| Address of Site: | 277 MILTON RD MILTON QLD 4064 |
| Real Property Description of Site: | L3 RP.55886 |
| Aspects of development and type of approval: | DA - PA - Building Work Development Permit - office DA - PA - Material Change of Use Development Permit - office DA - PA - Building Work Development Permit - dwelling house,partial demolition |
| Council File Reference: | A006923570 Permit Reference Number/s: DABW471466525; DAMC471466625; DABW471512025. |
| Package Status: | APPROVED - Version 1 (10th of June, 2026 10:10:14 AM) |
| Package Generated: | 10/06/2026 |
| Luke HADRICK Urban Planner Planning Services North Luke.Hadrick@brisbane.qld.gov.au (07) 3178 9403 |
Rhea CONNOLLY Principal Urban Planner Planning Services North Rhea.Connolly@brisbane.qld.gov.au 3178 0651 |
Lucy TING Senior Engineer Engineering Services Hydraulics lucy.ting@brisbane.qld.gov.au (07) 3403 5005 |
| Michael CHOU Network Planning Michael.Chou@brisbane.qld.gov.au |
Biraj DANGOLE Principal Engineering Officer Engineering Services North Biraj.Dangole@brisbane.qld.gov.au (07) 3178 2607 |
Richard WELCH Senior Engineer Engineering Scoping Richard.Welch@brisbane.qld.gov.au 34070603 |
| Callan BENNETT Principal Architect Architecture Team Callan.Bennett@brisbane.qld.gov.au 07 31780595 |
Fabrienne Michelle YU Principal Environmental Management Officer - Air Quality Environmental Management Services Michelle.Yu@brisbane.qld.gov.au 07 3403 0258 |
Joe MCSHANE Principal Urban Planner Planning Services North CPAS-DS-PS-North@brisbane.qld.gov.au (07) 3407 1306 |
DRAWINGS AND DOCUMENTS
| Drawing or Document | Number | Plan Date |
|---|---|---|
| Site Plans | 1001 Revision D | 26-MAR-2026 (Received) |
| Existing Floor Plan - Undercroft | 1101 Revision A | 26-MAR-2026 (Received) |
| Existing Floor Plan - Upperfloor | 1102 Revision A | 26-MAR-2026 (Received) |
| Existing Roof Plan | 1103 Revision A | 26-MAR-2026 (Received) |
| Demolition Floor Plan - Undercroft | 1201 Revision A | 26-MAR-2026 (Received) |
| Demolition Floor Plan - Upper Floor | 1202 Revision B | 26-MAR-2026 (Received) |
| Demolition Roof Plan | 1203 Revision B | 26-MAR-2026 (Received) |
| Existing & Demolition Elevations - Sheet 1 | 1301 Revision B | 26-MAR-2026 (Received) |
| Existing & Demolition Elevations - Sheet 2 | 1302 Revision B | 26-MAR-2026 (Received) |
| Proposed Floor Plan - Lower Ground Floor | 2101 Revision D (Amended In Red 03-JUN-2026) | 26-MAR-2026 (Received) |
| Proposed Floor Plan - Upper Floor | 2102 Revision B | 26-MAR-2026 (Received) |
| Proposed Roof Plan | 2103 Revision B | 26-MAR-2026 (Received) |
| Proposed Elevations - Sheet 1 | 3001 Revision C | 26-MAR-2026 (Received) |
| Proposed Elevations - Sheet 2 | 3002 Revision C | 26-MAR-2026 (Received) |
| Proposed Sections - Sheet 1 | 3101 Revision C | 26-MAR-2026 (Received) |
APPROVAL CONDITIONS
| Permit to Which These Conditions Relate: | DA - PA - Building Work |
| Activity(ies): | office |
| Stage: | Office in Traditional Building Character Overlay |
| 1) Maintain the Approved Development Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions. |
At all times |
| 2) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers. Note: This condition is imposed to ensure compliance with the conditions of development approval. |
While site/operational/building work is occurring |
| 3) Carry Out the Approved Development Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS. Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners. |
While site/operational/building work is occurring |
| 4) Complete All Building Work Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS. Note: Building work must also be completed in accordance with any other current development approval. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 5) Overall Height The overall height of the building(s) must be in accordance with the floor and roof levels and overall height shown on the APPROVED DRAWINGS AND DOCUMENTS. |
While site/operational/building work is occurring and then to be maintained |
5(a) Submit Certification Submit to Development Services certification from a Registered Surveyor (Qld) confirming that the 'as constructed' floor and roof levels and overall height are in accordance with the requirements of this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 6) Driveway Material and Finishes Provide materials and
finishes to the driveway and external carparking surfaces that reduce the
visual impact of these areas when viewed from the street. One or a combination
of the following must be used: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 7) On-site Erosion (Low Risk) Manage on-site erosion
and the release of sediment or sediment laden water from the site at all times
by implementing best industry practice for sediment and erosion control as per
the International Erosion Control Association, Best Practice Erosion and
Sediment Control documents (2008 or later version). Including but not limited
to: Note: Guidelines and factsheets to assist with this are available from the 'Healthy Waterways - Water by Design' website at http://hlw.org.au/initiatives/esc/house-sites Timing: Prior to commencement of any earth disturbing activities and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
7(a) Provide Land Occupier Notification to
