| Address of Site: | 330 JACKSON RD SUNNYBANK HILLS QLD 4109 |
| Real Property Description of Site: | L1 SP.278674 |
| Aspects of development and type of approval: | DA - SPA - Carry out Building Work Preliminary Approval under s241 -
Residential Care Facility,Extension DA - SPA - Material Change of Use Development Permit - Residential Care Facility,Extension |
| Council File Reference: | A007002653 Permit Reference Number/s: DABW336005017; DAMC336005117. |
| Package Status: | APPROVED - Version 6 (12th of June, 2026 5:18:40 PM) |
| Package Generated: | 12/06/2026 |
| Joanna STAVRIANOS Urban Planner Planning Services South Joanna.Stavrianos@brisbane.qld.gov.au 31785568 |
Ashleigh COOMBES Principal Urban Planner Planning Services South Ashleigh.Coombes@brisbane.qld.gov.au (07) 3403 1937 |
Alessio ZANCOLICH Principal Urban Planner Planning Services South alessio.zancolich@brisbane.qld.gov.au (07) 3407 8514 |
| Margaret ORR Team Manager Planning Services South margaret.orr@brisbane.qld.gov.au (07) 34070751 |
Mehdi BEIKI Senior Engineer Civil Infrastructure Mehdi.beiki@brisbane.qld.gov.au (07) 3178 6558 |
Mary CROSDALE Senior Architect Architect Services Mary.Crosdale@brisbane.qld.gov.au 0731782087 |
| Eric OWEN Senior Technical Officer Engineering Services South eric.owen@brisbane.qld.gov.au (07) 3178 5195 |
Zoe SAMSON Ecologist Green Space Services Zoe.Samson@brisbane.qld.gov.au 3178 1086 |
Barbara MARIC Urban Planner City Planning Barbara.Maric@brisbane.qld.gov.au (07) 3403 4249 |
| David ZANKER Urban Planner Planning Services South david.zanker@brisbane.qld.gov.au 31780066 |
Roger GREENWAY Principal Urban Planner Development Assurance & Outcomes roger.greenway@brisbane.qld.gov.au 34034392 |
Joanna SMEED Senior Urban Planner Planning Services Prelodgement Joanna.Smeed@brisbane.qld.gov.au 31780048 |
| Hayley STEEL Team Manager (Acting) Planning Services Special Assessment Hayley.Steel@brisbane.qld.gov.au (07) 3178 0022 |
Jenny BERNARD Urban Planner Planning Services North Jenny.Bernard@brisbane.qld.gov.au 0731780855 |
Christine GRAY Principal Urban Planner Planning Services North christine.gray@brisbane.qld.gov.au 3407 0160 |
| Callan BENNETT Principal Architect Architecture Team Callan.Bennett@brisbane.qld.gov.au 07 31780595 |
Emma MEZZINA Team Manager Planning Services South Emma.Mezzina@brisbane.qld.gov.au 3178 0049 |
DRAWINGS AND DOCUMENTS
| Drawing or Document | Number | Plan Date |
|---|---|---|
| Shadow Diagram | DA-007 Rev 4 | 18-DEC-2025 (Received) |
| Basement Level Plan | DA-002 Rev 4 | 18-DEC-2025 (Received) |
| Level 1 Plan | DA-003 Rev 5 (Amended In Red 02-MAR-2026) | 18-DEC-2025 (Received) |
| Level 2 Plan | DA-004 Rev 5 | 18-DEC-2025 (Received) |
| Level 3 - Sky Garden Plan & Roof Plan | DA-005 Rev 5 | 18-DEC-2025 (Received) |
| Building Elevations & Sections | DA-006 Rev 5 (Amended In Red 02-MAR-2026) | 18-DEC-2025 (Received) |
APPROVAL CONDITIONS
| Permit to Which These Conditions Relate: | DA - SPA - Carry out Building Work |
| Activity(ies): | Residential Care Facility Extension |
| Stage: | Carry out Building Work |
| 1) Complete All Building Work Complete all building work associated with this
development approval, including work required by any of the conditions included
in the Development Approval Package. Such building work must be carried out
generally in accordance with the approved DRAWINGS AND DOCUMENTS, and, where
the building work is assessable development, in accordance with a current
development approval. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
| Permit to Which These Conditions Relate: | DA - SPA - Material Change of Use |
| Activity(ies): | Residential Care Facility Extension |
| Stage: | Residential Care Facility, Extension |
| 2) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS
AND DOCUMENTS and the Development Approval Package must be available on
site. |
While site/operational/building work is occurring |
| 3) Carry Out the Approved Development Carry out the
approved development generally in accordance with the approved DRAWINGS AND
DOCUMENTS as amended in red. |
While site/operational/building work is occurring and then to be maintained |
| 4) Erect Screen Fence Erect a screen fence along the boundaries of the
site (unless where an acoustic fence is required) as shown on the approved
DRAWINGS AND DOCUMENTS. Unless an alternative design for the fence is agreed to
with the owner of adjoining land, the screen fence must be 1.8 metres in height
and be constructed from timber. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 5) Complete All Building Work Complete all building work associated with this
development approval, including work required by any of the conditions included
in the Development Approval Package. Such building work must be carried out
generally in accordance with the approved DRAWINGS AND DOCUMENTS, and, where
the building work is assessable development, in accordance with a current
development approval. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
| 6) Security Lighting Install and maintain a suitable system of security
lighting to operate from dusk to dawn within all areas where the public may
