| Address of Site: | 102 OXFORD ST BULIMBA QLD 4171 |
| Real Property Description of Site: | L3 RP.99892 |
| Aspects of development and type of approval: | DA - PA - Material Change of Use Development Permit - multiple
dwelling,shop |
| Council File Reference: | A007001317 Permit Reference Number/s: DAMC454941724. |
| Package Status: | APPROVED - Version 2 (12th of June, 2026 10:19:27 PM) |
| Package Generated: | 12/06/2026 |
| Chani ASHA Urban Planner Planning Services Special Assessment Chani.Asha@brisbane.qld.gov.au 07 3178 5178 |
Llewellyn BATSON Principal Urban Planner Planning Services Special Assessment Llewellyn.Batson@brisbane.qld.gov.au (07) 340 34980 |
Maggie BOYD Environmental Health Officer Environmental Health - Environment Team Maggie.Boyd@brisbane.qld.gov.au 07 3403 2561 |
| Mario FURLAN Architect Architecture Team Mario.Furlan@brisbane.qld.gov.au (07) 3403 5698 |
Thomas JONKER Landscape Architect Landscape Architecture Team Thomas.Jonker@brisbane.qld.gov.au 31780712 |
Craig SLACK Engineer Engineering Scoping craig.slack@brisbane.qld.gov.au (07) 3403 8888 |
| Daniel SPILLANE Senior Engineer Engineering Services South Daniel.Spillane@brisbane.qld.gov.au 3403 5285 |
Matthew CRANITCH Technical Officer WaRRS Assessment Matthew.Cranitch@brisbane.qld.gov.au |
Michael CHOU Network Planning Michael.Chou@brisbane.qld.gov.au |
| Kayal CHANDRASEKAR Senior Urban Planner Planning Services South Kayal.Chandrasekar@brisbane.qld.gov.au 34030086 |
Kathryn KELLY Principal Urban Planner Planning Services South kathryn.kelly@brisbane.qld.gov.au 07 3407 1308 |
DRAWINGS AND DOCUMENTS
| Drawing or Document | Number | Plan Date |
|---|---|---|
| Proposed Site Plan | A301 Issue F | 01-JUN-2026 (Received) |
| Ground Floor Plan | A304 Issue F (Amended In Red 09-JUN-2026) | 01-JUN-2026 (Received) |
| First Floor Plan | A305 Issue F | 01-JUN-2026 (Received) |
| Second Floor Plan | A306 Issue F | 01-JUN-2026 (Received) |
| Roof Terrace | A307 Issue F (Amended In Red 09-JUN-2026) | 01-JUN-2026 (Received) |
| Roof | A308 Issue F (Amended In Red 09-JUN-2026) | 01-JUN-2026 (Received) |
| Sections | SD401 Issue F | 01-JUN-2026 (Received) |
| Sections | SD402 Issue F | 01-JUN-2026 (Received) |
| Sections | SD403 Issue F | 01-JUN-2026 (Received) |
| Elevations | SD501 Issue F (Amended In Red 09-JUN-2026) | 01-JUN-2026 (Received) |
| Elevations | SD502 Issue F | 01-JUN-2026 (Received) |
| Landscape Design Intent | DA05 240220 (Amended In Red 14-MAY-2026) | 10-APR-2026 (Received) |
APPROVAL CONDITIONS
| Permit to Which These Conditions Relate: | DA - PA - Material Change of Use |
| Activity(ies): | multiple dwelling shop |
| Stage: | Multiple dwelling (4 units) and Shop |
| 1) Building Management Statement Ensure a Building Management Statement is registered on the title for each proposed lot. The Building Management Statement must cover common
building management items including but not limited to any shared: Timing: As part of the registration of the plan of subdivision notated by Council and then to be maintained. |
As indicated |
1(a) Submit Building Management
Statement The Building Management Statement must be submitted to, and the content endorsed by, Development Services. Timing: Prior to Council's notation on the plan of subdivision. |
As indicated |
1(b) Lodge Building Management
Statement Lodge the accepted Building Management Statement with the Registrar of Titles for the relevant Queensland State Government Authority. Timing: As part of the registration of the plan of subdivision notated by Council. |
As indicated |
1(c) Submit Evidence of
Registration Submit to Development Services, evidence of the registration of the endorsed Building Management Statement. Timing: Within one month of the registration of the Building Management Statement. |
As indicated |
| 2) Security Lighting - On Site Install and maintain a suitable system of security lighting to operate from dusk to dawn within all areas where the public may gain access, including car parking areas, internal pathways, building entrances and vegetated areas. Lighting of publicly accessible internal areas is in accordance with Australian Standard - AS/NZS 1158.3.1 Lighting for roads and public spaces - Pedestrian area lighting - Performance and design requirements. All external lighting within the site is in accordance with Australian Standard - AS4282- Control of the Obtrusive Effects of Outdoor Lighting. Lighting must be maintained in safe and good working order. Timing: 'Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first' |
As indicated |
| 3) Building Format Plan Where the timing of a condition, or part thereof , states 'Prior to issue of Certificate of Occupancy/Final Inspection Certificate' or 'Prior to commencement of use' and the development involves the creation of a Building Format Plan, the timing of the condition, or part thereof, is taken to mean 'prior to Council's endorsement of any plan of subdivision'. |
As indicated |
| 4) Attend a pre-start meeting Arrange and attend a pre-start meeting with Building and Construction Management Team, Development Services. Council will only attend the pre-start meeting once all applicable compliance fees have been paid. Note: To request a pre-start meeting and associated lodgement requirements, refer to Council's website and search 'Pre-start meeting'. Timing: Prior to site/operational/building work commencing. |
As indicated |
| 5) Car Parking The car parking within the premises must be maintained exclusively for the ancillary use of the development. The parking must not be made available to the general public and there must not be signage erected on or in the vicinity of the site advertising the availability of car parking to the general public. |
At all times |
| 6) Maintain the Approved Development Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions. |
At all times |
| 7) Erect Screen Fence Erect a screen fence along the northern boundary of the site as shown on the approved DRAWINGS AND DOCUMENTS. The screen fence must be 1.8 metres in height and be constructed from the ground level. |
"Prior to building works commencing, or prior to making application under Section 401 of SPA 2009, or prior to making application under Schedule 19 of SPR 2009, or where approved under IPA 1997, prior to survey plan endorsement, whichever comes first |
| 8) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers. Note: This condition is imposed to ensure compliance with the conditions of development approval. |
While site/operational/building work is occurring |
| 9) Carry Out the Approved Development Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS. Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners. |
While site/operational/building work is occurring |
