BRISBANE CITY COUNCIL'S APPROVAL PACKAGE.



APPLICATION DETAILS

This package relates to the application detailed below
Address of Site: 330 JACKSON RD SUNNYBANK HILLS QLD 4109
Real Property Description of Site: L1 SP.278674
Aspects of development and type of approval: DA - SPA - Carry out Building Work Preliminary Approval under s241 - Residential Care Facility,Extension
DA - SPA - Material Change of Use Development Permit - Residential Care Facility,Extension
Council File Reference: A007002653
Permit Reference Number/s: DABW336005017; DAMC336005117.
Package Status: APPROVED - Version 6 (12th of June, 2026 5:18:40 PM)
Package Generated: 12/06/2026


PROJECT TEAM

The assessment of this application has been undertaken by:
Joanna STAVRIANOS
Urban Planner
Planning Services South
Joanna.Stavrianos@brisbane.qld.gov.au
31785568
Ashleigh COOMBES
Principal Urban Planner
Planning Services South
Ashleigh.Coombes@brisbane.qld.gov.au
(07) 3403 1937
Alessio ZANCOLICH
Principal Urban Planner
Planning Services South
alessio.zancolich@brisbane.qld.gov.au
(07) 3407 8514
Margaret ORR
Team Manager
Planning Services South
margaret.orr@brisbane.qld.gov.au
(07) 34070751
Mehdi BEIKI
Senior Engineer
Civil Infrastructure
Mehdi.beiki@brisbane.qld.gov.au
(07) 3178 6558
Mary CROSDALE
Senior Architect
Architect Services
Mary.Crosdale@brisbane.qld.gov.au
0731782087
Eric OWEN
Senior Technical Officer
Engineering Services South
eric.owen@brisbane.qld.gov.au
(07) 3178 5195
Zoe SAMSON
Ecologist
Green Space Services
Zoe.Samson@brisbane.qld.gov.au
3178 1086
Barbara MARIC
Urban Planner
City Planning
Barbara.Maric@brisbane.qld.gov.au
(07) 3403 4249
David ZANKER
Urban Planner
Planning Services South
david.zanker@brisbane.qld.gov.au
31780066
Roger GREENWAY
Principal Urban Planner
Development Assurance & Outcomes
roger.greenway@brisbane.qld.gov.au
34034392
Joanna SMEED
Senior Urban Planner
Planning Services Prelodgement
Joanna.Smeed@brisbane.qld.gov.au
31780048
Hayley STEEL
Team Manager (Acting)
Planning Services Special Assessment
Hayley.Steel@brisbane.qld.gov.au
(07) 3178 0022
Jenny BERNARD
Urban Planner
Planning Services North
Jenny.Bernard@brisbane.qld.gov.au
0731780855
Christine GRAY
Principal Urban Planner
Planning Services North
christine.gray@brisbane.qld.gov.au
3407 0160
Callan BENNETT
Principal Architect
Architecture Team
Callan.Bennett@brisbane.qld.gov.au
07 31780595
Emma MEZZINA
Team Manager
Planning Services South
Emma.Mezzina@brisbane.qld.gov.au
3178 0049


DRAWINGS AND DOCUMENTS



The term 'drawings and documents' or similar expressions mean:
Drawing or Document Number Plan Date
Shadow Diagram DA-007 Rev 4 18-DEC-2025 (Received)
Basement Level Plan DA-002 Rev 4 18-DEC-2025 (Received)
Level 1 Plan DA-003 Rev 5 (Amended In Red 02-MAR-2026) 18-DEC-2025 (Received)
Level 2 Plan DA-004 Rev 5 18-DEC-2025 (Received)
Level 3 - Sky Garden Plan & Roof Plan DA-005 Rev 5 18-DEC-2025 (Received)
Building Elevations & Sections DA-006 Rev 5 (Amended In Red 02-MAR-2026) 18-DEC-2025 (Received)


Advice

Please see the attached document(s) for any advices.

APPROVAL CONDITIONS



Permit to Which These Conditions Relate: DA - SPA - Carry out Building Work
Activity(ies): Residential Care Facility
Extension
Stage: Carry out Building Work

General/Planning Requirements
 
Timing
1)   Complete All Building Work

Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out generally in accordance with the approved DRAWINGS AND DOCUMENTS, and, where the building work is assessable development, in accordance with a current development approval.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
 



Permit to Which These Conditions Relate: DA - SPA - Material Change of Use
Activity(ies): Residential Care Facility
Extension
Stage: Residential Care Facility, Extension

General/Planning Requirements
 
Timing
2)   Approved Drawings and Documents

A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be available on site.

Note.  This condition is imposed to ensure compliance with the conditions of development approval. The copy of the conditions and drawings should be located in a site management office or with the site foreman.

 
While site/operational/building work is occurring
 
3)   Carry Out the Approved Development

Carry out the approved development generally in accordance with the approved DRAWINGS AND DOCUMENTS as amended in red.

Note.  This development approval may include the location of fences, retaining walls and/or external walls of buildings on the boundary of a lot. This approval does not imply permission to enter neighbouring properties to carry out the construction (including associated drainage and earthworks) or maintenance activities.  Permission to enter neighbouring properties must be obtained from relevant property owners.

