| Address of Site: | 15 WILKINS ST E ANNERLEY QLD 4103 |
| Real Property Description of Site: | L16/17 RP.37866 |
| Aspects of development and type of approval: | DA - SPA - Carry out Building Work Preliminary Approval under s241 -
Demolition,Dwelling House DA - SPA - Carry out Building Work Preliminary Approval under s241 - Multiple Dwelling DA - SPA - Material Change of Use Development Permit - Multiple Dwelling |
| Council File Reference: | A007043433 Permit Reference Number/s: DABW296254514; DABW296254414; DAMC295902714. |
| Package Status: | APPROVED - Version 5 (14th of August, 2026 4:04:10 PM) |
| Package Generated: | 14/08/2026 |
| Allan NGUYEN Senior Urban Planner Planning Services South Allan.Nguyen@brisbane.qld.gov.au 3178 2207 |
Jenevere HEADING Principal Urban Planner Planning Services Governance Jenevere.Heading@brisbane.qld.gov.au (07) 3403 0124 |
Dalina HOWDEN Trunk Infrastructure & Calculations dalina.howden@brisbane.qld.gov.au (07) 3178 3895 |
| Kate POWER Senior Urban Planner House & Homes Kate.Power@brisbane.qld.gov.au (07)317 82616 |
Graeme BOLTON Principal Urban Planner Development Assessment Planning Services South Graeme.Bolton@brisbane.qld.gov.au 34034966 |
Anne FREEMAN Senior Urban Planner Development Assessment Infrastructure Charges Team anne.freeman@brisbane.qld.gov.au 3403 4092 |
| Zoc PANKALUIC Urban Planner Development Assessment Planning Services South zoc.pankaluic@brisbane.qld.gov.au 3407 0316 |
Brendan GILLHAM Planning Services Manager Planning Services Brendan.Gillham@brisbane.qld.gov.au (07) 3403 5958 |
Jennifer SNEESBY Team Manager (Acting) Planning Services City West Jennifer.Sneesby@brisbane.qld.gov.au (07) 3403 4436 |
| Jordan HEIT Senior Urban Planner Planning Services East Jordan.Heit@brisbane.qld.gov.au (07) 3403 9759 |
BILJANA DE SOUSA Planning Paratech Planning Application Review Service biljana.desousa@brisbane.qld.gov.au 3403 4737 |
Hayley STEEL Team Manager (Acting) Planning Services Special Assessment Hayley.Steel@brisbane.qld.gov.au (07) 3178 0022 |
| Llewellyn BATSON Principal Urban Planner Planning Services Special Assessment Llewellyn.Batson@brisbane.qld.gov.au (07) 340 34980 |
Diana SUN Urban Planner Planning Services South Diana.Sun@brisbane.qld.gov.au 0731785179 |
Ashleigh COOMBES Principal Urban Planner Planning Services South Ashleigh.Coombes@brisbane.qld.gov.au (07) 3403 1937 |
DRAWINGS AND DOCUMENTS
| Drawing or Document | Number | Plan Date |
|---|---|---|
| Site Plan - Proposed | DA-A-03b rev. 02 (Amended In Red 11-AUG-2026) | 08-JUN-2026 (Received) |
| MUD A Basement Floor Plan | DA-B-02 rev. 01 | 08-JUN-2026 (Received) |
| MUD A Ground Floor Plan - Proposed | DA-B-03 rev. 02 | 08-JUN-2026 (Received) |
| MUD A First Floor Plan | DA-B-04 rev. 02 | 08-JUN-2026 (Received) |
| MUD A Roof Plan | DA-B-05 | 23-MAY-2016 (Received) |
| MUD B Ground Floor Plan - Proposed | DA-B-06b rev. 02 | 08-JUN-2026 (Received) |
| MUD B First Floor Plan - Proposed | DA-B-07b rev. 02 | 08-JUN-2026 (Received) |
| MUD B Roof Plan - Proposed | DA-B-08b rev. 02 | 08-JUN-2026 (Received) |
| MUD A South Elevation (street) | DA-B-09 rev. 02 | 08-JUN-2026 (Received) |
| MUD A North Elevation | DA-B-10 rev. 02 | 08-JUN-2026 (Received) |
| MUD A East Elevation | DA-B-11 rev. 02 | 08-JUN-2026 (Received) |
| MUD A West Elevation | DA-B-12 rev. 02 | 08-JUN-2026 (Received) |
| MUD B North Elevation - Proposed | DA-B-13b rev. 01 | 08-JUN-2026 (Received) |
| MUD B South Elevation - Proposed | DA-B-14b rev. 02 | 08-JUN-2026 (Received) |
| MUD B East & West Elevation - Proposed | DA-B-15b rev. 02 | 08-JUN-2026 (Received) |
| Patio Area - Elevation Plans | SK01 (Amended In Red 13-AUG-2026) | 11-AUG-2026 (Received) |
| Patio Area - Side Elevations | SK02 (Amended In Red 13-AUG-2026) | 11-AUG-2026 (Received) |
| Section 1-1 | DA-B-16 (Amended In Red 14-AUG-2026) | 23-MAY-2016 (Received) |
| Section 2-2 (U1) | DA-B-17 (Amended In Red 14-AUG-2026) | 23-MAY-2016 (Received) |
| Section 3-3 (U2) | DA-B-18 (Amended In Red 14-AUG-2026) | 23-MAY-2026 (Received) |
APPROVAL CONDITIONS
| Permit to Which These Conditions Relate: | DA - SPA - Carry out Building Work |
| Activity(ies): | Demolition Dwelling House |
| Stage: | Partial Demolition of Pre-1946 dwelling |
| 1) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS
AND DOCUMENTS and the Development Approval Package must be available on
site. |
While site/operational/building work is occurring |
| 2) Carry Out the Approved Development Carry out the
approved development generally in accordance with the approved DRAWINGS AND
DOCUMENTS as amended in red. |
While site/operational/building work is occurring and then to be maintained |
| 3) Complete All Building Work Complete all building work associated with this
development approval, including work required by any of the conditions included
in the Development Approval Package. Such building work must be carried out
generally in accordance with the approved DRAWINGS AND DOCUMENTS, and, where
the building work is assessable development, in accordance with a current
development approval. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