gain access, including car parking areas, building entrances and vegetated
areas |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 7) Maintain the Approved Development Maintain the approved development generally in
accordance with the approved DRAWINGS AND DOCUMENTS, and any relevant Council
engineering or other approval required by the conditions. |
To be maintained |
| 8) Demolish or Relocate Buildings Demolish or relocate buildings/structures on the
site in accordance with the approved DRAWINGS AND DOCUMENTS. The removal of buildings/structures includes the
removal of all existing concrete slabs, foundations and footings. |
As indicated |
| 9) Limits of this Approval This approval is
limited to the following uses:
If any changes to the approved uses are proposed, a new development application will be required to be submitted and approved prior to undertaking the use/s. The development application will be required to be accompanied by updated reports, in particular a traffic report. |
At all times |
| 10) Mechanical Ventilation of Car Parking Areas Vents associated with the mechanical ventilation of car parking areas are not permitted to be located on the northern or southern boundary of the site unless agreed in writing with Council’s Delegate. |
Prior to the commencement of the use and then to be maintained |
| 11) Visitor Parking Visitor
car parking spaces must: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 12) Car Parking The car parking within the premises must be maintained
exclusively for the ancillary use of the development. The parking must not be
made available to the general public and there must not be signage erected on
or in the vicinity of the site advertising the availability of car parking to
the general public. |
To be maintained |
| 13) Screening Requirements Provide screening in accordance with the stamped
approved plans and the following: |
As indicated |
13(a) Screening Where any windows of habitable rooms of the
proposed dwelling(s) are (within 2 metres at ground floor level or 9 metres
above ground floor level) adjoining neighbouring dwelling(s) windows of
habitable rooms, provide suitable screening in accordance with the
following: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
13(b) Direct View Screening Where a direct view is available within 2 metres
at ground floor level or 9 metres above ground floor levels from balconies,
landings, terraces and decks into windows, balconies, landings, terraces and
decks in an adjacent residential building, that view is to be screened. Where screening is required, it is to
be: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 14) Western elevation Provide for assessment and issue of a compliance certificate by development services architect, solar control glass specifications to certify the glass used is certified to a maximum solar heat gain (SHGC) coefficient of .30. |
Prior to site works commencing |
| 15) Provide Pedestrian Prioritised Pathway Provide a pedestrian prioritised pathway from the street frontage and
parking spaces to the entry foyer/lobby. The pathway is to be differentiated in
colour and texture from the driveway surface. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 16) Final External Detailing of Building Construct the development in accordance with architectural drawings approved pursuant to this condition. The architectural drawings must be in accordance with the APPROVED DRAWINGS AND DOCUMENTS, relevant Brisbane Planning Scheme Codes and the requirements of this condition. |
To be maintained |
16(a) Submit Architectural
Drawings Submit
for the approval of Development Services architectural drawings prepared and
certified by a Registered Architect showing the final developed details of the
façade treatment, the ground interface and the roof top/building capping
elements which depict a higher level of documentation detail than that shown on
the APPROVED DRAWINGS AND DOCUMENTS, including: Elevation and façade treatment
drawings for all ground, podium and typical tower floor levels that demonstrate
the final design outcome for all elevations of the built form including: - Detailed plans, sections
and elevations at 1:50 or 1:20 scale for elements at the façade
including structural elements and fixed and operable elements such as
balustrades, screens, doors, windows, projecting fins and planter
beds/trellises - All servicing and infrastructure,
including but not limited to, padmount transformers,
pump rooms, fire hydrant boosters etc. - Roof top or building
capping elements, awnings and soffits - One rendered perspective
showing the intended finished built form The
architectural drawings must: - include dimensions for the extent of projecting elements, balustrade
height and door and window/glazing configurations - nominate materials, colours and
finishes -
have title blocks and be cross referenced to larger scaled
drawings. Timing: Prior to building works
commencing |
As indicated |
16(b) Arrange a Pre-Start
Meeting Arrange
a pre-start meeting with Development Services. Timing: Prior to building works commencing |
As indicated |
16(c) Implement Approved Architectural