 
While site/operational/building work is occurring and then to be maintained
 
4)   Erect Screen Fence

Erect a screen fence along the boundaries of the site (unless where an acoustic fence is required) as shown on the approved DRAWINGS AND DOCUMENTS. Unless an alternative design for the fence is agreed to with the owner of adjoining land, the screen fence must be 1.8 metres in height and be constructed from timber.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
5)   Complete All Building Work

Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out generally in accordance with the approved DRAWINGS AND DOCUMENTS, and, where the building work is assessable development, in accordance with a current development approval.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
 
6)   Security Lighting

Install and maintain a suitable system of security lighting to operate from dusk to dawn within all areas where the public may gain access, including car parking areas, building entrances and vegetated areas

Ensure that all external lighting is in accordance with Australian Standard - AS4282- Control of the Obtrusive Effects of Outdoor Lighting so as not to cause nuisance to nearby residents or passing motorists.

Ensure lighting over publicly accessible pathways covered by permanent awnings is in accordance with Australian Standard - AS/NZS 1158.3.1 Lighting for roads and public spaces - Pedestrian area (Category P) lighting - Performance and design requirements.

Lighting must be maintained by the owner of the building in a safe and good working order.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
7)   Maintain the Approved Development

Maintain the approved development generally in accordance with the approved DRAWINGS AND DOCUMENTS, and any relevant Council engineering or other approval required by the conditions.

 
To be maintained
 
8)   Demolish or Relocate Buildings

Demolish or relocate buildings/structures on the site in accordance with the approved DRAWINGS AND DOCUMENTS.  The removal of buildings/structures includes the removal of all existing concrete slabs, foundations and footings.

Timing:  Prior to any new building work occurring (MCU or BW) or prior to Council's notation on the plan of subdivision (ROL)

 
As indicated
 
9)   Limits of this Approval

This approval is limited to the following uses:

  • Residential Care Facility; and
  • Dinning, lounge, treatment room, servery, and sky garden shall remain ancillary to the Residential Care Facility for the use of residents, their guests, bona fide visitors and employees at all times.

 

If any changes to the approved uses are proposed, a new development application will be required to be submitted and approved prior to undertaking the use/s. The development application will be required to be accompanied by updated reports, in particular a traffic report.

 

 

 
At all times
 
10)   Mechanical Ventilation of Car Parking Areas

Vents associated with the mechanical ventilation of car parking areas are not permitted to be located on the northern or southern boundary of the site unless agreed in writing with Council’s Delegate.

 
Prior to the commencement of the use and then to be maintained
 
11)   Visitor Parking

Visitor car parking spaces must:

- Be used by bona fide visitors to the premises only;
- Be clearly labelled as ‘Visitor Parking’; and
- Remain unimpeded by landscaping, water tanks, storage (temporary or otherwise), gates or any other fitting, fixture or structure to provide unrestricted access for bona fide visitors between the hours of 7am and 7pm.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
12)   Car Parking

The car parking within the premises must be maintained exclusively for the ancillary use of the development. The parking must not be made available to the general public and there must not be signage erected on or in the vicinity of the site advertising the availability of car parking to the general public.

 
To be maintained
 
Architecture
 
Timing
13)   Screening Requirements

Provide screening in accordance with the stamped approved plans and the following:

 
As indicated
13(a) Screening

Where any windows of habitable rooms of the proposed dwelling(s) are (within 2 metres at ground floor level or 9 metres above ground floor level) adjoining neighbouring dwelling(s) windows of habitable rooms, provide suitable screening in accordance with the following:

-  Fixed opaque glazing in any part of the window below 1.5m above floor level; OR

-   Fixed external screens, OR

-  Sill heights of 1.5m above floor level, OR

-  Fencing to a minimum 1.5m above ground floor level (only applies to overlooking from windows at ground floor level).

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
13(b) Direct View Screening

Where a direct view is available within 2 metres at ground floor level or 9 metres above ground floor levels from balconies, landings, terraces and decks into windows, balconies, landings, terraces and decks in an adjacent residential building, that view is to be screened.  Where screening is required, it is to be:

-  Perforated panels, or trellises that are permanent and durable and have a maximum of 25% openings, with a maximum opening of 50mm, and that are permanently fixed and durable, OR

-  Where described on the approved drawings, as per the approved drawings.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
14)   Western elevation

Provide for assessment and issue of a compliance certificate by development services architect, solar control glass specifications to certify the glass used is certified to a maximum solar heat gain (SHGC) coefficient of .30.

 
Prior to site works commencing
 
15)   Provide Pedestrian Prioritised Pathway

Provide a pedestrian prioritised pathway from the street frontage and parking spaces to the entry foyer/lobby. The pathway is to be differentiated in colour and texture from the driveway surface.

 

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
16)   Final External Detailing of Building

Construct the development in accordance with architectural drawings approved pursuant to this condition. The architectural drawings must be in accordance with the APPROVED DRAWINGS AND DOCUMENTS, relevant Brisbane Planning Scheme Codes and the requirements of this condition.

 
To be maintained
16(a) Submit Architectural Drawings

Submit for the approval of Development Services architectural drawings prepared and certified by a Registered Architect showing the final developed details of the façade treatment, the ground interface and the roof top/building capping elements which depict a higher level of documentation detail than that shown on the APPROVED DRAWINGS AND DOCUMENTS, including:

  Elevation and façade treatment drawings for all ground, podium and typical tower floor levels that demonstrate the final design outcome for all elevations of the built form including:  

    - Detailed plans, sections and elevations at 1:50 or 1:20 scale for elements at the façade including structural elements and fixed and operable elements such as balustrades, screens, doors, windows, projecting fins and planter beds/trellises

    - All servicing and infrastructure, including but not limited to, padmount transformers, pump rooms, fire hydrant boosters etc.

    - Roof top or building capping elements, awnings and soffits

    - One rendered perspective showing the intended finished built form

The architectural drawings must:

  - include dimensions for  the extent of projecting elements, balustrade height and door and window/glazing configurations

  - nominate materials, colours and finishes

  - have title blocks and be cross referenced to larger scaled drawings.