| 4) Maintain the Approved Development Maintain the approved development generally in
accordance with the approved DRAWINGS AND DOCUMENTS, and any relevant Council
engineering or other approval required by the conditions. |
To be maintained |
| 5) Partial Demolition of Building Partial demolition resulting from this approval must be in accordance with the APPROVED DRAWINGS AND DOCUMENTS and all building work must comply with this condition |
While site/operational/building work is occurring and then to be maintained |
5(a) Adequate Bracing Provide adequate bracing from the commencement of any
demolition work and throughout the demolition and construction phases of the
project, to ensure that all parts of the building not specifically designated
for demolition on the APPROVED DRAWINGS AND DOCUMENTS are retained and
protected. Timing: While site/operational/building work is occurring |
As indicated |
5(b) Retain Original Fabric Retain all existing external original fabric in the
sections of the building which are not being demolished. This will include, but
is not limited to, existing decorative detailing, balustrading, wall cladding,
windows, doors, stairs and roof sheeting. Timing: While site/operational/building work is occurring and then to be maintained |
As indicated |
5(c) Submit Certification Submit to Development Assessment
certification by a Registered Architect / Building Designer (QBCC Open Licence)
confirming that the partial demolition has been carried out in accordance with
the requirements of this condition. Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use |
As indicated |
| 6) Retain and Protect Existing Street Tree(s) Identify, retain and protect
the existing street trees unless otherwise agreed in writing with Asset
Services. |
While site/operational/building work is occurring |
6(a) Implement Protection
Measures Install
tree protection measures in accordance with Australian Standard - AS4970
Retention of Trees on Development Site. |
As indicated |
6(b) Maintain Protection
Measures Maintain
protection measures while development is occurring and remove protection
measures prior to commencement of the use. |
As indicated |
| 7) Repair Damage to Kerb, Footpath Or Road Repair any damage to the
existing kerb and channel, footpath or roadway (including removal of concrete
slurry from footways, roads, kerb and channel and stormwater gullies and drainlines) and re-instate existing traffic signs and
pavement markings that have been removed or damaged during any works carried
out in association with the approved development. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 8) Ponding of Stormwater Carry out the approved development to ensure that
adjoining properties and roads are protected from ponding or nuisance from
stormwater as a result of the works. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 9) Further Development Permit required This Preliminary Approval (Carrying Out Building Works) does not include assessment under the
Building Act and does not permit building work to occur. Prior to the commencement of any building work,
Development Permit(s) for Carrying Out Building Work
will be required. |
As indicated |
| 10) Construction Noise and Dust Emissions Pursuant to the
Environmental Protection Act 1994, all development involving the emission of
noise and dust from building and/or construction activities, must ensure that
the emissions are in accordance with the requirements of the Act. |
As indicated |
| 11) Advice Please note that the information contained in this section under
the heading Standard Advice has been provided as advice only and does not form
part of the development approval conditions. This information has been provided to advise of other obligations under state legislation or local
laws that may require action to be undertaken prior to commencing the activity
approved by this development approval. |
As indicated |
| Permit to Which These Conditions Relate: | DA - SPA - Carry out Building Work |
| Activity(ies): | Multiple Dwelling |
| Stage: | Multiple Dwelling (4 units) |
| 12) Further Development Permit required This Preliminary Approval (Carrying Out Building Works) does not include assessment under the
Building Act and does not permit building work to occur. Prior to the commencement of any building work,
Development Permit(s) for Carrying Out Building Work
will be required. |
As indicated |
| Permit to Which These Conditions Relate: | DA - SPA - Material Change of Use |
| Activity(ies): | Multiple Dwelling |
| Stage: | Multiple Dwelling (4 units) |
| 13) Approved Drawings and Documents A legible copy of the
Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package
must be available on site. |
While site/operational/building work is occurring |
| 14) Carry Out the Approved Development Carry out the
approved development generally in accordance with the approved DRAWINGS AND
DOCUMENTS as amended in red. |
While site/operational/building work is occurring and then to be maintained |
| 15) Complete All Building Work Complete all building work associated with this
development approval, including work required by any of the conditions included
