| Address of Site: | 7 QUARRY ST HAMILTON QLD 4007 U 1 EVESHAM 7 QUARRY ST HAMILTON QLD 4007 U 2 EVESHAM 7 QUARRY ST HAMILTON QLD 4007 U 4 EVESHAM 7 QUARRY ST HAMILTON QLD 4007 |
| Real Property Description of Site: | LCommon Property BUP.104206 L1 BUP.104206 L2 BUP.104206 L4 BUP.104206 |
| Aspects of development and type of approval: | DA - PA - Material Change of Use Development Permit - Extension,multiple
dwelling DA - PA - Building Work Development Permit - Demolition |
| Council File Reference: | A007027221 Permit Reference Number/s: DAMC412185221; DABW419146922. |
| Package Status: | APPROVED - Version 3 (16th of July, 2026 12:33:35 PM) |
| Package Generated: | 16/07/2026 |
| Sultana ALAM Senior Urban Planner Planning Services House & Homes Sultana.Alam@brisbane.qld.gov.au 34036270 |
Luke LAWN Senior Landscape Architect Landscape Architecture Team Luke.Lawn@brisbane.qld.gov.au 3403 8888 |
Julie BONFIELD Senior Architect Architecture Team Julie.Bonfield@brisbane.qld.gov.au 31782575 |
| Asiya MOHAMMAD RAZA Urban Planner City Planning Asiya.MohammadRaza@brisbane.qld.gov.au (07) 3403 7737 |
Jolanta KRAWUS Principal Engineer, Development Assessment Engineering Scoping jolanta.krawus@brisbane.qld.gov.au 34036190 |
Sultana ALAM Senior Urban Planner Planning Services House & Homes Sultana.Alam@brisbane.qld.gov.au 34036270 |
| Alessio ZANCOLICH Principal Urban Planner Planning Services South alessio.zancolich@brisbane.qld.gov.au (07) 3407 8514 |
Sebit RAMBANG Urban Planner Planning Services Prelodgement Sebit.Rambang@brisbane.qld.gov.au 31787187 |
Luke HADRICK Urban Planner Planning Services North Luke.Hadrick@brisbane.qld.gov.au (07) 3178 9403 |
| Rhea CONNOLLY Principal Urban Planner Planning Services North Rhea.Connolly@brisbane.qld.gov.au 3178 0651 |
DRAWINGS AND DOCUMENTS
| Drawing or Document | Number | Plan Date |
|---|---|---|
| Elevation | 019, Issue B | 21-MAY-2026 (Received) |
| Elevation | 021, Issue F | 21-MAY-2026 (Received) |
| Adjoining Lot Plan | 022, Issue E | 21-MAY-2026 (Received) |
| Floor Plan | 005, Issue B | 21-MAY-2026 (Received) |
| Roof Plan | 015, Issue H (Amended In Red 16-JUL-2026) | 21-MAY-2026 (Received) |
| Roof Plan | 007, Issue B | 21-MAY-2026 (Received) |
| Site Plan | 002, Issue F | 21-MAY-2026 (Received) |
| Floor Plan | 003, Issue C | 21-MAY-2026 (Received) |
| Elevation | 008, Issue B | 21-MAY-2026 (Received) |
| Floor Plan | 004, Issue B | 21-MAY-2026 (Received) |
| Floor Plan | 006, Issue B | 21-MAY-2026 (Received) |
| Elevation | 009, Issue B | 21-MAY-2026 (Received) |
| Site Plan | 001, Issue B | 21-MAY-2026 (Received) |
| Elevation | 017, Issue E | 21-MAY-2026 (Received) |
| Floor Plan | 011, Issue F | 21-MAY-2026 (Received) |
| Floor Plan | 012, Issue G | 21-MAY-2026 (Received) |
| Elevation | 018, Issue I | 21-MAY-2026 (Received) |
| Floor Plan | 014, Issue K (Amended In Red 16-JUL-2026) | 21-MAY-2026 (Received) |
| Elevation | 016, Issue I | 21-MAY-2026 (Received) |
| Elevation | 020, Issue B | 21-MAY-2026 (Received) |
| Elevations | 010, Issue B | 21-MAY-2026 (Received) |
| Floor Plan | 013, Issue H | 21-MAY-2026 (Received) |
APPROVAL CONDITIONS
| Permit to Which These Conditions Relate: | DA - PA - Material Change of Use |
| Activity(ies): | Extension multiple dwelling |
| Stage: |
| 1) Maintain the Approved Development Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions. |
At all times |
| 2) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers. Note: This condition is imposed to ensure compliance with the conditions of development approval. |
While site/operational/building work is occurring |
| 3) Carry Out the Approved Development Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS. Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners. |
While site/operational/building work is occurring |
| 4) Complete All Building Work Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS. Note: Building work must also be completed in accordance with any other current development approval. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 5) Limitation of Approval The roof top terrace area is to remain unroofed and unenclosed and not to constitute a storey in accordance with the APPROVED DRAWINGS AND DOCUMENTS. |
At all times |
| 6) Balconies and Terraces to Remain Unenclosed All balconies and terraces shown on the approved
drawings and documents, are to remain unenclosed with
no shutters, glazing, louvres or similar permanent
fixtures other than those consistent with the relevant Brisbane Planning Scheme
Codes/Policies and clearly depicted on the approved drawings. Any Community Management Statement is to contain a
by-law which reflects the requirements of this condition. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 7) External Details Construct and maintain external details of the building(s) in accordance with the approved DRAWINGS AND DOCUMENTS. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
7(a) Submit External Details Submit for the approval of
Development Services, further details of the building, facade treatment and
external materials, colours and finishes consistent with the approved DRAWINGS
AND DOCUMENTS. |
As indicated |
7(b) Implement Approved External
Details Carry
out the approved external details treatment in accordance with approved
drawings. |
As indicated |
| 8) Overall Height The overall height of the building(s) must be in accordance with the floor and roof levels and overall height shown on the APPROVED DRAWINGS AND DOCUMENTS. NOTE: This condition should be read in conjunction with any other relevant condition requiring minimum height clearances for basement or undercover car parking and manoeuvring areas. |