Timing: Prior to building works commencing

 
As indicated
16(b) Arrange a Pre-Start Meeting

Arrange a pre-start meeting with Development Services.

Timing: Prior to building works commencing

 
As indicated
16(c) Implement Approved Architectural Drawings

Carry out the building work in accordance with the approved architectural drawings.

Timing: While building work is occurring and then to be maintained

 
As indicated
16(d) Submit Certification

Submit to Development Services certification by a Registered Architect confirming that the building has been constructed in accordance with the approved architectural drawings.

Timing: Prior to the commencement of the use

 
As indicated
 
17)   Overall Height

The overall height of the proposed building(s) must be in accordance with the floor and roof levels and overall height shown on the APPROVED DRAWINGS AND DOCUMENTS.

 
While site/operational/building work is occurring and then to be maintained
17(a) Submit Certification

Submit to Development Services certification from a registered surveyor confirming that the “as constructed” floor and roof levels and overall height are in accordance with the requirements of this condition.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
18)   Light Reflectivity and Solar (Heat) Reflectivity

Submit to Development Services documentary evidence that:

-  the level of light reflectivity from the glazing incorporated in the approved development does not exceed 20%

Timing:  Prior to building work above ground level commencing

 
As indicated
18(a) Install Glazing

Install and maintain glazing in accordance with the above specification.

Timing:  Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained

 
As indicated
 
19)   Balconies/Verandahs/Terraces

All balconies/verandahs/terraces must remain unenclosed with no shutters, glazing, louvres or similar permanent fixtures.

Note: Any Community Management Statement that may apply to this approval must contain a by-law which reflects the requirements of this condition.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
20)   Driveway Material and Finishes

Provide materials and finishes to the driveway and external carparking surfaces that reduce the visual impact of these areas when viewed from the street. One or a combination of the following must be used:

-  Coloured aggregate;

-  Concrete pavers; and/or

-  Banding and patterns in the surface design.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
21)   Screen Air Conditioning and Other Plant Enclosures

Install and maintain suitable screening to all air conditioning, lift motor rooms, plant and service facilities located at the top of or on the external face of the building. The screening structures must be constructed from materials that are consistent with materials used elsewhere on the facade of the building. There must be no individual external air conditioning units.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
Ecology
 
Timing
22)   Fauna Management - Fauna Spotter Catcher (High Risk)

Engage a licensed Fauna Spotter Catcher (qualified by the relevant Queensland State Government Authority) to manage the protection and relocation of any fauna prior to and during vegetation/ecological feature clearing.

 
Prior to site/operational/building work commencing and then to be maintained
22(a) Prior to Vegetation/ Ecological Feature Clearing

Submit to Development Services certification from the licensed Fauna Spotter Catcher that the site has been fully inspected and any necessary fauna protection measures or relocation procedures have been implemented.

Timing: Prior to vegetation/ ecological feature clearing commencing.

 
As indicated
22(b) During Vegetation/ Ecological Feature Clearing

The licensed Fauna Spotter Catcher must be present on site during all clearing operations to monitor works and to respond to any fauna situations that may arise. If any fauna is identified in vegetation or ecological features to be removed during clearing operations, work must cease immediately on that vegetation or ecological feature. The licensed Fauna Spotter Catcher must supervise the relocation of any identified fauna prior to vegetation/ ecological feature clearing recommencing.

Timing: While vegetation/ ecological feature clearing is occurring

 
As indicated
22(c) Submit Certification

Submit to Development Services certification from the licensed Fauna Spotter Catcher that vegetation/ ecological feature clearing was carried out in accordance with this condition.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)

 
As indicated
 
23)   Arboricultural Requirements

The following arboricultural requirements are to be performed to ensure the long-term health and safety of trees to be retained:

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
23(a) Site Works

In consultation with Development Assessment, the Arborist is to direct the civil works contractor in relation to any service installation activities utilising alternative technologies such as directional-boring or under-boring using vacuum excavation or air-spade. The Arborist must be a suitably qualified arboricultural consultant (minimum AQF Level 5 Diploma in Arboriculture).

 
While site/operational/building work is occurring
23(b) Certification

Submit to Development Assessment, certification from a suitably qualified arboricultural consultant (minimum AQF Level 5 Diploma in Arboriculture) that all necessary arboricultural works have been carried out in accordance with the requirements of all parts of this condition.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
23(c) Vegetation Pruning

Any necessary pruning, tree surgery and other maintenance works to maintain health and stability of any trees to be retained, and to reduce potential hazards for future residents, is to be carried out in consultation with Development Assessment.

All works must be performed by a suitably qualified arboricultural consultant (minimum AQF Level 5 Diploma in Arboriculture) in accordance with the Australian Standard 4373/96 for Pruning of Amenity Trees.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
Landscape Architecture and Open Space Planning
 
Timing
24)   Landscape the Site - Self Certification

Landscape the site in accordance with the requirements of this condition.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
24(a) Landscape Plan for Self Certification

Prepare a detailed Landscape Plan at a scale of 1:100 for all on-site landscape works identified on the approved DRAWINGS AND DOCUMENTS. The plan must be prepared by a registered Landscape Architect and must comply with the relevant Brisbane Planning Scheme Code. The plan must be certified by the registered Landscape Architect using Brisbane City Council Form CC10616 - Landscape Design Certification and the form must be submitted to Development Services.

