14) PARKLAND Pay to Council a monetary contribution towards the provision of parkland at the rate applicable at the time of payment. The amount is currently calculated at $18.00 per square metre of gross floor area. The required contribution currently totals $4,741.38. This park contribution is the current rate for the 2005/2006 financial year. GUIDELINE This condition is imposed when a monetary contribution for parkland is required. The contribution is calculated in accordance with Planning Scheme Policy 1 - Development Contributions for Parks and Recreational Facilities Arising from Subdivision of Land and from Material Change of Use or Development of Land. |
Prior to the commencement of the use or prior to the endorsement of a Community Management Statement, whichever is sooner |
| 15) FRONT FENCE Submit for the approval of the Team Leader Development Assessment, details including material and design, of a front fence which is to be constructed to either:
|
Prior to building work commencing |
| 16) SCREENING TO EXT. AIR CON. OR MECHANICAL
PLANT Provide screening for any externally mounted airconditioning or mechanical plant installations in accordance with the following requirements:
GUIDELINE This condition is imposed to ensure appropriate visual outcomes in relation to mechanical plant areas. For any enquiries about this condition, please contact the Development Assessment Team Architect. |
Prior to the commencement of the use and then to be maintained |
| 17) SOLAR SCREENING Provide solar screening to all western facing windows, to include a vertical screening element with a maximum opening of 30mm beteen pickets or battens and positioned in conjunction with a window hood. GUIDELINE This condition is imposed to ensure an appropriate level of climatic control to provide a comfortable internal living environment. For any enquiries about this condition, please contact the Development Assessment Team Architect. |
Prior to the commencement of the use and then to be maintained |
| 18) DRIVEWAY MATERIAL & FINISHES Provide materials and finishes to the driveway and external carparking surfaces which reduce the visual impact of these areas when viewed from the street. In order to achieve this outcome, one or a combination of the following is to be used:
GUIDELINE This condition is imposed to ensure that the development is appropriate coloured and textured so as not to visually detract from the surrounding residential area. For any enquiries about this condition, please contact the Development Assessment Team Architect. |
Prior to the commencement of the use and then to be maintained |
| 19) EXTERNAL COLOURS AND FINISHES Provide variation in the external colours and finishes of the development in accordance with the following requirements:
GUIDELINE This condition is imposed to ensure that the development is appropriately coloured and textured so as not to visually detract from the surrounding residential area and to further reduce building bulk. For any enquiries about this condition, please contact the Development Assessment Team Architect. |
Prior to the commencement of the use and then to be maintained |
| 20) RESIDENTIAL DEVELOPMENT-CONSTRUCTED WITH
REQ'MENTS Construct and maintain the residential
development to include the following:
Erect a screen fence along the rear and side boundaries of the site. Unless an alternative design for the fence is agreed to with the owner of adjoining land, the screen fence is to be1.8 metres in height and be constructed from timber (Note, combined height of any retaining wall and fence is not to exceed 2.0m) GUIDELINE This condition is imposed on an approval for a dwelling house on a small lot to identify important design details of the dwelling or where these necessary design details are not indicated on the approved plans. |
Prior to the commencement of the use and then to be maintained |
20(a) RESIDENTIAL DEVELOPMENT-CONSTRUCTED
WITH REQ'MENTS Any proposed fencing along the Golden Crest alignment to be a maximum 1.5 metres in height and constructed of a semi-transparent design to allow surveillance between the street and the front yard. |
Prior to the commencement of the use and then to be maintained |
| 21) DETAILED PLAN-MUD Prepare
and landscape the site in accordance with a Landscape Management, Site Works
and Planting Plan.