Drawings Carry
out the building work in accordance with the approved architectural drawings.
Timing: While building work is occurring and then to be maintained |
As indicated |
16(d) Submit Certification Submit to Development Services
certification by a Registered Architect confirming that the building has been
constructed in accordance with the approved architectural
drawings. Timing: Prior to the commencement of the use |
As indicated |
| 17) Overall Height The overall height of the proposed building(s) must be in accordance with the floor and roof levels and overall height shown on the APPROVED DRAWINGS AND DOCUMENTS. |
While site/operational/building work is occurring and then to be maintained |
17(a) Submit Certification Submit to Development
Services certification from a registered surveyor confirming that the “as
constructed” floor and roof levels and overall height are in accordance
with the requirements of this condition. Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 18) Light Reflectivity and Solar (Heat)
Reflectivity Submit to Development Services
documentary evidence that: |
As indicated |
18(a) Install Glazing Install and maintain glazing in accordance with the
above specification. |
As indicated |
| 19) Balconies/Verandahs/Terraces All balconies/verandahs/terraces must remain unenclosed with no shutters,
glazing, louvres or similar permanent fixtures. Note: Any Community Management Statement that may apply to this approval must contain a by-law which reflects the requirements of this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 20) Driveway Material and Finishes Provide materials and finishes to the driveway
and external carparking surfaces that reduce the
visual impact of these areas when viewed from the street. One or a combination
of the following must be used: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 21) Screen Air Conditioning and Other Plant
Enclosures Install and maintain suitable
screening to all air conditioning, lift motor rooms, plant and service
facilities located at the top of or on the external face of the building. The
screening structures must be constructed from materials that are consistent
with materials used elsewhere on the facade of the building. There must be no
individual external air conditioning units. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 22) Fauna Management - Fauna Spotter Catcher (High
Risk) Engage a licensed Fauna Spotter Catcher (qualified by the relevant Queensland State Government Authority) to manage the protection and relocation of any fauna prior to and during vegetation/ecological feature clearing. |
Prior to site/operational/building work commencing and then to be maintained |
22(a) Prior to Vegetation/ Ecological Feature
Clearing Submit
to Development Services certification from the licensed Fauna Spotter Catcher
that the site has been fully inspected and any necessary fauna protection
measures or relocation procedures have been implemented. Timing: Prior to vegetation/ ecological feature clearing commencing. |
As indicated |
22(b) During Vegetation/ Ecological Feature
Clearing The
licensed Fauna Spotter Catcher must be present on site during all clearing
operations to monitor works and to respond to any fauna situations that may
arise. If any fauna is identified in vegetation or ecological features to be
removed during clearing operations, work must cease immediately on that
vegetation or ecological feature. The licensed Fauna Spotter Catcher must
supervise the relocation of any identified fauna prior to vegetation/
ecological feature clearing recommencing. Timing: While vegetation/ ecological feature clearing is occurring |
As indicated |
22(c) Submit Certification Submit to Development Services
certification from the licensed Fauna Spotter Catcher that vegetation/
ecological feature clearing was carried out in accordance with this
condition. Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
As indicated |
| 23) Arboricultural Requirements The following arboricultural requirements are to be performed to ensure
the long-term health and safety of trees to be retained: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
23(a) Site Works In consultation with Development Assessment, the
Arborist is to direct the civil works contractor in
relation to any service installation activities utilising alternative
technologies such as directional-boring or under-boring using vacuum excavation
or air-spade. The Arborist must be a suitably
qualified arboricultural consultant (minimum AQF
Level 5 Diploma in Arboriculture). |
While site/operational/building work is occurring |
23(b) Certification Submit to Development Assessment, certification
from a suitably qualified arboricultural consultant
(minimum AQF Level 5 Diploma in Arboriculture) that all necessary arboricultural works have been carried out in accordance
with the requirements of all parts of this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
23(c) Vegetation Pruning Any necessary pruning, tree surgery and other
maintenance works to maintain health and stability of any trees to be retained,
