| Address of Site: | 1356 LYTTON RD HEMMANT QLD 4174 |
| Real Property Description of Site: | L2 RP.129609 |
| Aspects of development and type of approval: | DA - PA - Building Work Development Permit - animal keeping DA - PA - Material Change of Use Development Permit - animal keeping |
| Council File Reference: | A006879600 Permit Reference Number/s: DABW468947525; DAMC468947625. |
| Package Status: | APPROVED - Version 1 (26th of May, 2026 1:55:35 PM) |
| Package Generated: | 26/05/2026 |
| Richard DITCHFIELD Technical Officer Engineering Services South richard.ditchfield@brisbane.qld.gov.au 34036751 |
Carina FIESELER Landscape Architect Landscape Architecture Team carina.fieseler@brisbane.qld.gov.au 3403 5235 |
Michael PICKERILL Network Planning Michael.Pickerill@brisbane.qld.gov.au |
| Kim ROGERS Principal Urban Planner Planning Services South kim.rogers@brisbane.qld.gov.au 34071304 |
Diana SUN Urban Planner Planning Services South Diana.Sun@brisbane.qld.gov.au 0731785179 |
Alessio ZANCOLICH Principal Urban Planner Planning Services South alessio.zancolich@brisbane.qld.gov.au (07) 3407 8514 |
| Fabrienne Michelle YU Principal Environmental Management Officer - Air Quality Environmental Management Services Michelle.Yu@brisbane.qld.gov.au 07 3403 0258 |
Craig SLACK Engineer Engineering Scoping craig.slack@brisbane.qld.gov.au (07) 3403 8888 |
Andrew BLAKE Principal Engineer Engineering Services Hydraulics andrew.blake@brisbane.qld.gov.au (07) 3403 5018 |
| Ben COVE Principal Engineer Engineering Services Traffic Ben.Cove@brisbane.qld.gov.au |
Matthew CRANITCH Technical Officer WaRRS Assessment Matthew.Cranitch@brisbane.qld.gov.au |
Daniel PULMAN Principal Engineering Officer Engineering Services South Daniel.Pulman@brisbane.qld.gov.au 3403 8888 |
| Ashleigh COOMBES Principal Urban Planner Planning Services South Ashleigh.Coombes@brisbane.qld.gov.au (07) 3403 1937 |
DRAWINGS AND DOCUMENTS
| Drawing or Document | Number | Plan Date |
|---|---|---|
| Site Plan | 01 C (Amended In Red 28-APR-2026) | 16-MAR-2026 (Received) |
| GROUND FLOOR_PROPOSED | 02 C (Amended In Red 28-APR-2026) | 16-MAR-2026 (Received) |
| FIRST FLOOR | 03 D | 20-MAY-2026 (Received) |
| SOUTH WEST | 04 C | 16-MAR-2026 (Received) |
| NORTH EAST | 05 C | 16-MAR-2026 (Received) |
| SECTION X SECTION Y | 06 C | 16-MAR-2026 (Received) |
APPROVAL CONDITIONS
| Permit to Which These Conditions Relate: | DA - PA - Building Work |
| Activity(ies): | animal keeping |
| Stage: | Animal Keeping (Doggy Daycare) in Flood Overlay |
| 1) Maintain the Approved Development Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions. |
At all times |
| 2) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers. Note: This condition is imposed to ensure compliance with the conditions of development approval. |
While site/operational/building work is occurring |
| 3) Carry Out the Approved Development Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS. Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners. |
While site/operational/building work is occurring |
| 4) Complete All Building Work Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS. Note: Building work must also be completed in accordance with any other current development approval. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 5) Construction Noise and Dust Emissions Pursuant to the
Environmental Protection Act 1994, all development involving the emission of
noise and dust from building and/or construction activities, must ensure that
the emissions are in accordance with the requirements of the Act. |
As indicated |
| 6) Natural Asset Local Law (NALL) - Protected
Vegetation on Public Land, Road or Park The interference with or removal of protected vegetation on a public land or park requires a permit under the Natural Assets Local Law 2003 (NALL), issued by Public Space Operations Arboriculture (PSO- Arb). Detailed arrangements must be made with PSO-Arb in relation to the works carried out on protected vegetation (including provision for tree removal and replacement tree planning costs as determined by PSO-Arb) prior to carrying out any works on protected vegetation. PSO-Arb can be contacted via ISG-CS-PPI-PLANNING-ARB@brisbane.qld.gov.au. Note: All requirements of development approval conditions with timing stipulated as 'prior to site works commencing' (or equivalent) must be fulfilled before Council can issue a NALL permit. |
As indicated |
| 7) Waste Liquids - Discharging to Sewerage
System Any waste liquids (including wastewater from wash down and sanitising operations) must be directed to the sewerage system subject to the requirements and recommendations of the Distributer Retailer Authority or collected for recycling or disposed of by a licensed contractor at a liquid waste treatment facility. |
As indicated |
| 8) Contaminated Materials and Soils Any contaminated materials or soils encountered during siteworks, must be handled, stored and disposed of in accordance with the requirements of the relevant authority of the Queensland Government. A person must not dispose of contaminated soil or a hazardous substance at a place other than at a place approved by the relevant authority of the Queensland Government. |
As indicated |
| 9) Further Development Permit Required Further Development Permit(s) to carry out assessable building work under the Building Act may be required. |
As indicated |
| 10) Plumbing and Drainage Work Pursuant to the Plumbing and Drainage Act 2018, any plumbing and drainage work must be carried out in compliance with the Plumbing and Drainage Regulation 2019. Note: All new and existing plumbing services should be located within the lot that they serve. Compliance assessable plumbing and drainage work requires approval by Brisbane City Council prior to the work being carried out. |
As indicated |
