BRISBANE CITY COUNCIL'S APPROVAL PACKAGE.



APPLICATION DETAILS

This package relates to the application detailed below
Address of Site: 1356 LYTTON RD HEMMANT QLD 4174
Real Property Description of Site: L2 RP.129609
Aspects of development and type of approval: DA - PA - Building Work Development Permit - animal keeping
DA - PA - Material Change of Use Development Permit - animal keeping
Council File Reference: A006879600
Permit Reference Number/s: DABW468947525; DAMC468947625.
Package Status: APPROVED - Version 1 (26th of May, 2026 1:55:35 PM)
Package Generated: 26/05/2026


PROJECT TEAM

The assessment of this application has been undertaken by:
Richard DITCHFIELD
Technical Officer
Engineering Services South
richard.ditchfield@brisbane.qld.gov.au
34036751
Carina FIESELER
Landscape Architect
Landscape Architecture Team
carina.fieseler@brisbane.qld.gov.au
3403 5235
Michael PICKERILL

Network Planning
Michael.Pickerill@brisbane.qld.gov.au
Kim ROGERS
Principal Urban Planner
Planning Services South
kim.rogers@brisbane.qld.gov.au
34071304
Diana SUN
Urban Planner
Planning Services South
Diana.Sun@brisbane.qld.gov.au
0731785179
Alessio ZANCOLICH
Principal Urban Planner
Planning Services South
alessio.zancolich@brisbane.qld.gov.au
(07) 3407 8514
Fabrienne Michelle YU
Principal Environmental Management Officer - Air Quality
Environmental Management Services
Michelle.Yu@brisbane.qld.gov.au
07 3403 0258
Craig SLACK
Engineer
Engineering Scoping
craig.slack@brisbane.qld.gov.au
(07) 3403 8888
Andrew BLAKE
Principal Engineer
Engineering Services Hydraulics
andrew.blake@brisbane.qld.gov.au
(07) 3403 5018
Ben COVE
Principal Engineer
Engineering Services Traffic
Ben.Cove@brisbane.qld.gov.au
Matthew CRANITCH
Technical Officer
WaRRS Assessment
Matthew.Cranitch@brisbane.qld.gov.au
Daniel PULMAN
Principal Engineering Officer
Engineering Services South
Daniel.Pulman@brisbane.qld.gov.au
3403 8888
Ashleigh COOMBES
Principal Urban Planner
Planning Services South
Ashleigh.Coombes@brisbane.qld.gov.au
(07) 3403 1937


DRAWINGS AND DOCUMENTS



The term 'drawings and documents' or similar expressions mean:
Drawing or Document Number Plan Date
Site Plan 01 C (Amended In Red 28-APR-2026) 16-MAR-2026 (Received)
GROUND FLOOR_PROPOSED 02 C (Amended In Red 28-APR-2026) 16-MAR-2026 (Received)
FIRST FLOOR 03 D 20-MAY-2026 (Received)
SOUTH WEST 04 C 16-MAR-2026 (Received)
NORTH EAST 05 C 16-MAR-2026 (Received)
SECTION X SECTION Y 06 C 16-MAR-2026 (Received)


Advice

Please see the attached document(s) for any advices.

APPROVAL CONDITIONS



Permit to Which These Conditions Relate: DA - PA - Building Work
Activity(ies): animal keeping
Stage: Animal Keeping (Doggy Daycare) in Flood Overlay

General/Planning Requirements
 
Timing
1)   Maintain the Approved Development

Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions.

 
At all times
 
2)   Approved Drawings and Documents

A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers.

Note: This condition is imposed to ensure compliance with the conditions of development approval.

 
While site/operational/building work is occurring
 
3)   Carry Out the Approved Development

Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS.

Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners.

 
While site/operational/building work is occurring
 
4)   Complete All Building Work

Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS.