While site/operational/building work is occurring and then to be maintained |
8(a) Submit Certification Submit to Development Services certification from a registered surveyor confirming that the 'as constructed' floor and roof levels and overall height are in accordance with the requirements of this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 9) Sun Shading Devices Provide sun shading in accordance with the approved DRAWINGS AND DOCUMENTS. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 10) Screening Provide screening to windows of habitable rooms, balconies, landings, terraces and decks of the proposed dwelling(s) in accordance with the approved DRAWINGS AND DOCUMENTS and the following requirements. Suitable screening must be: For windows: For balconies, landings, terraces
and decks: Note: Screening devices must be either solid translucent screens, perforated or slatted panels, or fixed louvres that are permanent, be durable and fixed. Screening devices must have a maximum of 25% openings, with a maximum opening of 50mm. |
Prior to issue of Certificate of Classification/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 11) Screen Air Conditioning and Other Plant
Enclosures Install and maintain suitable screening to all air conditioning, lift motor rooms, plant and service facilities located at the top of or on the external face of the building and within the Private Open Spaces. The screening structures must be constructed from materials that are consistent with materials used elsewhere on the facade of the building. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 12) Landscape the Site - Self Certification Landscape the site in accordance with the requirements of this condition. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
12(a) Detailed Landscape Plan for Self-
Certification Prepare a Detailed Landscape Plan at a scale of 1:100 for all on-site landscape works including planting areas identified on the approved DRAWINGS AND DOCUMENTS. The plan must be prepared by a Qualified Landscape Architect and must comply with the relevant Brisbane Planning Scheme Codes.
The plan must include the
following: Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT A detailed landscape plan accompanied by Brisbane City Council Form CC10616 - Landscape Design Certificate. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
12(b) Multiple Unit Dwelling In
addition to the requirements listed above, the plan must include the
following: - Retain the existing trees located along northern
boundary. - Columnar canopy form or screening tree/shrub
species planted at suitable spacings along side and rear boundaries in
planting areas shown on the approved drawings. -
Shade and/or round canopy trees planted at suitable spacings along front
boundaries in planting areas shown on the approved
drawings. - Shade and/or round canopy trees in car parking
areas in planting areas shown on the approved drawings. -
Minimum internal depths and widths sufficient to support healthy plant growth,
with the following dimensions or other dimensions if achieving the same soil
volume; trees - 1200mm width x depth, large shrubs and palms - 800mm
width x depth, small shrubs and groundcovers - 600mm width x depth. (note: It
is understood that minimum 600mm depth is provided to upper level
planters). - One hose cock within any private landscape and recreation area. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT A detailed landscape plan accompanied by Brisbane City Council Form CC10616 - Landscape Design Certificate. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
12(c) Certify Detailed Landscape
Plan On completion of the Detailed Landscape Plan, submit to Development
Services: Timing: Prior to building work commencing. PROOF OF FULFILMENT A detailed landscape plan accompanied by Brisbane City Council Form CC10616 - Landscape Design Certificate. Timing: Prior to building work commencing. |
As indicated |
12(d) Implement Certified Detailed Landscape
Plan Carry out the landscape work in accordance with the above certified detailed Landscape Plan. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
12(e) Certify Work On completion of the
landscape work, submit to Development Services: Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT An as constructed landscape plan accompanied by Brisbane City Council Form CC10613 - Landscape Works Certificate. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
12(f) Maintain Landscape Work Maintain the landscape work, including deep planting, in accordance with the certified Detailed Landscape Plan. Timing: To be maintained. |
As indicated |
| 13) Mechanical Plant or Equipment - Acoustically
Screened Any new mechanical plant or equipment and existing mechanical plant or equipment that will be changed or relocated are to be acoustically screened from an adjoining sensitive use. Mechanical plant includes generators, motors, compressors and pumps such as air-conditioning, refrigeration and cold room motors. Acoustically screened is defined in City Plan 2014. NOTE: This condition does not authorise environmental nuisance under the Environmental Protection Act 1994. PROOF OF FULFILMENT Submit to Development Services, certification that all mechanical plant or equipment, is acoustically screened. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| 14) On-site Erosion (Low Risk) Manage on-site erosion