| 11) Currency Period The currency period for this development approval is stated in the Decision Notice and is expressed as a date. This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016. |
As indicated |
| 12) Referral Agency Requirements SARA as concurrence agency has imposed the requirements contained in the letter dated 18 December 2025. |
As indicated |
| 13) Trade Waste Approval Discharge of waste liquids to the sewerage system must be conducted in accordance with the conditions of a Trade Waste Approval. For further information on obtaining an approval, contact Urban Utilities. |
As indicated |
| 14) Equitable Access Provision must be made during and after construction
for equitable access for persons with disabilities to and within the site and
on adjoining public areas, in accordance with the following: |
As indicated |
| 15) Damage to Trees on Adjoining Land Please note that any damage caused to vegetation on adjoining land as a result of exercising this development approval may result in an offence under other legislation (e.g. Natural Assets Local Law) and/or civil action |
As indicated |
| 16) Fire Ant Movement Controls To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected. These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products. Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014. For further information contact the relevant Queensland State Government department on 13 QGOV. |
As indicated |
| 17) Water and Wastewater Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. For further information about any necessary Water Approvals contact Urban Utilities. |
As indicated |
| 18) Cultural Heritage Aboriginal cultural heritage is protected under the Aboriginal Cultural Heritage Act 2003. This Act establishes a cultural heritage duty of care and in section 23(1) mandates that a person who carries out an activity must take all reasonable and practicable measures for ensuring activities are managed to avoid or minimise harm to Aboriginal cultural heritage.
The Duty of Care Guidelines gazetted pursuant to the Aboriginal Cultural Heritage Act 2003 provide guidance on identifying and protecting Aboriginal cultural heritage to fulfil the duty of care.
For further information contact the relevant Queensland State Government Department (Department of Aboriginal and Torres Strait Islander Partnerships). |
As indicated |
| Permit to Which These Conditions Relate: | DA - PA - Material Change of Use |
| Activity(ies): | animal keeping |
| Stage: | Animal Keeping (Doggy Daycare) in Flood Overlay |
| 19) Maintain the Approved Development Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions. |
At all times |
| 20) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers. Note: This condition is imposed to ensure compliance with the conditions of development approval. |
While site/operational/building work is occurring |
| 21) Carry Out the Approved Development Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS. Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners. |
While site/operational/building work is occurring |
| 22) Complete All Building Work Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS. Note: Building work must also be completed in accordance with any other current development approval. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 23) Limitation of use Any animal grooming on-site must remain ancillary to the approved Animal Keeping use at all times. The ancillary office space/s on the site are to be limited to the area shown on the APPROVED DRAWINGS AND DOCUMENTS. This area/s must remain ancillary to the approved Animal Keeping use and must not operate separately. Should the approved Animal Keeping use cease, the use of the site for animal grooming and ancillary office area/s must also cease. Timing: At the time the approved use ceases. |
As indicated |
| 24) Hours of Operation Hours of operation for the approved animal keeping
(doggy day care) must be limited between 7am to 6pm. There is to be no boarding of animals overnight. |
At all times |
| 25) Close Southern Facade The southern facade (including the roller doors),
is to be closed at all times during hours of operation except for the sliding
door to the reception area which may be opened momentarily for ingress/egress
only. |
At all times |
| 26) Waste Liquids Waste liquids such as from dog washing or sanitation are to be directed to
sewer in accordance with a Trade Waste Permit issued by Urban Utilities or are
to be collected by a third-party contractor. Such waters are not to discharge
to ground or stormwater. |
At all times |
| 27) On-site Erosion (Low Risk) Manage on-site erosion
and the release of sediment or sediment laden water from the site at all times
by implementing best industry practice for sediment and erosion control as per
the International Erosion Control Association, Best Practice Erosion and
Sediment Control documents (2008 or later version). Including but not limited
to: Note: Guidelines and factsheets to assist with this are available from the 'Healthy Waterways - Water by Design' website at http://hlw.org.au/initiatives/esc/house-sites Timing: Prior to commencement of any earth disturbing activities and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
27(a) Provide Land Occupier Notification to
Council (i) Notify Council's ESC Team of proposed land occupier/s by sending an email to CARS-ESC@Brisbane.qld.gov.au (ii) If the land is to be occupied by any person other than the registered landowner then advice must be provided to Council that confirms the name, contact information and the duration of any proposed occupation of the land. Note: Occupier is any principal contractor occupying the land exercising a right under the development approval. Timing: Prior to commencement of any earth disturbing activities. |
As indicated |