and to reduce potential hazards for future residents, is to be carried out in
consultation with Development Assessment. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 24) Landscape the Site - Self Certification Landscape the site in accordance with the
requirements of this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
24(a) Landscape Plan for Self
Certification Prepare a detailed Landscape Plan at a scale of 1:100 for all on-site
landscape works identified on the approved DRAWINGS AND DOCUMENTS. The plan
must be prepared by a registered Landscape Architect and must comply with the
relevant Brisbane Planning Scheme Code. The plan must be certified by the
registered Landscape Architect using Brisbane City Council Form CC10616 -
Landscape Design Certification and the form must be submitted to Development
Services. In addition to the requirements
listed above, the plan must include the following: |
As indicated |
24(b) Implement Certified Landscape
Plan Carry out the landscaping work in
accordance with the above certified detailed Landscape Plan. |
As indicated |
24(c) Certify Work On completion of the
landscaping work, submit to Development Services Brisbane City Council Form
CC10613 - Landscape Works Certificate prepared by a registered Landscape
Architect or licensed Landscape Contractor to certify the completed landscaping
work complies with the certified detailed Landscape Plan. Note: A copy of the as-constructed detailed Landscape Plan must
accompany the completed Landscape Works Certificate. Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
24(d) Maintain Landscape Work Maintain the landscape work generally in accordance
with the certified detailed Landscape Plan. |
As indicated |
| 25) Plant and Equipment Certification Submit to Development
Services certification that the installation of all mechanical plant and
equipment (e.g. air conditioning, mechanical ventilation and refrigeration
equipment and heat pump hot water systems), is adequately noise-attenuated and
is in accordance with the criteria of the relevant Brisbane Planning Scheme
Codes. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 26) Hours of Operation - Vehicle movements Operation of trucks and
commercial vehicles (excluding waste collection vehicles) during the
operational phase of the development must only occur between 7am - 7pm Monday
to Saturday. |
To be maintained |
| 27) Filling and / or Excavation All proposed earthworks must
be carried out in accordance with the relevant Brisbane Planning Scheme
Codes. Timing: Prior to building work commencing (MCU or BW) or prior to
Council's notation of the plan of subdivision (ROL) |
As indicated |
27(a) Submit Earthworks
Drawings Submit for the approval of Development Services
earthworks drawings prepared and certified by a Registered Professional
Engineer Queensland in accordance with the approved DRAWINGS AND DOCUMENTS and
the relevant Brisbane Planning Scheme Codes. The Earthworks Drawings must include the
following: - The
location of any cut and/or fill; - The quantity of fill to be deposited and
finished fill levels; - Maintenance of access roads to and from the site
such that they remain free of all fill material and
are cleaned as necessary; - The existing and proposed finished levels in reference to the
Australian Height Datum (including cross-sections or long sections into the
adjacent properties); - Preservation of all drainage structures from the effects of
structural loading generated by the earthworks; - Protection of adjoining properties and roads
from ponding or nuisance from stormwater; - That all vehicles exiting from the site will be
cleaned and treated so as to prevent material being tracked or deposited on
public roads. Note: If the
earthworks impact on the road reserve, the Developer must obtain applicable
footpath and road permits prior to commencing any works. Such impacts may include footpath occupation, road
closures, re-profiling, ground anchors and/or relocation of services. If the excavation has to be stabilised
using ground anchors or similar then the submitted plans must show the location
of these in relation to all services. The cost of moving services, utilities
and assets is the responsibility of the Developer. The permission of the
service/utility/asset owner is required. |
As indicated |
27(b) Fill Material, Placement, Compaction
and Testing All fill material placed on the site must comprise
only natural earth and rock and must be free of contaminants (as defined by
Part 3, Division 2, Subdivision 2 Environmental contamination, Section 11 of
the Environmental Protection Act) and noxious, hazardous, deleterious and
organic materials. Fill
material, placement, compaction and testing must comply with the requirements
of Australian Standard - AS 3798, Guidelines on Earthworks for Commercial and
Residential Developments. Timing: While site/operational/building work is occurring |
As indicated |
27(c) Implement Approved Earthworks
Drawings Construct and maintain the earthworks in accordance
with the requirements of AS3798 and the approved earthworks drawings. |
As indicated |
27(d) Submit As Constructed
Drawings Submit to Development Services “As