Submit and receive approval by the Delegate, Development Assessment for a detailed Landscape Plan for all on-site landscape works identified on the approved plan(s) of layout P328-01, and 05-00176(RV A). The plan is to be prepared at a scale of 1:100 by a suitably qualified and experienced Landscape Architect/Designer, and must comply with the "Brisbane City Plan 2000- Landscaping Code". The plan should include the following: i) Siteworks:
ii) Planting:
GUIDELINE This condition is imposed when there is a landscape component to a High Level development application, and Council requires more details of the proposed landscape works. |
Prior to commencement of site works |
21(a) DETAILED PLAN-MUD Carry out the landscaping and associated works documented in the approved Landscape Management and Site Works Plan in accordance with standard Best Trade Practice. |
Prior to commencement of site works |
21(b) DETAILED PLAN-MUD Advise Council upon completion of the landscape works by completing the development details and Part B of the Compliance Certificate-Landscaping. |
Prior to commencement of site works |
| 22) ROAD NOISE SOUND LEVELS FOR RES. UNITS Design, construct and certify all proposed residential units
affected by road traffic in accordance with the recommended design sound levels
as specified below:
Design all proposed residential units affected by road traffic to achieve the relevant maximum recommended design sound levels specified in Australian Standard AS2107 "Acoustics - Recommended Design Sound Levels and Reverberation Times for Building Interiors" using the methods set out in Australian Standard AS3671- "Acoustics - Road Traffic Noise Intrusion Building Siting and Construction". GUIDELINE This condition is imposed where the achievement of acceptable noise levels is dependent on noise attenuation measures being implemented in the design and construction of the development. |
Prior to the commencement of the use and then to be maintained |
22(a) ROAD NOISE SOUND LEVELS FOR RES.
UNITS Construct all proposed residential units affected by road traffic in accordance with the approved design that achieves the relevant maximum recommended design sound levels specified in Australian Standard AS2107 "Acoustics - Recommended Design Sound Levels and Reverberation Times for Building Interiors" using the methods set out in Australian Standard AS3671- "Acoustics - Road Traffic Noise Intrusion Building Siting and Construction". |
Prior to the commencement of the use and then to be maintained |
| 23) ON SITE EROSION- MINOR WORK Minimise on-site erosion and the release of sediment or
sediment-laden stormwater from the site at all times.
Prepare an Erosion and Sediment Control (ESC) Management Plan for the site in accordance with Council's Best Practice Guidelines for the Control of Stormwater Pollution from Building Sites and accompanying fact sheets, Brisbane City Council and Gold Coast City Council, 2000 (or later version); GUIDELINE This condition is utilised where the potential for soil erosion, sediment loss from the site, and environmental impact on waterways is considered to be medium to low. Whilst not requiring submission of detailed information as defined in Council's "Erosion and Sediment Control Standard (Version 8 or later)", the ESC Management Plan must still satisfy the general requirements of this Standard (ie. minimise soil erosion and sediment loss from the site at all times during the works). No formal ESC Program is to be submitted for Council assessment however a copy of the ESC Management Plan is required on-site. Non-compliance may result in prosecution under Environmental Legislation. For any enquiries regarding this condition please contact the Engineering Delegate, Development and Regulatory Services. |
Prior to site works commencing (ie. any land-disturbing development) |
23(a) ON SITE EROSION- MINOR
WORK Implement and maintain on-site The ESC Management Plan for the duration of the operational or building works, and until exposed soil areas are permanently stabilised (e.g. turfed, concreted). The documented ESC Management Plan must be available on-site for inspection by Council Officers during these works. |
Prior to site works commencing (ie. any land-disturbing development) |
| 24) CUTTING/FILLING(MINOR) Undertake the works on the site in accordance with an
earthworks plan.
The plans are to include:-
GUIDELINE This condition is imposed for applications when minor earthworks are proposed in conjunction with a development proposal. For any enquiries about this condition, please contact the Engineering Delegate, Development and Regulatory Services. |
Prior to site works/building works commencing |
24(a) CUTTING/FILLING(MINOR) All fill material placed on the site comprising only natural earth and rock and is to be free of contaminants (as defined by section 11 of the Environmental Protection Act 1994), noxious, hazardous, deleterious and organic materials. No demolition material is to be used. Suitable fill material is deemed to comply with the requirements of clause 4.3, AS 3798, Guidelines on Earthworks for Commerial and Residential Developments. |
Prior to site works/building works commencing |
| 25) Protect Existing Infrastructure Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure. Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations. The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements. |
While site/operational/building work is occurring |
25(a) As Constructed Drawings - Alterations