| 10) Complete All Building Work Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS. Note: Building work must also be completed in accordance with any other current development approval. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 11) Visitor Parking Visitor car parking spaces must: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 12) Limitation of Use The Shop is limited to the ground floor tenancy and the total gross floor area is limited to a maximum of 155m square metres in accordance with the approved Ground Floor Plan, A304 Issue F, received 1 June 2026 as amended in red 9 June 2026. GUIDELINE This condition has been imposed to ensure the gross floor area and the permitted uses have adequate onsite car parking, servicing and refuse and recycling storage areas. |
At all times |
| 13) External Details External details of the building, facade treatment and external materials and finishes must be consistent with the approved DRAWINGS AND DOCUMENTS. Note: The requirement to use particular materials and finishes is imposed only for the purpose of achieving a built form outcome that displays architectural merit. Council has not assessed the materials and finishes for compliance with the Building Act, the Building Fire Safety Regulation, the Building Regulation, the Building Code of Australia, the Queensland Development Code, relevant Australian Standards, fire safety standards or any other relevant requirement of a statutory authority with regard to building work. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 14) Overall Height The overall height of the building must be in accordance with the floor and roof levels and overall height shown on the APPROVED DRAWINGS AND DOCUMENTS. This condition should be read in conjunction with any other relevant condition requiring minimum height clearances for basement or undercover car parking and manoeuvring areas. |
While site/operational/building work is occurring and then to be maintained |
14(a) Submit Certification Submit to Development Services certification from a Registered Surveyor (Qld) confirming that the 'as constructed' floor and roof levels and overall height are in accordance with the requirements of this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 15) Balconies/Verandahs/Terraces
Note: Any Community Management Statement that may apply to this approval must contain a by-law which reflects the requirements of this condition. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 16) Screening Provide suitable privacy screening to windows of balconies, landings, terraces and decks of the proposed dwelling(s) in accordance with the approved DRAWINGS AND DOCUMENTS. Suitable screening options must be: For windows: For balconies, landings, terraces
and decks: Note: Screening devices must be either solid translucent screens, perforated or slatted panels, or fixed louvres that are permanent, be durable and fixed. Screening devices must have a maximum of 25% openings, with a maximum opening of 50mm. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 17) Retain and Protect Existing Street Tree(s) Identify, retain and protect the existing street trees including the roots unless otherwise agreed in writing with Program, Planning and Integration Arboriculture (PPI Arb). Note: Street trees are protected under the Natural Assets Local Law. Street trees must not be removed or pruned without prior approval from PPI Arb. Where driveway crossovers occur within the Tree Protection Zone (TPZ) of existing street trees, seek approval from the Arboricultural Team in Program Planning and integration, City Standards for the final driveway crossover design and construction methodology to ensure the successful retention of the existing street tree(s) PROOF OF FULFILMENT Contextual photographic evidence that the tree has been retained in equal or greater health than before development commenced. OR, evidence in writing from Asset Services Arboriculture that an alternative arrangement has been made. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
At all times |
17(a) Implement Protection
Measures Install tree protection measures in accordance with Australian Standard - AS4970 Retention of Trees on Development Site. There must be no excavation, filling or storage of materials or plant within the drip line of the tree(s). Where works are within the canopy drip line of existing street trees, contact PPI Arb Coordinator in relation to the required provision of protection measures. Note: If fencing is to protect street trees, a permit to temporarily occupy the footway will be required from Compliance and Regulatory Services. Timing: Prior to site/operational/building work occurring. PROOF OF
FULFILMENT Contextual photographic evidence to demonstrate the installation of protection measures prior to building works commencing. Timing: Prior to site / operational / building work occurring. |
As indicated |
17(b) Maintain Protection
Measures Maintain protection measures while development is occurring and remove protection measures prior to commencement of the use. Timing: While to site/operational/building work is occurring. |
As indicated |
| 18) Streetscape Works - Centre Street Carry out streetscape improvement works to the verge of Oxford Street and Duke Street to a City Street Minor standard in accordance with the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD), the requirements of this condition and the Infrastructure Design Planning Scheme Policy including section 3.7.4.3. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
18(a) Submit Level Details Submit to Development
Services, and obtain approval for, details of the future finished levels of the
site and building entries (both pedestrian and vehicular) to demonstrate verge
levels and crossfalls complying with the Infrastructure Design Planning Scheme
Policy including section 3.7.3.5. The details must be provided by an RPEQ in
consultation with a qualified Landscape Architect and include the
following: Timing: Prior to site/operational/building work occurring. |
As indicated |
18(b) Submit Plan for Works in
Verge Submit, to an obtain approval from, Development Services, a detailed Landscape Works in Streetscape Plan for the required improvement works in accordance with the requirements of the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD) and the Infrastructure Design Planning Scheme Policy including section 3.7.4.3. The detailed Landscape Works in Streetscape Plan must be prepared at a scale of 1:100 by a qualified Landscape Architect and include the following: SPECIFIC REQUIREMENTS - Retention of the existing street tree on Duke Street DOCUMENTATION REQUIREMENTS - Finished surface levels at lot boundary and
kerb. Timing: Prior to building work above ground level commencing. |
As indicated |
18(c) Pre-Start Meeting Arrange and attend a pre-start meeting with Landscape Architecture Team, City Planning and Economic Development. Council will only attend the pre-start meeting once all applicable compliance and inspection fees have been paid. The project landscape architect must be present at the pre-start meeting. Timing: Prior to any work commencing to comply with this condition. |