| 28) Information Signage Erect an information sign on the subject property in
accordance with Council's general requirements for signage and in accordance
with the requirements outlined below: Timing: Prior to site works commencing and then to be maintained until completion of the development for all stages. |
As indicated |
| 29) Protect Existing Infrastructure Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure. Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations. The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements. |
While site/operational/building work is occurring |
29(a) As Constructed Drawings - Alterations
to Existing Infrastructure Submit to Development Services As Constructed drawings showing all new and/or rectification works and an asset register, prepared by a Registered Professional Engineer Queensland. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 30) Repair Damage to Kerb, Footpath or Road Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
30(a) Interim Repairs If at any time during the construction phase of the approved development, damage to the existing kerb and channel, footpath or roadway creates unsafe, unreasonable and/or not fit for purpose conditions as assessed by Council, interim repairs must be undertaken as directed by Program Planning and Integration. Note: Any interim repairs required to be undertaken shall not be considered to satisfy the requirements of this condition for the permanent repair of the infrastructure prior to the issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. Timing: While site / operational / building works is occurring. |
As indicated |
| 31) Access, Grades, Manoeuvring, Carparks, Signs and
Line Marking Construct and maintain access, parking and manoeuvring for vehicles on site in accordance with the relevant Brisbane Planning Scheme Codes, as indicated on the approved DRAWINGS AND DOCUMENTS, including the following: i. A pavement of minimum Local road standard or equivalent surface material (including associated drainage) to the area for the proposed tenancy driveway and on which motor vehicles will be driven and/or parked within the site. ii. Access to the site for the nominated refuse contractor’s refuse collection vehicle (RCV) and for the loading and unloading of vehicle(s). iii. Maintain the existing parking arrangement on the site and for the loading and unloading of vehicle(s) within the site. iv. An appropriate area for the storage and collection of refuse, including recyclables, in a position which is accessible to service vehicles on the site. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland, that the above requirements have been implemented in accordance with this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first and then to be maintained. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 32) Non-Residential Refuse Collection - On Site Provide for the installation and collection of refuse/recycling bins. |
At all times |
32(a) Arrange Refuse Collection Arrange for the installation of refuse/recycling bins and for the subsequent collection of refuse including recycling from the site by a private waste contractor.
Timing: A minimum of four weeks prior to the commencement of use and then to be maintained. PROOF OF
FULFILMENT Where a private waste contractor is engaged, provide written confirmation from the proposed waste collection contractor of the agreement to service the property. The written agreement must be submitted to Council's Waste and Resource Recovery Services and include full details of the proposed system, bin sizes, number of bins, frequency of collection and the refuse collection vehicle size. Prior to commencement of use |
As indicated |
| 33) Refuse Storage - On Site Collection Provide a roofed and wholly screened refuse enclosure utilising materials consistent with the development or a dedicated refuse storage room inside or attached to a building, in accordance with the City Plan 2014, Refuse Planning Scheme Policy. The enclosure/refuse storage room must be of a design to accommodate the quantity of refuse and recycling including source separation to allow for low servicing collection of the development. Bins must be located in an area which allows them to be manoeuvred from the bin storage area to the designated internal collection point. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 34) Ponding of Stormwater Carry out the approved development to ensure that adjoining properties and roads are protected from ponding or nuisance from stormwater during construction. Notes: If remedial works are necessary to comply with this condition, prior approval must be obtained from Development Services. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 35) On Site Drainage - Minor Provide a stormwater connection to all new or existing allotments and provide drainage infrastructure to ensure stormwater run-off from all roof and developed surface areas will be collected internally and piped in accordance with the relevant Brisbane Planning Scheme Codes to a lawful point of discharge. Note: Where connections are adjacent to a driveway crossover and within the TPZ of a street tree, Rectangular Hollow Section (RHS) is to be used. Note: - Guidance for requesting a pre- start and co-ordinating the On/Off Maintenance process can be found on Council's website (https://www.brisbane.qld.gov.au/planning-and- building/applying-and-post-approval/on-and-off-maintenance- approvals). |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 36) Service Conduits and Mains Provide and install all
service conduits, including street lighting as required by Council, and
meet the cost of any alterations to public utility mains, existing mains,
services, street lighting or installations that are required to carry out the