in the Development Approval Package. Such building work must be carried out
generally in accordance with the approved DRAWINGS AND DOCUMENTS, and, where
the building work is assessable development, in accordance with a current
development approval. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
| 16) Maintain the Approved Development Maintain the approved development generally in
accordance with the approved DRAWINGS AND DOCUMENTS, and any relevant Council
engineering or other approval required by the conditions. |
To be maintained |
| 17) Erect Screen Fence Erect a screen fence along the boundaries of the
site as shown on the approved DRAWINGS AND DOCUMENTS. Unless an alternative
design for the fence is agreed to with the owner of adjoining land, the screen
fence must be1.8metres in height. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 18) Bicycle Parking Install and maintain secure bicycle parking and associated
support facilities consistent with the approved DRAWINGS AND DOCUMENTS and in
accordance with the relevant Brisbane Planning Scheme
Codes. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 19) Security Lighting Install and maintain a suitable system of security
lighting to operate from dusk to dawn within all areas where the public may
gain access, including car parking areas, building entrances and vegetated
areas |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 20) Visitor Parking Visitor car parking spaces must: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 21) Car Parking The car parking within the premises must be maintained
exclusively for the ancillary use of the development. The parking must not be
made available to the general public and there must not be signage erected on
or in the vicinity of the site advertising the availability of car parking to
the general public. |
To be maintained |
| 22) Balconies and Terraces to Remain Unenclosed All balconies and terraces shown on the approved
drawings and documents, are to remain unenclosed with
no shutters, glazing, louvres or similar permanent
fixtures other than those consistent with the relevant Brisbane Planning Scheme
Codes/Policies and clearly depicted on the approved drawings. Any Community Management Statement is to contain a
by-law which reflects the requirements of this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 23) External Details External details of the building, facade treatment and external
materials, colours and finishes must be consistent with the approved DRAWINGS
AND DOCUMENTS. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 24) Overall Height The overall height of the proposed building(s) must be in accordance with the floor and roof levels and overall height shown on the APPROVED DRAWINGS AND DOCUMENTS. |
While site/operational/building work is occurring and then to be maintained |
24(a) Submit Certification Submit to Development
Assessment certification from a registered surveyor confirming that the
“as constructed” floor and roof levels and overall height are in
accordance with the requirements of this condition. Timing: Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 25) Provide Pedestrian Prioritised Pathway Provide a pedestrian prioritised
pathway from the street frontage to the front door of each unit. The pathway
must be differentiated in colour and texture from the driveway
surface. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 26) Driveway Material and Finishes Provide materials and finishes to the driveway
and external carparking surfaces that reduce the
visual impact of these areas when viewed from the street. One or a combination
of the following must be used: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 27) Screen Air Conditioning and Other Plant
Enclosures Install and maintain suitable
screening to all air conditioning, lift motor rooms, plant and service
facilities located at the top of or on the external face of the building. The
screening structures must be constructed from materials that are consistent
with materials used elsewhere on the facade of the building. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 28) Screening Multiple Dwelling / Dual
Occupancy Provide screening in accordance with the following: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 29) Retain and Protect Existing Street Tree(s) Identify, retain and protect
the existing street trees unless otherwise agreed in writing with Asset
Services. |
While site/operational/building work is occurring |
29(a) Implement Protection
Measures Install
tree protection measures in accordance with Australian Standard - AS4970
Retention of Trees on Development Site. |
As indicated |
29(b) Maintain Protection
Measures Maintain
protection measures while development is occurring and remove protection
measures prior to commencement of the use. |
As indicated |
| 30) Landscape the Site - Self Certification Landscape the site in accordance with the
requirements of this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
30(a) Landscape Plan for Self
Certification In addition to the requirements listed above, the plan must include the
following: |
As indicated |
30(b) Implement Certified Landscape