to Existing Infrastructure Submit to Development Services As Constructed drawings showing all new and/or rectification works and an asset register, prepared by a Registered Professional Engineer Queensland. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 26) RETAINING WALLS Any retaining walls greater than 1.0 metre in height are required to be structurally certified for design and construction by a Registered Professional Engineer Queensland (RPEQ). The certification is to include the stormwater drainage (surface and seepage water) associated with the wall ensuring that the water is directed to an acceptable lawful and legal point of discharge and does not cause any ponding, nuisance or disturbance to adjacent property owners. All retaining walls are to comply with the City Plan Filling and Excavation Code. GUIDELINE This condition is intended to ensure that retaining walls associated with the development that are higher than 1 metre, are designed and constructed to industry standards and also, to ensure that no adverse impact is created by the structures on the surrounding properties. The retaining wall designer should note that timber retaining walls facing onto Council property (including the road reserve) will not be permitted. Retaining walls facing onto road reserve or parkland are to be contained entirely within the proposed development site, including the retaining wall's footings. Where retaining walls are proposed to be constructed between adjoining properties, it is also suggested that the use of timber sleeper retaining walls be restricted due to their limited life and the potential problems they may cause to future property owners. Where the combined height of the retaining wall and fence exceeds 2.0 metres, a Development Permit for Building Work will need to be granted. For any enquires about this condition please contact the Engineering Delegate, Development and Regulatory Services. |
Prior to commencement of use |
| 27) ACCESS, GRADES, MANOEUVRING, CARPARKS,
SIGNS, Construct and delineate or sign (as required)
the following requirements as indicated on the approved plan(s) of layout:
A pavement of minimum Type A standard and surface with an impervious material (including associated drainage) to the area on which motor vehicles will be driven and/or parked. {Construction of such pavement is to be certified by a Registered Professional Engineer of Queensland (RPEQ)}; GUIDELINE The "Brisbane City Plan 2000 - Transport, Access, Parking and Servicing Planning Policy" requires adequate on- site provision of parking, servicing and manoeuvring areas. This condition specifies detailed design requirements as indicated on the approved drawings and documents to which the approval relates. The assessment of the approved plans of layout has adequately considered these requirements. |
Prior to the commencement of the use and then to be maintained |
27(a) ACCESS, GRADES, MANOEUVRING, CARPARKS,
SIGNS, The driveways at grades shown on the approved plans and documents (or if not shown at grades not greater than those set out in "Brisbane City Plan 2000 - Transport, Access, Parking and Servicing Planning Policy"); |
Prior to the commencement of the use and then to be maintained |
27(b) ACCESS, GRADES, MANOEUVRING, CARPARKS,
SIGNS, Parking on the site for 4 cars (including 1 separate visitor space) and for the loading and unloading of vehicles within the site; |
Prior to the commencement of the use and then to be maintained |
27(c) ACCESS, GRADES, MANOEUVRING, CARPARKS,
SIGNS, No gates, roller doors or other barriers are to be installed at the entrance point to the site and to provide unfettered access to the designated visitor car parking space. |
Prior to the commencement of the use and then to be maintained |
| 28) REPAIR DAMAGE TO KERB, FOOTPATH OR ROAD Repair any damage to existing kerb and channel, footpath or
roadway (including removal of concrete slurry from footways, roads, kerb and
channel and stormwater gullies and drainlines) that may occur during any works
carried in association with the approved development. GUIDELINE The intention of this condition is to ensure that any works undertaken as part of the approved development do not damage Council assets or leave Council assets in an unacceptable and unsightly manner. For enquiries regarding this condition, please contact the Engineering Delegate, Development and Regulatory Services. |
Prior to commencement of use |
| 29) CONSTRUCT FOOTPATH Construct a paved footpath along the full length of the site
frontage(s).
Construct a 1.2 metre wide concrete footpath along the full length of the frontage(s) of the site to Golden Crest Place and in accordance with Council's "Subdivision and Development Guidelines". The design of the footpath works is to include any permanent safety signs, markings and devices (if required). GUIDELINE This condition requires works to be undertaken in the road reserve. The intention of the condition is to ensure that the adjoining footpaths are designed and constructed to a standard suited to the demands created by the approved development. For advise regarding alignment and levels of the proposed works and any other enquires about this condition, please contact the Engineering Delegate, Development and Regulatory Services. |
Prior to commencement of use |
29(a) CONSTRUCT FOOTPATH Construct the works to a standard that will be satisfactory to be accepted "on" and "off" maintenance" as a Council asset, by the Engineering Delegate, Development and Regulatory Services; and |
Prior to commencement of use |
29(b) CONSTRUCT FOOTPATH Submit "As Constructed" plans including an asset register, approved by a Registered Professional Engineer of Queensland (RPEQ) (to a standard specified in Council's "Subdivision and Development Guidelines") certifying that the works have been completed in accordance with the approved design and any approved modifications. |
Prior to commencement of use |
| 30) PROVIDE/EXTEND 150 MM SEWER CONNECTION(S) Provide a sewer property connection to serve the development
designed and constructed in accordance with approved engineering plans and
Council's "Water and Sewerage Reticulation Standards".