In addition to the requirements listed above, the plan must include the following:

Planting
- Provide columnar trees at 3.0 metre intervals where possible along site boundaries
- Provide screening trees and shade trees along the entire length of the rear boundary
- Provide one small shade tree to each private courtyard
- Provide flowering / shade trees within the frontage at maximum centres of 6.0 metre, provided as 45 litre stock or larger, staked and tied
- Provide shade trees along driveways where possible
- Provide low shrubs and groundcovers to all landscape areas
- Provide a minimum of 2m wide landscaping for the street frontage excluding the driveway crossover and pedestrian access
- Provide a minimum of 1.5m wide landscaping for a side boundary excluding the area for built to boundary walls
- Provide a minimum 1m wide landscaping for a side boundary, where a driveway is located adjacent to the boundary
- Provides one tree per 20m of frontage capable of growing 15m high (minimum) at maturity
- Provide tree planting to achieve a minimum of 25% shade to outdoor communal spaces within 5 years
- Provide tree species that can provide a minimum 50% shade cover to a site’s open space within 10 years
- Provide a minimum of 25% landscaping within communal outdoor space consisting of a balanced combination of soft and hard landscape features
- Provide a minimum of 25% landscaping at a minimum 1m dimension within private open space areas on ground or in structure
Provide a minimum of 1 shade tree for every 6 car spaces

Amenity
- Ensure appropriate measures are taken to allow the healthy retention of existing vegetation where this is situated outside the building footprint
- Trees required to be retained are documented, protected and integrated into the landscape design in accordance with Australian Standard - AS4970 Protection of trees on development sites
- Provide a prioritised pedestrian entry to the units front and rear
- Fences and retaining walls must not exceed 2.0 metres in height from ground level unless stepped back and planted
- Hard surfaces must grade to landscaped areas
- Provide a hose cock for each courtyard

Containerised Planters
- Clearly identify the location, width and depth of containerised planting areas
- Details of raised planters must demonstrate adequate width, depth and suitability of soil for the proposed planting. Minimum internal depths of planters must be: trees – 1500mm; large shrubs and palms – 800mm; small shrubs
and groundcovers – 600mm
- Provide a reticulated drip irrigation system (connected to non-town water source) to all containerised planting areas, with drainage connected to the stormwater system

Terraced Retaining Walls
- Terracing of retaining walls in accordance with the relevant Brisbane Planning Scheme Codes. Planting must consist of drought-hardy small trees, medium shrubs and groundcovers planted at densities that, under normal growing conditions, will result in complete surface mulch coverage within 12 months of planting

Specifications
- Provide mulch and soil to meet Australian Standards
- Ensure that soil media is ameliorated to increase its water- holding abilities

Timing:  Prior to building work above ground level commencing

 
As indicated
24(b) Implement Certified Landscape Plan

Carry out the landscaping work in accordance with the above certified detailed Landscape Plan.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first

 
As indicated
24(c) Certify Work

On completion of the landscaping work, submit to Development Services Brisbane City Council Form CC10613 - Landscape Works Certificate prepared by a registered Landscape Architect or licensed Landscape Contractor to certify the completed landscaping work complies with the certified detailed Landscape Plan.

Note: A copy of the as-constructed detailed Landscape Plan must accompany the completed Landscape Works Certificate.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
24(d) Maintain Landscape Work

Maintain the landscape work generally in accordance with the certified detailed Landscape Plan.

Timing: To be maintained

 
As indicated
 
Pollution
 
Timing
25)   Plant and Equipment Certification

Submit to Development Services certification that the installation of all mechanical plant and equipment (e.g. air conditioning, mechanical ventilation and refrigeration equipment and heat pump hot water systems), is adequately noise-attenuated and is in accordance with the criteria of the relevant Brisbane Planning Scheme Codes.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
26)   Hours of Operation - Vehicle movements

Operation of trucks and commercial vehicles (excluding waste collection vehicles) during the operational phase of the development must only occur between 7am - 7pm Monday to Saturday.

 
To be maintained
 
Engineering
 
Timing
27)   Filling and / or Excavation

All proposed earthworks must be carried out in accordance with the relevant Brisbane Planning Scheme Codes.

Timing: Prior to building work commencing (MCU or BW) or prior to Council's notation of the plan of subdivision (ROL)

 
As indicated
27(a) Submit Earthworks Drawings

Submit for the approval of Development Services earthworks drawings prepared and certified by a Registered Professional Engineer Queensland in accordance with the approved DRAWINGS AND DOCUMENTS and the relevant Brisbane Planning Scheme Codes.

The Earthworks Drawings must include the following:

- The location of any cut and/or fill;

- The quantity of fill to be deposited and finished fill levels;

- Maintenance of access roads to and from the site such that they remain free of all fill material and are cleaned as necessary;

- The existing and proposed finished levels in reference to the Australian Height Datum (including cross-sections or long sections into the adjacent properties);

- Preservation of all drainage structures from the effects of structural loading generated by the earthworks;

- Protection of adjoining properties and roads from ponding or nuisance from stormwater;

- That all vehicles exiting from the site will be cleaned and treated so as to prevent material being tracked or deposited on public roads.

Note:

If the earthworks impact on the road reserve, the Developer must obtain applicable footpath and road permits prior to commencing any works.  Such impacts may include footpath occupation, road closures, re-profiling, ground anchors and/or relocation of services.  If the excavation has to be stabilised using ground anchors or similar then the submitted plans must show the location of these in relation to all services. The cost of moving services, utilities and assets is the responsibility of the Developer. The permission of the service/utility/asset owner is required.
Timing: Prior to site/operational/building work commencing

 
As indicated
27(b) Fill Material, Placement, Compaction and Testing

All fill material placed on the site must comprise only natural earth and rock and must be free of contaminants (as defined by Part 3, Division 2, Subdivision 2 Environmental contamination, Section 11 of the Environmental Protection Act) and noxious, hazardous, deleterious and organic materials.