Plan Carry out the landscaping work in
accordance with the above certified detailed Landscape Plan. |
As indicated |
30(c) Certify Work Submit to Development Assessment certification
in accordance with Brisbane City Council Form CC10613 Landscape Works
Certificate from a registered Landscape Architect or licensed Landscape
Contractor that the completed landscape work complies with the certified
detailed Landscape Plan. |
As indicated |
30(d) Maintain Landscape Work Maintain the landscape work generally in accordance
with the certified detailed Landscape Plan. |
As indicated |
| 31) Plant and Equipment Certification Submit to Development
Assessment certification that the installation of all mechanical plant and
equipment (e.g. air conditioning, mechanical ventilation and refrigeration
equipment and heat pump hot water systems), is adequately noise-attenuated and
is in accordance with the criteria of the relevant Brisbane Planning Scheme
Codes. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 32) Acoustic Barrier - General Erect a 1.8 metre high acoustic barrier, (relative to the finished RL
of the building pad) along the side boundaries as shown of the approved plans.
The acoustic barrier must: |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
32(a) Certification Submit to Development
Assessment certification from an appropriately qualified professional that the
constructed acoustic barrier complies with the above requirements. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 33) Construction Management Plan (Minor) Prepare a Construction
Management Plan for the subject site. |
Prior to site/operational/building work commencing |
33(a) Implement Construction Management Plan
(minor) Carry
out the development in accordance with the Construction Management Plan
prepared in accordance with this condition. |
As indicated |
| 34) Retaining Walls Design and construct all
retaining walls and associated fences, in accordance with the relevant Brisbane
Planning Scheme Codes and including the following: |
Prior to site/operational/building work commencing |
34(a) Certification of Retaining
Walls For
retaining walls over 1.0m in height, obtain certification from a Registered
Professional Engineer Queensland that the design and construction of the
retaining wall and ancillary drainage is in accordance with this condition. |
As indicated |
| 35) Protect Existing Infrastructure Where there is existing
infrastructure in the vicinity of the proposed work, the new work must not
damage or compromise the working ability of the existing infrastructure. Should
the development be required to provide alterations to public utility mains,
existing mains, services or installations, then the developer must notify
Council or the relevant infrastructure provider prior to work commencing as
well as meet the costs of the alteration/s, which must be carried out in
accordance with the relevant Brisbane Planning Scheme Codes or infrastructure
providers requirements. |
While site/operational/building work is occurring |
35(a) As Constructed Drawings If alterations to existing infrastructure are
required then submit to Development Assessment "As Constructed"
drawings, showing all new and/or rectification works and an asset register,
prepared and certified by a Registered Professional Engineer Queensland
certifying that the works have been completed in accordance with the relevant
Brisbane Planning Scheme Codes and any other relevant infrastructure
requirements. |
As indicated |
| 36) Filling and / or Excavation (Minor) Filling and/or excavation
works on the site must be in accordance with the relevant Brisbane Planning
Scheme Codes. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
36(a) Prepare Earthworks
Drawings Earthworks drawings must be prepared and certified by either: a
Registered Professional Engineer Queensland or a suitably qualified
geotechnical and structural consultant, in accordance with the relevant
Brisbane Planning Scheme Codes. |
As indicated |
36(b) Implement and Maintain the
Earthworks Carry
out and maintain the earthworks in accordance with the certified drawings. |
As indicated |
| 37) Repair Damage to Kerb, Footpath Or Road Repair any damage to the
existing kerb and channel, footpath or roadway (including removal of concrete
slurry from footways, roads, kerb and channel and stormwater gullies and drainlines) and re-instate existing traffic signs and
pavement markings that have been removed or damaged during any works carried
out in association with the approved development. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 38) Remove Redundant Drainage Outlets Remove any redundant drainage
outlets from the kerb and channel including any associated pipe work across the
footway and reinstate the kerb and channel and the footway area in accordance
with the relevant Brisbane Planning Scheme Codes. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 39) Access, Grades, Manoeuvring, Carparks, Signs and
Line Marking Provide access, parking and manoeuvring for vehicles on site in
accordance with the relevant Brisbane Planning Scheme Codes, as indicated on