As indicated |
18(d) Implement Streetscape
Works Remove the existing footway including affected street signage for the full length of the frontage. Carry out the works in accordance with the approved detailed Landscape Works in Streetscape Plan and to a standard and using materials in accordance with the requirements of the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD) and the Infrastructure Design Planning Scheme Policy section 3.7.4.3. Note: All existing artworks and regulatory signage must be secured and repositioned as agreed with Program Planning and Integration. Note: Any existing Brisbane Tuff or granite kerbing that is surplus to requirements must be returned to Program Planning and Integration. Note: At all times during construction provision must be made for people with a visual impairment. Where it is unavoidable that a
section of an existing Braille trail is to be blocked, or an object temporarily
located to intrude within the 1000 mm clearway on either side of the Braille
trail, the following actions must be undertaken to comply with the current
version of AS1428: Note: Lodge with and receive approval from Development Services for an 'Application for Permits Relating to Roads and Footway' prior to carrying out the approved works. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to the commencement of use, whichever comes first. |
As indicated |
18(e) Submit As-Constructed
Drawings Submit to Development Services Specialist Services As Constructed drawings including an asset register, prepared by a Registered Professional Engineer Queensland, certifying that the streetscape works have been completed in accordance with the approved detailed Landscape Works in Streetscape Plan and to a standard and using materials in accordance with the requirements of the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD) and the Infrastructure Design Planning Scheme Policy section 3.7.4.3. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
18(f) On-Maintenance Acceptance Arrange an on- maintenance inspection with Development Services and obtain written confirmation that the works have been accepted on-maintenance. Provide proof of Public Liability Insurance ($20 million) for the on- maintenance period. Lodge a bond for the streetscape works maintenance period of the works. The bond must be calculated in accordance with the relevant Brisbane Planning Scheme Codes (5% of total value of the landscape works or minimum of $5,000.00 whichever is greater). Note: To arrange an on-maintenance inspection with Development Services an email must be sent to specialistservices@brisbane.qld.gov.au. Note: A maintenance bond can consist of either a bank guarantee or monetary payment lodged with Council. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
18(g) On-Maintenance Period Provide a minimum of 12 months maintenance to the streetscape works and rectify any defects identified at the on-maintenance inspection and those arising during the on-maintenance period. Timing: Minimum 12 months from acceptance on- maintenance AND until the works are approved off-maintenance by Council. |
As indicated |
18(h) Off-Maintenance
Acceptance On completion of the on-maintenance period, arrange an off-maintenance inspection with Development Services and obtain written confirmation from Council that the work is accepted off-maintenance. Ensure all defects are rectified prior to making an appointment for off- maintenance inspection. Note: To arrange an off-maintenance inspection with Development Services an email must be sent to specialistservices@brisbane.qld.gov.au. Note: If the off- maintenance inspection is successful the maintenance bond will be released. Timing: On completion of the on-maintenance period. |
As indicated |
| 19) Pedestrian and/or Awning Lighting Install Pedestrian and/or Awning Lighting in accordance with the requirements of this condition. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
19(a) Submit a Pedestrian and Awning Lighting
Design Submit to Construction Branch, Citywide Services, City Lighting (CS- LIGHTING@brisbane.qld.gov.au), and obtain approval for, a detailed Pedestrian Lighting Design for the full street frontage of the development, and/or Awning Lighting Design to the underside of the proposed awning over the verge in accordance with the following: Pedestrian Lighting: Provide electrical reticulation plans prepared by a Registered Professional Engineer Queensland certifying that the design complies with Australian Standard - AS/NZS3000 Electrical installations known as the Australian/New Zealand Wiring Rules and Council's standard drawings (BSD-11000 series). Provide pedestrian and cycle lighting plans prepared by a Registered Professional Engineer Queensland or a member of the Illuminating Engineering Society of Australia and New Zealand certifying that the design complies with Australian Standard - AS/NZS 1158.3.1 Lighting for roads and public spaces - Pedestrian area (Lighting Sub-category PP3) lighting - Performance and Design requirements. And/Or Awning Lighting: Submit to Construction Branch, Citywide Services, City Lighting (CS-LIGHTING@brisbane.qld.gov.au), and obtain approval for, a detailed Awning Lighting Plan demonstrating that the under awning lighting complies with Australian Standard - AS/NZS 1158.3.1 Road Lighting Part 3.1: Pedestrian area (Lighting Sub-category PA1) lighting - Performance and installation design requirements and achieves glare control to ensure zero candelas (cd) at 90 degrees. Timing: Prior to commencing building work above ground level and prior to or concurrently with the submission of Landscape Works in Streetscape Plans for approval. |
As indicated |
19(b) Obtain an Electrical
Connection Obtain an electrical connection from the electricity supplier and enter into an arrangement with the electricity supplier to service the approved pedestrian lighting. Timing: Prior to commencing building work above ground level. |
As indicated |
19(c) Implement Approved Pedestrian and/or
Awning Lighting Design Install the lighting in accordance with the approved detailed Pedestrian Lighting Design and the approved Landscape Works in Streetscape Plan and/or Awning Lighting Design. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
19(d) Provide Certification of Connection and
Operation Provide to Construction Branch, Citywide Services, City Lighting (CS- LIGHTING@brisbane.qld.gov.au) certification from a licensed electrical contractor that the electrical connection has been installed in accordance with the approved detailed Pedestrian Lighting Design and/or Awning Lighting Design and that the lighting is fully operational. The certification must specify that the electrical installation has been tested to ensure it is electrically safe and in accordance with the requirements of Australian Standard - AS/NZS3000 Electrical installations known as the Australian/New Zealand Wiring Rules and any other standard applying to the electrical installation under the Electrical Safety Regulation 2002. A copy of the as-constructed Pedestrian Lighting Design Drawings must be included with the above certification. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