Fill material, placement, compaction and testing must comply with the requirements of Australian Standard - AS 3798, Guidelines on Earthworks for Commercial and Residential Developments.

Timing: While site/operational/building work is occurring

 
As indicated
27(c) Implement Approved Earthworks Drawings

Construct and maintain the earthworks in accordance with the requirements of AS3798 and the approved earthworks drawings.

Timing: While site/operational/building work is occurring and then to be maintained

 
As indicated
27(d) Submit As Constructed Drawings

Submit to Development Services “As Constructed” drawings prepared by a Registered Surveyor.

Timing: Prior to building work commencing (MCU or BW) or prior to Council's notation of the plan of subdivision (ROL)

 
As indicated
27(e) Submit Certification

Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the approved earthworks drawings.

Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that all fill material used complies with the quality requirements of this condition and that placement, compaction and testing has been carried out in accordance with AS3798.

Timing: Prior to building work commencing (MCU or BW) or prior to Council's notation of the plan of subdivision (ROL)

 
As indicated
 
28)   On-site Erosion (medium risk)

Minimise on-site erosion and the release of sediment or sediment laden stormwater from the site at all times.

Timing: While site works are occurring and until all exposed soil areas are permanently stabilised against erosion.

 
As indicated
28(a) Prepare Erosion and Sediment Control Plan

Prepare Erosion and Sediment Control (ESC) Plan(s), and provide design certificates for the site in accordance with the relevant Brisbane Planning Scheme Codes.

The plan(s) and design certificates must be certified by a Certified Professional in Erosion and Sediment Control (CPESC) or a Registered Professional Engineer Qld (RPEQ) with suitable qualifications and experience in erosion and sediment control.

Documentary evidence demonstrating appropriate qualifications in erosion and sediment control must be provided to the Council upon request.

At least 10 days prior to either the pre-start meeting or commencement of site works, submit copies of design certificates to Council’s Compliance and Regulatory Services at:

CARS-ESC@brisbane.qld.gov.au

Timing: Prior to pre-start meeting or commencement of any site works and to be maintained until all exposed soil areas are permanently stabilised against erosion.

 
As indicated
28(b) Attend a pre-start meeting

Request and attend a pre-start meeting with an Erosion & Sediment Control Officer from Council’s Compliance and Regulatory Services.  Requests are to be made when submitting copies of all required documentation, including design certificates to: CARS- ESC@brisbane.qld.gov.au

 

Timing: Prior to commencement of any site works causing exposure of soil.

 
As indicated
28(c) Implement Certified Erosion and Sediment Control Plan

Implement the certified ESC plan(s) to maintain compliance with all parts of the relevant Brisbane Planning Scheme Codes, while site works are occurring and until all exposed soil areas are permanently stabilised against erosion.

The plan(s) and design certifications must be available on site at all times for inspection by Council officers until all exposed soil areas are permanently stabilised against erosion.

Minimise on-site erosion and the release of sediment or sediment laden stormwater from the site at all times.

 

Timing: While site works are occurring and until all exposed soil areas are permanently stabilised against erosion.

 

 

 
As indicated
 
29)   Information Signage

Erect an "Information Sign" on the subject property in accordance with Council’s general requirements for signage and in accordance with the requirements outlined below:

a) The sign should provide a brief description of the development proposed;
b) The sign is to list the name, postal and/or email address and a contact telephone number for the following parties (where relevant) that are undertaking work on the site:

     Developer;
     Project Coordinator;
     Architect/Building Designer;
     Builder;
     Civil Engineer;
     Civil Contractor/s; and
     Landscape Architect;

c) The lettering on the sign is to be at least 25 millimetres in height, be of regular weight and in sentence case;
d) The sign is to be a minimum size of 1,200 millimetres by 900 millimetres;
e) The maximum area of the sign is to be 2.0m2;
f) The sign is to be positioned as follows:

     located centrally along each road frontage of the site to Jackson and Jayef Streets;
     located on or within 1.5 metres of the road frontage;
     mounted at least 300 millimetres above ground level; and
     clearly visible from the street for a pedestrian;

g) The sign is to contain no commercial or corporate advertising other than the name, logo or slogan of the parties outlined in part (b) of this condition;
h) The sign is to be non- illuminated; and
i) Both the sign and the supporting structure are to be made of weatherproof material and to be properly maintained at all times;

Timing: Prior to site works commencing and then to be maintained until completion of the development for all stages.

 
As indicated
 
30)   Retaining Walls

Design and construct all retaining walls and associated fences, in accordance with the relevant Brisbane Planning Scheme Codes and including the following:

- All retaining walls including the footings, must be located wholly within the property boundary of the site where works are occurring
- Retaining walls to stabilise excavation must be set back off property boundaries to accommodate subsoil drainage without encroachment into the neighbouring property. This set back may vary depending on the height, structure and design of the retaining wall, including loadings from neighbouring properties, and to provide a surface drain along the top of the retaining wall
- Retaining walls that are greater than 1.0m in height must be vertically and horizontally tiered by a ratio of 1:1 unless an alternative has been approved by Development Services
- Runoff from surface drains and subsoil drainage associated with the retaining wall must be collected and conveyed to a lawful point of discharge and must not cause any ponding, nuisance or disturbance to adjacent property owners
- Retaining walls in excess of 1.0m in height must be designed and certified by a Registered Professional Engineer Queensland
- Retaining walls facing onto Council property (including the road reserve and parkland) must not be constructed from timber.

 
Prior to site/operational/building work commencing
30(a) Certification of Retaining Walls

For retaining walls over 1.0m in height, obtain certification from a Registered Professional Engineer Queensland that the design and construction of the retaining wall and ancillary drainage is in accordance with this condition.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)

 
As indicated
 
31)   Protect Existing Infrastructure

Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure. Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations. The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements.