Constructed” drawings prepared by a Registered
Surveyor. Timing: Prior to building work commencing (MCU or BW) or prior to Council's notation of the plan of subdivision (ROL) |
As indicated |
27(e) Submit Certification Submit to Development Services certification from a Registered
Professional Engineer Queensland, confirming that the works have been completed
in accordance with the approved earthworks drawings. Submit to Development Services certification from a
Registered Professional Engineer Queensland, confirming that all fill material
used complies with the quality requirements of this condition and that
placement, compaction and testing has been carried out in accordance with
AS3798. Timing:
Prior to building work commencing (MCU or BW) or prior to Council's notation of
the plan of subdivision (ROL) |
As indicated |
| 28) On-site Erosion (medium risk) Minimise on-site
erosion and the release of sediment or sediment laden stormwater from the site
at all times. Timing: While site works are
occurring and until all exposed soil areas are permanently stabilised against
erosion. |
As indicated |
28(a) Prepare Erosion and Sediment Control
Plan Prepare Erosion and Sediment Control (ESC) Plan(s), and provide design
certificates for the site in accordance with the relevant Brisbane Planning
Scheme Codes. The plan(s) and design
certificates must be certified by a Certified Professional in Erosion and
Sediment Control (CPESC) or a Registered Professional Engineer Qld (RPEQ) with
suitable qualifications and experience in erosion and sediment
control. Documentary evidence demonstrating appropriate qualifications in
erosion and sediment control must be provided to the Council upon
request. At least 10 days prior to either
the pre-start meeting or commencement of site works, submit copies of design
certificates to Council’s Compliance and Regulatory Services
at: Timing: Prior to pre-start
meeting or commencement of any site works and to be maintained until all
exposed soil areas are permanently stabilised against
erosion. |
As indicated |
28(b) Attend a pre-start
meeting Request and attend a pre-start meeting with an Erosion & Sediment
Control Officer from Council’s Compliance and Regulatory Services. Requests are to be made when submitting
copies of all required documentation, including design certificates to:
CARS-
ESC@brisbane.qld.gov.au Timing: Prior to commencement of
any site works causing exposure of soil. |
As indicated |
28(c) Implement Certified Erosion and
Sediment Control Plan Implement the certified ESC plan(s) to maintain compliance
with all parts of the relevant Brisbane Planning Scheme Codes, while site works
are occurring and until all exposed soil areas are permanently stabilised
against erosion. The plan(s) and design
certifications must be available on site at all times for inspection by Council
officers until all exposed soil areas are permanently stabilised against
erosion. Minimise on-site erosion and the
release of sediment or sediment laden stormwater from the site at all
times. Timing: While site works are occurring and until all exposed
soil areas are permanently stabilised against erosion. |
As indicated |
| 29) Information Signage Erect an "Information Sign" on the subject
property in accordance with Council’s general requirements for signage
and in accordance with the requirements outlined below: a)
The sign should provide a brief description of the development proposed; Developer; c) The lettering on the sign is to be at least
25 millimetres in height, be of regular weight and in sentence case; located centrally along each road
frontage of the site to Jackson and Jayef Streets;
g) The sign is to contain no commercial
or corporate advertising other than the name, logo or slogan of the parties
outlined in part (b) of this condition; Timing: Prior to site works commencing and then to be maintained until completion of the development for all stages. |
As indicated |
| 30) Retaining Walls Design and construct all
retaining walls and associated fences, in accordance with the relevant Brisbane
Planning Scheme Codes and including the following: |
Prior to site/operational/building work commencing |
30(a) Certification of Retaining
Walls For
retaining walls over 1.0m in height, obtain certification from a Registered
Professional Engineer Queensland that the design and construction of the
retaining wall and ancillary drainage is in accordance with this condition. |
As indicated |
| 31) Protect Existing Infrastructure Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure. Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations. The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements. |
While site/operational/building work is occurring |
31(a) As Constructed Drawings Where alterations to existing infrastructure are required, submit to
Development Services "As Constructed" drawings showing all new and/or
rectification works and an asset register, prepared by a Registered
Professional Engineer Queensland. Timing: Prior to issue of Certificate of
Classification/Final Inspection Certificate or prior to commencement of use,