19(e) On-Maintenance Acceptance Arrange an on- maintenance inspection with Construction Branch, Citywide Services, City Lighting (CS- LIGHTING@brisbane.qld.gov.au) and obtain written confirmation from Council that the work has been completed in accordance with the requirements of the condition and is accepted on-maintenance. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
19(f) On-Maintenance Period Provide a minimum 12 months maintenance to the works from the time the works are accepted on- maintenance by Council. During this period maintain the lighting and rectify any defects identified at the on-maintenance inspection and those arising during the on-maintenance period. Timing: Minimum 12 months from acceptance on-maintenance AND until the works are approved off- maintenance by Council. |
As indicated |
19(g) Off-Maintenance
Acceptance On completion of the on-maintenance period arrange an off-maintenance inspection with Construction Branch, Citywide Services, City Lighting (CS- LIGHTING@brisbane.qld.gov.au) and obtain written confirmation from Council that the work is accepted off-maintenance. Ensure all defects are rectified prior to making an appointment for off-maintenance inspection. Timing: On completion of the on-maintenance period. |
As indicated |
19(h) Maintain the Work (Awning
Lighting) Maintain the awning lighting (including operating costs) in accordance with the approved Lighting Plan from dusk to dawn. Timing: To be maintained. |
As indicated |
| 20) Landscape the Site - Self Certification Landscape the site in accordance with the requirements of this condition. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
20(a) Detailed Landscape Plan for Self-
Certification Prepare a Detailed Landscape Plan at a scale of 1:100 for all on-site landscape works including planting areas identified on the approved DRAWINGS AND DOCUMENTS. The plan must be prepared by a Qualified Landscape Architect and must comply with the relevant Brisbane Planning Scheme Codes. The plan must include the following: Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
20(b) Centre or Mixed Use In addition to the
requirements listed above, the plan must include the following: Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
20(c) Certify Detailed Landscape
Plan On completion of the Detailed Landscape Plan, submit to Development
Services: Timing: Prior to building work commencing. PROOF OF FULFILMENT A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to building work commencing. |
As indicated |
20(d) Implement Certified Detailed Landscape
Plan Carry out the landscape work in accordance with the above certified detailed Landscape Plan. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
20(e) Certify Work On completion of the
landscape work, submit to Development Services: Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT An as constructed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
20(f) Maintain Landscape Work Maintain the landscape work, including deep planting, in accordance with the certified Detailed Landscape Plan. Timing: To be maintained. |
As indicated |
| 21) Car park and bus station exhaust vents -
(emitters) Car park and bus station exhaust vent outlets are separated from any sensitive use by a minimum of 15m. Note: This condition does not authorise environmental nuisance under the Environmental Protection Act 1994. |
At all times |
| 22) Exhaust vents - (sensitive uses) Dwellings and outdoor
air intakes for dwellings, are separated from: Note: This condition does not authorise environmental nuisance under the Environmental Protection Act 1994. |
At all times |
| 23) Fuel Burning Fuel burning (e.g. backup power
generator, fire pumps, etc) is to be in accordance with the
following: - Total maximum installed capacity of
0.1MW or less; - Operating 100 hours per year or
less; and - Not involving coal
combustion. |
As indicated |
| 24) Hours of Operation Hours of operation for the approved shop must be in accordance with the following: - Shop operating hours: 6am to 10pm - Delivery, loading and unloading:
7am to 10pm |
At all times |
| 25) Acid Sulfate Soils Submit for the approval of
Development Services, an Acid Sulfate Soils (ASS) Investigation
Report and Management Plan, where soil disturbance (e.g filling, excavation,
drainage works, stripping of topsoil) is greater than 100m3 and the
disturbance level is equal to or less than 5mAHD. The ASS Management Plan must
detail management measures of possible impacts of soil disturbance and
demonstrate the disturbance impact will be appropriately managed. Prepare the
ASS Investigation Report and Management Plan in accordance with the
Potential and Actual Acid Sulfate Soil Overlay Code and
associated Planning Scheme Policy. The Report and Management Plan are to be prepared by a suitably
qualified and experienced professional, with the following qualifications: |
Prior to site/operational/building work commencing |
25(a) Implement Plan Implement and maintain the provisions of the approved 'Acid Sulfate Soil Management Plan'. |
While site/operational/building work is occurring |
25(b) Certification Submit to Development Services certification from a Registered Professional Engineer Queensland, that the measures recommended in the Acid Sulfate Soils (ASS) Management Plan have been implemented into the development. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 26) Mechanical Plant or Equipment - Acoustically
Screened Mechanical plant or equipment is to be acoustically screened from an adjoining sensitive use. Mechanical plant includes generators, motors, compressors and pumps such as air-conditioning, refrigeration and cold room motors. Acoustically screened is defined in City Plan 2014. NOTE: This condition does not authorise environmental nuisance under the Environmental Protection Act 1994. PROOF OF FULFILMENT Submit to Development Services, certification that all mechanical plant or equipment, is acoustically screened. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 27) Acoustic Treatments for Dwellings in Centre or
Mixed Use Zone Dwellings are to be designed and constructed with all bedrooms and other habitable rooms achieving the following minimum acoustic performance: (i) Rw 35 for glazing (windows and doors) where total area of glazing is greater than 1.8m2; (ii) Rw 32 for glazing (windows and doors) where total area of glazing is less than or equal to 1.8m2. Timing: Prior to building work commencing, while building work is occurring and then to be maintained |
As indicated |
27(a) Submit Acoustic
Certification Submit certification to Council by a suitably qualified acoustic consultant demonstrating that the treatments as detailed above have been incorporated into the development.