Council (i) Notify Council's ESC Team of proposed land occupier/s by sending an email to CARS-ESC@Brisbane.qld.gov.au (ii) If the land is to be occupied by any person other than the registered landowner then advice must be provided to Council that confirms the name, contact information and the duration of any proposed occupation of the land. Note: Occupier is any principal contractor occupying the land exercising a right under the development approval. Timing: Prior to commencement of any earth disturbing activities. |
As indicated |
| 8) Protect Existing Infrastructure Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure. Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations. The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements. |
While site/operational/building work is occurring |
8(a) As Constructed Drawings - Alterations to
Existing Infrastructure Submit to Development Services As Constructed drawings showing all new and/or rectification works and an asset register, prepared by a Registered Professional Engineer Queensland. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 9) Repair Damage to Kerb, Footpath or Road Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
9(a) Interim Repairs If at any time during the construction phase of the approved development, damage to the existing kerb and channel, footpath or roadway creates unsafe, unreasonable and/or not fit for purpose conditions as assessed by Council, interim repairs must be undertaken as directed by Program Planning and Integration. Note: Any interim repairs required to be undertaken shall not be considered to satisfy the requirements of this condition for the permanent repair of the infrastructure prior to the issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. Timing: While site / operational / building works is occurring. |
As indicated |
| 10) Construction Noise and Dust Emissions Pursuant to the Environmental
Protection Act 1994, all development involving the emission of noise and dust
from building and/or construction activities, must ensure that the emissions
are in accordance with the requirements of the Act. |
As indicated |
| 11) Management of Asbestos Disposal, handling and restoration of any building materials containing asbestos must be in accordance with current state and federal legislation. |
As indicated |
| 12) Further Development Permit Required Further Development Permit(s) to carry out assessable building work under the Building Act may be required. |
As indicated |
| 13) Currency Period The currency period for this development approval is stated in the Decision Notice and is expressed as a date. This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016. |
As indicated |
| 14) Fire Ant Movement Controls To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected. These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products. Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014. For further information contact the relevant Queensland State Government department on 13 QGOV. |
As indicated |
| 15) Water and Wastewater Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. For further information about any necessary Water Approvals contact Urban Utilities. |
As indicated |
| Permit to Which These Conditions Relate: | DA - PA - Material Change of Use |
| Activity(ies): | office |
| Stage: | Office |
| 16) Approved Drawings and Documents A legible copy of the
Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package
must be maintained on site and kept available for inspection by site workers
and Council officers. |
While site/operational/building work is occurring |
| 17) Carry Out the Approved Development Carry out the approved
development generally in accordance with the approved DRAWINGS AND
DOCUMENTS. |
While site/operational/building work is occurring and then to be maintained |
| 18) Complete All Building Work Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out generally in accordance with the approved DRAWINGS AND DOCUMENTS, and, where the building work is assessable development, in accordance with a current development approval. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first (MCU or BW), or prior to Council's notation of the plan of subdivision (ROL), and then to be maintained |
| 19) Maintain the Approved Development Maintain the approved
development generally in accordance with the approved DRAWINGS AND DOCUMENTS,
and any relevant Council engineering or other approval required by the
conditions. The rooftop terrace is limited to use by
staff, and not to be used for patrons of the Food and drink outlet, or other
visitors to the site. |
To be maintained |
| 20) Retain and Protect Existing Street Tree(s) Identify, retain and protect the existing street trees including the roots unless otherwise agreed in writing with Public Space Operations Arboriculture Planning (PSO Arb Planning). Note: Street trees are protected under the Natural Assets Local Law. Street trees must not be removed or pruned without prior approval from PSO Arb Planning. Where driveway crossovers occur within the Tree Protection Zone (TPZ) of existing street trees, seek approval from PSO Arb Planning for the final driveway crossover design and construction methodology to ensure the successful retention of the existing street tree(s) PROOF OF FULFILMENT Contextual photographic evidence that the tree has been retained in equal or greater health than before development commenced. OR, evidence in writing from PSO Arb Planning that an alternative arrangement has been made. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