whichever comes first (MCU or BW), or prior to Council's notation of the plan
of subdivision (ROL) |
As indicated |
31(b) Submit Certification Where alterations to existing
infrastructure are required, submit to Development Services certification from
a Registered Professional Engineer Queensland, confirming that the alterations
have been completed in accordance with the relevant Brisbane Planning Scheme
Codes and any other relevant infrastructure requirements.
Timing: Prior to issue of Certificate of Classification/Final
Inspection Certificate or prior to commencement of use, whichever comes first
(MCU or BW), or prior to Council's notation of the plan of subdivision
(ROL) |
As indicated |
| 32) Construction Management Plan - Major Carry out development in accordance with a
Construction Management Plan prepared in accordance with the requirements of
this condition. |
While site/operational/building work is occurring |
32(a) Submit Construction Management
Plan Submit
for the approval of Development Services a Construction Management Plan for the
demolition, excavation and construction phases of the approved development.
Separate Construction Management Plans may be appropriate for the individual
components. The Construction Management Plan must be in accordance with the
relevant Brisbane Planning Scheme Codes, Workplace Health and Safety
Legislation, Environmental Protection Act, the requirements of any Concurrence
Agency, any other relevant legislative requirements and the following. |
While site/operational/building work is occurring |
32(b) Construction Management Plan - Pre-
start Meeting Arrange
a Pre-Start meeting with Development Services. |
While site/operational/building work is occurring |
32(c) Construction Management Plan -
Associated Activities in Road Reserve Obtain
relevant approvals to carry out any works required by the approved Construction
Management Plan, including the following, within the road reserve: |
While site/operational/building work is occurring |
32(d) Construction Management Plan -
Documentation on Site Legible copies of the approved Construction Management Plan and current
permits must be kept on site and be made available on request at all times. |
While site/operational/building work is occurring |
32(e) Construction Management Plan - Works to
be Performed Out of Hours Obtain approval from Development Services for any
work that is to be undertaken outside of normal business hours - 6:30am to
6:30pm, Monday to Saturday. |
While site/operational/building work is occurring |
32(f) Implement Approved Construction
Management Plan Carry
out the development in accordance with the approved Construction Management
Plan. |
While site/operational/building work is occurring |
| 33) Repair Damage to Kerb, Footpath Or Road Repair any damage to the
existing kerb and channel, footpath or roadway (including removal of concrete
slurry from footways, roads, kerb and channel and stormwater gullies and drainlines) and re-instate existing traffic signs and
pavement markings that have been removed or damaged during any works carried
out in association with the approved development. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 34) Access, Grades, Manoeuvring, Carparks, Signs and
Line Marking Construct access, parking and manoeuvring for vehicles on site in
accordance with the relevant Brisbane Planning Scheme Codes, as indicated on
the approved DRAWINGS AND DOCUMENTS, including the following: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
34(a) Submit certification Submit to Development
Services, certification from a Registered Professional Engineer Queensland,
that the above requirements have been implemented in accordance with this
condition. |
As indicated |
| 35) Refuse Storage - On Site Bulk Collection Provide a roofed and screened waste enclosure to accommodate the
type and quantity of bulk waste/recycling bins required to service the
development. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 36) Ponding of stormwater Adjoining properties and roads are to be protected from ponding or
nuisance from stormwater as a result of the works. Ensure the stormwater runoff from the site does not
adversely impact on flooding or drainage (peak discharge and duration for all
events up to the 100 year Average Recurrence Interval (ARI)) of properties that
are upstream, downstream or adjacent to the site. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 37) On Site Drainage - Minor Provide a stormwater
connection to all new or existing allotments and provide drainage
infrastructure to ensure stormwater run-off from all roof and developed surface
areas will be collected internally and piped in accordance with the relevant
Brisbane Planning Scheme Codes to a lawful point of
discharge. Note: Guidance for the preparation of
drawings and/or documents to comply with this condition is provided in the
Brisbane Planning Scheme Policies |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
37(a) Submit As Constructed
Drawings Where
reconfiguring a lot, submit to Development Services "As Constructed"
drawings prepared by a Registered Professional Engineer Queensland.