Timing: Prior to the commencement of the use |
As indicated |
| 28) Amplified Music/Speaker Any speaker is to have a sound-limiting device and is to be located indoor only. |
At all times |
| 29) Dampening of Grilles and Metal Plates All metal grilles, metal plates or similar located within vehicle parking and manoeuvring areas must be securely fastened and meet the requirements of AS3996:2019, Access covers and grates. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 30) Tyre Noise Reduction The driveways and carpark surfaces are to be appropriately treated/surfaced to reduce tyre noise impacts from the development. PROOF OF
FULFILMENT Provide Certification that appropriate treatments/surfacing has been provided to the driveways and carpark areas to reduce tyre noise impact from the development. Certification must be provided by a Member or professional eligible to be a Member of the Australian Acoustic Society. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 31) On-site Erosion (Low Risk) Manage on-site erosion
and the release of sediment or sediment laden water from the site at all times
by implementing best industry practice for sediment and erosion control as per
the International Erosion Control Association, Best Practice Erosion and
Sediment Control documents (2008 or later version). Including but not limited
to: Note: Guidelines and factsheets to assist with this are available from the 'Healthy Waterways - Water by Design' website at http://hlw.org.au/initiatives/esc/house-sites Timing: Prior to commencement of any earth disturbing activities and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
31(a) Provide Land Occupier Notification to
Council (i) Notify Council's ESC Team of proposed land occupier/s by sending an email to CARS-ESC@Brisbane.qld.gov.au (ii) If the land is to be occupied by any person other than the registered landowner then advice must be provided to Council that confirms the name, contact information and the duration of any proposed occupation of the land. Note: Occupier is any principal contractor occupying the land exercising a right under the development approval. Timing: Prior to commencement of any earth disturbing activities. |
As indicated |
| 32) Information Signage Erect an information sign on the subject property in
accordance with Council's general requirements for signage and in accordance
with the requirements outlined below: Timing: Prior to site works commencing and then to be maintained until completion of the development for all stages. |
As indicated |
| 33) Basement Excavation and Support Basement excavation and support of all exposed walls must be carried out in accordance with the relevant Brisbane Planning Scheme Codes and the requirements of this condition. |
Prior to building work commencing |
33(a) Prepare Engineering
Drawings Engineering drawings for the work required by this condition must be prepared and certified by a Registered Professional Engineer Queensland (Structural), in accordance with the relevant Brisbane Planning Scheme Codes detailing the design of the proposed excavation as well as proposed temporary and permanent support (if no temporary proposed) systems. The design must include at least the following: Notes: Timing: Prior to site/operational/building work commencing. |
As indicated |
33(b) Implement Certified Engineering
Drawings Construct and maintain the basement excavation and proposed support system in accordance with the above certified engineering drawings. Note: A copy of the certified engineering drawings must be available on- site for inspection by Council Officers during these works. Timing: While basement excavation and support system installation is occurring. |
As indicated |
33(c) Submit Post Construction
Certification Submit certification by a Registered Professional Engineer Queensland that the basement excavation and support have been installed in compliance with the certified engineering drawings, the relevant Brisbane Planning Scheme Codes and the requirements of this condition. Where ground or rock anchors have been installed, submit certification by a Registered Professional Engineer Queensland (Geo-technical) that all anchors have been de- stressed. Timing: Prior to building work commencing above ground. |
As indicated |
| 34) Construction Management Plan (Minor) Carry out development in a method consistent with a Construction Management Plan (Minor) prepared in accordance with the requirements of this condition. |
While site/operational/building work is occurring |
34(a) Construction Management Plan (Minor) -
Prepare Plan Prepare a detailed Construction Management Plan (CMP) for the
construction phase of the approved development.The Construction Management Plan
must be in accordance with the relevant Brisbane Planning Scheme Codes and
address the following: The Construction Management Plan must be supported by 'approval in principle' or written approvals from the relevant Council sections or other governing bodies responsible for any potentially impacted infrastructure. The list of relevant infrastructure and contacts is available on Council's website - Search 'Construction Management Plan'. Note: The Construction Management Plan is not required to be approved by Development Services. Timing: Prior to site/operational/building work commencing. |
As indicated |
34(b) Construction Management Plan (Minor) -
Submit Plan Submit a copy of the Construction Management Plan to Council's Development Services Branch at the following mailbox: engineeringservices@brisbane.qld.gov.au quoting the BCC planning development approval reference number. Timing: At least 10 days prior to site works commencing. |
As indicated |
34(c) Construction Management Plan (Minor) -
Documentation on Site Legible copies of the Construction Management Plan and current permits must be kept on site and be made available on request by Council at all times. The requirements of the CMP must be included in all induction of principal and subcontractors utilised in the development. An outline of the induction provided to contractors may be requested by Council to confirm compliance with this condition. Timing: While site/operational/building work is occurring. |
As indicated |
34(d) Construction Management Plan - Works to
be Performed Out of Hours Obtain an approval from Development Services for any
work that is proposed to be undertaken outside of normal business hours -
6:30am to 6:30pm, Monday to Saturday. |
As indicated |
34(e) Implement Construction Management Plan
(Minor) Carry out the development in accordance with the submitted Construction Management Plan. |
While site/operational/building work is occurring |
| 35) Protect Existing Infrastructure Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure. Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations. The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements. |
While site/operational/building work is occurring |