approved development. These works must be in accordance with the relevant
Brisbane Planning Scheme Codes, and include the following, where
applicable: Note: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
36(a) Submit Certification to
Council Submit to Development Services certification by a Registered Professional Engineer Queensland (RPEQ) that the works have been completed in accordance with the requirements of the condition. Note: Where rear allotment accesses or easements exist, the certification is to be supported by As-Constructed drawings certified by a RPEQ showing all services and/or conduits. Civil works are to be certified by a RPEQ (Civil) and electrical works are to be certified by a RPEQ (Electrical) Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the requirements of this condition. Note: Civil works are to be certified by a RPEQ(Civil) and electrical works are to be certified by a RPEQ (Electrical). |
As indicated |
| 37) Construction Noise and Dust Emissions Pursuant to the
Environmental Protection Act 1994, all development involving the emission of
noise and dust from building and/or construction activities, must ensure that
the emissions are in accordance with the requirements of the Act. |
As indicated |
| 38) Natural Asset Local Law (NALL) - Protected
Vegetation on Public Land, Road or Park The interference with or removal of protected vegetation on a public land or park requires a permit under the Natural Assets Local Law 2003 (NALL), issued by Public Space Operations Arboriculture (PSO- Arb). Detailed arrangements must be made with PSO-Arb in relation to the works carried out on protected vegetation (including provision for tree removal and replacement tree planning costs as determined by PSO-Arb) prior to carrying out any works on protected vegetation. PSO-Arb can be contacted via ISG-CS-PPI-PLANNING-ARB@brisbane.qld.gov.au. Note: All requirements of development approval conditions with timing stipulated as 'prior to site works commencing' (or equivalent) must be fulfilled before Council can issue a NALL permit. |
As indicated |
| 39) Waste Liquids - Discharging to Sewerage
System Any waste liquids (including wastewater from wash down and sanitising operations) must be directed to the sewerage system subject to the requirements and recommendations of the Distributer Retailer Authority or collected for recycling or disposed of by a licensed contractor at a liquid waste treatment facility. |
As indicated |
| 40) Contaminated Materials and Soils Any contaminated materials or soils encountered during siteworks, must be handled, stored and disposed of in accordance with the requirements of the relevant authority of the Queensland Government. A person must not dispose of contaminated soil or a hazardous substance at a place other than at a place approved by the relevant authority of the Queensland Government. |
As indicated |
| 41) Further Development Permit Required Further Development Permit(s) to carry out assessable building work under the Building Act may be required. |
As indicated |
| 42) Plumbing and Drainage Work Pursuant to the Plumbing and Drainage Act 2018, any plumbing and drainage work must be carried out in compliance with the Plumbing and Drainage Regulation 2019. Note: All new and existing plumbing services should be located within the lot that they serve. Compliance assessable plumbing and drainage work requires approval by Brisbane City Council prior to the work being carried out. |
As indicated |
| 43) Currency Period The currency period for this development approval is stated in the Decision Notice and is expressed as a date. This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016. |
As indicated |
| 44) Referral Agency Requirements SARA as concurrence agency has imposed the requirements contained in the letter dated 18 December 2025. |
As indicated |
| 45) Trade Waste Approval Discharge of waste liquids to the sewerage system must be conducted in accordance with the conditions of a Trade Waste Approval. For further information on obtaining an approval, contact Urban Utilities. |
As indicated |
| 46) Equitable Access Provision must be made during and after construction
for equitable access for persons with disabilities to and within the site and
on adjoining public areas, in accordance with the following: |
As indicated |
| 47) Damage to Trees on Adjoining Land Please note that any damage caused to vegetation on adjoining land as a result of exercising this development approval may result in an offence under other legislation (e.g. Natural Assets Local Law) and/or civil action |
As indicated |
| 48) Fire Ant Movement Controls To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected. These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products. Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014. For further information contact the relevant Queensland State Government department on 13 QGOV. |
As indicated |
| 49) Water and Wastewater Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. For further information about any necessary Water Approvals contact Urban Utilities. |
As indicated |
| 50) Cultural Heritage Aboriginal cultural heritage is protected under the Aboriginal Cultural Heritage Act 2003. This Act establishes a cultural heritage duty of care and in section 23(1) mandates that a person who carries out an activity must take all reasonable and practicable measures for ensuring activities are managed to avoid or minimise harm to Aboriginal cultural heritage.
The Duty of Care Guidelines gazetted pursuant to the Aboriginal Cultural Heritage Act 2003 provide guidance on identifying and protecting Aboriginal cultural heritage to fulfil the duty of care.
For further information contact the relevant Queensland State Government Department (Department of Aboriginal and Torres Strait Islander Partnerships). |
As indicated |