Note: Building work must also be completed in accordance with any other current development approval.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
Standard Advice
 
Timing
5)   Construction Noise and Dust Emissions

Pursuant to the Environmental Protection Act 1994, all development involving the emission of noise and dust from building and/or construction activities, must ensure that the emissions are in accordance with the requirements of the Act.
The Environmental Protection Act 1994 prescribes that:

1. A person must not carry out building work in a way that makes an audible noise-
-  on a business day or Saturday, before 6.30a.m. or after 6.30p.m; or
-   on any other day, at any time. 
2. The reference in subsection (1) to a person carrying out building work-
-  includes a person carrying out building work under an owner-builder permit; and
-  otherwise does not include a person carrying out building work at premises used by the person only for residential purposes.

Note: A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management delegate Development Services.

 
As indicated
 
6)   Natural Asset Local Law (NALL) - Protected Vegetation on Public Land, Road or Park

The interference with or removal of protected vegetation on a public land or park requires a permit under the Natural Assets Local Law 2003 (NALL), issued by Public Space Operations Arboriculture (PSO- Arb).

Detailed arrangements must be made with PSO-Arb in relation to the works carried out on protected vegetation (including provision for tree removal and replacement tree planning costs as determined by PSO-Arb) prior to carrying out any works on protected vegetation. PSO-Arb can be contacted via ISG-CS-PPI-PLANNING-ARB@brisbane.qld.gov.au.

Note: All requirements of development approval conditions with timing stipulated as 'prior to site works commencing' (or equivalent) must be fulfilled before Council can issue a NALL permit.

 
As indicated
 
7)   Waste Liquids - Discharging to Sewerage System

Any waste liquids (including wastewater from wash down and sanitising operations) must be directed to the sewerage system subject to the requirements and recommendations of the Distributer Retailer Authority or collected for recycling or disposed of by a licensed contractor at a liquid waste treatment facility.

 
As indicated
 
8)   Contaminated Materials and Soils

Any contaminated materials or soils encountered during siteworks, must be handled, stored and disposed of in accordance with the requirements of the relevant authority of the Queensland Government. A person must not dispose of contaminated soil or a hazardous substance at a place other than at a place approved by the relevant authority of the Queensland Government.

 
As indicated
 
9)   Further Development Permit Required

Further Development Permit(s) to carry out assessable building work under the Building Act may be required.

 
As indicated
 
10)   Plumbing and Drainage Work

Pursuant to the Plumbing and Drainage Act 2018, any plumbing and drainage work must be carried out in compliance with the Plumbing and Drainage Regulation 2019.

Note: All new and existing plumbing services should be located within the lot that they serve.

Compliance assessable plumbing and drainage work requires approval by Brisbane City Council prior to the work being carried out.

 
As indicated
 
11)   Currency Period

The currency period for this development approval is stated in the Decision Notice and is expressed as a date.

This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016.

 
As indicated
 
12)   Referral Agency Requirements

SARA as concurrence agency has imposed the requirements contained in the letter dated 18 December 2025.

 
As indicated
 
13)   Trade Waste Approval

Discharge of waste liquids to the sewerage system must be conducted in accordance with the conditions of a Trade Waste Approval.

For further information on obtaining an approval, contact Urban Utilities.

 
As indicated
 
14)   Equitable Access

Provision must be made during and after construction for equitable access for persons with disabilities to and within the site and on adjoining public areas, in accordance with the following:
- Queensland Anti-Discrimination Act 1991;
- Federal Disability Discrimination Act 1992;
- Australian Standards AS1428 Parts 1-4;
- Australian Standard for Access and Mobility; and
- National Construction Code.

 
As indicated
 
15)   Damage to Trees on Adjoining Land

Please note that any damage caused to vegetation on adjoining land as a result of exercising this development approval may result in an offence under other legislation (e.g. Natural Assets Local Law) and/or civil action

 
As indicated
 
16)   Fire Ant Movement Controls

To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected.

These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products.

Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014.

For further information contact the relevant Queensland State Government department on 13 QGOV.

 
As indicated
 
17)   Water and Wastewater

Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009.

For further information about any necessary Water Approvals contact Urban Utilities.

 
As indicated
 
18)   Cultural Heritage

Aboriginal cultural heritage is protected under the Aboriginal Cultural Heritage Act 2003. This Act establishes a cultural heritage duty of care and in section 23(1) mandates that a person who carries out an activity must take all reasonable and practicable measures for ensuring activities are managed to avoid or minimise harm to Aboriginal cultural heritage.