35(a) As Constructed Drawings - Alterations
to Existing Infrastructure Submit to Development Services As Constructed drawings showing all new and/or rectification works and an asset register, prepared by a Registered Professional Engineer Queensland. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 36) Existing Council Public Transport Facilities Bus
Stops and Shelters Ensure all existing public transport facilities are maintained and that the function of those facilities are uninterrupted by the development, in accordance this condition. |
While site/operational/building work is occurring |
36(a) Request Arrangement Enter into an arrangement with Council's Transport Planning and Operations Branch to manage and maintain the function of Bus Stops and Shelters. Timing: Prior to site/operational/building work commencing. |
As indicated |
36(b) Implement Arrangement Implement the arrangement made with Council's Transport Planning and Operations Branch. Timing: While site/operational/building work is commencing. |
While site/operational/building work is occurring |
| 37) Remove Improvements & Obstructions from Truncation
and Dedication Remove all improvements (fences, gates, letter boxes, garden beds and plots and other constructed items, etc.) and obstructions (existing earth banks, vegetation, etc.) from the area of the corner truncation and from the area of the dedicated road and reinstate the area as footway in accordance with the relevant Brisbane Planning Scheme Codes, excluding any requirements under the streetscape works conditions. Any new or existing installations of electrical pillar boxes, pad mounted transformers (PMTs), water meters and the like, must be installed/relocated to their ultimate alignment relative to the new property boundary and clear of the usable footpath areas irrespective of the alignment of the existing services/conduits. Note: The cost of moving services, utilities and assets is the responsibility of the Developer. The permission of the service, utility or asset owner will be required. Council permission is required if street trees, stormwater gullies/drains, and swales are affected. Urban Utilities permission is required if water supply and sewerage services are affected. Standard utility alignments may be found on Council's 'Brisbane Standard Drawings' 1013 to 1016 inclusive. PROOF OF FULFILMENT Certification from a Registered Surveyor (Qld) or Registered Professional Engineer Queensland that the above work has been completed in accordance with this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 38) Filling and / or Excavation (Minor) Filling and/or excavation works on the site must be in accordance with the APPROVED PLANS and the relevant Brisbane Planning Scheme Codes. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
38(a) Prepare Earthworks
Drawings Earthworks drawings must be prepared and certified by a Registered Professional Engineer Queensland in accordance with the relevant Brisbane Planning Scheme Codes. The drawings must include the
following: Timing: Prior to site/operational/building work commencing. Note: The Earthworks drawings are not required to be submitted for Council approval. |
As indicated |
38(b) Implement and Maintain the
Earthworks Carry out and maintain the earthworks in accordance with the certified drawings. Note: A copy of the certified Earthworks Drawings must be available on-site for inspection by Council Officers during these works. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 39) Retaining Walls Design and construct all retaining walls and associated fences, in accordance with the relevant Brisbane Planning Scheme Codes and the following: - All retaining walls including the footings, must be located wholly within the property boundaries of the site where works are occurring - Runoff from surface drains and subsoil drainage associated with the retaining walls must be collected and connected to a lawful point of discharge (LPD) where possible. If no LPD is available the surface drains and sub-soil drainage must be designed, installed and discharged to ensure there is no ponding, nuisance or concentration of stormwater discharge to adjacent properties. - Retaining walls to stabilise excavation must be set back from property boundaries to accommodate subsoil drainage without encroachment into the neighbouring property. This set back may vary depending on the height, structure and design of the retaining wall, surcharge loadings from neighbouring properties, and to provide a surface drain along the top of the retaining wall - For retaining walls in excess of
1.0m in height: NOTE: Refer to City Plan 2014; Infrastructure Design Planning Scheme Policy (IDPSP) for Council’s definition of a LPD. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
39(a) Certification of Retaining
Walls For retaining walls over 1.0m in height, obtain certification from a Registered Professional Engineer Queensland that the design and construction of the retaining walls and ancillary drainage are in accordance with the requirements of this condition. |
As indicated |
| 40) Repair Damage to Kerb, Footpath or Road Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
40(a) Interim Repairs If at any time during the construction phase of the approved development, damage to the existing kerb and channel, footpath or roadway creates unsafe, unreasonable and/or not fit for purpose conditions as assessed by Council, interim repairs must be undertaken as directed by Program Planning and Integration. Note: Any interim repairs required to be undertaken shall not be considered to satisfy the requirements of this condition for the permanent repair of the infrastructure prior to the issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. Timing: While site / operational / building works is occurring. |
As indicated |
| 41) Access, Grades, Manoeuvring, Carparks, Signs and
Line Marking Construct and maintain access, parking and manoeuvring for vehicles on site in accordance with the relevant Brisbane Planning Scheme Codes, as indicated on the approved DRAWINGS AND DOCUMENTS, including the following: i. A pavement of minimum Local road standard or equivalent surface material (including associated drainage) to the area on which motor vehicles will be driven and/or parked. ii. Standing on site for a refuse collection vehicle (Private Contractor’s 8.0m long RCV, for non-residential refuse collection) and for the loading and unloading of vehicle(s). iii. Parking on the site for eight (8) resident/tenant cars for the multiple dwelling component, two (2) cars for the commercial component, one (1) visitor space for the multiple dwelling component and for the loading and unloading of vehicle(s) within the site. There must a minimum total number of eleven (11) car parking spaces provided on site. iv. Provide and maintain five secure bicycle parking spaces (Four secure bicycle parking spaces for residents and one bicycle parking space for