the approved DRAWINGS AND DOCUMENTS, including the following:
|
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
39(a) Provide certification Submit to Development
Assessment, certification from a Registered Professional Engineer Queensland,
that the above requirements have been implemented in accordance with this
condition. |
As indicated |
| 40) Refuse Collection - Kerb Side (external road or
internal private road) Refuse
and recycling bins for the proposed development must be collected from the kerb
side unless alternative refuse collection arrangements are made with Brisbane
City Council's Waste Services. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 41) Refuse Storage - Kerb Side Collection Provide a roofed and screened
waste enclosure to accommodate the type and quantity of waste/recycling bins
required to service the development. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 42) Site Drainage - Major Provide an internal drainage system to collect
stormwater run-off from the developed site, roofed and developed surface areas
and any run-off onto the site from adjacent areas and convey the collected run-
off to a lawful point of discharge, pumped systems are to comply with Section
7.6.6.2 – Pumps and Storage Design Chapter 7 Stormwater drainage of the
City Plan 2014, and in accordance with the relevant Brisbane Planning Scheme
Codes. Note. The stormwater design must ensure the stormwater
runoff from the site does not adversely impact on flooding or drainage (peak
discharge and duration for all storm events up to the 1% AEP event) of
properties that are upstream, downstream or adjacent to the site. Some developments may require
implementation of one or more mitigation measures to offset adverse impacts,
(e.g. stormwater detention, rainwater tanks, and upgrade of stormwater drainage
infrastructure). |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
42(a) Submit Site Drainage
Drawings Submit
and obtain approval from Development Assessment, site drainage drawings and
engineering calculations, prepared and certified by a Registered Professional
Engineer Queensland, in accordance with the relevant Brisbane Planning Scheme
Codes. |
As indicated |
42(b) Implement Approved
Drawings Carry
out the works in accordance with the approved site drainage drawings. |
As indicated |
42(c) Submit As Constructed
Drawings Submit
"As Constructed" drawings prepared by a Registered Professional
Engineer Queensland certifying that the works have been completed in accordance
with the approved site drainage drawings. |
As indicated |
| 43) Ponding of Stormwater Carry out the approved development to ensure that
adjoining properties and roads are protected from ponding or nuisance from
stormwater as a result of the works. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 44) Water Approval Obtain from the
relevant distributor-retailer, any necessary water approval under the South-East
Queensland Water (Distribution and Retail Restructuring) Act
2009. |
Prior to site/operational/building work commencing |
| 45) Service Conduits and Mains Provide and install all service conduits and meet
the cost of any alterations to public utility mains, existing mains, services
or installations that are required to carry out the approved development. These
works must be in accordance with the relevant Brisbane Planning Scheme Codes,
and include the following, where applicable: Note: Applicants must
liaise with the appropriate service authorities. Typical underground services
and/or conduits to be constructed include power, phone, telecommunications,
sewer (including private combine drains) stormwater and gas, if
applicable. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
45(a) As Constructed Drawings Submit to Development Assessment "As Constructed" drawings,
including an asset register, prepared by a Registered Professional Engineer
Queensland certifying that the above works are in accordance with this
condition. |
As indicated |
| 46) Telecommunications Submit to Development Assessment, certification
from an authorised telecommunications carrier/contractor, that the following
works and infrastructure have been undertaken and installed in accordance with
telecommunications industry standards: a) Provide telecommunications to the subject buildings, lead-in conduits and equipment space in a suitable location within the buildings, to suit the carrier of choice. b) If new pits and conduit infrastructure are required to be installed within the road reserve fronting the site, it must be suitably sized to cater for future installation of fibre optic cables. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 47) Agreement with Electricity Supplier Submit to Development
Assessment, evidence of an agreement with an electricity supplier to provide
necessary services to the development in accordance with the relevant Brisbane
Planning Scheme Codes. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 48) Permanent Vehicle Crossover Provide a 4.0 metre wide permanent vehicle crossover to the frontage of the site in accordance with the relevant Brisbane Planning Scheme Codes and located as shown on the approved DRAWINGS AND DOCUMENTS.