 

The Duty of Care Guidelines gazetted pursuant to the Aboriginal Cultural Heritage Act 2003 provide guidance on identifying and protecting Aboriginal cultural heritage to fulfil the duty of care.

 

For further information contact the relevant Queensland State Government Department (Department of Aboriginal and Torres Strait Islander Partnerships).

 
As indicated
 



Permit to Which These Conditions Relate: DA - PA - Material Change of Use
Activity(ies): animal keeping
Stage: Animal Keeping (Doggy Daycare) in Flood Overlay

General/Planning Requirements
 
Timing
19)   Maintain the Approved Development

Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions.

 
At all times
 
20)   Approved Drawings and Documents

A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers.

Note: This condition is imposed to ensure compliance with the conditions of development approval.

 
While site/operational/building work is occurring
 
21)   Carry Out the Approved Development

Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS.

Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners.

 
While site/operational/building work is occurring
 
22)   Complete All Building Work

Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS.

Note: Building work must also be completed in accordance with any other current development approval.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
23)   Limitation of use

Any animal grooming on-site must remain ancillary to the approved Animal Keeping use at all times.

The ancillary office space/s on the site are to be limited to the area shown on the APPROVED DRAWINGS AND DOCUMENTS. This area/s must remain ancillary to the approved Animal Keeping use and must not operate separately.

Should the approved Animal Keeping use cease, the use of the site for animal grooming and ancillary office area/s must also cease. Timing: At the time the approved use ceases.

 
As indicated
 
Pollution
 
Timing
24)   Hours of Operation

Hours of operation for the approved animal keeping (doggy day care) must be limited between 7am to 6pm.

There is to be no boarding of animals overnight.

 
At all times
 
25)   Close Southern Facade

The southern facade (including the roller doors), is to be closed at all times during hours of operation except for the sliding door to the reception area which may be opened momentarily for ingress/egress only.

 
At all times
 
26)   Waste Liquids

Waste liquids such as from dog washing or sanitation are to be directed to sewer in accordance with a Trade Waste Permit issued by Urban Utilities or are to be collected by a third-party contractor. Such waters are not to discharge to ground or stormwater.

 
At all times
 
Engineering
 
Timing
27)   On-site Erosion (Low Risk)

Manage on-site erosion and the release of sediment or sediment laden water from the site at all times by implementing best industry practice for sediment and erosion control as per the International Erosion Control Association, Best Practice Erosion and Sediment Control documents (2008 or later version). Including but not limited to:
(i) Drainage control measures must be implemented and maintained to minimise water flow across areas of exposed earth.
(ii) Sediment and erosion control measures must be implemented and maintained to prevent soil loss from earth disturbance areas and prevent deposition beyond earth disturbance areas.
(iii) No release of contaminants to land beyond on-site area of earth disturbance.

Note: Guidelines and factsheets to assist with this are available from the 'Healthy Waterways - Water by Design' website at http://hlw.org.au/initiatives/esc/house-sites

Timing: Prior to commencement of any earth disturbing activities and until all exposed soil areas are permanently stabilised against erosion.

 
As indicated
27(a) Provide Land Occupier Notification to Council

(i) Notify Council's ESC Team of proposed land occupier/s by sending an email to CARS-ESC@Brisbane.qld.gov.au

(ii) If the land is to be occupied by any person other than the registered landowner then advice must be provided to Council that confirms the name, contact information and the duration of any proposed occupation of the land.

Note: Occupier is any principal contractor occupying the land exercising a right under the development approval.

Timing: Prior to commencement of any earth disturbing activities.

 
As indicated
 
28)   Information Signage

Erect an information sign on the subject property in accordance with Council's general requirements for signage and in accordance with the requirements outlined below:
a) The sign should provide a brief description of the development proposed;
b) The sign is to list the name, postal and/or email address and a contact telephone number for the following parties (where relevant) that are undertaking work on the site:
- Developer;
- Project Coordinator;
- Architect/Building Designer;
- Builder;
- Civil Engineer;
- Civil Contractor/s; and
- Landscape Architect;
c) The lettering on the sign is to be at least 25 millimetres in height, be of regular weight and in sentence case;
d) The sign is to be a minimum size of 1,200 millimetres by 900 millimetres;
e) The maximum area of the sign is to be 2.0m2;
f) The sign is to be positioned as follows:
- located centrally along the road frontage of the site;
- located on or within 1.5 metres of the road frontage;
- mounted at least 300 millimetres above ground level; and
- clearly visible from the street for a pedestrian;
g) The sign is to contain no commercial or corporate advertising other than the name, logo or slogan of the parties outlined in part (b) of this condition;
h) The sign is to be non-illuminated; and
i) Both the sign and the supporting structure are to be made of weatherproof material and to be properly maintained at all times;