Timing: Prior to Council's notation of the plan of subdivision |
As indicated |
37(b) Submit Certification Where reconfiguring a lot, submit to
Development Services certification from a Registered Professional Engineer
Queensland, confirming that the works have been completed in accordance with
this condition. Timing: Prior to Council's notation of the plan of subdivision |
As indicated |
| 38) Service Conduits and Mains Provide and install all service conduits and meet
the cost of any alterations to public utility mains, existing mains, services
or installations that are required to carry out the approved development. These
works must be in accordance with the relevant Brisbane Planning Scheme Codes,
and include the following, where applicable: Note: Applicants must
liaise with the appropriate service authorities. Typical underground services
and/or conduits to be constructed include power, phone, telecommunications,
sewer (including private combine drains) stormwater and gas, if
applicable. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
38(a) Submit As Constructed
Drawings Submit to Development Services "As
Constructed" drawings, including an asset register, prepared by a
Registered Professional Engineer Queensland.
|
As indicated |
38(b) Submit Certification Submit to Development Services certification from a
Registered Professional Engineer Queensland, confirming that the works have
been completed in accordance with the requirements of this
condition. Timing: Prior to issue of Certificate of Classification/Final
Inspection Certificate or prior to commencement of use, whichever comes first
(MCU or BW), or prior to Council's notation of the plan of subdivision
(ROL) |
As indicated |
| 39) Telecommunications Submit to Development Services, certification from
an authorised telecommunications carrier/contractor, that the following works
and infrastructure have been undertaken and installed in accordance with
telecommunications industry standards: a) Provide telecommunications to the subject buildings, lead-in conduits and equipment space in a suitable location within the buildings, to suit the carrier of choice. b) If new pits and conduit infrastructure are required to be installed within the road reserve fronting the site, it must be suitably sized to cater for future installation of fibre optic cables. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 40) Agreement with Electricity Supplier Submit to Development
Services, evidence of an agreement with an electricity supplier to provide
necessary services to the development in accordance with the relevant Brisbane
Planning Scheme Codes. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 41) Breaking Combine Sewer Drain The development site is currently served by a
combined sewer drain. A condition
of this development has not been set to break the combined drain, however it
may be a requirement of the plumbing approval that the sewerage reticulation is
extended to break the combined drain.
Please contact Council's Plumbing Services for further advice prior to
commencement of any site or building works. |
As indicated |
| 42) Food Hygiene All development involving the preparation, packing, storing,
handling, serving, selling or carrying of food requires that its design,
installation and operation be approved pursuant to the Food Act 2006. The premises must be registered and the
operator must hold a licence with Brisbane City Council to operate the business
under the above provisions. |
As indicated |
| 43) Further Development Permit required This Preliminary Approval (Carrying Out Building Works) does not include assessment under the
Building Act and does not permit building work to occur. Prior to the commencement of any building work,
Development Permit(s) for Carrying Out Building Work
will be required. |
As indicated |
| 44) Construction Noise and Dust Emissions Pursuant to the
Environmental Protection Act 1994, all development involving the emission of
noise and dust from building and/or construction activities, must ensure that
the emissions are in accordance with the requirements of the Act. The
Environmental Protection Act 1994 prescribes that: 1. A person
must not carry out building work in a way that makes an audible noise-
- on a business day or Saturday, before 6.30a.m. or after 6.30p.m; or
- on any other day, at any time.