At all times |
20(a) Implement Protection
Measures Install tree protection measures in accordance with Australian Standard - AS4970 Retention of Trees on Development Site. There must be no excavation, filling or storage of materials or plant within the drip line of the tree(s). Where works are within the canopy drip line of existing street trees, contact PSO Arb Planning in relation to the required provision of protection measures. Note: If fencing is to protect street trees, a permit to temporarily occupy the footway will be required from Compliance and Regulatory Services. Timing: Prior to site/operational/building work occurring. PROOF OF
FULFILMENT Contextual photographic evidence to demonstrate the installation of protection measures prior to building works commencing. Timing: Prior to site / operational / building work occurring. |
As indicated |
20(b) Maintain Protection
Measures Maintain protection measures while development is occurring and remove protection measures prior to commencement of the use. Timing: While to site/operational/building work is occurring. |
As indicated |
| 21) Streetscape Works - Neighbourhood Street
Minor Carry out streetscape improvement works including concrete path and turf to the Wight Street verge to a Neighbourhood Street Minor standard in accordance with the relevant Brisbane Planning Scheme Codes, Brisbane Standard Drawings (BSD), the requirements of this condition and the Infrastructure Design Planning Scheme Policy including sections 3.7.4.4 and 3.7.5. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
21(a) Concrete Path Install a 1.2m wide broom finished standard Portland grey concrete path. The edge of the path is to be setback 1300mm from the back of kerb.
Where the path cannot be installed on this alignment due to conflicts such as
street trees, or power poles, ensure the path is installed a minimum distance
of: If the above requirements cannot be achieved, contact the Landscape Architecture Team via email: specialistservices@brisbane.qld.gov.au. Transition to existing paths on verges that adjoin the development. The transition is to occur fronting the adjoining developments, not the subject site. Note: standard path alignments are shown on Brisbane Standard Drawing BSD-5201 sheet 2 but will vary depending on verge width and location. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Photographic evidence of concrete path. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
21(b) Submit As-Constructed
Drawings Submit to Development Services As Constructed plans including an asset register, checked by a Registered Professional Engineer Queensland, certifying that the concrete path works have been completed in accordance with relevant Brisbane Planning Scheme Codes/Policies. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT As constructed drawings signed by an RPEQ. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
21(c) Turf Install turf to the full width of the verge excluding any concrete path required by this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Photographic evidence of installed turf. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 22) Landscape the Site - Self Certification Landscape the site in accordance with the requirements of this condition. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
22(a) Detailed Landscape Plan for Self-
Certification Prepare a Detailed Landscape Plan at a scale of 1:100 for all on-site landscape works including planting areas identified on the approved DRAWINGS AND DOCUMENTS. The plan must be prepared by a Qualified Landscape Architect and must comply with the relevant Brisbane Planning Scheme Codes. The plan must include the following: In addition to the
above requirements, the plan must include the following: Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT A detailed landscape plan accompanied by Brisbane City Council Landscape design and landscape works online form. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
22(b) Certify Detailed Landscape
Plan On completion of the Detailed Landscape Plan, submit to Development Services a landscape design certification via the Landscape Design and Landscape Works Certification online form. Design certification is to be prepared by a Qualified Landscape Architect, certifying that the Detailed Landscape Plan complies with the requirements of this condition. The Certification must include a copy of the:
NOTE: The landscape design and landscape works certification online form can be found by searching development application forms on Council's website. Timing: Prior to building work commencing. PROOF OF FULFILMENT A copy of the landscape design certification form and certified detailed landscape plan |
As indicated |
22(c) Implement Certified Detailed Landscape
Plan Carry out the landscape work in accordance with the above certified detailed Landscape Plan. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
22(d) Certify Work On completion of the landscape work, submit a Landscape Works Certification via the Landscape Design and Landscape Works Certification online form. The landscape works certification is to be prepared by a Qualified Landscape Architect, certifying that the landscape works comply with the certified Detailed Landscape Plan. The certification must include:
- a copy of the as-constructed landscape drawings. - Photos of installed landscaping.