Timing: Prior to site works commencing and then to be maintained until completion of the development for all stages.

 
As indicated
 
29)   Protect Existing Infrastructure

Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure.

Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations.

The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements.

 
While site/operational/building work is occurring
29(a) As Constructed Drawings - Alterations to Existing Infrastructure

Submit to Development Services As Constructed drawings showing all new and/or rectification works and an asset register, prepared by a Registered Professional Engineer Queensland.

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

PROOF OF FULFILMENT
Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

 
As indicated
 
30)   Repair Damage to Kerb, Footpath or Road

Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
30(a) Interim Repairs

If at any time during the construction phase of the approved development, damage to the existing kerb and channel, footpath or roadway creates unsafe, unreasonable and/or not fit for purpose conditions as assessed by Council, interim repairs must be undertaken as directed by Program Planning and Integration.

Note: Any interim repairs required to be undertaken shall not be considered to satisfy the requirements of this condition for the permanent repair of the infrastructure prior to the issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

Timing: While site / operational / building works is occurring.

 
As indicated
 
31)   Access, Grades, Manoeuvring, Carparks, Signs and Line Marking

Construct and maintain access, parking and manoeuvring for vehicles on site in accordance with the relevant Brisbane Planning Scheme Codes, as indicated on the approved DRAWINGS AND DOCUMENTS, including the following:

i. A pavement of minimum Local road standard or equivalent surface material (including associated drainage) to the area for the proposed tenancy driveway and on which motor vehicles will be driven and/or parked within the site.

ii. Access to the site for the nominated refuse contractor’s refuse collection vehicle (RCV) and for the loading and unloading of vehicle(s).

iii. Maintain the existing parking arrangement on the site and for the loading and unloading of vehicle(s) within the site.

iv. An appropriate area for the storage and collection of refuse, including recyclables, in a position which is accessible to service vehicles on the site.

PROOF OF FULFILMENT
Certification from a Registered Professional Engineer Queensland, that the above requirements have been implemented in accordance with this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first and then to be maintained.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained
 
32)   Non-Residential Refuse Collection - On Site

Provide for the installation and collection of refuse/recycling bins.

 
At all times
32(a) Arrange Refuse Collection

Arrange for the installation of refuse/recycling bins and for the subsequent collection of refuse including recycling from the site by a private waste contractor.

Timing: A minimum of four weeks prior to the commencement of use and then to be maintained.

PROOF OF FULFILMENT
Where a private waste contractor is engaged, provide written confirmation from the proposed waste collection contractor of the agreement to service the property. The written agreement must be submitted to Council's Waste and Resource Recovery Services and include full details of the proposed system, bin sizes, number of bins, frequency of collection and the refuse collection vehicle size. Prior to commencement of use

 
As indicated
 
33)   Refuse Storage - On Site Collection

Provide a roofed and wholly screened refuse enclosure utilising materials consistent with the development or a dedicated refuse storage room inside or attached to a building, in accordance with the City Plan 2014, Refuse Planning Scheme Policy.

The enclosure/refuse storage room must be of a design to accommodate the quantity of refuse and recycling including source separation to allow for low servicing collection of the development.

Bins must be located in an area which allows them to be manoeuvred from the bin storage area to the designated internal collection point.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
34)   Ponding of Stormwater

Carry out the approved development to ensure that adjoining properties and roads are protected from ponding or nuisance from stormwater during construction.

Notes: If remedial works are necessary to comply with this condition, prior approval must be obtained from Development Services.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
35)   On Site Drainage - Minor

Provide a stormwater connection to all new or existing allotments and provide drainage infrastructure to ensure stormwater run-off from all roof and developed surface areas will be collected internally and piped in accordance with the relevant Brisbane Planning Scheme Codes to a lawful point of discharge.