2. The reference in subsection (1)
to a person carrying out building work- - includes a person carrying out building work under an owner-builder permit; and - otherwise does
not include a person carrying out building work at premises used by the person
only for residential purposes. Note: A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management delegate Development Services. |
As indicated |
| 45) Plumbing and Drainage Work Pursuant to the Plumbing and Drainage Act 2002,
any plumbing and drainage work must be carried out in compliance with the
Standard Plumbing and Drainage Regulation. Compliance assessable plumbing and
drainage work requires approval by Brisbane City Council prior to the work
being carried out. |
As indicated |
| 46) Natural Assets Local Law (NALL) - On Site Lodge and receive approval from Development
Assessment, an application to Carry Out Works on
Protected Vegetation on the site. |
Prior to site/operational/building work commencing |
| 47) Standard Building Regulations This approval does not include assessment
against the siting requirements of the Queensland
Development Code. Should the
approved development require a siting variation
against the Queensland Development Code, an application for a Siting Variation must be submitted for the approval of
Brisbane City Council - Compliance and Regulatory Services. |
As indicated |
| 48) Advice Please note that the information contained in this section under
the heading Standard Advice has been provided as advice only and does not form
part of the development approval conditions. This information has been provided to advise of other obligations under state legislation or local
laws that may require action to be undertaken prior to commencing the activity
approved by this development approval. |
As indicated |
| 49) Equitable Access Provision must be made for equitable access for persons with
disabilities to and within the site in accordance with the Queensland Anti-
Discrimination Act 1991, the Federal Disability Discrimination Act 1992 and
Australian Standard AS1428 Parts 1-4, Australian Standard for Access and
Mobility and the National Construction Code. |
As indicated |
| 50) Water and Wastewater Services for water and wastewater (sewerage) are
no longer under the jurisdiction of Brisbane City Council. Authorisation to
connect the approved development to the water/wastewater networks and for
property service connections requires a Water Approval under the South-East
Queensland Water (Distribution and Retail Restructuring) Act 2009. Any
necessary Water Approval must be obtained from the relevant distributor-
retailer (currently operating as Queensland Urban Utilities for the Brisbane
City Council area). For the purpose of compliance assessment of a subdivision plan pursuant to Schedule 19 of the Sustainable Planning Regulation 2009 (whether in relation to a development permit for Reconfiguring a Lot or a Building Format Plan subsequent to a development permit for a Material Change of Use), documentary evidence, issued by the relevant distributor-retailer, must be provided to Council to verify that the conditions of any necessary Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009, have been complied with. |
As indicated |
| 51) Fire Ant Movement Controls To prevent the spread of fire ants, the
Queensland Government has implemented movement controls in areas of Queensland
(biosecurity zones) where this pest species has been detected. These controls
apply to individuals and commercial operators, and restrict the movement of
materials that could carry fire ants which include soil, turf, potted plants,
mulch, baled hay or straw, animal manures, mining or quarry
products. Breaches of these controls can potentially
impact the community, economy and the environment. Penalties for non-compliance
with movement controls within fire ant biosecurity zones apply under the
Biosecurity Act 2014. If you are unsure of your obligations contact the relevant Queensland State Government Department (Biosecurity Queensland, Department of Agriculture and Fisheries) |
As indicated |
| 52) Treatment Of Asbestos Disposal, handling, removal and restoration of any building materials containing asbestos shall be in accordance with the Workplace Health and Safety Regulations 1989. Disposal of asbestos may
constitute a Schedule 2 - Notifiable Activity under
the Environmental Protection Act 1994. Under this Act, landowners
must inform the Department of Environment and Heritage Protection (EHP) that
land has been or is being used for a notifiable
activity. Prior approval from the Department of Environment and Heritage
Protection may be required, as determined by the Agency. The developer / site owner shall contact the EHP for advice, prior to
commencing building work on the site. |
As indicated |