NOTE: The landscape design and landscape works certification online form can be found by searching development application forms on Council's website. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT A copy of the Landscape works certification form, a copy of the as-constructed landscape drawings, photos of installed landscaping, confirmation in writing from the landscape contractor who completed the works, that the works were completed in accordance with best practice landscape construction and horticultural standards. |
As indicated |
22(e) Maintain Landscape Work Maintain the landscape work, including deep planting, in accordance with the certified Detailed Landscape Plan. Timing: To be maintained. |
As indicated |
| 23) Hours of Operation Hours of operation for the approved office, including deliveries, must be within 6am to 8pm. |
At all times |
| 24) Mechanical Plant or Equipment - Acoustically
Screened Mechanical plant or equipment is to be acoustically screened from an adjoining sensitive use. Mechanical plant includes generators, motors, compressors and pumps such as air-conditioning, refrigeration and cold room motors. Acoustically screened is defined in City Plan 2014. NOTE: This condition does not authorise environmental nuisance under the Environmental Protection Act 1994. PROOF OF FULFILMENT Submit to Development Services, certification that all mechanical plant or equipment, is acoustically screened. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 25) Indoor Activities All activities are be conducted within an enclosed
building. There is to be no outdoor activities. |
At all times |
| 26) Dampening of Grilles and Metal Plates All metal grilles, metal plates or similar located within vehicle parking and manoeuvring areas must be securely fastened and meet the requirements of AS3996:2019, Access covers and grates. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 27) Acoustic Fence - General Erect a 2m high
acoustic fence, (relative to the finished RL of the car park) along the entire
northern boundary and part of the eastern boundary where adjoining the car
park. The acoustic fence must: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
27(a) Certification Submit to Development Services certification from a person who is a Member or eligible to be a Member of the Australian Acoustic Society that the constructed acoustic fence complies with the above requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 28) Tyre Noise Reduction The driveways and carpark surfaces are to be appropriately treated/surfaced to reduce tyre noise impacts from the development. PROOF OF
FULFILMENT Provide Certification that appropriate treatments/surfacing has been provided to the driveways and carpark areas to reduce tyre noise impact from the development. Certification must be provided by a Member or professional eligible to be a Member of the Australian Acoustic Society. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 29) On-site Erosion (Low Risk) Manage on-site erosion
and the release of sediment or sediment laden water from the site at all times
by implementing best industry practice for sediment and erosion control as per
the International Erosion Control Association, Best Practice Erosion and
Sediment Control documents (2008 or later version). Including but not limited
to: Note: Guidelines and factsheets to assist with this are available from the 'Healthy Waterways - Water by Design' website at http://hlw.org.au/initiatives/esc/house-sites Timing: Prior to commencement of any earth disturbing activities and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
29(a) Provide Land Occupier Notification to
Council (i) Notify Council's ESC Team of proposed land occupier/s by sending an email to CARS-ESC@Brisbane.qld.gov.au (ii) If the land is to be occupied by any person other than the registered landowner then advice must be provided to Council that confirms the name, contact information and the duration of any proposed occupation of the land. Note: Occupier is any principal contractor occupying the land exercising a right under the development approval. Timing: Prior to commencement of any earth disturbing activities. |
As indicated |
| 30) Information Signage Erect an information sign on the subject property in
accordance with Council's general requirements for signage and in accordance
with the requirements outlined below: Timing: Prior to site works commencing and then to be maintained until completion of the development for all stages. |
As indicated |
| 31) Construction Management Plan (Minor) Carry out development in a method consistent with a Construction Management Plan (Minor) prepared in accordance with the requirements of this condition. |
While site/operational/building work is occurring |
31(a) Construction Management Plan (Minor) -
Prepare Plan Prepare a detailed Construction Management Plan (CMP) for the
construction phase of the approved development.The Construction Management Plan