The crossover must be located a minimum of 2m from the existing street tree. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 49) Redundant Crossover Remove the redundant existing vehicle crossing(s) on
the frontage(s) of the site and reinstate the kerb and channel, road pavement,
footways and footpaths in accordance with the relevant Brisbane Planning Scheme
Codes. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL) |
| 50) Construction Noise and Dust Emissions Pursuant to the
Environmental Protection Act 1994, all development involving the emission of
noise and dust from building and/or construction activities, must ensure that
the emissions are in accordance with the requirements of the Act. |
As indicated |
| 51) Construction Noise and Dust Emissions Pursuant to the
Environmental Protection Act 1994, all development involving the emission of
noise and dust from building and/or construction activities, must ensure that
the emissions are in accordance with the requirements of the Act. |
As indicated |
| 52) Natural Asset Local Law (NALL) - Protected
Vegetation on Public Land, Road or Park The interference with or removal of protected vegetation on a public land or park requires a permit under the Natural Assets Local Law 2003 (NALL), issued by Public Space Operations Arboriculture (PSO- Arb). Detailed arrangements must be made with PSO-Arb in relation to the works carried out on protected vegetation (including provision for tree removal and replacement tree planning costs as determined by PSO-Arb) prior to carrying out any works on protected vegetation. PSO-Arb can be contacted via ISG-CS-PPI-PLANNING-ARB@brisbane.qld.gov.au. Note: All requirements of development approval conditions with timing stipulated as 'prior to site works commencing' (or equivalent) must be fulfilled before Council can issue a NALL permit. |
As indicated |
| 53) Contaminated Materials and Soils Any contaminated materials or soils encountered during siteworks, must be handled, stored and disposed of in accordance with the requirements of the relevant authority of the Queensland Government. A person must not dispose of contaminated soil or a hazardous substance at a place other than at a place approved by the relevant authority of the Queensland Government. |
As indicated |
| 54) Further Development Permit Required Further Development Permit(s) to carry out assessable building work under the Building Act may be required. |
As indicated |
| 55) Plumbing and Drainage Work Pursuant to the Plumbing and Drainage Act 2018, any plumbing and drainage work must be carried out in compliance with the Plumbing and Drainage Regulation 2019. Note: All new and existing plumbing services should be located within the lot that they serve. Compliance assessable plumbing and drainage work requires approval by Brisbane City Council prior to the work being carried out. |
As indicated |
| 56) Equitable Access Provision must be made during and after construction
for equitable access for persons with disabilities to and within the site and
on adjoining public areas, in accordance with the following: |
As indicated |
| 57) Damage to Trees on Adjoining Land Please note that any damage caused to vegetation on adjoining land as a result of exercising this development approval may result in an offence under other legislation (e.g. Natural Assets Local Law) and/or civil action |
As indicated |
| 58) Fire Ant Movement Controls To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected. These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products. Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014. For further information contact the relevant Queensland State Government department on 13 QGOV. |
As indicated |
| 59) Water and Wastewater Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. For further information about any necessary Water Approvals contact Urban Utilities. |
As indicated |
| 60) Cultural Heritage Aboriginal cultural heritage is protected under the Aboriginal Cultural Heritage Act 2003. This Act establishes a cultural heritage duty of care and in section 23(1) mandates that a person who carries out an activity must take all reasonable and practicable measures for ensuring activities are managed to avoid or minimise harm to Aboriginal cultural heritage.
The Duty of Care Guidelines gazetted pursuant to the Aboriginal Cultural Heritage Act 2003 provide guidance on identifying and protecting Aboriginal cultural heritage to fulfil the duty of care.
For further information contact the relevant Queensland State Government Department (Department of Aboriginal and Torres Strait Islander Partnerships). |
As indicated |
| 61) Advice Please note that the information contained in this section under
the heading Standard Advice has been provided as advice only and does not form
part of the development approval conditions. This information has been provided to advise of other obligations under state legislation or local
laws that may require action to be undertaken prior to commencing the activity
approved by this development approval. |
As indicated |