NB. The size of the connection shall be determined by the total number of
fixture units.
Submit engineering plans prepared by a Registered Professional Engineer Queensland (RPEQ), and in accordance with Council's "Water and Sewerage Reticulation Standards" showing the design the works. Obtain the approval from the Engineering Delegate, Development Assessment, Development and Regulatory Services; GUIDELINE This condition is imposed to provide a separate new sewerage connection to the development. For enquiries regarding this condition, please contact the Engineering Delegate, Development and Regulatory Services. |
Prior to undertaking the works |
30(a) PROVIDE/EXTEND 150 MM SEWER
CONNECTION(S) Pay to Council the cost of live connection to the sewer main; |
Prior to undertaking the works |
30(b) PROVIDE/EXTEND 150 MM SEWER
CONNECTION(S) Construct the works in accordance with the approved engineering plans to a standard that will be satisfactory to be accepted "on" and "off" maintenance as a Council asset, by the Engineering Delegate, Development and Regulatory Services; |
Prior to undertaking the works |
30(c) PROVIDE/EXTEND 150 MM SEWER
CONNECTION(S) Submit "As Constructed" plans including an assest register, approved by a Registered Professional Engineer Queensland (RPEQ) (to a standard specified in Council's "Water and Sewerage Reticulation Standards") certifying that the works have been completed in accordance the approved design and any approved modifications. |
Prior to undertaking the works |
| 31) BOS (BUILD OVER SEWER) Obtain written permission from the Engineering Delegate, Development and Regulatory Services, to build over or near sewer infrastructure, or to relocate the sewer/sewer infrastructure at no cost to Council. GUIDELINE This condition is imposed so that the council does not incur costs associated with the erection of a building or structure over or near a sewer and/or sewer infrastructure. To avoid unnecessary expense and delay, the Council strongly recommends that the developer apply for permission to "Build Over Sewer" prior to the lodgement of any further development applications. For any enquiries regarding this condition, please contact the Delegate, Development and Regulatory services. |
Prior to lodging an application for Building Works |
| 32) CONNECT TO EXISTING SEWER Connect the proposed development to the new connections within the site and ensure that all private plumbing and drainage is located within the lot it serves. An application is required to be lodged with the Principal Plumbing Officer, Plumbing Services, and approval obtained prior to the above sewer work. GUIDELINE This condition is imposed to re-connect the existing house drains to the new sewer connection within the lot. For enquiries regarding this condition, please contact the Engineering Delegate, Development and Regulatory Services. |
Prior to commencement of use |
| 33) BONSW (BUILD OVER NEAR STORMWATER) Obtain written permission from Council to build over or near
storm water infrastructure (pipe drainage system or an easement for overland
flow), or, to relocate a storm water drainage system, all at no cost to
Council.
Submit engineering plans and calculations (if required), prepared by a Registered Professional Engineer Qld (RPEQ) and in accordance Council's "Guidelines for Building Over or Near Stormwater Facilities" in the "Subdivision and Development Guidelines" showning the manner in which it is intended to preserve the existing storm water drainage structures (or overland flow easements) within the site from damage, structural loading or obstruction. Obtain approval for the design from the Engineering Delegate, Development Assessment, Development and Regulatory Services. GUIDELINE This condition has been imposed to ensure that acceptable measures will be incorporated into the development to protect Council's Infrastructure. For any enquiries about this condition, please contact Council's Customer Contact Centre on ph. 3403 8888. |
Prior to lodging an application for Building Works |
33(a) BONSW (BUILD OVER NEAR
STORMWATER) Complete the works in accordance with the approved engineering plans. |
Prior to lodging an application for Building Works |
33(b) BONSW (BUILD OVER NEAR
STORMWATER) Submit "As Constructed" plans including an asset register (if required) of any modified or relocated stormwater drainage structure or other Council asset. The plans are to be approved by a Registered Professional Engineer of Queensland (RPEQ) (to a standard specified in Council's "Subdivision and Development Guidelines") and certified that the works have been completed in accordance with the approved design and any approved modifications. |
Prior to lodging an application for Building Works |
| 34) PONDING OF STORMWATER Adjoining properties and roads are to be protected from
ponding or nuisance from stormwater runoff.