and the release of sediment or sediment laden water from the site at all times
by implementing best industry practice for sediment and erosion control as per
the International Erosion Control Association, Best Practice Erosion and
Sediment Control documents (2008 or later version). Including but not limited
to: Note: Guidelines and factsheets to assist with this are available from the 'Healthy Waterways - Water by Design' website at http://hlw.org.au/initiatives/esc/house-sites Timing: Prior to commencement of any earth disturbing activities and until all exposed soil areas are permanently stabilised against erosion. |
As indicated |
14(a) Provide Land Occupier Notification to
Council (i) Notify Council's ESC Team of proposed land occupier/s by sending an email to CARS-ESC@Brisbane.qld.gov.au (ii) If the land is to be occupied by any person other than the registered landowner then advice must be provided to Council that confirms the name, contact information and the duration of any proposed occupation of the land. Note: Occupier is any principal contractor occupying the land exercising a right under the development approval. Timing: Prior to commencement of any earth disturbing activities. |
As indicated |
| 15) Protect Existing Infrastructure Where there is existing infrastructure in the vicinity of the proposed work, the new work must not damage or compromise the working ability of the existing infrastructure. Where alterations to public utility mains, existing mains, services or installations are necessitated by the development, prior to alterations commencing, the developer must notify Council or the relevant infrastructure provider and obtain agreement to the alterations. The developer must meet the costs of the alterations. The alterations must be carried out in accordance with the relevant Brisbane Planning Scheme Codes or infrastructure providers requirements. |
While site/operational/building work is occurring |
15(a) As Constructed Drawings - Alterations
to Existing Infrastructure Submit to Development Services As Constructed drawings showing all new and/or rectification works and an asset register, prepared by a Registered Professional Engineer Queensland. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. PROOF OF FULFILMENT Submit to Development Services certification from a Registered Professional Engineer Queensland, confirming that the alterations have been completed in accordance with the relevant Brisbane Planning Scheme Codes and any other relevant infrastructure requirements. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first. |
As indicated |
| 16) Repair Damage to Kerb, Footpath or Road Repair any damage to the existing kerb and channel, footpath or roadway (including removal of concrete slurry from footways, roads, kerb and channel, stormwater gullies and drainlines) and re-instate existing traffic signs and pavement markings that have been removed or damaged during any works carried out in association with the approved development. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 17) Ponding of Stormwater Carry out the approved development to ensure that adjoining properties and roads are protected from ponding or nuisance from stormwater during construction. Notes: If remedial works are necessary to comply with this condition, prior approval must be obtained from Development Services. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 18) On Site Drainage - Minor Stormwater run-off from additional roof areas must be collected internally and piped in accordance with the relevant Brisbane Planning Scheme Codes to an existing lawful point of discharge. Note: - Guidance for requesting a pre-start and co-ordinating the On/Off Maintenance process can be found on Council's website (https://www.brisbane.qld.gov.au/planning-and-building/applying-and-post- approval/on-and-off-maintenance-approvals). |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 19) Construction Noise and Dust Emissions Pursuant to the Environmental
Protection Act 1994, all development involving the emission of noise and dust
from building and/or construction activities, must ensure that the emissions
are in accordance with the requirements of the Act. |
As indicated |
| 20) Currency Period The currency period for this development approval is stated in the Decision Notice and is expressed as a date. This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016. |
As indicated |
| 21) Equitable Access Provision must be made during and after construction
for equitable access for persons with disabilities to and within the site and
on adjoining public areas, in accordance with the following: |
As indicated |
| 22) Water and Wastewater Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. For further information about any necessary Water Approvals contact Urban Utilities. |
As indicated |
| 23) Buildings in Transport Noise Corridors - Acoustic
Treatments All new houses, townhouses, units, hotels and motels (Class 1-4
buildings) on sites located in a designated transport noise corridor are
required to comply with the requirements of the Queensland Development Code
Mandatory Part 4.4 - Buildings in Transport Noise Corridors. The buildings will
need to achieve specific levels of noise mitigation through the use of
appropriate materials for floors, walls, roofs, windows and doors for the
relevant noise category. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first, and then to be maintained |
| Permit to Which These Conditions Relate: | DA - PA - Building Work |
| Activity(ies): | Demolition |
| Stage: |