 
While site/operational/building work is occurring
31(a) As Constructed Drawings

Where alterations to existing infrastructure are required, submit to Development Services "As Constructed" drawings showing all new and/or rectification works and an asset register, prepared by a Registered Professional Engineer Queensland.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)

 
As indicated
31(b) Submit Certification

Where alterations to existing infrastructure are required, submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)

 
As indicated
 
32)   Construction Management Plan - Major

Carry out development in accordance with a Construction Management Plan prepared in accordance with the requirements of this condition.

 
While site/operational/building work is occurring
32(a) Submit Construction Management Plan

Submit for the approval of Development Services a Construction Management Plan for the demolition, excavation and construction phases of the approved development. Separate Construction Management Plans may be appropriate for the individual components. The Construction Management Plan must be in accordance with the relevant Brisbane Planning Scheme Codes, Workplace Health and Safety Legislation, Environmental Protection Act, the requirements of any Concurrence Agency, any other relevant legislative requirements and the following.

The Construction Management Plan must be supported by Permits or written approvals from the relevant Council sections or other body listed below (where applicable to the Plan) to ensure all potential impacts to Council and other infrastructure have been addressed:

(i) Work Zones / Temporary Road Closures / Taxi Ranks - (Congestion Reduction Unit, Planned Incident Management / Temporary Road Closures);
(ii) Full/Partial Footway-Footpath Closures – (Brisbane Infrastructure – Congestion Reduction Unit);
(iii) Street Lighting - (Brisbane Infrastructure - Asset Services-City Lighting);
(iv) City Cycle bike stations and JCDecaux Advertising Signage (including obstruction to sight lines for such advertising - owned by JCDecaux)- (Brisbane Infrastructure - Transport Planning and Strategy, Contract Management section);
(v) Street Furniture (excluding bus stops) - (Brisbane Infrastructure, Transport Network Operations, Roads and Drainage);
(vi) Waste Bins - (Brisbane Infrastructure, Waste Service);
(vii) Bus Stops/Shelters - (Brisbane infrastructure - Transport Planning and Strategy-Strategic Planning; and Brisbane Transport - Network Planning & Bus Operations);
(viii) Street Trees - (Brisbane Infrastructure - Asset Services - Arboriculture);
(ix) Parking Meters/Spaces - (Brisbane Infrastructure - City Parking);
(x) Traffic Signals - (Brisbane Infrastructure - Traffic Signals Operations);
(xi) Stormwater Gullies/Pits etc - (Brisbane Infrastructure - Roads and Drainage);
(xii) Other service providers - (e.g. Energex, Telstra, Optus, Queensland Urban Utilities, AGL);
(xiii) Erect Scaffolding/Hoarding Permit, (Queen Street Mall, Reddacliff Place, Chinatown Mall and Brunswick Street Mall) - (City Planning and Sustainability – City Malls Management, City Planning and Economic Development);
(xiv) Vehicle Access Permits, (Queen Street Mall, Reddacliff Place, Chinatown Mall and Brunswick Street Mall) - (City Planning and Sustainability - City Malls Management, City Planning and Economic Development).

The construction management plan must address the following:

(i) Provision for pedestrian management including alternative pedestrian routes, past or around the site;
(ii) Location of and impacts on any Council or other authority's assets on or external to the site;
(iii) Temporary vehicular access points and frequency of use;
(iv) Provision for loading and unloading materials including the location of any remote loading sites;
(v) Location of materials, structures, plant and equipment to be stored or placed on the construction site;
(vi) How materials are to be loaded/unloaded and potential impacts on existing street trees;
(vii) Location of proposed external hoardings and gantries, (with clearances to street furniture and other footpath assets, (e.g. CityCycle bike stations);
(viii) Employee and visitor parking areas;
(ix) Anticipated staging, programming;
(x) Provision for fire exit routes for other uses on the subject or adjoining sites;
(xi) Notify Development Services of construction considered necessary to be conducted out of normal business hours (where normal hours are defined as Monday to Saturday between 6:30am and 6:30pm excluding public holidays).
(xii) The details identified in (xi) above must be accompanied by a consultation strategy for seeking, recording and addressing the impacts of the work on the affected community.

Notes:
- Approval for footpath closures and/or temporary vehicle access will only be considered where it can be demonstrated that no other reasonable alternative can be provided due to site constraints and that safety, capacity and/or operation of public transport, vehicle and pedestrian traffic are not compromised.
- Proposed arrangements utilising any part of the road reserve for construction related activities, for example, on-street work zones, overhead gantries, or where paid parking spaces are impacted upon or pedestrian diversions proposed are subject to separate application fees and rental fees.
- The approved Construction Management Plan will not allow the carrying out of specific work activities for any phase of construction outside of normal hours.

Timing: Prior to site/operational/building work commencing.

 
While site/operational/building work is occurring
32(b) Construction Management Plan - Pre- start Meeting

Arrange a Pre-Start meeting with Development Services.

Timing: Prior to site/operational/building work commencing.

 
While site/operational/building work is occurring
32(c) Construction Management Plan - Associated Activities in Road Reserve

Obtain relevant approvals to carry out any works required by the approved Construction Management Plan, including the following, within the road reserve:

-   Temporary lane closures;
-   Restricted work zones (subject to relaxation of clearway hours and resolution of alternative kerb side allocation including bus zones);
-  Overcoming clearway restrictions;
-  Gantry erection.