must be in accordance with the relevant Brisbane Planning Scheme Codes and
address the following: The Construction Management Plan must be supported by 'approval in principle' or written approvals from the relevant Council sections or other governing bodies responsible for any potentially impacted infrastructure. The list of relevant infrastructure and contacts is available on Council's website - Search 'Construction Management Plan'. Note: The Construction Management Plan is not required to be approved by Development Services. Timing: Prior to site/operational/building work commencing. |
As indicated |
31(b) Construction Management Plan (Minor) -
Submit Plan Submit a copy of the Construction Management Plan to Council's Development Services Branch at the following mailbox: engineeringservices@brisbane.qld.gov.au quoting the BCC planning development approval reference number. Timing: At least 10 days prior to site works commencing. |
As indicated |
31(c) Construction Management Plan (Minor) -
Documentation on Site Legible copies of the Construction Management Plan and current permits must be kept on site and be made available on request by Council at all times. The requirements of the CMP must be included in all induction of principal and subcontractors utilised in the development. An outline of the induction provided to contractors may be requested by Council to confirm compliance with this condition. Timing: While site/operational/building work is occurring. |
As indicated |
31(d) Construction Management Plan - Works to
be Performed Out of Hours Obtain an approval from Development Services for any
work that is proposed to be undertaken outside of normal business hours -
6:30am to 6:30pm, Monday to Saturday. |
As indicated |
31(e) Implement Construction Management Plan
(Minor) Carry out the development in accordance with the submitted Construction Management Plan. |
While site/operational/building work is occurring |
| 32) Filling and / or Excavation (Minor) Filling and/or excavation works on the site must be in accordance with the APPROVED PLANS and the relevant Brisbane Planning Scheme Codes. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
32(a) Prepare Earthworks
Drawings Earthworks drawings must be prepared and certified by a Registered Professional Engineer Queensland in accordance with the relevant Brisbane Planning Scheme Codes. The drawings must include the
following: Timing: Prior to site/operational/building work commencing. Note: The Earthworks drawings are not required to be submitted for Council approval. |
As indicated |
32(b) Implement and Maintain the
Earthworks Carry out and maintain the earthworks in accordance with the certified drawings. Note: A copy of the certified Earthworks Drawings must be available on-site for inspection by Council Officers during these works. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 33) Repair Damage to Kerb, Footpath or Road Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
33(a) Interim Repairs If at any time during the construction phase of the approved development, damage to the existing kerb and channel, footpath or roadway creates unsafe, unreasonable and/or not fit for purpose conditions as assessed by Council, interim repairs must be undertaken as directed by Program Planning and Integration. Note: Any interim repairs required to be undertaken shall not be considered to satisfy the requirements of this condition for the permanent repair of the infrastructure prior to the issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. Timing: While site / operational / building works is occurring. |
As indicated |
| 34) Access, Grades, Manoeuvring, Carparks, Signs and
Line Marking Construct and maintain access, parking and manoeuvring for vehicles on site in accordance with the relevant Brisbane Planning Scheme Codes, as indicated on the approved DRAWINGS AND DOCUMENTS, including the following: i. A pavement of minimum Local Road standard or equivalent surface material (including associated drainage) to the area on which motor vehicles will be driven and/or parked. ii. Manoeuvring on site for a VAN and for the loading and unloading of vehicle(s); iii. Parking on the site for 3 Car spaces, and for the loading and unloading of vehicle(s) within the site. iv. A minimum of 2.3 metres height clearance to all undercover parking areas. The minimum clear height must be measured to the lowest protrusion from the ceiling (e.g. fire sprinklers, services, lighting fixtures, signs, etc). v. A height clearance sign located at the entrance(s) to undercover car parking areas and a directional visitor parking sign clearly visible from the vehicle entrance to the site. vi. An appropriate area for the storage and collection of refuse, including recyclables, in a position which is accessible to service vehicles on the site. vi. Prepare and implement signs and line markings drawings that show the internal paved areas signed and delineated in accordance with the approved drawings and documents. The drawings must be prepared and certified by a Registered Professional Engineer Queensland in accordance with the relevant Brisbane Planning Scheme Codes and the Manual of Uniform Traffic Control Devices. PROOF OF