| 24) Maintain the Approved Development Maintain the approved development in accordance with the approved DRAWINGS AND DOCUMENTS, and any other relevant Council approval required by the conditions. |
At all times |
| 25) Approved Drawings and Documents A legible copy of the Council approved DRAWINGS AND DOCUMENTS and the Development Approval Package must be maintained on site and kept available for inspection by site workers and Council officers. Note: This condition is imposed to ensure compliance with the conditions of development approval. |
While site/operational/building work is occurring |
| 26) Carry Out the Approved Development Carry out the approved development in accordance with the approved DRAWINGS AND DOCUMENTS. Note: This approval does not imply permission to enter neighbouring properties to carry out the construction (including, but not limited to, associated drainage and earthworks). Permission to enter neighbouring properties must be obtained from the relevant property owners. |
While site/operational/building work is occurring |
| 27) Complete All Building Work Complete all building work associated with this development approval, including work required by any of the conditions included in the Development Approval Package. Such building work must be carried out in accordance with the approved DRAWINGS AND DOCUMENTS. Note: Building work must also be completed in accordance with any other current development approval. |
Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use, whichever comes first |
| 28) Partial Demolition of Building Partial demolition resulting
from this approval must be in accordance with the APPROVED DRAWINGS AND
DOCUMENTS and all building work must comply with this
condition. |
While site/operational/building work is occurring and then to be maintained |
28(a) Adequate Bracing Provide adequate bracing from
the commencement of any demolition work and throughout the demolition and
construction phases of the project, to ensure that all parts of the building
not specifically designated for demolition on the APPROVED DRAWINGS AND
DOCUMENTS are retained and protected. |
As indicated |
28(b) Retain Original Fabric Retain all existing external
original fabric in the sections of the building which are not being demolished.
This will include, but is not limited to, existing decorative detailing,
balustrading, wall cladding, windows, doors, stairs and roof sheeting. |
As indicated |
28(c) Submit Certification Submit to Development Services certification by a Registered Architect / Building Designer (holding a Queensland Building and Construction Commission Licence appropriate to the scale of the approved development) confirming that the partial demolition has been carried out in accordance with the requirements of this condition. Timing: Prior to issue of Certificate of Occupancy/Final Inspection Certificate or prior to commencement of use |
As indicated |
| 29) Construction Noise and Dust Emissions Pursuant to the Environmental
Protection Act 1994, all development involving the emission of noise and dust
from building and/or construction activities, must ensure that the emissions
are in accordance with the requirements of the Act. |
As indicated |
| 30) Currency Period The currency period for this development approval is stated in the Decision Notice and is expressed as a date. This development approval lapses at the end of the currency period (the date stated in the decision notice) pursuant to section 85 of the Planning Act 2016. |
As indicated |
| 31) Damage to Trees on Adjoining Land Please note that any damage caused to vegetation on adjoining land as a result of exercising this development approval may result in an offence under other legislation (e.g. Natural Assets Local Law) and/or civil action |
As indicated |
| 32) Fire Ant Movement Controls To prevent the spread of fire ants, the Queensland Government has implemented improvement controls in areas of Queensland (biosecurity zones) where this pest species has been detected. These controls apply to individuals and commercial operators and restrict the movement of materials that could carry fire ants which include soil, turf, potted plants, mulch, baled hay or straw, animal manures, mining or quarry products. Breaches of these controls can potentially impact the community, economy and the environment. Penalties for non-compliance with movement controls within fire ant biosecurity zones apply under the Biosecurity Act 2014. For further information contact the relevant Queensland State Government department on 13 QGOV. |
As indicated |
| 33) Water and Wastewater Services for water and wastewater (sewerage) are not under the jurisdiction of Brisbane City Council. Authorisation to connect the approved development to the water/wastewater networks and for property service connections required a Water Approval under the South-East Queensland Water (Distribution and Retail Restructuring) Act 2009. For further information about any necessary Water Approvals contact Urban Utilities. |
As indicated |
| 34) Standard Building Regulations This approval does not include assessment against the siting requirements of the Queensland Development Code. Should the approved development require a siting variation against the Queensland Development Code, an application for a Siting Variation must be submitted for the approval of Brisbane City Council - Development Services. Note. This development approval does not commit to an approval of any siting variation shown on the approved drawings. |
As indicated |