Note:

Where connections are adjacent to a driveway crossover and within the TPZ of a street tree, Rectangular Hollow Section (RHS) is to be used.

Note:
- Guidance for the preparation of drawings and/or documents to comply with this condition is provided in the Brisbane Planning Scheme Policies.
- Queensland Building and Construction Commission licensed hydraulic consultants may design the stormwater system for sites less than 2000m2 with an upstream catchment servicing no more than 4 residential lots. This excludes stormwater drainage design (including subsoil drainage) of basements in flood planning areas and the design of any onsite stormwater detention system.
- Where external works are required and infrastructure will be handed over to Council (e.g. Stormwater pipes 375mm or greater and/or manholes within the road reserve, etc), the applicant will be required to request a Pre-Start with Council and ensure all future owned Council assets follow the On/Off Maintenance process in accordance with Council's Infrastructure Installation & Construction Requirements Manual.

- Guidance for requesting a pre- start and co-ordinating the On/Off Maintenance process can be found on Council's website (https://www.brisbane.qld.gov.au/planning-and- building/applying-and-post-approval/on-and-off-maintenance- approvals).

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
 
36)   Service Conduits and Mains

Provide and install all service conduits, including street lighting as required by Council,  and meet the cost of any alterations to public utility mains, existing mains, services, street lighting or installations that are required to carry out the approved development. These works must be in accordance with the relevant Brisbane Planning Scheme Codes, and include the following, where applicable:
- the provision of all services and/or conduits along the full length of any rear allotment access or access easement.
- the breaking and/or relocation of any existing sewer combine drains.
- the relocation of any fire hydrant and/or valves from the development's vehicular footway crossings.
- the retention and/or relocation of any existing foul water lines that currently exist within the site.
- any new or existing installations of electrical pillar boxes, pad mounted transformers (PMTs), water reticulation mains, water meters and the like, must be installed/relocated to their ultimate alignment relative to the new property boundary and clear of the usable footpath areas irrespective of the alignment of the existing services/conduits.

Note:
- The cost of moving services, utilities and assets is the responsibility of the Developer. The permission of the service, utility or asset owner will be required. Council permission is required if street trees, stormwater gullies/drains, and swales are affected. Urban Utilities permission is required if water supply and sewerage services are affected.
- Standard utility alignments may be found on Council's 'Brisbane Standard Drawings' 1013 to 1016 inclusive.
- Applicants must liaise with the appropriate service authorities. Typical underground services and/or conduits to be constructed include power, phone, telecommunications, sewer (including private combine drains) stormwater and gas, if applicable.

 
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first
36(a) Submit Certification to Council

Submit to Development Services certification by a Registered Professional Engineer Queensland (RPEQ) that the works have been completed in accordance with the requirements of the condition. 

Note: Where rear allotment accesses or easements exist, the certification is to be supported by As-Constructed drawings certified by a RPEQ showing all services and/or conduits. Civil works are to be certified by a RPEQ (Civil) and electrical works are to be certified by a RPEQ (Electrical)

Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first.

PROOF OF FULFILMENT
Certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the requirements of this condition. Note: Civil works are to be certified by a RPEQ(Civil) and electrical works are to be certified by a RPEQ (Electrical).

 
As indicated
 
Standard Advice
 
Timing
37)   Construction Noise and Dust Emissions

Pursuant to the Environmental Protection Act 1994, all development involving the emission of noise and dust from building and/or construction activities, must ensure that the emissions are in accordance with the requirements of the Act.
The Environmental Protection Act 1994 prescribes that:

1. A person must not carry out building work in a way that makes an audible noise-
-  on a business day or Saturday, before 6.30a.m. or after 6.30p.m; or
-   on any other day, at any time. 
2. The reference in subsection (1) to a person carrying out building work-
-  includes a person carrying out building work under an owner-builder permit; and
-  otherwise does not include a person carrying out building work at premises used by the person only for residential purposes.

Note: A request can be made to work outside of these hours by submitting an Environmental Management Plan for assessment and obtaining an endorsed decision from the Environmental Management delegate Development Services.