Adjoining properties and roads are to be protected from ponding or nuisance from stormwater as a result of the proposed works; GUIDELINE This condition is imposed to ensure that the developer is aware that they are responsible for all remedial works required as a result of any site works and, that they must protect neighbouring properties and roads from ponding and nuisance water from the proposed development. Where this rectification work involved drainage, plans are to be lodged showing the manner in which it is intended to rectify the site drainage. These plans must be approved by the Engineering Delegate. For any enquiries about this condition, please contact the Engineering Delegate, Development and Regulatory Services. |
Prior to commencement of use |
34(a) PONDING OF STORMWATER Rectify all damage resulting from the ponding of stormwater or nuisance from discharge of stormwater from the site to adjacent properties. |
Prior to commencement of use |
| 35) CONNECT TO EXISTING STORMWATER Stormwater runoff from roof and surface areas is to be collected internally and piped generally in accordance with Chapter 6.3.2 of Part B of the "Subdivision and Development Guidelines" to the existing 375mm diameter stormwater pipe / stormwater pits in the north eastern corner of the site. Plans of the proposed stormwater works are to lodged electronically with the Principle Officer, Plumbing Services. The works must be completed and certified in accordance with engineering plans prepared by either a Registered Professional Engineer Queensland (RPEQ) or a member of the QBSA (Hydraulic Services Designer). GUIDELINE The purpose of this condition is to ensure that stormwater run off from the site and adjacent properties will be handled adequately. Disposal of storm water by gravity pipeline is required. For any enquiries about this condition, please contact the Engineering Delegate, Development and Regulatory Services. Where it is proposed to perform works in the road reserve, a permit is to be obtained from Council by calling the Council's Customer Contact Centre on ph. 3403 8888. |
Prior to commencement of use |
| 36) SERVICE CONDUITS & MAINS Supply and install all service conduits and meet the cost of
any alterations to public utility mains, existing mains, services or
installations required in connection with the approved development. This
includes the relocation of any fire hydrants and valves from within the limits
of the development's vehicular footway crossings if applicable.
Complete the works required by this condition; GUIDELINE This condition is imposed when additions, alterations or extensions to service conduits, mains and other services are required as a result of the approved development. Applicants should liaise with the appropriate service authorities. For any enquiries about this condition, please contact the Engineering Delegate, Development and Regulatory Services (regarding advise on traffic signal conduits, stormwater, water supply and sewerage mains etc.) or the relevant public utility authorities (for advice on other services). |
Prior to commencement of use |
36(a) SERVICE CONDUITS & MAINS Submit "As Constructed" plans including an asset register (if required), approved by a registered Professional Engineer Queensland (RPEQ) (in accordance with Council's "Subdivision and Development Guidelines" and "Water and Sewerage Reticulation Standards") showing the works required by this condition. |
Prior to commencement of use |
| 37) TELECOMMUNICATION - UNDERGROUND Provide underground telecommunication services to the proposed
development.
Enter into an agreement with a telecommunication company and provide underground telecommunication services within and adjacent to the proposed development; and GUIDELINE This condition is imposed to ensure that the provision of essential communication services are provided to the development. For any enquiries about this condition, please contact relevant service carriers regarding communications or Telstra (pH 132 200). |
Prior to commencement of use |
37(a) TELECOMMUNICATION -
UNDERGROUND Forward a copy of the agreement to the Engineering Delegate, Development and Regulatory Services. |
Prior to commencement of use |
| 38) ELECTRICITY (UNDERGROUND SUPPLY AREA) Provide underground electricity services in accordance with an
approved electricity reticulation plan and the Council's "Subdivision and
Development Guidelines (Public Utilities Section)". Note: Even though the
development may be in an area serviced by overhead electricity, UNDERGROUND
supply to the development is now required - no additional poles or overhead
mains are to be erected.
Lodge electricity reticulation plans showing and the proposed electricity services and obtain approval from the City Lighting Unit, Local Asset Services Central District; GUIDELINE This condition is imposed when a proposed development would require the provision of electricity services in accordance with Council's "Guidelines for the Provision of Underground Electricity". Please refer to the Council's information sheet on lodging detailed design applications. For any enquiries about this condition, please contact the City Lighting Unit (pH 3403 0307) regarding electricity reticulation plans or Energex (pH: 131 253) regarding electricity supply. |
Prior to commencement of use |
38(a) ELECTRICITY (UNDERGROUND SUPPLY
AREA) Enter into an agreement with an
electricity supplier to provide underground electricity services in accordance
with the above approved electricity reticulation plans;
and |
Prior to commencement of use |
38(b) ELECTRICITY (UNDERGROUND SUPPLY
AREA) Forward a copy of the agreement to the Engineering Delegate, Development and Regulatory Services. |
Prior to commencement of use |
| 39) PERMANENT VEHICULAR CROSSOVER Construct a permanent vehicular crossover(s) to the site.