FULFILMENT Certification from a Registered Professional Engineer Queensland, that the above requirements have been implemented in accordance with this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first and then to be maintained. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 35) Refuse Storage - Kerb Side Collection Provide a refuse storage area to accommodate the type and quantity of refuse and recycling bins required to service the development, as shown on the APPROVED DRAWINGS AND DOCUMENTS. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 36) On Site Drainage - Minor Provide a stormwater connection to all new or existing allotments and provide drainage infrastructure to ensure stormwater run-off from all roof and developed surface areas will be collected internally and piped in accordance with the relevant Brisbane Planning Scheme Codes to a lawful point of discharge / kerb and channel, as may be required. Note: Where connections are adjacent to a driveway crossover and within the TPZ of a street tree, Rectangular Hollow Section (RHS) is to be used. Note: - Guidance for requesting a pre-start and co-ordinating the On/Off Maintenance process can be found on Council's website (https://www.brisbane.qld.gov.au/planning-and-building/applying-and-post- approval/on-and-off-maintenance-approvals). |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 37) Service Conduits and Mains Provide and install all
service conduits, including street lighting as required by Council, and
meet the cost of any alterations to public utility mains, existing mains,
services, street lighting or installations that are required to carry out the
approved development. These works must be in accordance with the relevant
Brisbane Planning Scheme Codes, and include the following, where
applicable: Note: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
37(a) Submit Certification to
Council Submit to Development Services certification by a Registered Professional Engineer Queensland (RPEQ) that the works have been completed in accordance with the requirements of the condition. Note: Where rear allotment accesses or easements exist, the certification is to be supported by As-Constructed drawings certified by a RPEQ showing all services and/or conduits. Civil works are to be certified by a RPEQ (Civil) and electrical works are to be certified by a RPEQ (Electrical) Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Certification from a Registered Professional Engineer Queensland, confirming that the works have been completed in accordance with the requirements of this condition. Note: Civil works are to be certified by a RPEQ(Civil) and electrical works are to be certified by a RPEQ (Electrical). |
As indicated |
| 38) Telecommunications Submit to Development Services, certification from
an authorised telecommunications carrier/contractor, that the following works
and infrastructure have been undertaken and installed in accordance with
telecommunications industry standards: |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 39) Agreement with Electricity Supplier Submit to Development Services, evidence of an agreement with an electricity supplier to provide necessary services to the development in accordance with the relevant Brisbane Planning Scheme Codes. Where development is within an established area of overhead electricity supply and the electricity supplier determines that a property pole is the appropriate solution to supply electricity to the development, the developer must be responsible for the installation of the property pole(s). In the above circumstances, submit to Development Services, certification from the developer's electrical consultant confirming that the above installation has been completed in accordance with the relevant AS/NZS Standards and the Queensland Electricity Connection Manual (QECM) and Queensland Electricity Metering Manual (QEMM). |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 40) Water and Wastewater Pursuant to Schedule 18 of the Planning Regulation 2017 submit to Development Services, documentary evidence, issued by the relevant distributor-retailer, to verify that the conditions of any necessary connection certificate under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009, have been complied with. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 41) Redundant Driveway Crossover Remove the redundant existing driveway crossover and the associated existing dropped kerbs along the frontage(s) of the site and reinstate the kerb and channel, road pavement, footways and footpaths in accordance with the relevant Brisbane Planning Scheme Codes. Note: Additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 42) Permanent Driveway Crossover Provide a replacement 5.0m wide Type A permanent driveway crossover to the frontage of the site in accordance with the relevant Brisbane Planning Scheme Codes and located as shown on the approved DRAWINGS AND DOCUMENTS. Written consent must be obtained from Program, Planning and Integration Arboriculture (PPI Arb) prior to any works occurring that will either impact on or require removal of a street tree (this includes pruning, excavation or fill within the root zone/canopy of the tree) At all times during construction of the crossover, safe pedestrian access along the site frontage must be maintained. Note: No further driveway permit is required however additional footway permits or lane closure permits may be required for footpath/verge closures and/or lane closures. These permits must be obtained prior to construction of the crossover. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 43) Construction Noise and Dust Emissions Pursuant to the Environmental
Protection Act 1994, all development involving the emission of noise and dust
from building and/or construction activities, must ensure that the emissions
are in accordance with the requirements of the Act. |
As indicated |
| 44) Natural Asset Local Law (NALL) - Protected
Vegetation on Public Land, Road or Park The interference with or removal of protected vegetation on a public land or park requires a permit under the Natural Assets Local Law 2003 (NALL), issued by Public Space Operations Arboriculture (PSO- Arb). Detailed arrangements must be made with PSO-Arb in relation to the works carried out on protected vegetation (including provision for tree removal and replacement tree planning costs as determined by PSO-Arb) prior to carrying out any works on protected vegetation. PSO-Arb can be contacted via ISG-CS-PPI-PLANNING-ARB@brisbane.qld.gov.au. Note: All requirements of development approval conditions with timing stipulated as 'prior to site works commencing' (or equivalent) must be fulfilled before Council can issue a NALL permit. |
As indicated |
| 45) Contaminated Materials and Soils Any contaminated materials or soils encountered during siteworks, must be handled, stored and disposed of in accordance with the requirements of the relevant authority of the Queensland Government. A person must not dispose of contaminated soil or a hazardous substance at a place other than at a place approved by the relevant authority of the Queensland Government. |
As indicated |
| 46) Management of Asbestos Disposal, handling and restoration of any building materials containing asbestos must be in accordance with current state and federal legislation. |
As indicated |
| 47) Further Development Permit Required Further Development Permit(s) to carry out assessable building work under the Building Act may be required. |
As indicated |
| 48) Plumbing and Drainage Work Pursuant to the Plumbing and Drainage Act 2018, any plumbing and drainage work must be carried out in compliance with the Plumbing and Drainage Regulation 2019. Note: All new and existing plumbing services should be located within the lot that they serve. Compliance assessable plumbing and drainage work requires approval by Brisbane City Council prior to the work being carried out. |
As indicated |
| 49) Currency Period The currency period for this development approval is stated in the Decision Notice and is expressed as a date. This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016. |
As indicated |
| 50) Equitable Access Provision must be made during and after construction
for equitable access for persons with disabilities to and within the site and
on adjoining public areas, in accordance with the following: |
As indicated |
| 51) Damage to Trees on Adjoining Land Please note that any damage caused to vegetation on adjoining land as a result of exercising this development approval may result in an offence under other legislation (e.g. Natural Assets Local Law) and/or civil action |
As indicated |
| 52) Fire Ant Movement Controls To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected. These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products. Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014. For further information contact the relevant Queensland State Government department on 13 QGOV. |
As indicated |
| 53) Water and Wastewater Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. For further information about any necessary Water Approvals contact Urban Utilities. |
As indicated |
| 54) Cultural Heritage Aboriginal cultural heritage is protected under the Aboriginal Cultural Heritage Act 2003. This Act establishes a cultural heritage duty of care and in section 23(1) mandates that a person who carries out an activity must take all reasonable and practicable measures for ensuring activities are managed to avoid or minimise harm to Aboriginal cultural heritage.
The Duty of Care Guidelines gazetted pursuant to the Aboriginal Cultural Heritage Act 2003 provide guidance on identifying and protecting Aboriginal cultural heritage to fulfil the duty of care.