Notes:
-  Applications will be assessed on the basis of road and footpath network operating conditions prevailing at the time. Council will consider impacts of other construction works or events that occur during the life of the permit.
-  All fees must be paid in full prior to any permit being granted by Council. Council may revoke any permits at any time for non-compliance with requirements or if it considers that safety, capacity and /or operation of public transport, vehicle and pedestrian traffic are likely to be compromised during the construction phase.

Timing: Prior to site/operational/building work commencing.

 
While site/operational/building work is occurring
32(d) Construction Management Plan - Documentation on Site

Legible copies of the approved Construction Management Plan and current permits must be kept on site and be made available on request at all times.

Timing: While site/operational/building work is occurring

 
While site/operational/building work is occurring
32(e) Construction Management Plan - Works to be Performed Out of Hours

Obtain approval from Development Services for any work that is to be undertaken outside of normal business hours - 6:30am to 6:30pm, Monday to Saturday.

Timing: Prior to site/operational/building work commencing.

 
While site/operational/building work is occurring
32(f) Implement Approved Construction Management Plan

Carry out the development in accordance with the approved Construction Management Plan.

Timing: While site/operational/building work is occurring.

 
While site/operational/building work is occurring
 
33)   Repair Damage to Kerb, Footpath Or Road

Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel and stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
34)   Access, Grades, Manoeuvring, Carparks, Signs and Line Marking

Construct access, parking and manoeuvring for vehicles on site in accordance with the relevant Brisbane Planning Scheme Codes, as indicated on the approved DRAWINGS AND DOCUMENTS, including the following:

i. A pavement of minimum Local road standard or equivalent surface material (including associated drainage) to the area on which motor vehicles will be driven and/or parked.

ii. Manoeuvring on site for a RCV and for the loading and unloading of vehicle(s).

iii. Parking on the site for 22 cars (66 in total), for the loading and unloading of vehicle(s) within the site

v. A minimum of 2.3 metres height clearance to all undercover parking areas and a minimum of 2.5 metres above parking spaces for people with disabilities.  The minimum clear height must be measured to the lowest protrusion from the ceiling (e.g. fire sprinklers, services, lighting fixtures, signs, etc).

vi. A height clearance sign located at the entrance(s) to undercover car parking areas and a directional visitor parking sign clearly visible from the vehicle entrance to the site.

vii. An appropriate area for the storage and collection of refuse, including recyclables, in a position which is accessible to service vehicles on the site.

viii. The internal paved areas must be signed and delineated in accordance with the approved drawings and Manual of Uniform Traffic Control Devices - Queensland Department of Transport and Main Roads - Transport Operations (Road Use Management) Act 1995.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
34(a) Submit certification

Submit to Development Services, certification from a Registered Professional Engineer Queensland, that the above requirements have been implemented in accordance with this condition.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first

 
As indicated
 
35)   Refuse Storage - On Site Bulk Collection

Provide a roofed and screened waste enclosure to accommodate the type and quantity of bulk waste/recycling bins required to service the development.
Bins must be located in an area which allows them to be manoeuvred from the bin storage area to the designated internal collection point.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
36)   Ponding of stormwater

Adjoining properties and roads are to be protected from ponding or nuisance from stormwater as a result of the works.  Ensure the stormwater runoff from the site does not adversely impact on flooding or drainage (peak discharge and duration for all events up to the 100 year Average Recurrence Interval (ARI)) of properties that are upstream, downstream or adjacent to the site.

Notes.
-  If remedial works are required that involve drainage, drawings are to be submitted and approval obtained from Development Services, to provide a means to rectify the site drainage.

-  This condition is imposed to ensure that the developer is aware that they are responsible for all remedial works required as a result of any site works and, that they must protect neighbouring properties and roads from ponding and nuisance water from the proposed development.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
37)   On Site Drainage - Minor

Provide a stormwater connection to all new or existing allotments and provide drainage infrastructure to ensure stormwater run-off from all roof and developed surface areas will be collected internally and piped in accordance with the relevant Brisbane Planning Scheme Codes to a lawful point of discharge.

Note: Guidance for the preparation of drawings and/or documents to comply with this condition is provided in the Brisbane Planning Scheme Policies

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained
37(a) Submit As Constructed Drawings

Where reconfiguring a lot, submit to Development Services "As Constructed" drawings prepared by a Registered Professional Engineer Queensland.

Timing: Prior to Council's notation of the plan of subdivision

 
As indicated
37(b) Submit Certification

Where reconfiguring a lot, submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with this condition.

Timing: Prior to Council's notation of the plan of subdivision

 
As indicated
 
38)   Service Conduits and Mains

Provide and install all service conduits and meet the cost of any alterations to public utility mains, existing mains, services or installations that are required to carry out the approved development. These works must be in accordance with the relevant Brisbane Planning Scheme Codes, and include the following, where applicable:

- the provision of all services and/or conduits along the full length of any rear allotment access or access easement.
- the breaking and/or relocation of any existing sewer combine drains.
- the relocation of any fire hydrant and/or valves from the development's vehicular footway crossings.
- the retention and/or relocation of any existing foul water lines that currently exist within the site

Note:  Applicants must liaise with the appropriate service authorities. Typical underground services and/or conduits to be constructed include power, phone, telecommunications, sewer (including private combine drains) stormwater and gas, if applicable.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
38(a) Submit As Constructed Drawings

Submit to Development Services "As Constructed" drawings, including an asset register, prepared by a Registered Professional Engineer Queensland.


Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)

 
As indicated
38(b) Submit Certification

Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the requirements of this condition.

Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)

 
As indicated
 
39)   Telecommunications

Submit to Development Services, certification from an authorised telecommunications carrier/contractor, that the following works and infrastructure have been undertaken and installed in accordance with telecommunications industry standards:

a)     Provide telecommunications to the subject buildings, lead-in conduits and equipment space in a suitable location within the buildings, to suit the carrier of choice.

b)    If new pits and conduit infrastructure are required to be installed within the road reserve fronting the site, it must be suitably sized to cater for future installation of fibre optic cables.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
40)   Agreement with Electricity Supplier

Submit to Development Services, evidence of an agreement with an electricity supplier to provide necessary services to the development in accordance with the relevant Brisbane Planning Scheme Codes.

 
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL)
 
Standard Advice
 
Timing
41)   Breaking Combine Sewer Drain

The development site is currently served by a combined sewer drain.  A condition of this development has not been set to break the combined drain, however it may be a requirement of the plumbing approval that the sewerage reticulation is extended to break the combined drain.  Please contact Council's Plumbing Services for further advice prior to commencement of any site or building works.

Please note: The above information has been provided to the applicant as an advice only, and does not form part of the development approval conditions.  This advice has been provided to the applicant to inform them of other obligations they may have to comply with (under state legislation or local laws) prior to their activity commencing.

 
As indicated
 
42)   Food Hygiene

All development involving the preparation, packing, storing, handling, serving, selling or carrying of food requires that its design, installation and operation be approved pursuant to the Food Act 2006.  The premises must be registered and the operator must hold a licence with Brisbane City Council to operate the business under the above provisions.

Licences can be obtained from Brisbane City Council.  To obtain a Licence Information Kit contact Council on 3403 8888.

 
As indicated
 
43)   Further Development Permit required

This Preliminary Approval (Carrying Out Building Works) does not include assessment under the Building Act and does not permit building work to occur.  Prior to the commencement of any building work, Development Permit(s) for Carrying Out Building Work will be required.

 
As indicated
 
44)   Construction Noise and Dust Emissions

Pursuant to the Environmental Protection Act 1994, all development involving the emission of noise and dust from building and/or construction activities, must ensure that the emissions are in accordance with the requirements of the Act. 

The Environmental Protection Act 1994 prescribes that: 

1. A person must not carry out building work in a way that makes an audible noise-

  - on a business day or Saturday, before 6.30a.m. or after 6.30p.m; or

  - on any other day, at any time. 

2. The reference in subsection (1) to a person carrying out building work-

  - includes a person carrying out building work under an owner-builder permit; and

  - otherwise does not include a person carrying out building work at premises used by the person only for residential purposes.    

Note:   A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management delegate Development Services.

 
As indicated
 
45)   Plumbing and Drainage Work

Pursuant to the Plumbing and Drainage Act 2002, any plumbing and drainage work must be carried out in compliance with the Standard Plumbing and Drainage Regulation. Compliance assessable plumbing and drainage work requires approval by Brisbane City Council prior to the work being carried out.

 
As indicated
 
46)   Natural Assets Local Law (NALL) - On Site

Lodge and receive approval from Development Assessment, an application to Carry Out Works on Protected Vegetation on the site.

 
Prior to site/operational/building work commencing
 
47)   Standard Building Regulations

This approval does not include assessment against the siting requirements of the Queensland Development Code.  Should the approved development require a siting variation against the Queensland Development Code, an application for a Siting Variation must be submitted for the approval of Brisbane City Council - Compliance and Regulatory Services.

Note.  This development approval does not commit Compliance and Regulatory Services to approve any siting variation shown on the approved drawings.

 
As indicated
 
48)   Advice

Please note that the information contained in this section under the heading Standard Advice has been provided as advice only and does not form part of the development approval conditions.  This information has been provided to advise of other obligations under state legislation or local laws that may require action to be undertaken prior to commencing the activity approved by this development approval.

 
As indicated
 
49)   Equitable Access

Provision must be made for equitable access for persons with disabilities to and within the site in accordance with the Queensland Anti- Discrimination Act 1991, the Federal Disability Discrimination Act 1992 and Australian Standard AS1428 Parts 1-4, Australian Standard for Access and Mobility and the National Construction Code.

 
As indicated
 
50)   Water and Wastewater

Services for water and wastewater (sewerage) are no longer under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections requires a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. Any necessary Water Approval must be obtained from the relevant distributor- retailer (currently operating as Queensland Urban Utilities for the Brisbane City Council area).

For the purpose of compliance assessment of a subdivision plan pursuant to Schedule 19 of the Sustainable Planning Regulation 2009 (whether in relation to a development permit for Reconfiguring a Lot or a Building Format Plan subsequent to a development permit for a Material Change of Use), documentary evidence, issued by the relevant distributor-retailer, must be provided to Council to verify that the conditions of any necessary Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009, have been complied with.

 
As indicated
 
51)   Fire Ant Movement Controls

To prevent the spread of fire ants, the Queensland Government has implemented movement controls in areas of Queensland (biosecurity zones) where this pest species has been detected. These controls apply to individuals and commercial operators, and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products.

Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014.

If you are unsure of your obligations contact the relevant Queensland State Government Department (Biosecurity Queensland, Department of Agriculture and Fisheries)

 
As indicated
 
52)   Treatment Of Asbestos

Disposal, handling, removal and restoration of any building materials containing asbestos shall be in accordance with the Workplace Health and Safety Regulations 1989.

Disposal of asbestos may constitute a Schedule 2 - Notifiable Activity under the Environmental Protection Act 1994. Under this Act, landowners must inform the Department of Environment and Heritage Protection (EHP) that land has been or is being used for a notifiable activity. Prior approval from the Department of Environment and Heritage Protection may be required, as determined by the Agency.

The developer / site owner shall contact the EHP for advice, prior to commencing building work on the site.

 
As indicated
 

** End of Package **