 
As indicated
 
38)   Natural Asset Local Law (NALL) - Protected Vegetation on Public Land, Road or Park

The interference with or removal of protected vegetation on a public land or park requires a permit under the Natural Assets Local Law 2003 (NALL), issued by Public Space Operations Arboriculture (PSO- Arb).

Detailed arrangements must be made with PSO-Arb in relation to the works carried out on protected vegetation (including provision for tree removal and replacement tree planning costs as determined by PSO-Arb) prior to carrying out any works on protected vegetation. PSO-Arb can be contacted via ISG-CS-PPI-PLANNING-ARB@brisbane.qld.gov.au.

Note: All requirements of development approval conditions with timing stipulated as 'prior to site works commencing' (or equivalent) must be fulfilled before Council can issue a NALL permit.

 
As indicated
 
39)   Waste Liquids - Discharging to Sewerage System

Any waste liquids (including wastewater from wash down and sanitising operations) must be directed to the sewerage system subject to the requirements and recommendations of the Distributer Retailer Authority or collected for recycling or disposed of by a licensed contractor at a liquid waste treatment facility.

 
As indicated
 
40)   Contaminated Materials and Soils

Any contaminated materials or soils encountered during siteworks, must be handled, stored and disposed of in accordance with the requirements of the relevant authority of the Queensland Government. A person must not dispose of contaminated soil or a hazardous substance at a place other than at a place approved by the relevant authority of the Queensland Government.

 
As indicated
 
41)   Further Development Permit Required

Further Development Permit(s) to carry out assessable building work under the Building Act may be required.

 
As indicated
 
42)   Plumbing and Drainage Work

Pursuant to the Plumbing and Drainage Act 2018, any plumbing and drainage work must be carried out in compliance with the Plumbing and Drainage Regulation 2019.

Note: All new and existing plumbing services should be located within the lot that they serve.

Compliance assessable plumbing and drainage work requires approval by Brisbane City Council prior to the work being carried out.

 
As indicated
 
43)   Currency Period

The currency period for this development approval is stated in the Decision Notice and is expressed as a date.

This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016.

 
As indicated
 
44)   Referral Agency Requirements

SARA as concurrence agency has imposed the requirements contained in the letter dated 18 December 2025.

 
As indicated
 
45)   Trade Waste Approval

Discharge of waste liquids to the sewerage system must be conducted in accordance with the conditions of a Trade Waste Approval.

For further information on obtaining an approval, contact Urban Utilities.

 
As indicated
 
46)   Equitable Access

Provision must be made during and after construction for equitable access for persons with disabilities to and within the site and on adjoining public areas, in accordance with the following:
- Queensland Anti-Discrimination Act 1991;
- Federal Disability Discrimination Act 1992;
- Australian Standards AS1428 Parts 1-4;
- Australian Standard for Access and Mobility; and
- National Construction Code.

 
As indicated
 
47)   Damage to Trees on Adjoining Land

Please note that any damage caused to vegetation on adjoining land as a result of exercising this development approval may result in an offence under other legislation (e.g. Natural Assets Local Law) and/or civil action

 
As indicated
 
48)   Fire Ant Movement Controls

To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected.

These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products.

Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014.

For further information contact the relevant Queensland State Government department on 13 QGOV.

 
As indicated
 
49)   Water and Wastewater

Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009.

For further information about any necessary Water Approvals contact Urban Utilities.

 
As indicated
 
50)   Cultural Heritage

Aboriginal cultural heritage is protected under the Aboriginal Cultural Heritage Act 2003. This Act establishes a cultural heritage duty of care and in section 23(1) mandates that a person who carries out an activity must take all reasonable and practicable measures for ensuring activities are managed to avoid or minimise harm to Aboriginal cultural heritage.

 

The Duty of Care Guidelines gazetted pursuant to the Aboriginal Cultural Heritage Act 2003 provide guidance on identifying and protecting Aboriginal cultural heritage to fulfil the duty of care.

 

For further information contact the relevant Queensland State Government Department (Department of Aboriginal and Torres Strait Islander Partnerships).

 
As indicated
 

** End of Package **