visitors). v. A minimum of 2.3 metres height clearance to all undercover parking areas, including the entry and access to these areas, and a minimum of 2.5 metres above parking spaces for people with disabilities. The minimum clear height must be measured to the lowest protrusion from the ceiling (e.g. fire sprinklers, services, lighting fixtures, signs, etc). vi. A height clearance sign located at the entrance(s) to undercover car parking areas and a directional visitor parking sign clearly visible from the vehicle entrance to the site. vii. An appropriate area for the storage and collection of refuse, including recyclables, in a position which is accessible to service vehicles on the site. viii. Prepare and implement signs and line markings drawings that show the internal paved areas signed and delineated in accordance with the approved drawings and documents. The drawings must be prepared and certified by a Registered Professional Engineer Queensland in accordance with the relevant Brisbane Planning Scheme Codes and the Manual of Uniform Traffic Control Devices. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland, that the above requirements have been implemented in accordance with this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first and then to be maintained. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 42) Refuse Collection - Kerb Side (external road or
internal private road) Refuse and recycling bins for the residential use of the development must be collected from the kerb side as shown on the APPROVED DRAWINGS AND DOCUMENTS. Arrange for the installation of refuse/recycling bins and for the subsequent collection of refuse including recycling from the site by Brisbane City Council's Waste and Resource Recovery Services. Timing: At the commencement of use and then to be maintained. |
As indicated |
| 43) Non-Residential Refuse Collection - On Site Provide for the installation and collection of refuse/recycling bins. |
At all times |
43(a) Arrange Refuse Collection Arrange for the installation of refuse/recycling bins and for the subsequent collection of refuse including recycling from the site by a private waste contractor.
Timing: A minimum of four weeks prior to the commencement of use and then to be maintained.
PROOF OF FULFILMENT Where a private waste contractor is engaged, provide written confirmation from the proposed waste collection contractor of the agreement to service the property. The written agreement must be submitted to Council's Waste and Resource Recovery Services and include full details of the proposed system, bin sizes, number of bins, frequency of collection and the refuse collection vehicle size. Prior to commencement of use |
As indicated |
| 44) Refuse Storage - Kerb Side Collection Provide a residential refuse storage area to accommodate the type and quantity of refuse and recycling bins required to service the development, as shown on the APPROVED DRAWINGS AND DOCUMENTS. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 45) Refuse Storage - On Site Collection Provide a roofed and wholly screened non-residential refuse enclosure utilising materials consistent with the development or a dedicated refuse storage room, as shown on the approved plans and documents. The enclosure/refuse storage room must be of a design to accommodate the quantity of refuse and recycling including source separation to allow for low servicing collection of the development. Bins must be located in an area which allows them to be manoeuvred from the bin storage area to the designated internal collection point. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 46) Land for Transport Network - Road (Non-
trunk) Dedicate as road land shown as new road (non-trunk) on the APPROVED DRAWING, Ground Floor Plan, A304 Issue F, received 1 June 2026 and as amended in red 9 June 2026, including the following: i. A widening along the full length of the Oxford Street frontage of the site to achieve a total verge width of 3.75 metres. ii. A six (6.0) metre by six (6.0) metre by three (3) equal chord truncation at the corner of Oxford Street and Duke Street. Note: This condition is imposed under section 145 of the Planning Act 2016. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
46(a) Submit Plan of
Subdivision Submit to, and obtain approval from, Development Services, a plan of subdivision showing the land to be dedicated for road to demonstrate compliance with the requirements of this condition. Timing: As part of the submission of the request pursuant to Schedule 18 of the Planning Regulation 2017 for Council's notation on the plan of subdivision necessary to comply with this condition. |
As indicated |
46(b) Lodge Notated Plan Lodge the plan of subdivision notated by Council pursuant to Schedule 18 of the Planning Regulation 2017 with the Registrar of Titles for the relevant Queensland State Government Authority. Timing: Prior to commencement of use. PROOF OF FULFILMENT Evidence of the registration of the required plan of subdivision. Timing: Within one month of the registration of the plan of subdivision. |
As indicated |
| 47) Remove Redundant Drainage Outlets Remove any redundant
drainage outlets from the kerb and channel including any associated pipe work
across the footway and reinstate the kerb and channel and the footway area in
accordance with the relevant Brisbane Planning Scheme Codes. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 48) All Basements - Stormwater Runoff Design and construct basements to manage stormwater runoff in accordance with the relevant Brisbane Planning Scheme Codes and the following: (i) All stormwater pump systems must be designed to gravity drain to a Council stormwater system. (ii) The driveway into a basement must be designed and constructed to minimise local driveway stormwater runoff entering the basement. The drainage must be designed to capture runoff from a 10% AEP rainfall event and gravity drain to a lawful point of discharge. (iii) Vehicle access into any basement from a Council road will require the basement driveway to ramp up a minimum of 200mm, above adjacent road channel invert, to maintain road major flow capacity. (iv) All roofwater drainage is to be directed to a lawful point of discharge via gravity drainage, not directed into the basement. (v) Any stormwater within a basement that connects via gravity drainage directly to a council pipe or manhole must incorporate backflow prevention devices. PROOF OF
FULFILMENT Certification from a Registered Professional Engineer Queensland that the development has been designed and constructed in accordance with this condition. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
48(a) Submit Certification to
Council Submit to Council certification by a Registered Professional Engineer Queensland that the stormwater, subsoil drainage, specifications and drawings for the basement construction is in accordance with the requirements of this condition.
Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 49) Ponding of Stormwater Carry out the approved development to ensure that adjoining properties and roads are protected from ponding or nuisance from stormwater during construction. Notes: If remedial works are necessary to comply with this condition, prior approval must be obtained from Development Services. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 50) On Site Drainage - Minor Provide a stormwater connection to all new or existing allotments and provide drainage infrastructure to ensure stormwater run-off from all roof and developed surface areas will be collected internally and piped in accordance with the relevant Brisbane Planning Scheme Codes to a lawful point of discharge, being kerb adaptor/s connected to the kerb and channel along the street frontage to the site. Note: - Guidance for requesting a pre-start and co-ordinating the On/Off Maintenance process can be found on Council's website (https://www.brisbane.qld.gov.au/planning-and-building/applying-and-post- approval/on-and-off-maintenance-approvals). |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 51) Service Conduits and Mains Provide and install all
service conduits and meet the cost of any alterations to public utility mains,
existing mains, services, street lighting or installations that are required to
carry out the approved development. These works must be in accordance with the
relevant Brisbane Planning Scheme Codes, and include the following, where
applicable: Note: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
51(a) Submit As Constructed
Drawings Submit to Development Services As Constructed drawings, including an asset register, prepared and certified by a Registered Professional Engineer Queensland. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the requirements of this condition. Note: Civil works are to be certified by a RPEQ(Civil) and electrical works are to be certified by a RPEQ (Electrical). |
As indicated |
| 52) Telecommunications Submit to Development Services, certification from
an authorised telecommunications carrier/contractor, that the following works
and infrastructure have been undertaken and installed in accordance with
telecommunications industry standards: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 53) Agreement with Electricity Supplier Submit to Development Services, evidence of an agreement with an electricity supplier to provide necessary services to the development in accordance with the relevant Brisbane Planning Scheme Codes. Where development is within an established area of overhead electricity supply and the electricity supplier determines that a property pole is the appropriate solution to supply electricity to the development, the developer must be responsible for the installation of the property pole(s). In the above circumstances, submit to Development Services, certification from the developer's electrical consultant confirming that the above installation has been completed in accordance with the relevant AS/NZS Standards and the Queensland Electricity Connection Manual (QECM) and Queensland Electricity Metering Manual (QEMM). |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 54) Redundant Driveway Crossover Remove the redundant existing driveway crossover(s) on the frontage(s) of the site and reinstate the kerb and channel, road pavement, footways and footpaths in accordance with the relevant Brisbane Planning Scheme Codes. Note: Additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 55) Permanent Driveway Crossover Provide a 6.2 metre wide Type B1 permanent driveway crossover to the Duke Street frontage of the site in accordance with the relevant Brisbane Planning Scheme Codes and located as shown on the approved DRAWINGS AND DOCUMENTS. Written consent must be obtained from Program, Planning and Integration Arboriculture (PPI Arb) prior to any works occurring that will either impact on or require removal of a street tree (this includes pruning, excavation or fill within the root zone/canopy of the tree). At all times during construction of the crossover, safe pedestrian access along the site frontage must be maintained. Note: No further driveway permit is required however additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 56) Construction Noise and Dust Emissions Pursuant to the
Environmental Protection Act 1994, all development involving the emission of
noise and dust from building and/or construction activities, must ensure that
the emissions are in accordance with the requirements of the Act. |
As indicated |
| 57) Natural Asset Local Law (NALL) - Protected
Vegetation on Public Land, Road or Park The interference with or removal of protected vegetation on a public land or park requires a permit under the Natural Assets Local Law (NALL), issued by Program Planning and Integration (PPI). Detailed arrangements must be made with PPI in relation to the works carried out on protected vegetation (including provision for tree removal and replacement tree planning costs as determined by the Arboriculture Team) prior to carrying out any works on protected vegetation. PPI Arboriculture Team can be contacted via BI- PPI-PLANNING-ARB@brisbane.qld.gov.au. Note: All requirements of development approval conditions with timing stipulated as 'prior to site works commencing' (or equivalent) must be fulfilled before Council can issue a NALL permit. |
As indicated |
| 58) Further Development Permit Required Further Development Permit(s) to carry out assessable building work under the Building Act may be required. |
As indicated |
| 59) Plumbing and Drainage Work Pursuant to the Plumbing and Drainage Act 2018, any plumbing and drainage work must be carried out in compliance with the Plumbing and Drainage Regulation 2019. Note: All new and existing plumbing services should be located within the lot that they serve. Compliance assessable plumbing and drainage work requires approval by Brisbane City Council prior to the work being carried out. |
As indicated |
| 60) Currency Period The currency period for this development approval is stated in the Decision Notice and is expressed as a date. This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016. |
As indicated |
| 61) Trade Waste Approval Discharge of waste liquids to the sewerage system must be conducted in accordance with the conditions of a Trade Waste Approval. For further information on obtaining an approval, contact Urban Utilities. |
As indicated |
| 62) Equitable Access Provision must be made during and after construction
for equitable access for persons with disabilities to and within the site and
on adjoining public areas, in accordance with the following: |
As indicated |
| 63) Damage to Trees on Adjoining Land Please note that any damage caused to vegetation on adjoining land as a result of exercising this development approval may result in an offence under other legislation (e.g. Natural Assets Local Law) and/or civil action |
As indicated |
| 64) Fire Ant Movement Controls To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected. These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products. Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014. For further information contact the relevant Queensland State Government department on 13 QGOV. |
As indicated |
| 65) Water and Wastewater Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. For further information about any necessary Water Approvals contact Urban Utilities. |
As indicated |