For further information contact the relevant Queensland State Government Department (Department of Aboriginal and Torres Strait Islander Partnerships). |
As indicated |
| Permit to Which These Conditions Relate: | DA - PA - Building Work |
| Activity(ies): | dwelling house partial demolition |
| Stage: | Partial Demolition to pre-1946 Dwelling House in Traditional Building Character Overlay |
| 55) Maintain the Approved Development Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions. |
At all times |
| 56) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers. Note: This condition is imposed to ensure compliance with the conditions of development approval. |
While site/operational/building work is occurring |
| 57) Carry Out the Approved Development Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS. Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners. |
While site/operational/building work is occurring |
| 58) Complete All Building Work Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS. Note: Building work must also be completed in accordance with any other current development approval. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 59) External Details External details of the building, facade treatment and external materials and finishes must be consistent with the approved DRAWINGS AND DOCUMENTS. Note: The requirement to use particular materials and finishes is imposed only for the purpose of achieving a built form outcome that displays architectural merit. Council has not assessed the materials and finishes for compliance with the Building Act, the Building Fire Safety Regulation, the Building Regulation, the Building Code of Australia, the Queensland Development Code, relevant Australian Standards, fire safety standards or any other relevant requirement of a statutory authority with regard to building work. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 60) Partial Demolition of Building Partial demolition resulting from this approval must be in accordance with the APPROVED DRAWINGS AND DOCUMENTS and all building work must comply with this condition. |
While site/operational/building work is occurring and then to be maintained |
60(a) Adequate Bracing Provide adequate
bracing from the commencement of any demolition work and throughout the
demolition and construction phases of the project, to ensure that all parts of
the building not specifically designated for demolition on the APPROVED
DRAWINGS AND DOCUMENTS are retained and protected. |
As indicated |
60(b) Retain Original Fabric Retain all existing
external original fabric in the sections of the building which are not being
demolished. This will include, but is not limited to, existing decorative
detailing, balustrading, wall cladding, windows, doors, stairs and roof
sheeting. |
As indicated |
60(c) Submit Written
Confirmation Submit to Development Services written confirmation by a Registered Architect / Building Designer (holding a Queensland Building and Construction Commission Licence appropriate to the scale of the approved development)/ Building Certifier / Structural Engineer confirming that the partial demolition has been carried out in accordance with the requirements of this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use |
As indicated |
| 61) Repair Damage to Kerb, Footpath or Road Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
61(a) Interim Repairs If at any time during the construction phase of the approved development, damage to the existing kerb and channel, footpath or roadway creates unsafe, unreasonable and/or not fit for purpose conditions as assessed by Council, interim repairs must be undertaken as directed by Program Planning and Integration. Note: Any interim repairs required to be undertaken shall not be considered to satisfy the requirements of this condition for the permanent repair of the infrastructure prior to the issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. Timing: While site / operational / building works is occurring. |
As indicated |
| 62) Construction Noise and Dust Emissions Pursuant to the Environmental
Protection Act 1994, all development involving the emission of noise and dust
from building and/or construction activities, must ensure that the emissions
are in accordance with the requirements of the Act. |
As indicated |
| 63) Management of Asbestos Disposal, handling and restoration of any building materials containing asbestos must be in accordance with current state and federal legislation. |
As indicated |
| 64) Further Development Permit Required Further Development Permit(s) to carry out assessable building work under the Building Act may be required. |
As indicated |
| 65) Currency Period The currency period for this development approval is stated in the Decision Notice and is expressed as a date. This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016. |
As indicated |
| 66) Damage to Trees on Adjoining Land Please note that any damage caused to vegetation on adjoining land as a result of exercising this development approval may result in an offence under other legislation (e.g. Natural Assets Local Law) and/or civil action |
As indicated |
| 67) Fire Ant Movement Controls To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected. These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products. Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014. For further information contact the relevant Queensland State Government department on 13 QGOV. |
As indicated |
| 68) Water and Wastewater Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. For further information about any necessary Water Approvals contact Urban Utilities. |
As indicated |