Construct a 6.0 metre wide type B1 permanent vehicular crossover to the frontage(s) of the site in accordance with Council's "Subdivision and Development Guidelines". Such works may include footpath reconstruction, reprofiling and/or relocation of services. GUIDELINE This condition requiries works to be undertaken in the road reserve. The intention of the condition is to ensure that vehicular access to the site is designed and constructed to a standard suited to the demands created by the approved development. It is advantageous for the Developer to obtain the necessary driveway approvals and permit prior to commencing any site works to ensure the proposed internal site levels will suit the necessary permanent levels of the footway areas adjacent to the site. Generally, the vehicular footway crossings for a site are to have a minimum 1 in 40 crossfall to the kerb and channel for the full width of the footway area. Ramping the driveway up or down to the pad level should occur within the subject site only. This will ensure that driveways do not channel stormwater overflow from the roadway into the subject property and additionally maintain safer pedestrian movement. For enquires regarding this condition, please contact the Engineering Delegate, Development and Regulatory Services. |
Prior to commencement of use |
39(a) PERMANENT VEHICULAR
CROSSOVER Obtain a permit from Council's Engineering Delegate, Development and Regulatory Services, to carry out such works within the road reserve; |
Prior to commencement of use |
39(b) PERMANENT VEHICULAR
CROSSOVER Prior to the concrete pour for the construction of the permanent vehicular crossover(s) to the development, request an inspection by Council's Engineering Delegate, to ensure the approved works will be constructed in accordance with Council's requirements. |
Prior to commencement of use |
| 40) WATER SERVICE, METER ASSEMBLY & METER BOX Provide an appropriately sized water service with approved
Council meter assembly and meter box to the boundary of the development in
accordance with Council's "Water and Sewerage Reticulation Standards".
Submit engineering plans prepared by a Registered Professional Engineer Queensland (RPEQ), and in accordance with Council's "Water and Sewerage Reticulation Standards" showing service and meter works. (The size of the service shall be determined by the water supply requirement of the proposed development.). Obtain the approval from the Engineering Delegate, Development Assessment, Development and Regulatory Services; GUIDELINE This condition is imposed to supply a water service and a meter to a development/Community Title development. The meter should be accessable to BCC employees or agents for the purpose of reading and maintaining the meter. The meter will become and remain property of the BCC. For enquiries regarding this condition, please contact the Engineering Delegate, Development and Regulatory Services. |
Prior to undertaking the works |
40(a) WATER SERVICE, METER ASSEMBLY & METER
BOX Pay to Council the cost of live connection to the water main; |
Prior to undertaking the works |
40(b) WATER SERVICE, METER ASSEMBLY & METER
BOX Such construction is to be to a standard that is satisfactory to be accepted on and off maintenance. |
Prior to undertaking the works |
40(c) WATER SERVICE, METER ASSEMBLY & METER
BOX If the meters are purchased other than from Council, pay to Council a documentation fee for each water service provided. If the meters are purchased from Council, forward a copy of the receipt of purchase to the Engineering Delegate, Development and Regulatory Services. |
Prior to undertaking the works |
| 41) FUTURE WATER METER, INSTALLED BY BODY
CORPORATE Lodge a detailed hydraulics plan which demonstrates how it is proposed to make provision for a future water meter to be installed by the body corporate.
The plan must identify the location and proposed method of metering each lot in accordance with AS3565.
Obtain approval from the Principal Plumbing Inspector. GUIDELINE This condition is imposed to allow future Community Title owners to install water meters to each unit. The future water meter must be accessible for the purpose of reading and maintenance and be suitable to be read by the body corporate. The meter will become and remain property of the body corporate. A meter box is to be installed where the proposed meter is to be located underground. |
Prior to undertaking the works |
| 42) CONCURRENCE AGENCY CONDITIONS Brisbane City Council advise that Department Main Roads as concurrence agency has imposed the conditions contained in the letter dated 7 June 2005, Reference no. 510/232(F226). |
As indicated |